You are on page 1of 45

City of McKinney Stream Restoration Project

Old Settlers Creek Restoration Design Report

Prepared for
The City of McKinney
September 2012

Fouad Jaber
Omar Al-Qudah
Texas A&M AgriLife Research and Extension Center - Dallas

Summary
Old Settlers Creek in the City of McKinney was pre-selected by the City of McKinney Development Services/Engineering (DSE) and Texas AgriLife Research for a stream restoration
project as thecreek had faced head cutting and some bank erosion due in part to the increased
development in the creek watershed and additional stormwater runoff from adjacent streets. In
addition, the site is very visible with high potential for successful restoration.
The evaluation process for this stream was undertaken by DSE and Texas AgriLife based
on Watershed Assessment for River Stability and Sediment Supply (WARSSS) procedures
(Rosgen, 2006), and this included a reconnaissance level assessment, a sediment and stability
consequence assessment, and a prediction level assessment.
A restoration plan has been developed based WARSSS, Old Settlers Creek profile and
cross sectional survey, and a Reference Reachs (Timber Creek) morphological parameters.
Design procedures involved designing a stable cross section and profile including bankfull, pool
to pool and riffle to riffle spacings,slope, and other geomorphological features. Other tasks
performed in this study are:

Selection of appropriate stabilization structures (cross vanes)


Developing a planting plan
Developing a construction sequence and erosion control plan
Calculation of shear stress and flood studies for design check.

The report includes, 1) Old Settlers Creek field survey (existing conditions; cross section
survey; and profile survey), and its hydrology calculations (drainage area; rain intensity; flow
rate; and flow velocity); 2) Timber Creek (the reference reach) field survey (profile survey; cross
section survey; pattern survey; and pebble count), in addition to its hydrology calculations; and
3) the designing procedures listed above.

2|Page

Table of Contents
Summary ..................................................................................................................................... 2
Abbreviations .............................................................................................................................. 4
1. Old Settlers Creek Evaluation:............................................................................................. 8
1.1.

Old Settlers Creek Present Conditions: ........................................................................ 9

1.2.

Old Settlers creek Profile Survey: .............................................................................. 12

1.3.

Old Settlers Creek Cross Section Survey: .................................................................. 13

1.4.

Old Settlers Creek Bankfull Determination: .............................................................. 16

2.

Timber Creek Reference Reach: .................................................................................... 18


2.1.

Timber Creek Profile Survey: ................................................................................. 18

2.2.

Timber Creek Cross Section Survey: ......................................................................... 20

2.5.

Timber Creek Pebble Count Evaluation: .................................................................... 27

3. Old Settlers Creek Restoration Design: ............................................................................. 28


3.1.

Old Settlers Creek Watershed Data: ........................................................................... 28

3.2.

Old Settlers Creek Part B-Design: .............................................................................. 36

3.3.

Cut and Fill ................................................................................................................. 41

4. Vegetation Plan .................................................................................................................. 41


4.1

Planting Methods ........................................................................................................ 41

5. Plant Selection ................................................................................................................... 42


6.

Erosion and Sediment Control Plan ............................................................................... 44


6.1

Construction Sequence ............................................................................................... 44

6.2

Pollution Control: Seeding ......................................................................................... 45

7. References .......................................................................................................................... 45

3|Page

Abbreviations
Station

Distance

BS

Backsight

HI

Instrument height

FS

Foresight

BM

Benchmark

LBKF

Left Bankfull

RBKF

Right Bankfull

LTB

Left Top of Bank

RTB

Right Top of Bank

THL

Channel Thalweg

LEW

Left Edge Water

REW

Right Edge Water

Abkf

Area at Bankfull

Wbkf

Width at bankfull

Wfpa

Width Flood Prone Area

Dmax

Maximum Depth Bankfull

DTOB

Bankfull Max Depth Top Low Bank

Dbkf

Mean Depth at Bankfull

ER

Entrenchment Ratio

Wbkf/Dbkf

Bankfull Width to Depth Ratio

BHR = (DTOB/Dmax)

Bankfull Bank Height Ratio

Dmax/Dbkf

Bankfull Max Depth Ratio

4|Page

dElev

Elevation change (head first riffle to head last


riffle)

LTHL

Length of channel Thalweg (ft)

LV

Length of Valley (ft)

Save = dElev/LTHL

slope of Channel Thalweg

SV = dElev/LV

Slope of Valley

K = LTHL/LV

Sinuosity

Acs(ft2)

Cross section area

Wcs(ft)

cross section width

Dcs(ft) = (Acs/Wcs)

Cross Section Mean Depth

Wcs/Dcs

Cross Section Width to Depth Ratio

Dcsmax

Cross Section Maximum Depth

DcsTOB (ft)

Cross Section Max Depth Top Low Bank

BHRcs = (DcsTOB/Dcsmax)

Cross Section Bank Height Ratio

Dcsmax/Dcs

Cross Section Max Depth Ratio

HT

High Terrace

FP

Floodplain

MT

Middle Terrace

BKF

Bankfull

TP

Turning Point

End Rif

End of Riffle / Top of Pool

Top Rif

Top of Riffle / End of Pool

CL

Centerline (of Channel)

Drainage area

DA

5|Page

Wpbkf = 2*Dbkf+Wbkf

Wetted perimeter

R=Abkf/Wpbkf

Hydraulic Radius

R/d84

Relative Roughness

g = 32.174 ft/s2

Gravitational acceleration

(U*=((gRSave)^0.5)

Shear Velocity

Qbkf

Bankfull discharge

Ubkf = Qbkf/Abkf

Bankfull velocity

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))

Manning's n

U=[2.83+(5.66*log(R/d84)]*U*

Friction Factor/Relative Roughness

Lm

Meander wave length

MLR = Lm/Wbkf

Meander length ratio

Rc

Meander radius of curvature

Rc/Wbkf

Radius of curvature ratio

Wblt

Belt width

Wblt/Wbkf

Meander width ratio

Lrif

Riffle length

Lrif/Wbkf

Riffle length ratio

Srif

Riffle slope

Srif/Save

Riffle slope ratio

Dmaxriff

Maximun riffle depth

Dpool

Pool max depth

Dpool/Dbkf

Pool max depth ratio

Dmaxpool

Maximum Pool Depth

Dmaxpool/Dbkf

Maximum pool Depth Ratio

6|Page

Apool

Pool Area

Apool/Abkf

Pool Area Ratio

Wpool

Pool Width

Wpool/Wbkf

Pool Width Ratio

Lpool

Pool Length

Lpool/Wbkf

Pool Length Ratio

P-P

Pool to Pool Spacing

P-P/Wbkf

Pool to Pool Spacing Ratio

PdElv

Pool Elevation change

Spool

Pool slope

Spool/Save

Pool slope ratio

Lrun

Run length

RundElv

Run elevation change

Srun

Run slope

Srun/Save

Run slope ratio

Lglide

Glide length

GlidedElv

Glide elevation change

Sglide

Glide slope

Sglide/Save

Glide slope ratio

Dmaxriff/Dbkf

Maximum riffle Depth Ratio

7|Page

1.

Old Settlers Creek Evaluation:

Old settlers is located within the city of McKinney limit, south of E. Virginia St; north of E.
Louisiana St; and east of N. Murray St., as shown in Figures 1 and 2 below.

Figure 1: Location of Old Settlers Creek and the reference reach (Timber creek).
The portion of Old Settlers, that was selected for natural restoration based on the concepts
mentioned above, lies between two bridges, one to the west and the other to the east of the
stream portion (points A and B) in the Figure 2 below. The latitude, longitude, and the elevation
for the bridges (A and B) are, respectively: (La. A: 33.198023; Lo. A: -96.605149: El. A: 567 ft
above sea level [ASL]), and (La. B: 33.197957; Lo. B: -96.602767; El. B: 548 ft - ASL). Old
Settler stream type was evaluated based on the Rosgen Classification Method as F6 indicating
severe erosion in portions of the reach.

8|Page

Figure 2: Satellite photo of stream location

1.1.

Old Settlers Creek Present Conditions:

The field survey of the Old Settlers Creek(Figures 3a-3l) showed that the stream has faced head
cutting and some bank erosion due in part to increased development in the watershed and
stormwater runoff from adjacent streets. The site is in a highly visited park and has high
visibility with the public. In addition the presence of large trees on some of the banks was
detected with the implications of fact on stream restoration taken into account. Debris was lao
present in large quantities in the stream channel.

9|Page

Figure 3a: Bank erosion.

Figure 3b: Bank erosion and some large trees on


the bank.

Figure 3c: Debris and bank erosion

Figure 3d: Debris and bank erosion

Figure 3e: Bank erosion

Figure 3f: Bank erosion

10 | P a g e

Figure 3g: Bank erosion

Figure 3h: Bank erosion and some large trees on


the bank.

Figure 3i: Bank erosion and some large trees on


the bank.

Figure 3j: Bank erosion with some meandering

Figure 3k: Bank erosion with some meandering

Figure 3l: Bank erosion

11 | P a g e

1.2.

Old Settlers creek Profile Survey:

Old Settler profile survey included the elevation measurement of left bank, right bank, and the
stream channel (thalweg), and the measurement of the channel and valley length. The elevation
was designed to be measured from west to east, starting on the streams left bank (looking
downstream) at bridge [A] as a benchmark and measured every 20 ft,until reaching bridge
[B](Figure 4).While surveying the stream profile, eight locations were selected for the cross
sectional survey (Figure 5) such that it is representative of the whole stream reach, and at
locations that facilitates the survey process. Summary of the collected data is presented in Figure
5 and Table 1, and the whole set of data is provided on a separate spread sheet.

Figure 4: Satellite photo of the stream shows thalweg profile increments, as well as the
thalweg and valley length.

12 | P a g e

Figure 5: Stream profile shows the elevation of the thalweg, left bank, right bank as well as
the length of each one and the selected locations for cross sectional survey sites.
Table 1:Old Settlers creek profile's morphological parameters:
Length of channel thalweg, LthL (ft)
720.0

1.3.

Length of valley, LV (ft)

649.0

Thalweg elevation change, dEleva (ft)

13.11

Channel slope, Save = dElev/Lthl

0.0182

Valley slope, Sv = dElev/LV

0.0202

Sinuosity, K=Lthl/LV

1.1094

Old Settlers CreekCross Section Survey:

Along the stream, eight site locations were considered for cross section survey, and each
location was separated by a gap of 100 ft from the next one. Summary of the collected data is
presented in Figures 6a-6h and Table 2, and the whole set of data is provided on a separate
spread sheet for each cross section.

13 | P a g e

102
101
100
Elevation (ft)

Elevation (ft)

106
105
104
103
102
101
100
99
98
97

99
98
97
96
95

12

16

20

24

28

32

36

40

6
8
10 12 14
Distance of Station (ft)

Distance of Station (ft)

Figure 6a: Cross section #1, upstream (at a riffle) at 0 ft


of the valley length (Lv), and 0 ft of the thalweg length
(Lthl)

16

18

20

Figure 6b: Cross section #2 (at a pool) at 100ft-Lv,


100 ft-Lthl

101

99
98

99
Elevation (ft)

Elevation (ft)

100

98
97
96

96
95

95
0

8
10
12
14
Distance of Station (ft)

16

18

20

Figure 6c: Cross section #3 (riffle) at 200 ft-Lv, 220 ftLthl

Elevation (ft)

96
95
94
0

10 12 14 16 18 20 22 24 26 28

Distance of Station (ft)

Figure 6e: Cross section #5 (pool) at 349 ft-Lv, 400 ftLthl

14 | P a g e

10

12

14

16

18

20

22

Figure 6d: Cross section #4 (riffle) at 300 ft-Lv, 300


ft-Lthl

98
97

Distance of Station (ft)

99
Elevation (ft)

97

98
97
96
95
94
93
92
91
90
0

10

12

14

16

Distance of Station (ft)

Figure 6f: Cross section #6 (riffle) at 449 ft-Lv, 500


ft-Lthl

91

93

90

92

89

91

Elevation (ft)

Elevation (ft)

94

90
89
88

88
87
86
85

87

84

86
0

8
10
12
14
Distance of Station (ft)

16

18

20

10

12

14

16

18

20

Distance of Station (ft)

Figure 6g: Cross section #7 (pool) at 549 ft-Lv, 620 ftLthl

Figure 6h: Cross section #8 (riffle) at 649 ft-Lv, 720


ft-Lthl

Table 2: Old Settlers Creekcross section morphological parameters:


Morphological Parameters
CS#1 CS#2 CS#3 CS#4

CS#5

CS#6

CS#7

CS#8

Cross section area(ft2), Acs

136.3

52.1

44.7

30.1

70.9

47.5

54.2

53.1

Cross section width (ft), Wcs

36.8

20

20

21

26.3

16.2

18

18.4

Cross section mean depth (ft), Dcs (ft) =


(Acs/Wcs)

3.7

2.6

2.2

1.4

2.7

2.9

2.9

Width flood prone area (ft), Wfpa

16.3

16

23

10.7

26.5

15.6

17.5

12.2

Entrenchment ratio (ft/ft), ER= Wfpa/Wcs

0.4

0.8

1.2

0.5

0.7

Cross section width to depth ratio Wcs/Dcs

9.9

7.7

8.9

14.7

9.8

5.5

6.4

Cross section maximum depth (ft), Dcsmax

6.9

4.3

2.7

6.7

6.6

6.2

5.5

Cross section max depth top low bank (ft),


DcsTOB

5.2

4.7

3.5

2.7

5.0

4.8

6.2

5.1

Bank height ratio (ft/ft), BHRcs =


(DcsTOB/Dcsmax)

0.8

0.9

0.8

0.7

0.7

0.9

Max depth ratio (ft/ft)=Dcsmax/Dcs

1.9

1.9

1.9

1.9

2.5

2.2

2.1

1.9

15 | P a g e

1.4.

Old Settlers Creek Bankfull Determination:

99.6
99.4
99.2
99.0
98.8
98.6
98.4
98.2
98.0

98.5
98.0

Elevation (ft)

Elevation (ft)

The stream bankfull stagewas determined for each cross section above, during the cross
section survey. The bankfull determined from left to right bank looking downstream. Summary
of the collected data is presented in Figures 7a-7h and Table 3, and the detailed set of data is
provided on a separate spread sheet for each cross section.

97.0
96.5
96.0
95.5

3
4
5
6
Distance of Station (ft)

3
4
5
6
Distance of Station (ft)

Figure 7b: Bankful #2, (at a pool)

Figure 7a: Bankful #1, upstream (at a riffle)


98.5

95.6

98.0

95.5

97.5

Elevation (ft)

Elevation (ft)

97.5

97.0
96.5
96.0

95.4
95.3
95.2
95.1

95.5
95.0

95.0
0

Distance of Station (ft)

Figure 7c: Bankful #3, (at a riffle)

16 | P a g e

10

11

2
3
4
Distance of Station (ft)

Figure 7d: Bankful #4, (at a riffle)

95.0
Elevation (ft)

Elevation (ft)

96.0

96.0
95.5
95.0
94.5
94.0
93.5
93.0
92.5
92.0
91.5

93.0
92.0
91.0
90.0

3
4
5
Distance of Station (ft)

Distance of Station (ft)

Figure 7e: Bankful #5, (at a pool)

Figure 7f: Bankful #6, (at a riffle)

89.5

87.2

89.0

86.8

88.5
Elevation (ft)

Elevation (ft)

94.0

88.0
87.5
87.0
86.5

86.4
86.0
85.6
85.2
84.8

86.0
0

2
3
4
5
Distance of Station (ft)

Figure 7g: Bankful #7, (at a pool)

2
3
4
Distance of Station (ft)

Figure 7h: Bankful #8, (at a riffle)

Table 3: Old Settlers Creekbankfull morphological parameters:


Morphological Parameters
BKF#1 BKF#2 BKF#3 BKF#4 BKF#5 BKF#6 BKF#7 BKF#8
Area at Bankfull (ft2), Abkf

7.0

10.4

14.7

1.0

11.9

19.0

9.7

7.3

Width at bankfull (ft), Wbkf

8.6

8.7

10.4

5.5

7.6

8.5

8.0

7.3

Width Flood Prone Area (ft), Wfpa

16.3

16

23

10.7

26.5

15.6

17.5

12.2

Maximum Depth Bankfull (ft), Dmax

1.2

2.1

2.6

0.3

3.7

4.4

2.8

1.8

Max Depth Top Low Bank (ft), DTOB 1.2

2.1

2.6

0.3

3.7

4.4

2.8

1.8

Mean Depth at Bankfull (ft),


Dbkf=Abkf/Wbkf

0.8

1.2

1.4

0.2

1.6

2.2

1.2

1.0

Entrenchment Ratio (ft/ft), ER=


Wfpa/Wbkf

1.9

1.8

2.2

1.9

3.5

1.8

2.2

1.7

17 | P a g e

Width to Depth Ratio (ft/ft),


W/D=Wbkf/Dbkf

10.6

7.3

7.4

31.7

4.9

3.8

6.6

7.3

Bank Height Ratio (ft/ft),


BHR=DTOB/Dmax

1.0

1.0

1.0

1.0

1.0

1.0

1.0

1.0

Max Depth Ratio (ft/ft)=Dmax/Dbkf

1.5

1.8

1.8

1.9

2.4

2.0

2.3

1.8

2.

Timber Creek Reference Reach:

Timber Creek has been chosen as a suitable reference reach to simulate its profile, cross
section, and pattern on the Old Settler Park Creek. Timber Creek is located within the city of
McKinney limits as shown in Figure 1, north west of Old settlers stream. The portion of Timber
Creek that has been selected for this study is shown in Figure 8 between point A and point B.
The GPS location of points A and B are, respectively: (La. A: 33.243575; Lo. A: -96.650177; El.
A: 638 ft-ASL), (La. B: 33.243467; Lo. B: -96.648914; El. B: 640 ft-ASL). Timber Creek
drainage area, discharge flow rate, flow velocity, and flow depth are, respectively, 0.15 sq. mile,
40 cfs, 5.5 ft/s, and 1.5 ft. Timber Creek stream type was evaluated based on RosgenStream
Classification System as B6c.This is an indication that the stream is stable.
The same procedure of Old Settlers Creek profile and cross section survey has been
applied here too. Pattern survey and pebble count have been added to Timber Creek survey in
order to get a full morphological picture of the Timber Creek which could lead to a stable design
for Old Settlers stream.

2.1.

Timber Creek Profile Survey:

Summary of the Timber Creek profile survey data is presented in Figure 9 and Table 4,
and the detailed set of data is provided on a separate spread sheet. Figure 9 shows the thalweg
profile of the Timber Creek in addition to six locations for the cross section survey.

18 | P a g e

Figure 8: Satellite image of Timber Creek reference reach.

Figure 9: Timber Creek thalweg profile showed six locations for cross section survey.

19 | P a g e

Table 4: Timber Creekprofile morphological parameters:


Length of channel thalweg, LthL (ft)
604.21

2.2.

Length of valley, LV (ft)

360

Thalweg elevation change, dEleva (ft)

2.91

Channel slope, Save = dElev/Lthl

0.0048

Valley slope, Sv = dElev/LV

0.0081

Sinuosity, K=Lthl/LV

1.6784

Average riffle length (ft)

39.4

Average riffle slope

0.0087

Average pool length (ft)

37.85

Average pool slope

0.0154

Average pool to pool spacing (ft)

89.5

Average run length (ft)

25.89

Average run slope

0.0176

Average glide length (ft)

10.59

Average glide slope

0.0074

Timber CreekCross Section Survey:

Summary of the Timber Creek cross sectional data collected is presented in Figures 10a10f and Table 5, and the whole set of data is provided on a separate spread sheet for each cross
section.

20 | P a g e

Elevation (ft)

Elevation (ft)

101
100.8
100.6
100.4
100.2
100
99.8
99.6
99.4
99.2
99
0

2
3
4
5
Distance of Station (ft)

Figure 10a: Cross section #1, upstream (middle of


riffle)at 512.51 ft of the thalweg length (Lthl)

100.8
100.6
100.4
100.2
100
99.8
99.6
99.4
99.2
99
98.8
98.6
98.4
0

100.5

100.1

100.2

99.8

99.9
Elevation (ft)

Elevation (ft)

99.2
98.9
98.6

3 4 5 6 7
Distance of Station (ft)

10 11 12

99.6
99.3
99
98.7

98.3

98.4

98.0

98.1

97.7
0

4
5
6
7
8
Distance of Station (ft)

10

Figure 10c: Cross section #3 (pool) at 15.9 ft


downstream of CS#2; 551.11 ft of Lthl

100.2
99.9
99.6
99.3
99
98.7
98.4
98.1
97.8

6
8
10 12
Distance of Station (ft)

14

16

18

Figure 10d: Cross section #4 (riffle) at 15.2 ft


downstream of CS#3; 566.31 ft of Lthl

100
99.5
Elevation (ft)

Elevation (ft)

Figure 10b: Cross section #2 (end of riffle) at 22.7 ft


downstream of CS#1; 535.21 ft of Lthl

100.4

99.5

99
98.5
98

3 4 5 6 7 8
Distance of Station (ft)

9 10 11 12 13

Figure 10e: Cross section #5 (pool) at 29.2 ft


downstream of CS#4; 595.51 ft of Lthl

21 | P a g e

6
8 10 12 14
Distance of Station (ft)

16

18

20

Figure 10f: Cross section #6 (at end of a meanderneck) at 8.7 ft downstream of CS#5; 604.21 f of Lthl

Table 5: Timber Creek cross section morphological parameters:


Morphological Parameters
CS#1
CS#2

CS#3

CS#4

CS#5

CS#6

Cross section area(ft2), Acs

5.918

11.837

12.464

11.136

10.76

10.565

Cross section width (ft), Wcs

12

10

18.5

13

19.5

Cross section mean depth (ft), Dcs (ft) = (Acs/Wcs)

0.657

0.986

1.246

0.602

0.828

0.542

Width flood prone area (ft), Wfpa

18.5

Entrenchment ratio (ft/ft), ER= Wfpa/Wcs

2.055

Cross section width to depth ratio Wcs/Dcs

13.685

12.165

8.023

30.734

15.706 35.991

Cross section maximum depth (ft), Dcsmax

1.22

1.71

2.12

1.63

1.63

0.94

Cross section max depth top low bank (ft), DcsTOB

1.22

1.71

2.12

1.63

1.63

0.94

Bank height ratio (ft/ft), BHRcs = (DcsTOB/Dcsmax)

Max depth ratio (ft/ft)=Dcsmax/Dcs

1.855

1.733

1.701

2.708

1.969

1.735

2.3.

Timber Creek Bankfull Determination:

Summary of the Timber Creek bankfull survey data is presented in Figures 11-12f and
Table 6, and the detailed set of data is provided on a separate spread sheet for each cross section.

22 | P a g e

Figure 11: Timber Creek bankfull

23 | P a g e

100.6
100.4

100.0

Elevation (ft)

Elevation (ft)

100.2

99.8
99.6
99.4
99.2
99.0
0

2
3
4
Distance of Station (ft)

10 11 12

Figure 12b: Bankfull #2 (end of riffle)

100.2

99.6

99.9

99.4

99.6
Elevation (ft)

99.2

99.3
Elevation (ft)

Distance of Station (ft)

Figure 12a: Bankfull #1, upstream (middle of riffle)

99.0
98.7

99.0
98.8
98.6

98.4

98.4

98.1

98.2

97.8
0

3
4
5
Distance of Station (ft)

Figure 12c: Bankfull #3 (pool)

2
3
4
Distance of Station (ft)

Figure 12d: Bankfull #4 (riffle)

99.4

99.2

99.2

99.1
99.0
Elevation (ft)

99
Elevation (ft)

100.6
100.4
100.2
100.0
99.8
99.6
99.4
99.2
99.0
98.8
98.6
98.4

98.8
98.6
98.4

98.9
98.8
98.7
98.6
98.5

98.2

98.4

98

98.3
97.8

0
0

3
4
5
6
Distance of Station (ft)

Figure 12e: Bankfull#5 (pool)

24 | P a g e

9 10 11 12 13 14

9
Distance of Station (ft)

Figure 12f: Bankfull#6 (at end of a meander-neck)

Table 6: Timber Creek bankfull morphological parameters:


Morphological Parameters
BKF#1 BKF#2 BKF#3

BKF#4

BKF#5 BKF#6

Area at bankfull (ft2), Abkf

5.9

11.8

11.8

4.2

6.9

7.0

Width at bankfull (ft), Wbkf

7.4

11.5

8.9

6.2

8.7

14.4

Width Flood Prone Area (ft), Wfpa

18.3

Maximum Depth Bankfull (ft), Dmax

1.2

1.7

2.1

1.2

1.3

0.7

Max Depth Top Low Bank (ft), DTOB

1.2

1.7

2.1

1.2

1.3

0.7

Mean Depth at Bankfull (ft),


Dbkf=Abkf/Wbkf

0.8

1.0

1.3

0.7

0.8

0.5

Entrenchment Ratio (ft/ft), ER=


Wfpa/Wbkf

2.5

0.0

0.0

0.0

0.0

0.0

Width to Depth Ratio (ft/ft),


W/D=Wbkf/Dbkf

9.3

11.2

6.7

9.2

10.9

29.6

Bank Height Ratio (ft/ft),


BHR=DTOB/Dmax

1.0

1.0

1.0

1.0

1.0

1.0

Max Depth Ratio (ft/ft)=Dmax/Dbkf

1.5

1.7

1.5

1.8

1.6

1.5

2.4.

Timber Creek Pattern Determination:

Summary of the Timber Creek pattern survey data is presented in Figures13 and 14, and
Table 7, and the detailed set of data is provided on a separate spread sheet.

25 | P a g e

Figure 13: Timber Creek pattern parameters

Figure 14: One of Timber Creek meanders


Table 7: Timber Creek pattern morphological parameters:
Meander wave length, Lm (ft)
Meander belt width, Wblt (ft)

26 | P a g e

198.963
115.026

2.5.

C (ft)

123.575

M (ft)

32.642

Meander radious of curvature, RC (ft) =


((C^2)/(8*M))+(M/2)

74.799

Timber Creek Pebble Count Evaluation:

Summary of the Timber Creek pebble count survey data is presented in Figure 15 and
Table 8, and the detailed set of data is provided on a separate spread sheet.
110
100
90

Pebble percentage

80
70
60

riffle 100

50

pool 100

40

average 100

30
20
10
0
0.1

10

100

1000

Pebble size (mm)

Figure 15: Timber Creek pebble count survey


Table 8: Timber Creek pebble count morphological parameters:c
Median diameter of the riffle bed (from 100 count in the riffle), d50 (mm)

0.375

Median diameter of the bar sample, d50 (mm)

0.062

Largest particle from the bar, di (mm)

19

Average intermediate axis width of 84% of bed material count at riffle, d84
(mm)

7.2

27 | P a g e

3.

Old Settlers Creek Restoration Design:

Old Settlers Creekhas three water flow sources, one is the direct precipitation the other is
the runoff from downtown McKinney as it flows through a culvert in the channel and the third is
flow from a pipe located at 300 ft of the thalweg length east (downstream) of bridge A. Because
of the change in flow and streambed slope upstream and downstream of the pipe, restoration
design has been divided into two parts. The first part located between the bridge A and the pipe,
and the second located between the pipe and bridge B as shown in Figure 16. Part A includes
cross sections 1-4, and part B includes cross sections 5-8.

Figure 16: Satellite image of Old Settlers stream shows the proposed design partitioning.

3.1.

Old Settlers CreekWatershed Data:

The mainhydrologic parameters (drainage area, rain intensity, and flow rate discharge)for
the stream have been obtained for part A (point A to C) and the whole stream (which is for part
B; point A to B) by using the rational methodas shown in Table 9.

28 | P a g e

Table (9): Old Settlers stream watershed data (rational methods):


DA

1.5Y

10Y

25Y

50Y

100Y

1.5Y

10Y

25Y

50Y

100Y

Part A (point A to C)mouth of channel

0.12

0.8

3.9

5.8

6.7

7.4

8.2

174.4

268.4

359.3

400.0

442.0

Part B (point A to B)downstream + Pipe Flow +


Sheet Flow

0.15

0.67

3.8

5.6

6.4

7.2

7.9

203.9

310.2

414.9

461.9

510.2

13.5

16.6

22.2

24.7

27.2

Pipe Flow Only 24" Pipe

DA: drainage area (sq. mile); C: runoff coefficient (dimensionless); I: rainfall intensity (in/h); Y:
recurrence interval in years; Q: flow rate discharge (cfs).
In order to get an accurate estimate of the stream watershed data, the main hydrologic
parameters(drainage area, rain intensity, and flow rate discharge)were estimated using different
methods depending on the Old Settlers and Timber Creek drainage area and/or bankfull area, as
shown in Table 10. An average value for Qbkfof 71.03 cfs was selected.
Table (10) Summary of the morphological data obtained from Old Settlers and Timber
Creek survey (present conditions):
Parameter
DA

Unit
mi

Stream type (Rosgen)

Old
Settlers

Old
Settlers

Part A

Part B

0.12

0.15

F6

Timber
Creek
0.15
B6c

Average, Abkf

ft2

14.70

13.16

11.79

Average, Wbkf

ft

10.40

7.90

11.50

Dbkf = Abkf/Wbkf

ft

1.41

1.67

1.03

Wbkf/Dbkf

ft/ft

7.36

4.74

11.22

Dmax

ft

2.59

3.11

1.71

Dmax/Dbkf

ft/ft

1.83

1.86

1.67

LTHL

ft

280

420.00

604.21

LV

ft

252

380.00

360

dElev

ft

1.86

10.10

2.91

K = LTHL/LV

ft/ft

1.11

1.1053

1.68

SV = dElev/LV

ft/ft

0.0074

0.0266

0.0081

Save = dElev/LTHL

ft/ft

0.0066

0.02405

0.0048

Wpbkf = 2*Dbkf+Wbkf

ft

13.23

11.23

13.55

R=Abkf/Wpbkf

ft

1.11

1.17

0.87

R/d84

ft/ft

47.05

49.61

36.84

(U*=((gRSave)^0.5)

ft/s

0.49

0.95

0.37

Qbkf (calculated based on Drainage area-OK-region1)

cfs

65.89

74.20

73.95

Ubkf = Qbkf/Abkf

ft/s

4.48

5.64

6.27

29 | P a g e

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))

0.029

0.0454

0.0150

Qbkf (calculated based on Drainage area-OK-region1&2)

cfs

79.69

88.38

88.12

Ubkf = Qbkf/Abkf

ft/s

5.42

6.71

7.47

0.024

0.0382

0.0126

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
Qbkf (calculated based on Drainage area-NC-Urban)

cfs

80.26

94.50

94.06

Ubkf = Qbkf/Abkf

ft/s

5.46

7.18

7.98

0.0238

0.0357

0.0118

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
Qbkf (calculated based on bankfull area-OK-region 1)

cfs

71.4529

64.0064

57.3547

Ubkf = Qbkf/Abkf

ft/s

4.8606

4.8623

4.8639

0.0267

0.0527

0.0193

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
Qbkf (calculated based on bankfull area-OK-Region 1&2)

cfs

49.2389

43.7630

57.3547

Ubkf = Qbkf/Abkf

ft/s

3.3495

3.3245

4.8639

0.0388

0.0770

0.0193

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
Qbkf (calculated based on Drainage area-USGS-Urban)

cfs

76.4133

91.7114

91.2465

Ubkf = Qbkf/Abkf

ft/s

5.1981

6.9669

7.7380

0.0250

0.0368

0.0121

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
Qbkf (calculated based on Drainage area -USGS-Rural)

cfs

77.5268

90.0578

89.6828

Ubkf = Qbkf/Abkf

ft/s

5.2738

6.8413

7.6054

0.0246

0.0374

0.0124

5.99

11.83

4.29

U/U*

12.30

12.43

11.70

n obtained from Rosgen (1996) Figure

0.026

0.026

0.027

n = (1.486/Qbkf)*(Abkf*((R)^(2/3))*((Save)^(0.5)))
U=[2.83+(5.66*log(R/d84)]*U*

ft/s

Qbkf=(1.486/n)*(Abkf*((R)^(2/3))*((Save)^(1/2))

cfs

73.473

129.689

41.053

Ubkf=(1.486/n)*((R)^(2/3))*((Save)^(1/2))

ft/s

4.998

9.852

3.481

Wfpa

ft

19.5

13.9

18.3

ER= Wfpa/Wbkf

ft/ft

1.88

1.76

1.5913

DTOB

ft

2.593

3.109

1.71

BHR = (DTOB/Dmax)

ft/ft

0.999

0.999

0.99

Lm (measured)

ft

198.96

MLR = Lm/Wbkf
Rc (measured)

17.30
ft

74.80

Rc/Wbkf
Wblt (measured)

6.50
ft

115.03

Wblt/Wbkf
Lrif

10.00
ft

Lrif/Wbkf
Riffle dElev

45.0

39.43

3.84

5.70

3.43

0.18

1.315

0.30

Srif

0.0045

0.0287

0.00752

Srif/Save

0.68

1.19

1.56

2.59

3.11

1.71

1.83

1.86

1.67

Dmaxriff
Dmaxriff/Dbkf

30 | P a g e

ft

40.0

ft

Dpool

ft

Dpool/Dbkf
Dmaxpool

ft

Dmaxpool/Dbkf
2

Apool

ft

Apool/Abkf
Wpool

ft

Wpool/Wbkf
Lpool

ft

Lpool/Wbkf
P-P

ft

P-P/Wbkf
PdElv

ft

1.39

1.32

1.20

0.84

1.29

0.85

3.2305

2.05

2.11

1.94

1.999

1.49

10.81

11.78

10.40

0.82

0.999

0.71

7.80

8.90

8.70

0.99

0.77

0.84

37.8

37.85

3.85

4.78

3.29

60

65

89.5

5.77

8.23

7.78

0.3

0.47

0.2825

Spool (down)

0.0255

0.053

0.0137

Spool/Save (down)

3.84

2.22

2.85

Spool (up)

0.0105

0.0176

0.017

Spool/Save (up)

1.58

0.733

3.555

Lrun

ft

20

20

25.895

RundElv

ft

0.47

0.96

0.455

Srun

0.0235

0.048

0.017

Srun/Save

3.54

1.996

3.648

Lglide

ft

20

20

10.59

GlidedElv

ft

0.53

0.34

0.06

Sglide

0.0265

0.017

0.00745

Sglide/Save

3.989

0.707

1.546

0.0236

0.0236

0.0236

32.2

32.2

32.2

d84 at riffle

3.1.

ft
ft/s

Old Settlers Creek Part A-Design:

The Proposed deign for the first part (part A) of Old Settlers Creek includes cross section,
and profile design. The stream pattern will stay as is. Summary of the new morphological
parameters and the new shapes of cross section, and profile are presented in Table 11 and
Figures 17-21. The detailed set of data is provided on a separate spread sheet.
Table 11:The new morphological parameters for Part A of Old Settlers.
Abkf (the same as the present average bankfull area of part A )

14.70

Qbkf (average value of the values presented in Table 10)

71.03

(W/D) based on Timber Creek ratio

11.22

31 | P a g e

Wbkf = (Abkf*(W/D))^0.5

12.84

Dbkf = Wbkf/(W/D) or Abkf/Wbkf

1.14

K (based on Timber Creek value)

1.68

Save = (SvalOld Settlers)/(KTimber Creek)

0.007

Validate the design--transport sediment

Good

Shear Stress ( = *R*Save)--(=62.4 lb/ft3)

0.403

Grain diameter(shear stress figure) (mm)

22-28

Wp = 2*Dbkf+Wbkf

15.129

R=Abkf/Wp

0.971

R/d84

41.131

Vbkf = Qbkf/Abkf

4.83

Manning's n = (1.486/Q)*(A*R^(2/3)*S^0.5)

0.025

Dmax = (Dmax/Dbkf)TC*Dbkf-OS

1.91

Wfpa-based on Old Settlers present conditions

27

Entrenchment ratio, Wfpa/Wbkf

2.10

Lv

252

Lthl (new shape)

280

K (based on new shape)

1.11

Sval

0.0074

Save=(Sval/K)

0.0066

Srif

0.0074

Max. Riffle depth

1.91

Spool

0.019

Apool

12.54

32 | P a g e

Dmax-pool

1.99

Wpool

10.34

Lpool

45.82

P-P spacing

87.0

Srun

0.024

Sglide

0.011119307

Stream type C6

.019

.019

.019

101

Legend
EG Q100Y
EG Q10Y
WS Q100Y
Crit Q100Y

100

EG Q1.5Y
Crit Q10Y
WS Q10Y
WS Q1.5Y
Crit Q1.5Y
Ground

99
Elevation (ft)

Bank Sta

98

97

96

10

20

30

40

50

Station (ft)

Figure 17: Old Settlers part A designed riffle-cross section, with the water level contributed
with the discharge rate.

33 | P a g e

101
100.5
100
99.5

Elevation (ft)

99
98.5
Designed riffle cross section

98

Present riffle cross section

97.5

97
96.5
96

95.5
0

10

15

20

25

30

35

40

45

Station (ft)

Figure 18: Old Settlers part A designed riffle-cross section, comparing to the present cross
section
.019

.019

.019

101

Legend
EG Q100Y
WS Q100Y
EG Q10Y
WS Q10Y

100

EG Q1.5Y
Crit Q10Y
WS Q1.5Y
Crit Q1.5Y
Ground
Bank Sta

Elevation (ft)

99

98

97

96

10

20

30

40

50

Station (ft)

Figure 19: Old Settlers part A designed pool-cross section, with the water level contributed
with the discharge rate.

34 | P a g e

102
101

Elevation (ft)

100
99
Designed pool cross section

98

Present pool cross section


97
96
95
0

10

20

30

40

50

Station (ft)

Figure 20: Old Settlers part A designed pool-cross section, comparing to the present cross
section
106
ES-THL
DS THL
104

ES-LB
ES-RB

102

DS-LBKF
DS-LBANK-Wfpa

100

98

96

94
0

20

40

60

80

100

120

140

160

180

200

220

240

260

280

300

320

Figure 21: Old Settlers part A designed profile. ES-THL: existing stream thalweg; DSTHL: designed stream thalweg; ES-LB: existing stream left bank; ES-RB: existing stream
right bank; DS-LBKF: designed stream left bankfull; DS-LBANK: designed stream left
bank.

35 | P a g e

3.2.

Old Settlers Creek Part B-Design:

The Proposed design for the first part (part B) of Old Settlers Creek includes cross
section, profile, and cross vanes design. The stream pattern will stay as is. Summary of the new
morphological parameters and the new shapes of cross section, and profile are presented in Table
12 and Figures 22-24. The detailed set of data is provided on a separate spread sheet.
Table 12:The new morphological parameters for Part B of Old Settlers.
Abkf (the same as the present average bankfull area of part A )

13.16

Qbkf (average value of the values presented in Table 10)

77.43

(W/D) based on Timber Creek ratio

11.22

Wbkf = (Abkf*(W/D))^0.5

12.15

Dbkf = Wbkf/(W/D) or Abkf/Wbkf

1.08

K (based on Timber Creek value)

1.11

Save = (SvalOld Settlers)/(KTimber Creek)

0.024

Validate the design--transport sediment

Good

Shear Stress ( = *R*Save)--(=62.4 lb/ft3)

1.38

Grain diameter(shear stress figure) (mm)

90

Wp = 2*Dbkf+Wbkf

14.32

R=Abkf/Wp

0.92

R/d84

38.92

Vbkf = Qbkf/Abkf

5.88

Manning's n = (1.486/Q)*(A*R^(2/3)*S^0.5)

0.037

Dmax = (Dmax/Dbkf)TC*Dbkf-OS

1.81

Wfpa-based on Old Settlers present conditions

26

Entrenchment ratio, Wfpa/Wbkf

2.14

Lv

380

36 | P a g e

Lthl (new shape)

420

K (based on new shape)

1.105

Sval

0.0266

Save=(Sval/K)

0.024

Srif

0.033

Max. Riffle depth

1.81

Spool

0.056

Apool

11.98

Dmax-pool

1.945

Wpool

10.70

Lpool

49.06

P-P spacing

63.0

Srun

0.067

Sglide

0.027

Stream type C6

37 | P a g e

99
98
97
96
95
Designed riffle cross section
94

Present riffle cross section

93
92
91
90
0

10

15

20

25

30

35

40

45

Figure 22: Old Settlers part B designed riffle-cross section, comparing to the present cross
section
99
98
97
96
Designed pool cross section

95

Present pool cross section


94
93
92
91
0

10

15

20

25

30

35

40

45

Figure 23: Old Settlers part B designed pool-cross section, comparing to the present cross
section

38 | P a g e

100
98
96
94

ES-THL
DS THL

92

ES-LB
90

ES-RB
DS-LBKF

88

DS-LBANK-Wfpa
86
84
82
300

340

380

420

460

500

540

580

620

660

700

740

780

820

860

Figure 24: Old Settlers part B designed profile. ES-THL: existing stream thalweg; DSTHL: designed stream thalweg; ES-LB: existing stream left bank; ES-RB: existing stream
right bank; DS-LBKF: designed stream left bankfull; DS-LBANK: designed stream left
bank.
In order to get more stability to the stream, it is better to simulate the thalweg slope of the
part A, and to do that cross vane is proposed to control the stream grade. The thalweg elevation
difference in part A is 1.86 ft, and that for part B is 10.1 ft, so the elevation difference that needs
control is 8.24 ft. Figures 25-29 show the design of cross vanes on riffle and pool.

39 | P a g e

3
2

0
-5

0
0

10

15

20

Figure 25: Cross vane design on riffle-top view.


cross vane side (leg) length = 8.1 ft; cross vane
(cross beam) length = 4.05 ft; angle = 30

-5

10

15

Figure 26: Cross vane design on pool -top view.


cross vane side (leg) length 713 ft; cross vane
(cross beam) length = 3.57 ft, angle = 30

2.00

2.50

1.80
1.60

2.00

1.40
1.20

1.50

1.00
0.80

1.00

0.60
0.40

0.50

0.20
0.00
-5

0.00
0

10

15

Figure 27: Cross vane design on riffle-side


view. Each cross vane can make 1.01 ft
differencein the elevation

20

-5

10

15

Figure 28: Cross vane design on riffle-side view.


Each cross vane can make 0.48 ft differencein the
elevation

From figures 25-28, number of cross vanes that could reduce the elevation difference
from 10.1 to 1.86 are 8 vanes on riffles by 51 ft gap between each other or 17 vanes on pools by
24 ft gap between each other. Based on the bankfull shear stress the minimum rock size required
to build the vanes is 3.16 ft.

40 | P a g e

Figure 29: Old Settlers part B cross vane design.

3.3.

Cut and Fill

While approximate estimates of cut and fill would be possible from the above design, more
accurate estimates can be made if a construction survey is performed in the area. Based on
figures 18-24, it is obvious that the amount of soil to be hauled off-site would be minimal and
most of the work will consist of moving earth and reshaping the channels.

4.

Vegetation Plan

4.1

Planting Methods

While a combination of panting methods are available for stabilization of the steambanks, an
approach will need to be taken to ensure the best and most economic results. The planting
methods include:
aOn-site vegetation salvaging: Due to the location of the site, very few riparian vegetation
is present especially in Part A of the stream. A closer vegetation survey of Part B of the stream
will allow us to select riparian vegetation and remove invasive species. The City Arborist could
also recommend the saving of riparian trees or the removal of other trees in the streambank area.
Some salvaged vegetation will need to be removed and replanted after construction.
bLive Staking: Cuts from certain trees from the site can be taken and replanted. Stakes
should range from 1-hlaf inch t o2 inch in diameter. Stakes should be planted in late fall to early
spring when they are dormant. They are installed 2- 4 feet apart using triangular spacing along
the streambanks.

41 | P a g e

c-

Bare root plantings: This type of planting is not recommended for this site.

dContainer plant material: This is the most expensive plant material but can be an option
for large trees that are suitable for the area and are only available through nurseries.
ePermanent seeding: This is the most recommended method for this site. It provides
maximum habitat diversity and ground cover. Permanent seeding mixtures are available from
nurseries. A native flora mix with herbaceous species and grasses is recommended. Site
preparation would include mechanical loosening of the bed (where possible) and disking of
compacted soils. Mixing 2-4 inches plant-based compost would improve germination rates and
establishment. Mulch with straw mulch over seeded areas at a rate of 3 bales per 1000 sq. ft.
Anchor with biodegradable netting.
fIn order to increase community involvement, the planting process can be organized as a
community event with Master Gardeners, Master Naturalists, school students, scout troops and
the general public (in the neighborhood) involvement as the primary groups to target.

5.

Plant Selection

Plant selection will be from a palette of native species suitable for stream bank
revegetation developed by NRCS (Table 2). A combination of grasses and woody plants
appropriate for the soil and sunlight conditions will be selected. Planting techniques will include
a combination of direct seeding for grasses and transplanting for perennials and woodies,
salvaging and enhancing on-site vegetation, and live staking.
Table 13. List of plant species to be considered for use in the stabilization of
eroded streams in the Cedar Creek Reservoir watershed.
SCIENTIFIC NAME

COMMON NAME(S)

Grasses Sun
Panicum virgatum

Switchgrass

Sorghastrum nutans

Indian grass

Muhlenbergia capillaris

Gulf muhly grass

Muhlenbergia linderheimeri

Lindheimer muhly

Perennials Sun
Helianthus maximiliana

Maximillian sunflower

Hibiscus militaris

Halberd leaf hibiscus

Phylla nodiflora

Frogfruit

42 | P a g e

Physotegia virginiana

Fall obedient plant

Woodies- Sun
Amorpha fruticosa

Indigobush

Baccharis salicifolia

Mule-fat, False willow, Seep willow

Baccharis halimifolia

Eastern baccharis

Cornus drummondii

Roughleaf dogwood

Cornus racemosa

Gray dogwood

Elaeagnus commutata

Silverberry

Lonicera involucrate

Twinberry honeysuckle, Black twinberry

Populus angustifolia

Narrowleaf cottonwood

Populus balsamifera

Black cottonwood

Populus deltoids

Eastern cottonwood

Populus deltoids

Plains cottonwood

Robinia pseudoacacia

Black locust

Salix nigra

Black willow

Salix exigua

Narrowleaf willow

Salix amygdaloides

Peachleaf willow

Salix lasiolepsis

Arroyo willow

Salix caroliniana

Coastal Plain willow

Salix humilis

Prairie willow

Viburnum dentatum

Southern arrowwood

Grasses Shade
Chasmanthium latifolium

Inland sea oats, River oats

Tripsacum dactyloides

Eastern gama grass, Fakahatchee

Muhlenbergia reverchonii

Seep muhly

Perennials Shade
Eupatorium coelestinum

43 | P a g e

Blue mistflower, wild ageratum

Lobelia cardinalis

Cardinal flower

Salvia coccinea

Scarlet, tropical sage

Thelypteris kunthii

Wood fern

Woodies Shade
Callicarpa Americana

American beautyberry

Ilex decidua

Possumhaw holly

Ilex vomitoria

Yaupon holly

Itea virginica

Sweetspire

Malvaviscus drummondii

Turks cap

Myrica cerifica

Wax myrtle

Myrica pussila

Dwarf wax myrtle

Natural Resources Conservation Service (NRCS). 2010. Stream Restoration, Planning and Design
Field Guide. 128 p.
Plant List for Revegetation (1 p.), from Laura M. Miller, County Extension Agent (Commercial
Horticulture) in Tarrant County, Texas.

6.

Erosion and Sediment Control Plan

All restoration should comply with TCEQ regulations and the Clean Water Act. During
construction measures must be taken to control erosion and minimize the production of sediment
and other pollutants of water and air.

6.1

Construction Sequence

The stream should be divided in to Part 1 and Part 2 (Figure 16) and the first segment can
be completed and stabilized before completing the second segment. Areas excavated should be
unprotecte4d from erosion for the shortest time feasible. Stockpiled soils should be gathered in
designated areas and surrounded with silt fences.
Construction should be done during dry times or a diversion channel will need to be
constructed during restoration of the main channel. Alternatively, a pump can be used given the
small size of the watershed. If these options are too expensive, working in the active channel,
although to be avoided, can still be done. In the latter case, the work in the active channel should
be completed during a single day.
Other temporary measures to be considered are:

44 | P a g e

6.2

Stream crossings: equipment should cross at fords or temporary culverts. The fords
ramps need to be graded at 5:1 or flatter and lined with stone. Filter fabric combined with
stone should be installed in the bed. Temporary culverts need to carry at least the bankfull
flow. Stones should be placed upstream and downstream of the culverts and soil should
be filled around the culvert. Stones should be placed on top of the fill where heavy
machinery will operate.
Sediment filters: Geotextile sediment fencesshould be built to trap sediments in low
runoff areas (not concentrated flow). Install the fences on the contour along the entire
downstream perimeter of the area being disturbed.
Coconut/Straw Fiber Blankets: should be used on the banks of non-vegetated streams.
Biodegradable blankets can be left in place while vegetation establish and are safer for
wildlife.

Pollution Control: Seeding

All disturbed areas including streambanks, access areas, and stockpile locations need to
be seeded immediately after construction is completed. Temporary (annual) and permanent
seeding should be used. Seeding requires bed preparation, which consists of loosening the seed
bed mechanically, breaking any compaction and applying 2-4 inches of plant based compost
tilled into the soil.

7.

References

Doll, B.A., G.L. Grabow, K.R. Hall, J. Halley, W.A. Harman, G.D. Jennings and D.E. Wise,
2003. Stream Restoration: A Natural Channel Design Handbook. NC Stream Restoration
Institute, NC State University. 128 pp.
Dutnell. 2000. Development of bankfull discharge and channel geometry relationships for
natural channel design in Oklahoma using a fluvial geomorphic approach. Masters Thesis.
University of Oklahoma.
Rosgen, D.L. (1996). Applied River Morphology. Wildland Hydrology, Pagosa
Springs,Colorado.
Rosgen, D.L. (2006). Watershed Assessment of River Stability and Sediment Supply
(WARSSS). Wildland Hydrology, Fort Collins, Colorado.
USGS. 2001. Methods for estimating flood magnitude and frequency for natural basins in Texas,
2001. Fact sheet # 022-01. Washington, DC.

45 | P a g e

You might also like