to Dammam, Saudi Arabia and back) for those CONSULTANT'S staff who
attended the design review meeting.
4.3.10 Upon the effective of this CONSULTANT CONTRACT, CONSULTANT shall assurne
the responsibility in the Design Review and Approval of drawings of Qurayyah
Power Plant CONSTRUCTION CONTRACT for PROJECTS I & II, and upon the
effective date of the Qurayyah Power Plant Combined Cycle CONTRACT
(PROJECT III) as indicated in Attachment I of this Schedule "B",
CONSTRUCTION CONTRACTORS shall submit to COMPANY and CONSULTANT a
list of all proposed drawings and documents to be produced for the PROJECT.
Upon receipt CONSULTANT and COMPANY shall review this list and advice the
CONSTRUCTION CONTRACTOR of all drawings and documents which must be
submitted for approval, and any drawings and documents which must be
submitted as information items by the CONSTRUCTION CONTRACTOR but
which do not require approval.
4.3.11 CONSULTANT REPORTS
4.3.11.1 CONSULTANT shall submit to COMPANY a monthly status report
during the design review, which shall include but shall not be limited
to the following information:
(i)
Drawings:
(a)
(b)
(c)
(d)
(e)
(ii)
(HI)
(iv)
Decisions Required/Recommendations
(v)
General Comments
(vi)
LAACII 2...eearmAn
Saudi Etectricity Cornparry
4.3.12 CONSULTANT shall review, evaluate, prepare studies and arrive at Optimum
sofutions to COMPANY'S concerns regarding problems encountered in the
CONSTRUCTION CONTRACTOR'S detailed design, construction commissioning,
performance testing and during the warranty period.
4.4 PROCUREMENT REVIEW SERVICES
4.4.1 As part of the payment items in the Qurayyah Power Plant CONSTRUCTION
CONTRACTS Schedule "C", Purchase Order Placement for Engineered
Equipment, CONSULTANT shall confirm that line item billed by CONSTRUCTION
CONTRACTOR are eligible for progress payment, i.e., Purchase Order's have
been placed for the approved materials and that purchase Order's include the
required conditions, inspection, etc.
4.4.2 CONSULTANT shall review the CONSTRUCTION CONTRACTOR inspection and
QA/QC procedures to assure that CONSTRUCTION CONTRACTOR is complying
with inspection and QA/QC requirements for equipment and materials, including
items manufactured by the CONSTRUCTION CONTRACTOR, their subsidiaries,
sub-contractors and other approved vendors.
4.4.3 CONSULTANT services under this item shall include review of documentation
procedures, forms and records, as well as witness of certain tests and review of
test results. CONSULTANT shall prepare a plan for audit of CONSTRUCTION
CONTRACTOR performance after commencement of work or immediale!), upon
award of this CONTRACT.
4.4.4 No equipment inspection shall be scheduled without prior approval of the
COMPANY.
4.4.5 CONSULTANT shall review all vendor manuals and ensure that the information
provided corresponds to the actual specification of the equipment. Furthermore,
CONSULTANT shall confirm that the spare parts listing furnished by the Vendor
for any equipment is complete, well documented and supported with all
required references and data for easy procurement.
4.5 NOT USED
4.6 SITE CONSTRUCTION SERVICES
4.6.1 CONSULTANT shall perform all activities required to provide COMPANY with
assurance that PROJECT is being executed in accordance with the design
specifications and high quality construction standards.
4.6.2 CONSTRUCTION CONTRACTOR is required to submit Monthly Progress Report
for the CONTRACT. CONSULTANT shall review/advise and direct such action as
may be required relating to the Progress Report.
4.6.3 CONSULTANT shall also review progress reported for payment purposes against
line items contained in Qurayyah Power Plant CONSTRUCTION CONTRACTS
Pricing Attachment to Schedule "C", "Breakdown of Lump Sum Portion of
CONTRACT Price", and shall review and recommend for COMPANY payment of
the monthly invoice and any other invoices for changes or amendments.
4.6.4 Material On-SITE
4.6.4.1 CONSULTANT shall audit the receiving and invoicing for material an
SITE for payment under Schedule "C" and for evaluation of PROJECT
progress against schedule.