Professional Documents
Culture Documents
Internal Faults:
Internal faults are the faults which occur internal to the transformer which may seriously damage
the insulation of the transformer and causes break down in transformer. So the transformer should
be immediately protected from these faults. These faults are divided as electrical and mechanical
faults
-Electrical faults:
Phase to Phase fault, Phase to ground, Inter turn faults will come under electrical internal faults. As
a result of winding insulation failure which often creates short circuit between phase to phase or
phase to ground results in high current flow. This high current flow may break the down the
winding.
A conducting bridge across the laminated structures of the core can permit sufficient eddycurrent to flow to cause serious overheating. The bolts that clamp the core together are always
insulated to avoid this trouble. If any portion of the core insulation becomes defective, the
resultant heating may reach a magnitude sufficient to damage the winding .
So for these faults the transformer should be switched off immediately and should be taken in to
service.
-Mechanical Faults
-The cooling medium failure results in high temperatures in transformer which effects the
insulation and casing. In long run this may result deterioration of component or even it may
also create fire in the transformer.
-In transformer tap changing mechanism there will be high current flow in the taping, if any
fault in this mechanism may result in flashing at tap changers
Through Faults:
Through faults are the faults which occur outside the transformer zone and cleared by the
downstream components. However the fault is not cleared by them, it may results in severe over
loading on transformer which results in large current flow through the transformer.
If the fault is at secondary side then a large current flow will result in secondary and it reflects high
current flow in corresponding primary winding. These faults are not serious but these may
deteriorate the insulation of the transformer and may create long time fault. Normally these faults
are cleared by over current protection which is placed on transformer primary.
16
Two basic requirements that the relay connection must satisfy are:
1. The relay must not operate for loads or external faults.
2. The relay must operate for internal faults.
Gives the connection for star and delta side show in Fig .2-2. in both cases three current
transformers is required.
To get the arrangement the following rules are followed:
- given power transformer former is connected in delta .Secondary of CTs connected in star .
- given power transformer former is connected in star . Secondary of CTs connected in delta .
by the two current transformers will usually be different, thus causing their
transformation errors to be unequal. The resulting differences in the secondary currents
will cause imbalance current to flow in the relay. As the primary and secondary line CT
ratios may not exactly match the transformer rated winding currents, digital/numerical relays
are provided with ratio correction factors for each of the CT inputs. If interposing CTs
are used, ratio correction may not be such an easy task and may need to take into account a
factor of 3 if delta-connected CTs or ICTs are involved. If the transformer is fitted with a tap
changer, line ct ratios and correction factors are normally chosen to achieve current
balance at the mid tap of the transformer.
3. Tap changing alters the ratio of voltage (and currents) between HV side and LV side.
Differential protection should be provided with bias (restrain) which exceeds the effect of
variation in secondary current due to tap changing.
4. Magnetizing current inrush: When power transformers are switched on, initially there is no
induced e.m.f., the conditions is similar to switching an inductive circuit. Since the resistance
of the coil is low, a large inrush of magnetizing current takes place. The magnitude of which
depend on circuit conditions and the voltage at the instant of switching. Maximum values of 6
to 8 times the rated current can flow in the winding. Usually this high current decays after few
cycles to the normal current but in some cases it may take 2 4 seconds.
Formerly, the relay was provided with time lag of 0.2 1 second. By this time, the inrush
current would vanish and the relay does not trip unnecessary. However for many faults, the
relay time lag might cause substantial damage to the transformer.
To prevent this problem make update in differential system called (percentage biased) differential
relay .
coil with the operating coil connected to the mid point of the restraining coil, then the total
ampere-turns are equal to I1(N/2 ) + I2 (N/2 ), which is the same as if (I1+I2 )/2 flowed through
all of the restraining coil.
the relay restraining force increases with the magnitude of
unnecessary tripping due to any ct unbalance errors. In addition, the restraining torque is increased
in the presence of through-fault currents, producing a more stable operating characteristic and
preventing relay mal operation. In relays that have variable tapings in the restraint coil
circuits, the tapings can be set to balance out any currents due to differences in the CTs.
-The Slope (1) region is used between the minimum pickup region and the slope 2 breakpoint.
Slope1 provides security against false tripping due to CT accuracy. Class C CT accuracy is +/10%,
therefore 20% should be the absolute minimum setting with greater than 40% preferred. For LTC
applications, another +/10% is added.
-End of slop 1 This is the second knee point of the tripping characteristic determines the end of the
over current zone in the direction of increasing restraining current in fault free operation. It is
recommended to set half the maximum through fault current
-The Slope (2) region is used above the slope 2 breakpoint, which is normally set at 2pu. Slope 2
Provides security against false tripping during through fault events where CT saturation is likely.
Above 2pu current, a significant DC current component will be present and therefore saturation is
likely. Slope 2 is normally set at 6080%
21
23