Professional Documents
Culture Documents
Hi,
one of my Blog reader has a Problem. She has Project and she must apply three different Pay rates for Resource
on the Task in MS PROJECT 2010. Here is an example:
John is working on task, and it will have Duration = 14 days! John will work from Monday to Sunday 12
hours per day! Regular work is 8 hours per day, and 4 hour per day are overtime work. BUT! Every Sunday
John will earn double time fee.
OK! Firs we have to SETUP our Regular work:
then:
But, where is the Overtime rate applied? NOWHERE! Why? Remember that you should assign overtime work
by your own. That means, if someone will work 12 hours on a task per day, it doesnt mean that MS PROJECT
2010 will charge 4 extra hours with overtime rate.
Now I will click anywhere in Task Form, and on the format Tab select Work:
Now what? John has to work 12 hours per day, and 4 hours will be overtime. 14 days * 12 hours per day = 168
hours. 14 days * 4 overtime hours per day = 56 hours. I will put those figures in Task Form:
You can see that Cost per day (except Sunday) is $1.400. (8 hours * $100) + (4 hours * $150) = $1.400. At
Sunday Cost is 12 hours * $200 = $2.400.
Thats it.
Regards!
About these ads
Like
One blogger likes this.
Related
MS PROJECT 2013
In "MICROSOFT PROJECT"
PROJECT 2010
In "MICROSOFT PROJECT"
This entry was posted in MICROSOFT PROJECT, Microsoft PRoject 2010, MS PROJECT 2010, MS PROJECT 20101, PMI, PRoject Management and tagged Microsoft Project
2010, MS PROJECT 2010 - assigning Overtime Pay Rates, PMI, Project Management. Bookmark the permalink.
20 Responses to How to apply Overtime, and Double time rates in MS PROJECT 2010
paul przekowiak says:
February 9, 2014 at 5:51 pm
Hi Nenad,
Thanks a lot for all posts written
Please, could you help me to better understand the calculating methods of MS Project because I dont well understand MS
Project behaviour: To explain my problem, here is my context :
CONTEX
PROBLEM
But MS project calculates also overtime work, and I dont understand how because
For February 10 , overtime work = 3,28h
For February 11, ovt work = 3,72
Firstly, no way to change this repartition, automatically calculated. Impossible to type data on ovt work field
Secondly, its better to overload the ovt work of the Feb. 10 because this ovt rate is lower than the ovt rate of th Feb.11
Finally the total calculated cost by Project = 327,19 but according to my own calculation it should be egal to 334,40
Feb 10 = 4h std time x 10 std rate + 3,28h ovt x 20 ovt rate = 105,60
Feb 11 = (4 x 20 ) + (3,72 x 40) = 228,80
Total cost = 334,40
Please, could you help me to better understand the calculating methods of MS Project
Sorry for my approximate translation
Thanks a lot
Paul PRZEKOWIAK
Reply
bharanikumar says:
August 13, 2013 at 12:29 pm
if two activity 6 hours and 6 hours for one more then how?
Reply
I was pretty confused by overtime hours. Maybe it will help to explain that OT hous are a subset of work hours. E.g.,
if 14 hours total were worked and 2 of those hours were OT, you enter 14 in Work field and 2 in OT field. Now, if you
dont want to go with Standard OT rate, you can assign any rate to a task but again this is tricky. You need to assign
the resource to the task, then go to task usage view, select the resource and double click. You will see cost rate table
on the general tab of the pop up box. You can select the appropriate rate (A,B,C, etc.) from there. You need to load the
rates in the resource sheet view first. Hope that helps. Took me forever to figure it out.
Reply
galadar says:
March 28, 2013 at 7:08 am
Hi dear
first I would like to say thanks for your above post, after that I would like to share one question with you which I have in
mind, it is also something about cost calculation thats why I am asking here:
How to set up different pay rate units such as ($/m, $/m2, $/m3, $/ton and so) and thats it. you know in most
construction projects like building, roads, tunnel, canal even dam constructions cost of much of items such as excavation,
drainage and so will calculated based on different pay rates as indicated above. for example if I want to setup cost of
excavation task how I suppose to do that, if I have to setup unit pay rate of this task in resource sheets ? so which kind of
resource I suppose to assign (work, material or cost resource) and how I use different pay rate ? or if I suppose to setup this
kind of cost in different place, where is that place ?
with thanks and respect
Reply
Thanks for this information! My question is regarding cost per task. I have temp employees working overtime. In a given
week they are paid overtime rate for hours over 8 per day. In the same week they could leave early so they may have a day
where I need to assign $0 for 4 hours. I entered a task called Unpaid Time so I could measure how many hours they take off
but project is not letting me assign rate table cost of $0. Do you know how to report this? Thanks again!
Reply
I will write a post for this issue next week! Thank you for a great Idea
Reply
Igor says:
October 18, 2012 at 4:30 pm
Let me clear one thing out! You want to drive your car at Saturday 12 hours and Sunday 12 hours! And 12 hours
per day are overtime?
Reply
Igor says:
October 19, 2012 at 3:52 pm
Yes, thats right. Saturday and Sunday are days off, so if the I work that days its overtime. I cant work more
than 12 hours, according to the law, so how can I make it happen? When I do it, the microsoft project used to
change the duration (which is fisically impossible) or It used to allocate to work 24 hours at Saturday.
Anna says:
July 10, 2012 at 2:15 pm
YOu can apply only one standard rate and one overtime rate per day!
Reply
But yoiu can apply differnt tables (pax / costs) per task, if that can help you!
Reply
Anna says:
July 11, 2012 at 1:47 pm
hennry says:
June 22, 2012 at 8:51 am
Hai Mr. Nenad Trajkovski; Im Hennry from Indonesia; I have problem with Peak resources;
at the beginning I have 200% carpenters; and because of some task so he overlocated and got the red mark; I try to resolve by
add 200% carpenters, the red mark disappears, but there is information peak for the carpenters are 600%; so I arrange for
the 4 carpenters to different days, but I still not sure about peak. Would you help me please ? thanks in advance, best
regards,
hennry
Reply
Gordon says:
February 17, 2012 at 9:11 am
Nenad Trajkovski
The Twenty Ten Theme
Blog at WordPress.com.