Professional Documents
Culture Documents
20 PSC Slab)
by Elimination of Pile Cap and Pier
By
Mukesh Mandalia*
A.K.Panday**
SYNOPSIS
The proposed bridge site is between Gandhidham and Kandla Port, near the Kandla Port Station on Nakti
river which is a creek experiencing two high tides and two low tides every day. Form the Google map of
the bridge location, it is seen that the entire area remains flooded and submerged due to high tides.
Surrounding area was marshy and having compressible soil. A large area of land was required adjacent to
the site for stacking of cement, steel, erection of batching plant, CPCC treatment, sand blasting,
fabrication of MS liners, pile driving equipments etc. To carry out the above activities, huge amount of
earthwork had to be carried out make a leveled platform. Due to compressible nature of soil underneath,
there was lot of difficulty in the plying of vehicle i.e. trucks, trailers cranes etc. It was not feasible to
construct the bridge in a conventional way of piling, pile cap, abutment & pier and then slab. So it was
decided to do away with pile cap and abutment/pier and directly construct bed block on piles.
* XEN(C)-ADI
**AXEN(TMC)-NER
54
1.
n
2.
n
3.
Introduction
Kandla Port is a major Port on the western cost of
India. There was single BG line between Kandla Port
and Gandhidham.
Due to vast development of Kandla Port in the recent
times, the cargo handling has increased many folds in
the recent years.
Due to this, the Rail Traffic to and from the Kandla port
had also increased substantially.
To meet with the increased traffic to and from the
Kandla Port, the need for doubling of GandhidhmKandla Port had arisen. Therefore, the work of
doubling between Gandhidham-Kandla) Port (12.00
KM) was sanctioned and it was targeted to be opened
before 31.3.2011.
Bottle Necks and Difficulties
In the doubling between Gandhidham-Kandla Port,
construction of Major Br. No.316 (7X12.20 M PSC
Slab) on NAKTI RIVER, which passed through
creek of Kandla port was a bottleneck as it carries
back water and is perennially under water.
There was huge tidal variation of approx. 6 M and the
velocity of the flow at the time of high tide was
extremely high.
The net available time for completion of this project
including Major Br. No. 316 was only 3 and half
months. The work was started on 15.12.2010 and it
was targeted to be completed before 31.3.2011.
Scheme of Construction:
There were two options available for the construction
of this bridge
(i) Construction of pile cap at river bed level and pier
by constructing water tight coffer dam.
(ii) Elimination of pile cap and pier by following
method
Construction of earthen bank up to pier cap
level
Driving piles from top of earthen island up to
pier cap level.
Removal of earthen island and with the pile
from bed level to pier cap level serving as pier.
This portion of pile is to be cast with casing.
3.1 Drawback of Scheme-(i)
n
The option of providing pile cap at bed level would
have required water tight coffer dam with sheet piles.
In this method, there was a possibility of ingress of
subsoil water which would have required massive
arrangement for bailing out subsoil water by well point
4.0 Planning
There was extremely stiff target of 3 and half months
for the completion of this bridge.
n
Therefore what was required was the meticulous
planning and strict implementation of that planning
n
A bar chart was prepared keeping in view the
availability of machinery, material, labour festivals
etc. All arrangements of Machineries, material and
labour were closely monitored as per the bar chart.
n
Problems with regard to labour, material, machineries
were immediately identified and corrective measures
were taken so as not to deviate from the bar chart
n
For any deviation in the original planning and bar
chart due to any unforeseen reasons, corrective
measures were taken and back up plans were
immediately drawn to make up the loss or delay in the
work.
n
The construction of Bridge was done in two phases
n
55
5.0 Phase-i
n
PHASE-I
PIER CAP
PIER CAP
PIER CAP
ABUTMENT
PILE CAP
PILE
BED
LEVEL
9161
56
PIER CAP
Grade of CC
Pile Dia.
Pile Nos.
Depth of piles
For Pier
M:35
1200 mm dia.
4 Nos
For Abutment
M:35
1200 mm dia.
9 Nos
(B) Substructure:
Structure
Grade of CC
Size
Remarks
Pier
M:35
4X 1200 mm Dia.
Cast as pile
Pier cap
M:35
1X5100mmX5100 mmX1800 mm
Abutment
M:35
This Bridge being in earthquake zone-V, Therefore, no Elastomeric bearings were provided as per RDSO guidelines.
Free Board
2185 mm
Clearance
1005 mm
Waterway
265.44 SQM
deployed at a time.
n
57
11.0 Superstructure
Since the pile above the bed level acts as a pier, extra
care was taken to ensure the verticality of the pile.
(I)
58
13.0
Piles cast between bed level and pier cap level served
as pier. Pier cap were directly constructed on pile
14.0 PHASE-II
15. Conclusion
14. PHASE-II
n
59