Professional Documents
Culture Documents
Conceptual
Design Report
Contents
Section 1
1.1
1.2
1.3
1.4
1.5
Section 2
2.1
2.2
2.3
Section 3
3.1
3.2
3.3
3.4
3.5
3.6
Section 4
4.1
4.2
4.3
4.4
A
5816-72780
Introduction
Purpose ...................................................................................................................... 1-1
Existing Biosolids Treatment .................................................................................. 1-2
Project Drivers, Goals and Objectives.................................................................... 1-3
Project Components ................................................................................................. 1-3
Facility Layout Options ........................................................................................... 1-4
1.5.1
Option 1: New Separate Facility ............................................................. 1-5
1.5.2
Option 2: Retrofit of Existing Interior Process Space .......................... 1-5
Table of Contents
Lewiston Auburn Water Pollution Control Facility
Anaerobic Digestion / Energy Recovery Project
Draft Conceptual Design Report
4.5
4.6
4.7
Section 5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
Section 6
6.1
6.2
6.3
ii
Table of Contents
Lewiston Auburn Water Pollution Control Facility
Anaerobic Digestion / Energy Recovery Project
Draft Conceptual Design Report
6.3.5
6.3.6
6.3.7
6.3.8
6.3.9
Section 7
7.1
7.2
Section 8
8.1
8.2
Section 9
9.1
9.2
Table of Contents
Lewiston Auburn Water Pollution Control Facility
Anaerobic Digestion / Energy Recovery Project
Draft Conceptual Design Report
9.3
Section 10
10.1
10.2
10.3
Section 11
11.1
11.2
9.2.4
Subsurface Investigations......................................................................... 9-2
9.2.5
Geotechnical Laboratory Testing ............................................................ 9-3
9.2.6
Conceptual-Level Geotechnical Evaluation........................................... 9-5
9.2.7
Conceptual-Level Foundation Recommendations ............................... 9-6
9.2.8
Recommended Phase 2 Exploration Program ....................................... 9-7
Site Design Considerations ..................................................................................... 9-7
9.3.1
Codes and Standards ................................................................................ 9-7
9.3.2
Site Preparation.......................................................................................... 9-8
9.3.3
Materials ..................................................................................................... 9-8
9.3.4
Grading and Drainage .............................................................................. 9-9
9.3.5
Erosion and Sedimentation Control ....................................................... 9-9
9.3.6
Landscape ................................................................................................... 9-9
9.3.7
Layout Specific Site Design Considerations ........................................ 9-10
Permitting
Purpose .................................................................................................................... 10-1
Local Permitting...................................................................................................... 10-1
10.2.1 Urban Enterprise (UE) and Resource Conservation (RC) Zoning
Districts Provisions ................................................................................. 10-1
10.2.2 Local Flood Protection Provisions ........................................................ 10-1
10.2.3 Natural Resources Protection Act (NRPA) Permit ............................. 10-2
10.2.4 Stormwater Runoff and Flood Management Permitting ................... 10-2
10.2.5 Local Permit Application and Approval Schedule ............................. 10-2
Air Quality Permitting ........................................................................................... 10-3
Appendices
Appendix A:
Appendix B:
Appendix C:
iv
Table of Contents
Lewiston Auburn Water Pollution Control Facility
Anaerobic Digestion / Energy Recovery Project
Draft Conceptual Design Report
Tables
2-1
2-2
2-3
2-4
2-5
2-6
3-1
3-2
3-3
3-4
3-5
4-1
4-2
4-3
4-4
4-5
4-6
5-1
5-2
5-3
7-1
9-1
9-2
10-1
11-1
11-2
Conceptual Estimate of Project Costs Based on 10% Level of Design ............ 11-1
Comparison of Facility Layout Options .............................................................. 11-2
Table of Contents
Lewiston Auburn Water Pollution Control Facility
Anaerobic Digestion / Energy Recovery Project
Draft Conceptual Design Report
Figures
vi
1-1
1-2
1-3
4-1
4-2
4-3
4-4
4-5
5-1
7-1
7-2
9-1
9-2
Section 1
Introduction
1.1
Purpose
A
5816-72780
1-1
Section 1
Introduction
Section 1
Introduction
biosolids while lime stabilization is used primarily in the late spring, summer and
early fall months.
Elimination of the cost to transport excess biosolids that currently exceed the
capacity of the composting facility. Associated tipping fees will also be eliminated.
Reduction of biosolids odors, thereby making the LAWPCAs existing Class B land
application program more acceptable to nearby property owners.
Biogas utilization from the anaerobic digestion process in a combined heat and
power (CHP) application to produce electricity and heat. The electricity produced
would offset a portion of power currently purchased and the heat would be used
for digester and building heating.
Increase of the overall solids handling capacity of the plant by reducing the volume
of sludge through anaerobic digestion. Currently the plant is limited by the
capacity of the existing dewatering and biosolids stabilization equipment.
Establish LAWPCA and the Cities of Lewiston and Auburn as environmental and
energy conservation leaders in the State of Maine with the first anaerobic digestion
facility in the state.
1-3
Section 1
Introduction
option, additional facilities and equipment required to support the digesters would
include the following:
Waste gas burner for burning any excess gas not utilized and to provide an outlet
for gas production should gas treatment and utilization be out of service.
Yard piping modifications for digester overflow, drain, sludge feed, sludge
recirculation, sludge mixing and other utilities as required; and
It should also be noted that, in the event that Option 2 is selected, the layout of this
equipment and associated space constraints will require modifications to the influent
screening systems. In this event, the following equipment upgrades will also likely be
required as part of the project:
Modifications to the existing screening garage to provide an isolated space for new
equipment for the digestion process.
The solids process flow diagram associated with the proposed anaerobic digestion
and energy recovery system systems and equipment is presented in Figure 1-1.
1-4
Section 1
Introduction
Reduce the amount of new interior process space by installing a portion of the
digestion equipment within the existing building;
Minimize yard piping and pumping by locating the new digestion facility as close
as physically possible to the existing thickening and dewatering areas; and
As shown in Figure 1-3, the current configuration of the Option 2 layout attempted
to reuse the space as previously intended. It should be noted however that, due to
space limitations within the screenings garage and adjacent areas, a new (subsurface)
interior process space adjacent to the new digesters is still required. In addition, a
new screenings garage located to the east of the process building is also needed to
replace the existing garage.
The advantages, disadvantages and cost implications of each layout option are further
detailed in subsequent sections of this report.
1-5
Section 2
Biosolids Quantities and Characteristics
2.1 Existing Sludge Quantities and Characteristics
The purpose of this section is to review the sludge quantities and characteristics used
as the preliminary basis of design for waste activated sludge (WAS) thickening and
anaerobic digestion improvements at the LAWPCA facility. Though a summary of
the biosolids design criteria is presented here, a detailed breakdown as to the
development of these values can be found in the Feasibility Study.
To establish current wastewater solids quantities and characteristics, LAWPCA
recommended that CDM utilize the results of the calibrated BioWin model, presented
in the 2008 Capacity Evaluation of the Water Pollution Control Facility for the Lewiston
Auburn Water Pollution Control Authority prepared by Wright-Pierce. Current flows
and loads to the primary clarifiers are summarized in Table 2-1. Approximately 96%
of the plant influent is raw wastewater from the cities of Lewiston and Auburn, 1.5%
from Cascade Auburn Fiber de-inking facility, 1.5% from solids handing recycle, and
less than 1% from septage received. The concentration of BOD in the wastewater from
Cascade Auburn Fiber is approximately 4,100 mg/l. As such, approximately 35% to
50% of the BOD load to the treatment facility comes from the de-inking facility.
Primary sludge is thickened by gravity and WAS is thickened using dissolved air
floatation (DAF). Table 2-2 and Table 2-3 summarize thickened primary sludge and
WAS quantities and characteristics. Currently, thickened primary sludge and WAS
are blended and dewatered using belt filter presses (BFPs). With anaerobic digestion
incorporated into the existing biosolids processing system, the primary sludge and
WAS will continue to be thickened separately, then blended, and digested and
dewatered using the existing BFPs.
9/2003 9/2007
Average Day
Max Month
13.2
20.1
32.0
32.0
BOD (lbs/day)
25,100
38,300
TSS (lbs/day)
23,300
32,500
Table 2-1
Plant Influent, 2003-2007
A
5816-72780
2-1
Section 2
Biosolids Quantities and Characteristics
Average Day
Max Month
MGD
0.024
0.035
12,900
18,900
6.3
6.5
% Solids
Table 2-2
Thickened Primary Sludge, 2003-2007
Average Day
Max Month
MGD
0.051
0.066
10,900
18,600
2.6
3.4
% Solids
Table 2-3
Thickened Waste Activated Sludge, 2003-2007
Max Month
MGD
0.026
0.045
10,900
18,600
5.0
5.0
% Solids
Table 2-4
Thickened Waste Activated Sludge, DAF Replacement
2-2
Section 2
Biosolids Quantities and Characteristics
According to plant staff, the existing gravity thickeners are operating well and no
improvements are necessary or planned outside of normal maintenance and periodic
rehabilitation. With new WAS thickening equipment and the existing primary
thickeners remaining, the combined thickened sludge will have the estimated
quantities and characteristics given in Table 2-5. Based on plant operating data, a
volatile suspended solids (VSS) to total suspended solids (TSS) concentration of 0.75 is
used.
Average Day
Max Month
0.050
0.080
5.7
5.6
TSS (lbs/day)
23,800
37,500
VSS (lbs/day)
17,800
28,100
5,900
9,400
Table 2-5
Combined Thickened Sludge, WAS thickened to 5%
Current + 15%
Average Day
Max Month
Average Day
Max Month
0.050
0.080
0.058
0.092
5.7
5.6
5.7
5.6
TSS (lbs/day)
23,800
37,500
27,400
43,100
VSS (lbs/day)
17,800
28,100
20,500
32,300
5,900
9,400
6,900
10,800
Table 2-6
Combined Thickened Sludge Feed to Digester
2-3
Section 3
Waste Activated Sludge Thickening
Improvements
3.1 Background and Existing Conditions
As previously noted, currently at the LAWPCA Facility secondary sludge is pumped
directly from return activated sludge lines to two dissolved air floatation (DAF) units,
thickening the waste activated sludge (WAS) to between 2.63.3% solids. The two
existing DAF units were constructed along with the original Secondary Treatment
Facilities in 1971.
After the DAF thickening process, the thickened WAS (TWAS) flows by gravity from
the DAF units to one of four dedicated holding tanks. Facility operators have reported
that when both DAF units are operating, the TWAS solids concentration should be
approximately 3% solids or less to allow it to flow by gravity from the DAFs to the
TWAS holding tanks.
For thickened sludge concentrations exceeding 3% a pair of TWAS transfer pumps are
required to pump sludge to the holding tanks. According to plant operators, the
TWAS pumps are not operational and have not been operated since their original
installation nearly forty years ago. The current location of the TWAS pumps (DAF
room sub-basement crawl space) is a confined space and access to the pumps is
restricted due to numerous ducts and pipelines that block direct access to the pumps.
According to plant operators, The DAFs meet current process requirements, however,
the anaerobic digestion process being proposed will require WAS to be thickened to
over 5.5% in the future. As previously noted, the existing DAF equipment is original
to the plant and would required substantial rehabilitation or replacement in order to
achieve TWAS concentrations required for optimal performance of the proposed
digestion. Furthermore, operation and maintenance costs for the units have been
escalating recently as spare parts are difficult to locate or are no longer readily
available from the manufacturer or aftermarket suppliers.
Although the DAF thickeners are original to the plant and have reached the end of
their anticipated life expectancy, the main driver for replacing the units is to increase
the solids percentage of the sludge being fed to the anaerobic digester. By increasing
the solids percentage, the volume of the digester decreases and less tankage is
required. Furthermore, irrespective of the proposed digestion improvements,
replacement of the DAFs will provide for a more efficient, reliable, and cost effective
method for thickening waste activated sludge.
A
5816-72780
3-1
Section 3
Waste Activated Sludge Thickening Improvements
Condition
Hydraulic
Loading
Hydraulic
Loading
Solids
Loading
Percent Solids
(wet - gpd)
(WET-GPM)
(dry lb/hr)
(%)
Average Day
208,000
408
1,500
0.71
Maximum Month
283,000
555
2,500
0.92
Table 3-1
Estimated Loading Rates for WAS Thickening
3.3
Current available technologies that were considered for sludge thickening include
gravity belt thickeners (GBTs), Rotary Drum Thickeners, and DAFs.
Continued use of the existing DAFs is not being considered as an alternative for
future thickening at the facility due to the limited and unreliable thickening
3-2
Section 3
Waste Activated Sludge Thickening Improvements
performance, advanced age of the equipment, lack of availability of spare parts, and
higher operating costs associated with the DAF system.
Gravity belt thickeners (GBTs) and rotary drum thickeners (RDTs) are both evaluated
further as viable WAS thickening options. Both GBTs and RDTs are considered
relatively simple to operate, require minimal operator attention, and have a proven
track record for WAS thickening.
The following sections review the evaluation and comparison of Rotary Drum
Thickeners and Gravity Belt Thickeners.
Process Description
A rotary drum thickener, similar to a gravity belt thickener, achieves solid-liquid
separation by coagulation and flocculation of solids and drainage of free water
through a rotating porous media. The porous media typically consists of a drum with
wedge wires, perforations, or stainless steel mesh screen.
The thickener consists of an internally fed rotary drum with an internal screw, which
is used to transport the thickened sludge out of the drum, The drum rotates on
trunnion wheels and is driven by a variable speed drive. Sludge is usually polymer
conditioned and mixed in a flocculation tank prior to thickening.
The conditioned sludge is then fed directly to the interior of the drum via piping to
one end of the drum. As the drum rotates free water passes through the drum
perforations into a collection trough, leaving thickened sludge inside the drum that is
discharged by the internal screw at the opposite end into a hopper. A continuous
fixed spray bar extends along the entire length of the drum to clean and prevent
blinding of the screen.
Process Assessment
Several equipment manufacturers were contacted for equipment consultation and
sizing assistance for RDT WAS thickening applications and provided the following
information:
3-3
Section 3
Waste Activated Sludge Thickening Improvements
Polymer consumption for WAS thickening ranges from 8 12 lbs / dry ton
Odors are generated during thickening but can be contained by adding odor
control covers
A total of (3) RDT units each rated at 350 GPM are required to meet max month
conditions during an operating shift
Capital Costs per RDT range from $168,000 $200,000 each (equipment only)
Process Description
GBTs operate on the principle of coagulation and flocculation of solids in dilute
sludge. The sludge is conditioned with polymer to coagulate and concentrate the
solids. The conditioned sludge is then fed to a distribution box, which evenly applies
the conditioned sludge to a fabric belt. As the conditioned sludge is conveyed along
the belt, plow blades create furrows that allow water to pass through the belt.
The thickened sludge is then discharged to a hopper and the belt passes through a
wash cycle to remove any trapped solids in the fabric mesh. GBTs can achieve a
solids capture of approximately 95 percent and can thicken sludge with initial
concentrations of 0.5% up to 4 to 8%. GBTs can be furnished with enclosures integral
to the GBT frame to contain odors and exhaust them to an odor control system. The
enclosures provide access to the top of the belt through hinged access panels while
the side panels are typically bolted on.
Process Assessment
Several equipment manufacturers were contacted for equipment consultation and
sizing assistance for GBT WAS thickening applications and provided the following
information:
3-4
Section 3
Waste Activated Sludge Thickening Improvements
Gravity belt thickeners offer a higher degree of process performance flexibility than
RDTs due to their ability to be loaded at higher hydraulic and solids loading rates
than a comparable RDT.
Hydraulically loading rates for WAS thickening applications range between 250
300 gpm/meter.
Polymer consumption for WAS thickening ranges from 6-12 lbs/dry ton
Odors are generated during thickening and increased ventilation of thickening area
is recommended.
A total of two 2-meter GBT units each rated at 550 GPM are required to meet max
month conditions. (1 duty 1 standby)
Capital Costs per GBT range from $135,000 $168,000 each (equipment only)
3-5
Section 3
Waste Activated Sludge Thickening Improvements
Process
Rotary Drum
Thickeners
Advantages
Relatively low power consumption
Polymer Dependent
Compact Footprint
Gravity Belt
Thickening
Disadvantages
Odors generated
Polymer dependent
Odors generated
Building corrosion potential if not
ventilated adequately
Higher washwater pressure requiring
a booster pump
Table 3-2
Non-Cost Comparison of Thickening Alternatives
3-6
Section 3
Waste Activated Sludge Thickening Improvements
Parameter:
Komline Sanderson
Parkson Corporation
Charter Machine
Vulcan Industries
Ashbrook
BDP Industries
Size Unit:
< 95 %
Manufacturers Referenced:
Thickened Solids
Polymer Consumption
35 40 gpm @ 85 PSI
40 51 pm @ 40 psi
Motor horsepower
(connected)
Table 3-3
Performance Comparison for Thickening Alternatives
$ 504,000 $600,000
$ 270,000 $330,000
Table 3-4
Comparison Costs for Thickening Alternatives
3-7
Section 3
Waste Activated Sludge Thickening Improvements
Installation, annual labor, and maintenance costs were not evaluated in this analysis
because they were assumed to be relatively equal for both thickening options. As
presented above, thickening of secondary sludge utilizing two 2-meter GBTs is a
significantly less expensive option than thickening by RDTs by approximately
$174,000 or more.
Section 3
Waste Activated Sludge Thickening Improvements
2 meters
8.5 hours per day, 7 days per week - Avg Day
11 hours per day, 7 days per week Max Month
Number of units
0.7% 0.92%
5.0 6.0%
Minimum capture
95%
10 lbs/ton
Several manufacturers were contacted for details on equipment which could meet the
design criteria provided above. GBT performance specifications, cost and other
information were provided by Komline-Sanderson, Charter Machine, and Ashbrook.
3-9
Section 3
Waste Activated Sludge Thickening Improvements
thickened sludge hopper at the discharge end of each GBT. The pumps will draw
sludge directly from thickened sludge hoppers at each GBT and pump TWAS to one
of several holding tanks.
Progressive cavity pumps are being recommended for TWAS pumping due to the
wide pumping range high discharge pressure abilities. Each pump will be rated at
180 gpm at 40 psig and driven with a 15-HP variable speed motor.
The pumps will be controlled by level sensors in the thickened sludge hoppers. The
pump speed will be varied by a controller located in the local Operator Control Panels
to regulate sludge levels in the hopper during thickening operations.
The sludge pumps will also be equipped with instrumentation devices to protect the
pumps and piping. These include High/Low discharge pressure switches to stop the
pump on high or low discharge pressure and a Low seal water pressure switch which
will stop the pump on low seal water pressure. These pressure switches will be
interlocked with the sludge feed to the thickener such that the thickener system will
stop operating in the event of high discharge pressure or low seal water pressure. The
basis of design for the TWAS transfer pumps is presented in Table 3-5 below:
Description
Criteria
Quantity
Pump type
Progressive cavity
Pump capacity
0 180 GPM
Discharge pressure
100 PSI
4% 6%
Motor type
Variable speed
Motor size
15 HP
Table 3-5
Design Criteria TWAS Transfer Pumps
3-10
Section 3
Waste Activated Sludge Thickening Improvements
3.6
To facilitate the installation of the new GBTs, construct the new electrical room, and
demolish the old DAF units, construction will require strict sequencing to maintain
WAS thickening capability at all times. A brief summary of the proposed construction
sequence is provided below:
1.
2.
Construct new electrical room and install new electrical equipment switchover
from old to new MCC.
3.
4.
5.
6.
7.
8.
9.
3-11
Section 4
Anaerobic Digestion and Sludge Storage
Improvements
4.1 General
Anaerobic digestion is a biological process that stabilizes organic matter in the
absence of oxygen. During this process, organic matter is converted to methane (CH4)
and carbon dioxide (CO2) and the remaining solids are stabilized. The digested sludge
is less odorous, attracts fewer vectors, and contains fewer pathogens than undigested
sludge. The conversion of solids into gas, results in less mass and volume to process
downstream and dispose of or be beneficially used.
A
5816-72780
4-1
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Average Day
Max Month
0.058
0.092
Percent Solids
5.7
5.6
TSS (lbs/day)
27,400
43,100
VSS (lbs/day)
20,500
32,300
6,900
10,800
Flow (MGD)
Table 4-1
Combined Thickened Sludge to Digester System, Basis of Design
Table 4-2 summarizes the digester configuration options while Figure 4-1 depicts the
general layout of the tanks.
4-2
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Alternative A
Standard Digesters
Parameter
Number of Digesters
Alternative B
Cylindrical Digesters
Diameter, feet
65
50
30.5
52
15
20
690,000
690,000
92,000
92,000
Gallons
760,000
760,000
Cubic Feet
101,500
101,500
1,520,000
1,520,000
203,000
203,000
Average
20
20
Maximum month
15
15
Tank Dimensions
(2 Tanks)
Gallons
Cubic Feet
Design SRT
Table 4-2
Digester System Configurations Summary
4-3
Section 4
Anaerobic Digestion and Sludge Storage Improvements
operate between 8.5 and 11 hours per day. As a result, storage volume is required to
contain and allow for continuous feed of TWAS to the digesters during the 13 to 15.5
hours per day during which the WAS thickening system is not in operation.
For the proposed digestion project, it is recommended that the existing TWAS storage
tanks, located west of the Process Building below grade, be used to feed TWAS to the
digesters continuously. The four tanks have a combined volume of approximately
40,000 gallons, not all of which is considered to be active due to pumping
considerations. At average day conditions, approximately 17,000 gallons of the tank
volume will be utilized during off hours while using a continuous feed rate to the
digesters of approximately 20 gallons per minute (gpm). At maximum month
conditions, 24,000 gallons of TWAS storage will likely be needed, which would be fed
continuously to the digesters at a rate of approximately 30 gpm. It should also be
noted that the TWAS storage volume required will vary depending on the actual
percent solids, flow rates and daily processing schedule.
Section 4
Anaerobic Digestion and Sludge Storage Improvements
flowing by gravity to the digested sludge storage tank, would be stored within this
tank and then be pumped to the belt filter presses when in operation. It is also
recommended that a bypass from the digester sludge feed pipe be provided to this
storage tank. This bypass would allow thickened sludge flows and loads which
might exceed the design loading rates of the digester system to bypass the digesters
and be sent directly to dewatering.
Figure 4-2 depicts the general layout of the proposed sludge storage tank.
Compensate for heat losses through walls, floor and digester roof; and
Make up the losses that may occur in the piping between the heat source and the
digester tank. Typically when the pipe length is limited, these losses are minimal
and are not included in the digester heating requirements calculations.
Q1 = W C p (T2 T1 )
where:
W = Sludge to Digester, lbs/hour
Q1 = Heating Required (BTU/hr)
Cp = Specific Heat of Water (BTU/lb/F)
T2 = Heated Sludge Temperature (F)
T1 = Cold Sludge temperature (F)
T1 can be estimated based on the geographical location of the digester as well as
historical plant data. For the purpose of this evaluation, it is estimated that the
4-5
Section 4
Anaerobic Digestion and Sludge Storage Improvements
temperature of the sludge entering the digester is 45 F in the winter and 70 F in the
summer. Table 4-3 presents the estimated energy required to heat the sludge entering
the digester. Heating requirements are given in millions of British Thermal Units per
hour (MBTU/hr).
Average Day
Maximum Month
Winter
Summer
Winter
Summer
58,000
58,000
92,000
92,000
95
95
95
95
45
70
45
70
45
25
45
25
20,000
20,000
32,000
32,000
1.00
0.50
1.60
0.80
Table 4-3
Sludge Heating Requirements
Q2 = U A (T2 T1 )
Where:
Q2 = heat loss (BTU/hr)
U = heat transfer coefficient (BTU/ ft2/F/hr)
T2 = operating Temperature of Digester (F)
T1 = air temperature outside of tank (F)
A = Area of exposed surface (ft2)
The design outside temperatures used in the heat loss analysis are based on the 2009
Pluming Code for Portland, ME and are -1 F in winter and 72 F in summer. Though
the heat losses per digester, summarized in Table 4-4, were calculated based on the
standard digester tank configuration, it should be noted that similar calculations were
performed for the cylinder tank option and yielded similar heat loss results.
4-6
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Description
Configuration
Number of Digesters
Diameter
65 feet
Sidewater Depth
30.5 feet
Floor
Digester Cover
Table 4-4
Digester Tank Configuration
Table 4-5 summarizes conductive heat losses based on the digester tank configuration
and the digester material U factors. U factors values are from the EPAs Process
Design Manual for Sludge Treatment and Disposal (United States Environmental
Protection Agency, 1979).
Winter
Summer
0.09
0.02
0.05
0.01
0.07
0.02
0.16
0.04
0.37
0.09
0.74
0.018
Table 4-5
Conductive Heat Loss
4-7
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Average Day
Maximum Month
Winter
Summer
Winter
Summer
1.00
0.50
1.60
0.80
0.74
0.18
0.74
0.18
1.74
0.68
2.34
0.98
Table 4-6
Digester Heating Requirements
Heating system
Mixing system
Digester covers
4-8
Section 4
Anaerobic Digestion and Sludge Storage Improvements
blending and preheating of the feed and active digester sludge before it enters the
digester.
External heat exchangers include combined boiler/heat exchangers and separate
tube-in-tube, spiral and water bath heat exchangers. In a combined boiler/heat
exchanger, the boiler heats a water bath in which tubes carrying sludge pass. Tube-intube heat exchangers consist of two concentric pipes, one carrying sludge and one
carrying hot water. The liquids flow in opposite directions. Spiral tubes have pairs of
passages wrapped to form spirals. One passage carries sludge; the other passage
carries water flowing in the opposite direction. In water-bath heat exchangers, sludge
pipes pass through a heated water bath.
Waste heat from the cogeneration system is typically reclaimed in the form of hot
water and circulated through a heat exchanger to provide heat for the digesters. In
the event that the cogeneration system is not operating or does not produce enough
waste heat, a boiler utilizing biogas or natural gas may be utilized.
For the LAWPCA facility, an external, tube in tube heat exchanger system is
recommended, as tube in tube heat exchangers are typically more efficient than other
types of heat exchangers. For the Option 1 location and layout, the boiler and two
heat exchangers (one operating per digester) are located on the first floor of the
digester equipment building. For Option 2, which utilizes existing space in the
Process Building for digester equipment, the boiler and heat exchangers are located in
the space that is currently being used to haul away influent screenings.
4-9
Section 4
Anaerobic Digestion and Sludge Storage Improvements
equipment. In each system, biogas is taken from the headspace of the digester tank,
compressed, and distributed to multiple mixing devices.
Draft Tube Mixing
Mechanical draft tube mixing systems consist of a propeller, drive shaft, and drive.
Most mechanical mixing systems are mounted in a draft tube to direct sludge flow
within the digester. Drives are typically reversible, allowing the sludge to discharge
at the top or bottom of the draft tube. Mixer/draft tube assemblies may be located at
the center of the digester tank, at the mid-radius point, or outside the digester tank.
Mixing System Recommendation
A pump recirculation mixing system is recommended for LAWPCA based primarily
on operation and maintenance considerations. With these systems, pumps are located
inside a building along with other equipment and are easily accessed. In addition,
plant operators are generally familiar with maintaining pumps of this nature and find
them more operator friendly. In comparison, mechanical draft tube motors are
located on top of the digester tanks creating a difficult maintenance environment
especially during winter conditions. In addition, due to the inability to grind the
recirculation flow with a draft tube mixer, rags and other fibrous materials could tend
to accumulate within the digesters and create a maintenance concern. Further, due to
the configuration of draft tube mixers, a crane would be required for any significant
maintenance procedures. Gas mixing systems were removed from consideration due
to cost and the historical maintenance concerns associated with the biogas compressor
systems and general safety concerns associated with biogas handing.
It should also be noted that a mixing system will also be required for the sludge
storage tank discussed in Section 4.2. The piping and jets associated with the digester
tank and sludge storage tank mixing systems are shown in Figure 4-1 and Figure 4-2,
respectively. The locations of the pumps under the two alternative layout options
will be discussed later in this section.
4-10
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Fixed Covers
Fixed concrete and steel covers are also widely used throughout the wastewater
industry. They have historically been the option with the lowest cost and least
potential for operation and maintenance problems in comparison to floating covers.
However, fixed covers offer minimal biogas storage and limited flexibility with
regard to sludge liquid level. One variation on the fixed concrete cover design is the
submerged fixed cover (SFC). Compared to flat fixed cover designs, the submerged
fixed cover is effective at utilizing the upper portion of the tank volume by inhibiting
the buildup of floating foam and scum and directs mixing energy for better efficiency.
SFCs are similar in costs to flat roof digesters and less costly to construct than domed
roofs. The key to the submerged fixed cover digester is a sloped roof that leads to a
centrally located gas dome. In a SFC design, the liquid level is allowed to rise into the
gas dome above the side wall, submerging the underside of the cover. Submerging
the cover provides a gradual transition at the cover side wall connection, directing
mixing patterns more effectively. Operating the liquid level in the gas dome
minimizes the gas to liquid interface. By minimizing this interface, foam and scum
can be removed more effectively. With minimal gas storage volume, a fixed cover
system must either rely on storage spheres, piping, flares, vacuum and pressure relief
valves, or some other means of gas storage to keep the pressures consistent inside the
tank.
Gas Membrane Covers
Gas membrane covers are a relatively new product that was first used in the U.S. in
the early 1990s. They provide a large volume of digester gas storage using a doublemembrane design and may be installed on digester tanks or sludge storage tanks. The
outer membrane maintains a consistent dome shape, while the inner membrane
moves up or down depending upon gas storage requirements. Ambient air fans and
valves add or release air from the space between the inner and outer membranes to
maintain the consistent outer membrane shape and constant biogas pressure. This
also allows for substantial changes in the depth of sludge in the digester.
Cover Recommendation
SFCs are recommended for the digesters at LAWPA facility based on the following
considerations:
Fixed covers tend to be less costly than floating covers or gas holder membranes.
SFC minimize foaming, which is often expensive and difficult to control and
contain.
The digester tank configuration shown in Figure 4-1 depicts the general arrangement
of the recommended SFC.
It is further recommended that the digested sludge storage tank, as discussed in
Section 4.2 and shown in Figure 4-2, be installed with a gas membrane cover to store
4-11
Section 4
Anaerobic Digestion and Sludge Storage Improvements
excess biogas before it is used in cogeneration. Biogas storage and use will be further
discussed in Section 5.
4-12
Section 4
Anaerobic Digestion and Sludge Storage Improvements
the multiple pipes and conduits which would be required between the existing
process building and new sludge pumping area, a pipe tunnel has been provided
under this option between the new space and the existing process tunnel. The
existing piping connecting to TWAS tank No. 4 in the area of the proposed tunnel
would need to be relocated as part of this work.
As shown on Figure 4-4, this option does require a substantial retrofit of the existing
screenings area. The existing wall between the intake screening area and the existing
screenings garage would be relocated to the east while the existing bathroom, laundry
rooms and associated hallway would be removed to allow room for the new
equipment. In addition, to facilitate screenings removal, a new screenings handling
system (new wash presses and conveyor system) along with a new screenings garage
at the east end of the process building would be required. At the request of
LAWPCA, this alternative has also included the complete replacement of the existing
intake screens with new multi-rake style screens.
Due to the site constraints inherent with Layout Option 2 which are apparent in
Figure 1-3, the 65-ft diameter, less costly, standard tank was not a viable option. As a
result, the layout of this option has utilized the taller 50-ft diameter tanks that would
be installed as shown along with the 50-ft digested sludge/biogas storage tank.
Digester tanks:
9 Layout Option 1 Separate Facility. Standard Tanks two, 65 foot diameter
concrete tanks with insulation; SWD of each tank is 30.5 feet
9 Layout Option 2 Retrofit. Cylinder Tanks two, 50 foot diameter concrete
tanks with insulation; SWD of each tank is 52 feet
Digester feed Utilize existing TWAS storage tanks to continuously feed TWAS to
digester system. Pump thickened primary sludge from gravity thickeners to
digesters continuously.
Digester Heating External heat exchangers. Typically, waste heat from the
cogeneration system provides hot water. In the event that the cogeneration system
is not operating or not producing enough heat to meet the digester heat needs, a
boiler utilizing biogas or natural gas may be used.
4-13
Section 4
Anaerobic Digestion and Sludge Storage Improvements
Digested Sludge Storage One 50-foot diameter by 15-foot deep tank to store
digested sludge prior to dewatering and new belt filter press feed pumps.
4-14
Section 5
Biogas Handling and Cogeneration
5.1 General
Gas generated by the anaerobic digestion of organic solids is often referred to as
biogas. This gas contains primarily methane and carbon dioxide and is an excellent
source of energy. The energy can be harnessed in a variety of ways, including boilers
for digester and building heating, and reciprocating engines and microturbines for
electricity production.
Volatile solids comprise 75% of the total dry solids fed to the digesters.
Volatile solids destruction in digester of 55% (average) and 50% (maximum month).
Digester gas production typically ranges from 1218 cubic feet per pound of
volatiles destroyed. For the purpose of the conceptual design, a value of 15 cubic
feet per pound of volatile solids destroyed is used.
Heating value of digester biogas typically ranges from 500 to 650 BTU/cubic foot.
To be conservative for the purpose of this conceptual design, a value of 550
BTU/cubic foot is used.
A
5816-72780
5-1
Section 5
Biogas Handling and Cogeneration
and/or building heating. In cold climates, the amount of heat reclaimed from the
cogeneration system is not enough to meet the heat needs of the digester and a
supplemental boiler is required.
Average Day
Max Month
27,300
43,100
20,500
32,300
6,800
10,800
11,300
16,100
170,000
242,000
93
133
3.88
5.54
Table 5-1
Biogas Production Rates and Energy Value of Biogas
From the Anaerobic Digestion/Energy Recovery Feasibility study, reciprocating
engines were the recommended technology for cogeneration. Engines were
recommended due to their high electrical efficiency, number of successful operating
installations, and lower capital and installation costs relative to other cogeneration
systems.
Reciprocating internal combustion engines are a widespread and established
technology. Reciprocating engines are available for power generation applications in
sizes ranging from a 70 kW to over 5 MW. Reciprocating engine technology has
improved over the past few decades, driven by economics, environmental
regulations, increased fuel efficiency and reduced emissions.
5-2
Section 5
Biogas Handling and Cogeneration
Average Daily
Biogas Produced
(MMBTU/hr)
Rated
Energy Input
Per Engine
(MMBTU/hr)
Number of
Units
Net
Electrical
Output
(Output
Parasitic
Load) (kW
Recoverable Heat
from Units
(MMBTU/hr)
374
2.01
384
1.97
399
1.95
140 kW
3.88
1.38
3 at 94% load
220 kW
3.88
2.11
2 at 92% load
280 kW
3.88
2.60
2 at 75% load
Table 5-2
Utilizing Biogas in Engine Application
Based on average daily flow, there is enough biogas produced to operate three
140-kW engines at 94% load, two 220-kW engines at 92% load, or two 270-kW engines
operating at 75% load.
The heating needs of the digester system versus the amount heat provided by the
engine system are summarized in Table 5-3. Based on this evaluation all three engine
systems produce enough recoverable heat to heat the digesters year-round at average
day conditions.
Average Day
Winter
Summer
1.74
0.68
2.01
2.01
1.97
1.97
1.95
1.95
Table 5-3
Digester and Facility Heating Needs vs. Heat from Engine
5-3
Section 5
Biogas Handling and Cogeneration
Section 5
Biogas Handling and Cogeneration
burner safely flares excess biogas to the atmosphere and eliminates the potential for
hazardous accumulation of biogas within the conveyance and storage system. For
safety considerations a minimum of 50 feet is required between the waste gas burner
and the digester tanks.
See Figure 5-1 for the proposed layout of the gas safety and handling equipment.
5-5
Section 5
Biogas Handling and Cogeneration
tank will store sludge prior to dewatering in the existing belt filter presses. This
storage tank may be fitted with a double membrane gas membrane holder cover
(described in Section 4.5.3) fixed to the top of the tank, allowing for several hours of
biogas storage. The outer membrane maintains a consistent dome shape, while the
inner membrane moves up or down depending upon gas storage requirements.
Ambient air fans and valves add or release air from the space between the inner and
outer membranes to maintain the consistent outer membrane shape and constant
biogas pressure.
5-6
Section 5
Biogas Handling and Cogeneration
combusted, siloxanes are converted to silicon dioxide (SiO2), which is then deposited
in the combustion or exhaust stages of the equipment.
In reciprocating engines, evidence of siloxanes is found in the form of white powder
deposited on combustion surfaces. In boilers, siloxanes are often deposited in the fire
tubes of boilers utilizing biogas.
The most commonly used method to reduce siloxane levels is carbon adsorption of
the siloxane compounds. In these systems, biogas flows through vessels filled with a
carbon based media.
5.7 Summary
The recommended systems to handle and utilize the biogas at the LAWPCA include
the following components:
Biogas Conveyance and Storage: biogas safety equipment (flame trap, waste gas
burner), moisture and sediment removal, biogas metering, biogas storage in
digested sludge storage tank with gas membrane cover;
5-7
Section 5
Biogas Handling and Cogeneration
5-8
Section 6
Architectural and Structural Considerations
This section presents the major existing architectural and structural features of the
proposed digestion facilities to be installed at the LAWPCA wastewater treatment
plant.
In addition, with P.L. 2007 Resolve 46, the Legislature recognized that Maine needs
more uniformity of building-related codes across the state. It directed the state to
develop a building and building rehabilitation code implementation plan. A
committee comprised of the departments of Economic and Community Development
and Professional and Financial Regulation, the Fire Marshals Office, Maine Historic
Preservation Commission, and State Planning Office presented their
recommendations report and implementation plan to the Business Research and
Economic Development (BRED) Committee on January 31, 2008. The BRED
Committee accepted the committees recommendations and enacted PL 2007, Chapter
699. On January 1, 2010, Maine will have a new statewide building and energy code.
A new board will streamline code administration and a uniform code will bring more
consistency to builders, developers, and towns. The final design will comply with the
provisions of this new statewide building and energy code.
A
5816-72780
6-1
Section 6
Architectural and Structural Considerations
6.2
Architectural Considerations
Existing Process Building There will be a New Gravity Belt Thickener Room
with an area of approximately 2,084 sq. ft., comprised of two zones open into each
other and without any interruptions: one measuring approximately 45'-9"x 36'-8"
and the other measuring approximately 14'-7" x 28'-0". The Room will be accessed
from the corridor through an air-lock vestibule with an area of 106 square feet and
through two sets of double doors equipped with pressure gaskets. The walls will
be 2-hr rated and five vision panels equipped with rated safety glass will also be
provided. Additionally, a New Electrical Room with an area of 356 square feet
will be provided with approximate dimensions of 45'-9" x 7'-10". The New
Electrical Room will be provided with an independent set of 90-min. rated double
doors. The two new rooms will be adjacent to each other and separated by a
2-hour rated 6-inch CMU wall and communicating through a 90-min. rated single
door.
Tanks There will be two new cast-in-place digester tanks with a 65-foot interior
diameter; provisions for the expansion to a future cast-inplace digester tank with
the same dimensions as the new proposed ones are also being made; additionally
there will be a cast-in-place sludge & gas holding tank with a 50-foot interior
diameter.
Tank Locations The four tanks are placed with their centers, each located on
one of four vertices of an imaginary square with a side measuring approximately
94 feet. The new digesters are located respectively on the West and South vertices,
the future digester on the North vertex and the storage/gas holding tank on the
East vertex of the square. Please refer to paragraph 6.3.9 for additional facility
specific structural design considerations.
New Digestion Building The building will have a square footprint with the
sides measuring approximately 45 feet, and located in the center amongst all three
proposed and one future tank. The building is oriented in such a way so that its
vertices are diagonally oriented in relation to the imaginary square whose vertices
are occupied by the centers of the tanks. The building vertices will be located
respectively at the North-South/West, and at the North-South East. The building
will have two levels. The lower level will be entirely occupied by a Sludge Pump
Room and by an enclosed Stairwell leading to the exterior through the upper level
at grade. The upper level will be occupied by the Boiler/Heat Exchanger Room,
6-2
Section 6
Architectural and Structural Considerations
by the Electrical Room with its independent entrance opening directly to the
exterior, and by the enclosed Stairwell leading to the exterior.
New Gas Safety Equipment Building The small approximately 12' x 20'
enclosed structure will primarily house gas safety equipment. It will be
constructed with reinforced 8-inch CMU and with a precast concrete hollow core
planks and provided with an access door.
Existing Process Building Refer to Option 1 at paragraph 6.2.1 above plus the
following additional changes:
a. New Boiler/Heat Exchanger Room The new room with an area of
approximately 1,516 square feet will be located in an area currently occupied
by the screening garage and by a portion of the headworks area. It will be
separated by 2-hr rated 8-inch reinforced CMU wall. One door will be used to
egress the room to the exterior.
b. New Headworks The new space will have an area of approximately 1,085
square feet, therefore reduced from the current size, and it will be separated
from the adjacent Boiler/Heat Exchanger Room by the new 2-hr rated
reinforced 8-inch CMU wall. The existing exterior door will have to be
relocated to the south to accommodate a new dumpster garage on the East
side.
c. New Screening Dumpster Garage The garage, with an approximate size of
16'-0"x 20'-0", will be structured with a separate frame of cast-in-place concrete
columns and beams and with reinforced 8-inch CMU infill walls. The roof will
be structured with precast concrete hollow core planks. The dumpster can be
6-3
Section 6
Architectural and Structural Considerations
Tanks There will be two new cast-in-place digester tanks with a 50-foot interior
diameter, and one cast-in-place sludge and gas holding tank with a 50-foot
interior diameter.
New Sub-grade Sludge Pump Room and Tunnel The new Pump room will be
entirely below grade between the two digester tanks, with an approximate area of
1,656 square feet. The sides of the room flanking the two digesters will have an
additional segmented separation wall to follow the curvature of the digesters and
it will be built with reinforced 8-inch CMU. A cast-in-place concrete tunnel will
connect this room to the existing building below grade and a cast-in-place
concrete egress stair will lead off the tunnel to the exterior above grade.
6-4
Section 6
Architectural and Structural Considerations
equipment, but much more critical to the installation of the new Gravity Thickeners,
and it is the temporary removal of the existing window system to allow the
installation of the Thickeners and re-installation of the same in place. This additional
consideration has been made with the assumption that the existing window system
can be, indeed, temporarily removed and reinstalled. During final design,
replacement of this with a new window or with a fully insulated wall should be
considered. A hazardous materials assessment survey will be required in the existing
buildings to determine the location and approximate quantities of hazardous
materials that are or might be present in areas subject to modifications.
6-5
Section 6
Architectural and Structural Considerations
thickness necessary to meet energy code requirements (New Digestion Building only
in Option 1) and to provide drainage slopes.
6.2.6.1 Floors
6.2.6.2 Walls
6.2.6.3 Ceilings
Exterior Stainless Steel for long life, ease of maintenance and durability.
6-6
Section 6
Architectural and Structural Considerations
CRSI Handbook
50 psf
125 psf
100 psf
100 psf
30 psf
Roofs
20 psf
Storage areas
250 psf
Catwalks
100 psf
100 psf
Office areas
150 psf
150 psf
150 psf
150 psf
6-7
Section 6
Architectural and Structural Considerations
Storage areas
300 psf
200 psf
Electrical rooms
300 psf
Control rooms
150 psf
Maintenance garages
Unrestricted vehicular areas
Equipment Loads
Loads from equipment will be considered live loads. The maximum loads and
support details for each major piece of equipment will be provided by the
discipline designing or specifying it. Final weights of process-mechanical
equipment will be established during preliminary design. Preliminary weights of
building service equipment (HVAC, plumbing, and electrical) will be confirmed
during final design.
In addition to the mechanisms static dead load, design will be performed for
other effects, such as those due to operation, maintenance and malfunction.
Examples include, but are not limited to, the following.
9 Rotating agitator equipment (mixers, flocculators, and mechanical aerators)
Design will be performed for moment, torque, and lateral/vertical thrust.
9 Rotating clarifier mechanisms Design will be performed for stalling torque.
9 Vertical turbine pumps Design will be performed for suction load plus the
weight of the suspended water column in the riser.
9 Sluice gates, non-self-contained Design will be performed for a load equal
to the breaking strength of the operating stem, or the stalling torque of the
motorized operator, in the event the gate is frozen.
9 All equipment Design will be performed for required maintenance
procedures, such as the removal of a large component and the placing of it
temporarily on the adjacent structure.
Impact Loads
Static loads will be increased for the effects of impact by the following
percentages:
6-8
Section 6
Architectural and Structural Considerations
load, and 10 percent of the sum of the hoist capacity and total crane weight
will be applied as a longitudinal load.
9 Monorail supports 25 percent of hoist capacity. 10 percent of the sum of the
hoist capacity and hoist weight will be applied as a longitudinal load.
9 Light machinery supports, shaft or motor driven 20 percent of the operating
weight (minimum) or manufacturer's recommendation.
9 Reciprocating machinery or power-driven unit supports 50 percent of the
operating weight (minimum) or manufacturer's recommendation.
9 Hangers supporting floors or balconies 33 percent of live load reaction
Construction Live Loads
When it is necessary to provide particular restrictions on construction sequencing,
special load conditions may result. This is particularly applicable to work involving
the modification of existing structures. These cases will be evaluated and appropriate
criteria established during final design. Such restrictions will be indicated in the
drawings or specifications.
70 psf
Establish for each structure per governing code
based on occupancy
Roofs will be designed for retained water to its maximum depth (accounting for
deflection) assuming that the primary drainage system is blocked. Overflow scuppers
or other secondary drainage systems may be used to minimize this load. This
criterion will be coordinated with architectural and plumbing disciplines.
Wind Loads
Wind loads will be developed from the following criteria in accordance with the
governing code. Appropriate shape modification factors, uneven distributions, and
orthogonal effects will be considered for each structure. Main wind force resisting
systems, as well as appropriate components and cladding, will be designed for
internal and external effects. Increased allowable stresses or reduced load factors will
be used, as appropriate.
6-9
Section 6
Architectural and Structural Considerations
0.323
0.080
Loads on the seismic resisting system will be developed in accordance with the
governing code for the particular system. The Site Class will be used as
recommended in the geotechnical report. Loads from mechanical and architectural
components not covered by the governing code will be developed in accordance with
IBC.
6-10
Section 6
Architectural and Structural Considerations
will be designed for a 12-inch minimum water level differential, unless hydraulic
analyses indicate a different level.
Closed liquid containing structures will, whenever possible, be vented to preclude
pressurization or depressurization. However, certain structures may experience
pressure or vacuum effects due to particular mechanical or process systems, or the
malfunction of systems or components. In such cases, design will be performed for
the maximum water, air or gas pressure as provided by the mechanical-process
discipline in preliminary design.
6-11
Section 6
Architectural and Structural Considerations
for groundwater at the flood elevation for increased allowable stresses or reduced
load factors, as appropriate.
Lateral Soil and Groundwater Pressures
The following equivalent fluid pressures will be used in preliminary design for wellgraded, granular, mineral soils with a moist unit weight of 120 pcf. Soil pressures for
final design will be developed in accordance with the geotechnical report. Design for
cantilevered walls of environmental engineering structures will be performed for atrest soil pressures.
Pressure
Condition
Pressure
Coefficient
Below Groundwater
At Rest (minimum)
0.50
60 pcf
90 pcf
Active (minimum)
0.33
40 pcf
80 pcf
Passive (maximum)
3.00
360 pcf
170 pcf
Combination of certain loads will not be considered when the probability of their
simultaneous occurrence is negligible. Such loads include wind and seismic on
superstructures; and seismic, live load surcharge, and flood on substructures.
6-12
Section 6
Architectural and Structural Considerations
The effects of any load type (other than dead load) will not be used to reduce the
effects of another load type. A maximum of 90 percent of the dead load will be
used in any combination where it reduces the effects of another load type.
6.3.2 Serviceability
Additional requirements for serviceability will be considered as provided in
subsequent sections and referenced standards for specific materials.
6.3.2.1 Deflection
Design will be performed to limit deflections to the following. In cases indicated with
an asterisk (*), deflection limit will apply to live load effects only. For monorails and
cranes, impact need not be included.
Monorails, including the effects of differential support deflection
L/450
L/1000
L/360
L/240
L/360
L/360
Floors, concrete
6.3.2.2 Ponding
Ponding refers to water retention due to the effects of deflection on a flat roof. For
flexible roof systems, sufficient stiffness will be provided to prevent successive water
retention and deflection leading to failure.
6-13
Section 6
Architectural and Structural Considerations
6.3.2.3 Vibration
Design will be performed for the effects of vibration to provide appropriate protection
against structural deterioration, mechanical deterioration, and significant occupant
discomfort. Under normal circumstances, the guidelines below will generally be
followed. If deemed necessary by the supervising structural personnel, a dynamic
analysis of the system will be performed.
Mechanical Vibration
Concern for mechanical vibration is greatest for equipment such as blowers,
generators, compressors, steady bearings at pump shafts and centrifuges. Operating
frequencies, unbalanced loads, and specific design recommendations will be obtained
from the manufacturer by the discipline specifying the equipment.
To avoid resonant vibration, the ratio of the structures natural frequency to the
operating frequency of the equipment will be restricted to less than 0.50 or greater
than 1.50. Where practical, the latter will be used to avoid resonance during
equipment startup and shutdown. Consideration will be given to applicable modes
of vibration, including vertical, lateral, and rotational.
Design will be performed in accordance with the following guidelines for equipment
which produce significant vibrational effects, where possible and appropriate.
A foundation mat will be provided with a mass equal to ten times the rotating
mass of the equipment or three times the gross mass of the equipment (minimum),
whichever is greater.
Transient Vibration
For elevated steel walkways or platforms, beams will be provided with a depth
greater than or equal to 1/20 of the span.
6-14
Section 6
Architectural and Structural Considerations
2.0
Sliding:
1.5
For design of retaining walls with portions below the design groundwater level, the
effects of uplift pressures will be considered in stability analyses.
6-15
Section 6
Architectural and Structural Considerations
6.3.3.5 Buoyancy
Buoyancy is defined as the condition of instability resulting when uplift forces due to
groundwater exceed resisting forces due to dead load and anchorage systems. Design
will be performed in accordance with the following.
Complete Structures
For groundwater at the design level, structures will be designed to resist buoyancy
considering only the structure dead load, soil directly above the structure and footing
extensions. The effects of live loads, liquid contents (unless relief valves are used),
vertical soil friction and soil cohesion will be neglected. When anchorage systems are
used, they will be designed to resist the net uplift force transmitted to the components
of the anchorage. Structures will be designed to provide a minimum factor of safety
of 1.15, calculated as the ratio of total resisting force to total buoyant force.
Partially Complete Structures
Since the contractor will normally be required to maintain a dewatered excavation, it
will be assumed that groundwater will be maintained, at any given time, at or below
the surface of the backfill currently in place. If the completed portion of the structure
has insufficient resistance against pressures generated in this condition, the
groundwater elevations at which the structure is stable will be provided in the
contract documents.
Buoyancy Prevention Systems
Pressure relief valves will usually be wall-mounted valves, designed to allow
groundwater to enter a liquid-containing cell when the groundwater pressure exceeds
the interior liquid pressure. Where possible, they will be installed at an elevation
above normal groundwater level to allow dewatering of the cell under most normal
conditions. The valves will normally be connected to an underdrain system, as
described below, to relieve pressure build-up at locations remote from the valves.
Where appropriate, design buoyant pressures will be reduced using an underdrain
system beneath the structure. The system will consist of a network of perforated
underdrain pipes, connected installed in a continuous layer of crushed stone. Filter
fabric will be provided between the crushed stone and surrounding soil to prevent
migration of fines into the stone voids.
6-16
Section 6
Architectural and Structural Considerations
Precast site structures, including manholes, vaults, pipe, culverts, and headwalls
ACI 318
ACI 350
AWS D1.4
Structures that convey, store or treat liquid, are subjected to severe exposures, or have
restrictive leakage requirements will be designed as environmental engineering
structures.
Design of miscellaneous roadway structures, such as culverts and headwalls will be
performed in accordance with the state highway standards and the AASHTO
Specification.
4,000 psi
Concrete topping:
4,000 psi
Precast concrete:
5,000 psi
Prestressed concrete:
5,000 psi
Design will be performed for the strengths and properties of the following materials.
ASTM A706
ASTM A185
ASTM A497
6-17
Section 6
Architectural and Structural Considerations
ASTM C126
Grout
6-18
Section 6
Architectural and Structural Considerations
Reinforcement:
Deformed Bars
Joint Reinforcing
ASTM A82
1500 psi
6.3.6.3 Veneer
Non-structural masonry veneers will be selected, detailed and specified by the
architectural discipline. The structural adequacy of veneer attachments and the
weights used in dead load calculations will be verified.
6-19
Section 6
Architectural and Structural Considerations
Access hatches
SJI Specification
SDI Manual
Aluminum:
Stainless steel:
AISI
Welding, steel:
AWS D1.1
6-20
Section 6
Architectural and Structural Considerations
Welding, aluminum:
AWS D1.2
AWS D1.6
ASTM A 992
ASTM A 36
ASTM A53
ASTM A 325-SC
ASTM A 307
Welding electrodes:
AWS E70XX
Aluminum:
Aluminum extruded shapes:
Stainless Steel:
Stainless steel shapes:
6-21
Section 6
Architectural and Structural Considerations
Steel Deck
Deck sizes, profiles and connections will be selected from load tables in the referenced
standards.
Joists and Joist Girders
Sizes will be selected from load tables in the referenced standards. Design loads will
be provided in the contract documents. For loads other than uniform loads, a load
diagram will be provided.
Gratings
Sizes of metal gratings will be selected in accordance with the manufacturers load
tables for uniform loads and limited concentrated loads defined in the tables. For
other loads, design will be performed in accordance with ASD methods specified in
the appropriate material standards.
6-22
Section 6
Architectural and Structural Considerations
Option 2
Two new digesters, approximately 50 feet in diameter, with a sidewater depth of
approximately 52 feet, will be provided. The digesters will be constructed out of castin-place reinforced concrete, and they will be pile-supported. The base slab of the
digester will slope (at approximately 1V:6H) to a low point in the center of the
digester. A fixed cast-in-place concrete cover will be provided at the top of the
digester. Finished grade will be approximately 20 feet above the base mat high point.
6-23
Section 6
Architectural and Structural Considerations
6-24
Section 6
Architectural and Structural Considerations
6-25
Section 7
Electrical and Instrumentation Functions
This section describes the support functions and facilities including the sites electrical
distribution system. This section summarizes existing conditions, recommended
upgrades and improvements to these support functions.
7.1.2.1
Utility Service
Electrical service to the LAWPCA facility is provided by Central Maine Power Co.
(CMP). A 12kV primary feeder runs overhead along Lincoln Street to a service riser
pole located on the Northeast side of the Administration Building. The primary feeder
extends underground from this location to three utility-owned 500 kVA single phase
transformers located in an enclosed area on the South side of the Administration
Building.
The transformers are configured to provide 1500 kVA with a secondary voltage of
480/277V, 3-phase, 4-wire, 60Hz. The secondary conductors are run underground
from the transformers to a LAWPCA-owned 2000-amp switchboard located in the
Main Electrical Room. The CMP service has secondary meters on the 480V conductors
in the main switchboard.
A
5816-72780
7-1
Section 7
Electrical and Instrumentation Functions
7.1.2.2
The existing electrical distribution system at the WWTP has remained essentially
intact over the last 40 years since the original construction contract in 1970 with
upgrades as necessary to support upgraded process equipment.
As shown in Figure 7-1, the distribution system extends from the existing 480V main
switchboard to local motor control centers (MCC) located in various process areas
throughout the plant to serve the plant process and mechanical loads. The MCCs and
process loads are fed from a single bus in the 480V switchboard. This arrangement
does not meet the EPA Class II reliability requirements for the Anaerobic
Digestion/Energy Recovery project.
7.1.3.2
Conditions
7.1.3.3
There are several points within the electrical distribution system that are susceptible
to common mode failures. Common mode failure is a point within the electrical
distribution system where a single failure results in the complete loss of critical
processes or pumping systems.
Areas of vulnerability are summarized below:
7-2
The 480V switchboard located in the main electrical room is approaching 40 years
old. The switchboard contains an automatic transfer switch without a bypass
mechanism. A failure or fault on the transfer switch would render the entire
Section 7
Electrical and Instrumentation Functions
facility inoperable. Additionally the standby generator is located within the same
room as the switchboard. A failure resulting in significant damage (e.g., fire) to
the generator could be fatal to the switchboard. Again resulting in loss of
operability to the aforementioned equipment regardless of commercial power
availability.
The main switchboard supplies power to MCC-3 located in the Pump Room. A
single failure or fault on the MCC bus would render the plants influent pumping
capabilities inoperable.
The switchboard also supplies power to the balance of the MCCs located in
various process areas throughout the plant. A single failure or fault on any MCC
bus would render that area of the plant inoperable, including the Pump & Pipe
Gallery, Control Building, and the Solids Processing Area.
It is desirable to have the electrical equipment especially solid state electronics such
as variable frequency drives installed inside climate controlled rooms due to heat
dissipation and the environment surrounding the facility. Therefore, the Sludge
Thickening Room and Digester Building are recommended to have dedicated
electrical rooms. Refer to Figure 7-2 for the proposed electrical one-line diagrams for
these areas.
7-3
Section 7
Electrical and Instrumentation Functions
Life safety systems will be designed in accordance with all applicable codes. In
general life safety systems will consist of emergency egress lighting, fire alarm, and
combustible gas/ventilation failure alarm systems. The existing fire alarm system
will be extended as necessary in accordance with NFPA 72. Emergency egress
lighting will be provided in accordance with NFPA 101 and the Maine Uniform
Building and Energy Code to maintain required illumination of all emergency egress
paths affected by the upgraded facilities. Emergency lighting shall also be provided
near all new equipment (e.g., MCC, Switchboard, Generators, etc.) that need to be
accessed to restore normal power. Additional emergency lighting can be provided in
process critical areas as defined by the process engineers and directed by the owner.
The combustible gas detection and ventilation failure alarm systems shall be installed
in accordance with NFPA 820. It is important to note that the new cogen generators
installed at this facility will be suitable for stand-by power only and shall not be
considered to be life safety or emergency equipment.
Electrical conduits and underground raceway systems will be installed to
accommodate and support SCADA system modifications as necessary.
New conduit and wiring associated with the Task I process equipment referenced
above, including variable frequency drives specified for the Thickened WAS
pumps.
New lighting and small power systems will be installed in the upgraded process
areas and new electrical room.
7-4
Section 7
Electrical and Instrumentation Functions
7.1.4.3
Anaerobic Digester Option 1 includes a new Digester Building located between the
digester tanks. Under this option, a new motor control center (MCC-6) will be housed
in an electrical Room located on the buildings Upper Level with exterior access to
isolate the electrical equipment from the process areas. MCC-6 will serve the sludge
recirculation pumps, mixing pumps for the digesters and sludge storage tank, belt
filter press feed pumps, boiler, hot water pumps and HVAC equipment as shown in
Figure 7-2.
The Anaerobic Digester phase of this project includes a component for energy
recovery and cogeneration. As such, the incoming service requires modification as
referenced in Paragraph 7.1.4.5 to include a new 480 Volt Switchgear in an outdoor,
NEMA 3R, enclosure. Modifications to the existing electrical service to accommodate
the new switchgear are required under both Option 1 and Option 2.
Electrical work under this option includes:
New feeders via underground raceways from the new 480 Volt outdoor
switchgear to MCC-6 in the Digester Building Electrical Room.
Conduit and wiring associated with the process and HVAC equipment referenced
above to serve the new Anaerobic Digesters.
Conduit and wiring associated with lighting, small power and support systems
will be installed in the Digester Building.
Conduit and wiring for instrumentation and control, combustible gas detection,
ventilation failure alarm and fire alarm systems.
7.1.4.4
Anaerobic Digester Option 2 makes provisions for installing new process equipment
in the existing Screenings garage, as shown on Figure 4-4, and includes modifications
to the Screenings area. Under this option, a new motor control center (MCC-6) will be
housed in the Sludge Thickening Electrical Room referenced in Paragraph 6.1.4.4
above. New MCC-6 will serve the new digester recirculation pumps, digester and
storage tank mixing pumps, belt filter press feed pumps, boiler, hot water pumps and
HVAC equipment as shown in Figure 7-2.
Electrical work under this option includes:
New feeders via underground and overhead raceways from the new 480 Volt
outdoor switchgear to MCC-6 in the Sludge Thickening Electrical Room.
New conduit and wiring associated with the process and HVAC equipment
referenced above to serve the new Anaerobic Digesters.
7-5
Section 7
Electrical and Instrumentation Functions
7.1.4.5
7.1.4.6
Consistent with the double-ended (i.e., two electrical buses configured in a main-tiemain configuration) configuration of the main switchgear, the downstream feeders to
each new double-ended motor control centers shall be derived from the A and B
7-6
Section 7
Electrical and Instrumentation Functions
Busses of the main switchgear respectively. The cables shall be sized to accommodate
the full demand load of a motor control center series (e.g., MCC-6A and 6B) under a
single ended condition.
7.2
7.2.1 General
This section establishes general concepts and the criteria necessary for the design
requirements of the proposed digestion and Cogen Control Panels and associated
Programmable Logic Controllers (PLCs) into the plant-wide Supervisory Control and
Data Acquisition (SCADA) system. The modified SCADA system will allow
monitoring and control of the newly installed systems to be operated from the
existing control room in the Administration Building from a pair of redundant
SCADA Nodes.
7.2.2 Objectives
The goal of the instrumentation and control system is to provide effective monitoring
and control of the system processes and associated plant equipment. The system will
provide operations and maintenance as well as management the information
necessary to operate the thickening and Cogen systems in an efficient and effective
manner. The system will be flexible and easy for plant personnel to use.
7-7
FDS:
Ventilation Failure
VF:
ACH:
CGD:
N/A
N/A
Unclassified
Unclassified
Class I, Division 1
Class I, Division 1
Unclassified
Unclassified
Class I, Division 2
Class I, Division 1
NReq
NReq
CGD
CGD
NReq
NReq
CGD
NReq
Gas
Detection/
Ventilation
Failure
N6
N5
N4
N3
N7
N1
Notes
Table 7-1
LAWPCA Facility Area Classification Summary
N1: Space hazardous classification extends 10 ft. above the highest point of the cover and 5 ft. from any wall.
N2: Space hazardous classification has been reduced with continuous ventilation rate as indicated and physical separation from the digesters.
Ventilation system monitoring is required.
N3: This space is not being declassified with ventilation. Equipment shall be rated for hazardous classification indicated.
N4: The corridors and space outside the New Sludge Thickening Room is classified Class 1, Div. 1 due to open access to the Influent Wetwell
and Screenings Room.
N5: Fire alarm system is required.
N6: The Electrical Room opens into the Sludge Thickening Room and the Loading dock, Ventilation rates are not set by NFPA 820.
N7: The upper level of the Digester Building is physically separated from the sludge pumping area below and is therefore unclassified.
N/A
N/A
Design Ventilation
Code Reference
Anerobic Digesters
Area
Elec.
Classification
Section 7
Electrical and Instrumentation Functions
Section 7
Electrical and Instrumentation Functions
Cogeneration Engines;
In this work, CDM will interface the Digestion and Cogen System with the plants
existing Belt Filter Press System in either a hardwired or networked configuration for
monitoring and control by SCADA.
7-9
Section 7
Electrical and Instrumentation Functions
7.2.3.1
Field Instrumentation
Field instruments that are no longer working should be replaced with new
instruments that will properly measure the process and are easy to maintain;
7.2.3.2
The Plants existing SCADA system will be modified to communicate with the Sludge
Thickening and Cogen Systems Control Panels and other vendor system control
panels that provide both automatic and manual control for each system. Each control
panel will incorporate a PLC that will monitor digester levels, digester gas pressure
and flow, thickened waste activated sludge (TWAS) tank levels, pumping equipment
status, heat exchange systems, boiler status, generator engine status, and other
process variables automatically to pre-set operator set points. The PLCs will be able
to start and stop equipment and monitor the status of that equipment based upon
control interlocks or operator intervention.
The PLCs will be located in NEMA-rated panels as required per the area
environmental requirements. Each PLC will consist of an Allen-Bradley SLC 5/05
central processing unit (CPU) equipped with the necessary communication modules,
input/output (I/O) modules and power supplies.
7-10
Section 7
Electrical and Instrumentation Functions
OITs will be provided in for both the Thickening and Cogen Control Panels as a
means of controlling the system independently from SCADA in the event the SCADA
System goes down. The new OITs will meet or exceed the functionality of the OITs
currently installed at the plant and will likely be of the same manufacturer as the
newly installed PLCs. The OITs will provide alpha-numerical and graphical
monitoring and control of system set-points, operational modes, process variables,
and system equipment.
The PLCs will perform the data gathering and process control functions and
communicate the collected information to the OITs and OWSs / HMIs for display,
control, alarming, trending and printing (TBD). The PLCs will also respond to control
commands and set points from both local OITs and the redundant SCADA PCs.
7.2.3.3
The operator will access the SCADA system via the existing Operator Workstations
OWSs located in the plants control room. The OWSs are a redundant pair of SCADA
Nodes designed to operate in a Microsoft Windows-type environment. Via window
displays, each OWS will allow plant operating personnel to view multiple windows
of information simultaneously on a single screen.
The operator will be provided with the same graphics at each OWS. The graphic
screens will allow the operator to control the process equipment associated with the
new Thickening and Cogen Systems as well as any pre-existing plant system. The
OWS will permit entry of operator set-points, selection of operational modes,
monitoring of process variables and equipment status, and alarm annunciation. The
OWS / HMI will manipulate and store all the data required for monitoring and report
generation in each of the redundant SCADA Nodes databases. The data will be used
for shift, daily, monthly, and annual reports, and gas usage reports.
The graphic displays will include detail for control and monitoring of every process
parameter and equipment in a manner that lends itself to the natural breaks of the
particular process. The graphic displays may include: index displays, single point
displays for variable and contact process inputs, process graphic displays, group
review displays, digital trend displays, analog trend displays, and alarm summary
displays. All displays will contain the date and time of day and list all process values
in engineering units. Index displays will be provided as a guide to the available
display options.
All graphic screen and displays will be available on all the OWSs. However, the
system will have the capability to limit control and/or viewing through security,
based on operator log-in. All the screens and displays will be password protected in
that only certain individuals can control equipment, change set points, etc. from the
display screens. The system will perform the following general functions:
7-11
Section 7
Electrical and Instrumentation Functions
Check all process inputs against pre-set high, low, and deviation values;
Scan all status and alarm values and alert the operator to alarm conditions
through visual, audible, and printed messages (TBD);
Respond to operator commands for displays, printouts (TBD), data entry, and
alarm and control settings;
Send current and shift report data, system documentation, and alarm messages to
the printer (TBD);
Perform continuous internal error checking and diagnostics of all data transfer
and system operation; and
Section 7
Electrical and Instrumentation Functions
ISA Code
Combined Tag
LIT
LIT-1000
Hand Switch
HS
HS-1100
Flow Element
FE
FE-1200
When several similar instruments or devices are on, or related to the same piece of
equipment, an alpha loop suffix shall be added to the tag. Examples are as follows:
Instrument or Device
ISA Code
Combined Tag
TSH
TSH-2000A
TSH
TSH-2000B
7.2.4.3
All mechanical equipment, tanks, motors, pumps, and VFDs shall have the same loop
number as the hand switches and instruments that are associated with that piece of
equipment. The process and mechanical engineers using CDM standards shall
determine the mechanical equipment abbreviations used in the equipment tag.
Examples are as follows:
Instrument or Device
ISA Code
Equipment
Equipment Tag
Hand Switch
HS-3000
Motor
M-3000
Level Transmitter
LT-3100
Tank
TK-3100
Hand Switch
HS-3200
Pump
P-3200
7-13
Section 7
Electrical and Instrumentation Functions
7.2.4.4
Description Tags
7.2.4.5
Abbreviation
RAS
WAS
All vendor panels, PLC panels, etc., shall be assigned a name tag. The name tag shall
be assigned by the proper discipline engineers and shall be used throughout all
discipline drawings. Once the panel name tag is assigned, it shall be used on all
drawings, lists and memoranda associated with that panel. Tag names for the new
Thickening and Cogen Control Panels are:
Thickening Control Panel
THKCP
COCP
7-14
Section 7
Electrical and Instrumentation Functions
Most control will be designed for only two layers; at the piece of equipment and at the
PLC system. Process equipment supplied with vendor package control systems may
have multiple layers of control.
Vendor Based Control Panels will be provided for the following systems:
9 Thickening and Associated Pumping Systems
9 Gas Cleaning Skid System
9 Generator Engines
9 Heat Exchanging Systems
9 Gas storage system
9 Waste gas burner
Modification of Plants high-speed, fiber optic, Ethernet star network will link the
PLC & OIT Based Thickener and Cogen Control Panels.
Process Control System Supplier Panels (PLC & OIT Based) that interface with
I/O from Vendor Panels and other associated instrumentation which
communicates with the modified Plant SCADA System:
7-15
Section 7
Electrical and Instrumentation Functions
Details of the above SCADA system will be developed during final design.
7-16
Section 8
HVAC and Plumbing Functions
8.1 HVAC
8.1.1 General
CDM staff visited the LAWPCA facility and inspected the existing heating, ventilating
and air conditioning systems as related to the Anaerobic Digestion / Energy Recovery
project. Based on these field observations, a review of the original facility design
documents and based on current codes and industrial standards, CDM has
established criteria for the project design. The criteria include the following standards
and codes:
8.1.3 Demolition
The sludge thickening system replacement work associated with both facility layout
options requires that the existing HVAC system ductwork supplying conditioned air
to the corridor and thickener area be relocated in order not to interfere with the
construction of new wall between the corridor and thickener area. Additionally,
under Layout Option 2, the following HVAC demolition work would be required:
A
5816-72780
Relocate exhaust fan EF-14 (exhaust from sludge holding tank area), reroute the
ductwork;
8-1
Section 8
HVAC and Plumbing Functions
Relocate HV-4 (supply to sludge holding tank area), relocate associated ductwork;
and
HV-5 in the Grit/Screening area should be removed and the associated supply air
ductwork demolished.
8.1.4.1
8.1.4.2
Section 8
HVAC and Plumbing Functions
8.1.4.3
8-3
Section 8
HVAC and Plumbing Functions
boilers should be examined during final design to determine whether they can
provide for additional heating loads.
Existing Process Building Intake Screening Area
This area should be provided with a new rooftop heating and ventilating unit and
new ductwork, sized to ventilate the space at the rate of 6 air changes per hour. An
exhaust air louver should be installed in the exterior wall to relieve the excess air from
the space. The unit heating coil should be heated by low pressure steam from the
existing boiler room. Steam condensate from the Equipment and Screening Areas
should be collected and pumped by the same condensate receiver to the boiler room.
Existing Process Building New Screenings Garage
The garage should be heated by approximately two unit heaters located adjacent to
the overhead door. The unit heaters should be electric, explosion proof type.
New Gas Safety Equipment Building
As this space would be considered a Class 1 Division 1 electrically, the building
should be heated and ventilated by an explosion proof electric heater and wall
exhaust fan. A supply air louver would be installed in the exterior wall.
8.2 Plumbing
This section describes support functions and facilities for plumbing and fire
protection. The section summarizes the status and recommended upgrades and
improvements to these support functions.
8.2.1 General
The design of the plumbing and fire protection systems should be based upon the
applicable codes and standards, including the following:
8.2.2 Demolition
Though Layout Option 1 would not require any significant plumbing demolition
work, in the event Option 2 were pursued, the following retrofit/demolition work
would be required to create room for the new digestion equipment area:
8-4
Section 8
HVAC and Plumbing Functions
Remove piping: 1/2-inch HW, 1-1/4-inch CW with risers from fixtures; remove
4-inch vent with the riser; and
Cap one floor cleanout and four sanitary pipe risers at the floor level.
8.2.3.2
8-5
Section 8
HVAC and Plumbing Functions
8-6
Section 9
Preliminary Geotechnical, Civil and Site
Design Recommendations
9.1 General
As part of the current preliminary design process, CDM has developed the following
discussion summarizing conceptual geotechnical, site improvements and site design
recommendations and standards associated with the LAWPCA Anaerobic
Digestion/Energy Recovery Project.
A
5816-72780
9-1
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
The proposed combination digester gas and sludge storage tank has a diameter of
about 50 feet and will extend about 15 feet below grade.
We understand the new pump house building is a one story structure above grade
with one level below grade. The structure is about 40 feet by 50 feet in plan
dimensions
A new cogeneration equipment pad is also proposed. The proposed pad has plan
dimensions of 70 feet by 25 feet.
Existing conditions as well as approximate location of the new facilities for the two
options are shown on Figure 9-1 and Figure 9-2.
Conduct laboratory tests on select soil samples to assist with classification of soils
encountered and determine engineering properties;
9-2
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
9-3
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
Subsurface Conditions
In general, subsurface conditions encounter during the recent test boring program
consisted of a sequence of silty sand, clay, silt and sand underlain by a sand layer.
Silty sand was encountered at both test boring locations. Typically, the silty sand
layer consisted of dry to wet, loose to medium dense, brown, gray, and orange, fine
SAND, with varying amounts of silt and occasionally trace gravel. The silty sand is
about 8 to 19 feet in thickness at CDM-1 and CDM-3 respectively. SPT N-values
ranged from 8 blows/foot (bl/ft) to 16 bl/ft at the recent exploration locations.
Below the silty sand, a layer of clay was encountered. The clay stratum consisted of
wet, soft to medium stiff, gray, silty CLAY with occasionally little to trace sand and
trace gravel. The clay layer was approximately 12.5 and 9 feet in thickness at CDM-1
and CDM-3, respectively. SPT N-values ranged from 3 bl/ft to 8 bl/ft.
Below the clay stratum, silt and sand was encountered at test boring CDM-3 with a
thickness of 35 feet. Typically, the silt and sand consisted of wet, loose to very dense,
gray, SILT with little fine sand. SPT N-values ranged from 6 bl/ft to 52 bl/ft at the
recent exploration location.
A sand layer was encountered below the clay layer at CDM-1 and below the silt and
sand layer at CDM-3. Typically, the sand layer consisted of wet, medium dense to
very dense, brown or gray, fine to coarse SAND, with some to trace gravel and trace
silt. This layer was not fully penetrated at either test boring location. SPT N-values
ranged from 11 bl/ft to 53 bl/ft at the recent exploration locations. Refusal was
encountered at 59.7 ft below ground surface at test boring CDM-1.
A summary of the subsurface conditions encountered at our recent test boring
locations is presented in Table 9-2.
Groundwater Conditions
Groundwater was observed in all of the recent test borings at the completion of
drilling. Groundwater levels measured in the boreholes ranged from 16.5 to 17 feet
below existing ground surface (approximately El. 118.4 to El. 118.8). However,
stabilized groundwater levels can be difficult to obtain in borings drilled using drive
and wash drilling methods due to the introduction of drilling fluid in the borehole. In
addition, due to the sites close proximity to the Androscoggin River, the
groundwater level is likely influenced by the river level.
Variation in Subsurface Conditions
Interpretation of general subsurface soil conditions presented herein is based on soil
and groundwater conditions observed in the recent test boring program and test
boring logs of previous explorations conducted by others. However, subsurface
conditions may vary between exploration locations. If conditions are found to be
different than assumed, recommendations contained in this report should be
reevaluated by CDM and confirmed in writing.
9-4
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
The presence of loose silt and sand underlying the clay layer at the Option 2 location:
A loose silt and sand layer is underlying the soft clay layer at the Option 2 location
whereas a well graded and denser sand layer is below the soft clay layer at the
Option 1 location.
The depth and foundation bearing load of the proposed structure foundations:
The relatively large loads of the proposed 50-foot diameter sludge tanks (5 ksf) are
anticipated to induce larger settlements than are typical considered tolerable for
structures.
The distance from and potential impact on nearby existing structures at the Option 2
location.
The proposed structures at the Option 2 location are located within approximately
4 feet of the existing TWAS tank No. 4 and 13 feet off the existing sludge thickener
tanks. Since the existing structures are understood to be supported on mat
foundations on loose to medium dense silt and sand, those existing structures will
be susceptible to construction vibration-induced settlements. In addition, the
excavation for the 50-foot diameter digester tank extends at least 6 feet below the
adjacent TWAS tanks. The excavation will extend within the zone of influence of
the TWAS tank, potentially causing settlement/deformation of the existing tank.
9-5
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
9-6
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
Deep Foundations
Based on the considerations discussed above, deep foundations may be required to
support some structures depending on the location, the type of structure selected and
settlement tolerances.
Option 1. Although a number of pile types are considered feasible, for the purpose of
conceptual design, we recommend that precast prestressed concrete (PCP) pile be
assumed for any structures requiring foundations at the Option 1 location. Typical
PCP piles sizes include 12- and 14-inch square piles with approximate structural
capacities of 99 and 134 tons, respectively.
Option 2. Due to the close proximity of the proposed structures to the existing
shallow-supported structures and the susceptibility of the existing structures to
vibration induced settlements, we recommend the structures at the Option 2 location
be supported on drilled, cast-in-place reinforced concrete piles.
Based on the limited deep boring information, the required pile lengths are not
known at this time. However, piles are anticipated to extend to a depth of at least of
65 to 70 feet bgs. Final design recommendations regarding foundation type and other
geotechnical design recommendations are pending additional test borings, final
facility layout and loading information for the tanks and structures.
9-7
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
New structures and roadways should be located using a coordinate system based on
Maine State Plane Coordinate System or dimensioned from existing structures.
Dimensions will be to column lines, outside face of building corner walls, or center of
circular tanks. New roadways will be established based on centerline dimensions.
Minimum width for new roadways will be 20 feet for two-way traffic with the
preferred width of 24 feet. Access driveways and one-way roadways will have a
minimum width of 15 feet. Minimum radii at roadway intersections will be 35 feet to
accommodate turning requirements of 30-foot fixed wheel or 55-foot semi-truck type
vehicles. New paved areas are anticipated around the proposed Digester Facility and
Gas Safety Equipment Buildings. Final dimensions will be determined based on
access requirements and anticipated vehicle type. New pedestrian walkways will
have a minimum dimension of 5 feet.
9.3.3 Materials
All new roadways and service areas will be bituminous concrete pavement composed
of a 12-inch gravel base layer over compacted subgrade. Above this will be installed a
primer coat, two and one half inch binder course, tack coat, and one and one half inch
top course. Areas being re-paved will have the same section depth, however the
hammer milled material and existing base material may be substituted for the 12-inch
gravel base. Pedestrian pathways will be a bituminous concrete pavement composed
9-8
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
of an 8-inch processed gravel base layer over compacted subgrade. Above this will be
installed a primer coat and a two and one half inch wearing course.
Sidewalks adjacent to structures will be concrete with expansion joints placed at
30-foot intervals. Vehicle control if required will be accomplished by steel beam
guardrail or vertical granite curb. Post height will be thirty inches above grade, and
will be packed in six inches of tamped screened gravel on all sides. Curb height will
be 6 inches above finished grade. Concrete filled steel pipe bollards will be located
adjacent to structures. Manholes and catch basins will be precast concrete units with
cast iron frames and grates. Units must be designed for H20 loading. Precast concrete
units shall have cone tops. RCP drain pipe will be utilized for subsurface drainage.
Flared end with riprap apron consisting of stone six to eight inches in diameter.
9.3.6 Landscape
All disturbed areas not covered with pavement or structures will receive loam and be
seeded. Some additional tree and shrub planting will be considered. Existing trees
will require protection. No construction activities will be permitted within twenty feet
of the trunks. These areas surrounding selected trees shall be fenced off with orange
safety fence. No materials shall be stockpiled, nor equipment allowed within this
area. Additional tree protection measures may be required based on evaluation of
trees to be protected. On site loam will be screened and reused on site. Additional
loam may be obtained from sources off site if necessary.
9-9
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
30%
Kentucky Bluegrass
50%
Perennial Ryegrass
20%
40%
Perennial Ryegrass
15%
Chewings Fescue
10%
Hard Fescue
10%
Birdsfoot Trefoil
10%
Switchgrass
05%
White Clover
05%
Redtop
05%
9-10
ML
26.4
28.6
0.0
0.0
0.7
30.1
3.0
30.8
89.6
26.0
38.0
LL
17.0
22.0
PL
Atterberg Limits
Non-plastic
NP
Table 9-1
Summary of Geotechnical Laboratory Testing
NV
Lean clay
--
Sandy Silt
CL
9.0
16.0
PI
(3)
Silty Sand
68.9
97.0
68.5
10.2
8.2
14.0
Fines
(%)
(2)
ML
SP-SM
CDM-3
CL
Clay
Silt and Sand
28.9
0.2
57.2
65.4
3.
30-32
CDM-3
ML
Silty Sand
21.8
34.6
20.6
SM
20-22
CDM-3
SP-SM
Sand
9.5
8.7
10-12
CDM-1
SM
SP-SM
Sand
Sand (%)
2.
51-53
CDM-1
Gravel
(%)
Abbreviations:
40-42
CDM-1
CL
Sand
Clay
(1)
20-22
CDM-1
Strata
Moisture
Content
(%)
1.
15-17
Test Boring
Number
USCS
Classification
Notes:
Sample
Depth
(ft.)
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
135.75
134.85
CDM-1
CDM-3
27.5
59.7
Exploration
Depth
(ft.)
19.0
8.0
Silty Sand
9.0
12.5
Clay
32.0
NE
>5
>39.2
Sand
16.5
17.0
Estimated
Groundwater
Depth
(ft.)
NE
>
Abbreviations:
Table 9-2
Summary of Subsurface Conditions
Notes:
Ground Surface
Elevation
(ft.)
Exploration
Number
Section 9
Preliminary Geotechnical, Civil and
Site Design Recommendations
Section 10
Permitting
10.1
Purpose
As part of the current conceptual design, an initial assessment was completed related
to the site development and environmental permitting requirements of the project.
The assessment included a review of the following issues:
Related ordinances, rules, regulations and laws of the City of Lewiston, Maine
(as confirmed through discussions with David Hediger, Lewiston City Planner);
Based on this review, we have determined that the following site development and
environmental permits will be needed for the project.
10.2
Local Permitting
A
5816-72780
10-1
Section 10
Permitting
10-2
Section 10
Permitting
The permitting on this project is very similar to the permitting required for the
Lewiston CSO Storage Facility on Water Street that received approvals from the
Planning Board in one meeting and a PBR approval from MDEP. Based on our
experience, we expect the permits described above for this project should be obtained
within 30 days after the applications are submitted.
10.3
Stationary internal combustion engines (SICE) (or combination thereof) that are
less than 5.0 mmBtu/hr and are excluded from the applicability determination.
The equipment proposed to be installed at the project site includes two 220-kW
cogeneration engines, one boiler, and one waste gas burner. The engines and boilers
will both be constructed so that they will be capable of burning either digester gas or
natural gas; the waste gas burner will be used to burn any excess digester gas. Based
on the applicable rule definitions, the required licenses that must be obtained for the
project site are itemized below:
Based on the information provided for the equipment, the two engines are
estimated to have a rated capacity of 4.1 mmBtu/hr (total); therefore, the engines
would be excluded from the applicability threshold and are exempt from
permitting.
The only equipment that meets the definition of fuel-burning equipment, other
than the SICE, is the boiler. The maximum rated capacity of the boiler is
2.2 mmBtu/hr; therefore, since the total capacity is less than 10.0 mmBtu/hr, the
boiler is exempt from permitting.
The waste gas burner does not meet the definition of fuel-burning equipment
because its primary purpose is not to produce heat or power. As a result, no
exemption from permitting is applicable to the waste gas burner; therefore, the
waste gas burner is required to obtain an air emissions license.
Emissions of criteria pollutants from the equipment were estimated using emission
factors from the San Diego Air Pollution Control District (SDAPCD). Assuming that
the equipment operates continuously (8,760 hours per year), the maximum potential
to emit (PTE) is provided in Table 10-1. Although the engines and boiler are exempt
from permitting, their emissions were still estimated for reference purposes only.
10-3
Section 10
Permitting
Boiler
Flare
Total
NOx
73.75
0.94
2.34
77.04
CO
6.87
0.79
0.09
7.75
SOx
0.06
0.03
0.10
0.19
VOC
2.34
0.05
0.59
2.98
PM10
0.83
0.07
0.58
1.49
Key
CO:
carbon monoxide
oxides of sulfur
Table 10-1
Summary of Maximum Annual Emissions
The Maine DEP classifies sources as either minor or major, with the latter being
federally enforceable, based on the sources PTE. Sources are classified as minor
sources if emissions are less than either 50 tons per year VOC or 100 tons per year of
any other regulated pollutant. Since the sources emissions (flare only) are less than
both of these thresholds, the source will be required to obtain a minor source license.
The source will be required to obtain an air emissions license prior to breaking
ground or commencing construction at the project location. The application process
involves filing necessary forms with the DEP, paying any necessary fees, and
providing information on equipment emissions and operation. A review of Best
Available Control Technology (BACT) will also be required as part of the licensing
process.
10-4
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
11.1
The current estimated construction costs based on the recommendations made in this
Conceptual Design Report are shown in Table 11-1. The total project costs for Layout
Option 1 and Option 2 of this project are currently estimated to be $16.3M and
$21.0M, respectively
Project Component
Site Work
Option 1
New Separate
Facility
Option 2
Retrofit of
Existing Facility
$229,000
$337,000
$0
$2,730,000
Yard Piping
$515,000
$305,000
$873,000
$839,000
$0
$1,249,000
$0
$895,000
$3,124,000
$1,796,000
Digestion Tanks
$2,824,000
$3,443,000
$666,000
$697,000
$1,277,000
$1,230,000
Cogeneration System
$1,235,000
$1,240,000
Electrical
$1,944,000
$1,687,000
$363,000
$363,000
$13,049,000
$16,811,000
$3,262,000
$4,203,000
$16,311,000
$21,014,000
2. Escalation for Option I is at 4% per year until midpoint of construction, September 2010
3. Escalation for Option II is at 4% per year until midpoint of construction, November 2010
4. Costs do not include mitigation of hazardous waste in existing soils, ledge removal or
legal/administrative costs
Table 11-1
Conceptual Estimate of Project Costs Based on 10% Level of Design
A
5816-72780
11-1
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
11.2
Comparison of Options
The two facility layout options discussed through this report each have distinct
advantages and disadvantages associated with them. Some of the more significant
points for consideration are noted in Table 11-2 below.
Advantages
Disadvantages
Option 1
(New Separate
Facility)
Option 2
( Retrofit of
Existing Interior
Process
Space)
Digestion equipment
distributed between multiple
process areas;
Significant impact on
Maintenance of Plant
Operations (MOPO) during
construction;
Does not readily allow for
future digestion tank capacity
expansion;
Geotechnical support would
require deep foundation
system (drilled piles);
Limited space requires taller,
more costly digester tank
configuration; and
Limits vehicle access around
and into existing process
building.
Table 11-2
Comparison of Facility Layout Options
11-2
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
Due to the significant cost and non-cost advantages associated with Option 1, it is
recommended that a separate new digestion facility be pursued in lieu of attempting
to retrofit the existing interior screenings handling area as included in Option 2. In
addition, listed below are several possibilities for screening handling improvements
(e.g., new intake screens, screenings wash compactors, and conveyors) :
Include in Option 1, the full intake screening modifications shown in Option 2, with
the exception of utilizing the existing screenings garage in lieu of constructing a
new one to the east;
It should be also noted that, the cost estimate included in Table 11-1 assumes the
construction of a new screenings garage (as required by Option 2) and the reuse of the
existing screenings garage area would likely yield cost savings not reflected in the
current estimate for this work.
11.3
Financial Analysis
As the findings, recommendations and revised capitol cost estimate included in this
Conceptual Design affect the financial analysis which was produced in conjunction
with the Feasibility Study, the project costs have been revisited and updated as
detailed below.
11-3
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
Current
Biosolids
Management
Biosolids
Management
With Anaerobic
Digestion
Savings
$34,000
$20,400
$13,600
$12,000
$12,000
$0
$3,840
$2,300
$1,540
$90,000
$0
$90,000
$30,000
$0
$30,000
$295,000
$177,000
$118,000
$18,600
$11,000
$7,600
$90,000
$63,000
$27,000
$113,000
$79,000
$34,000
($55,000)
($33,000)
($22,000)
Lime Stabilization
Lime Cost 4
Fertilizer Costs due to pH and calcium
5
saturation
Composting Facility
Amendment Cost 6
Vehicles (fuels, maintenance)
Treatment Facility
Vehicles (fuel, maintenance) 10
$54,000
$32,400
$21,600
$445,000
$445,000
$0
$84,000
$84,000
$0
$291,000
$175,000
$116,000
$157,000
$0
$157,000
$0
$25,000
($25,000)
$0
$26,000
($26,000)
$0
$75,000
($75,000)
Cogeneration System
Estimated Value of Power Production
18
($/year)
$0
($369,000)
$369,000
$0
$15,000
($15,000)
$0
$41,000
($41,000)
$1,662,000
$881,000
$781,000
12
Residual Disposal
Biosolids Land Application Cost 13
Biosolids Landfilling Cost
14
Table 11-3
Annual Estimated Operating Costs
1)
Polymer Usage is expected to decrease by 40% due to less biosolids for dewatering
2)
HP of existing DAF equipment is approximately equal to the HP required to operate the new GBT equipment
3)
Estimated BFP will operate 40% less due to reduction in sludge volume
4)
5)
11-4
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
6)
7)
8)
9)
Compost revue will decrease due to less biosolids available for composting
Scenario 2: Without any grants or low interest loans, but with an increase in waste
collection revenues equivalent to ~$200,000 per year (current dollars); and
Table 11-4 shows the results of the financial analysis. Capital costs were taken from
Table 11-1. Annual bond costs were based on a 20-year revenue bond of 3 percent
with equal monthly payments. The annual operating cost savings were based on the
average savings over a 20-year period and are approximate. The operating cost
savings includes both reduced operating costs due to lower quantities of biosolids as
well as the savings from avoided electricity costs. An escalation rate for electricity of
3 percent was used, although many economists expect that energy costs will escalate
faster than other costs. To include the effects of inflation, all operating costs were
escalated at 3 percent per year. A standard 20-year planning discount rate of 4.7
percent as recommended by the U.S. Office of Management and Budget was used.
Another factor in the financial analysis is the current LAWPCA debt service
payments. The Authority has three loans issued 1990, 1991 and 1992 that will be
completed by 2012. In 2009, the Authority incurred $790,000 in costs associated with
these loans which will decrease to zero in 2012.
11-5
Section 11
Preliminary Cost Estimate and
Revised Life Cycle Cost Analysis
For the scenario with no grants, the net average annual cost to the Authority are
approximately $50,000 and are within the cost estimating accuracy of this feasibility
study. With a 50 percent grant equivalent, the average savings is significant at
approximately $4.4M.
Item
Scenario 1:
Scenario 2:
Scenario 3:
No Grants
No Grants,
Increased
Revenue
50 Percent Grant
$16,300,000
$16,300,000
$8,150,000
$1,086,000
$1,086,000
$543,000
$1,036,000
$1,036,000
$1,036,000
$270,000
($50,000)
$320,000
$493,000
($1,300,000)
$2,000,000
$4,400,000
Table 11-4
Financial Analysis of Anaerobic Digester/Energy
Recovery Project
11-6
Appendix A
Historical Boring Logs
Appendix B
Recent Boring Logs
Sheet 1 of 3
Boring Number:
CDM-1
Client: Lewiston-Auburn WPCA
Project Location: Lewiston, ME
Strata
Plasticity
Index
Graphic Log
135.8
0
Sample
Recovery (in)
Blows per
6 inches
Sample
Length (in)
Sample
Number
Material Description
Remarks
130.8
5
SS
S-1
24
5
6
6
5
24
1
1
2
2
24
24
1
2
2
3
24
125.8
10
S-2
24
CLAY
SS
SILTY SAND
Elev.
Depth
(ft)
Sample
Type
120.8
15
SS
S-3
115.8
Sample Types
Consistency vs Blowcount/Foot
Granular (Sand):
AS - Auger/Grab Sample HP - Hydro Punch
CS - California Sampler SS - Split Spoon
V. Loose:
0-4 Dense:
ST
Shelby
Tube
BQ - 1.5" Rock Core
4-10 V. Dense:
WS - Wash Sample Loose:
NQ - 2" Rock Core
M. Dense: 10-30
GP - Geoprobe
Burmister Classification
V. Soft:
Soft:
M. Stiff:
Date: 9/28/2009
<2
2-4
4-8
Stiff:
V. Stiff:
Hard:
8-15
15-30
>30
and
35-50%
some
20-35%
little
10-20%
trace
<10%
moisture, density, color
Sheet 2 of 3
Boring Number:
CDM-1
SS
S-4
SS
S-5
S-6
24
15
15
24
25
Material Description
14
Remarks
A: (0"-6")
B: (6"-14")
10
10
SAND
SS
Strata
24
7
9
10
11
105.8
30
24
7
7
7
8
110.8
25
Plasticity
Index
Blows per
6 inches
24
2
11
9
8
115.8
20
Sample
Recovery (in)
Sample
Length (in)
Sample
Number
Elev.
Depth
(ft)
Sample
Type
100.8
35
95.8
40
SS
S-7
12
90.8
45
Sheet 3 of 3
Boring Number:
CDM-1
Strata
Plasticity
Index
Blows per
6 inches
24
6
5
6
7
Sample
Recovery (in)
Sample
Length (in)
Sample
Number
Elev.
Depth
(ft)
Sample
Type
Material Description
Remarks
85.8
50
S-8
8
SAND
SS
80.8
55
75.8
60
100/0"
SPT Refusal
Encountered
70.8
65
65.8
70
Sheet 1 of 3
Boring Number:
CDM-3
Client: Lewiston-Auburn WPCA
Project Location: Lewiston, ME
S-1
SS
S-2
SS
S-3
24
2
2
5
13
119.9
15
S-4
Remarks
16
14
10
18
A: (0"-16")
B: (16"-18")
CLAY
SS
Strata
24
3
3
5
5
124.9
10
Graphic Log
24
7
7
7
5
129.9
5
Material Description
SILTY SAND
SS
Plasticity
Index
Blows per
6 inches
24
4
9
7
8
134.9
0
Sample
Recovery (in)
Sample
Length (in)
Sample
Number
Elev.
Depth
(ft)
Sample
Type
114.9
Sample Types
Consistency vs Blowcount/Foot
Granular (Sand):
AS - Auger/Grab Sample HP - Hydro Punch
CS - California Sampler SS - Split Spoon
V. Loose:
0-4 Dense:
ST
Shelby
Tube
BQ - 1.5" Rock Core
4-10 V. Dense:
WS - Wash Sample Loose:
NQ - 2" Rock Core
M. Dense: 10-30
GP - Geoprobe
Burmister Classification
V. Soft:
Soft:
M. Stiff:
Date: 9/28/2009
<2
2-4
4-8
Stiff:
V. Stiff:
Hard:
8-15
15-30
>30
and
35-50%
some
20-35%
little
10-20%
trace
<10%
moisture, density, color
Sheet 2 of 3
Boring Number:
CDM-3
24
SS
S-6
SS
S-7
SS
S-8
24
2
2
4
5
24
4
4
5
5
24
4
6
8
11
24
6
8
10
13
94.9
40
SS
S-9
89.9
45
SS
S-10
24
CLAY
24
99.9
35
Remarks
21
2
3
5
5
104.9
30
Material Description
14
109.9
25
Strata
U-1
SS
Plasticity
Index
24
114.9
20
Sample
Recovery (in)
Blows per
6 inches
S-5
Sample
Number
SS
3
3
2
3
Sample
Type
Elev.
Depth
(ft)
Sample
Length (in)
Sheet 3 of 3
Boring Number:
CDM-3
S-11
24
16
22
31
30
Strata
24
14
20
32
32
Graphic Log
24
7
8
11
17
Material Description
Remarks
SS
Plasticity
Index
Blows per
6 inches
24
9
12
14
15
84.9
50
Sample
Recovery (in)
Sample
Length (in)
Sample
Number
Elev.
Depth
(ft)
Sample
Type
79.9
55
SS
S-12
74.9
60
S-13
18
SS
SS
69.9
65
S-14
16
64.9
70
Appendix C
Geotechnical Laboratory Test Results
rO
PLASTICITY INDEX
40
30
20
rO
10
CL-ML
4
7
ML or OL
MH or OH
0
0
10
20
30
40
MATERIAL DESCRIPTION
50
60
LIQUID LIMIT
70
LL
PL
PI
38
22
16
26
17
80
90
%<#40
100
%<#200
Depth: 15-17
Depth: 20-22
99.5
97.0
Remarks:
CDM
Cambridge, Massachusetts
USCS
CL
110
Figure
CL
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
6.9
Coarse
13.7
17.6
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
93.1
79.4
61.8
44.0
31.9
22.1
14.0
% Sand
Medium
29.9
% Fines
Fine
Silt
Clay
17.9
3.8
10.2
Soil Description
silty sand with gravel
PL= --
Atterberg Limits
LL= --
D85= 7.0675
D30= 0.3596
Cu=
USCS= SM
PI=
Coefficients
D60= 1.8393
D50= 1.1422
D15= 0.0869
D10=
Cc =
Classification
AASHTO=
Remarks
As received moisture content=8.7%
* (no specification provided)
Sample No.: S-4B
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-1
5816-72780
Figure
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
23.4
Coarse
11.2
13.2
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
76.6
65.4
52.2
40.3
31.6
19.0
8.2
% Sand
Medium
20.6
% Fines
Fine
Silt
23.4
Clay
8.2
Soil Description
poorly graded sand with silt and gravel
PL= --
Atterberg Limits
LL= --
D85= 34.5434
D30= 0.3707
Cu= 38.83
USCS= SP-SM
PI=
Coefficients
D60= 3.2447
D50= 1.7324
D15= 0.1146
D10= 0.0836
Cc= 0.51
Classification
AASHTO=
Remarks
As received moisture content=9.5%
* (no specification provided)
Sample No.: S-7
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-1
5816-72780
Figure
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
0.0
Coarse
0.2
0.4
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
100.0
99.8
99.4
92.0
71.7
29.6
10.2
% Sand
Medium
27.7
% Fines
Fine
Silt
61.5
Clay
10.2
Soil Description
poorly graded sand with silt
PL= --
Atterberg Limits
LL= --
D85= 0.6330
D30= 0.1518
Cu=
USCS= SP-SM
PI=
Coefficients
D60= 0.3180
D50= 0.2514
D15= 0.0909
D10=
Cc =
Classification
AASHTO=
Remarks
As received moisture content=21.8%
* (no specification provided)
Sample No.: S-8
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-1
5816-72780
Figure
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
0.0
Coarse
0.7
0.2
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
100.0
99.3
99.1
99.0
98.9
92.9
68.5
% Sand
Medium
0.2
% Fines
Fine
Silt
30.4
Clay
68.5
Soil Description
sandy silt
PL= --
Atterberg Limits
LL= --
D85= 0.1144
D30=
Cu=
USCS= ML
PI=
Coefficients
D60=
D50=
D15=
D10=
Cc =
Classification
AASHTO=
Remarks
As received moisture content=28.9%
* (no specification provided)
Sample No.: S-3
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-3
5816-72780
Figure
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
0.0
Coarse
0.0
0.1
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
100.0
100.0
99.9
99.8
99.5
99.2
97.0
% Sand
Medium
% Fines
Fine
Silt
Clay
2.5
55.1
41.9
0.4
Soil Description
lean clay
PL= 17
Atterberg Limits
LL= 26
D85= 0.0565
D30=
Cu=
USCS= CL
PI= 9
Coefficients
D60= 0.0183
D50= 0.0089
D15=
D10=
Cc =
Classification
AASHTO= A-4(7)
Remarks
As received moisture content=28.6%
* (no specification provided)
Sample No.: S-5
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-3
5816-72780
Figure
#200
#140
#100
#60
#40
#30
#20
#10
#4
3/8 in.
in.
in.
1 in.
1 in.
2 in.
3 in.
6 in.
80
PERCENT FINER
70
60
50
40
30
20
10
0
100
10
0.1
0.01
0.001
% +3"
0.0
0.0
Coarse
0.0
0.0
SIEVE
PERCENT
SPEC.*
PASS?
SIZE
FINER
PERCENT
(X=NO)
3
3/4
#4
#10
#20
#40
#100
#200
100.0
100.0
100.0
100.0
100.0
99.9
97.6
68.9
% Sand
Medium
0.1
% Fines
Fine
Silt
31.0
Clay
68.9
Soil Description
sandy silt
PL= --
Atterberg Limits
LL= --
D85= 0.1051
D30=
Cu=
USCS= ML
PI=
Coefficients
D60=
D50=
D15=
D10=
Cc =
Classification
AASHTO=
Remarks
As received moisture content=26.4%
* (no specification provided)
Sample No.: S-7
Location:
Source of Sample:
CDM
Cambridge, Massachusetts
CDM-3
5816-72780
Figure