METHOD STATEMENT FOR ERECTION OF

STIFFFNER ANGLE WITH EXISTING CURB


CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

METHOD STATEMENT FOR ERECTION OF STIFFENER


ANGLE WITH EXISTING CURB CHANNEL WITH
ERECTION OF DEFLECTOR PLATE ARRANGEMENT FOR
TANK T006

DATE

SIGN

NAME

REV

DESCRIPTION

DATE

PREPARED BY

CHECKED BY

APPROVED BY

Page 1 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Date
15.10.2016

Details of Revision
Submission for Review & Approval

18.10.2016

Resubmission for Review & Approval

Rev No. : 01

Rev.

00
01

Page 2 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

Content
1.0

Safety

2.0

Terms and definition

3.0

Roles and responsibilities

4.0

Methodology for Erection of stiffener angle with existing


curb channel

5.0

Painting

6.0

Quality Controls / Checks

Page 3 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

1. Safety:
I.

Job Safety analysis shall be submitted later before commencement of job.

II.

JSA to be prepared as per the approved JMS activities and submitted for
approval, work to be carried only after getting approval of JSA.

For working at height safety procedure VTKN/9001/PRO/SHE/ /014 shall be


followed.
III.

The First Aider will be informed of the ongoing activity and First Aid Box with
ingredients shall be made available at site. Ambulance would be stationed
outside terminal for the duration of site work.

IV.

Fire fighting system, such as fire extinguishers, fire buckets, motivational


displays, shall always be kept ready. Fire watcher deployment at hot work
location provides added safety at work site.

V.

Deployment of hole watcher is mandatory for any confined space entry prior
to obtaining PTW.

VI.

For any emergency, assembly and evacuation would be done based on the
Terminal sirens and follow the terminal instructions.

Project emergency response for height work and entrapment shall be followed as per
the procedure VTKN/9001/PRO/SHE/ /003

2. Terms and Definition


a. Client :.
b. PMC

: Ltd.

c. EPC

:.

d. AFC

Page 4 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

3. Roles and responsibilities


Construction Manager
Reporting to Project Manager and Responsible for:-

Responsible for overall execution planning at micro level, monitoring and controlling of all
fabrication, erection and commissioning activities to be ensure fulfillment of contract
commitment.
To monitor shop environment, health & safety and quality performance regularly
To act as communication channel for information exchange between PMC & and executing
agencies and forward relevant feedback to concerned till the completion of contract.
To ensure that modification is carried out as per approved procedure.
To participate in safety committee meetings
To control client supplied materials
To ensure storing of all items in proper manner to prevent damage or deterioration
To ensure SHE norms and applicable legislation are followed in camp and work sites.
Construction Engineer
Reporting to Construction Manager and Responsible for:-

Responsible for overall construction activities on site, and maintaining safety norms, for
complying, environment, health & safety of construction
To ensure that all construction activities are as per approved procedure
Responsible for execution, planning and quality of fabrication, erection and painting
Responsible for handling of material supplied by client
Preparation of JSA along with Safety Engineer

Page 5 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

Quality Engineer
Reporting to Quality Manager and responsible for:Quality Management system implementation and monitoring
All activity control on site construction
Witnessing and reporting as per relevant ITP requirement.
Reports sign off and maintaining
Monitoring of construction activity as per API 653 & IS-803. If any deviation found, informed
to concern Dept. at the early stage.

Safety Engineer
Reporting to Safety Manager and responsible for:To monitor shop environment, health & safety performance regularly
Arrange and participate Everyday tool box meeting at site
To ensure SHE norms and applicable legislation are followed in camp and work sites.
Incident and accident reporting and recording
Analysis of job safety (JSA) along with Construction Engineer

4. Methodology for Erection of stiffener angle with existing curb channel


Due to defect to existing curb channel by.
This section describes the method and sequence for the erection of stiffener angle with existing curb
channel and hence sequence for erection of deflector arrangement on the stiffener angle. The
sequences are as follows:

Page 6 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

a. Erection of Scaffolding
Deflector plate location is with existing curb channel which is at top, therefore to reach at the
location we need to erect scaffolding around the tank.

b. Removal of existing deflector plate


In order to erect stiffener angle we need to remove all deflector plates. The removal of deflector
plate will be done after cutting each segment of deflector plates. The removed plates will be kept on
top of tank roof for further handling purpose.
c. Cutting of deflector plate cleat
Now after removal of deflector plate the space for stiffener angle of ISA 50 need to be clear,
therefore all cleats need to be removed. Precaution will be taken for cutting from curb channel
because the lap portion over curb channel will not be cut. 25mm spacer cleat will be grinded on shell
plate. Hence the cleats must be retained where it is welded with roof plates and ground welded
from the cut line with curb channel. The following figure illustrates the preceding statement:

Fig: Illustration of ground welding of all deflector cleat with curb channel.
The damaged curb channel must be kept untouched and retained as damaged because cut bu (to be
left as they are)

d. Erection of stiffener angle with existing curb channel


Stiffener angle of dimension ISA 50x50x6 will be used with existing curb channel. The following
illustration will describe the schematic arrangement. The length of stiffener angle must be 3m
minimum properly rolled in radius of 3050 mm minimum. Cleat will be used to hold stiffener angle
to arrest stiffener angle. Following figure illustrate the schematic arrangement of stiffener angle
with existing curb channel:

Page 7 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

Fig: Illustration of ground welding of all deflector cleat with curb channel.
The location of stiffener angle will be kept offset with the vertical joints of curb channels and groove
will be cut from stiffener angle where it is coinciding with curb channel weldings. After fitup all
grooves will be ground welded.

e. Erection of Deflector cleats


New deflector cleat will be erected now on stiffener angle as shown in the following illustration

Deflector cleat must be clear from shell plate and do not touch with the same. No spacer plate will
be used in between deflector cleat and shell plate. No Welding /Hot work will be done on shell plate.

f.

Erection of deflector plates

Page 8 of 9

METHOD STATEMENT FOR ERECTION OF


STIFFFNER ANGLE WITH EXISTING CURB
CHANNEL WITH ERECTION OF DEFLECTOR
PLATE ARRANGEMENT FOR TANK T006

Doc. No. : VTKN/9001/TT/MS/24

Rev No. : 01

The removed deflector plates will now erected over deflector cleat and welded as fixed earlier. A
uniform gap must be there in between shell and deflector plates. No hot work or welding will be
done on shell plate.

5.

Painting
stiffener angle with existing curb channel and hence sequence for erection of
deflector arrangement on the stiffener angle must be sand blasted and primer
painted as per the specification at shop prior to reach at site. The touch up painting
will be done after completion of all works and pattern must be matched with the
existing pattern of tank.

6.

Quality Controls/Checks
The activities involved in the construction are much diversified and
therefore it is required to maintain all records and reports. The reports
and records must be retaining for future reference. Prior to
commencement of any work it is required to know the scope of work,
the method to execute and the safety measures to achieve the quality
and safety goal of the organization. Inspection and Test Plan should
come in existence to support the construction activities. This will
develop a culture of close supervision in construction activities, the
basic quality control measures are as:
i. SITP: Site inspection and test planning
ii. Field Observation reports
iii. Regular inspection and random inspection
iv. Conformity and non conformity as per the standard of construction
v. Recording of all inspections through approved formats
vi. Organizing job specific tool box to educate the workman engaged in
individual activities

Page 9 of 9