Purpose
The purpose of this procedure is to detail the means and materials that will be
used to perform structural backfilling on the project.
B.
Scope of Work
-
C.
Backfilling
Soil investigation & Density test
Reference Document
The following documents are the reference documents for this work :
D.
E.
Sequence of Works
a.
b.
Backfilling shall not commence until the request for inspection before
backfilling is completed and any deficiencies corrected. All areas to
Page
2 of 4
METHODE PROCEDURE
for FOR BACKFILLING WORK
Rev. no.
:0
Date
: 1 Jun 2015
Doc. No.
: SSP/MP-RTF/004
receive backfill shall be free of water, debris and organic material and
shall be sufficiently wide to permit the equipment to operate efficiently.
c.
F.
Density Test
The required density for structural backfilling shall be as follows :
b.
Layer 30 cm from the finished surface shall be compacted to 90% of
maximum dry density according to AASHTO
c.
Field density test (CBR) shall be carried out for 2500 m2 or 50 m x 50 m
of each lift / layer.
d.
If location not properly for CBR Test shall be conform to ASTM D 1556
for sand cone replacement method.
G.
Equipment to be used
The following equipment shall be available for the purpose of compacting
structural fill :
1.
2.
3.
4.
5.
H.
Page
3 of 4
METHODE PROCEDURE
for FOR BACKFILLING WORK
I.
Rev. no.
:0
Date
: 1 Jun 2015
Doc. No.
: SSP/MP-RTF/004
Page
4 of 4