You are on page 1of 18

Automation 2011

Name
Job Title
Company

: Jigish Jepal
: Executive Manager
: Yokogawa India Limited

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Presentation Points
KeyPointsinFieldbus Project
Typicalearly(before~2004)FFprojectexecutionandlessonLearned
Presentday(after2004)FFprojectexecution
Fieldbus projectexecutionmethodology
Fieldbus projectexecutionprocedure example
Fieldbus projectsupporttools
Fieldbus segmentdesignguidelineandsegmentchecktools
Engineeringtools
FactoryAcceptanceTestprocedure
SiteAcceptanceTestprocedure

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Key Points in Fieldbus Project (1/2)


UnderstandingofDifferenceofFFSystemfromConventionalSystem
Technology
Design & Engineering
Design&Engineering
FAT/SATMethodology
Installation
Commissioning
DeviceFunctions

EstablishmentofFFProjectExecutionMethodology
ProjectHandlingProcedure
g
g
g
DesignandEngineeringProcedure
DesignDocumentation
DesignInformationExchangeScheme

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Key Points in Fieldbus Project (2/2)

CommonUnderstandingofFFSystemamongUsers/EPC/Licensersand
Vendor

AssignmentofExperiencedEngineersinProjectTeam

ConfirmationofDeviceInteroperabilityandAvailability
Confirmation
of Device Interoperability and Availability ofAux.
of Aux
Equipments;PowerSupply/Exi Barrier/Terminatoretc.

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Typical early (before ~2004) FF project execution and lesson Learned


ConventionalI/OBasis
FeedPhase

EngineeringPhase
Basic
Design

Feed

DetailedDesign

KOM

Generation&Debug

SiteActivityPhase

FAT

SAT

Commissioning

Shipping

Spec.Freeze

FFBasis
FeedPhase

EngineeringPhase

Feed

BasicDesign

KOM

DetailedDesign

Generation&Debug

Spec.Freeze

SiteActivityPhase

FAT

SAT &
SAT&
Commissioning

RiskatSite

Shipping

FFKnowledge

ExperiencedEngineersResource
p
g

Device Interoperability
DeviceInteroperability

PJTExecutionProcedure

Device&Aux.Equipment Selection

FAT/SATProcedure

DesignDocuments

SegmentDesign
DeviceGrouping,PIDAllocation
Device Grouping PID Allocation
Macrocycle,CableLength:Trunk&Spur

Service&MaintenanceTool

ProblemsobservedinearlierstageofProject
FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Present day (after 2004) FF Project Execution


FFBasis

BasicDesign

Feed

DetailedDesign

KOM

Generation&Debug

FAT

Spec.Freeze

FeedPhase
Feed

SiteActivityPhase

EngineeringPhase

FeedPhase

DetailedDesign

KOM

Generation&Debug

Spec.Freeze

RiskatSite

Shipping

EngineeringPhase
Basic
Design

SAT&Commissioning

SiteActivityPhase
FAT

SAT&Commissioning

Shipping

DesignandEngineeringTools&Procedure
FieldbusTutorial
Fieldbus
Tutorial
FFTechnologyIntroduction
FFProjectExecutionGuide
FFSegmentDesignGuideline
FunctionalDesignSpecification
SegmentCheckTool
Device&Aux.Equip.SelectionGuide

SystemEngineeringGuide
BetterEngineeringTool
FATProcedure
SATProcedure

BenefitstoCustomer
MinimizeHumanErrors
PreventReworks
ShortenPJTSchedule

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Execution Methodology


ProjectKOM

FFsegmentdesignin
FF
td i i
basicdesignphaseis
akeyelementintheFF
projectexecution.

BasicDesign

HardwareDesign

MainframeofFFproject
executionprocedureis
sameasconventionalI/O
system.
Eachworkitemneedssome
changesandadditionsto
implement FF technology
implementFFtechnology.

SoftwareDesign
SystemStaging
&InternalTest

FATmethodologyis
gy
differentfromthe
conventionalI/Osystem.

FAT
FAT

Needstosetup
Needs
to set up
FFsystemproject
coordinationprocedure
Designinformation
exchange scheme
exchangescheme

Delivery

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Execution Procedure : Example (1/3)


DeliverablesbyCustomer
1)PJTSchedule
2) PJT Organization
2)PJTOrganization
3)InquirySpecification
4)FFDesignrequirements

Milestone
Kick Off
KickOff

Basic Systemdesign
FFSegmentDesignPhilosophy

DeliverablesbySystemVendor
1)ProjectExecutionPlan
)
g
2)PJTOrganization
3)PJTSchedule
4)QA/QCPlan
5)Technical&CommercialProposal
6)BillOffMaterials(BOM)
FFSystemDesignSpecification
FFSegmentDesignSpecification

1)InstrumentIndex
2)I/OPointList
3)LoopDrawing

DesignRequirementsfor;
1)Console&Aux.Cabinet
2)Subsystem
3)Aux.Equipment

HardwareDesign

H/WDesignSpecification
1)DCSSystemConfiguration
2) DCS H/W E i
2)DCSH/WEquipmentSpec
tS
3)EquipmentDimension
4)PowerSupply/Grounding
5)Subsystem/Aux.Equipment

A
FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Execution Procedure : Example (2/3)


DeliverablesbyEPCContractor
FFDesignInformation
1) D i Li & T
1)DeviceList&Type
2)FBAssignment
3DeviceGrouping
4)ExpectedCableLength
5)CableSpecification

Milestone

DeliverablesbyDCSVendor

FFSegmentDetailDesign

1)ComplexLoopSchematics
2)NarrativeofComplexLoop&FB
)
i
f
l
&
3)Sequence&InterlockLogic
4)GraphicSketch
5)SubsystemCommunicationSpec

1)H/WDesignSpecification
&Drawig
2) BOM f H d
2)BOMofHardware
3)I/OCardAssignment
4)TypicalLoopConfiguration

MaterialOrder&Manufacturing

SoftwareDesign

S/WDesignSpecification
1)ControlFunctions
2) MMI F ti
2)MMIFunctions
3)AlarmFunction
4)Access/SecurityFunctions
5)Graphic/Logging
6)SubsystemInterface

B
FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Execution Procedure : Example (3/3)


DeliverablesbyEPCContractor

Milestone

DeliverablesbyDCSVendor

B
1)JBScheduleforMarshallingRack
)
2)WiringDetails
3)InstallationDetails
1)LoopDrawings
2) Assignmentof
MarshallingRack

1)CommunicationPointList
1)
Communication Point List
2)GraphicDisplayData
3)LoggingFormats
4)GroupDisplayAssignment
5)TrendAssignment
S/WGeneration

SystemStaging

InternalTest
l
FATProcedure
FAT
Delivery
FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Support Tools (1/2)


ProjectExecutionPhase
SupportTools

Category

Feed
Phase

Engineering
Phase

GeneralSpecificationofFF

GeneralInformation

FFTutorial

GeneralInformation

FF Technology Introduction
FFTechnologyIntroduction

General Information
GeneralInformation

DesignGuideline

Procedure&Manual

DesignGuideline

DesignTool

FFSegmentDesignGuideline
FFPJTExecutionGuideline
SystemEngineeringProcedure
SegmentCheckTool

Site
Activity
Phase

EngineeringTool

EngineeringTool

Device&Equip.SelectionGuide

DesignGuideline

FATGuideline

DesignGuideline

SATGuideline

DesignGuideline

Startup&ServiceManual
Training Manual
TrainingManual
QuotationGuideline

Procedure&Manual
Manual

QuotationGuideline

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Project Support Tools (2/2)


9

GeneralSpecificationFFinDCS

FFTutorial

FFTechnologyIntroduction

FFSegmentDesignGuideline

FFPJTExecutionGuideline

SystemEngineeringProcedure

I&C
Plant/
SegmentCheckTool
AFE
System
System
Process
Process
9
Device&Equip.SelectionGuide
Design
Design
9
9

FATGuideline

SATGuideline

g
TrainingManual

QuotationGuideline

FeedPhase

FDS

FFSegmentDesignGuideline

Device&Equip.SelectionGuide

SAT Guideline
SATGuideline

StartUp&ServiceManual

SAT

Installation

Commissioning

Operation

SiteActivityPhase
DetailedDesign

Quotation/
Clarifications

Basic
Design

FF Segment Design Guideline


FFSegmentDesignGuideline

FFPJTExecutionGuideline

SystemEngineeringProcedure

SWIFTPlusEngineeringTool

Device&Equip.SelectionGuide
i &
i S l i G id

FATGuideline

SATGuideline
FFIC:Automation2011 Mumbai

H/WDesign&
Manufacturing

Gen./
Debug

FAT

S/WDesign/
Configuration

EngineeringPhase
2011FieldbusFoundation

Fieldbus Segment Design Guideline

Table of Contents
1. General
1.1 FF Segment Design Methodology
2. Basic Segment Design
2.1 Hazardous Area Classification
2.2 Redundancy
2.3 Segment Loading
2.4 Spare Philosophy
3. Wiring Design
3.1 Topology
3.2 Cable Length
3.3 Cable Type
3 4 Power Consumption
3.4
3.5 Minimum Operating Voltage

4. Segment Execution Time


4.1 Macrocycle Time
4.2 Scheduling
5. Control Assignment
6. Application Specific Design
6.1 Control Valve Fail State
6 2 ESD Valve Status Equalization
6.2
6.3 Risk Assessment For Control
Loops
7. Documentation
7.1 Segment Drawing
7.2 Loop Configuration Drawing

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Fieldbus Segment Check Tools

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Typical Engg. Tool

CustomerDB

INtoolsRDB
Instrument
IndexModule Export
(INtools)
Source ocuments
SourceDocuments
P&ID
Control
Narratives
etc.

MS Excel
MSExcel
/Access

Crosslink

Engg.
gg
DB

Engg.Tool

Meeting

Typical
oops
loops
marking
onP&ID

Typical FAT
TypicalFAT

Autogeneration

Text DB
TextDB
Typical
Loops

DCSDB
Builder
(DCS)

w/generictag
numbers

Export
(DCS)

DCSDBw/targettag
numbers

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Factory Acceptance Test Procedure

9 DeviceListVerification
9 DDFileAndCapabilitiesFileVerification
9 FieldbusApplicationVerification
:ConnectionofFunctionBlocks
9 H1CommunicationSchedulingChartVerification
9 ConnectionTestwithActualFieldDevice
( y
(byUsingRepresentativeModel)
g p
)
9 SegmentFunctionalTestforSelectedSegment
withActualFieldDevices

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Site Acceptance Test Procedure

9 ConfirmPhysicalConnectionoftheFieldDevices
9
9
9
9
9
9

DownloadConfigurationDatatoFieldDevices
Download
Configuration Data to Field Devices
LoopConnectionCheck
VerifyVoltageatDeviceTerminals
Observe and Check Signal Wave
ObserveandCheckSignalWave
VerifyLoopOperation(LASRedundancyChecketc.)
AdjustLoopParameters

Note
9 ArrangementofProperSiteOrganizationforSiteActivities
(SAT&Commissioning)
9 PrepareToolsforTroubleshootingatFAT/SAT
(BusMonitor,VoltMeterandOscilloscope)

FFIC:Automation2011 Mumbai
2011FieldbusFoundation

Thank You
Fieldbus Foundation
IndiaCommittee

21st September,2011
www.fieldbus.org
FFIC:Automation2011 Mumbai