Cluster Optimization

Prepared by:
Samsung

Course Name : CLOT Procedure


Who should attend

Course Objective

Field Engineers/DT Engineers


This module will enable participants
(SOLPAR)
to understand and conduct or Project Manager (SOLPAR)
Samsung Optimizer(Samsung)
Manage Cluster Optimization.
Area Manager (Samsung)
Circle Head (Samsung)
RF Head(Samsung)
Afternoon Session (2:30pm to 6pm)

CLOT Introduction
Day 1

Test procedure

Lunch break

Morning Session (10:30am to 1:30pm)

WAS
XCAL Demonstration
Hands on exercises

Document History

Edition

Date of Issue

V1.0

-----

V1.3

14August2014

Author

Remarks

Samsung
Initial Version
Training Team
Samsung
Updated with 5 tests and screen shots for test
Training Team procedures
Samsung
Training Team Updated with WAS Procedure

V2.0

5fth Nov2014

V4.0

10th Oct 2015

Samsung
Totally revamped and updated with APK 524
Training Team

V5.0

27th

Samsung
Updated with APK 529 and 850 MHz Clot scenarios
Training Team
and KPIs.

Oct 2015

Good to know
Keep your mobile phone in the silent mode during the session

Need to sign attendance sheet at the start and end of each day
At the end of each training post test will be conducted
Stick to break timings
Your valuable feedback will be taken at the end to enhance training experience
For logistics support contact the co-ordinator

Agenda
CHAPTER 1: CLOT Introduction

LTE System Introduction


Definition and purpose of CLOT
CLOT Terminologies
Factors that affect CLOT
Cluster Optimization Criteria
CLOT process
Tools and equipment for DT
Optimization System
Tools for Post processing analysis
CLOT objective , an introduction to KPIs

CHAPTER 2: Activity before CLOT DRIVE

DT Cluster selection
What is Front why it is necessary
Installing XCAL apk
Features of APK 529
Pre-Checks

Pre-Check for Rigger


Pre-Check with LSM-R Engineer ( NW Availability , Alarm check)
Pre-check for DT Engineer ( Antenna validation, UE configuration, Network
configuration, Key parameters , Alarm check before DT starts)

CHAPTER 3: Activity during DT

Drive Route guidelines


Call Scenarios
Drive setup
CLOT Test scenario GUI description
Test scenario for 850MHz
Additional GUI information

Agenda
CHAPTER 4: Activity after DT

Log file upload to FMS


Optimization process
Optimization process by NHQ
Apply recommendation by NHQ in field
DRIVE-2
CLOT Report

CHAPTER 5 : CLOT failure reasons

Missing Route
Recommendation not applied
Site SWAP not noticed
Site down / Alarm

CHAPTER 6 : Prohibited actions

Manipulation of Log files


Unclear justification
Not applying Optimizer recommendations
Missing parameter update in SF

CHAPTER 7 : CLOT process via SiteForge

CLOT Work flow


Optimization results on site forge for field application
Project closure

CHAPTER 1: CLOT Introduction

LTE System Introduction - Evolution of Cellular Networks


Packet core
Packet switched
data

Peak data
rates
Circuit switched
voice support

1G

1980s

1990s

Late 90s

2000

2003

2008

2010 onwards

LTE System Introduction : Network Comparison


IP

PSTN

IP

GGSN

GMSC

Core
Network
MSC

BSC / RNC

Access
Network
BTS / NodeB

GSM / WCDMA

SGSN

Single-node access
network
Completely PS network
Separate USER and
CONTROL planes

Controller node in access


network
Separate CS and PS cores
Combined user and
control planes

eNodeB

LTE

LTE System Introduction : LTE Network Architecture


External 3GPP Core
Network

EPC

E-UTRAN

S3
S6a
eNodeB

S4

X2
S1-C
Uu

Gx

S11
eNodeB
S1-U

S5 / S8

SGi

Combined into
SAE - GW

PDN

Definition of a cluster
Wireless system utilize number of low-power
transmitted to create many cells and then form a
cluster.
The Cluster consist the group os several eNBs. The
purpose is to check interworking between each eNB
and overall network quality, service environment
and each signal coverage as well as Up/Download
data throughput and Handover function on the
move can be checked.
Clusters Definition
Cluster can be small (2 sites ) or large up to 30 sites.
Cluster may have EARFCN , TA as well as LSM
boundary.
Sites can be located in different morphology area
but still cab be art of cluster occasionally, in rural
area cluster may not have contiguous coverage.
BSP boundary is the main boundary for any
clusters not based on cluster boundary

Purpose of CLOT
SCFT Aims to ensure the following

Site is properly installed.

Site parameters are properly configured.

Services are available.

CLOT aims to provide the following

Optimize signal coverage

Ensure normal distribution of RF Signals

Control PCI pollution

Meet all agreed KPIs

CLOT Terminologies What is BSP


BSP stands for Best Server Plot which is nothing but predicated signal strength of
each cell.
It is generated by RF planning software such as Atoll tool to give reasonable
approximation as to how many sites required to
provide LTE services in City, Town or rural areas and how far LTE coverage footprint
would go.
It takes many factors in to consideration to generate BSP.
Factors such as Frequency Band, Antenna (Type, Beawidth, Height, Orientation)
Morphology, UL/DL Path loss model.
It aids to guesstimate drive route and Actix use as reference to draw exclusion
boundary line in order to calcuate KPIs.

CLOT Terminologies M-tilt and E-tilt


Tilts : Following E&M tilts guidelines are used prior to cluster
drive
M-tilt=0, E-tilt=4/2 urban/rural or hwy morphologies.

M-TILT
The pattern in front goes down and behind goes up.
The guideline recommended that mechanical down tilt
of an antenna should not exceed more than one-half of
its vertical beam width.
E-TILT
The pattern droops all around like an inverted saucer.
Depending upon scenarios cells can be E-down tilted or Eup tilted.
EDT applied to contain over propagating signal.
EUT applied to increase cell foot print.

CLOT Terminologies What is RSRP and SINR


RSRP
Reference Signal Received Power
Coverage footprint
Aids handover
Ranges -44dBm - -140dBm

SINR
Signal to Interference & Noise ratio
Measure network strength
SINR gives the idea about channel conditions.
Major contributor for throughput KPI
SINR=(S/I+N)

RF Conditions

RSRP(dBm)

SINR(dB)

Excellent

>=-80

>=20

Good

(-80 to -90)

(13 to 20)

Mid Cell

(-90 to -100)

(0 to 13)

Cell Edge

<=-100

<=0

LTE Network Factors that affect CLOT


1.
2.
3.
4.

Antenna Type
Antenna Azimuth
Antenna Height
Antenna Tilt

Cluster Optimization Test Criteria


(((

(((

Test entrance criteria


At least 90% of the eNBs in the test
cluster shall have passed SCFT and
shall have compliance with EMF
norms

(((

(((

(((

(((

Cluster Definition
Minimum of 25 to 30 eNBs
Contiguous coverage
Can cross TA boundaries

SCFT and EMF compliance report for


each eNB for the test cluster has to
be verified

(((

(((

(((

(((

Any changes to the eNB physical


configuration required for EMF
compliance shall be updated in the
cluster database
DT Front should be 98%(discussed
later)

CLOT Work Flow


Before CLOT

Additional process

Main process

SELECT NEW
CLUSTER TO BE
DRIVEN

1. CLOT Triggered
for CLOT Test

Site On-air

2. DTR Preparation

SCFT & EMF


Cluster
Ready
>=90%

4a. Hold, If JIRA not


cleared

3. NAV >=98%

NOK
NOK

OK
NOK

5a. Hold if Site Down

6a. Hold if Site Down

NOK

4. CLOT PreCheck
Request via
JRA OK

Additional process

9a. Recommendation
for Improvement like
Change Parameter
Request
Parameter Implement
Update in SiteForge
Go for DT+

5.
Online
Surveilla
nce
RequestOK
6. Go
for DT1
OK

7a. Justification
submission to NOPT
(Pics of Block road)

7. 100%
Route
Covered
8.
Analysis
(NOPT)

9. Are
KPIs
met
10. Report
Submission

Tools and Equipment for DT


Check list for RIGGER

Weather proofing kit.


Complete Tool Kit (Spanners/Knife/Hammer/Cable Tie etc.)
Connector making tools.
Safety belts
Safety shoes
Helmet
Rope with board and extra riggers (with full protective gear) in case of
wall mount sites.
First aid box
Annexure - 3 to be filled up and handed over to SOLPAR PM, who sends
it over to Samsung RF manager.

Tools and equipment for DT


Checklist for Rigger Contd

LTE Network Optimization System

Tools for Post processing

XCAP

Post processing
tool
Log file analysis

AnyPlan Optimizer

Simulation tool
Physical
optimization
recommendations

Actix One

Post processing
tool
KPI report
generation

Tools for Post processing contd

Atoll
RF Planning
tool
BSP Plot
generation

MapInfo

XCAL

Geo mapping
tool
Drive route
creation

Drive test tool


Field
Measurement

Clot Objective : Introduction to KPIs


Field Drive Test:
Field engineer will start performing field drive test after completing site survey successfully. Field engineer
will use 5 handsets to perform five tests using Accuver DM tool installed in mobile handset.
Each handset will perform one of the test given below
1. LDL 1
2. LDL 2
3. LUL
4. VoLTE Long
5. VoLTE Short
All test scenarios are already predefined in Accuver DM tool. Drive test engineer will select different test
scenarios per handset.

Introduction
About Exclusion & Non Exclusion
Zone

to KPIs

Cluster A
PCI capture
during
drive

Cluster B

BSP of Site

222222222222222222233333333333333333444444444444455555

Drive Route

Zone

PCI belongs
to target
Cluster Site

Drive within Best


server Plot of
Target Cluster Site

Drive within Best server


plot of Active Site

Exclusion / Non
Exclusion ZONE of
Cluster A

Non Exclusion Zone

Exclusion Zone

Exclusion Zone

Non Exclusion Zone

Remark

In this case Site 1 of Cluster A is not active

In this case another cluster site is over shooting


In this case drive has been done out of Cluster coverage

Non Active Site = If PCI of site not found during drive


5 mtr
5 mtr

All Drive Samples

5x5 Area Bin samples


( Bin Sample is avg value of all samples in 5x5 grid )

01. Cluster Acceptance Checklist

CLOT ACCEPTANCE REPORT

KPIs

Call Model

Category

Target
Value

Non-Exclusion

Exclusion

Status

RSRP

LDL, LUL

KPI

>= 95 %

97.70% (28835 /29514)

97.72% (27691 /28336)

PASS

RSRP 2300

Ping 2300

Info

Report Only

RSRP 1800

Ping 1800

Info

Report Only

SINR >= -2 dB

LDL, LUL

Info

96.81% (26252/27116)

96.87% (25481/26304)

Report Only

Overlapping Servers within 5 dB <= 1

LDL, LUL

KPI

>= 60 %

75.08% (20207 /26915)

75.25% (19493 /25904)

PASS

Overlapping Servers within 5 dB <= 2

LDL, LUL

KPI

>= 90 %

94.97% (25560 /26915)

94.90% (24583 /25904)

PASS

PCI for all Sectors Observed

LDL, LUL

Info

60 / 63

Report Only

MAC Throughput DL >= 1024 Kbps

LDL

KPI

93.40% (30422/32573)

93.55% (29588/31628)

PASS

MAC Throughput UL >= 256 kbps

LUL

KPI

>= 95 %

99.88% (16797/16818)

99.87% (16300/16322)

PASS

Average MAC Throughput DL (kbps)

LDL

KPI

>= 5,120

8,553.35

8,617.83

PASS

Average MAC Throughput UL (kbps)

LUL

KPI

>= 3,200

4,670.68

4,704.32

PASS

Call Drop Rate

LDL, LUL

KPI

<= 1 %

0.07% (2/2908.90)

0.07% (2/2837.61)

PASS

TAU Success Rate

LDL, LUL

Info

95.00% (19/20)

94.74% (18/19)

Report Only

Handover Success Rate

LDL, LUL

KPI

>= 98 %

98.27% (2220/2259)

98.22% (2098/2136)

PASS

Handover Success Rate of 2300

Ping 2300

Info

Report Only

Handover Success Rate of 1800

Ping 1800

Info

Report Only

Handover Interruption Time < 100ms

LDL, LUL

KPI

>= 95 %

99.64% (2212/2220)

99.62% (2090/2098)

PASS

RACH Success Rate

VoS

KPI

>= 99 %

100.00% (819/819)

100.00% (799/799)

PASS

Attach Success Rate

VoS

Info

99.87% (774/775)

100.00% (752/752)

Report Only

VoLTE Setup Success Rate

VoS

Info

100.00% (771/771)

100.00% (749/749)

Report Only

Attach Setup Time < 1.5 s

VoS

Info

100.00% (0.70)

100.00% (0.70)

Report Only

IMS Registration Setup Time < 1.5 s

VoS

Info

0.00% (2.62)

0.00% (2.62)

Report Only

VoLTE Setup Time < 1.5 s

VoS

Info

99.09% (0.78)

99.20% (0.78)

Report Only

VoLTE Jitter < 40 ms

VoS

KPI

>= 95 %

100.00% (01.47)

100.00% (01.50)

PASS

VoLTE Latency < 100 ms

VoS

KPI

>= 95 %

100.00% (10.47)

100.00% (10.12)

PASS

VoLTE RTP Packet Loss Rate

VoS

KPI

<= 1 %

0.15%

0.18%

PASS

CHAPTER 2 : Activity before CLOT DRIVE

Selection of cluster

> 90% sites


SCFT & EMF
done

No Alarm on
any ENB in the
cluster
CLUSTER SELECTED

Past 3 days
network
availability >=
98%

What is front

>= 90% SCFT & EMF


compliant sites
Past 3 days NAV of All
ready for drive sites >=98%
All sites in cluster are alarm
free

Installing new 529 XCAL APK in handset

New XCAL APK version 529 is released

850 MHz BAND support

New GUI introduced

5 handsets for CLOT remain unchanged

Installing new XCAL

Remove

Install

Work

Remove existing XCAL app


from mobile
Installing new XCAL APK
Making XCAL work- some tips
to remember

1. Remove existing XCAL app


1. From Mobile front screen select Settings go to Application
Manager

1.Remove existing XCAL app ..continued


1. Select XCAL and UNINSTALL

1.Remove existing XCAL app ..continued


1. Select XCAL Router and UNINSTALL

1.Remove existing XCAL app ..continued


1. Select XCAL Service and UNINSTALL

1.Remove existing XCAL app ..continued


1. Go back to Mobile home page and select My Files Select
Device storage

1.Remove existing XCAL app ..continued


1. Go back to Mobile home page and select My Files Select
Device storage

2. Install new XCAL 524 app


1. Go back to Mobile home page and select My Files Select
Device storage - Download (if APK 529 is copied in download)

2. Install new XCAL 529 app


Select new apk 529 from folder and install.

Installing XCAL
Next..Next until installation complete.

Pre-requirements to make XCAL work


Following are required to make X-CAL work
1. WiFi should be OFF
2. Mobile network should be in LTE only mode
3. SIM card selected for Data should be RJIL
4. Mobile data should be ON
5. Location mode ON
6. Data roaming ON

Making XCAL work


Launch X-CAL from Mobile app page for license select IMEI and download license
( If LTE connection is not successful license update will fail)

Making XCAL work


Select the band for testing. If it is tri band cluster we can select 2300

Making XCAL work


Select the band for testing. If it is tri band cluster we can select 2300

Making XCAL work


Select the band for testing. If it is tri band cluster we can select 2300 to start the test

Select the 3 dots to


go to FMS mode

Pre-Checks

Pre-Check
Pre-check for RIGGER

Weather proofing kit.


Tool Kit (Spanners/Knife/Hammer/Cable Tie etc.)
Connector making tools.
Safety belts
Safety shoes
Helmet
Rope with board and extra riggers (with full protective gear) in case of
wall mount sites.
First aid box
Annexure - 3 to be filled up and handed over to SOLPAR PM, who sends
it over to Samsung RF manager.

Pre-Check
Checklist for Rigger Contd

Pre-Check for LSMR Engineer


Pre-Check with LSM-R

Enable 76% OCNS loading on all eNBs of target cluster & disable Smart scheduler
function.

The LSMR engineer should confirm the PE details to the SOLPAR engineer

If site has service impacting alarm (like VSWR, backhaul issue, card failure etc.) that
need site visit by deployment team

Sites in targeted cluster should be operational

If a neighboring cluster is already launched, in that case the neighbor cluster should
also be alarm free, and so as to avoid any handover related issues during CLOT

Pre-Check for LSMR Engineer


Pre-Check with LSM-R contd
Below site parameters needs to be checked with given site database (cell ref).

In case of discrepancy he needs to get it rectified via LSMR engineer, in same PE.

Pre-checks for DT Engineer


DT Engineer should be fully aware of Cluster he is going to drive
Network configuration
Key parameters
Antenna Validation
Alarm check with LSMR before DT starts
Hard copy of drive route based on best server plot
5 handset FULLY CHARGED with XCAL loaded and sufficient storage space
Magnetic Compass, Tilt Meter & Laser meter.
Obtaining door key & site access via respective authority. Authorization letter from
RJIL, to conduct drive test.
DT Vehicle with inverter, extension box, Mobile holders
Planned Event co-ordination with LSMR engineer

Pre-checks for DT Engineer


Check License information of XCAL

CHAPTER-3 : Activity during DT

Drive Route guidelines


UE should be served by all sectors of every eNB in the cluster ( all PCIs)
Justification/approval needed if any PCIs cannot be covered
Include highways, major and minor roads in the cluster
Should cover all drivable roads, proof required for any blocked roads
Route should represent potential subscriber usage locations
Should not leave the designed coverage area for the cluster
First and second drive routes should remain identical
UE position should be identical during drive tests
Do not cross 40 kmph

Drive route guidelines


Drive Route Guidelines

Check, whether the drive route along with site database is visible in map
window of XCAL Auto mobile. ( Handset with LDL2 test scenario for 2.3GHz
and 1.8GHz and 1800 ping handset for 850MHz) If he is not able to view the
map after said procedure, he should immediately inform the optimization
engineer via Samsung RF lead & withhold the drive until the map route is
uploaded.
The drive route is assumed to be covering, all motor-able roads not
accessible or cant be driven due to any blockage should be captured with a
snapshot for proof.

Drive route guidelines cont


Drive route sample

DT Engineer will instruct the car driver for the direction to be followed
based on pre-defined drive route based on GPS location in drive test
tool. Engineer will also carry the drive route handmade copy, during
the CLOT test.

Drive setup
1. Spike Guard, mobile charger & Handset
2. Cigarette lighter input inverter
3. Mobile holder

(1)

(2)

(3)

Drive setup guidelines


Setup & guidelines Arrange all five handsets in following configuration

Drive setup guidelines cont


Setup

& guidelines Arrange all five handsets in following configuration

Samsung LTE Core


Prime handset

Drive setup guidelines cont


Setup & guidelines cont
Check whether the GPS in all the mobiles, have got latched & stable GPS icon
appears
Check whether the mobiles are getting charged via car inverter

Start LDL1, LDL2, LUL, VoL & VoS calls simultaneously


Check whether the logs are getting generated
Start moving on the defined drive route, as seen on the map window of the XCAL
mobile.
Phone which is used to check the drive route, the map window should be
configured in such a way that, it should reflect the main KPI as the legend
Check the file size limit (50MB with DRX format) indication displayed on each
handset

Call Scenarios
Perform the 1st CLOT automation drive using XCAL- Auto Mobile
Total 5 call scenarios, should be running in parallel, over 5 different Samsung
Prime handsets.
2300Hz and 1800 MHz

850MHz

LDL1 (Long FTP download call 1).

LDL1 (Long FTP download call 1).

LDL2 (Long FTP download call 2).

Ping 1800

LUL (Long FTP Upload call).

LUL (Long FTP Upload call).

VoL (Long VoLTE call).

Ping 2300

VoS (Short VoLTE call).

VoS (Short VoLTE call).

Test Scenario for Clot 2300/1800MHz


LDL1

LUL

LDL2

VoL

VoS

FTP Downlink Long Call - LDL1 and LDL2


Ensure that OCNS is enabled for all eNBs in the
cluster with 76% downlink load
Ensure that the UE is successfully attached to
the LTE network
Select the appropriate UE and download the
FTP DL Scenario from FMS
Start the Autocall test. FTP download uses a
single file with the highest possible
compression and file size of 8GB.
Ensure that the log files are being captured
Start traversing around the pre-defined drive
route at 30-40 Kmph, continuing the
FTP download and reinitiating in case of call
drop

At the end of the drive route stop the logging


and ensure that the log files are uploaded

FTP Uplink Long Call (LUL)


Ensure that OCNS is enabled for all eNBs in the
cluster with 76% downlink load
Ensure that the UE is successfully attached to
the LTE network
Select the appropriate UE and download the
FTP UL Scenario from FMS
Start the Autocall test. FTP UL uses a single file
of highest possible compression and file size of
1GB. ( Attach to detach - 60 min & 10 Sec Idle
time)
Ensure that the log files are being captured
Start traversing around the pre-defined drive
route at 30-40 Kmph, continuing the
FTP upload and reinitiating in case of call drop

At the end of the drive route stop the logging


and ensure that the log files are uploaded

VoLTE Short Call (VoS)


Ensure that OCNS is enabled for all eNBs in
the cluster with 76% downlink load
Ensure that the UE is successfully attached
to the LTE network and successfully
registered for VoLTE service
Select the appropriate UE and download
the VoLTE Short call Scenario from FMS
Start the Autocall test. Ensure that the log
files are being captured

Start traversing around the pre-defined


drive route at 30-40 Kmph, continuing the
short calls
At the end of the drive route stop the
logging and ensure that the log files are
uploaded

VoLTE Long Call (VoL)


Ensure that OCNS is enabled for all eNBs in the
cluster with 76% downlink load
Ensure that the UE is successfully attached to the
LTE network and successfully registered for VoLTE
service
Select the appropriate UE and download the VoLTE
Long call Scenario from FMS
Start the Autocall test. Ensure that the log files are
being captured
Start traversing around the pre-defined drive route
at 30-40 Kmph, continuing the long call and
reinitiating in case of call drop
At the end of the drive route stop the logging and
ensure that the log files are uploaded

Step 1: Band Lock


After launching in XCAL in all 5 handset lock the band
For testing 2300 all 5 handset must be locked to 2300
For testing 1800 all 5 handset must be locked to 1800
For testing 850 MHz 3 handset should be locked to 850MHz and one to 2300 ( for
Ping 2300 test scenario) and another to 1800 ( for Ping 1800 test scenario)

Restart handset
Select the band for testing. If it is tri band cluster we can select 2300

Step 2: Select FMS Mode


Select the band for testing. If it is tri band cluster we can select 2300 to start the test

Select the 3 dots to


go to FMS mode

Step 3: Check the current band

Step 4: GPS Value


Select GPS Value and keep the icon pressed

Step 5: Select cluster


Select the cluster. The cluster DTR get downloaded

Step 6 : Select Setting Select Type


Select Setting and then click on Select Type

Step 7: Select Cycle


Select Cluster and Cycle C1

Step 8: Downloading DTR

Step 9: Select Scenario


Test Scenario for 2300 and 1800 band are LDL1,LDL2, LUL, VoS, VoL

Step 10 : Select FTP Server

Start Autocall
Press Start Button

Clot test Scenario-LDL1


Additional Requirements:
1.
2.
3.

SINR
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
MAP with DT route covered % bin

Note: Clot scenario is same for Band 2300/1800. So GUI is also same for both bands

Selected band

GPS Status window


Lock/Unlock
Latitude,longitude
RSRP Window
RSRP measured
No. of PCI for Cluster
No.of PCI found
During the drive
for selected cluster
Call Scenario
Traffic/Idle

FTP Connection window


Success/Fail
Server IP Address

Throughput window
MAC UL Throughput
PCI details

% of PCI found during


Drive
File Name

Clot test Scenario-LDL2


Additional Requirements:
1.
2.
3.
4.

RSRP Window
SINR window
Serving PCI window.
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot

GPS Status window


Lock/Unlock
Latitude,longitude

Note: Clot scenario is same for Band 2300/1800. So


GUI is also same for both bands

Selected band
UL Thoughput

Drive test route


completed
FTP Connection
window success/Fail
server IP address

Call Scenario
Traffic/Idle

File Name

Clot test Scenario-LUL


Additional Requirements:
1.
2.
3.

SINR window
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
MAP with DT route covered % bin

Selected band
GPS Status
window
Lock/Unlock
Lat/long

FTP Connection window


Success/Fail
Server IP Address

RSRP Window
RSRP measured

Throughput window
MAC UL Throughput

No. of PCI for


Cluster
No.of PCI found
During the drive
for selected
cluster

Serving PCI
PCI Details

File Name

Call Scenario
Traffic/Idle

Note: Clot scenario is same for Band 2300/1800. So GUI is also same for both bands

Clot test Scenario-VoL


Additional Requirements:
1.
2.
3.
4.
5.
6.

SINR window
Serving PCI
RSRP window
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
MAP with DT route covered % bin
SIP message window

Selected band
GPS Status window
Lock/Unlock
Latitude,longitude

RTP Loss Window


Measured RTP Loss
RTP Loss % for KPI
Volte Call Result
Window
Success/fail

Call Scenario
Traffic/Idle

Note: Clot scenario is same for Band 2300/1800. So


GUI is also same for both bands

Clot test Scenario-VoS


Additional Requirements:
1.
2.
3.
4.

RSRP window
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
MAP with DT route covered % bin
SIP message window

Note: Clot scenario is same for Band 2300/1800. So GUI is also same for both bands

Selected band
GPS Status
window
Lock/Unlock
Lat/long
SINR Window
Measured SINR
Min. SINR for Cluster

Attach Window
Success/Fail
Call Scenario
Traffic/Idle

RACH Window
RACH Attempt
RACH Success
RACH Fail
Volte Window
Success/Fail
Success/fail/total no of call

Test Scenario for Clot 850MHz


LDL1

LUL

P1800

P2300

VoS

Test Scenario for Band 850 MHz Clot

Clot test Scenario-Ping 1800


Additional Requirements:
1.
2.

PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
MAP with DT route covered % bin

GPS Status
window
GPS
lock/unlock
status
Current
lat/long of UE

Selected Band
RSRP Window

Serving cell RSRP

SINR Window
Serving Cell SINR

Data Activity
window
Traffic/Idle
status

Test scenario
Name
Traffic/idle
time

SINR Threshold

Success/fail/total no of
ping

Clot test Scenario-Ping 2300


Additional Requirements:
1.
2.
3.

RSRP window
PCI X/Y/Z(x=No of PCI found, Y=No of scft done , Z= total no of PCI in clot
Serving PCI

GPS Status
window
Lock/Unlock
Lat/long

Selected Band
Data Activity window
Traffic/Idle status
Drive route completed Bin %
count

RSRP Window

Serving cell
RSRP

Traffic/Idle time

Map window with PCI info


of cells

Success/fail/total no of ping

Important checks during DT


Check Alarms if any During DT with LSMR Engineer
Check for missing route. 100% route should be driven for CLOT to be successful
Check Sector SWAP : Most CLOT failure happens since DT engineer fail to
notice sector swap.

CHAPTER 4: Activity after DT

Log file upload to FMS


After stopping Autocall mode, one additional option added as cancel. So if you
select option cancel then logfile will save as cancel in place of in progress or
complete
Cancelled logfile will not be consider for report generation through Actix-One

2014 Samsung Electronics

90

Activity after DT
Inform SOLPAR Manager, Samsung RF lead & LSM-R engineer after task
completion drive1

Log files should be uploaded to FMS server. SOLPAR engineer should wait till all
the drive log files get uploaded.
Solpar DT engineer should complete approval process for cluster driven less than
pre-defined route
Once uploading is done, SOLPAR engineer will call LSM-R engineer to remove 76%
OCNS loading on the site & to start the smart scheduler function.
SOLPAR engineer needs to wait, till he gets confirmation from LSM-R engineer
regarding normal functioning of services.
SOLPAR engineer should inform Samsung RF lead via SOLPAR manager regarding
completion of drive test
CLOSE THE TASK THROUGH SITEFORGE

Optimization Process
Samsung Optimization engineer suggestion to SOLPAR Manager via RF lead.
SOLPAR engineer is not directly involved in this process.
Once the drive logs are uploaded into the server, the optimization engineer
will download the log files to be imported into AnyPlan optimizer software.
The software is used to give physical optimization suggestion, prior to CLOT2 drive by SOLPAR engineer.
The optimization engineer will verify these results and also analyze any bad
KPI results based on report of CLOT-1 drive.
Optimization engineer will provide his optimization inputs to the SOLPAR
manager through circle RF lead. He might give parametric optimization
suggestion to LSM-R engineer separately.
These inputs will be in mutual agreement with RJIL team.

Optimization Process
Maximize
Performance
Antenna
Parameters
OPTIMIZATION

Optimization Process contd..


Analyze Problem Areas and Find Solutions
Noise & Interference

Poor RF Area

System Parameters

1. Antenna Parameter

1. Cell planning parameters (PCID,


1. UL/DL RSRP
Preamble root sequence number)
2. SINR
2. Neighbor lists ( Remove blacklists
cells / Add omitted cells
3. Verify Interference

2. eNB Tx Power

3. HO Parameters ( A3-Event-Offset,
Hysteresis, Time-to-Trigger, etc)

Acceptance / Exit Criteria


Purpose

KPIs

Call Model

Category

3MHz

5MHz

10MHz

Exclusion/N
on
Exclusion

Remark

Exclusion

RSRP Criteria for 3MHz =


RSRP of 2300 + 13dB
RSRP Criteria for 5MHz =
RSRP of 2300 + 11dB
RSRP Criteria for 10MHz =
RSRP of 2300 + 8dB

RF Design
Validation

RSRP <= RSRP


Criteria

LDL, LUL

KPI

>=95%

>=95%

>=95%

RF Design
Validation

SINR >= -2 dB

LDL, LUL

Info

Info

Info

Info

Exclusion

Exclusion

RF Design
Validation

Overlapping Servers
within 5 dB <= 1

LDL, LUL

KPI

>=60%

>=60%

>=60%

Exclusion

Exclusion

RF Design
Validation

Overlapping Servers
within 5 dB <= 2

LDL, LUL

KPI

>=90%

>=90%

>=90%

Exclusion

Exclusion

RF Design
Validation

MAC Throughput DL
>= DL Edge TP

LDL

KPI

>=95%

>=95%

>=95%

Exclusion

DL Edge Throughput for 3MHz


= 500kbps
DL Edge Throughput for 5MHz
= 800kbps
DL Edge Throughput for
10MHz = 1,600kbps

RF Design
Validation

MAC Throughput UL
>= 256 kbps

LUL

KPI

>=95%

>=95%

>=95%

Exclusion

Exclusion

RF Design
Validation

Average MAC
Throughput DL (kbps)

LDL

KPI

>=3.0Mb
ps

>=5.0Mb
ps

>=10.0M
bps

Exclusion

Exclusion

RF Design
Validation

Average MAC
Throughput UL (kbps)

LUL

KPI

>=1.875
Mbps

>=3.125
Mbps

>=6.25M
bps

Exclusion

Exclusion

Handover Test

Handover Success
Rate

LDL, LUL

KPI

>=98%

>=98%

>=98%

Exclusion

Exclusion

Handover Test

Handover Interruption
Time < 100ms

LDL, LUL

KPI

>=95%

>=95%

>=95%

Exclusion

Exclusion

Acceptance / Exit Criteria


Accessibility

RACH Success Rate

VoS

KPI

>=99%

>=99%

>=99%

Exclusion

Non Exclusion

Retainability

Call Drop Rate

LDL, LUL

KPI

<=1%

<=1%

<=1%

Exclusion

Non Exclusion

VoLTE Quality

VoLTE Jitter < 40 ms

VoS

Info

Info

Info

Info

Exclusion

Non Exclusion

VoLTE Quality

VoLTE Latency < 100


ms

VoS

Info

Info

Info

Info

Exclusion

Non Exclusion

VoLTE Quality

VoLTE RTP Packet


Loss Rate

VoS

Info

Info

Info

Info

Exclusion

Non Exclusion

Additional
Information

PCI for all Sectors


Observed

LDL, LUL

Info

Info

Info

Info

Exclusion

Non Exclusion

Additional
Information

TAU Success Rate

LDL, LUL

Info

Info

Info

Info

Exclusion

Non Exclusion

RF Design
Validation of
1800 Mhz

RSRP of 1800

1800 Ping

Info

Info

Info

Info

Exclusion

Non Exclusion

Handover Test
1800

Handover Success
Rate of 1800

1800 Ping

Info

Info

Info

Info

Exclusion

Non Exclusion

RF Design
Validation of
2300 Mhz

RSRP of 2300

2300 Ping

Info

Info

Info

Info

Exclusion

Non Exclusion

Handover Test
1800

Handover Success
Rate of 2300

2300 Ping

Info

Info

Info

Info

Exclusion

Non Exclusion

Apply recommendation by NHQ

( Example only )
Site
ID

Drive-2
SOLPAR manager informs SOLPAR engineer to perform 2nd drive with
necessary optimization /Changes suggestion.
SOLPAR engineer gets the optimization task to be performed on affected
areas within the Cluster through SOLPAR manager.
Post this, SOLPAR engineer will continue with 2nd Cluster Optimization drive
preparations.

Preparation for CLOT process drive 2


Pre checks with LSM-R engineer prior to cluster drive 2
Perform the 2nd CLOT automation drive using XCAL- Auto Mobile
SOLPAR engineer, along with help of rigger, should perform necessary
optimization suggestion given by optimization engineer, as mentioned in
previous section.
Rest process as given in section 4 for CLOT needs to be re-performed by the
SOLPAR engineer.

Drive-2 Closure
Inform SOLPAR Manager, Samsung RF lead & LSM-R engineer after task
completion 2

CLOT task closure through SiteForge (At SOLPAR engineer end)


Note : Sites Radiating in Already Accepted Cluster
Once Fill in eNodeBs start radiating in a cluster (Cluster acceptance drive has
been completed with sites <100% & >90% in targeted cluster) then the drive
test for the fill in site should encompass the eNodeBs designed coverage area
as per RF design and up to 2 tier of neighbor eNodeB cells for that site
acceptance. The report for the site will be only Cluster acceptance report with
the drive test till the 2nd tier neighbor and no need to do separate SCFT for the
site

CHAPTER 5: CLOT failure reasons

CLOT Failure reasons


Main reason for CLOT failures are the following
Missing route : Occurs when all routes as per DTR are not covered
Antenna Recommendation not applied : If SOLPAR does not carry out
implementation of recommendations provided by optimization team before second
drive CLOT fails
Sector SWAP not noticed : Solpar need to identify the Sector Swap.
Site down / Alarm : If the Site goes down or Alarms are generated during DT and the
same is not noticed or rectified CLOT fails
Missing PCI found
UE Configuration issue: IPSEC not disabled
Cell ref Antenna parameter mismatch, discuss with RF lead

Details of Failure Categories:


Issue Category

DT Process Deviation

Check List

Missing Route
Not Apply Antenna
Parameter
Site Down

UE Issue

2014 Samsung Electronics

Detailed Description
- PCI not detected,
- Re-used logfile,
- Stationary Test,
- DT Plot mismatch between test scenarios
- Logfile corrupted / DTR changed (Solpar)
- DT Route Changed,
- Wrong DTR prepared (with not integrated sites),
- DT done on not triggered CLOT,
- Parameter mismatch in cellref,
- Cluster boundary issue,
- Missing logs in report
- Missing Route without justification and supporting photographs.
- Main Roads/Main Area not covered
- Recommendation not implemented on field/LSMR and not updated on Site forge.
- 1.8G/850M Antenna Parameters are not same as of 2.3G Passed Cluster or vice versa.
- Service affecting Alarm on Site during drive
- GTP Loss / Backhaul fluctuation during drive
- High RSSI during drive resulting in poor UL throughput/RACH Fail
- UE config issue (IPSec/IPv4 setting)
- GPS unlock during drive
- UE malfunctioning (Huge difference in RSRP level between different UEs)
102

Apply Antenna recommendation by NHQ

( Example only )

Make sure that default Antenna parameters are implemented on field


If it is a drive on a frequency for which the same cluster has already passed on
other frequency then the same antenna parameter needs to be applied on this
cluster as well
Make sure new antenna parameters are updated in site forge and Cell ref

Drive Route mismatch between Different UEs

As can be seen in the above snap, the drive route is different in all 3 scenarios, it
Could be because of UE issue, Human unforced error, Knowingly done.
At all times keep checking if your UE is still connected and GPS is not lost

Stationary
test done
Stationary
Test Done

As can be seen in above snap that Stationary drive has been done to improve samples
and KPI as a result.
Analysis team has macros that automatically identify if Stationary test has been done,
Doing the same will make you re-drive the cluster

LDL1: PCI Count check

LDL2: Drive Progress status

LDL2 v/s FMS: DT Progress % for RF Lead in FMS


DT Progress %

LUL Throughput

VOS: SINR & (RACH/Attach/VOLTE Setup) Success rate

VoL: RTP Loss

Action Items: Circle RF Lead


Circle RF Lead to ensure to train new Solpar engineer before deploying on field and ensure that they follow the proper process
during the drive and log upload.
Circle RF Lead to ensure to prepare the DTR for CLOT Triggered Sites and within the BSP strictly.
Circle RF Lead to ensure the planned CLOT given for alarm surveillance and timely information reaches to respective DT engineer in
case of any service affecting alarms.
Circle RF Lead to check and ensure that 1.8G & 850M antenna parameters matches with 2.3G passed cluster before giving go ahead
for 1.8G & 850M drive test.
Circle RF Lead to ensure all recommendations (Antenna parameters/Sector Swap removal) to be implemented on field/LSMR and
siteforge before starting the next level of drive test.
Circle RF Lead need to ensure that solpar engineer monitors the main KPIs i.e. DL/UL Throughput, VOLTE setup, Attach Success,
RACH Success during DT and should hold the drive if he finds any abnormality and contact to Help Desk for issue resolution. He
should resume the drive test once issue resolved.
Circle RF Lead need to ensure that solpar engineer monitors that all 5 test scenarios are continuously running during the drive test.
No stationary test to be conducted for any test scenario and old logfiles not to be reused in any circumstances.
Circle RF Lead to instruct Solpar engineer to prepare the less drive justification PPT during the upload of logfiles in to FMS and send
to respective circle & NHQ SPOCs so that it reaches to NHQ analyzers on time.
Circle RF Lead to ensure not to give blind approval for less drive cases until unless it is genuinely justified by solpar engineer. You can
ask photos & non driven area on whatsapp or on mail for necessary verification for approval.

2014 Samsung Electronics

112

CHAPTER 6: Prohibited actions

Prohibited actions during CLOT


Following actions are taken by SOLPAR which resulted in failure of CLOT

Manipulate of log files : Do not attempt to modify log files at any stage
Providing unclear justifications ( NEED CLEAR JUSTIFICATIONS)
Not implementing Optimizer recommendations
Missing parameter update in SF
Renaming should be correct.
Old logfiles should not be used.
Drive tester should stick to the guidelines provided by

QUIZ
Q 1) How many scenarios are there in 2300 MHz CLOT ?
Ans a) 3

b) 2

c) 5

d)4

Q 2) In 850 Mhz Clot, How many mobiles will be locked to 850 Mhz
band?
Ans a) 3

b) 2

c) 5

d)4

Q 3) In a cluster of 20 sites, atleast how many sites should have got


SCFT done ?
Ans a) 16

b) 18

c)19

b) 20

CHAPTER 7 : CLOT process through Siteforge

CLOT Process Flow Chart


Work assignment
through SiteForge

Preparation for CLOT


process - drive1

Pre checks with


LSM-R engineer

Perform the 1st CLOT


automation drive test

Inform SOLPAR
Manager,
Samsg. RF lead & LSM-R

CLOT task closure


(in Site Forge)

Samsung. Opt. Eng.


suggestion to
SOLPAR Mgr. via RF
lead

SOLPAR mgr. informs


SOLPAR engr. to
perform 2nd drive with
Changes on site.

Preparation for
CLOT process drive2

CLOT Process Flow Chart cont


Pre checks with
LSM-R engineer
prior to drive - 2

CLOT task closure


through SITE
FORGE

Perform the 2nd


CLOT drive

Repeat process,
to meet cluster
KPI

Infm. SOLPAR Mangr.,


Samsg. RF lead,LSM-R
eng. on completion

CLOT WORK FLOW


START
Reject

Auto trigger if
90% SCFT done Samsung RF
Lead

Samsung
OPT team
Accept

RJIL RF
Engineer

Reject

Accept

Samsung AM

RJIL RF
Lead

Solpar PM

Reject

RJIL CLOTAccept
QA
Auditor

Solpar Field Eng


for drive test -1

Accept

RJIL CLOT QA
Manager

Close

WAS workflow cont..


Cluster Task trigger
Drive route preparation and upload at FMS

AM assignment

SOLPAR Assignment
Field engineer assignment
Cluster task performed by field engineer
Report trigger to optimization engineer
Validation by optimization engineer
Report submission to RJIL central RF team for approval
RJIL central RF team accept the report.
Task closer

SiteForge log in window

Samsung RF Head window

Assignment for Cluster Task to AM

RF Head assign Task to AM

Assignment for Cluster Task to AM

RF Head assign Task to AM

Cluster Task assignment to AM

Work order assigned to AM

Cluster Task Assignment to SOLPAR PM

AM assign Cluster task to SOLPAR PM

Cluster Task Assignment to SOLPAR PM

AM assign Cluster task to SOLPAR PM

Cluster Task Assignment to SOLPAR PM

AM assign Cluster task to SOLPAR PM

Cluster Task Assignment to SOLPAR PM

Cluster task assigned to SOLPAR PM

Cluster Task assignment to Field engineer

Cluster task assign to field engineer

Cluster Task assignment to Field engineer

Cluster task assign to field engineer

Cluster Task assignment to Field engineer

Cluster task assign to field engineer

Cluster Task assignment to Field engineer

Cluster task assigned to field engineer

Cluster task activity by Field engineer

First time field engineer will perform the drive , upload log file and complete the task at Site Forge

Cluster task activity by Field engineer

Field engineer complete the Task

Optimization Engineer Task

Optimization engineer will download the Cluster report, Analyze and upload the suggestions at Site
forge when reject the TASK

Optimization Engineer Task

Uploading Suggestions to SiteForge Site by site

Optimization Engineer Task

Uploading Suggestions to SiteForge Site by site

Optimization Engineer Task

Uploading Suggestions to SiteForge Site by site

Optimization Engineer Task

Uploading Suggestions to SiteForge Site by site

Optimization Engineer Task

Uploading Suggestions to SiteForge Site by site and Save.

Optimization Engineer Task

Suggested parameter updated successfully

Optimization Engineer Task

Suggested parameter updated successfully

Optimization Engineer Task

Suggested parameter need to be update site wise for cluster all sites

Optimization Engineer Task

After putting all suggested parameters , Optimizer will reject the task

Optimization Engineer Task

After putting all suggested parameters , Optimizer will reject the task

Optimization Engineer Task

Task rejected by Optimizer, rejected TASK will go to AM

Area Manager Task

Area Manager Task

AM re-assign the TASK to SOLPAR PM

Area Manager Task

AM re-assign the TASK to SOLPAR PM

Area Manager Task

AM re-assign the TASK to SOLPAR PM

Area Manager Task

AM re-assign the TASK to SOLPAR PM

Area Manager Task

Task re-assigned to SOLPAR PM

SOLPAR PM Task

SOLPAR PM assign TASK to Field engineer

SOLPAR PM Task

SOLPAR PM assign TASK to Field engineer

SOLPAR PM Task

TASK assigned to Field engineer

Field engineer Task

Field engineer will check suggested parameter and implement the changes

Field engineer Task

Field engineer will check suggested parameter and implement the changes

Field Engineer Task

Field engineer will check suggested parameter and implement the changes

Field Engineer Task

Field engineer will check suggested parameter and implement the changes

Field Engineer Task

Field engineer will check suggested parameter and implement the changes

Field Engineer Task

Field engineer will check suggested parameter and implement the changes and update at Siteforge

Field Engineer Task

Field engineer will check suggested parameter and implement the changes and update at Siteforge

Field Engineer Task

Field engineer will check suggested parameter and implement the changes and update at Siteforge
and verify .

Field Engineer Task

Field engineer will Perform the drive test and upload the log post all suggested changes .
After successful log upload he will complete the TASK.

Field Engineer Task

Task Completed by field engineer

Optimization Engineer Task

Optimizer will download the report and analyze, if pass then will accept and send for RJIL Central RF
Team

Optimization Engineer Task

Optimizer can check that suggested parameter has been implemented or not.

Optimization Engineer Task

Optimizer can check that suggested parameter has been implemented or not.

Optimization Engineer Task

Optimizer can check that suggested parameter has been implemented or not.

Optimization Engineer Task

Optimizer accept the report with remark(if any) and send it to approval for RJIL Central RF Team

Optimization Engineer Task

Optimizer accept the report with remark(if any) and send it to approval for RJIL Central RF Team

Reliance central RF

RJIL Central RF team accept the report

Reliance central RF

RJIL Central RF team accept the report and Task Closed.