You are on page 1of 317

A.P.

REVISED STANDARD DATA

PART-III

BUILDINGS & ELECTRICAL ITEMS

GOVERNMENT OF ANDHRA PRADESH, ROADS & BUILDINGS DEPARTMENT

STANDARD DATA USER GUIDELINES

PREAMBLE
1. The existing AP Standard data for various constructions items are based on observations made
several decades back, mostly utilising eployment of machinery was at the barest minimum. The
Board of Chief engineers have been adopting almost the same data, duly modifying the rates of
labour; materials, hire charges of limited machinery, every year. The advent of construction
machinery and its usage in construction industry has changed the structure and methodology of
data formulation & rate structure and hence, the present estimation of work item rates are not
reflecting ground reality. The CWC(Ministry of Irrigation) has also recommended that where
standard or schedule of rates are revised or where is necessary to do so, the primary guiding
principle should be escalation in labour and material cost and not on trend of rates quoted by
contractors. But the above recommended principle is not being followed by the Board of Chief
Engineers in Andhra Pradesh.
2. Government, in GO 7326 (GAD-GPM& AR) Dated 26-10-05, has observed that the age old
Standard data requires revision and updation with reference to the latest machinery and
contemporary practices and has constituted a High Level Committee to advise on updating and
revision of standard data and schedule of rates. The work has been taken up by CGG and SPIUirrigation. The secretary (Irrigation ) is the member- convener of the committee Accordingly the
data has been revised adopting the procedures and guidelines given by CWC, Report on
committee on cost control of river valley Projects, BIS specifications, NHAI, MORTH, MORD, CPWD
and Government of Karnataka and revised data and formulated schedule of rates for all
infrastructure Departments (I&CAD, R&B, PR and PH). The team of senior engineers interacted
with the S.R Committee of Karnataka on implementation and improvements needed. For irrigation
works the data pattern as adopted by Karnataka has been considered and for other Departments
the data adopted by MORTH,MORD and NHAI etc., is adopted
3. Sequence followed in revision of standard data is,
(a) The first step is the revision and formulation of standard data for each work
component
(b) The second step is to work out the details of inputs. This enables to generate the unit
work item rates, by incorporating the use rates of machinery, materials, labour charges
and other supplementary parameters
(c) The third step is to develop software tool to generate unit rate using the software
(completed for irrigation works by the SPI Unit of Irrigation)
4. The Detailed draft data was communicated to all the HODs and interacted through many
seminars and discussions and incorporated the relevant features.The Board of chief engineers in
their meetings have recommended for acceptance to the data formulated and schedule of rates.

STANDARD DATA USER GUIDELINES

It was proposed to examine the recommendations on important parameters, to refer to high level
committee, for their specific recommendations for adoption, as they are common to all
departments. The committee made in depth study on the methodology and systems followed by
the reputed National organizations and other States and made detailed deliberations with HODs
and representatives of Builders Association of India and

made

recommendations to the

Government, on adoption of such parameters in A.P.


5. The Chief Secretary held a detailed discussions on 04-07-2007,with the Secretaries of the
Departments and Heads of Departments.
B. GUIDELINES
1) The Revised Standard Data is formulated under four Parts which are applicable to all the
Engineering Departments and other Organisations.
PART -1: Irrigation& CAD (Dam and Allied Works, Canals And Allied Works, Canal C.D.
Works, Tunnels and Allied Works, Preliminary and Maintenance Works, Hydraulic
Gates and allied works and Leads and Lifts applicable to all Departments
PART -2: Roads and Bridges
PART -3: Buildings including Electrical Works
PART -4: Drinking Water Supply and Public Health (ONLY FOR WORKS DONE BY MANUAL
MEANS)

2)

Brief description of item of work. :

Brief description of the item of work to cover all important aspects of the work included in the in
the Data . On reading the item description, the user should be in a position to assess the various
cost components involved in the work.
3)

Data for assessing quantities :

The data reflects various assessments / assumptions made in arriving at the quantities of
materials, machinery, labour and other in-puts. In case of plants and equipment the output of
main plant is worked out and the requirement of all other inputs and assessed to match the
output of the main plant. Cycle time of operations is the criteria for assessing the output of
equipment. Generally the equipment manufacturers furnish the output of machinery under ideal
conditions of working. Suitable job and management efficiency factors are considered while
working out the average output of machinery under field conditions. In case of combination of
machinery and manpower the assessment of manpower shall match the output of machinery.
Though cycle time of operations is the criteria for hourly / daily out-put of machinery work-force
,the actual progress of work depends on several other factors such as power interruptions, minor
break-downs, time for meals and other needs of work-force, stray rains etc. Therefore, it is the
general practice to consider 50 minutes as the actual working time per hour for working out the
hourly / daily out-put of machinery / work-force.CWC / BIS guide-lines stipulate the actual working

STANDARD DATA USER GUIDELINES

hours for the purpose of equipment planning and utilisation. The daily out-put is computed duly
considering the actual available working time and feed back from the field.

For gate and hoist works it is the general practice to specify the quantity of work in

terms of number of sets of embedded parts / gates. The requirement of machinery and workforce for cutting, bending, fabrication, erection, painting etc., is assessed to commensurate with
the task involved.

The data for gates and E.M. Parts is arrived per Ton quantity.

The data for Hoists and Gantry Cranes is worked out on the basis of capacity in tonnage

4) The lead and lift charges provided in PART-I (B) are generally applicable and common to all
Departments. Any item is not covered in this part, the rates as provided in the data of the
relevant works may be adopted in preparation of estimates.
5) The basic material inputs needed for all works are listed and incorporated in the data. The
requirements are analyzed and the specifications adopted shall confirm to Standards published by
the BIS.

The labour and material rates will be communicated by the Board of Chief engineers.

Unless otherwise specified, all material rates shall be inclusive of all taxes, duties, levies,
royalty/seigniorage, transportation and handling costs up to project area.

For sand, gravel , murum, stones , course aggregates etc, the rates are to be fixed for
delivery at Quarry, adding seigniorage ( royality) charges, loading charges by machinery /
manual means and idle hire charges of machinery

(as per table under chapter

conveyance or lead and lift charges), as applicable.

For earth/ soil for embankment works from borrow areas, which is not included in the
material list of schedule of rates, seigniorage charges are to be added separately,if
applicable.

For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs, the rates are
to be taken prevailing at major commercial centre near project area. The lead charges, as
applicable are to be added in preparing estimates.

The specifications of the aggregates for sizes and gradation and its adoption shall be as
per IS 383.

6) The labour component in the data is mentioned for unit work.

No allowance towards labour importation and labour amenities added extra as they are
included in the recommended overheads.

On Labour Component: Certain additional allowances are added extra to the wages of
labour (,i.e. only on labour component in the work item) in the form of percentage, as
recommended by the Government/Board of chief engineers,due to statutory and other
provisions.

STANDARD DATA USER GUIDELINES

However, If more than one area allowances, such as those for (1) Municipalities (2)
Agency / Tribal areas (3) Industrial areas are applicable for a particular situation, only the
maximum out of the allowable percentages is to be allowed.

7) HIRE CHARGES OF MACHINERY:


The machinery and /or group of machinery for items of works and their output has been
worked based on the availability of machinery generally in the market and working in the the
field successfully, duly considering cycle time, idle time, operator efficiency, type of work etc.

The hire charge of a machinery / equipment is worked out based on the guidelines
published by CWC and BIS codes.

For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH.

8) Lead Charges

The high level committee has recommended to adopt, for conveyance by head load, a
minimum lead of 50 meters and additional lead up to 150 meters in the intervals of 50
meters. Beyond 150 meters lead ,only machinery rates are to be adopted.

The basic item rates provided in the schedule of rates include 50 m or 1 km as initial lead
and no lead charges shall be allowed where the source of material is within the initial
lead specified in item rate. Additional lead charges shall be allowed for the lead
exceeding initial lead specified in the item rate.

The lead charges per unit quantity for conveyance of the materials are worked out,and
included in the schedule of rates in increment of 50 m for head load and in increment of
1 km for mechanical mode.

The rates for lead charges by head load upto 150 meters and by machinery up to 5 km,
shall be cumulative and inclusive of lead charges for preceding lead. For lead beyond 5
km the lead charges shall be worked out on per km basis.

9) Loading and Unloading charges for Materials


The following features are considered:
(a) Loading and unloading charges are not payable for conveyance by head load.
(b) Loading and unloading charges are not payable for conveyance by mechanical
means, for disposal of excavated material unless specified.
(c) The rates for unloading of materials except earth, sand, gravel, coarse aggregate,
rubble, size stone and cut stone, are inclusive of stackingwherever applicable.
10) LIFT CHARGES :

STANDARD DATA USER GUIDELINES

The data includes initial lift charges of 3 meters ,for materials conveyance by head load,
Additional leads in the interval of 1.0 meters are worked out, as additional labour input
and incorporated in the chapter on Lead and lifts .

Where the conveyance / lifting of material is done by mechanical means, lift charges shall
not be considered, as the cycle time of operation of the machine includes lifts involved.

The data and rates for lift charges is cumulative and are inclusive of rates for preceding
lifts also.

11) Wastage of Materials

Cement : No wastage allowance is recommended towards the quantity of cement


used in works, as the wastage is already included in the input and in major works
bulk quantities are used.

steel : The wastage of steel @ 2.5% is allowed for gates and allied structures. For
RCC works the wastage is @2.5% for the reinforcement rods above 36mm did and
@ 5% for rods below 36mm dia. including overlaps, if they are not welded. If welding
is adopted for the reinforcement rods even for below 36mm dia, 2.5% of wastage is
only recommended.

12) Provision for rate for water:The Committee has recommended not considering the water charges in the Irrigation
Project works. But, it may be considered in specific cases as per the site conditions.

13)

In respect of RCC works the rate for cement concrete for 1 cum is worked separately for

all grades based on Indian Standards. The rate for ton is calculated separately and to be added
separately in the estimates of RCC works as a separate item.

14) Soil classification: The Committee recommended to allow uniform classification of soils for all
Departments and data is worked out accordingly.
1. All soils
2. Marshy soil
3. ordinary rock ( not requiring blasting),
4. hard rock
a. hard rock (requiring blasting)
b. hard rock (controlled blasting)
c. removable by chiseling(blasting prohibited)
15) Use of Super Plasticizers and Admixtures:
Concrete admixtures such as Air-Entraining Agent (AEA) / Water reducing agent can be
used advantageously for better quality concrete. The high level committee has
recommended adopting for super plasticizers and admixtures at 0.4% on cement for
concrete work as per MORTH standards for batching plants.
16) Contractors overheads, profit and other provisions:

STANDARD DATA USER GUIDELINES

High Level Committee has recommended to add 14% plus 4% towards VAT or as

applicable on item rate towards overheads labour including importation and amenities &
contractor profits, which includes various items recommended in MORTH.

This also includes 4% of VAT and should be exhibited separately. In the

agreements, it should be mentioned that it will be reimbursed as per actuals. The


provisions allowed in Go Ms. No. 94, I & CAD, Dt. 1-7-03, need not be added separately.
The overhead charges include the following elements:
Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements.
Office furniture, equipment and communications
Expenditure on:
Corporate office of contractor
site supervision
Documentation and as built drawings
Mobilisation/ de-mobilisation of resources
Labour camps with minimum amenities and transportation to work sites.
Light vehicles for site supervision including administrative and managerial requirements.
Laboratory equipment and quality control including field and laboratory testing.
Minor T & P and survey instruments and setting outworks, including verification of line,
dimensions, trial pits and bore holes, where required.
Watch and ward
Traffic management during construction
Expenditure on safeguarding environment
Sundries
Financing Expenditure
Sales/ Turn overtax
Work Insurance/ compensation
17) EXCISE DUTY ON SUPPLIES :

In respect of gates, hoists and allied works excise duty is applicable on the value of
fabricated components supplied to site. Excise duty is not applicable on erection charges.
Further, the excise duty shall not be considered in the rate analysis on material
component, as basic material rates are inclusive of excise duty.
Therefore, excise duty is considered in the rate analysis only on
machinery and labour components required for fabrication of gates and hoists at the
central fabrication yard. It is difficult to determine the machinery and labour components
separately for fabrication and erection.

STANDARD DATA USER GUIDELINES

For the purpose of computation of excise duty to be included in the rate analysis the
machinery and labour components may apportioned at 75 % for central fabrication yard
and 25 % for field erection and commissioning. Therefore, 75 % of the machinery and
labour components may be considered for assessing the extent of excise duty to be
added in the rate analysis.

18) DEWATERING & DESILTING:


The High level committee considering the local conditions of rainfall / seepage has
recommended towards de-watering and de-silting at 3 percent on the relevant work
component for which dewatering is required.
It is also proposed as per CWC guidelines; to keep a condition in the agreements shall be
incorporated, to fix a ceiling of 5% in extreme cases, with the specific approval of chief
engineer/Government.

19) Computerization of Data:

A software program is developed by the SPI Unit(Irrigation), which facilitates automatic

changes and generation of unit rates, based on basic input rates of Labour, materials and capital
cost of machinery.

A soft ware tool is also developed for auto preparation of estimates based on in put

quantities.

Other Departments are also advised to develop such program.

20) For each chapter separate additional details are incorporated for clarity.
USER GUIDELINES OF REVISED STANDARD DATA

i)

Please select the item of work, as given in Index Code, and view the relevant data.

ii)

The common data items like, lead, lift, conveyance and manual excavation (without involving
contracting agencies) is applicable to all Departments (volume-1)

iii) The departments have to adopt the relevant data from other Departments, if such works are
executed by them
iv) The unit rate /hire charges, of machinery not covered in the Irrigation data, the MORTH data
may be taken with the approval of Board of Chief Engineers
v)

For Drinking water Supply works(PART-IV), the data incorporated is generally applicable
only for manual means of execution. The rates deploying machinery have to be worked out
by the Board of Chief engineers and approved for adoption.

STANDARD DATA USER GUIDELINES

ROLE OF CENTRAL COMPETENT AGENCY FOR SCHEDULE OF RATES


( BOARD OF CHIEF ENGINEERS)
a)
The Board Of Chief Engineers under the chairman ship of Engineer-in-chief,
(administration) I&CAD Department is the competent authority to finalise and recommend the Schedule of
Rates applicable for all engineering Departments. The board has to assess and incorporate only the three
basic inputs required to generate unit work item rates as below.
Basic rates of labour:
Wages of labour commonly required in execution of works has to be arrived and incorporated in the
schedule of rates ( Basic Input Of Labour Wages), without adding extra towards area allowances ( like
municipality allowance, tribal area and ghat road allowances etc, which shall be added to the rates where
applicable in the form of separate percentage as explained in the preceeding paras. The rates shall be the
prevailing daily rates in the State and shall not be less than the minimum wages fixed by the
Government from time to time.
Materials rates:
The basic input material rates common to all departmental works are listed out and
incorporated (in the chapter Basic inputs) The
material specifications adopted shall confirm to
Standards published by the BIS The Prevailing market rates for all basic input materials shall be obtained
from the major commercial centers near the project areas. Average of the rates, ignoring freak rates, shall
be reckoned as the prevailing market rate. Unless otherwise specified, all material rates shall be inclusive
of all taxes, duties, levies, royalty, transportation and handling costs up to project area. For sand, gravel,
murrum, stones , aggregates etc, the rates are For delivery at Quarry including seigniorage, loading
charges and idle hire charges. For steel, Cement, AC sheets, GI sheets, Hume pipes, wood and stone slabs,
the rates prevailing at major commercial centre near project area has to be adopted.
Use rate of machinery:
The third parameter for incorporation in the Basic Inputs, is the use rate
of machinery. To arrive at the use rate of machinery, the inputs to be
incorporated are

The list and capital cost of machinery required to be used in the construction activity, The rate
has to be obtained from major manufacturers and outlet sources and the rate shall be the current market
price inclusive of all taxes, duties and freight charges.

The prevailing fuel charges of petrol and diesel are ascertained and average rate adopted

Borrow rate of interest as fixed by the Government/competent authority be indicated.

For the other machinery not covered by the list, the R&B and other users may adopt hire
charges as recommended by the MORTH
b)
The Chairman, Board of Chief Engineers or competent authority
appointed by the Government, based on the approved basic inputs, load the above three basic
parameters in the software program. The unit rate of all works including hire charges of all machinery will
be generated automatically for adoption.
He shall communicate the uniform Schedule of rates arrived from Standard Data, to all users for
uniform and direct adoption in all infrastructure Departments, as applicable

STANDARD DATA BOOK BUILDING WORK ITEMS BASIC APPROACH

Basic approach and General conditions and assumptions for the preparation of Standard Data
Book for Building Works.

The Basic approach for the preparation of Standard Data for Building works is indicated as under.

1. Description of Items: The description of items is given briefly and linked with the relevant
specifications in AP Standard Specifications.
2. Use of Machinery: For concrete work mixing is proposed with machinery as well as
manually. For laying concrete, lifting is proposed with either by winches or machinery.
Manual means have been proposed for all other items.
3. Working Conditions: The inputs for the Data have been analyzed for the average working
conditions prevailing in the state.
4. Over Heads : This is assumed to include interalia the following elements:
i.

Site accommodation, setting up plant, access road, water supply, electricity and general
site arrangements

ii. Office furniture, equipment and communications


iii. Provision towards expenditure on:
(a) Corporate office of contractor
(b) Site supervision
(c) Documentation and "as built" drawings
iv. Mobilisation / de-mobilisation of resources .
v. Labour camps with minimum amenities required as per labour laws and transportation
to work sites
vi. Light vehicles for site supervision including administrative and managerial requirements
vii. Setting up of Laboratories for quality control, field and laboratory testing for control of
quality of various items of work and documentation of test results as per requirement of
the Specifications.
viii. Minor T&P including vibrators for concrete work and survey instruments and setting
outworks, including verification of line,

dimensions, taking trial pits and bore holes,

where required.
10

STANDARD DATA BOOK BUILDING WORK ITEMS BASIC APPROACH

ix. Watch and ward


x. Arraignment for Traffic and Traffic Management during construction.
xi. Provision towards safeguarding environment
xii. Sundries
xiii. Financing expenditure of the Contractor
xiv. Work Insurance / compensation.
4.1 Sales/Turnover Tax / VAT: Allow 4% and which should be exhibited separately. In
agreements it should be mentioned that it will be reimbursed as per actuals.
5. Contractors Profit : It is considered to allow 14% towards over head charges (Item 4) and
Contractor Profits put together.
6. General :
a) The AP Standard Specifications shall be followed with relevant BIS Specifications of
various materials and construction work.
b) The sources of all materials and samples of materials are required to be approved by the
Engineer-in- Charge before starting of the work.
c) For reinforced steel both HYSD and TMT bars continuing to IS 1786 and MS bars upto 36
mm dia as per IS 432 Part 1 have been considered.
d) The Data includes inputs for testing of soil, materials and works.
e) The contractor shall arrange and to provide and maintain an adequate equipped field
laboratory.
f)

Quality Control of Works shall be governed by relevant AP Standard Specifications read


with BIS Specifications.

g) Sundries to cater for unforeseen contingency and miscellaneous items have been added
in the overheads.
h) The various activities of works shall also be documented in photographs and video
cassettes.
i)

The Data for various Earth Work Excavation Items including classification of soils shall be
as in Standard Data for Roads and Bridges.

j)

The course and fine aggregates shall conform to IS : 383


11

STANDARD DATA BOOK BUILDING WORK ITEMS BASIC APPROACH

7. Basic Inputs :
Standard Data Book is based on the requirements of basic inputs of materials, labour and
machineries for various items. The rates for labour, material and usage charges of machinery
for the area where the project is located are to be ascertained from local authorities/enquiries
to prepare Schedule of Rates for the area. The basic rates of materials, such as, stone
boulders, stone for masonry, stone ballast, stone dust, moorum, gravel, lime, manure,
sludge, quarry sweep, kankar, bricks, brick ballast, crushed slag, etc. at quarry / crusher sites
shall be fixed by the Board of Chief Engineers yearly (effective from 1st June to 31st May).
However, the basic rate of materials hand broken / machine broken, crushed aggregates
shall be based on Analysis in Chapter 1 of Roads & Bridges. The cost of materials should
include the cost at source and the cost of their carriage (as per Schedule of rates arrived in
Chapter 1 of Roads & Bridges for conveyance, loading and unloading charges) upto the work
site.
8. Labour
The labour wages should be as per rates fixed by the Board of Chief Engineers keeping the
minimum wages fixed as per Minimum Wages Act. Skilled labour include mason, carpenter,
blacksmith, mechanics and other trades.
9. Materials :
Quantities of materials considered in the rate analysis are approximate for the purpose of
estimation and include normal wastages. Actual consumption would depend on mix design.
The rates of material should include basic cost at locations of stone crushers/factory/rail head
and cost of its carriage to the site of work/plant including loading, unloading and stacking.
Credit for Dismantled Material: The dismantled materials should be examined and a realistic
assessment made for credit for such materials, which can be utilized for works or auctioned.
The basic rates should include all octroi charges, toll tax, sale tax, VAT, municipal taxes and
other local taxes, etc.
10. The Data for the following items of work shall be as per Data Items covered in AP Standard
Data for Roads & Bridges
i. Loading, Unloading, Carriage, Crushing of Materials
ii. Site Clearance
iii. Earth Work Items including classification of Excavated Material.
iv. Horticulture
12

STANDARD DATA BOOK BUILDING WORK ITEMS BASIC APPROACH

11. Concrete Items :


For Concrete Work, the Grades of Concrete covered by Data Book is in accordance to IS 456 :
2000. The nominal mix of concrete shall be used upto M 20 Grade only. For RCC Work, M 20
Grade nominal mix may be used in exceptional cases of Remoteness. The design mix shall
invariably used for M 20 and above Grades of Concrete as per IS 456 : 2000. The Data
accounts for inputs of Material by Weight and use of ordinary mixture or ordinary mixer with
weight batch arrangement. The Hire charges for vibrators are included in overhead charges.
10% extra cement may be provided for concreting under water, where ever required. Steel
requirement of cement concrete work is required to be provided separately.
12. Plants and Equipment : The usage charges for machines include ownership charges, cost of
repair and maintenance including replacement of tyres and running and operating charges
which includes crew, fuel and lubricants. The hire charges shall be worked out based on the
Guidelines issued CWC for machinery covered in CWC Guidelines.
13. Measurement and Rates
Measurement of various items and their units shall be as defined in the respective Clauses
of AP Standard Specifications. The rates for various items of work shall include all sub items
defined in the respective Clauses of AP Standard Specifications.
14. Privileged Document
The Standard Data Book is for Department use only. It should not be produced in any court of
law as reference/ authority and to that extent it is a privileged document.

13

STANDARD DATA BOOK BUILDING WORK ITEMS

Andhra Pradesh Standard Data


BUILDINGS
Index-code
BLD-CSTN1
BLD-CSTN1-1

BLD-CSTN1-2

BLD-CSTN1-3

BLD-CSTN1-4

Sl
No
1

Description

Unit

Quantity

kg.
cum
cum

1440.00
1.05
1.05

Rate
Rs.
5

Amount
Rs.
6

Rem
arks
7

MORTARS
1

Cement Mortar (1 : 1)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 1.5)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 2)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 3)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:

day

0.20

kg.
cum
cum

960.00
1.05
1.05

day

0.20

kg.
cum
cum

720.00
1.05

day

0.20

kg.
cum
cum

480.00
1.05
1.05

14

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN1-5

BLD-CSTN1-6

BLD-CSTN1-7

BLD-CSTN1-8

Man mazdoor for mixing mortar


Grand Total
Cement Mortar (1 : 4)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 5)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 6)

Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Cement Mortar (1 : 8)
Unit : 1cum
A. MATERIALS:
Cement
Sand (including 5% wastage)
Seigniorage charges for sand
B. MACHINERY
- Nil C. LABOUR:
Man mazdoor for mixing mortar
Grand Total
Excavation for Foundations

day

0.20

kg.
cum
cum

360.00
1.05
1.05

day

0.20

kg.
cum
cum

288.00
1.05
1.05

day

0.20

kg.
cum
cum

240.00
1.05
1.05

day

0.20

kg.
cum
cum

180.00
1.05
1.05

day

0.20

15

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN2

BLD-CSTN2-1

Earth work excavation for foundations and


depositing on bank for all lifts and with an
initial lead of 10m including all operational,
incidental, labour charges such as shoring
,sheeting, planking, strutting, etc. complete
for finished item of work including
seigniorage excluding dewatering charges etc
as per SS - 20 B (APSS 308).
9

Ordinary Soil-Manual Means-Upto 3 m depth


Unit = cum
Taking output = 10 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

3.64

b&c) Overheads & Contractors Profit


Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of
labour cost. Assessment for dewatering shall be made as per site conditions.
BLD-CSTN2-2

10

Ordinary soils-Mechcanical Means-Upto 3 m


depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

8.32

hour

6.00

b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.
BLD-CSTN2-3

11

Ordinary Soils-Mechcanical Means-3 m to 6


m depth
Unit = cum
Taking output = 210 cum
a)

Labour

Mate

day

day

8.32

hour

6.00

Mazdoor (Unskilled)
b)

Machinery

Hydraulic excavator 1.0 cum bucket capacity


c&d) Overheads & Contractors Profit
Cost for 210 cum = a+b+c+d

16

STANDARD DATA BOOK BUILDING WORK ITEMS

Rate per cum = (a+b+c+d)/210


Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where required.
Assessment for dewatering shall be made as per site conditions.
BLD-CSTN2-4

12

Ordinary rock (not requiring blasting)-Manual


Means-Upto 3 m depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

5.20

b&c) Overheads & Contractors Profit


Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : Cost of dewatering upto 5 per cent of labour cost may be added, where
required as per site condition.
BLD-CSTN2-5

13

Ordinary rock (not requiring blasting)Mechanical Means-Upto 3 m depth


Unit = cum
Taking output = 180 cum
a) Labour
Mate

day

Mazdoor (Unskilled)

day

6.24

hour

6.00

b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to
10 per cent of labour cost. Assessment for dewatering shall be made as per site
conditions.

BLD-CSTN2-6

14

Hard rock (requiring blasting)-Upto 3 m


depth
Unit = cum
Taking output = 10 cum
a) Labour
Mate

day

Driller

day

0.50

Blaster

day

0.25

Mazdoor (Unskilled)

day

8.35

hour

b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack
hammers for drilling at 15 cum per hour
c) Material

17

STANDARD DATA BOOK BUILDING WORK ITEMS

Gelatin 80%

kg

3.50

Nos.

14.00

Mate

day

Mazdoor (Unskilled)

day

5.20

hour

6.00

Mate

day

Mazdoor (Unskilled)

day

0.31

cum

1.00

Detonator electric
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of
(a+b) may be added, where required as per
site condition.
BLD-CSTN2-7

15

Hard rock (blasting prohibited)-Upto 3 m


depth
Unit = cum
Taking output = 10 cum
a) Labour

b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack
hammers of pneumatic breaker at 1 cum per
hour
c) & d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10
Note : Cost of dewatering up to 5 per cent of
(a+b) may be added, where required as per
site conditions.
Filling with useful available excavated earth
(excluding rock) in trenches, sides of
foundations and basement with initial lead in
layers not exceeding 15 cm thick,
consolidating each deposited layer by
watering and ramming including cost and
conveyance of water to work site and all
operational, incidental, labour charges, hire
charges of T & P etc., complete for finished
item of work. (APSS NO. 309 & 310)
BLD-CSTN2-8

16

Sand filling
Unit = cum
a) Labour

b) Material
Sand
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
BLD-CSTN2-9

17

Earth filling (ordinary soil)


Unit = cum
18

STANDARD DATA BOOK BUILDING WORK ITEMS

Taking output = 6 cum


a) Labour
Mate

day

Mazdoor (Unskilled)

day

3.12

b) & c) Overheads & Contractors Profit


Cost for 6 cum = a+b+c
Rate per cum = (a+b+c)/6
Note : Cost of transportation of good quality earth has not been included. Only
labour for carrying carted earth with a lead of 50 m to the foundation pits has been
taken in the rate. The cost of carted earth/ sand may be worked out separately if
the same is not available from the adjoining area.
BLD-CSTN3
BLD-CSTN3-1

18

CONCRETE, DAMP PROOF COURSE &


REINFORCEMENT
Plain Cement concrete Grade M20 - Nominal
Mix
using 20mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 20mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

Kg
cum
cum
cum
cum

400.00
0.90
0.45
0.90
0.45

day

0.10

Mazdoor (unskilled)
day
Water (including for curing)
kl
Grand Total
Note : For Nominal Mix : Considering table 9 IS 456 :
2000, the quantity of cement needed is 405 kgs / cum.
Hence proposed 400 kgs of cement for cum of CC M20
BLD-CSTN3-2

19

Plain Cement concrete Grade M10 - Nominal


Mix upto Plinth level
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
Grand Total

2.36
1.20

Kg
cum
cum
cum
cum
kl

220.00
0.90
0.45
0.90
0.45
1.20

hour

1.00

day

0.10

day

1.39

19

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN3-3

BLD-CSTN3-4

BLD-CSTN3-5

BLD-CSTN3-6

20

21

22

23

PCC Grade M15 - Nominal mix 1:2.5:5 (Hand


mixing)
Unit = 1cum
A) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
Water (including for curing)
B) Labour
Mason (1st Class)
Mazdoor (Unskilled)
Grand Total
Plain Cement concrete (1:4:8) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:4:8) using 40 mm
metal with concrete mixture.
All work
upto plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
Water Charges 1%
Grand Total
Plain Cement concrete (1:5:10) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement

kg
cum
cum
cum
cum
kl

275.00
0.48
0.54
0.27
0.09
1.20

day
day

0.10
2.36

kg
cum
cum
cum
cum
kl

162.00
0.90
0.45
0.90
0.45
1.20

day

0.10

day

2.36

kg
cum
cum
cum
cum
kl

162.00
0.90
0.45
0.90
0.45
1.20

hour

1.00

day

0.10

day

1.39
-

kg

129.60
20

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN3-7

BLD-CSTN3-8

BLD-CSTN3-9

24

25

26

Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class

cum
cum
cum
cum
kl

0.90
0.45
0.90
0.45
1.20

day

0.10

Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:5:10) using 40 mm
metal with Concrete mixture. All work upto
plinth level.
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

day

2.36

kg
cum
cum
cum
cum
kl

129.60
0.90
0.45
0.90
0.45
1.20

hour

1.00

day

0.10

day

1.39

kg
cum
cum
cum
cum
kl

129.60
0.90
0.54
0.90
0.54
1.20

day

0.10

day

2.36

kg
cum
cum
cum
cum
kl

129.60
0.90
0.54
0.90
0.54
1.20

Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with hand mixing upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class
Mazdoor (unskilled)
Grand Total
Plain Cement concrete (1:6:10) using 40 mm
metal with Concrete mixture upto Plinth level
Unit = 1cum
A. MATERIALS:
Cement
Coarse aggregate 40 mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)

21

STANDARD DATA BOOK BUILDING WORK ITEMS

B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

BLD-CSTN3-10

27

Mazdoor (unskilled)
Grand Total
Plain Cement concrete - Nominal Mix (1:3:6)
using 40mm metal with hand mixing
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. LABOUR:
st
Mason 1 class

BLD-CSTN3-11

28

Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 20) Nominal Mix
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

BLD-CSTN3-12

29

Mazdoor (unskilled)
Grand Total
Plain Cement concrete (M 15) Nominal Mix
1:2.5:5
using 40mm metal using concrete mixer
Unit : 1cum
A. MATERIALS:
Cement
Coarse aggregate 40mm
Coarse aggregate 20mm
Coarse aggregate 10mm
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A

hour

1.00

day

0.10

day

1.39

Kg
cum
cum
cum
cum
kl

220.00
0.90
0.45
0.90
0.45
1.20

day

0.10

day

2.36

Kg
cum
cum
cum
cum
kl

330.00
0.90
0.45
0.90
0.45
1.20

hour

1.00

day

0.10

day

1.39

Kg
cum
cum
cum
cum
cum
cum

275.000
0.540
0.270
0.090
0.480
0.900
0.480
22

STANDARD DATA BOOK BUILDING WORK ITEMS

Water (including for curing)


B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

BLD-CSTN3-13

30

Mazdoor (unskilled)
Grand Total
R.C.C. M-20 Nominal Mix

kl

1.20

hour

1.000

day

0.100

day

1.390

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.133
0.267
3.600

hour

1.000

hour
kl

1.000
1.200

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.167
0.167
4.700

RCC M- 20 Nominal mix (Cement:fine


aggregate: coarse aggregate) corresponding
to Table 9 of IS 456 using 20mm size graded
machine crushed hard granite metal (coarse
aggregate) from approved quarry including
cost and conveyance of all materials like
cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including
Seigniorage charges, sales & other taxes on
all materials including all operational,
incidental and labour charges such as
machine mixing, laying concrete, curing
etc.,complete but excluding cost of steel and
its fabrication charges for finished item of
work, but excluding centering, shuttering.
A

FOUNDATIONS, PLINTH, PEDESTALS (Below


Plinth)
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
C. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
COLUMNS, LINTELS, WATER TANKS, RCC
WALLS IN BUILDINGS
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
C. MACHINERY

23

STANDARD DATA BOOK BUILDING WORK ITEMS

31

BLD-CSTN3-14

Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)


capacity
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
RCC SLABS, BEAMS
A. MATERIALS:
20mm HBG graded metal
Sand
Cement
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men and Women)
C. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
DESIGN MIX CONCRETE (WEIGH BATCH at
SITE)
Supply and placing of the Design Mix
Concrete corresponding to IS 456 using
WEIGH BATCHER / MIXER with 20mm size
graded machine crushed hard granite metal
(coarse aggregate) from approved quarry
including cost and conveyance of all
materials like cement, fine aggregate (sand)
coarse aggregate, water etc., to site and
including Seigniorage charges, sales & other
taxes on all materials including all
operational, incidental and labour charges
such as weigh batching, machine mixing,
laying concrete, curing etc.,complete but
excluding cost of steel and its fabrication
charges for finished item of work (APSS No.
402)with minimum cement content as per IS
code from standard suppliers approved by
the
department
including
pumping,
centering, shuttering, laying concrete,
vibrating, curing etc. complete but excluding
cost of steel and its fabrication charges for
finished item of work.
FOUNDATIONS, PLINTH, PEDESTALS (Below
Plinth)
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal
Sand
B. LABOUR:
1st Class Mason

hour

1.000

hour
kl

1.000
1.200

cum
cum
Kgs

0.900
0.450
400.000

day
day
day

0.067
0.133
2.500

hour

0.267

hour
kl

0.267
1.200

Excluding Cement cost

cum
cum

0.80
0.40

day

0.133
24

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN3-15

BLD-CSTN3-16

BLD-CSTN3-17

2nd Class Mason


Mazdoor (Both Men & Women)
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing)
charges
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
COLUMNS, LINTELS, WATER TANKS, RCC
WALLS IN BUILDINGS
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal
Sand
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing)
charges
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
RCC SLABS, BEAMS
ANY GRADE OF MIX
A. MATERIALS:
20mm HBG graded metal
Sand
B. LABOUR:
1st Class Mason
2nd Class Mason
Mazdoor (Both Men & Women)
C. MACHINERY
Weigh Batcher Hire charges (Machine mixing)
charges
Vibrator hire charges
Water (including for curing)
BASIC COST per 1 cum
DESIGN MIX CONCRETE (BATCHING PLANT at
site)
FOUNDATIONS, PLINTH, PEDESTALS (Below
Plinth)
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY

day
day

0.267
4.600

hour

1.333

hour
Kl

1.333
1.200

cum
cum

0.80
0.40

day
day
day

0.167
0.167
5.600

hour

1.333

hour
kl

1.333
1.200

cum
cum

0.80
0.40

day
day
day

0.067
0.133
3.077

hour

0.308

hour
kl

0.308
1.200

cum
cum
cum
cum
kl

0.80
0.40
0.80
0.40
1.20

25

STANDARD DATA BOOK BUILDING WORK ITEMS

Batching plant at 20 cum per hour


Transit mixer 4cum capacity for lead upto
1km
Concrete Pump
C. LABOUR:
st
Mason 1 class

hour
hour

0.222
0.222

day

0.222

day

0.056

Mason 2 class

day

0.056

Mazdoor (unskilled)
Grand Total
Note : Wherever concrete is carried out using
batching plant, transit mixer, concrete pump,
then Admixtures @ 0.4% of weight of cement
may be added for achieving desired slump of
concrete. If concentrated Admixture is
proposed, only 0.04% of weight of Cement
shall be used.

day

0.917

cum
cum
cum
cum
kl

0.80
0.40
0.80
0.40
1.20

hour
hour

0.444
0.444

day

0.444

nd

BLD-CSTN3-18

BLD-CSTN3-19

COLUMNS, LINTELS, WATER TANKS, RCC


WALLS IN BUILDINGS
Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto
1km
Concrete Pump
C. LABOUR:
st
Mason 1 class

day

0.111

nd

Mason 2 class

day

0.222

Mazdoor (unskilled)
Grand Total
RCC SLABS, BEAMS

day

1.556

cum
cum
cum
cum
kl

0.80
0.40
0.80
0.40
1.20

hour
hour

0.133
0.133

day

0.133

day

0.033

day

0.067

Unit : 1cum
A. MATERIALS:
Coarse aggregate 20mm graded
Fine aggregate (Sand)
Seigniorage charges for C.A
Seigniorage charges for F.A
Water (including for curing)
B. MACHINERY
Batching plant at 20 cum per hour
Transit mixer 4cum capacity for lead upto
1km
Concrete Pump
C. LABOUR:
st
Mason 1 class
nd

Mason 2 class

26

STANDARD DATA BOOK BUILDING WORK ITEMS

Mazdoor (unskilled)
day
Note : Quantity of cement proposed for various
design mixes is for estimating purpose only. Actual
quantity of cement will be as per approved mix design.
Similarly quantity for coarse and fine aggregates is for
estimating purpose and the exact quantity shall be as
per the mix design. Nominal mix of grades M20 is to
be used with adequate supervision and quality control
requirements.
For Design mix concrete, allow Cement as
follows (for estimate purpose only) :

BLD-CSTN3-20

32

33

Grade

Kgs

M 20
M 25
M 30
M 35
M 40

350
380
400
420
430

Damp proof course 40mm thick with cement


concrete (1:2:4 Nominal mix), using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials,
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)
Unit = 25 sqm
A. MATERIALS:
Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
Seigniorage charges of sand
Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

BLD-CSTN3-21

0.433

Mazdoor (unskilled)
D. Grand Total for 25 sqm
Rate per Sqm = D/25
Damp proof course 50mm thick with 1:2:4
cement concrete Nominal mix, using 12mm
hard broken stone aggregate including cost
of all materials, seigniorage charges,
excluding conveyance charges of materials
including the cost of machinery, labour
charges, mixing, placing in position, leveling,
vibrating, curing etc. complete for finished
item of work. (Using concrete mixer)

kgs
cum
cum
cum
cum
L.S.

320.00
0.90
0.45
0.90
0.45

hour

1.00

day

0.1

day

1.98

Unit = 20 sqm
A. MATERIALS:
27

STANDARD DATA BOOK BUILDING WORK ITEMS

Cement
Coarse aggregate 12mm
Fine aggregate (sand)
Seigniorage charges of coarse aggregate
Seigniorage charges of sand
Form work
B. MACHINERY
Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum)
capacity
C. LABOUR:
st
Mason 1 class

BLD-CSTN4-1

34

35

Mazdoor (unskilled)
D. Grand Total for 20 sqm
Rate per Sqm = D/20
Supplying, fitting and placing HYSD bar
reinforcement in foundation complete as per
drawings and technical specifications for Bars
below 36 mm dia including over laps and
wastage, where they are not welded
Unit = MT
(a) Material
HYSD bars including 5 per cent for overlaps
and wastage
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
Sundries on Material
Rate per t = a+b+c+d
Supplying, fitting and placing HYSD bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints /
ton)
Welding Charges (Hire charges of Welding
Machine)
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)

kgs
cum
cum
cum
cum
L.S.

320.00
0.90
0.45
0.90
0.45

hour

1.00

day

0.1

day

1.98

MT

1.05

kg

6.00

day
day

2.00
6.40

1.025

each

70.000

Hr

10.00

kg

6.00

day
day
day

2.50
2.00
6.40

28

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN4-2

36

37

Rate per t = a+b+c+d


Supplying, fitting and placing TMT bar
reinforcement in VRCC works complete as
per drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded.
Unit = t
(a) Material
TMT bars including 5 per cent for overlaps
and wastage
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
Supplying, fitting and placingTMT bar
reinforcement in VRCC works complete
including wastage, as per drawings and
technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars
36 mm dia and above, where welding
required to be done compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage

BLD-CSTN4-3

38

Welding Electrodes @ 5 per joint (14 joints /


ton)
Welding Charges (Hire charges of Welding
Machine)
Binding wire
(b) Labour for cutting, bending, shifting to
site, tying and placing in position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
Supplying, fitting and placing MS bar
reinforcement in VRCC works complete as
per drawings and technical specifications for
Bars below 36 mm dia including over laps and
wastage, where they are not welded
Unit = t
(a) Material
MS bars including 5 per cent for overlaps and
wastage
Binding wire

1.05

kg

6.00

day
day

2.00
6.40

1.025

each

70.000

Hr

10.00

kg

6.00

day
day
day

2.50
2.00
6.40

1.05

kg

6.00
29

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN5
BLD-CSTN5-1

(b) Labour for cutting, bending, shifting to


site, tying and placing in position
Blacksmith / Bar bender
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
Rate per t = a+b+c+d
BRICK WORK, HONEY - COMBWORK
39

day
day

2.00
6.40

kg
Nos

96.00
512.00

cum
cum

0.20
0.20

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Note : For Bricks 2.4 % wastage taken.
Brick Masonry in CM (1:4) with Bricks
traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

day

1.89

kg
Nos

72.00
512.00

cum
cum

0.20
0.20

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Bricks
traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

day

1.89

kg
Nos

57.60
512.00

cum
cum

0.20
0.20

Brick Masonry in CM (1:3) with Bricks with


traditional size 23 x 11 x 7 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

BLD-CSTN5-2

40

nd

BLD-CSTN5-3

41

day

0.24

nd

Mason 2 class

day

0.56

Mazdoor (unskilled)

day

1.89

30

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN5-4

42

Grand Total
Brick Masonry in CM (1:6) with 2nd class
Bricks traditional size 23 x 11 x 7 cms
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

kg
Nos

48.00
512.00

cum
cum

0.20
0.20

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Bricks
traditional size 23 x 11 x 7 cms 2nd Class
Unit = 1cum
A. MATERIALS:
Cement
Bricks traditional size 23 x 11 x 7 cms 2nd
class
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

day

1.89

kg
Nos

36.00
512.00

cum
cum

0.20
0.20

day

0.24

day

0.56

nd

BLD-CSTN5-5

43

nd

Mason 2 class

BLD-CSTN5-6

44

Mazdoor (unskilled)
day
Grand Total
Note : 1. When Mortar mix is changed as CM 1:4, 1:5,
1:6 and 1:8, proportionate quantity of cement has to
be substituted. No change in other data.
2. When First class Modular Bricks are used provide
570 nos bricks of size 19 x 9 x 9 cms.
Brick Masonry in CM (1:3) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
kg
Bricks modular size 19 x 9 x 9 cms 2nd class
Nos
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

45

100.60
520.00

cum
cum

0.21
0.21

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:4) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:

day

1.89

nd

BLD-CSTN5-7

1.89

31

STANDARD DATA BOOK BUILDING WORK ITEMS

Cement
Bricks modular size 19 x 9 x 9 cms 2nd class

kg
Nos

75.60
520.00

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

cum
cum

0.21
0.21

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:5) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class

day

1.89

kg
Nos

60.48
520.00

cum
cum

0.21
0.21

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:6) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class

day

1.89

kg
Nos

50.40
520.00

cum
cum

0.21
0.21

day

0.24

Mason 2 class

day

0.56

Mazdoor (unskilled)
Grand Total
Brick Masonry in CM (1:8) with Modular
Bricks 19 x 9 x 9 cms 2nd class
Unit = 1cum
A. MATERIALS:
Cement
Bricks modular size 19 x 9 x 9 cms 2nd class

day

1.89

kg
Nos

37.80
520.00

cum
cum

0.21
0.21

nd

BLD-CSTN5-8

46

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

BLD-CSTN5-9

47

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

BLD-CSTN5-10

48

Fine aggregate (Sand)


Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

day

0.24

Mason 2 class

nd

day

0.56

Mazdoor (unskilled)

day

1.89
32

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN5-11

49

Grand Total
11.5 cm wide Brick masonry for superstructure on ground floor in cm (1:3) using
second class traditional size bricks including
cost of all materials, seigniorage charges,
labour and all operations for constructing
half brick masonry, mixing cement mortar,
curing etc., complete for finished item of
work, but excluding conveyance charges of
materials.
unit:10sqm
A. MATERIALS:
Country bricks, second class traditional size
23x11x7cm
Cement
Sand
Seigniorage charges for sand
B. LABOUR:
st
Mason 1 class

nos

565.000

kg.
cum
cum

106.000
0.220
0.220

day

0.600

Mason 2 class

day

0.600

Mazdoor (unskilled)
Add water charges 1%
Grand Total
Reinforced Brick Masonary walls of 11.5cm in
CM(1:6) using 2nd bricks having a crushing
strength of not less than 35.00kg/cm2 and
using two mild steel bars of 6m dia in every
third layer of brick masory, with free joints of
the main block work including cost and
seignorage charges and conveyance of all
materials and water from approved sources
to work site and all operational, incidental,
labour charges such as scaffolding mixing
mortor constructing masonary lift charges,
curing etc. complete but excluding the cost of
steel and its fabrication charges for finished
item of work as per SS 509

day

2.750
1.00%

Nos
cum

512.000
0.200

nd

BLD-CSTN5-12

50

Ground Floor :
A. MATERIALS:
II Class Bricks
C.M.(1:6)
B. LABOUR:
st
Mason 1 class

day

0.600

Mason 2 class

nd

day

0.600

Mazdoor (unskilled)
Grand Total

day

2.750

33

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN5-13

51

Exposed brick masonry for super structure on


ground floor in cm (1:6) using wire cut bricks
or moulded bricks including making
horizontal and vertical grooves 10mm Wide
12mm deep, cost of all materials, seigniorage
charges, labour and all operations, mixing
cement mortar, curing etc., complete for
finished item of work, but excluding
conveyance charges of materials
unit:1cum
A. MATERIALS:
Wire cut bricks or moulded bricks size
19x9x9cm
Cement
Sand
Seigniorage charges for sand
B. LABOUR:
st
Mason 1 class

nos

520.000

kg.
cum
cum

48.00
0.20
0.20

day

0.57

Mason 2 class

day

0.57

Mazdoor (unskilled)
Add water charges 1%
Grand Total
Note : Compressive strength of individual
2
Brick shall not be less than 70 kg / cm

day

2.54
1.00%

nd

BLD-CSTN5-14

BLD-CSTN5-15

52

53

Brickwork in arches in cement mortar 1:4


complete including centering and shuttering
excluding pointing and plastering as per
drawing and technical specifications Clauses
606 and 1205.1 MORD
Unit = cum
a) Material
Wire cut bricks or moulded bricks size
Nos.
525.00
19x9x9cm
Cement mortar (1:4)
cum
0.24
b) Labour
Mazdoor (Unskilled)
day
1.88
Mason (1st Class)
day
2.00
c) Add for centering and shuttering @ 110%
of (a+b)
Grand Total
Note : 1 ) In case cement mortar 1:3 is used, proportionate rate is to be adopted.
2) Quantity of bricks for arches will be about 10 per cent more than that for
ordinary brickwork .
3) In case special arch bricks are used, the quantity of bricks per cum shall be taken
as 580 Nos.
4) Rates for spandrel walls shall be taken same as for brickwork in substructure.
5) Rate for spandrel filling will depend on the filling material adopted
Honey Comb work with Bricks of traditional
Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
34

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN5-16

BLD-CSTN5-17

54

55

BLD-CSTN6
BLD-CSTN6-1

56

a) Material
Brick 2nd class 23 x 11 x 7
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Honey Comb work with Bricks of Modular
Size and Plastered One Coat 10 mm. thick
Cement Mortar 1:5 including White Washing
2 Coats
Unit = cum
a) Material
Brick 2nd class 19 x 9 x 9
Cement mortar (1:5)
b) Labour
Mazdoor (Unskilled)
Mason (1st Class)
Mason (2nd Class)
White Washing 2 Coats
Grand Total
Masonry work in CM (1:8) prop with Flyash
Cement solid blocks of size 290 x 225 x 140
mm for manufacturing of flyash solid blocks
using flyash of 80 kgs, cement of 15 kgs.
Gypsum of 5 kgs. and stone dust including
cost and conveyance of all materials, labour
charges, seiniorage charges, scaffolding and
curing etc., cpomplete with a compresive
strength not lessthan 50 kg/sqm for walls for
Superstructure Walls.
Ground Floor
Unit = 1 cum
A. MATERIALS:
No of blocks required for one cum of
Masonry
Cost of Cement Mortar (1:6)
B. LABOUR
Mason 1st class
Mason 2nd class
Man Mazdoor
Woman Mazdoor
Total
STONE MASONRY, DAMP PROOF COURSE,
DRY STONE PACKING, QUARRY RUBBISH &
GRAVEL BACKING
Cut Stone Masonry in CM 1:2
Unit = 1cum
A. MATERIALS:
Cement

Nos.
cum

750.00
0.67

day
day
day
LS

6.60
2.41
6.21
LS

Nos.
cum

790.00
0.67

day
day
day
LS

6.60
2.41
6.21
LS

Nos

110.000

cum

0.100

day
day
day
day

0.420
0.920
0.700
2.100

kg

115.20
35

STANDARD DATA BOOK BUILDING WORK ITEMS

Cut Stone Roughly dressed to shape at quarry

cum

0.89

Bond Stones
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

cum
cum
cum

0.16
0.16
0.16

day

1.05

day

2.45

nd

Mason 2 class

BLD-CSTN6-2

57

Man mazdoor
day
Woman mazdoor
day
Grand Total
Note : When Mortar mix is changed as CM 1:3, 1:4,
1:5, 1:6 and 1:8, proportionate quantity of cement has
to be substituted. No change in other data.
CRS Masonry in CM (1:2) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

BLD-CSTN6-3

58

Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:3) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

BLD-CSTN6-4

59

Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:4) 1st Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)

3.50
2.80

kg
cum
7Nos.

201.60
0.94
0.16

cum
cum
cum

0.28
0.28
1.10

day

2.50

day

2.32

kg
cum
7Nos.

134.40
0.94
0.16

cum
cum
cum

0.28
0.28
1.10

day

2.50

day

2.32

kg
cum
7Nos.

100.80
0.94
0.16

cum

0.28
36

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN6-5

60

Seigniorage charges for F.A


Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

cum
cum

0.28
1.10

day

2.50

Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:6) 1st Sort

day

2.32

kg
cum
7Nos.

67.20
0.94
0.16

cum
cum
cum

0.28
0.28
1.10

day

2.50

day

2.32

kg
cum
cum

76.80
0.94
0.16

cum
cum
cum

0.32
0.32
1.10

day

1.50

Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

BLD-CSTN6-6

61

Mazdoor (unskilled)
Grand Total
CRS Masonry in CM (1:6) 2nd Sort
Unit = 1cum
A. MATERIALS:
Cement
Coursed Rubble Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data.
BLD-CSTN6-7

62

2.32

Coursed rubble stone masonry arch (Ist sort)


in cement mortar (1:4) complete including
centering etc. complete as per drawing and
technical specifications Clauses 706 and
1205.1
Unit = cum
A. Material
Stone for CR masonry 1st sort
Through and bond stone (7
0.24x0.24x0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 II)
B. Labour
Mason (1st Class)

Nos

cum
Nos.

0.94
0.16

cum

0.30

day

3.00
37

STANDARD DATA BOOK BUILDING WORK ITEMS

Mazdoor (Unskilled)
day
C. Add for centering and shuttering @ 100 %
of (a+b)
Grand Total
Note : 1) In case cement mortar 1:3 is used,
proportionate rate is to be adopted.

2.43

2) The addition for centering and sluttering at (c)


above is for arch above 6 m span. For lesser span
length the addition shall be 80 per cent for span above
4 m length and 50 per cent for spans less than 4 m.
BLD-CSTN6-8

63

Ashlar Arch Work in Cement Mortar (1:4)


Unit = 1cum
A. MATERIALS:
Cement
Cut Stone Roughly dressed to shape at quarry

kg
cum

57.60
0.89

cum
cum

0.16
0.16
0.16

day

5.05

Mason 2 class

day

2.45

Mazdoor (unskilled)
Centering Charges
Grand Total
Rubble Arch Work in Cement Mortar (1:4)

day
LS

6.30

kg
cum

100.80
1.15

cum
cum

0.28
0.28

day

0.90

Mason 2 class

day

2.10

Mazdoor (unskilled)
Centering Charges
Grand Total
Providing & Laying
reinforced cement
concrete arch complete including centering
and shuttering excluding reinforcement as
per drawings and technical specifications
Clauses 800, 900 and 1205.1

day
LS

2.43

0.40

Bond Stones of Cutstone quality


Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

BLD-CSTN6-9

64

Unit = 1cum
A. MATERIALS:
Cement
Seleted Stone of sizes as per specification
(including Bond Stones)
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

65

BLD-CSTN6-10

Unit = cum
RCC grade M20 nominal mix
a) Material
Cement

38

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN6-11

66

Coarse sand
20 mm aggregate
10 mm aggregate
b) Labour
Mason (1st Class)
Mazdoor (Unskilled)
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
RCC Grade M 25 (Design mix)

cum
cum
cum

0.45
0.54
0.36

day
day

0.20
2.15

hour

0.40

a) Material
Cement
t
Coarse sand
cum
20 mm aggregate
cum
10 mm aggregate
cum
b) Labour
Mason (1st Class)
day
Mazdoor (Unskilled)
day
c) Machinery
Concrete mixer 0.4/0.28 cum capacity
hour
d) Add for cost of centering and shuttering as
per the rates worked out on relevant data
items
Grand Total
Note : The additional cost of centering and shuttering
@ 50 per cent of cost of material and labour shall hold
good for arch spans of 6 m and above. For lesser
length of spans, the corresponding additional cost can
be taken as 40 per cent for spans above 4 m length
and 30 per cent for spans less than 4 m.
BLD-CSTN6-12

67

68

0.20
2.15
0.40

RR Masonry in CM (1:6)
Unit = 1cum
A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

BLD-CSTN6-13

0.38
0.45
0.54
0.36

Mazdoor (unskilled)
Grand Total
RR Masonry in CM (1:8)

kg
cum
cum
cum

79.20
0.44
0.50
0.16

cum
cum
cum

0.33
0.33
1.10

day

1.20

day

2.00

Unit = 1cum
39

STANDARD DATA BOOK BUILDING WORK ITEMS

A. MATERIALS:
Cement
CR Stone
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Fine aggregate (Sand)
Seigniorage charges for F.A
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

kg
cum
cum
cum

59.40
0.44
0.50
0.16

cum
cum
cum

0.33
0.33
1.10

day

1.20

Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted. No change in
other data
BLD-CSTN6-14

69

Dry Stone Masonry for Retaining Walls


Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

cum
cum

1.04
0.16

cum

1.20

day

0.33

Mason 2 class

day

0.77

Mazdoor (unskilled)
Grand Total
Dry Stone Masonry for Well steining

day

1.10

cum
cum
cum

1.04
0.16
1.20

nd

BLD-CSTN6-15

70

Unit = 1cum
A. MATERIALS:
Rough Stone
Bond Stones
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

day

0.45

Mason 2 class

day

1.05

Mazdoor (unskilled)
Grand Total
Damp Proof, Course Damp Proof (or anti
Proof) Course with Cuddapah / Shabad slabs
50 mm. thick in CM (1:3) (Unit - 10 sqm)

day

1.10

sqm
cum

10.50
0.15

day

0.90

nd

BLD-CSTN6-16

71

2.00

A. MATERIALS:
Cuddapah / Shabad slabs 50 mm. thick
Cement Mortar 1:3
Seigniorage charges for Stone
B. LABOUR:
st
Mason 1 class

40

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN7
BLD-CSTN7-1

BLD-CSTN7-2

72

73

Mason 2 class

nd

day

2.10

Mazdoor (unskilled)
Grand Total
POINTING

day

2.00

kg
cum
cum

14.40
0.03
0.03

day

0.50

day

0.74

kg
cum
cum

14.40
0.03
0.03

day

0.50

day

0.74

kg
cum
cum

28.80
0.06
0.06

day

0.50

Flush Pointing with CM (1:3) to Brick / CRS


Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class
Mazdoor (unskilled)
Grand Total
Flush Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class

BLD-CSTN7-3

74

Mazdoor (unskilled)
Grand Total
Raised Pointing with CM (1:3) to RR Masonry
Unit = 10 sqm
A. MATERIALS:
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class

BLD-CSTN7-4

75

Mazdoor (unskilled)
day
Grand Total
Raised and cut pointing on coursed or Ashlar
stone masonry or concrete block walling in
white cement mortar 1 : 3 (1 white cement :
3 marble dust).
Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
cum
Labour :
Mason llnd class
day
Mazdoor (unskilled)
day
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Note : When Mortar mix is changed as CM 1:4

0.74

0.038
1.460
2.260

41

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN8
BLD-CSTN8-1

proportionate quantity of cement


substituted. No change in other data.
PLASTERING
76

77

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

BLD-CSTN8-3

78

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:5), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

BLD-CSTN8-4

79

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:6), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:6)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

BLD-CSTN8-5

80

to

be

Plastering with CM (1:3), 12 mm thick


Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

BLD-CSTN8-2

has

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:8), 12 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortor (1:5)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

cum
cum

0.15
0.15

day

0.60

day

0.96

cum
cum

0.15
0.15

day

0.60

day

0.96

cum
cum

0.150
0.150

day

0.60

day

0.96

cum
cum

0.15
0.15

day

0.60

day

0.96

cum
cum

0.15
0.15

day

0.60
42

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN8-6

81

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 15 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class

BLD-CSTN8-7

82

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:4), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:4)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class

BLD-CSTN8-8

83

Mazdoor (unskilled)
Grand Total
Plastering with CM (1:3), 20 mm thick
Unit = 10 sqm
A. MATERIALS:
Cement Mortar (1:3)
Seigniorage charges for F.A
B. LABOUR:
nd
Mason 2 class

day

0.96

cum
cum

0.19
0.19

day

0.60

day

0.96

cum
cum

0.210
0.21

day

0.94

day

1.60

cum
cum

0.210
0.21

day

0.94

Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
BLD-CSTN8-9

84

Plastering with CM 2 coats, 20 mm thick,


base coat in CM (1:6), 16mm thick and top
coat in CM (1:4), 4mm thick with Dubara
sponze finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:6), 16 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:4), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class

1.60

kg
cum

43.00
0.18

kg
cum
cum

14.50
0.04
0.22

day

0.63

nd

Mason 2 class

day

1.47

Mazdoor (unskilled)
Grand Total

day

3.90

43

STANDARD DATA BOOK BUILDING WORK ITEMS

Note : When Mortar mix is changed proportionate


quantity of cement has to be substituted
BLD-CSTN8-10

85

Plastering with CM 2 coats, 12 mm thick,


base coat in CM (1:5), 8mm thick and top
coat in CM (1:3), 4mm thick with sponze
finishing.
Unit = 10 sqm
A. MATERIALS:
Base Coat in CM(1:5), 8 mm thick
Cement
Fine aggregate (Sand)
Top Coat in CM(1:3), 4 mm thick
Cement
Fine aggregate (Sand)
Seigniorage charges for F.A
B. LABOUR:
st
Mason 1 class
nd

Mason 2 class

BLD-CSTN8-11

86

kg
cum

31.70
0.11

kg
cum
cum

19.20
0.04
0.15

day

0.63

day

1.47

Mazdoor (unskilled)
day
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted
RCM FACIA WORKS
RCM facia 5cm thick in CM (1:3) for drop walls, fins
with rabbit wire mesh & nominal reinforcement as
directed by Engineer-in-charge with dubara sponge
finishing, including cost & conveyance of all materials
to site, seigniorage charges, sales & other taxes on all
materials, operational & incidental, cost and
conveyance of cement, wire mesh, water to work site,
centering, scaffolding and form work, lift charges etc.,
complete for finished items of work but excluding cost
of steel & its fabrication charges, for finished item of
work. (APSS No.403 & 903)
Unit - 10 sqm
A) MATERIALS
Rabbit wire mesh (1.0 M panna for 0.6 M
sqm
drop)
Cement Mortar 1:3 for 25 mm thick
cum
Dry Cement for making Lumps
kg
12 mm Plastering 2 coats in 1:4 & 1:2 cm
sqm
both sides
Excluding HYSD Steel/ Mild steel & Binding
wire
B) LABOUR CHARGES
1st Class Mason
day
Miller Operator
day
Mazdoor (unskilled)
day
c) Machinery
Machine Mixing Mortar with Miller - Hire
Hrs
charges
BASIC COST per 10 sqm

3.90

13.30
0.25
50.00
21.80

8.00
1.00
10.00
32.00
2.00

44

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN8-12

BLD-CSTN8-13

87

88

20 mm thick rough cast exterior cement


plaster on walls upto height of 10 metres
above ground level consisting of 10 mm thick
backing coat of 1 : 3 cement mortar (1
cement : 3 sand) and 10 mm thick finishing
coat of 1 : 3 cement mortar (1 cement : 3
coarse aggregate of size 6 mm to 10 mm)
including arrises, chamfers and/or rounded
angles not exceeding 80 mm in girth.
Details of cost for 10 sq.m
Materials :Cement mortar 1:3 (1 cement: 3 sand)
Cement mortar 1:3(1 cement: 3 coarse
aggregate of size 6 mm to 10 mm)
Cement
Coarse aggregate of size 6 mm -10 mm
Mazdoo (unskilled) for mixing mortar with
coarse aggreagate 6 - 10 mm
Labour for backing coat and finishing coat Plaster work :
Mason, llnd class
Mazdoo (unskilled)
Extra labour for scooping :
Mason, llnd class
Mazdoor (male)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Rough cast exterior cement plaster on walls
upto a height of 10 metres above ground
level with a mixture of sand and gravel or
crushed stone graded from 6 mm to 10 mm
nominal size dashed over and including fresh
plaster in two coats, backing coat 10 mm
cement plaster 1 : 3 (1 cemen" : 3 sand) and
finishing coat 10 mm cement plaster with
cement mortar 1:3 (1 cement: 3 sand) mixed
with 10% finely grounded hydrated lime by
volume of cement including arrises, chamfers
and/or rounded angles not exceeding 80 mm
in girth.
(a) Natural cement finish using ordinary
cement.
Details of cost for 10 sq.m.
Materials :
Cement mortar 1:3 (1 cement: 3 sand)
Sand and gravel or crushed stone graded
from 6 mm to 10 mm nominal size
Coarse aggregate of size 6 mm -10 mm
Carriage
Grounded hydrated lime
Carriage

cum

0.110

kg
cum
day

52.800
0.110
0.020

day
day

1.710
3.270

day
day

0.250
0.250

cum

0.224

cum

0.100

kg

9.280

45

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN8-14

BLD-CSTN8-15

BLD-CSTN8-16

89

90

91

Labour for backing coat and finishing coat Plaster work :


Mason, llnd class
Mazdoo (unskilled)
Add labour for dashing crushed stone
Mason 1st class
Mazdoo (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
(b) Dark coloured finish using ordinary
cement and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of colour
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
(c) Light coloured finish using white cement
and pigment
Details of cost for 10 sq.m.
Same rate as per (a) above item ()
Add cost of light colour
Add for water charges on cost of colour @ 1
%
Add for contractor's profit and overheads on
cost of colour and water charges
Cost for 10 sq.m.
Cost per sq.m
Pebble dash exterior plaster on walls upto a
height of 10 metres above ground level with
a mixture of washed pebble or crushed stone
graded from 6 mm to 12 mm nominal size
dashed over and including fresh cement
plaster in two coats, backing coat 10 mm
cement plaster 1 : 3 (1 cement : 3 sand) and
finishing coat 10 mm cement plaster 1 : 3 (1
cement : 3 sand) mixed with 10% finely
grounded hydrated lime by volume of
cement including arrises, chamfers and/or
rounded angles not exceeding 80 mm in girth
Details of cost for 10 sq.m
Materials :
Cement mortar 1:3
Grounded hydrated lime
Pebbles or crushed stone graded from 6 mm
to 12 mm nominal size
Crushed stone / Pebble of size 6 mm -12 mm
Labour for backing coat and finishing coat :Mason llnd class
Mazdoor (unskilled)

day
day

1.710
3.270

day
day

0.500
1.000

kg

6.000

kg

6.000

cum
kg

0.224
9.280

cum

0.100

day
day

1.710
3.270
46

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN8-17

92

93

94

BLD-CSTN8-18

95

Labour for pebble dashing


Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Plain Cement Mortar Bands :
20 mm thick plain cement mortar bands in
cement mortar 1 : 4 (1cement : 4 sand) upto
300 mm in width
(a) Flush Band :Details of cost for 10 metres long and 10 cm
wide band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
b) Sunk band :Details of cost for 10 metres long and 10 cm
wide band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
C) Raised Band :Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
20 mm thick plain cement mortar bands in
cement mortar 1:4(1 cement: 4 sand) above
300 mm in width
Flush Band :Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)

day
day

0.500
0.610

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.300
0.350

cum

0.023

day
day

0.380
0.430

cum

0.224

day
day

2.200
2.700
47

STANDARD DATA BOOK BUILDING WORK ITEMS

96

97

BLD-CSTN8-19

BLD-CSTN9
BLD-CSTN9-1

98

99

Add for water charges @ 1 %


Cost for 10 sq.m.
Cost per sq.m
Sunk band :Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Raised band
Details of cost for 10 sq.m
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Moulded Cement Mortar Bands 15 mm
15 mm thick moulded cement mortar band in
cement mortar 1 : 4 (1cement: 4 sand)
Details of cost for 10 metres long and 10 cm
wide band
Materials :Cement mortar 1 :4
Labour :
Mason llnd class
Mazdoor (unskilled)
Add for water charges @ 1 %
Cost for 10 metres long and 10 cm wide band
Cost per cm width x metre long
FLOORING

cum

0.224

day
day

2.500
3.000

cum

0.224

day
day

3.000
3.500

cum

0.023

day
day

0.870
0.920

Flooring with polished shahabad stones ...


mm thick set over base coat of CM (1:8) over
already laid CC bed / RCC Roof Slab, including
neat cement slurry of honey like consistency
spread @ 3.3 kgs per sqm. & Jointed with
neat cement to full depth including cost of all
materials like cement, sand, and water and
flooring stones etc., complete, including
seigniorage charges, labour charges for
dressing of flooring stones etc., complete for
finished item of work, .

Unit = 10 sqm
A. MATERIALS:

48

STANDARD DATA BOOK BUILDING WORK ITEMS

Polished Shabad Stone mm thick


Cement for CM (1:8) proportion for base coat
Cement for slurry
Cement for jointing
Sand for CM (1:8) proportion
Seigniorage charges of sand
B. LABOUR:
st
Mason 1 class

100

11.00
21.60
33.00
20.00
0.12
0.12

day

3.10

Mason 2 class

day

1.10

Mazdoor (unskilled)
Add water charges 1%
Grand Total
Flooring with Rough Kadapa/Shahabad ...
mm thick stones, set over base coat of
cement mortar (1 : 8) 12 mm thick over CC
bed already laid or RCC roof slab, including
pointing with cement mortar 1:3 duly filling
joints nearly, including cost of all materials
like flooring stone, cement, sand, and water
etc., complete, including seigniorage charges,
labour charges for dressing of flooring stones
etc., complete for finished item of work, .

day

0.86

sqm

10.50

kg.

21.60

kg.
cum
cum
cum

9.60
0.12
0.02
0.14

day

0.960

Mason 2 class

day

2.240

Mazdoor (unskilled)
Add water charges 1%
Grand Total

day

3.30

nd

BLD-CSTN9-2

sqm
kg.
kg.
kg.
cum
cum

Unit = 10 sqm
A. MATERIALS:
Rough Cuddapah/Shabad stones (40 mm
thick) (0.457 x 0.457 m)
Cement for CM (1:8) proportion for base coat
Cement for CM 1:3 proportion for pointing
Sand for CM (1:8) proportion
Sand for CM (1:3) proportion
Seigniorage charges of sand
B. LABOUR:
st
Mason 1 class
nd

49

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-3

101

Flooring with polished marble slab... mm


thick set over base coat of cement mortar
(1:6) 20 mm thick (joints of stone must be
flushed) over CC bed already laid or RCC roof
slab, including near cement slurry of honey
like consistency spread @ 3.30 kgs per sqm.
Jointed with neat cement to full depth mixed
with pigment of matching shade, including
cost of all materials like flooring slab,
cement, sand, and water etc., complete,
including seigniorage charges, labour charges
for dressing, rubbing and polishing of flooring
stones etc., complete for finished item of
work, .
Unit = 10 sqm
A. MATERIALS:
Marble slab of size mm.thick. mm
Cement for CM (1:8) proportion for base coat
Cement for slurry for bedding
White Cement for pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. Machinery
Machine for rubbing of floor
C. LABOUR:
st
Mason 1 class

sqm
kg.
kg.
kg.
cum
cum

10.50
48.00
33.00
5.00
0.20
0.20

day

1.00

day

2.10

Mason 2 class

day

3.00

Mazdoor (unskilled)
Add water charges 1%
Grand Total
Flooring with chequrred terrazzo tiles of 22
mm thick (medium shade) set over base coat
of cement mortar (1:6) 12 mm thick over CC
bed already laid or RCC roof slab, including
near cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed with
neat cement to full depth mixed with
pigment of matching shade including cost of
all materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
complete for finished item of work, .

day

5.00

sqm

10.50

kg.
kg.
kg.
kg.
cum

28.80
33.00
6.00

nd

BLD-CSTN9-4

102

Unit = 10 sqm
A. MATERIALS:
Chequerred terrazzo tiles of 22 mm thick
(medium shade)
Cement for CM (1:6) proportion for base coat
Cement for slurry
Cement for jointing & pointing
Pigment
Sand for CM (1:6) proportion

0.12
50

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-5

103

Seigniorage charges of sand


B. MACHINERY
Nill
C. LABOUR
nd
Mason 2 class

cum

0.12

day

0.960

Man mazdoor
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with vitrified tiles of 1st quality, set
over base coat of cement mortar (1:8), 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste to full depth mixed with pigment of
matching shade, including cost of all
materials like cement, sand water and tiles
etc., complete, including seigniorage charges,
etc., complete for finished item of work, .

day
day

2.240
3.30

Unit = 10 sqm
A. MATERIALS:
st
Vitrified tiles of 1 quality of size

sqm

10.50

Cement for CM (1:8) proportion for base coat

kg.

21.60

Cement for slurry


Cement for Pointing with CM (1:3)
Sand for CM (1:8)
Sand for pointing
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class

kg.
kg.
cum
cum
cum

33.00
6.000
0.12
0.020
0.140

day

0.96

Mason 2 class

day

2.24

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with ceramic tiles, set over base coat
of cement mortar (1:8), 12 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste to full depth mixed
with pigment of matching shade, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work, .

day

3.30
1.00%

sqm
kg.

10.50
21.60

nd

BLD-CSTN9-6

104

Unit = 10 sqm
A. MATERIALS:
Ceramic tiles
Cement for CM (1:8) proportion for base coat

51

STANDARD DATA BOOK BUILDING WORK ITEMS

Cement for slurry


White cement
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class

105

day

0.96

day

2.24

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with high polished granite slabs ...
mm thick other than black set over base coat
of cement mortar (1:8), 20 mm thick over CC
bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tilesetc., complete, including seigniorage
charges, labour charges for dressing of
tilesetc., complete for finished item of work,

day

3.30
1.00%

sqm

10.50

kg.
kg.
kg.
kg.
cum
cum

36.00
33.00
6.00

day

3.00

Mason 2 class

day

1.00

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with marble tiles polished 8 mm
thick set over base coat of cement mortar
(1:8), 12 mm thick over CC bed already laid or
RCC roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with white cement
paste mixed with pigment of matching shade
to full depth, including cost of all materials
like cement, sand water and tiles etc.,
complete, including seigniorage charges, etc.,
complete for finished item of work,

day

8.00
1.00%

Unit = 10 sqm
A. MATERIALS:
High polished granite slab other than black
mm thick
Cement for CM (1:8) proportion for base coat
Cement for slurry
White cement for jointing & pointing
Cement for jointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd

BLD-CSTN9-8

106

33.00
2.00
0.12
0.12

Mason 2 class

nd

BLD-CSTN9-7

kg.
kg.
cum
cum

0.20
0.20

Unit = 10 sqm

52

STANDARD DATA BOOK BUILDING WORK ITEMS

A. MATERIALS:
Marble tiles polished 8 mm thick
Cement for CM (1:8) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR (including for polishing & rubbing)

sqm
kg.
kg.
kg.
cum
cum

10.50
36.00
33.00
5.00
0.20
0.20

Mason 1 class

day

4.00

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with granite stone tiles 8 mm thick
(mirror polished of all shades) set over base
coat of cement mortar (1:6), 12 mm thick
over CC bed already laid or RCC roof slab,
including neat cement slurry of honey like
consistency spread @ 3.3.kgs per sqm &
jointed neatly with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
cement, sand water and tiles etc., complete,
including seigniorage charges, etc., complete
for finished item of work, .

day

8.00
1.00%

sqm

10.50

kg.
cum
cum

48.00
0.20
0.20

day

0.96

Mason 2 class

day

2.24

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with decorated white back ground
glazed tiles, set over base coat of cement
mortar (1:6), 12 mm thick over CC bed
already laid or RCC roof slab, including neat
cement slurry of honey like consistency
spread @ 3.3.kgs per sqm & jointed neatly
with white cement paste mixed with pigment
of matching shade to full depth, including
cost of all materials like cement, sand water
and tiles etc., complete, including seigniorage
charges, etc., complete for finished item of
work,

day

3.30
1.00%

st

BLD-CSTN9-9

107

Unit = 10 sqm
A. MATERIALS:
Granite stone tiles 8 mm thick (mirror
polished of all shades)
Cement for CM (1:6) for base coat
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd

BLD-CSTN9-10

108

Unit = 10 sqm
A. MATERIALS:
53

STANDARD DATA BOOK BUILDING WORK ITEMS

Decorated white back ground glazed tiles


Cement for CM (1:6) for base coat
Cement for slurry
White cement for jointing & pointing
Sand for CM (1:6)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class

sqm
kg.
kg.
kg.
cum
cum

10.50
28.80
33.00
6.00
0.12
0.12

day

0.96

Mason 2 class

day

2.24

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with pressed clay flooring tiles, set
over base coat of cement mortar (1:8) 12
mm thick over CC bed already laid or RCC
roof slab, including neat cement slurry of
honey like consistency spread @ 3.3.kgs per
sqm & jointed neatly with cement mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,

day

3.30
1.00%

1000
Nos
kg.
kg.
10sqm
cum
cum
cum

0.255
21.600
6.000
1.000
0.040
0.120
0.120

nd

BLD-CSTN9-11

109

Unit = 10 sqm
A. MATERIALS:
20 X 20 cm pressed clay flooring tiles
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class

day

0.960

Mason 2 class

day

2.240

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Plain Cement tiles, set over
base coat of cement mortar (1:8) 12 mm
thick over CC bed already laid or RCC roof
slab, including neat cement slurry of honey
like consistency spread @ 3.3.kgs per sqm &
jointed neatly with cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like cement,
sand water and tiles etc., complete, including
seigniorage charges, etc., complete for
finished item of work,

day

4.30
1.00%

nd

BLD-CSTN9-12

110

54

STANDARD DATA BOOK BUILDING WORK ITEMS

Unit = 10 sqm
A. MATERIALS:
Plain cement Tiles 20 x 20 cms
Cement for CM (1:8) for base coat
Cement for jointing & pointing
Pointing with CM (1:3)
Deduct CM (1:3)
Sand for CM (1:8)
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
nd

Mason 2 class

BLD-CSTN9-13

111

0.255

day

0.960

day

2.240
3.30
1.00%

cum

0.17

kg
cum
cum

120.00
0.085
0.085

day

1.25

Mason 2 class

day

0.06

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with 100mm thick Cement Concrete
1:6:10, using 40mm metal, 100mm thick and
20 mm Cement Concrete surface (Ellis
Pattern, 1st Sort)
Unit = 10 sqm
A. MATERIALS:

day

3.00
1.00%

nd

112

21.600
6.000
1.000
0.040
0.120
0.120

Mazdoor (unskiled)
day
Add water charges 1%
Grand Total
Note : When Mortar mix is changed proportionate
quantity of cement has to be substituted for all above
Flooring Items. The same data holds good for stones
with all colours. Adopt same data for polished Kadapa
Stones and Bethamcherla stones.
Gronolithie Concrete Flooring 20 mm thick
with (1:1:2), using 6mm to 12 mm size hard
granite machine crushed metal laid over CC
bed already laid or RCC roof slab, in alternate
panels of size not exceeding 1.50 m x 1.50 m
and finishing the top surface to required
smoothness and slopes and thread lining
including cost of all materials like cement,
metal, sand and water etc., complete,
including seigniorage charges, etc., complete
for finished item of work,
Unit = 10 sqm
A. MATERIALS:
6mm to 12 mm H.G. Metal (Machine
crushed)
Cement
Sand
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class

BLD-CSTN9-14

1000
Nos
kg.
kg.
10sqm
cum
cum
cum

55

STANDARD DATA BOOK BUILDING WORK ITEMS

Cement Concrete 1:6:10 using concrete


mixer
Stone Chippings 3.34 mm - 10 mm
Cement
B. LABOUR
st
Mason 1 class

cum

1.000

cum
kg

0.250
120.000

day

0.150

Mason 2 class

day

0.350

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3)

day

5.40
1.00%

cum

1.00

10
sqm

1.00

day

0.150

Mason 2 class

day

0.350

Mazdoor (unskiled)
Add water charges 1%
Grand Total
Flooring with Cement Concrete 1:6:10, using
40mm metal, 100mm thick and plastered
over with 12 mm thick in CM(1:3) using Red
oxid, with polished surface

day

5.40
1.00%

cum

1.00

10
sqm
kg

1.00
10.00

day

0.150

Mason 2 class

day

0.350

Mazdoor (unskiled)
Add water charges 1%
Masons for polishing
Grand Total

day

5.40
1.00%
1.10

nd

BLD-CSTN9-15

113

Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete
mixer
Plastering with CM (1:3), 12 mm thick
B. LABOUR
st
Mason 1 class
nd

BLD-CSTN9-16

114

Unit = 10 sqm
A. MATERIALS:
Cement Concrete 1:6:10 using concrete
mixer
Plastering with CM (1:3), 12 mm thick
Red oxid
B. LABOUR
st
Mason 1 class
nd

Nos

56

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-17

115

6 mm thick terrazzo flooring in situ with


white, black, chocolate, gray, yellow or green
superior marble chips, over 20 mm thick base
coat of CM (1:3) laid over CC bed already laid
or RCC roof slab, including cost of all
materials like cement marble powder, marble
chips, sand & water etc., complete including
polishing to get high smooth finishing,
seigniorage charges, etc., complete for
finished item of work,
Unit = 10 sqm
A. MATERIALS:
Marble Powder
Marble Chips
Cement for top layer
Cement for base coat in CM (1:3)
Sand for base coat
Seigniorage charges of sand
B. MACHINERY
Polishing Charges
C. LABOUR
st
Mason 1 class

kg
cum
kg.
kg.
cum
cum

17.000
0.060
50.000
96.000
0.200
0.200

sqm

10.000

day

0.960

Mason 2 class

day

2.240

Mazdoor (unskiled)
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with ceramic tiles 7.30
mm thick length equal to flooring stones, set
over base coat of CM (1:3) 12 mm thick with
cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and
jointed with white cement paste mixed with
pigment of matching shade to full depth,
including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,

day

3.30

sqm
cum
kgs
kgs
kgs
cum

10.50
0.12
57.60
33.00
6.00
0.12

day

0.77

day

0.80

nd

BLD-CSTN9-18

116

Unit = 10 sqm
A. MATERIALS:
Ceramic tiles 7.30 mm thick
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
st
Mason 1 class
Mazdoor (unskiled)
Grand Total

57

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-19

BLD-CSTN9-20

117

118

Providing skirting to internal walls to 15 cm


height/risers of steps with marble
slab..mm thickness, length equal to
flooring stones, set over base coat of CM
(1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like marble slab, cement, sand
and water etc., complete including
seigniorage charges, etc., complete for
finished item of work,
Unit = 10 sqm
A. MATERIALS:
Marble slabmm thickness
Sand for base coat
Cement for base coat
Cement for slurry
White cement for jointing & pointing
Flate nosing charges
Machine cutting charges
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Man mazdoor (Beldar)
Man mazdoor (Beldar) for polishing &
rubbing
Woman mazdoor
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with vitrified tiles
length equal to flooring stones, set over base
coat of CM (1:5) 12 mm thick with cement
slurry of honey like consistency spread at the
rate of 3.30 kgs per sqm and jointed with
white cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like tiles, cement, sand and
water etc., complete including seigniorage
charges, etc., complete for finished item of
work,
Unit = 10 sqm
A. MATERIALS:
Vitrified tiles polished 1st quality
Sand for cm 1:5 base coat
Cement for cm 1:5 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR

sqm
cum
kg
kg
kg
RM
RM
cum

10.50
0.12
57.60
33.00
5.00
66.67
67.67
0.12

day
day
day

2.10
4.90
4.00

day

4.00

sqm
cum
kgs
kgs
kgs
cum

10.50
0.12
34.56
33.00
2.00
0.12

58

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-21

119

Mason Ist class


nd
Mason 2 class

day
day

0.96
2.24

Mazdoor (unskilled)
Add water charges 1%
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with 8 mm thick mirror
polished granite tiles length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like tiles,
cement, sand and water etc., complete
including seigniorage charges, etc., complete
for finished item of work,

day

3.30
1.00%

sqm
cum
kgs
kgs
kgs
cum

10.50
0.12
57.60
33.00
5.00
0.12

day
day

2.10
0.80
4.90

Unit = 10 sqm
A. MATERIALS:
8 mm thick mirror polished granite tiles
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
White cement for jointing & pointing
Seigniorage charges of sand
B. LABOUR
Mason Ist class
Mazdoor (unskiled)
nd
Mason 2 class

BLD-CSTN9-22

120

Add water charges 1%


Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with polished kadapa
stone ... mm thick length equal to flooring
stones, set over base coat of CM (1:3) 12 mm
thick with cement slurry of honey like
consistency spread at the rate of 3.30 kgs per
sqm and jointed with white cement paste
mixed with pigment of matching shade to full
depth, including cost of all materials like
Cuddapah stone, cement, sand and water
etc., complete including seigniorage charges,
etc., complete for finished item of work,
Unit = 10 sqm
A. MATERIALS:
Polished kadapa stone . mm thick
Sand for cm 1:3 base coat
Cement for cm 1:3 base coat
Cement for slurry
Seigniorage charges of sand
B. LABOUR

1.00%

sqm
cum
kgs
kgs
cum

10.50
0.12
57.60
33.00
0.12

59

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-23

121

Mason Ist class


Mason 2nd class
Mazdoor (unskiled)
Add water charges 1%
Grand Total
Providing skirting to internal walls to 15 cm
height/risers of steps with ... mm thick
polished Shahabad stone length equal to
flooring stones, set over base coat of CM
(1:3) 12 mm thick with cement slurry of
honey like consistency spread at the rate of
3.30 kgs per sqm and jointed with white
cement paste mixed with pigment of
matching shade to full depth, including cost
of all materials like Shahabad stone, cement,
sand and water etc., complete including
seigniorage charges, etc., complete for
finished item of work,

day
day
day

Unit = 10 sqm
A. MATERIALS:
25 mm thick polished Shahabad stone
sqm
(White)
Sand for cm 1:3 base coat
cum
Cement for cm 1:3 base coat
kgs
Cement for slurry
kgs
Seigniorage charges of sand
cum
B. LABOUR
Mason Ist class
day
Mason 2nd class
Mazdoor (unskiled)
day
Add water charges 1%
Grand Total
Note : a) When Mortar mix is changed proportionate
quantity of cement has to be substituted for all
Skirting Items.

0.96
2.24
3.10
1.00%

11.00
0.12
57.60
33.00
0.12
0.96
2.24
3.10
1.00%

b) For dadooing or cladding items, data for relevant


Skirting Items may be adopted adding the cutting
charges of the stones/ tiles as the case may be.
c) For treads items, data for relevant flooring Items
may be adopted adding the cutting charges of the
stones/ tiles as the case may be.
d) For risers items, data for relevant skirting Items
may be adopted adding the cutting charges of the
stones/ tiles as the case may be.
BLD-CSTN9-24

122

Teak Wood Flooring 40mm. Thick Tongued


and Grooved Planks, including cost of all
materials, labour etc., complete
Unit = 10 sqm
A. MATERIALS:
Teak Wood Planks 40mm thick
75 mm Long Screws

cum
100
Nos

0.44
3.00

60

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN9-25

BLD-CSTN10
BLD-CSTN10-1

123

124

B. LABOUR
Carpenters 1st Class
Carpenters 2nd Class
Man mazdoor
Note : Deduct 4.3 Nos Carpenters if plank rate
tongued and grooved ready planned.
Grand Total
Flooring with Gravel 150 mm thick including
cost of all materials, labour, watering etc.,
complete
Unit = 10 sqm
A. MATERIALS:
Gravel (including 2% wastage)
B. LABOUR
Man mazdoor
Woman mazdoor
Grand Total
ROOFING & CEILING

day
day
day
is for

1.95
4.55
5.40

cum

1.53

day
day

1.10
0.50

kgs
nos

103.09
47.91

nos
nos

43.90

nos

91.82

nos
litre
litre

91.82
0.14
0.20

day
day

0.84
0.91

day
day

0.06
0.06

day

0.14

Roofing with corrugated G.I sheets 0.80mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (up to a
0
pitch of 60 ) and seigniorage charges, etc.,
complete, excluding the cost of purlins,
rafters, trusses & cost of conveyance of all
materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 0.80 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I bolts & nuts 20 x 6
G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos. with washers or srews, if wooden
battens used.
Limpet washers (for scam & J bolts)
884 + 810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter

61

STANDARD DATA BOOK BUILDING WORK ITEMS

Mazdor (coolie)
Sundries including 50 x 6 mm iron wind ties
white lead etc.
Add for Standard specification 1mm. Thick
ridging and 1.25 mm thick sheet vallyes when
such are required for a particular work.
Average allowance for 10 sqm roofing.

BLD-CSTN10-2

125

day
LS

0.14

LS

Grand Total
Rate per 10 sqm = Grand Total/10
Roofing with corrugated G.I sheets 1.00mm
thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.00 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884
G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos
= 810 nos.
Limpet washers (for scam & J bolts)
884 + 810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10

kgs
nos

126.07
47.91

nos

43.90

nos

91.82

nos
litre
litre

91.82
0.14
0.20

day
day

0.84
0.91

day
day

0.06
0.06

day
day

0.14
0.14

62

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-3

126

Roofing with corrugated G.I sheets 1.25mm


thick fixed with G.I J bolts & nuts 8 mm dia
with bitumen & G.I limpet washers filled with
white lead & including a coat of approved
steel primer and two coats of approved paint
on over lapping of sheets complete (upto a
0
pitch of 60 ) and seigniorage charges,
turnover tax etc., complete, excluding the
cost of purlins, rafters, trusses & cost of
conveyance of all materials
Unit = 184.518 sqm
A. MATERIALS:
G.I corrugated 1.25 mm thick sheets
G.I scam bolts & nuts 2 x 27 (laps) x 17 = 884

BLD-CSTN10-4

127

G.I J bolts 8 mm dia 2 x 5 x 27 sheets x 3 nos


= 810 nos.
Limpet washers (for scam & J bolts)
884
+ 810 = 1694
Bitumen washers
Zinc cromate yellow paint
Ready mixed paint
B. LABOUR
For roofing
Carpenter II class
Man mazdoor (beldar)
For premier painting one coat
Painter
Mazdoor (coolie)
For two coats of painting to over laps
Painter
Mazdor (coolie)
Grand Total
Rate per 10 sqm = Grand Total/10
Roofing with 6 mm thick corrugated asbestos
cement sheets, fixing with G.I J bolts & nuts
8 mm dia G.I plain washers complete
including seigniorage charges etc., complete
for finished item of work, but excluding the
cost of purlins, rafters, trusses & cost of
0
conveyance of all materials upto 60 pitch.
Unit = 216.14 sqm
A. MATERIALS:
6 mm thick corrugated AC sheets
8 mm dia G.I J bolts & nuts
G.I washers
Bitumen washers
B. LABOUR
Carpenter II class
Man mazdoor

kgs
nos

154.80
47.91

nos

43.90

nos

91.82

nos
litre
litre

91.82
0.14
0.20

day
day

0.84
0.91

day
day

0.06
0.06

day
day

0.14
0.14

T
/sqm
nos
nos
nos

0.15
22.03
22.03
22.03

day
day

0.43
0.54
63

STANDARD DATA BOOK BUILDING WORK ITEMS

Sundries including 50 x 6 mm iron wind ties


white lead etc.
Add for Standard specification 1mm. Thick
ridging and 1.25 mm thick sheet vallyes when
such are required for a particular work.
Average allowance for 10 sqm roofing.

BLD-CSTN10-5

128

Grand Total
Rate per 10 sqm = Grand Total/10
Best Tiled Roofing with Pan tiles over Flat
Tiles and Lime mortar Borders including Teak
Reapers.
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Flat Tiles 150 x 150 x 15 mm

BLD-CSTN10-6

129

Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime
Lime Mortar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including tarring reepers, extra
labour / for pointing the underside of flat
tiles and white washing the same.
Grand Total
Sub Analysis :
Lime Mortar 1:2
lime
Sand
Grinding Lime Mortar
Total
Best Tiled Roofing with Pan tiles and Lime
mortar Borders including Teak Reapers at
100 mm. centres
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total

LS
LS

1000
No
1000
No
10RM
kgs
cum
cum

1560

75.000
0.500
0.008
0.300

day
day
day
day
LS

0.800
2.200
1.100
5.400
LS

cum
cum
day

0.500
1.000
1.000

1000
No
10RM
kgs
cum

1560
107.000
0.700
0.120

day
day
day
day

1.100
1.400
1.100
3.200

470

64

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-7

130

Best Tiled Roofing with Pan tiles laid on


Bamboo Rafters, Bamboo Reepers and
Bamboo Mats,
including Lime mortar
Borders
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Bamboo rafters (450 mm apart) 75 to 100
mm dia
Bamboo reepers, Split 25 mm dia
Bamboo mats

BLD-CSTN10-8

131

Lime Moratar for Borders


B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including nails
Grand Total
Best Tiled Roofing with Mangalore tiles set in
Lime mortar over Flat Tiles and including
Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
Flat Tiles 150 x 150 x 15 mm
Teak Reepers 50 x 12 mm
Wire Nails 40 mm long
Lime
Lime Moratr
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Sundries including tarring reepers iron wind
ties 30 x 3 mm, G.I. Screw, washers etc., and
extra labour for pointing the underside of flat
tiles and white washing the same.

BLD-CSTN10-9

132

Grand Total
Best Tiled Roofing with Mangalore tiles
including Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Mangalore tiles (vide Stadard Specification)
Teak Reepers 50 x 12 mm

1000
No
RM

1560

100
No
10
sqm
cum

150
10.500

day
day
day
day

1.100
1.400
1.100
3.200

1000
No
1000
No
10RM
kgs
cum
cum

160

75.000
0.500
0.008
0.380

day
day
day
day
LS

0.800
1.600
1.100
4.300
LS

1000
No
10RM

160

25

0.120

470

36.000
65

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-10

133

Wire Nails 50 mm long


Lime Moratar
B. LABOUR
Carpenter
Bricklayers
Man mazdoor
Woman mazdoor
Grand Total
Best Tiled Roofing with Mangalore tiles over
Ceiling Tiles with Air Spaces and including
Teak Reepers
Unit = 10 sqm
A. MATERIALS:
Rate for "Best Mangalore tiled roofing with
Mangalore tiles including teak reeper".
Add
Terracing tiles
B. LABOUR
Bricklayers
Woman mazdoor
Grand Total
Common note Applicabable for Items 196 to
201 :1. The quantity proposed for Pan Tiles /
Mangalore Tiles includes allowance for cost
of special tiles for ridges and hips.
2. Reepers size is for rafter spacing 600 mm.
including allowance for eves and valleys.

BLD-CSTN10-11

134

3. Labour including fixing galvanized iron


sheeting-cost of sheeting to be paid
separately.
Sub Analysis :
Lime Mortar (1: 1.5) :
Unit = 1 cum
Lime
Fine Sand
Grinding Mortar (Spl Grinding)
Sundries
Total
Plastering with Lime Mortar 3 Coats, 25 mm
thick (Sebara Rendering)
Unit = 10 sqm
Lime Mortar (1:2)
Lime Mortar (1:1.5)
Lime
LABOUR
Bricklayers
Mazdoor (unskilled)
Sundries
Total

kgs
cum

0.500
0.090

day
day
day
day

0.500
0.500
1.100
2.200

10
sqm

10.000

100
No

156

day
day

0.500
1.100

cum
cum
day
LS

0.670
1.000
1.000

cum
cum
cum

0.180
0.080
0.023

day
day
LS

3.200
6.500
LS

66

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-12

135

Terrace Roofing with Brick on edge 75 mm.


Concrete 2 Courses of Flat Tiles at Top and
pointing Flat Tiles in Cement Mortar (1:3) and
one coat of Cement Plaster (1:3)
Unit = 10 sqm
A. MATERIALS:
Terracing Bricks 150 x 75 x 25mm
Flat Tiles 150 x 150 x 15 mm

BLD-CSTN10-13

136

1000
No
100
No
cum
cum
cum
10
sqm
cum

Broken brick 20 mm cube


Lime
Lime Moratar
Pointing with cement mortar 1:3 (for rate vide relevant schedule item)
Cement Mortar 1:3
B. LABOUR
Bricklayers
day
Mazdoor (unskilled)
day
Grand Total
Note : The quantity proposed for broken brick allows
for the brick powder formed, replacing sand for
concrete layers.
Reinforced cement Concrete Roofing 125 mm
thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Reinforced Concrete Roofing slab 125 mm
thick (for rate - vide relevant schedule item)
Flat Tiles 150 x 150 x 20 mm
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate vide relevant schedule item)
B. LABOUR
Bricklayers
Woman mazdoor
Sundries including crude oil
Grand Total
Sub Analysis :
RCC (M 20) using 20 mm HG graded metal
using Concrete mixturefor Roofing 125 mm
thick
CC (M 20) (Item No.
Centering Charges

2000
900
0.980
0.380
0.210
1.000
0.240
4.300
6.500

10
sqm

10.000

100
No
cum
10
sqm

900
0.260
1.000

day
day
LS

2.200
2.200

cum
10
sqm

1.250
1.000

Form Work
Total

67

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-14

BLD-CSTN10-15

BLD-CSTN10-16

BLD-CSTN10-17

137

138

139

140

Reinforced cement Concrete Roofing 140 mm


thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)
Unit = 10 sqm
A. MATERIALS:
Rate of "Reinforced cement Concrete Roofing
125 mm thick and 2 courses of Flat Tiles at
Top including pointing with Cement Mortar
(1:3)"
Add :
For extra thickness of roofing slab
Grand Total
Reinforced cement Concrete Roofing 150 mm
thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)
Rate of "Reinforced cement Concrete Roofing
125 mm thick and 2 courses of Flat Tiles at
Top including pointing with Cement Mortar
(1:3)"
Add :
For extra thickness of roofing slab
Grand Total
Reinforced cement Concrete Roofing 100 mm
thick with CC (M 20) using 20 mm graded
metal and 2 courses of Flat Tiles at Top
including Pointing with Cement Mortar (1:3)
Rate of "Reinforced cement Concrete Roofing
125 mm thick and 2 courses of Flat Tiles at
Top including pointing with Cement Mortar
(1:3)"
Deduct :
For Less thickness of roofing slab
Grand Total
Reinforced cement Concrete Roofing 100 mm
thick with CC (M 20) using 20 mm graded
metal with Imprevious Coat with 12 mm thick
Plastering in CM (1:3) with 1 kg. of Impermo
Compound or ACCO Proof per Bag of Cement
and laid when slab is Green.
Unit = 10 sqm
Reinforced Concrete Roofing slab 100 mm
thick (for rate - vide relevant schedule item)
Centering Charges
Plastering with CM (1:3), 12 mm thick

10
sqm

1.000

cum

0.150

10
sqm

1.000

cum

0.250

10
sqm

1.000

cum

0.250

10
sqm

1.000

10
sqm
10
sqm

1.000
1.000

68

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-18

141

Impermo Compound
Grand Total
Note for Items 204 - 207 :
1. No extra rate will be paid for finishing the
bottom surface of the roofing slab as
described in SS No.
"For estimating purpose the extra allowance
for camber concrete, when such is required
may be given under sundries."
Complete Surface Repairs to Leaky Terrace
Roofs with Flat Tiles
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Cement Mortar 1:3
Pointing with cement mortar 1:3 (for rate vide relevant schedule item)
B. LABOUR
Bricklayers
Man Mazdoor
Clean removal of lime plaster from terraced
roofs and raking out joints 12 mm deep (for
rate - vide relevant schedule item)

BLD-CSTN10-19

142

Sub Analysis :
Mazdoor (unskilled)
Mate
Sundries including crude oil
Grand Total
Best Sloping Bengal Terrace with 3 courses of
Flat Tiles at Top including Teak Wood
Reepers
Unit = 10 sqm
A. MATERIALS:
Flat Tiles 150 x 150 x 15 mm
Lime
Lime Moratar (1:1.5)
Teak Reepers 52 x 12 mm
Wire Nails 40 mm long
Plastering with lime mortar 3 coats (for rate vide relevant schedule item)
B. LABOUR
Carpenter
Bricklayers
Woman mazdoor
Sundries including tarring reepers
Grand Total
Note : 1. Reepers size is for rafter spacing 600
mm. including allowance for eves and valleys.

kgs

1.500

1000
No
cum
10
sqm

450

day
day
10
sqm

0.110
1.000

1.100
1.100
1.000

Day
Day
LS

1000
No
cum
cum
10 RM
kgs
10
sqm
day
day
day
LS

1350
0.008
0.150
75.000
0.500
1.000

0.800
2.200
2.200

69

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-20

BLD-CSTN10-21

BLD-CSTN10-22

BLD-CSTN10-23

BLD-CSTN10-24

143

144

145

146

147

2. No extra rate will bepaid for finishing the


bottom surface of the roofing slab as
described in SS No.
Removing Old Tiles and Retiling with New
Pan Tiles over Old Teak Reepers including
New White Washed Lime Mortar Borders 230
x 50 mm. at 2 Metres Intervals
Unit = 10 sqm
A. MATERIALS:
Pan Tiles 230 x (140 + 130)/2, 12 mm thick
Lime Moratar
B. LABOUR
Bricklayers
Man Mazdoor
Woman mazdoor
Sundries
Grand Total
Shifting Pan Tiles (Labour Only)
Unit = 10 sqm
Bricklayers
Man Mazdoor
Grand Total
Shifting Pan Tilesand forming new White
Washed Lime Mortar Boarders, 230 x 50 mm
at 2 Metres Intervals
Unit = 10 sqm
Rate of "Shifting Pan Tiles"
Add : Lime Mortar Borders and White
Washing
Grand Total
12 mm. Teak Wood Plank Ceiling Tongued
and Grooved Planking
Unit = 10 sqm
A. MATERIALS:
Teak Wood Planks 150 x 12 mm
Screws 40mm long
B. LABOUR
Carpenter
Man Mazdoor
Sundries
Grand Total
Note : Deduct 4.3 Nos Carpenters if plank
rate is for tongued and grooved ready
planned.
12 mm. Teak Wood Plank Ceiling with 40 x 12
mm Teak Wood Battens
Unit = 10 sqm
Rate for "12 mm. Teak Wood Plank Ceiling
Tongued and Grooved Planking"

1000
No
cum

1560
0.120

day
day
day
LS

1.400
1.100
4.300

day
day

1.100
0.800

10
sqm
LS

1.000

cum
100
No

0.132
300

day
day
LS

6.500
5.400

10
sqm

10.000

70

STANDARD DATA BOOK BUILDING WORK ITEMS

Teak Wood Battens 40 x 12 mm


Brass screws 25 mm long

BLD-CSTN10-25

148

10 RM
100
No

66.000
240

day
LS

1.100

cum
kg

0.210
2.000

day

0.660

Mason 2 class

day

1.540

Mazdoor (unskiled)
Grand Total
Providing & fixing insulating board ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials

day

3.70

sqm

11.00

day
day

2.50
2.00

sqm

11.00

day
day

2.50
2.00

Deduct :
Carpenter
Sundries
Grand Total
Providing impervious coat to exposed RCC
roof slab surface with CM(1:3), 20mm thick
with 1kg of water proof compound per bag of
cement laid over roof when it is green
including cost of all materials, seigniorage
charges, excluding conveyance charges of
materials and including all operational,
incidental and labour charges for mixing
mortar, laying, rendering smooth and thread
lining, curing, rounding off junctions of wall
and slab etc,, complete for finished item of
work
Unit = 10 sqm
A. MATERIALS:
Cement Mortal 1:3
Water proof compound
B. LABOUR
st
Mason 1 class
nd

BLD-CSTN10-26

BLD-CSTN10-27

149

150

Unit = 10 sqm
A. MATERIALS:
12 mm thick insulating board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing & fixing hard board sheet ceiling of
approved quality with nails etc., complete,
excluding the cost of frame work for base
and cost of conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
3 mm thick standard quality of hard board
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total

71

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-28

151

Providing & fixing flat pressed 3 layer


medium density particle board sheet with
necessary nails etc., complete, excluding the
cost of frame work for base and cost of
conveyance of all materials
Unit = 10 sqm
A. MATERIALS:
Standard quality of flat pressed 3 layer
medium density board sheet 4.50 mm thick

BLD-CSTN10-29

BLD-CSTN10-30

sqm

11.00

day
day

2.50
2.00

sqm

11.00

day
day

2.50
2.00

cum

0.05

Nails
Rabbit wire mesh
Plaster of paris
B. LABOUR
for Jointing the wooden strips including fixing
the rabbit mesh
Carpenter Ist class
Man mazdoor (beldar)
For doing plaster of paris over wooden strips

kg
sqm
kg

0.75
10.20
219.76

day
day

2.60
1.60

Mason Ist class


Mason IInd class
Mazdoor (unskilled)
Grand Total
Gypboard Suspended false ceiling

day
day
day

2.62
1.62
377.00

152

B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing & fixing plain AC sheet ceiling of
approved quality with necessary nails etc.,
complete, excluding the cost of frame work
for base and cost of conveyance of all
materials

153

Unit = 10 sqm
A. MATERIALS:
Plain AC sheet for ceiling
B. LABOUR
Carpenter Ist class
Man mazdoor
Grand Total
Providing 10 mm thick plaster of paris
(Gypsum anhydrous) ceiling upto a height of
5 m above floor level over first class BT wood
strips 25 x 6 mm with 10 mm gap in between
and reinforced with rabbit wire mesh fixed to
wooden frame excluding cost of wooden
frame for base & cost of conveyance of all
materials.
Unit = 10 sqm
A. MATERIALS:
st
Wooden strips 1 class BT wood 25 x 6 mm
size

72

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN10-31

154

Supplying and fixing Gyp Board Suspended


regular single layer false ceiling (GS-MFSC-4.1
as per India Gypsum) using 12.5 mm thick
Gyp Board conforming to IS 2095 - 1982
fixing to Gyp steel GI perimeter channels of
size 20 mm x 27 mm x 30 mm(web) of 0.55
mm thick along the perimeter of ceiling
screw fixed to brick work/ partition at 610
mm c/c and suspending the frame work using
Intermediate channels (45 mm x 15mm x
15mm x 0.9 mm) from soffit at 1220 mm c/c
with ceiling angle (25 mm x 10 mm x 0.55
mm) fixed with GI Cleat and steel expansion
fasteners & connecting clip to the ceiling
channels (with knurled web of 51.5 mm x 26
mm x 10.5 mm x 0.55 mm) fixed in direction
perpendicular to the intermediate channel at
457 mm c/c and fixing the 12.5 mm tapered
edge Gypboard with 25 mm drywall screws at
230 mm c/c & jointing and finishing using
joint compound and paper tape to have a
flush look including filling the tapered &
square edges with jointing compound, two
coats of drywall topcoat complete for
finished item of work as per Idia Gypsum Ltd
specification.

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm Gypboard
1219 mm x 1829 mm size Boards
Ceiling Angle
25 mm x 10 mm x 0.55 mm
Connecting Clips
Ceiling Section
51.5 mm x 26 mm x 10.5 mm x 0.55 mm thick
Intermediate Channel
45 mmx 15 mm x 15 mm x 0.9 mm
Perimeter Channel
20 mm x 27 mm x 30 mm(web) of 0.55 mm
thick
Rawl Plug
Soffit Cleats
Drywall Screws - 25 mm
Jointing Compound
Jointing Paper Tape
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter

sqm

1.03

RM
Nos

0.64
1.84

RM

2.30

RM

0.84

RM

0.40

Nos
Nos
Nos
Kgs
RM
Lits

0.64
0.64
18.00
0.55
1.46
0.15

day
day

0.40
0.40
73

STANDARD DATA BOOK BUILDING WORK ITEMS

1st Class Painter


2nd Class Painter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN10-32

155

day
day
day

0.08
0.08
0.04

day
day

0.08
0.24

Hrs

0.32

Hrs

0.64

Scaffolding charges
BASIC COST per 1 sqm
Gyp Board Fine Line Grid false ceiling
Supplying and fixing Gyp Board Fine Line Grid
false ceiling (GS-FLC-4.6 as per India Gypsum)
in size 600 mm x 600 mm using 12.5 mm
thick/ 9.5 mm thick Gyp Board sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm conforming to IS 2095 - 1982 fixing to
Gyp steel precoated GI wall angle of size 25
mm x 25 mm x of 0.70 mm thick along the
perimeter of ceiling screw fixed to brick
work/ partition at 610 mm c/c and
suspending the frame work using precoated
GI Tee section (24 mm x 38 mm x 0.7 mm)
from soffit at 1220 mm c/c fixed with GI
Soffit Cleat, rawl plugs and steel expansion
fasteners & connecting clip to the GI T
section with 4 mm dia GI Rod with galvanised
spring steel level clip of PVC unversal holding
clips system at 1200 mm c/c and fixing the
12.5 mm / 9.5 mm Gypboard Sheet tiles of
size 595 mm x 595 mm or 595 mm x 1195
mm and finishing two coats of drywall
topcoat complete for finished item of work
as per Idia Gypsum Ltd specification.

1%

UNIT -1 sqm
A) Material requirement as per India Gypsum
12.5 mm / 9.5 mm - Gypboard Tiles
Either - 595 mm x 595 mm Or - 595 mm x 1195 mm GI Angle - Precoated
25 mm x 25 mm x 0.7 mm
GI - Precoated - T Section - 3600 mm long
24 mm x 38 mm x 0.7 mm thick
GI - Precoated - T Section - 600 mm long
24 mm x 38 mm x 0.7 mm thick
GI Rod - 4 mm Dia
Connecting Rod
Rawl Plug

sqm

1.00

RM

0.40

RM

1.60

RM

1.60

RM
Nos

1.28
1.28
74

STANDARD DATA BOOK BUILDING WORK ITEMS

Soffit Cleats
Unversal Holding Clips
Drywall Top Coat
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN10-33

156

Nos
Nos
Lits

1.28
5.36
0.15

day
day
day
day
day

0.40
0.40
0.08
0.08
0.04

day
day

0.04
0.24

Hrs

0.32

Hrs

0.32

Scaffolding charges
BASIC COST per 1 sqm
Armstrong False ceiling
Providing and fixing in true horizontal level
600 mm x 600 mm 15 mm thick Arm strong
false ceiling system manufactured by M/s
Arm strong world Industries using hot dipped
Galvanised Steel section exposed surface
with pre-coated capping, main Tee of size 24
x 32 mm at every 1200 mm c/c maximum
and rotary stiched cross tee of size 24 x 27
mm at evry 600 mm c/c and sub-cross tee of
size 24 mm x 25 mm at 1200 mm c/c and wall
angle of size 19 x 19 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick pre-straightened GI Wire laying
fine fissured butt edge ceiling tiles of 15 mm
thick mineral fiber Board manufactured by
M/s Arm Strong World Industries Ltd., having
RH 99% and for finished of size 600 x 600 mm
including Cost &conveyance of all materials
and labour charges such as cutting , fixing of
standing of frame work exposing roof making
complete for finished item of work

UNIT 1 sqm
A) Material requirement
15 mm - Armstrong Mineral Fiber sheet 600 x
600
Hotdipped GI Angle - Precoated - Grid
19 mm x 19 mm
Polyster painted GI - T Section - 1200 mm
(1) 24 x 32 mm and (2) 24 x 25 mm (sub-cross
Tee)

1%

sqm

1.00

RM

0.40

RM

1.60

75

STANDARD DATA BOOK BUILDING WORK ITEMS

Polyster painted GI - T Section - 300 mm


24 mm x 27 mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
6 mm Nylon Rawl Plug
B) LABOUR CHARGES
PER UNIT 1 sqm
1st Class Carpenter
2nd Class Carpenter
1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN10-34

157

RM

1.60

RM
Nos

1.28
1.28

day
day
day
day
day

0.40
0.40
0.08
0.08
0.04

day
day

0.04
0.24

Hrs

0.32

Hrs

0.32

Scaffolding charges
BASIC COST per 1 sqm
Thermocole False ceiling
Providing and fixing Thermocole False ceiling
in true horizontal level 600 mm x 600 mm
using 15 mm/ 19 mm thick Thermocole
sheet anodised Aluminium Tee sections of
size 24.50 mm x 24.0 mm x 2.4 mm in grid
with cross tee of size 24 x 24.5 mm at every
600 mm c/c and anodised aluminium wall
angle of size 24 x 24 mm fixed to periphery of
the wall and the above grid is suspended at
every 1200 mm c/c in both directions using
2.0 mm thick GI Wire for finished of size 600
x 600 mm including Cost &conveyance of all
materials and labour charges such as cutting ,
fixing of standing of frame work exposing
roof making complete for finished item of
work
UNIT 1 sqm
A) Material requirement
15 mm/ 19 mm Thermocole sheet 600 x 600
Alumninium Angle
24 mm x 24 mm
Anodised Aluminium T Section
(1) 24 x 24.5 x 2.4 mm mm
GI Rod - prestraightened - 2.0 mm dia
Connecting Rod
Rawl Plugs
B) LABOUR CHARGES
1st Class Carpenter

1%

sqm

1.00

RM

0.40

RM

3.20

Nos
Nos

1.28
1.28

day

0.36
76

STANDARD DATA BOOK BUILDING WORK ITEMS

2nd Class Carpenter


1st Class Painter
2nd Class Painter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN11
BLD-CSTN11-1

BLD-CSTN11-2

158

159

day
day
day
day

0.36
0.00
0.00
0.02

day
day

0.04
0.20

Hrs

0.16

Hrs

0.32

Scaffolding charges
BASIC COST per 1 sqm
WHITE WASHING, COLOUR WASHING &
DISTEMPERING
White washing one coat with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers
Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm
White washing two coats with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers

1%

cum

0.005
L.S

day
day
LS

0.11
0.22

cum

0.007
L.S

day

0.160
77

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN11-3

BLD-CSTN11-4

160

161

Mazdoor (unskilled)
Sundries including brushes etc.,
Total cost for 10 sqm
White washing three coats with lime of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Fine screened shell lime
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
White washer
Brick Layers
Man Mazdoor
Women mazdoor
Mazdoor (unskilled)
Sundries including brushes, ladders etc.,
Total cost for 10 sqm
White washing one coat with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement
Gum, conjee water, or prickly pear juice
including necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm

day
LS

0.32

cum

0.009
L.S

day
day
day
day
day
LS

0.220
0.43

with White Cement Grade


II

cum /
kg

1.20

day
day

0.11
0.22
0.50%

78

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN11-5

162

White washing two coats with whiting of


approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement

BLD-CSTN11-6

163

Gum, conjee water, or prickly pear juice


including necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
White washing three coats with whiting of
approved quality to give an even shade after
thoroughly brushing the surface to remove
all dirt and remains of loose powdered
materials including cost of all materials,
labour charges and incidental such as
scaffolding, lift charges etc., complete for
finished item of work, but excluding
conveyance charges of materials
Unit: 10 sqm
A. MATERIALS :
Whiting / White Cement

BLD-CSTN11-7

164

Gum, conjee water, or prickly pear juice


including necessary fire wood
B. LABOUR
Brick Layers / Painter
Mazdoor (unskilled)
Total cost for 10 sqm
Colour Washing, One Coat
Unit: 10 sqm
Rate for "White Washing" one coat

BLD-CSTN11-8

165

cum /
kg

2.00
L.S

day
day

0.210
0.320
1.00%

cum /
kg

2.800

day
day

0.300
0.430

10
sqm

1.000

Add: For Colours, etc., (50 percent of above


rate)
Total
Colour Washing, Two Coats
Unit: 10 sqm

79

STANDARD DATA BOOK BUILDING WORK ITEMS

Rate for "White Washing" two coats

BLD-CSTN11-9

BLD-CSTN11-10

BLD-CSTN12
BLD-CSTN12-1

BLD-CSTN12-2

166

167

168

169

Add: For Colours, etc., (50 percent of above


rate)
Total
Distempering, 2 Coats with Water Bound
Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
Distempering, 2 Coats with Oil Bound
Distemper
Unit: 10 sqm
A. MATERIALS :
Distemper
B. LABOUR
Painter
Sundries including brushes, ladders, etc.,
Total cost for 10 sqm
PAINTING & VARNISHING

10
sqm

1.000

kg

1.340

day
day

0.500
1.300
1.000%

kg

1.700

day

1.200
1.000%

Lts
Nos
Nos
Lts
Nos
Nos

0.50
0.08
0.19
1.70
0.36
0.84

kg

1.00

Painting to new walls with 2 coats of ready


mixed oil bound wahsable distemper of
approved brand and shade over a base coat
of appropriate primer of approved brand,
making 3 coats in all to give an even shade
after thourughly brushing the surface to
remove all dirt and remains of loose
powdered materials, including cost and
conveyance of all materials to work site and
all operational, incidental, labour charges etc.
complete for finished item of work as per SS
911 for internal walls
PRIMARY COAT:
Cost of Primer
Painter I st class
Pianter Iind class
Cost of washable Oil Bound Distemper
1st class painter
II class painter
Total cost
Painting, Priming Coat on New Plastered
Surface
Unit: 10 sqm
A. MATERIALS :
Cement Primer
B. LABOUR

80

STANDARD DATA BOOK BUILDING WORK ITEMS

Painter
Sundries including brushes, soaps, putty etc.,

BLD-CSTN12-3

BLD-CSTN12-4

BLD-CSTN12-5

BLD-CSTN12-6

170

171

172

173

day

0.700
0.500%

kg

2.000

day
day

0.300
1.500
1.000%

kg

3.500

day
day

0.500
1.500
1.000%

kg
day
day
kg

1.00
0.21
0.49
3.50

day
day
day

0.15
0.35
1.50

Total cost for 10 sqm


Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint
over Priming Coat, One Coat (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 5 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
Painting Walls with Snowcem or other equal
and approved Water Proof Cement Paint
over Priming Coat, 2 Coats (All Colours)
Unit: 10 sqm
A. MATERIALS :
Cement Paint at 3 sqm., per kg
B. LABOUR
Painter
Mazdoor (unskilled)
Sundries including brushes, etc.,
Total cost for 10 sqm
Painting to new walls with 2 coats of water
proof cement paint of apporved brand and
shade over a base coat of approved cement
primer grade I making making 3 coats in all to
give an even shade after thourughly brushing
the surface to remove all dirt and remains of
loose powdered materials, including cost and
conveyance of all materials to work site and
all operational, incidental, labour charges etc.
complete for finished item of work as per SS
912 for internal walls

Cost of Cement Primer


Ist class painter
2nd class painter
Cost of water proof cement Paint of
approved quality
1st class painter
2nd class painter
Mazdoor (unskilled)
Total cost
Painting, Priming Coat on New Wood Work
Unit: 10 sqm
A. MATERIALS :

81

STANDARD DATA BOOK BUILDING WORK ITEMS

Wood Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

BLD-CSTN12-7

174

BLD-CSTN12-9

BLD-CSTN12-10

175

Total cost for 10 sqm


Varnishing to Wood Work, One Coat

176

Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
Varnishing to Wood Work, Two Coats

177

178

0.700

day

0.700
1.000%

0.70

day

0.70

L
L

0.800
0.600

day
day

0.700
0.700

L
L

1.200
1.100

day
day

1.100
1.100

kg

1.600

day
LS

0.700

kg

2.800

Total cost for 10 sqm


Painting, Priming Coat on New Iron Work
Unit: 10 sqm
A. MATERIALS :
Red Oxide Primer
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

BLD-CSTN12-8

Unit: 10 sqm
A. MATERIALS :
Varnish
Linseed Oil - boiled
B. LABOUR
Painter
Man Mazdoor
Sundries including brushes,fuel, size etc.,
Total cost for 10 sqm
Painting with Ready mixed oil paint (all
colours)
i. One Coat - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint

82

STANDARD DATA BOOK BUILDING WORK ITEMS

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

179

180

181

182

183

184

Total cost for 10 sqm


One Coat - Old Wood Work & New Iron Work
:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Wood Work & New Iron
Work:
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
One Coat - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Two Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Three Coats - Old Iron Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Three Coats - New Wood Work :
Unit: 10 sqm
A. MATERIALS :
Ready mixed paint

day
LS

1.200

kg

1.500

day
LS

0.700

kg

2.4.

day
LS

1.200

kg

1.200

day
LS

0.700

kg

2.100

day
LS

1.100

kg

3.400

day
LS

1.500

kg

3.900
83

STANDARD DATA BOOK BUILDING WORK ITEMS

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

BLD-CSTN12-11

185

187

188

189

1.600

0.500

day

0.700

0.400

day

0.700

0.900

day

1.200

0.800

day

1.200

0.800

Total cost for 10 sqm


Painting with :
i. Plastic Emulsion paint Grade I - One Coat
for New Wood Work, Old Wood Work & New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

186

day
LS

Total cost for 10 sqm


Plastic Emulsion paints - One Coat for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for Old
Wood Work & New Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Two Coats for New
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.

84

STANDARD DATA BOOK BUILDING WORK ITEMS

B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

190

191

192

BLD-CSTN12-12

193

194

Total cost for 10 sqm


Plastic Emulsion paints - Two Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Three Coats for
New Wood Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Plastic Emulsion paints - Three Coats for Old
Iron Work :
A. MATERIALS :
Plastic Emulsion paint (at 20 sqm / litre as per
British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - One
Coat - for New Wood Work, Old Wood Work
& New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - One
Coat - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter

day

1.100

0.700

day

1.100

1.200

day

1.600

1.100

day

1.500

0.700

day

0.700

0.500

day

0.700
85

STANDARD DATA BOOK BUILDING WORK ITEMS

Sundries including brushes, soap, putty etc.,

195

196

197

198

199

Total cost for 10 sqm


Painting with Synthetic Enamel paints - Two
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - For Old Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - For New Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Two
Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,
Total cost for 10 sqm
Painting with Synthetic Enamel paints - Three
Coats - for New Wood Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

1.200

day

1.200

1.100

day

1.200

1.100

day

1.100

0.900

day

1.100

1.700

day

1.600

Total cost for 10 sqm


86

STANDARD DATA BOOK BUILDING WORK ITEMS

200

BLD-CSTN12-13

201

Painting with Synthetic Enamel paints - Three


Coats - For Old Iron Work
A. MATERIALS :
Synthetic Enamel paint (at 20 sqm / litre as
per British Paints (I) Ltd.
B. LABOUR
Painter
Sundries including brushes, soap, putty etc.,

BLD-CSTN12-15

BLD-CSTN13
BLD-CSTN13-1

202

203

204

1.600

day

1.500

kg

0.500

day
day
LS

0.800
0.800

0.650

day
day
LS

0.800
0.800

kg
L

0.228
1.630

day
LS

3.200

cum

1.000

day
day

17.700
8.800

Total cost for 10 sqm


Polishing on wood work with readymade wax
polish of approved brand and manufacture
New Work :
A. MATERIALS :
Readymade wax polish
B. LABOUR
Painter
Helper
Sundries including brushes, soap, cloth etc.,

BLD-CSTN12-14

Total cost for 10 sqm


Melamine polishing on wood work (one coat)
New Work :
A. MATERIALS :
Melamine polish
B. LABOUR
Painter
Healper
Sundries for Spraying Machine etc.,
Total cost for 10 sqm
French Spirit polishing Two or more coats on
new works including a coat of wood filler.
A. MATERIALS :
Shellac
Spirit
B. LABOUR
Painter
Sundries such as pigment, terpentaine, sand
paper, putty, wood filler, white woolen cloth,
linseed oil, cotton etc.,
Total cost for 10 sqm
WOOD
WORK,
ALUMINUM
DOORS,
WINDOWS, VENTILATORS Etc.,
Best Teak Wood wrought and put up to 2
meters (Schedule Item No 286)
Unit = 1 cum
Materials :
Teak wood large scantlings upto 2 m
Labour :
Carpenter
Man Mazdoor

87

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-2

BLD-CSTN13-3

BLD-CSTN13-4

BLD-CSTN13-5

205

206

207

208

209

Sundries including nails, screws etc.,


Cost per cum
Best Teak Wood wrought and put up over 2
metres and below 3 metres in length
(Schedule Item No 287)
Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and
below 3 m in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
Best Teak Wood wrought and put up in large
scantling of over 3 metres in length (Schedule
Item No 288)
Unit = 1 cum
Materials :
Teak wood large scantlings over 2 m and
below 3 m in length
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
Best Teak Wood wrought and put up for
trusses including straps and all iron work
(Schedule Item No 289)
Unit = 1 cum
Materials :
Teak wood large scantlings
Iron Work (average)
Labour :
Carpenter
Man Mazdoor
Sundries including nails, screws etc.,
Cost per cum
Fully Panelled doors - External or Internal Moulded panels (Schedule Item No 290)
Single Shutter
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters

LS

cum

1.000

day
day

17.700
8.800
LS

cum

1.000

day
day

17.700
8.800
LS

cum
kg

1.000
112.000

day
day

26.500
8.800
LS

cum
sqm

0.083
1.600
LS

cum
sqm

0.088
1.800

88

STANDARD DATA BOOK BUILDING WORK ITEMS

210

211

212

213

214

215

Sundries inclusive of holdfasts and all wind


appliances
(Vide
relevant
standard
specification)
Total for each door
1100 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1500 x 2400 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door

cum
sqm

0.109
2.200
LS

cum
sqm

0.123
2.520

cum
sqm

0.094
1.890
LS

cum
sqm

0.159
3.600
LS

cum
sqm

0.096
1.800

cum
sqm

0.104
2.000

89

STANDARD DATA BOOK BUILDING WORK ITEMS

216

217

BLD-CSTN13-6

218

219

220

221

1300 x 2200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
Fully Panelled doors - Internal Five Ply - Plywood Panels (Schedule Item No 291)
Single Shutter
800 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1200 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1300 x 2200 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters

cum
sqm

0.134
2.860

cum
sqm

0.147
3.220

cum
sqm
sqm

0.068
0.720
1.600
LS

cum
sqm
sqm

0.071
0.870
1.800

cum
sqm
sqm

0.100
1.160
2.520
LS

cum
sqm
sqm

0.106
1.390
2.860

90

STANDARD DATA BOOK BUILDING WORK ITEMS

222

223

224

225

226

227

Sundries inclusive of holdfasts and all wind


appliances
(Vide
relevant
standard
specification)
Total for each door
900 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2100 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1000 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1100 x 2000 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1400 x 2300 mm
*Teak wood
Five - Ply - Ply - Wood brich

cum
sqm
sqm

0.077
0.880
1.890
LS

cum
sqm
sqm

0.091
0.880
2.100

cum
sqm
sqm

0.082
0.710
1.800

cum
sqm
sqm

0.088
0.820
2.000

cum
sqm
sqm

0.090
0.940
2.200

cum
sqm

0.123
1.900
91

STANDARD DATA BOOK BUILDING WORK ITEMS

228

BLD-CSTN13-7

BLD-CSTN13-8

BLD-CSTN13-9

229

230

231

232

Labour, wrought and putup in position frame


& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
1500 x 2400 mm
*Teak wood
Five - Ply - Ply - Wood brich
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of holdfasts and all wind
appliances
(Vide
relevant
standard
specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough plank
Furniture - Iron - for External doors (Schedule
Item 292)
Top Tower bolts (Ave : Size)
Bottom Tower bolts 150mm long
Parliament hings with screws
Oxidised aldrop with bolts
Wind cleats with hings
(Same for all doors)
Furniture - Iron - Internal doors (Schedule
Item 293)
Top Tower bolts (Ave : Size)
Bottom Tower bolts 150mm long
Butt hings with screws
Wind cleats with hings
(Same for all doors)
Glazed and Panelled doors (Schedule Item
No. 294)
Single Shutter
800 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door

sqm

3.600

cum
sqm
sqm

0.130
1.280
3.600

Nos
Nos
Nos
Nos
Nos

2
2
6
1
2

Nos
Nos
Nos
Nos

1
2
6
2

cum
sqm
sqm

0.072
0.470
1.600

LS

cum
sqm
sqm

0.076
0.560
1.800

LS

92

STANDARD DATA BOOK BUILDING WORK ITEMS

233

234

235

236

237

238

1200 x 2100 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1300 x 2200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
Double Shutter
900 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1000 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1100 x 2000 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
1400 x 2300 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters

cum
sqm
sqm

0.106
0.760
2.520

LS

cum
sqm
sqm

0.115
0.870
2.860

LS

cum
sqm
sqm

0.087
0.420
1.800

LS

cum
sqm
sqm

0.092
0.510
2.000

LS

cum
sqm
sqm

0.096
0.600
2.200

LS

cum
sqm
sqm

0.123
1.060
3.220

93

STANDARD DATA BOOK BUILDING WORK ITEMS

239

BLD-CSTN13-10

240

BLD-CSTN13-11

241

242

BLD-CSTN13-12

243

244

Sundries inclusive of putty, brads, hold fasts


and all wind appliances (Vide relevant
standard specification)
Total for each door
1500 x 2400 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and all wind appliances (Vide relevant
standard specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough planks.
Furniture - Same as for Fully Panelled Doors
External (Schedule Item No. 295)
Total for each door
Framed and Planked Doors (Schedule Item
No. 296)
1000 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
1200 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
* Note : Average rate for respective size
scantlings and rough planks.
Country wood Framed and Planked Doors
(Schedule Item No. 297)
Single Shutter :
1000 x 2000 mm
Country wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances and screws for planks
(Vide standard specification)
Total for each door
1200 x 2100 mm
Country wood
Labour, wrought and putup in position frame
& shutters

LS

cum
sqm
sqm

0.130
1.280
3.600

LS

cum
sqm

0.107
2.000

LS

cum
sqm

0.127
2.520

LS

cum
sqm

0.107
2.000

LS

cum
sqm

0.127
2.520

94

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-13

245

BLD-CSTN13-14

246

247

BLD-CSTN13-15

248

249

Sundries inclusive of putty, brads, hold fasts


and wind appliances and screws for planks
(Vide standard specification)
Total for each door
Furniture - 6 Butt Hings - 1 Top and 2 Bottom
Tower Bolts and One Wrought steel safety
Hasp L.S. (Schedule Item No. 298)
Each Door
Ledged Braced and Planked Doors (Schedule
Item No. 299)
Single Shutter :
800 x 2000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for
size - 2 Nos Chain and slopes country make.
Total for each door
1000 x 2100 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for
size - 2 Nos Chain and slopes country make.
Total for each door
Note : * Average rate for respective size
scantlings and rough planks.
** Note that for this type of door the
furniture will be supplied and fixed by the
contractor.
* Country wood Ledged Braced and Planked
Doors (Schedule Item No. 300)
800 x 2000 mm
Country wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for
size - 2 Nos Chain and slopes country make.

LS

cum
sqm

0.083
1.600

LS

LS

cum
sqm

0.100
2.100

LS

LS

cum
sqm

0.083
1.600

LS

LS

Total for each door


1000 x 2100 mm
95

STANDARD DATA BOOK BUILDING WORK ITEMS

Country wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances and nails for planks (Vide standard
specification)
** Furniture - 3 Nos T - hinges - Vide SS for
size - 2 Nos Chain and slopes country make.

BLD-CSTN13-16

250

BLD-CSTN13-17

252

0.100
2.100

LS

LS

Total for each door


** Note that for this type of door the
furniture will be supplied and fixed by the
contractor.
Note : * Class of Country wood to be defined
in relevent schedule item.
Flush type Doors with 35mm Thick Flush
Shutters with Bondwood solied Block Board
Type Faced on Both the sides with
Commercial Type Plywood (Schedule Item
No. 301.)
Single Shutter :
900 x 2000 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant
standard specification)
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)

251

cum
sqm

Total for each door


1000 x 2100 mm
*Teak wood
Flush Shutter 35mm thick (Vide relevant
standard specification)
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and all wind
appliances (Vide standard specification)

cum
sqm

0.035
1.530

sqm

1.800

cum
sqm

0.037
1.820

sqm

2.100

cum
sqm
sqm

0.028
0.390
0.720

Total for each door


*Note : Average rate for respective size
scantlings.
Windows Glazed (Schedule Item No. 302)
Single Shutter :
600 x 1200 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)

96

STANDARD DATA BOOK BUILDING WORK ITEMS

253

254

255

256

257

BLD-CSTN13-18

258

Total for each window


800 x 1200 mm
*Teak wood
cum
Glass
sqm
Labour, wrought and putup in position frame
sqm
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
Double Shutter :
1000 x 1200 mm
*Teak wood
cum
Glass
sqm
Labour, wrought and putup in position frame
sqm
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
1200 x 1200 mm
*Teak wood
cum
Glass
sqm
Labour, wrought and putup in position frame
sqm
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
1500 x 1200 mm (3 Pannels)
*Teak wood
cum
Glass
sqm
Labour, wrought and putup in position frame
sqm
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
1000 x 1700 mm (2 Pannels)
*Teak wood
cum
Glass
sqm
Labour, wrought and putup in position frame
sqm
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
*Note : Average rate for respective size scantlings.
Furniture for Double Leaf Windows Glazed
With Top Lights (Schedule Item No. 303)
Banel Bolts 100 mm long
each
Top tower bolts 150 mm long
each
Bottom bolts 150 mm long
each

0.037
0.500
0.960

0.041
0.700
1.200

0.061
0.710
1.440

0.072
0.920
1.800

0.059
0.970
1.700

2
2
2
97

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-19

BLD-CSTN13-20

BLD-CSTN13-21

259

260

261

262

263

264

265

Parliament hinges
Furniture for Double Leaf Windows Glazed
without Top Lights (Schedule Item No. 304)
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Parliament hinges
Same for all such windows
Furniture for Single Leaf Windows Glazed
without Top Lights (Schedule Item No. 305)
Top tower bolts 150 mm long
Bottom tower bolts 150 mm long
Parliament hinges
Same for all such windows
Windows Panelled (Schedule Item No. 306)
Single Shutter
600 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
700 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
Double Shutter
800 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
1000 x 12000 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
1200 x 1200 mm
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window

each
LS

each
each
each

2
2
4

LS
each
each
each

1
1
2

cum
sqm

0.039
0.720

cum
sqm

0.043
0.840

cum
sqm

0.051
0.960

cum
sqm

0.059
1.200

cum
sqm

0.081
1.440

98

STANDARD DATA BOOK BUILDING WORK ITEMS

266

BLD-CSTN13-22

267

268

269

270

*Note : Average rate for respective size


scantlings.
900 x 1200 mm
**Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of hold fasts and wind
appliances (Vide standard specification)
Total for each window
**Note : Average rate for respective size
scantlings and rough planks.
Windows Panelled & Glazed (Schedule Item
No. 307)
Single Shutter
600 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
Double Shutter
900 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
1200 x 1200 mm
**Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
1500 x 1200 mm (3 Pannels)
**Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty, brads, hold fasts
and wind appliances (Vide standard
specification)
Total for each window
**Note : Average rate for respective size
scantlings and rough planks.

cum
sqm

0.056
1.080

cum
sqm
sqm

0.036
0.070
0.720

cum
sqm
sqm

0.052
0.100
1.080

cum
sqm
sqm

0.077
0.120
1.440

cum
sqm
sqm

0.094
0.150
1.800

99

STANDARD DATA BOOK BUILDING WORK ITEMS

271

BLD-CSTN13-23

BLD-CSTN13-24

272

273

274

275

276

Furniture for Windows Panelled : Single Leaf


with half Shutters (Schedule Item No. 308)
Cabin hooks and eyes 200 mm long
Butt hinges 75 mm size
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
Furniture for Windows Panelled : Double Leaf
with half Shutters (Schedule Item No. 309)

each
each
each
each

2
4
1
1

Cabin hooks and eyes 200 mm long


Butt hinges 75 mm size
Top tower bolts 150 mm long
Bottom bolts 150 mm long
Same for all such windows
Teak Wood Windows - Ledged Braced and
Planked (Schedule Item No. 310)
600 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of all furniture and fitting
in accordance with relevant standard
specification
Total for each window
800 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of all furniture and fitting
in accordance with relevant standard
specification
Total for each window
900 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of all furniture and fitting
in accordance with relevant standard
specification
Total for each window
1000 x 1200 mm (half Shutters)
*Teak wood
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of all furniture and fitting
in accordance with relevant standard
specification
Total for each window
*Note : Average rate for respective size
scantlings and rough planks.

each
each
each
each

4
8
2
2

cum
sqm

0.034
0.720

LS

cum
sqm

0.048
0.960

LS

cum
sqm

0.052
1.080

LS

cum
sqm

0.052
1.200

LS

100

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-25

277

278

279

BLD-CSTN13-26

280

281

Ventilators Glazed - Fixed Double Frame and


with Wire Netting (Schedule Item No. 312)
800 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
1000 x 500 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
1200 x 600 mm
*Teak wood
Glass
Wire netting
Labour, wrought and putup in position
Sundries inclusive of putty brads and iron
hold fasts where such are necessary say in 30
cm wall.
Total for each Ventilator
*Note : Average rate for respective size
scantlings
Swing Ventilators - Glazed (Schedule Item
No. 313)
800 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.
Total for each Ventilator
1000 x 500 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.

cum
sqm
sqm
sqm
LS

0.012
0.240
0.190
0.400

cum
sqm
sqm
sqm
LS

0.014
0.310
0.240
0.500

cum
sqm
sqm
sqm
LS

0.018
0.480
0.290
0.720

cum
sqm
sqm

0.021
0.190
0.400

LS

cum
sqm
sqm

0.025
0.024
0.500

LS

Total for each Ventilator


101

STANDARD DATA BOOK BUILDING WORK ITEMS

282

BLD-CSTN13-27

283

1200 x 600 mm
*Teak wood
Glass
Labour, wrought and putup in position frame
& shutters
Sundries inclusive of putty brads sash centres
brass ring iron cleats and window card - vide
relevant standard specifications.

cum
sqm
sqm

0.030
0.390
0.720

LS

Total for each Ventilator


*Note : Average rate for respective size
scantlings and rough planks.
Aluminium Fixed Glazing
Supply and fixing of aluminimum fixed
glazing as per drawing using standard
powder coated/ anodised aluminimum
section of 101.4 x 44.45 x 3.18 mm thick
fitted with 6.0mm thick / 4.0 mm thick plain
glass glazing fitted with suitable Aluminimum
glazing clips and aproved brand silicon
sealant including cost and conveyance of all
materials labour charges for manufacturing
fixing in position using wooden blocks and
sheet metal screw etc. to complete for
finished item of work as approved by
Engineer-in-charge
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminimum Partition partly glazed

Kgs
sqm
Kgs
RM

as per design
as per design
as per design
as per design

day
day
day

0.947
1.158
0.105

day
day

0.211
0.632

Hrs

0.842

Hrs
Nos

1.684
0.211
1%

102

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-28

284

Supply and fixing of aluminimum Partition


partly glazed as per drawing using standard
powder coated/ anodised aluminimum
section of 101.4 x 44.45 x 3.18 mm thick
fitted with 12.0mm thick Particle Boards prelaminated up to 2.1 M height and balance
height provided with 5.0 mm thick plain glass
glazing fitted with suitable Aluminimum
glazing clips and aproved brand silicon
sealant including cost and conveyance of all
materials labour charges for manufacturing
fixing in position using wooden blocks and
sheet metal screw etc. to complete for
finished item of work as approved by
Engineer-in-charge
Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
PARTICLE BOARD - Prelaminated
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN13-29

285

Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium Anodised Casement windows

Kgs
sqm
sqm
Kgs
RM

as per design
as per design
as per design
as per design
as per design

day
day
day

1.042
1.042
0.104

day
day

0.139
0.347

Hrs

0.833

Hrs

1.111

Nos

0.174
1%

Unit - 1 sqm

103

STANDARD DATA BOOK BUILDING WORK ITEMS

Supply and fixing Aluminium Anodised


Casement windows as per approved drawing
with aluminium anodised sections of Series C
Jindal Hollow sections and outer frame of
8804 of size 46 x 44 mm, Shutter frame of
8802 of size 44 mm x 46 mm and Mullion
frame of 8803 of size 59 x 38 and glazing
section of 4433 with plain clear float glass 6
mm thick fixed including supply and fixing
aluminium powder coated 1 No.of casement
friction stay hinges for each shutter, 1 Nos.
aluminium handles of 150 mm for each
shutter and all labour charges for fixing the
fixtures with required no.of screws, bolts and
nuts and including labour charges for fixing
the frame in position, fixing shutter to frame
etc. completed for finished item of work

Unit - 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Friction stay casement
hinges
Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium
Two/ Three Track Sliding
Windows

Kgs
sqm
Kgs
RM
Each

as per design
as per design
as per design
as per design
as per design

Each

as per design

day
day
day

0.360
1.081
0.360

day
day

0.360
1.081

Hrs

2.883

Hrs

2.883

Nos

0.360
1%

104

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-30

286

Supply and fixing Aluminium Anodised Two/


Three Track Sliding Windows as per approved
drawing with aluminium anodised sections of
Series C Jindal sections and outer frame top
horizontals & both verticals of 8774 of size 62
x 29.5 mm and bottom horizontal - two track
frame of 8773 of size 62 x 29.5 mm, Shutter
frame top, bottom and verticals of 8304 of
size 50 mm x 20 mm and Weather
interlocking frame of 8306 of size 50 x 20
with plain clear float glass 5 mm thick fixed
including supply and fixing aluminium
handles of 100 mm for each shutter, nylon
rollers assembly and all labour charges for
fixing the fixtures with required no.of screws,
bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter
to frame etc. completed for finished item of
work
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges
Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
Aluminium Anodised Doors - Single Shutter

Kgs
sqm
Kgs
RM
Each

as per design
as per design
as per design
as per design
as per design

day
day
day

0.347
1.042
0.347

day
day

0.347
1.042

Hrs

2.778

Hrs

2.778

Nos

0.347
1%

105

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN13-31

287

Supply and fixing Aluminium Anodised Doors


- Single Shutter as per approved drawing with
aluminium anodised sections of Jindal
sections and outer frame top horizontals &
both verticals of 2408 of size 101.6 x 44.75 x
3.18 mm Shutter frame top, bottom and
verticals of 4504 of size 44.45 mm x 47.62
mm x 3.18 and Middle lock rail of 4621 of
size 49.91 x 44.45 x 3 mm with plain clear
float glass 5 mm thick fixed including supply
and fixing aluminium handles of 100 mm for
each shutter, floor springs/ hydraulic door
closure assembly and all labour charges for
fixing the fixtures with required no.of screws,
bolts and nuts and including labour charges
for fixing the frame in position, fixing shutter
to frame etc. completed for finished item of
work
UNIT 1 sqm
A) MATERIAL REQUIREMENT
ALUMINIUM SECTION
GLAZING with GLASS
SILICON SEALANT
RUBBER BEADING
Alum.Anodised.PC Handles
Hydraulic Floor Spring/ Door Closure
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Power Saw Cutter - Hand Operated Operator
Power Drill - Hand Operated - Operator
Unskilled Mazdoor
C) Machinery
Power Saw Cutter - Hand Operated - Hire
charges
Power Drill - Hand Operated - Hire Charges

BLD-CSTN14
BLD-CSTN14-1

Supervision Charges
Power charges for Motors
BASIC COST per 1 sqm
DISMANTLING & DEMOLITION
288

Kgs
sqm
Kgs
RM
Each
Each

as per design
as per design
as per design
as per design
as per design
as per design

day
day
day

0.417
0.833
0.417

day
day

0.417
1.250

Hrs

3.333

Hrs

3.333

Nos

0.417
1%

day
day

0.010
0.170

Removing white wash or colour wash by steel


wire brushing and/or scraping; sand papering
and preparing the wall surface smooth
including necessary repairs to scratches
complete
Details of cost for 10 sq.m
Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)

106

STANDARD DATA BOOK BUILDING WORK ITEMS

Sundries such as sand paper and scraper etc.

BLD-CSTN14-2

289

Scaffolding
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete
Deatailed cost for 10 sqm
Rate as per above item

BLD-CSTN14-3

290

10
sqm

Add 10 % extra for ceiling / sloping roof


Cost per 10 sq.m
Cost per sq.m
Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering
and preparing the wall surface smooth
including necessary repairs to scratches
complete for the wall surface spoiled by
smoke soot
Rate as per Item No (203)

10
sqm

For washing the wall surface spoiled by


smoke soot with clear water before sand
papering the surface smooth and including
necessary repairs to the scratches complete

BLD-CSTN14-4

291

Details of cost for 10 sq.m


Labour :
Mazdoor (unskilled)
Sundries
Add for water charges @ 1 %
Add for contractor's profit and overheads
Cost for 10 sq.m.
Cost per sq.m
Removing white wash or colour wash by steel
wire brushing and/or scraping; sand papering
and preparing the ceiling and/or sloping
roofs surface smooth including necessary
repairs to scratches complete for the ceiling
surface spoiled by smoke soot
Rate as per Item No (205)

day

0.080

10
sqm

Extra 10% for washing the surface with clean


water on ceiling and/or sloping roofs
Cost per 10 sq.m
Cost per sq.m

107

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN14-5

292

BLD-CSTN14-6

293

BLD-CSTN14-7

294

BLD-CSTN14-8

295

296

297

Washing and cleaning of decorated wall


surfaces with soap, soda and water
Details of cost for 10 sq.m
Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries such as soap, soda, sand paper and
scaper etc
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Washing and cleaning of the old plastered
ceiling and/or sloping roofs with soap, soda
and water
Rate as per Item above
Extra 10% over
Cost per 10 sq.m
Cost per sq.m
Washing and cleaning of oil and grease spots
on decorated wall surface by suitable
chemical
Details of cost for 10 sq.m
Labour :
White washer / Mason 2nd Class
Mazdoor (unskilled)
Sundries, such as chemical etc.
Add for water charges @ 1 %
Cost for 10 sq.m.
Cost per sq.m
Demolishing
and
disposal
of
unserviceable materials within 100 metres
lead
Lime concrete.
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Cost per cu m
Unreinforced cement concrete upto 15 cm
thicknes
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Cost per cu m
Unreinforced cement concrete more than 15
cm thickness
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Cost per cu m

day
day

0.010
0.170

day
day

0.010
0.170

day

1.220

day

2.440

day

4.880

108

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN14-9

298

299

BLD-CSTN14-10

BLD-CSTN14-11

BLD-CSTN15
BLD-CSTN15-1

300

Demolition including stacking of serviceable


materials and disposal of unserviceable
materials within 100 metres lead
R.C.C. work
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Cost per cu m
Brick work:
Details of cost for 1 cu.m.
Labour :Mazdoor (unskilled)
Sundries
Cost per cu m
Extra over item 14.2.ii for cutting steel bars in
R.C.C. of R.B. work (sectional area of R.C.C. or
R.B. Work to be measured) Details of cost for
one Sq.m. of sectional area
Reinforced area considering 1% Labour for
cuttings 0.01 Sq.m. reinforcement

301

Blacksmith 2nd class


Mazdoor (Male)
Sundries
Cost per sq m
Dismantling doors, windows and clear storey
windows, ventilators etc.; (wood or steel)
shutters including chowkhats, architraves,
hold fasts and other attachments etc.,
complete and stacking them within 100
metre lead

302

Not exceeding 3 sq.m. in area:


Details of cost per each
Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Cost per each
Exceeding 3 sq.m. in area
Details of cost per each
Labour :Mason, II class
Mazdoor (male)
Blacksmith II class
Sundries
Cost per each
MISCELLANEOUS BUILDING ITEMS

303

day

4.320

day

4.090

day
day

0.500
0.500

day
day
day

0.100
0.200
0.050

day
day
day

0.130
0.270
0.070

Providing and fixing aluminium step edging


'L' shape of size 38 mm x 12 mm x 3 mm
(thick) to stairs
109

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN15-2

BLD-CSTN15-3

BLD-CSTN15-4

304

305

306

Details of cost for 3 metres length


Materials:
Aluminium step edging 'L' shape 38 x 12 x
3mm (thick) = 3.00 metres with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint,
etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Cost for 3 m
Cost per m
Providing and fixing aluminium step edging
'L' shape of size 57 mm x16 mm x 3 mm
(thick) to stairs
Details of cost for 3 metres length
Materials:
Aluminium step edging 'L' shape 57 mm x16
mm x 3 mm (thick) with 5% wasage
Carriage of materials
Sundries (Wooden plugs, screws and painting
underneath of strips with bitumanistic paint,
etc.,)
Labour :Carpenter II class
Mason I class
Mazdoor (male)
Cost for 3 m
Cost per m
Cutting RCC steps for fixing of aluminium
step edging and make good to match the
surroundings
Details of cost for 3 metres
Cement Mortar
Labour :Mason, II Class
Mazdoor (male)
Cost for 3 m
Cost per m
Providing and fixing 25 mm bore galvanised
M.S. tube (light grade) outlet in cement
mortar 1:3(1 cement: 3 fine sand) including
cutting and making good the wall
Details of cost for 10 pipes 12.5 cm long day
i.e., 1.25 metres
Materials:
Galvanised mild steel tube (light grade) 25
mm nominal bore 10 x 12.5 cm = 1.25 metre
with wastage of 5%
Labour :For cutting and fixing in position

3.150

day
day
day

0.090
0.250
0.250

3.150

day
day
day

0.090
0.250
0.250

day
day

1.000
0.100

1.310

110

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN15-5

BLD-CSTN15-6

307

308

Assistant fitter
Mason.
Mazdoor (male).
Sundries
Cost for 1.25 m
Cost per m
Providing and fixing 1.80 metre long RCC
fencing posts with 6 mm bar nibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 pipes 12.5 cm long day
i.e., 1.25 metres
Materials:
Galvanised mild steel tube (light grade) 40
mm nominal bore 10 x 12.5 cm = 1.25 metre
with wastage of 5%
Labour :For cutting and fixing in position
Assistant fitter
Mason.
Mazdoor (male).
Sundries
Cost for 1.25 m
Cost per m
Providing and fixing 1.80 metre long RCC
fencing posts with 6 mm bar bibs as per
design in plate No. 22/2/2. (earth work &
concrete to be paid for separately)
Details of cost for 10 posts, i.e., 0.336 Cu. m
(Details as per Annexure ' X ' at the end of
this item)
Materials:
Cement concrete 1:2:4 (1 cement : 2 coarse
sand :4 graded stone aggregate 12.5 mm
nominal size)
(Rate as per item Concrete work)
M.S. reinforcement 6 mm dia bars
10 x
4 x 1.88 = 75.20 metres
10 x 9 x
0.50 = 45.00 metres./ l20.00 m 120.20 m @
0.22 Kg/m=26.44 Kg
(Rate as per item No.5.51 Section Concrete
work)
Centering and shuttering
(Details as per Annexure 'X')
(Rate as per item No.9.1.8. of Section 9 Form
work).
10 mm cement plaster with cement mortar
1:2 (1 cement: 2 sand)
(Details as per Annexure 'X')
Carriage of R.C.C. posts
6 mm bar bibs
Sundries

day
day
day

0.100
0.400
0.400

1.310

day
day
day

0.100
0.400
0.400

cum

0.336

kg

26.440

cum

0.336

sqm

9.880

111

STANDARD DATA BOOK BUILDING WORK ITEMS

Labour for fixing posts in line


Mason, 1st Class
Mason, 2nd Class
Mazdoor (Male)
Add Water charges on A @ 1%
Add Contractor's profit and overheads on 'A'
+ 'B' + 'C @ 10%
Cost for 10 posts
Cost per post
Sub Analysis :
Plastering with CM 1:3, 12 mm thick
Deduct - CM 1:3
Add - Cement (720-480 x .125)
Rate for 10 sqm
Rate per sqm
Annexure - 'X'
Details of quantities for RCC posts
Concrete quantity
Area of bottom A, =15+12.5/2 x 8.75+1/2 x
22/7 (6.25) = 120.31+61.38=181.69 Sq.m.
Area of top A2= 10+7.5/1 x 6.25 + 1/2 x 22 x
2
(3.75) / 7= 54.69+22.10=76.79 Sq.Cm.

day
day
day

0.120
0.120
0.250

10
sqm
cum
cum

1.000
0.025
30.000

Av A2 = 118.12 Sq. Cm.


Volume = h/3(A, + A2 + VA,A2)
A2+A2+A, A2=0.V03766 Sq.m
Volume = 1.05/3 * 0.03766 = 0.0131810
Cu.m. =0.0132 Cu.m.
Volume
of
lower
square
portion
=0.165x0.165x0.75 =0.0204 Cu.m
Total volume = 0.0336 Cu. m
Quantity for 10 posts = 0.336 Cu.m
Quantity of centring & shuttering 0.2770*
1.05=0.2908 Sq.m.
3x0.165x0.75=0.3712
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.6992 Sq.m..
For ten posts=10 x 0.6992 = 6.992 Sq.m.
Quantity
of
surface
plaster
area
12.50+7.60+7.60=27.70 Cm.
xr=3.1416x5=15.71Cm./43.41Cm 0.434 x
1.05=0.4560 Sq.m.
4x0.165x0.75=0.4950
0.165x0.165=0.0272
0.10 x 0.10=0.0100/0.9882 Sq.m.
For
10 posts = 10 x 0.9882=9.88 Sq.m.

112

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN15-7

BLD-CSTN15-8

BLD-CSTN16

309

310

Supplying and fixing galvanised steel barbed


wire (IS : 278-1962 Type I) weighing 9.38 Kg
per 100 metres (min.), Straining and fixing to
any type of standard, rails, straining bolts,
including securing with and provision of
galvanised mild steel wire, stapples or steel
pins, etc., as directed (Posts and struts of
wood, concrete, steel, etc.) and straining
bolts shall be paid for separately).
Details of Cost per 100 metres (day line of
wire)
Materials:
Galvanised steel barbed wire IS type I
weighing 9.38 Kg/100 metre
Carriage of barbed wire.
G.I. staples steel pins or binding wire
Labour :For fixing & stretching wire
Blacksmith, 1st Class
Blacksmith, 2nd Class
Mazdoor (male).
Sundries.
Add water charges @ 1 %
Cost for 100 metres day line of wire
Rate per m
Broken glass coping as specified on top of
walls
In cement mortar 1:3 (1 cement: 3 sand)
Details of cost per one Sq.m.
Materials:
Broken glass.
Cement mortar 1:3(1 cement: 3 sand)
Labour :Mason (Skilled)
Mazdoor (Male)
Scaffolding etc
Add water charges @ 1 %
Cost per Sq.metre
ANTE-TERMITE TREATMENT

kg

9.380

LS

day
day
day

0.150
0.150
0.300

kg
cum

19.500
0.040

day
day

0.080
0.160

113

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN16-1

BLD-CSTN17
BLD-CSTN17-1

311

Providing Antitermite treatment as per IS


6315 (Part - 2) 2001 (Pre-constructional
chemical treatment measures) along the
internal & external vertical faces of the
columns, plinth beams, basement and top
surface of the basement filling below flooring
bed as per the specified procedure
conforming to IS 6315 (Part-2) 2001 and
other relevant approved specification duly
using Chlorpyriphos/ Lindane emulsifiable
concentrate 20% with 1% concentration @
7.5 Liters/ sqm of the vertical surface & @
5.0 Liters/ sqm of the horizontal surface of
the substructure to a depth of 500 mm
around columns & 300 mm deep around
plinth beams, basements & floor filling area
including excavation channel along the wall &
rodding etc & cost & conveyance of all
materials to the site, cost of labour for
spraying, rodding etc complete for finished
item of work as per the approval of the
Engineer-in-Charge

Unit = 10 sqm
A) Chlorpyriphos/ Lindane emulsifiable
concentrate of 20%
1 liter : 19 Parts water Therefore: 868.55 L
/20
Add 12%wastage
Total Quantity
B) Add Water Charges @ 1%
C) Labour Charges
Man Mazdoor
Sprayer
D) Hire charges
Sprayer, drilling machine etc
sundries & contingencies
Water charges & electricity
Add OH & CP
BASIC COST per 1 sqm
CENTERING, FORM WORK etc.
312

Lit

4.100

Liters

0.41
4.51
1%

day
day

3.0
0.22
10%
3%
1.50%

Providing traditional centering, shuttering


and scaffolding using Casurina balli props and
bracings supporting wooden brackets,
wooden wall plates, wooden runners and
steel plate form work as per the approved
plan and other accessories as per the
standard trade practice including hire
charges for ballies, runners, wooden
members and cost and conveyance of all
other consumable accessories, taxes etc
complete for finished item of work

114

STANDARD DATA BOOK BUILDING WORK ITEMS

UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Wall Plate Brackets / beam bottom supports

313

314

Nos

2.40

Nos

1.44

Wedge Plate fixture


Runner beams of approximately 4" x 4" size

Nos
RM

1.44
16.00

Steel Plate - form work plates B) LABOUR CHARGES


1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Unsupported Roof Height up to - 4.60 M
(15'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Wall Plate Brackets / beam bottom supports

sqm

1.86

day
day
day
day

0.16
0.28
0.48
0.04
1%
1%
1%

Nos

4.32

Nos

1.44

Wedge Plate fixture


Runner beams of approximately 4" x 4" size

Nos
RM

1.44
16.00

Steel Plate - form work plates B) LABOUR CHARGES


1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Unsupported Roof Height up to - 7.30 M
(24'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Wall Plate Brackets / beam bottom supports

sqm

1.86

Nos
Nos
Nos
Nos

0.20
0.36
0.68
0.06
1%

Wedge Plate fixture


Runner beams of approximately 4" x 4" size

1%
1%

Nos

5.76

Nos

1.44

Nos
RM

1.44
16.00

115

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN17-2

315

Steel Plate - form work plates B) LABOUR CHARGES


1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Providing rigid Steel centering, shuttering
and scaffolding using steel pipes, adjustable
Jack screw props, acro spans, couplers, tie
rods, bracings members, supporting brackets,
acro span beams and steel plate/ ply-wood
form work as per the approved shuttering
designs & plan and other accessories as per
the IS Norms and stability calculations
including hire charges for jack pipes, acro
spans, runners, wooden members and cost
and conveyance of all other consumable
accessories, taxes etc complete for finished
item of work
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Approximately 33'-0" x 33'-0" roof area
Span Beams - 2.4 M Long (Acro Spans) Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates 9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor

sqm

1.86

Nos
Nos
Nos
Nos

0.28
0.52
1.08
0.08
1%
1%
1%

Kgs

62.51

day
day
day

0.22
0.38
0.72
116

STANDARD DATA BOOK BUILDING WORK ITEMS

316

BLD-CSTN17-3

317

Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Span Beams - 2.4 M Long (Acro Spans) Approximtely
Wallers, Couplers, Foot Plates
Steel Plate Beam Bottom - form work plates 9" wide
230 mm wide plate x 80 RM
Beam Sides - form work plates - 15" wide
400 mm wide plate x 80 RM - both sides
Slab Bottom Plates - formwork plates
3'-0" x 4'-0" - 7 Nos
3'-0" x 2'-0" - 2 Nos
1'-0" x 4'-0" - 1 Nos
Slab Sides - 0-6" Height - 40.0 RM
Total Scaffolding Pipes & Centering Plates Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm
Providing STAGE SCAFFOLD with staging
using Casurina balli props and bracings
supporting wooden brackets, wooden stage
scaffold boards including hire charges for
Casurina ballies, wooden baords, scaffolds
etc., and cost and conveyance of all other
consumable accessories, taxes etc complete
for finished item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES

day

0.04
1%
1%
1%

Kgs

112.635

day
day
day
day

0.32
0.52
1.28
0.06
1%
1%
1%

Nos

2.40

Nos

2.70

117

STANDARD DATA BOOK BUILDING WORK ITEMS

318

319

BLD-CSTN17-4

320

1st Class Carpenter


2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 4.60 M
(15'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.30 M
(24'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Providing ACCESS SCAFFOLD using Casurina
balli props and bracings supporting wooden
brackets, wooden stage scaffold boards
including hire charges for Casurina ballies,
wooden baords, scaffolds etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA

day
day
day
day

0.04
0.30
0.48
0.04
1%
1%
1%

Nos

4.32

Nos

2.70

day
day
day
day

0.08
0.38
0.68
0.06
1%
1%
1%

Nos

5.76

Nos

2.70

day
day
day
day

0.12
0.54
1.08
0.08
1%
1%
1%

UNIT 1 sqm
118

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN17-5

321

322

Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - 12'-0"
Height
Scaffold Boards - Bamboo scaffolds Bamboos - 8'0" long
B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
Providing STAGE SCAFFOLD using Steel
Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for PLAN AREA
UNIT 1 sqm
Unsupported Roof Height up to - 3.66 M
(12'0")
A) MATERIAL REQUIREMENT
Jack Screw Adjsutable Props - 50 mm dia B
Class Pipes
for vertical props placed @ 3'0" c/c in
bothways
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Unsupported Roof Height up to - 7.32 M
(24'0")
A) MATERIAL REQUIREMENT
Heavy Frames - 50 mm dia B Class Pipes (HD
Towers)
Lock Pins

Nos

1.74

Nos

0.72

day
day
day
day

0.07
0.11
0.2
0.04
1%
1%
1%

Kgs

39.26

day
day
day
day

0.04
0.34
0.60
0.04
1%
1%
1%

119

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN17-6

323

324

LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - PLAN AREA
Providing ACCESS SCAFFOLD using Steel
Scaffolding Pipe Frames made of 40 mmd ia
MS Pipes and bracings with scaffold boards
including hire charges for MS Pipe Frames
scaffolds boards etc., and cost and
conveyance of all other consumable
accessories, taxes etc complete for finished
item of work for ELEVATION AREA
UNIT 1 sqm
Up to - 3.66 M (12'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers
Total Scaffolding Pipes - Appx B) LABOUR CHARGES
1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
Up to - 7.32 M (24'0")
A) MATERIAL REQUIREMENT
MS Pipe Scaffold Frames - 1.20 x 1.50 M
Approximately 27.3 M Long x 3.66 M High
MS Pipe Bracing structure - 1.5 x 2.25 M
Scaffold Board
Lock Pins
LD Foot Plates
LD Couplers

Kgs

112.635

day
day
day
day

0.12
0.58
1.20
0.08
1%
1%
1%

Kgs

19.7496

day
day
day
day

0.07
0.11
0.24
0.04
1%
1%
1%

120

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN17-7

325

Total Scaffolding Pipes - Appx B) LABOUR CHARGES


1st Class Carpenter
2nd Class Carpenter
Unskilled Mazdoor
Supervision Charges
Consumables like Rope, Nails, de-shuttering
oil
Tape, cover plates
Tools like Hammers etc.,
BASIC COST per 1 sqm - VERTICAL ELEVATION
AREA
Fixing steel barricading with MS Angle Iron
Pegs and GI Pipes with nuts & bolts duly
excavating pits and its removal after the
function is over including transporting of the
entire barricading materials from the
Divisional stores to the barricading site duly
engaging labour to load, transport and
unload the materials at barricading site & as
per the schedule given by the departmental
authorities and loading back into the trucks,
unloading at Divisional stores, accounting for
the received materials, labour for loading,
unloading, fixing, handling etc, complete for
finished item of work
A) MATERIAL REQUIREMENT
a. MS Iron Angle Posts using ISA 65x65x6 mm
- 1.5 M long - 329 Nos in 1000 RM length 3015 Kgs
b. GI Pipes of 32 mm dia Nominal Bore
medium grade 2000 RM in 1000 RM length 6300 Kgs
c. Nuts & Bolts - 329 posts x 4 Nos = 1316
Nos in a length of 1000 RM - 130 Kgs
Total Barricading Weight - Appx
(if departmental material is used no hire
charges shall be calculated)
B) LABOUR CHARGES
a. for materials loading & carriage to work
spot

Kgs

19.14

day
day
day
day

0.12
0.22
0.44
0.04
1%
1%
1%

9445

Kgs

day

64.00

day

32.00

1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers


1 Night - (2 Days - 16 Hrs) 16 + 16 Numbers
b. for removal, unloading & return to stores
back
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
Total 64 Numbers
c. for fixing the barricading materials
1 Day ( 8 Hrs) - Men Mazdoor 16 Numbers
Night - (1 Day - 8 Hrs) 16 Numbers
Total 32 Numbers
BASIC COST per 1000 RM

121

STANDARD DATA BOOK BUILDING WORK ITEMS

BLD-CSTN17-8

326

Providing barricading arrangement with


casurina ballies as per the design duly
excavating pits and its removal after the
function is over including hire charges of the
barricading materials as per the schedule
given by the departmental authorities
complete for finished item of work
2 - TIER (2 Nos Horizontals- 6'-0" long - 1 No
Vertical -4'-0" High)
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - (50 Nos-4
RM & 55 Nos-2 RM = 200+110=310 RM/3.66
= 85 Nos, if 12'-0" long ballies are used)

BLD-CSTN17-9

327

B) LABOUR CHARGES
Unskilled Mazdoor
Consumables like Rope, Nails
Conveyance, loading & unloading etc
Tools like Hammers etc.,
BASIC COST per 100 RM
3 - TIER (3 Nos Horizontals- 6'-0" long - 1 No
Vertical -4'-0" High)
A) MATERIAL REQUIREMENT
Casurina Balli Props - 3" to 4" dia - (75 Nos-4
RM & 55 Nos-2 RM = 300+110=410 RM/3.66
= 112 Nos, if 12'-0" long ballies are used)
B) LABOUR CHARGES
Unskilled Mazdoor
Consumables like Rope, Nails
Conveyance, loading & unloading etc
Tools like Hammers etc.,
BASIC COST per 100 RM

BLD-CSTN17-10

328

Nos

85

day

12
1%
1%
1%

Nos

130

day

12.5
1%
1%
1%

cum
Kgs

1.00
95.00

day

0.10

day

2.36

Providing and laying cinder concrete in


cement cinder mix (1:15) prop. using 12.5
mm nominal size cinder laid in layers and
compacted as directed for filling sunken
floors including cost and conveyance of all
materials, water to work site, seigniorage
charges and all operational, incidental, labour
charges, such as mixing cement & cinder etc.
complete for finished item of work.
A) MATERIAL REQUIREMENT
Cost of Cinder
Cement
B) LABOUR CHARGES
st
Mason 1 class
Mazdoor (unskilled)

122

STANDARD DATA BOOK BUILDING WORK ITEMS

HIRE & LIFT CHARGES - for all Scaffolding Materials


a

Casurina Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Number of uses of Scaffolding materials =
U
(Rs. A - Rs. B)
U

Therefore, Hire Charges of scaffolding Materials:


b

Steel scaffolding pipes, jack Props, wallers, Foot plates, brackets, steel Centering Plates,etc., (As per relevant data item)
Cost of Scaffolding materials = Rs. A
Scrap value of Scaffolding materials = Rs. B (Usually B = A * 10%)
Period of Hire of Scaffolding materials, in years =
C
Life of Scaffolding materials, in years =
D
[(Rs. A - Rs. B)*C]
D

Therefore, Hire Charges of scaffolding Materials:


1
H
L

Sl

RATE ANALYSIS FOR HIRE CHARGES OF CENTRING & SCAFFOLDING MATERIALS FOR ALL R.C.C. STRUCTURAL MEMBERS - ANY HEIGHT
Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10
Rs.
Labour Charges
Rs.

NAME OF THE STRUCTURE COMPONENT


(b)

Qty

Unit

(a)
1

FOOTINGS

(c)
3.880

(d)
sqm

PEDESTALS

6.170

sqm

PLINTH BEAMS

9.350

sqm

LINTELS

7.940

sqm

CHAJJAS - SUNSHADES

1.220

sqm

COLUMNS

11.150

sqm

Hire
Charges
H
(e)

Labour
Charges
L
(f)

SubTotal
(H + L)
(g)

Duty Factor
C1
C1
(h)

Centring
Charges
(c)*(g)*(h)
(i)

Unit of Measurement
(j)
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 sqm of concrete
member
per 1 cum of concrete
123

STANDARD DATA BOOK BUILDING WORK ITEMS

BEAMS

9.350

sqm

SLABS - Up to 150 mm thick

1.050

sqm

SLABS - above 150 mm - Up to 300 mm thick

1.090

sqm

10

SLABS - above 300 mm thick

1.140

sqm

11

WAFFLE(GRID)SLABS(Rib Beams with Slabs)

3.850

sqm

12

PERGOLA SLABS (Only Rib Beams)

2.700

sqm

13

ARCHE BEAMS - up to 1.5 M Span

10.630

sqm

14

ARCHE BEAMS - above 1.5 M Span

10.780

sqm

15

DOME SLABS

17.190

sqm

16

HELICAL STAIRCASES

1.310

sqm

member
per 1 cum of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 sqm of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 cum of concrete
member
per 1 sqm of concrete
member

124

STANDARD DATA BOOK BUILDING WORK ITEMS

RATE ANALYSIS FOR HIRE CHARGES SCAFFOLDING MATERIALS FOR BRICK & STONE MASONRY
H
L

Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items
Labour Charges - as per Access Scaffolds items

Sl

SCAFFOLDING CHARGES FOR BRICK / STONE


MASONRY

(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

(b)
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor
11th Floor
12th Floor
13th Floor
14th Floor
15th Floor

16

....

Qty

Unit

(c)
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00
1.00

(d)
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm

...

...

Hire
Charges
H
(e)

Labour Charges
L
(f)

(g)
100%
150%
200%
250%
300%
350%
400%
450%
500%
550%
600%
650%
700%
750%
800%

Lift Charges
(f) * (g)
(h)

Rs.
Rs.
Duty
Factor C1
C1
(i)

Scaffolding Charges
[(e)+(h)]*(i)
(j)

...

125

STANDARD DATA BOOK BUILDING WORK ITEMS

RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR WALL PLASTERINGS, RCM WORKS - ANY THICK
H

Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Access Scaffold items

Rs.

Labour Charges - as per Access Scaffolds


items

Rs.

Sl

SCAFFOLDING CHARGES FOR BRICK / STONE


MASONRY

(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

(b)
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor
6th Floor
7th Floor
8th Floor
9th Floor
10th Floor
11th Floor
12th Floor
13th Floor
14th Floor
15th Floor

16

....

Qty

Unit

(c)
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00
10.00

(d)
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm
sqm

...

...

Hire
Charges
H
(e)

Labour Charges
L
(f)

(g)
100%
150%
200%
250%
300%
350%
400%
450%
500%
550%
600%
650%
700%
750%
800%

Lift Charges
(f) * (g)
(h)

Duty
Factor C1
C1
(i)

Scaffolding Charges
[(e)+(h)]*(i)
(j)

...

126

STANDARD DATA BOOK BUILDING WORK ITEMS

RATE ANALYSIS FOR HIRE CHARGES OF SCAFFOLDING MATERIALS FOR CEILING PLASTERINGS - ANY THICK
H
L

(a)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

Hire Charges of Steel scaffolding: a/365 (OR) Wooden scaffolding: b/10 - as per Stage Scaffold items
Labour Charges - as per Stage Scaffolds items
Hire
Labour Charges
Lift Charges
SCAFFOLDING CHARGES FOR BRICK / STONE
Qty
Unit Charges
MASONRY
H
L
(f) * (g)
(b)
(c)
(d)
(e)
(f)
(g)
(h)
1st Floor
10.00
sqm
100%
2nd Floor
10.00
sqm
150%
3rd Floor
10.00
sqm
200%
4th Floor
10.00
sqm
250%
5th Floor
10.00
sqm
300%
6th Floor
10.00
sqm
350%
7th Floor
10.00
sqm
400%
8th Floor
10.00
sqm
450%
9th Floor
10.00
sqm
500%
10th Floor
10.00
sqm
550%
11th Floor
10.00
sqm
600%
12th Floor
10.00
sqm
650%
13th Floor
10.00
sqm
700%
14th Floor
10.00
sqm
750%
15th Floor
10.00
sqm
800%

16

....

Sl

...

...

Rs.
Rs.
Duty
Factor C1
C1
(i)

Scaffolding Charges
[(e)+(h)]*(i)
(j)

...

127

STANDARD DATA BOOK BUILDING WORK ITEMS

Note
1
2
a
b
c
d
e
f
3

For Material Lift Charges & Labour rate for scaffolding above 7.32 M - increase @ 50% on labour component for each upper
floor on First Floor Rate (7.32 M)
For Hire Charges of scaffolding Materials following ratesmay be allowed:
Number of uses of Scaffolding materials (C )
Wooden Materials - No of Uses - 10 Times (C)
Period of Hire of Steel Scaffolding materials, in years =
1.64 (C )
Life of Steel Forms & Scaffolding Material - 3
Years (D)
Duty Factor - Steel Scaffolding
C1
0.500
Duty Factor - Wooden Scaffolding
C1
0.333
Add Area Allowances as applicable on labour
charges

128

STANDARD DATA BOOK BUILDING WORK ITEMS

RATE ANALYSIS FOR HIRE CHARGES OF BARRICADING MATERIALS


a

Casurina Ballies (As per relevant data item)


Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Number of uses of Barricading materials =
U
(Rs. A - Rs. B)
U

Therefore, Hire Charges of Barricading Materials:


b

Steel Barricading G.I. Pipes, Mild Steel IS Angles (As per relevant data item)
Cost of Barricading materials = Rs. A
Scrap value of Barricading materials = Rs. B (Usually B = A * 10%)
Period of Hire of Barricading materials, in years =
C
Life of Barricading materials, in years =
D
[(Rs. A - Rs. B)*C]
D

Therefore, Hire Charges of Barricading Materials:


H
L

Sl
(a)
1
3
4

Hire Charges of Steel Barricading: a/365 (OR) Wooden Barricading: b/10 - as per Barricading Item
Labour Charges: as per Barricading work
data items

NAME OF THE STRUCTURE COMPONENT


(b)
STEEL BARRICADING
WOODEN BARRICADING
2 - TIER
3 - TIER

Qty

Unit

(c)
1000.00

(d)
RM

100.00
100.00

RM
RM

Hire
Charges
H
(e)

No of
Days of
Hire
R
(f)

Rs.
Rs.

Duty
Factor

MaterialHire
charges

Labour
Charges

Barricading Charges

C1
(g)

(e*f*g)
(h)

L
(i)

(h) + (i)
(j)

129

STANDARD DATA BOOK BUILDING WORK ITEMS

Note
1

2
a
b
c
d
e
f
3

25% extra over the corresponding labour rates in respect of the work to be done during night time subject to issue of
certificate accordingly by the concerned estimate sanctioning authority for providing in the data and by concerned
Executive Engineer in charge of the work for payment. The night time allowance is applicable only to the works done under
Greater Hyderabad Municipal Corporation limits only
For Hire Charges of Barricading Materials following ratesmay be allowed:
Number of uses of woodenBarricading
materials (U )
Wooden Materials - No of Uses - 10 Times (U)
Period of Hire of Steel Barricading materials, in years =
1.64 (C )
Life of Steel Forms & Barricading Material - 3
Years (D)
Duty Factor - Steel Barricading
C1
0.500
Duty Factor - Wooden Barricading
C1
0.333
Add Area Allowances as applicable on labour
charges

130

STANDARD DATA BOOK BUILDING WORK ITEMS

LIFT CHARGES FOR ALL ITEMS OF WORKS


6

LIFT CHARGES - for all RCC Items


1. For Lift Charges of Labour, increase @ 10% on labour charges for each upper floor on Ground Floor Rate
2. For Lift Charges of Materials only, for lifting Concrete above 6.1 M (2nd floor onwards) Winch/ Lift hire charges may be
allowed at following rates:

Description of Structure
a. FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
b. COLUMNS, LINTELS, WATER TANKS, RCC WALLS
c. RCC SLABS, BEAMS

Basic Rate for 2nd


Floor (7.32 M)
Nil
1.333
0.267

Hrs
Hrs

for each additional


floor (3.66 M) over
and above 2nd
floor (7.32 M)
Nil
10%
10%

LIFT CHARGES - for Brick Masonry, all Plastering items, all Flooring items, HYSD Steel fabrication, impervious coats, RCM Works
1

For Lift Charges of Labour, increase @ 10% on labour charges of respective item for each upper floor on Ground Floor Rate

Add Area Allowances as applicable on labour


charges

9
1
2

LIFT CHARGES - for Scaffolding Works


For Lift Charges of Labour, increase @ 50% on labour charges of respective item for each upper floor on Ground Floor Rate
Add Area Allowances as applicable on labour
charges

131

STANDARD DATA BOOK LEAD CHARGES

LEAD/LIFT/LOADING & UNLOADING CHARGES

COM-LDLFT-1

DATA FOR LEAD CHARGES BY HEAD


LOAD :
Earth / Sand / Gravel / Murrum /
Lime / Surki / Coarse aggregate /
Rubble stone / Size stone / Cut
stone
LEAD UP TO 100 m
A) LABOUR
Mazdoor
Cost for 7 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 150 m
A) LABOUR
Mazdoor
Cost for 7 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
Cement/ HYSD Steel/ Structural
steel
LEAD UP TO 100 m
A) LABOUR
Mazdoor
Cost for 12 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 150 m
A) LABOUR
Mazdoor
Cost for 12 MT =
Contractor's profit and overhead
charges
RATE PER 1 CUM
PCC slab / Shahabad stone slab /
CC block / Laterite stone / BS slab /
Wood
LEAD UP TO 100 m
A) LABOUR
Mazdoor
Cost for 5.5 cum =
Contractor's profit and overhead
charges

Unit

Quantity

day

day

day

day

day

Rate Rs.

Amount
Rs.

132

STANDARD DATA BOOK LEAD CHARGES

RATE PER 1 CUM


6

COM-LDLFT-2

10

LEAD UP TO 150 m
A) LABOUR
Mazdoor
Cost for 5.5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
(Lead) Conveyance charges for machinery
per kilometer for transporting materials
by tippers and trucks excluding loading,
unloading and hire charges of machinery
Earth / Sand / Gravel / Murrum /
Lime / Surki /Coarse aggregate /
Rubble stone / Size stone / Cut
stone
LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges

day

Hr
Hr
Hr

0.15
0.15
0.15

Hr
Hr
Hr

0.21
0.21
0.21

Hr
Hr
Hr

0.28
0.28
0.28

Hr
Hr
Hr

0.34
0.34
0.34
133

STANDARD DATA BOOK LEAD CHARGES

Cost for 5 cum =


Contractor's profit and overhead
charges
RATE PER 1 CUM
11

12

13

14

15

LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 5 cum =
Contractor's profit and overhead
charges
RATE PER 1 CUM
Cement/ Steel/ Pipes/ RCC poles/
AC & GI sheets/ Packed materials
LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges

Hr
Hr
Hr

0.40
0.40
0.40

Hr
Hr
Hr

0.06
0.06
0.06

Hr
Hr
Hr

0.05
0.05
0.05

Hr
Hr
Hr

0.15
0.15
0.15

Hr
Hr

0.21
0.21

134

STANDARD DATA BOOK LEAD CHARGES

Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
16

17

18

19

20

LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges

Hr

0.21

Hr
Hr
Hr

0.28
0.28
0.28

Hr
Hr
Hr

0.34
0.34
0.34

Hr
Hr
Hr

0.40
0.40
0.40

Hr
Hr
Hr

0.06
0.06
0.06

Hr
Hr
Hr

0.05
0.05
0.05

135

STANDARD DATA BOOK LEAD CHARGES

Cost for 8 MT =
Contractor's profit and overhead
charges
RATE PER 1 MT
PCC slabs/ Shahabad slabs/ BS
slabs/ CC & Laterite blocks/ Wood
21

22

23

24

25

LEAD UP TO 1 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges

Hr
Hr
Hr

0.15
0.15
0.15

Hr
Hr
Hr

0.21
0.21
0.21

Hr
Hr
Hr

0.28
0.28
0.28

Hr
Hr
Hr

0.34
0.34
0.34

Hr
Hr
Hr

0.40
0.40
0.40
136

STANDARD DATA BOOK LEAD CHARGES

Cost for 3.4 CUM =


Contractor's profit and overhead
charges
RATE PER 1 CUM
26

27

28

29

30

LEAD UPTO 5 to 30 KM/ EVERY


KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Tipper charges
Fuel Charges
Crew charges
Cost for 3.4 CUM =
Contractor's profit and overhead
charges
RATE PER 1 CUM
WATER
LEAD UP TO 1 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges

Hr
Hr
Hr

0.06
0.06
0.06

Hr
Hr
Hr

0.05
0.05
0.05

Hr
Hr
Hr

0.15
0.15
0.15

Hr
Hr
Hr

0.21
0.21
0.21

Hr
Hr
Hr

0.28
0.28
0.28

137

STANDARD DATA BOOK LEAD CHARGES

Cost for 8000 Litres =


Contractor's profit and overhead
charges
RATE PER 1000 Litres
31

32

33

34

35

LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
LEAD BEYOND 30 KM/ EVERY KM
A) HIRE CHARGES
Water Tanker Charges
Fuel Charges
Crew charges
Cost for 8000 Litres =
Contractor's profit and overhead
charges
RATE PER 1000 Litres
BRICKS
LEAD UP TO 1 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges

Hr
Hr
Hr

0.34
0.34
0.34

Hr
Hr
Hr

0.40
0.40
0.40

Hr
Hr
Hr

0.06
0.06
0.06

Hr
Hr
Hr

0.05
0.05
0.05

Hr
Hr
Hr

0.15
0.15
0.15

138

STANDARD DATA BOOK LEAD CHARGES

Cost for 3000 Nos =


Contractor's profit and overhead
charges
RATE PER 1000 Nos
36

37

38

39

40

LEAD UP TO 1 to 2 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 2 to 3 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 3 to 4 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UP TO 4 to 5 KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos
LEAD UPTO 5 to 30 KM/ EVERY
KM
A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =

Hr
Hr
Hr

0.21
0.21
0.21

Hr
Hr
Hr

0.28
0.28
0.28

Hr
Hr
Hr

0.34
0.34
0.34

Hr
Hr
Hr

0.40
0.40
0.40

Hr
Hr
Hr

0.06
0.06
0.06

139

STANDARD DATA BOOK LEAD CHARGES

Contractor's profit and overhead


charges
RATE PER 1000 Nos
41

COM-LDLFT-3

LEAD BEYOND 30 KM/ EVERY KM


A) HIRE CHARGES
Truck 10 T Charges
Fuel Charges
Crew charges
Cost for 3000 Nos =
Contractor's profit and overhead
charges
RATE PER 1000 Nos

Hr
Hr
Hr

0.05
0.05
0.05

LOADING AND UNLOADING CHARGES BY MANUAL MEANS (idle hire charges of trucks
are not added)
42

LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 CUM

43

UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM

44

LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 CUM

45

day
day

0.02
0.50

day
day

0.01
0.25

UNLOADING
50% of the loading charges i.e.,
140

STANDARD DATA BOOK LEAD CHARGES

RATE PER 1 CUM


46

LOADING
Loading
of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1000 Nos

47

UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1000 Nos

48

LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 MT

49

UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT

50

LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
Contractor's profit and overhead
charges
RATE PER 1 MT

51

day
day

0.01
0.25

day
day

0.06
1.50

day
day

0.07
1.80

UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT
141

STANDARD DATA BOOK LEAD CHARGES

COM-LDLFT-4

LOADING AND UNLOADING CHARGES BY MANUAL MEANS (Including idle hire charges
of trucks )
52

LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone for Masonry
Work by manual means including a
lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM

53

UNLOADING
50% of the loading charges i.e.,
RATE PER 1 CUM

54

LOADING
Loading of Earth, Sand, Murrum,
Manure, Fly-Ash, by manual means
including a lead upto 30 m
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM

55

UNLOADING
Unit = cum
Taking output = 5.5 cum
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 CUM

day
day

0.02
0.50

Hour

0.50

day
day

0.01
0.25

Hour

0.500

day
day

0.005
0.125

Hour

0.166

142

STANDARD DATA BOOK LEAD CHARGES

56

57

58

LOADING
Loading
of Bricks-1000 Nos
(Regular sizes - 225x140x70 mm)
by manual means including a lead
upto 30 m
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1000 Nos
UNLOADING & STACKING
Unit = 1000 Nos
Taking output = 2000 Nos
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1000 Nos

0.01
0.25

Hour

0.33

day
day

0.06
1.50

Hour

1.00

day
day

0.06
1.50

Hour

1.00

day
day

0.07
1.80

Hour

1.00

LOADING
Loading of Cement by manual
means including a lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 MT

59

day
day

UNLOADING & STACKING


Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T

143

STANDARD DATA BOOK LEAD CHARGES

Contractor's profit and overhead


charges
RATE PER 1 MT
60

61

COM-LDLFT-5

LOADING
Loading of Structural Steel, Steel
Bars by manual means including a
lead upto 30 m
Unit = 1 MT
Taking output = 10 MT
A) LABOUR
Head Mazdoor
Mazdoor
B) MACHINERY
TRUCK - 10 T
Contractor's profit and overhead
charges
RATE PER 1 MT

day
day

0.07
1.80

Hour

1.00

UNLOADING & STACKING


100% of the loading charges i.e.,
RATE PER 1 MT
LOADING AND UNLOADING CHARGES BY MECHANICAL MEANS (including idle hire
charges of trucks)

62

LOADING
Loading of Lime, Aggregate, Stone
Boulder, Brick Aggregate, Kankar,
Building Rubbish, Building Rubbish,
Crushed Slag, Stone by mechanical
means including a lead upto 30 m
placing a tipper at loading point ,
loading with front end loader
excluding time for haulage and
return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading
point
ii) Loading by front end loader 1
cum bucket capacity
@ 45 / 25 cum per hour
iii) Manoevouring, reversing,
dumping and turning
for return
iv) Waiting time, unforeseen
contingencies, etc.
Total
A) MACHIENRY
Tipper 10 t capacity

Min

1.00

Min

7.33

Min

Min

2.00

Min

10.33
hour

0.17

144

STANDARD DATA BOOK LEAD CHARGES

Front end-loader 1 cum bucket


capacity @ 45 cum
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5
63

0.12

Loading of Earth, Sand, Murrum,


Gravel,
Manure, Fly-Ash, by
mechanical means including a lead
upto 30 m placing a tipper at
loading point , loading with front
end loader excluding time for
haulage and return trip
Unit = cum
Taking output = 5.5 cum
Time required for
i) Positioning of tipper at loading
point
ii) Loading by front end loader 1
cum bucket capacity
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen
contingencies, etc.
Total
A) MACHINERY
Tipper 10 t capacity
Front end-loader 1 cum bucket
capacity @ 45 cum
per hour
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5

64

hour

Min

1.00

Min

3.30

Min

2.00

Min

6.30
hour
hour

0.11
0.06

UNLOADING
Unloading
of Earth, Sand,
Murrum, Gravel, Manure, Fly-Ash,
Lime, Aggregate, Stone Boulder,
Brick Aggregate, Kankar, Building
Rubbish, Building Rubbish, Crushed
Slag, Stone by mechanical means
including a lead upto 30 m placing
a tipper at loading point , loading
with front end loader excluding
time for haulage and return trip
Placing tipper at unloading point,
excluding time
for haulage and return trip.
Taking output = 5.5 cum
Time required for
145

STANDARD DATA BOOK LEAD CHARGES

i) Positioning of tipper at loading


point
ii) Loading by front end loader 1
cum bucket capacity
@ 45 / 25 cum per hour
iii) Waiting time, unforeseen
contingencies, etc.
Total
A) MACHINERY
Tipper 10 t capacity
Cost for 5.5 cum =
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/5.5
COM-LDLFT-6

Min

1.00

Min

2.00

Min

2.00
5.00
hour

0.08

LIFT CHARGES FOR MATERIALS BY HEAD LOAD


65

LIFT UPTO 3.00 M


FOR CATEGORY : Earth / Sand /
Gravel / Murrum / Lime / Surki /
Coarse aggregate /
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.
Lift charges are admissible only
lifting effort beyond initial lift
specified in the work item.

66

ADDITIONAL LIFT CHARGES FOR


each 1 METER LIFT BEYOND 3 M
INITIAL LIFT
For additional lift of 1m beyond
initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by
head load
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 60 )
No. of trips per day for lift 1.0 m
above 3 m ( 8 x 60 / 0..12)
Quantity of material by head load
Quantity of material by head load
per day ( 4000x 0.015 )
Deploy 1 mazdoor for every
additional lift of 1.0 m beyond
initial lift.
A) LABOUR
Mazdoor
b) contractor's profit and
overhead charges

60 M/
minute

min

0.12
4000

cum
cum

0.015
60

day

1.00

146

STANDARD DATA BOOK LEAD CHARGES

Rate per cum = (a+b)/60


67

LIFT UPTO 3.00 M


FOR CATEGORY : Cement Bag/
Reinforcement Steel/ Structural
Steel sections
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.
Lift charges are admissible only
lifting effort beyond initial lift
specified in the work item.

68

ADDITIONAL LIFT CHARGES FOR


each 1 METER LIFT BEYOND 3 M
INITIAL LIFT
For additional lift of 1m beyond
initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by
head load
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 25 )
No. of trips per day foradditional
lift 1.0 m above 3 m ( 8 x 60 / 0.29)

69

25 M/
Minute

min

0.29
1655

Quantity of material by head load

kgs

50

Quantity of material by head load


per day ( 1655x50x 0.015 )
Deploy 1 mazdoor for every
additional lift of 1.5 m beyond
initial lift.or2/3 mazdoor
A) LABOUR
Mazdoor
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/83

tons

83

day

1.00

LIFT UPTO 3.00 M


FOR CATEGORY : PCC slab /
Shahabad stone slab / CC block /
Laterite stone / BS slab / Wood
FOR CATEGORY : Cement Bag/
Reinforcement Steel/ Structural
Steel sections
This is the initial lift and forms
integral part of the activities in the
basic rate of work item.

147

STANDARD DATA BOOK LEAD CHARGES

Lift charges are admissible only


lifting effort beyond initial lift
specified in the work item.
For additional lift of 1m beyond
initial lift of 3 m
one meter lift is taken equivalent
to 6 meters lead
average speed of conveyance by
head load
Round trip cycle time for 1.00 m
considering 50 min/ hr working
1 x6x 60 / 50 / 40 )
No. of trips per day for lift 1.0 m (8
x 60 / 0.18 )
Quantity of material by head load
Quantity of material by head load
per day ( 1667x 0.018 )
Deploy 1 mazdoor for every
additional lift of 1.5 m beyond
initial lift.or2/3 mazdoor
A) LABOUR
Mazdoor
b) contractor's profit and
overhead charges
Rate per cum = (a+b)/45

25 M/
Minute

min

0.18
2667

cum

0.017

cum

45

day

1.00

148

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

STANDARD DATA ELECTRICAL ITEMS FOR BUILDINGS


PREAMBLE
The Standard Data for Electrical Works are prepared based on the relevant BIS
Specifications in conjunction with National Electric Code. Similarly the method of execution
shall be as per the provisions contained in IE Rules and National Electric Code.
The following are the Chapters.
CHAPTER 1 : CONDUIT LAYING
This chapter contains conduit laying i.e. M.S. Conduit, PVC Pipe and PVC Casing and
Capping. The MS Conduit shall be finished with stone enameled surface. The MS Conduit
accessories shall be threaded type only. The conduit shall be joined by means of screwed
couplers and screwed accessories only.
The PVC Pipe should confirm with relevant IS Specifications. PVC casing and capping
is meant of emergency and additional points only.
For LAN / Telephone / Computer Separate Conduit should be laid.
CHAPTER 2 : WIRING
This unit comprises of copper wiring for light points and fan points. Further,
electrical accessories such as Plug Sockets, Batten Holders, Call Bells etc., are provided in this
chapter.
The PVC insulated and flexible copper wires shall be Fire Retardant and confirm to
IS 694. The colour code for wires shall be followed strictly for the entire installation as
follows :
R Red
Y Yellow
B Blue
B Black
G Green

For Phases
-----

For Neutral
For Earth

All Switch boards for neutral conduit wiring shall be fabricated with CRCA Sheet
Steel from 1.6 mm (16 SWG) thick with 7 tank process and powder coating or Hot dip
galvanized boxes.
The mounting height of boards (Bottom of Box) shall be as follows :
a) All Switch Boards

1.32 m from FFL (Finished Floor Level)

b) 16 A Power Plugs
and Metal Sockets

Sill Level of the Window

c) 16 A Power Plugs
and Metal Sockets in Kitchen :

Above 30 cm on Platform

d) MCB Distribution Board

2 m from FFL

The entire installation shall be tested for


(i)

Installation Resistance

(ii)

Earth Continuity

149

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

CHAPTER 3 : RUN OF MAINS


This chapter contains run of mains and circuit mains from Main Distribution Board to
Sub-distribution Boards and Sub-distribution Boards to Switch Boards. All the cables shall
confirm to IS : 694 and if fire retardant.

CHAPTER 4 : SWITCH GEAR & MCB DISTRIBUTION BOARD


This chapter contains of Switch Disconnection Fuse (SDF), On-Load Change Over
Switches (OLCOS), Moulded Case Circuit Breakers (MCCB), Distribution Boards (DB),
Miniature Circuit Breakers (MCB), Isolators, Residual Current Circuit Breakers (RCCB), Earth
Leakage Circuit Breakers (ELCB). The following are the relevant I.S. Specifications for the
Switchgear.
(i) SDF

---

IS : 13947 (Part 3) 1993

(ii) OLCOS

---

IS : 13947 (Part 3) 1993

(iii) MCCB

---

IS : 13947 (Part 2) 1993

(iv) MCB

---

IS : 8828 : 96

(v) Isolator

---

IS : 13947 (Part 3) 1993

(vi) RCCB / ELCB

---

IS : 12640 - 1 : 2000

(vii) DISTRIBUTION BOARD IS : 13032


The Distribution Board shall have vermin, dust and rust proof as per IP 20 and IP
42 protections.
An earth leakage circuit breaker of sufficient rating earth leakage shall be provided
on the low voltage side to detect the leakage in x-ray installation, as per Rule 73 (ee) of IE
Rules.
CHAPTER 5 : EARTHING
This chapter comprises of GI Pipe earthing, Copper Plate earthing, Earth Lead &
Earth Strip.
The earthing should be provided for all power consuming devices as per IS
Specifications. Copper Plate earthing shall be provided for sophisticated electronic
equipment.
The Earthing Work shall confirm to the IS : 732.
CHAPTER 6 : SERVICE MAINS & LTOH LINES
Weather Proof Single Core (WPSC) and Weather Proof Twin Core (WPTC) Service
Cables are provided in this chapter. Accessories for LTOH Lines, PSCC Poles are also covered
under this chapter.
The supports for overhead lines shall be of adequate strength confirming in all
respects to Rule 76 of IE Rules. The insulators shall confirm to IS : 1445. The OH Conductor
(AAAC) shall confirm with IS : 398.
CHAPTER 7 : STREET LIGHT LUMINARIES
In this chapter, Florescent Luminaire, MV Luminaire, SV Luminaire, Metal Halide
Luminaire, Post Top Luminaire, Well Glass Luminaire and Flood Light Luminaire are covered.
150

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

Provision of SV/ MV / MH Lamps shall be restricted to Non-residential buildings and


residential buildings where security is involved such as residences of Honble Judges, Honble
Ministers, IAS / IPS Bungalows, IBs, Guest Houses and Security Lighting keeping in view of
the increase in current consumption charges.
CHAPTER 8 : INTERNAL LUMINAIRE
This chapter is meant for Internal Illumination. General Luminaire, Fluorescent
Luminaire, Industrial Luminaire, Mirror Optic Fittings, T-5 Luminaire, CFL / Halogen Down
Lights are covered under this chapter. It is suggested to provide compact Fluorescent Lamps
/ T- 5 Lamps where minimum lux level is required so as to conserve the electrical energy.

CHAPTER 9 : AC AND REFRIGERATION , FANS


Window type, Split type AC Units, Refrigerators, Ceiling fans and exhaust fans are
covered under this chapter.
The Air-condition Units shall confirm to IS : 1391, Refrigerators shall confirm to IS :
1476 and ceiling fans shall confirm IS : 374.
CHAPTER 10 : WATER HEATERS
This chapter comprises of Water Heaters and their accessories and repairs.
The Water Heater shall confirm to IS : 2082. Effective earthing shall be provided to
Water Heaters.
CHAPTER 11 : WATER PUMPS
In this chapter, Mono Block Pumps, Jet Pumps, Submersible Pumps (Bore well type
& Open well type) along with their accessories are covered.
Data for pump sets are prepared excluding the suction and delivery pipes. The pump
sets shall confirm to IS : 9079 and other relevant specifications where ever exist. For the
items covered under Civil SSR, rates have to be carried from Civil SSR.
CHAPTER 12 : BUS BARS
CHAPTER 13 : SWAGED POLES
DIFFERENT SIZES OF Swaged Poles as per IS : 2713 / 1980 are proposed in this
chapter with necessary brackets, garden posts and accessories.
The classification of roads and recommended assignment of MS Poles shall be as per
Part 5, out door installation of National Electric Code.
CHAPTER 14 : CONTROL PANEL & METERING EQUIPMENT
The Control Panel Board shall be :
(i)
(ii)
(iii)
(iv)

Of the metal enclosed, indoor, floor mounted, free standing type.


Made up of the requisite vertical sections when compiled together shall
form continuous dead front switch boards.
Provide dust and damp protection, the degree of the protection being not
less than IP 51.
Readily extendable on both sides by the addition of vertical sections after
removal of end covers.

The height of the panel board should not be more than 2400 mm. The depth of the
panel should be adequate to cater proper cable termination.
151

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

All the Steel Work used in the construction of the panel boards should have
undergone a rigorous metal treatment process i.e. 7- tank process.

CHAPTER 15 : CABLES / CABLE GLANDS / LUGS


In this chapter, Armoured under ground cables with their accessories are provided.
The armoured cables shall confirm with IS : 1554 and XLPE cables shall confirm with
IS : 7098.
Manufacturer test report shall be submitted for tests on cables in accordance with
BIS specifications. Cables shall be tested after installation and before commissioning by the
using 1100 volts meggar and the following reading shall be obtained.
a) Continuity of all conductors
b) Insulation Resistance
(i)
Between conductors
(ii)
All conductors and ground.
Cable glands shall be provided wherever the armoured cables are connected to
Distribution boards. Cable laying and terminations shall confirm to IS : 1255. Earthing of
cable glands shall confirm to IS : 3043.
Cables if laid underground shall be at a depth of not less than 600 mm in a trench.
Sand filling shall be provided at the bottom of trench before laying the cable. Bricks shall be
provided on either side of the laid cable. Sand filling shall be done to cover the cable laid.
Bricks shall be provided on top. Earth filling shall be done. Cable identification tags to be
provided at every 8 m length of cable laid.
GI Pipe / RCC Hume Pipe / Double Corrugated PVC / HDPE Pipe shall be provided for
cable protection to with stand wear and tear of Vehicular Traffic at road crossings.
Cables shall bent to a radius of 20 times diameter of the cable with a minimum of 10
times the diameter at restricted space.
Ladder or perforated type cable trays shall be provided if cable laid inside the
buildings and shall be properly clamped to the trays by plated MS Saddles at proper
intervals.

CHAPTER 16 : TEMPORARY ILLUMINATION


This chapter provides Hire charges for temporary lighting arrangements. Data are
worked out based on the observed data. However, statutory service charges or VAT shall be
added to the data at prevailing rate of percentages

CHAPTER 17 : GENERATORS AND TRANSFORMERS


The Alternator shall confirm with IS : 13364 of 1992 and Diesel Engine shall confirm
with IS : 10001 and IS 10002. Transforms, substation equipment, substation maintenance
and protective gear data are provided in this chapter.
The transformers shall be designed, manufactured and tested as per IS : 2026. For LT
bulk supply, only Core Self Protected (CSP) type aluminum wound distribution transformers
152

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS - PREAMBLE

of 63 KVA / 100 KVA shall be proposed. Where HT supply is required, only copper wound
distribution transformers are to be proposed.
The lightening arrestors shall confirm to IS : 3070 and the protection against the
lightening shall be in accordance with Rule 92 of IE Rules.

CHAPTER 18 : REPAIRS TO MOTORS & REWINDING


All the miscellaneous repairs to motors & fans are covered under this chapter.

153

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Standard Data - Electrical Items For Buildings


Index-code

Specifica
tion No.
1

BLD-ELEC-1
BLD-ELEC-1
BLD-ELEC-11

1
1.1
1.1.1

1.1.2

Description
2
Conduit Laying
MS / PVC / Trunks Coduit Laying
M.S.CONDUIT (Surface)

Unit

Quant
ity

Rate
Rs.

Amou
nt Rs.

Remarks

Supply and Fixing of 20mm dia 16 SWG


(ISI Mark) MS Surface conduit pipe duly
threading at Joints with all required
accessories fixing on T.W. Separators
with chromium plated base saddles
and No.18 SWG MS box for light, fan
and separate plug points including cost
of Cement, all materials, accessories
and all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 16 SWG MS conduit
T.W seperators
30mm Screws No.8
Rawal Plugs
12mm Screws
20mm Saddles MS
20mm 1,2,3 & 4 way Junction box
20mm dia HG bends
200mm x 250mm sheet metal deep
box
Cement (As per civil SSR)
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 25mm dia 16 SWG
(ISI MARK) MS Surface pipe duly
threading at Joints with all required
accessories fixing on T.W. Seperators
with chromium plated base saddles
and No.18 SWG MS box for run of
mains including cost of Cement, all
materials, accessories and all labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 16 SWG MS conduit
T.W seperators
38mm Screws No.8
Rawal Plugs

Note for
All Items
for
Coduit
Laying

100 M
100 Nos
100 Nos
100 Nos
100 Nos
100 Nos
Dozen
Dozen
Each

1
2
2
2
4
2
1
1
3

kg

12.5

day
day
day

3
3
3

100 M
100 Nos
100 Nos
100 Nos

1
1.5
1.5
1.5
154

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.1.3

BLD-ELEC-12

1.2
1.2.1

12mm Screws
25mm Saddles MS
25mm 1,2,3 & 4 way Junction box
25mm dia HG bends
Cement (As per civil SSR)
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 32mm dia 16 SWG
(ISI MARK) MS Surface pipe duly
threading at Joints with all required
accessories fixing on T.W. Seperators
with chromium plated base saddles
and No.18 SWG MS box for run of
mains including cost of Cement, all
materials, accessories and all labour
charges etc., complete.
Unit = 1Metre
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit
T.W seperators
38mm Screws No.8
Rawal Plugs
12mm Screws
32mm Saddles MS
32mm 1,2,3 & 4 way Junction box
32mm dia HG bends
Cement (As per civil SSR)
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
MS Conduit Concealed

100 Nos
100 Nos
Dozen
Dozen
kg

3
1.5
0.5
1
12.5

day
day
day

3
3
3

100 M
100 Nos
100 Nos
100 Nos
100 Nos
100 Nos
Dozen
Dozen
kg

1
1.5
1.5
1.5
3
1.5
0.5
1
12.5

day
day
day

3
3
3

Supply and Fixing of 20mm dia 16 SWG


(ISI Mark) MS concealed conduit, duly
threadig at Joints, on wall with
required
accessories
including
chiselling the wall for light, Fan and
separate
plug
point
including
necessary sheet metal deep boxes,
masonsary work and all labour charges
etc. complete.
Taking Output = 100 M
a) Material
155

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.2.2

1.2.3

20mm dia 16 SWG MS conduit pipe


U' Nails
200mm x 250mm sheet metal deep
box
20mm HG bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 25mm dia 16 SWG
(ISI MARK) MS concealed conduit, duly
threadig at Joints in Slab and on wall
with required accessories including
chiselling the wall and necessary
Masonary and all labour charges etc.
complete for run of mains.
Taking Output = 100 M
a) Material
25mm dia 16 SWG MS conduit pipe
U' Nails
25 mm Deep Junction Box
25mm HG bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 32mm dia 16 SWG
(ISI Mark) MS concealed conduit, duly
threadig at Joints in Slab and on wall
with required accessories including
chiselling the wall and necessary
Masonary and all labour charges etc.
complete for run of mains.
Taking Output = 100 M
a) Material
32mm dia 16 SWG MS conduit pipe
U' Nails
32 mm Deep Junction Box
32mm HG bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician

100 M
100 Nos
Each

1
2
3

Dozen
kg

1
12.5

day
day
day
day

3
3
3
3

100 M
100 Nos
Dozen
Dozen
kg

1
2
1
1
50

day
day
day
day

3
3
3
3

100 M
100 Nos
Dozen
Dozen
kg

1
2
1
1
50

day
day

3
3
156

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

BLD-ELEC-13

1.3
1.3.1

1.3.2

Helpers
day
Mason Ist class
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
NOTE : For Laying MS Concealed Conduit pipe in roof
Slab, deduct the Cost of Cement and U' Nails.
P.V.C. Conduit (Surface)

3
3

Supply and Fixing of 20mm dia 1.5mm


thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles and
decolam board for switches for Light,
Fan and separate plug point including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
20mm 1,2,3, & 4 way Junction boxes
20mm PVC Bends
8" x10" Decolam Board
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 25mm dia 1.5mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
25mm 1,2,3, & 4 way Junction boxes
25mm PVC Bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries

100 M
100 Nos
100 Nos
Each
Each
Each
Each
kg

1
2
2
200
12
12
3
25

day
day
day

2
2
2

100 M
100 Nos
100 Nos
Each
Each
Each
kg

1
2
2
200
12
12
25

day
day
day

2
2
2

157

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.3.3

1.3.4

1.3.5

C) Cost for 100 RM


Rate per Metre = C/100
Supply and Fixing of 32mm dia 2mm
thick surface P.V.C. pipe (ISI Mark) with
all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains
Taking Output = 100 M
a) Material
32mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
32mm 1,2,3, & 4 way Junction boxes
32mm PVC Bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 40mm dia 2mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.
Taking Output = 100 M
a) Material
40mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
40mm 1,2,3, & 4 way Junction boxes
40mm PVC Bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 50mm dia 2mm
thick surface P.V.C. pipe (ISI MARK)
with all accessories fixing on chromium
plated metallic base saddles including
all labour charges etc., complete for
run of mains.

100 M
100 Nos
100 Nos
Each
Each
Each
kg

1
2
2
200
12
12
25

day
day
day

2
2
2

100 M
100 Nos
100 Nos
Each
Each
Each
kg

1
2
2
200
12
12
25

day
day
day

2
2
2

Taking Output = 100 M


158

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

BLD-ELEC-14

1.4
1.4.1 (a)

(b)

a) Material
50mm dia 1.5mm thick PVC pipe
Rawl Plugs
35mm Screws
Chromium Plated saddles with base
50mm 1,2,3, & 4 way Junction boxes
50mm PVC Bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
P.V.C. Conduit (Concealed)

100 M
100 Nos
100 Nos
Each
Each
Each
kg

1
2
2
200
12
12
25

day
day
day

2
2
2

100 M
100 Nos
Each
Each

1
2
3
12

Each
kg

12
50

day
day
day
day

2
2
2
2

100 M
100 Nos
Each

1
2
3

Supply and Fixing of 20mm dia 2mm


thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 2mm thick PVC pipe
U' Links
10" x 8" Wooden deep box
20mm dia 1,2,3 & 4 way deep Junction
Box
20mm PVC bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 20mm dia 1.5mm
thick P.V.C. pipe (ISI MARK) concealed
in wall with all required accessories
including masonary work for light, fan
and separate plug point with well
seasoned wooden deep box including
all labour charges etc., complete.
Taking Output = 100 M
a) Material
20mm dia 1.5mm thick PVC pipe
U' Links
10" x 8" Wooden deep box

159

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.4.2
(a)

(b)

20mm dia 1,2,3 & 4 way deep Junction


Box
20mm PVC bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 25mm dia 2mm
thick PVC pipe (ISI MARK) concealed in
wall with all required accessories
including masonary work and labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 2mm thick PVC pipe
U' Links
25mm dia 1,2,3 & 4 way deep Junction
Box
25mm PVC bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Fixing of 25mm dia 1.5mm
thick PVC pipe (ISI MARK) concealed in
wall with all required accessories
including masonary work and labour
charges etc., complete.
Taking Output = 100 M
a) Material
25mm dia 1.5mm thick PVC pipe
U' Links
25mm dia 1,2,3 & 4 way deep Junction
Box
25mm PVC bends
Cement
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Mason Ist class
Sundries
C) Cost for 100 RM

Each

12

Each
kg

12
50

day
day
day
day

2
2
2
2

100 M
100 Nos
Each

1
2
12

Each
kg

12
50

day
day
day
day

2
2
2
2

100 M
100 Nos
Each

1
2
12

Each
kg

12
50

day
day
day
day

2
2
2
2

160

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Rate per Metre = C/100


Supply and Fixing of 25mm dia 2mm
thick PVC pipe (ISI MARK) concealed in
Roof Slabs with all required accessories
including masonary work and labour
charges etc., complete.

BLD-ELEC-15

1.5
1.5.1

1.5.2

Taking Output = 100 M


a) Material
25mm dia 2mm thick PVC pipe
100 M
25mm dia 1,2,3 & 4 way deep Junction
Each
Box
25mm PVC bends
Each
b) Labour charges :
Skilled Electrician
day
Semi skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : 1. If 25mm dia PVC / MS pipes are used for
light / fan point, add the cost of sheet metal / well
seasoned wooden board / box.
P.V.C. Casing and Caping

1
12
12
2
2
2

Supply and Laying of P.V.C casing and


caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height
19/20mm size with all accessories, duly
sealed at points and erected on Wall /
Ceiling including cost of all materials
and labour charges complete.
Taking Output = 100 M
a) Material
19mm / 20mm x 12.5 mm height
Casing and Caping
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries such as screws, Rawal Plugs,
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height 25mm
size with all accessories, duly sealed at
points and erected on Wall / Ceiling
including cost of all materials and
labour charges complete.

100 M

day
day
day
LS

1
1
2

161

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

1.5.3

1.5.4

Taking Output = 100 M


a) Material
25mm x 12.5 mm height Casing and
Caping
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries such as screws, Rawal Plugs,
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height
31/32mm size with all accessories, duly
sealed at points and erected on Wall /
Ceiling including cost of all materials
and labour charges complete.
Taking Output = 100 M
a) Material
30 / 32mm x 12.5 mm height Casing
and Caping
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries such as screws, Rawal Plugs,
Gutting, Cement, Sand and Rounding
off.
C) Cost for 100 RM
Rate per Metre = C/100
Supply and Laying of P.V.C casing and
caping (ISI MARK) with double locking
arrangments with groover trunking of
size not below 12.5mm height 38/40
size with all accessories, duly sealed at
points and erected on Wall / Ceiling
including cost of all materials and
labour charges complete.
Taking Output = 100 M
a) Material
38 / 40mm x 12.5 mm height Casing
and Caping
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
Sundries such as screws, Rawal Plugs,
Gutting, Cement, Sand and Rounding
off.

100 M

day
day
day
LS

1
1
2

100 M

day
day
day
LS

1
1
2

100 M

day
day
day
LS

1
1
2

162

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

BLD-ELEC-2
BLD-ELEC-21

2
2.1

2.1.1

2.1.2

C) Cost for 100 RM


Rate per Metre = C/100
Wiring
Copper Wiring

Note for
All Items
for
Wiring
The R&B
Departm
ent
Proposed
Labour,
for both
piping &
wiring
consideri
ng 40%
Labour,
for Wire
draw.
Keeping
this, the
labour is
proposed
for
wiring
100 RM.

Wiring with 2 runs of 14/0.3mm (1.0


Sq.mm) Fire Retardant (FR) P.V.C.
insulated flexible copper cable (ISI
MARK) in existing pipe with 6A switch,
Ceiling rose and 3mm thick hylam
sheet covering to switch control box
including all labour charges etc.,
complete for light, bell, fan and
exhaust fan points in Non-Residential
Buildings
Taking Output = 6 Points
a) Material

14/0.3mm PVC FR flexible copper wire


6A Switch @16/each
6A 2 way Ceiling Rose@17/each
25 x 20 cms (10" x8") Hylam sheet
3mm thick
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
C) Cost for 6 Points
Rate per Point = C/6
Wiring with 2 runs of 14/0.3mm (1.0
Sq.mm) P.V.C. insulated F.R flexible
copper cable (ISI MARK) in existing
pipe with 6A switch, Ceiling rose and
3mm thick hylam sheet covering to
switch control box including all labour
charges etc., complete for light, bell,
fan and exhaust fan points in
Residential Buildings.
Taking Output = 7 Points
a) Material
14/0.3mm PVC FR flexible copper wire
6A Switch @16/each
6A 2 way Ceiling Rose@17/each
25 x 20 cms (10" x8") Hylam sheet
3mm thick
b) Labour charges :

100 M
each
each
sqm

1
6
6
0.05

day
day
day

0.6
1.2
0.6

100 M
each
each
sqm

1
7
7
0.05

163

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.1.3

2.1.4

2.1.5

Skilled Electrician
Semi skilled Electrician
Helpers
C) Cost for 7 Points
Rate per Points = C/7
Wiring with 2 of 14/0.3mm (1.0
Sq.mm) P.V.C. insulated F.R. flexible
copper cable (ISI MARK) in existing
pipe with 6A switch control and 3/2 pin
sockets fixing on separate board
including all labour charges etc.,
complete.
Taking Output = 15 Points
a) Material
14/0.3mm PVC FR flexible copper wire
6A switches @16/each
6A 3 pin / 2 Pin Socket
b) Labour charges :
Skilled Electrician
Semi skilled Electrician
Helpers
C) Cost for 15 Points
Rate per Points = C/15
Supply and fixing of 6A 3 pin wall plug
socket with 6A switch control on a
common switch board with earth
continuity including wire leads, earth
connections along with all labour
charges etc., complete.

day
day
day

0.7
1.4
0.7

100 M
each
each

1
15
15

day
day
day

1.5
1.5
1.5

each
each

1
1

day
day

0.067
0.067

Taking Output = each


a) Material
6A 3 pin / 2 pin Socket
6A switch
b) Labour charges :
Skilled Electrician
Helpers
Rate per each
Note : Labour Charges proposed for
considering 15 per day
Supply and fixing of 16A 3pin / 6A 3pin
plug socket with indicator lamp and
16Amps fuse unit and 16 Amps switch
control (5 in one) on decolam sheet
covered board including earth
connection and all labour charges etc.,
complete on wall.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Decolam sheet
covered board
16A 3 pin / 6A 3pin Plug socket with
indicator lamp, fuse unit (5 in 1)
b) Labour charges :

1point

each

each

164

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.1.6

2.1.7

2.1.8

Skilled Electrician
day
Helpers
day
Rate per each
Note : Labour Charges proposed for 1point
considering 10 per day
Supply and Fixing of 16A 3pin and 6A
3pin plug socket with indicator lamp
and 16A fuse unit and 16A switch
control (5 in 1) duly recessed in wall
with wooden deep box of 6" x8" x2
1/2" size covered with hylam sheet
including earth connections and all
labour charges etc., complete.
Taking Output = each
a) Material
20 x 15 cms (8" x6") Wooden deep box
each
21.6 x 16.6 cms (8.5 x 6.5") 3mm thick
each
hylam sheet
16A 3 pin / 6A 3pin plug socket (5 in 1)
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Rate per each
Note : Labour Charges proposed for 10 jobs per day
Supply and fixing of batten holder /
slanting holder in lieu of ceiling rose of
light point complete with all
connections and all labour charges
with 40W bulb (for new installation).
Taking Output = each
a) Material
PVC batten holder
each
40W bulb
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
Note : 1. The Cost of Ceiling Rose may be deducted in
view of holder.
2. Labour Charges proposed for 20 jobs per day
Supply and fixing of batten holder /
angle holder on existing block, but
without bulb including all connections
etc., complete (For replacement).
Taking Output = each
a) Material
PVC batten holder
each
Less : Cost of ceiling Rose
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each

0.1
0.1

1
1
1
0.1
0.1
0.1

1
1
0.05
0.05

0.05
0.05

165

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.1.9

2.1.10

2.1.11

NOTE : Labour Charges proposed for 20 jobs per day


Supply and fixing of 0.5mtr length
angle
iron
upright
of
size
40mmx40mmx6mm with eye bolt and
shackle insulator with accessories and
all labour charges etc., complete.
Taking Output = each
a) Material
40x40x6mm angle iron
Kg
Eye bolt.
each
Shackle Insulator
each
b) Labour charges :
Semi Skilled Electrician
day
Mason 2nd class
day
Welder 2nd Class
day
Rate per each
NOTE : Labour Charges proposed for 8 jobs per day
Supply and fixing of bed light
transformer
with M.C. holders
including giving connections and cost
of all accessories and all labour charges
etc., complete with bulb.
Taking Output = each
a) Material
Bed light transformer
each
M.C.holder
each
6V bulb
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
NOTE : Labour Charges proposed for 20 jobs per day
Supply and fixing of night lamp fixed at
30 cms height from floor level with 100
x 178 x 20 mm (4"x7"x3/4") wooden
deep box, acrylic cover and batten
holder including cost of all accessories
and labour charges etc., complete with
bulb.
Taking Output = each
a) Material
100 x 178 (4"x7") wooden deep box
each
Acrylic cover
each
Batten holder
each
Zero watt bulb
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
NOTE : Labour Charges proposed for 20 jobs per day

5
1
1
0.125
0.125
0.125

1
1
1
0.05
0.05

1
1
1
1
0.05
0.05

166

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

2.1.12

2.1.13

2.1.14

BLD-ELEC-3
BLD-ELEC-31

3
3.1
3.1.1

Supply and fixing of buzzer / Calling


bell on 100 x 100 mm (4"x4") decolam
block including giving connections, cost
of all accessories and labour charges
etc., complete.
Taking Output = each
a) Material
Buzzer
each
100 x 100 mm (4"x4") decolam block
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
Supply and fixing of ding dong bell on
100 x 178 mm (4"x7") decolam block
including giving connections cost of all
accessories and all labour charges etc.,
complete.
Taking Output = each
a) Material
Ding Dong bell
each
100 x 178 mm (4"x7") Decolam block
each
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
Supply and fixing of Electronic musical
bell on 150 x 200 mm (6"x8") decolam
block including giving connections cost
of all accessories and all labour charges
etc., complete.
Taking Output = each
a) Material
Electronic Musical bell
Nos
150 x 200 mm (6"x8") Decolam block
Nos
b) Labour charges :
Skilled Electrician
day
Helpers
day
Rate per each
NOTE : Labour Charges proposed for 16 jobs per day
RUN OF MAINS
Wiring with F.R P.V.C. insulated
flexible copper cable
Supply and run of 2 of 14/0.3mm (1.0
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire

100 M

1
1
0.062
0.062

1
1
0.062
0.062

1
1
0.062
0.062

2
167

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

3.1.2

3.1.3

3.1.4

b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 1 of 14 /0.3mm (1.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity including all labour charges
etc., complete.
Taking Output = 100 M
a) Material
14/0.3mm FR PVC copper wire
100 M
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 22/0.3mm (1.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
22/0.3mm FR PVC copper wire
100 M
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper
wire
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers

0.67
2
0.67

1
0.34
1
0.34

2
0.67
2
0.67

100 M

day
day
day

0.67
2
0.67
168

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

3.1.4 (a)

3.1.5

3.1.6

Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 1 of 36/0.3mm (2.5
Sq.mm) F.R P.V.C. insulated flexible
copper cable in existing pipe for earth
continuity inlcuding all labour charges
etc., complete.
Taking Output = 100 M
a) Material
36/0.3mm (2.5 sqmm) FR PVC copper
100 M
wire
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
Supply and run of 2 of 56/0.3mm (4
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
56 /0.3mm (4 sqmm)FR PVC flexible
100 M
copper wire.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
Supply and run of 2 of 84/0.3mm (6.0
Sq.mm) FR P.V.C. insulated flexible
copper cable in existing pipe for mains
inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
84 /0.3mm (6 Sq.mm) FR PVC flexible
copper wire.
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries
C) Cost for 100 RM

0.34
1
0.34

1
3
1

100 M

day
day
day

1
3
1

169

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

3.3.7

3.3.8

BLD-ELEC-4

4
4.1
4.1.1

Rate per Metre = C/100


Note : Labour Charges considered for 100 M / day
Supply and run of 2 of 140 /0.3mm (10
Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains
including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
140/0.3 (10 Sq.mm) FR PVC flexible
100 M
copper wire
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
Supply and run of 2 of 126 /0.4mm (16
Sq.mm) F.R PVC insulated flexible
copper cable in existing pipe for mains
including all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
126/0.4mm (16 Sq.mm) FR PVC flexible
100 M
copper wire
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 100 M / day
SWITCH GEAR & MCB DISTRIBUTION
BOARDS.
Panel Mounting Cubical type SDF
Supply and erection of Panel mounting
cubical type 30 / 32A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
30 / 32A TPN 415V, 50 Hz. switchs
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician

1
3
1

1
3
1

each

day
day

0.167
0.167
170

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.1.2

4.1.3

4.1.4

Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 60 / 63A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
60 / 63A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 125A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
125A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type 200A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
200A TPN 415V, 50 Hz. switchs
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician

0.333

0.167
0.167
0.333

0.167
0.167
0.333

each

day

0.2
171

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.1.5

4.1.6

4.1.7

Semi Skilled Electrician


day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type 250A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
250A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type 400A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
400A TPN 415V, 50 Hz. switchs
each
Disconnector fuse unit with HRC fuses.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
Supply and erection of Panel mounting
cubical type 630A TPN 415V, 50 Hz.
switch disconnector fuse unit complete
with front drive mechanism with door
inter lock, padlocking arrangement
etc., complete with fuse links on
existing control panel.
Taking Output = each
a) Material
630A TPN 415V, 50 Hz. switchs
Disconnector fuse unit with HRC fuses.
b) Labour charges :

each

0.4
0.4

0.2
0.4
0.4

0.25
0.5
0.5

172

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

BLD-ELEC-42

4.2

4.2.1

4.2.2

4.2.3

Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
Panel Mounting Cubical type, 4pole
onload change over switch confirming
to IS 13947-3-1993.
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 60 / 63A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
60 / 63A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 125A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
125A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 200A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
200A, 4 Pole, 415V, 50 Hz. On load
cubical type C.O.S
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician

0.25
0.5
0.5

0.167
0.167
0.333

0.167
0.167
0.333

each

day
day

0.2
0.4
173

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.2.4

4.2.5

4.2.6

Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 250A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
250A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 400A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
400A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 630A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
630A, 4 Pole, 415V, 50 Hz. On load
each
cubical type C.O.S
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 4 jobs / day

0.4

0.2
0.4
0.4

0.25
0.5
0.5

0.25
0.5
0.5

174

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.2.7

4.2.8

BLD-ELEC-43

4.3
4.3.1

Supply and erection of Panel mounting


cubical type L.T heavy duty ON LOAD
change over switch of 800A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
800A, 4 Pole, 415V, 50 Hz. On load
cubical type C.O.S
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries such as hardware etc.,
Rate per each
Supply and erection of Panel mounting
cubical type L.T heavy duty ON LOAD
change over switch of 1060A, 4 pole,
415V, 50 Hz. with all accessories etc.,
complete on existing control panel.
Taking Output = each
a) Material
1060A, 4 Pole, 415V, 50 Hz. On load
cubical type C.O.S
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries such as hardware etc.,
Rate per each
Panel Mounting Moulded Case Circute
Breakers (MCCBs)
Supply and erection of Panel mounting
60 / 63A, 3 Pole, 10 /16kA, MCCB with
thermal
magnetic
setting
/
Microprocessor
based
release
arrangement with all connections etc.,
complete on existing panel.

each

day
day
day
LS

1
1
1

each

day
day
day
LS

1
1
1

Taking Output = each


a) Material
60 / 63A, 3 Pole, 10 / 16kA, MCCB.
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day

1
0.167
0.167
0.333

175

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.3.2

4.3.3

4.3.4

Supply and erection of Panel mounting


60 / 63A, 4 Pole, 10 / 16kA, MCCB with
thermal
magnetic
setting
/
Microprocessor
based
release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
Cost of 60 / 63A, 4 Pole Panel
each
mounting 10 / 16 kA, MCCB
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
125A, 3 Pole, 25kA, MCCB with thermal
magnetic setting / Microprocessor
based release arrangement with all
connections etc., complete on existing
panel.
Taking Output = each
a) Material
Cost of 125A, 3 Pole, 25 kA panel
each
mounting MCCB.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day
Supply and erection of Panel mounting
125A, 4 Pole, 25kA, MCCB with thermal
magnetic setting / Microprocessor
based release arrangement with all
connections etc., complete on existing
panel.
Taking Output = each
a) Material
Cost of 125A, 4 Pole, 25 kA panel
each
mounting MCCB.
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 6 jobs / day

0.167
0.167
0.333

0.167
0.167
0.333

0.167
0.167
0.333

176

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.3.5

4.3.6

BLD-ELEC-44

4.4
4.4.1

Supply and erection of Panel mounting


250A, 4 Pole, 35 / 36kA, MCCB with
thermal
magnetic
setting
/
Microprocessor
based
release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
250A, 4 Pole, 36/35kA panel mounting
each
MCCB
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
Supply and erection of Panel mounting
400A, 4 Pole, 35 /36kA, MCCB with
thermal
magnetic
setting
/
Microprocessor
based
release
arrangement with all connections etc.,
complete on existing panel.
Taking Output = each
a) Material
400A, 4 Pole, 36/35kA panel mounting
each
MCCB
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware etc.,
LS
Rate per each
Note : Labour Charges considered for 5 jobs / day
DISTRIBUTION BOARDS
Supply and fixing SPN Distribution
board with IP-20 protection suitable
for single phase Earth Leakage Circute
Braker (ELCB) / Residual Current
Circute Braker (RCCB) / Double Pole
(DP) Isolator as incomer and 10kA SP
MCBs as out going including internal
connections and labour charges for
surface / flush mounting etc.,
complete.
40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 4Nos
for outgoing.
Taking Output = each
a) Material
SPN 4way D.B with IP-20 Protection
suitable for single phase ECCB / RCCB/
DP Isolator.

each

0.2
0.4
0.4

0.2
0.4
0.4

177

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.2

40A D.P.Isolator / ECCB / RCCB


each
10 kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
SPN 8way D.B with IP-20 Protection
each
suitable for single phase ECCB / RCCB/
DP Isolator.
40A D.P.Isolator / ECCB / RCCB
each
10 kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 8Nos
for outgoing.
Taking Output = each
a) Material
SPN 12 way D.B with IP-20 Protection
each
suitable for single phase ECCB / RCCB/
DP Isolator.
40A D.P.Isolator / ECCB / RCCB
each
10 kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing SPN Distribution
board with IP-42 protection (Metal
Door) suitable for single phase ELCB /
RCCB/DP Isolator as incomer and 10kA
SP MCBs as outing going including
internal connection and labour charges
for surface / flush mounting etc.,

1
4
0.5
0.5
1

1
6
0.5
0.5
1

1
8
0.5
0.5
1

178

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

complete.

40A DP Isolator/ RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 4Nos
for outgoing.
Taking Output = each
a) Material
SPN 4 way D.B with IP-42 Protection
each
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB
each
10 kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
SPN 8 way D.B with IP-42 Protection
each
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB
each
10 kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
40A DP Isolator/ RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 8 Nos
for outgoing.
Taking Output = each
a) Material
SPN 12 way D.B with IP-42 Protection
each
(MD) suitable for single phase ECCB /
RCCB/ DP Isolator.
40A D.P.Isolator / ECCB / RCCB
each
10 kA - 6-32A range SP MCBs
each

1
4
0.5
0.5
1

1
6
0.5
0.5
1

1
8
179

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.3

b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as hardware, cement
LS
etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN Distribution
board with IP-20 protection suitable
for 3 phase ELCB / RCCB / FP Isolator as
incomer and 10kA SP MCBs as outing
going including internal connection
and labour charges for surface / flush
mounting etc., complete.
40A FP Isolator/ RCCB / ELCB - 1 No
for incomer,
10kA-6-32A SP
MCBs - 12Nos for outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection
each
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
63A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-20 Protection
each
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
80A FP Isolator - 1 No for incomer,
10kA- 6-32A SP MCBs - 18Nos for

0.5
0.5
1

1
12
0.5
1
1

1
12
0.5
1
1

180

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

outgoing.

4.4.4

Taking Output = each


a) Material
6 way TPN, D.B with IP-20 Protection
each
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN Distribution
board with IP-42 protection (Metal
Door) suitable for 3 phase ELCB / RCCB
/ FP Isolator as incomer and 10kA SP
MCBs as outing going including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-42 Protection
each
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
40A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
63A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
4way TPN, D.B with IP-42 Protection
each
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
63A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each

1
18
0.5
1
1

1
12
0.5
1
1

1
12

181

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.5

b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
80A FP Isolator - 1 No for incomer, 632A SP MCBs - 18Nos for outgoing.
Taking Output = each
a) Material
6 way TPN, D.B with IP-42 Protection
each
(MD) suitable for 3 phase ELCB / RCCB/
FP Isolator as incommer.
80A, 4 Pole Isolator / ELCB / RCCB
each
10kA - 6-32A range SP MCBs
each
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN - Vertical type
Distribution board with IP - 20
Protection suitable for 3 phase ELCB /
RCCB / FP Isolator as incomer and 10
kA TP / SP MCBs as outing going
including internal connection and
labour charges for surface / flush
mounting etc., complete.
Incomer : 63A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-20
Nos
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB
32A TP MCBs
10kA -6-32A SP MCBs
b) Labour charges :
Skilled Electrician
Semi Skilled Electrician
Helpers
Sundries, suchas T.W plugs, Screws,
Cement etc,
Rate per each

0.5
1
1

1
18
0.5
1
1

Nos
Nos
Nos

1
2
6

day
day
day
LS

0.5
1
1

182

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.6

Note : Labour Charges considered for 2 jobs / day


Incomer : 80A FP Isolator / ELCB /
RCCB
Outgoing : 32A TP MCBs 4 Nos and
6-32A SP MCBs 12Nos
a) Material
8way TPN - Vertical type DB with IP-20
Nos
protection suitable for 3 Phase ELCB /
RCCB / 4 Pole Isolator as in commer
and TP / SP MCBs as outgoing with
Bus-bar arrangment etc.,
80 Apms, 4 Pole Isolator / ELCB / RCCB
Nos
32A TP MCBs
Nos
10kA -6-32A SP MCBs
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries, suchas T.W plugs, Screws,
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN - Vertical type
Distribution board with IP - 42
Protection (Metal Door) suitable for 3
phase ELCB / RCCB / FP Isolator as
incomer and 10 kA TP / SP MCBs as
outing going including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
Incomer : 63A FP Isolator/ ELCB /
RCCB
Outgoing : 32A TP MCBs 2 Nos and
6-32A SP MCBs 6 Nos
a) Material
4way TPN - Vertical type DB with IP-42
Nos
(Metal Door) protection suitable for 3
Phase ELCB / RCCB / 4 Pole Isolator as
in commer and TP / SP MCBs as
outgoing with Bus-bar arrangment etc.,
63Apms, 4 Pole Isolator / ELCB / RCCB
Nos
32A TP MCBs
Nos
10kA -6-32A SP MCBs
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries, suchas T.W plugs, Screws,
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Incomer : 80A FP Isolator/ ELCB /
RCCB

1
4
8
0.5
1
1

1
2
6
0.5
1
1

183

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Outgoing : 32A TP MCBs 4 Nos and


6-32A SP MCBs 12 Nos
a) Material
8way TPN - Vertical type DB with IP-42
(MD) protection suitable for 3 Phase
ELCB / RCCB / 4 Pole Isolator as in
commer and TP / SP MCBs as outgoing
with Bus-bar arrangment etc.,

4.4.7

Nos

80 Apms, 4 Pole Isolator / ELCB / RCCB


Nos
32A TP MCBs
Nos
10kA -6-32A SP MCBs
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries, suchas T.W plugs, Screws,
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing 7 Segment, TPN
Distribution
board
with
IP-42
Protection (Metal door) with phase
segregation and separation between
incoming and outgoing suitable for 3
Phase ELCB / RCCB / FP Isolator as
incomer and DP Isolator / RCCB for
phase control with 10kA SP MCCB as
outgoing including internal connection
and labour charges for surface / flush
mounting etc., complete.
Incomer
: 63A FP Isolator/ ELCB
/ RCCB
Phase Control : 40A DP Isolator 3
Nos
Outgoing
: 10kA 6-32A SP
MCBs 12 Nos
a) Material
7 Segment, TPN Distribution 4Way DB
Nos
with IP-42 (Metal Door) protection
with phase segregation and seperation
between incomming an outgoing.
63A, 4 Pole Isolator / ELCB / RCCB .
Nos
40A DP Isolator
Nos
6-32 Amps range SP MCBs.
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as T.W. Plugs, Screws,
LS
Cement etc.,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Incomer
: 80A FP Isolator/ ELCB
/ RCCB

1
4
8
0.5
1
1

1
3
12
0.5
1
1

184

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.8

4.4.9

Phase Control : 63A DP Isolator 3


Nos
Outgoing
: 10kA-6-32A SP
MCBs 24 Nos
a) Material
7 Segment, TPN Distribution 8 Way DB
Nos
with IP-42 (Metal Door) protection
with phase segregation and seperation
between incomming an outgoing.
80A, 4 Pole Isolator / ELCB / RCCB .
Nos
63A DP Isolator
Nos
6-32 Amps range SP MCBs.
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as T.W. Plugs, Screws,
LS
Cement etc.,
Rate per each
Note : Labour Charges considered for 2 jobs / day
Supply and fixing TPN - Vertical type
Distribution board with IP -42
Protection (Metal Door) with 125A,
4Pole 25 kA MCCB as incomer with
4Nos 32A TP MCBs and 12 Nos. 10 kA
SPMCBs as outgoing including internal
connection and labour charges for
surface / flush mounting etc.,
complete.
a) Material
8 Way TPN Vertical DB with IP -42
Nos
(Metal door) protection suitable for
125A, 4 Pole, 16kA MCCB as incomer.
125 Amps, 4 Pole , 25 kA MCCB
Nos
10 kA, 32A TP MCBs:
Nos
10kA, 6 to 32A SP MCBs: Rs.119 / Each
Nos
b) Labour charges :
Skilled Electrician
day
Semi Skilled Electrician
day
Helpers
day
Sundries such as T.W. Plugs, Screws,
LS
Cement etc.,
Rate per each
Note : 1. Labour Charges considered for 2 jobs / day
2. If the Distribution Boards from Item No. 4.4.1 to
4.4.8 proposed for concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
Supply and fixing Distribution board
with 20A single phase plug and Socket,
in sheet steel enclosure with
10/16/20A SP MCB including internal
connection and labour charges for
surface / flush mounting etc., complete

1
3
12
1
1
1

1
4
12
1
1
1

185

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

4.4.10

BLD-ELEC-5
BLD-ELEC-51

5
5.1
5.1.1

a) Material
1 Phase Distribution board with 20A
Nos
plug and socket.
10/16/20A SP MCB
Nos
b) Labour charges :
Skilled Electrician
Nos
Semi skilled Electrician
Nos
Helpers
Nos
Sundries such as Cement, Sand, T.W.
LS
Plugs, Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 4 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
Supply and fixing Distribution board
with 20A 3 phase plug and Socket, in
sheet steel enclosure with 16/20A TP
MCB including internal connection and
labour charges for surface / flush
mounting etc., complete.
a) Material
Distribution board with 3 Ph. 20A Plug
Each
and Socket .
32A TP MCB, 10 kA
Each
b) Labour charges :
Skilled Electrician
Nos
Semi skilled Electrician
Nos
Helpers
Nos
Sundries such as Cement, T.W. Plugs,
Screws etc.,
Rate per each
Note : 1. Labour Charges considered for 3 jobs / day
2. For concealing, add the following:
a 1No. Semi skilled mason
b 1/4 bag cement
EARTHING
EARTHING

1
1
0.25
0.25
0.25

1
1
0.33
0.33
0.33

Providing independent earthling by


excavating a trench to a depth of 2.1 M
in all soils, as per size specified in the
Data, using 40mm dia 'B' class GI pipe
of 2.5 Mtrs length with necessary
accessories with hume pipe ring duly
providing staggered holes including
filling with equal proportion of Salt and
Charcoal in layers and all labour
charges etc., complete for small
quarters.
a) Material

186

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

5.1.2

Earth Work Excavation of Hard gravel


Soil with small boulder for trench 1st
step of size 1.5 x 0.6 x 0.9 m (5'x2'x3')
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of
size 1.2 x 0.6 x 1.2 m (Civil SSR)
(4'x2'x4')
25% extra for narrow trench & pit and
back filling with Sand, Coke, Salt etc.,
and leveling
40mm dia 'B' Class G.I pipe
25 x 6 mm (1"X 1/4") G.I Flat duly
drilled 12mm holes (4 Nos) of 200 mm
(8") length
Drilling of 16 Nos through holes of
12mm dia to G.I pipe
G.I Nuts, Bolts an Washers
18" dia hume pipe ring
Hard Coke
Salt
b) labour charges for fixing pipe ring
and connections
Semi skilled Electrician
Helpers
Sundries
Rate per each
Providing independent earthing for
Important equipment with 40mm dia
'B' class 2.5m long G.I pipe and 19mm
dia 'B' class G.I pipe of 0.3mtr. long
connected with reducer providing G.I
funnel with mesh enclosed in
C.C.Chamber of 400m x 400m x
400mm with R.C.C. Slab cover duly
providing staggered holes filling with
salt and charcoal from the bottom of
the pipe giving earth connection from
electrode through G.I strip of 25 x
6mm x 200mm length with all
accessories and labour charges
complete, as per IS specifications
732/1982 (Part II)
a) Material
Earth work excavation of hard gravel
soil with small boulders for trench 1st
step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and
boulders for trench 2nd Step of size 1.2
x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit,
back filling and blending.
Laying C.C bed in Cement mortar with
1: 2:4 with 20 mm HBG Stone Metal
(Civil SSR).

cum

0.85

cum

0.9

Mtr
Each

2.5
1

Each

16

Set
Each
Kg
Kg
Each

4
1
40
20

Nos
Nos

0.5
0.5

cum

1.27

cum

1.87

cum

0.9

187

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

5.1.3

Masonary through with brick Masonry


with CM 1:3
Cement plastering inside through with
1:3 Cement mortar, 12 mm thick (Civil
SSR).
40mm dia G.I pipe Class 'B' (Civil SSR)
19mm dia G.I pipe
40mm x 19mm reducer
G.I Funel covered with wire mesh
25mm x 6mm x 200 mm length G.I
Strip (Flat) with 4 Nos. Holes of 12mm
dia.
Drilling of staggered holes of 12mm
dia to G.I pipe.
G.I Bolts, Nuts and Washers.
Hard Coke.
Salt.
Cost Iron cover 400 mm x 400mm x
50mm.
b) labour charges for fixing pipe
Skilled Electrician
Sundries such as Lugs and Saddles
Rate per each
Providing independent earthing for
Sophisticated Electronic equipment
with 600mm x 600mm x 3.15mm thick
copper plate rigidly fixed to 40mm dia
G.I Pipe of 0.3mtr. length connected
with reducer providing G.I funnel with
wiremesh as per National Electric Code
including C.C.Chamber of size 400m x
400m x 400mm covered with R.C.C.
Slab filling with salt and charcoal
giving earth connection from electrode
G.I strip of 25mm x 6mm x 200mm
length with all accessories and labour
charges
complete
as
per
IS
specification 732/1982 (Part II).
a) Material
Earth work excavation of hard gravel
soil with small boulders for trench 1st
step of size 1.5 x 0.9 x 0.9 m (5'x3'x3')
Earth work hard disintegrated rock and
boulders for trench 2nd Step of size 1.2
x 0.9 x 1.65 m (Civil SSR-16) (4'x3'x5.5')
25% extra for trenches and narrow Pit,
back filling and blending.
Laying C.C bed in Cement mortar with
1: 2:4 with 20 mm HBG Stone Metal
(Civil SSR).
Masonary through with brick Masonry
with CM 1:3
Cement plastering inside through with
1:3 Cement mortar, 12 mm thick (Civil

cum

0.23

sqm

2.09

Mtr
Mtr
Each
Each
Each

2.5
0.3
1
1
1

Each

16

Set
kg
kg
L.S

4
4
20

Nos

cum

1.27

cum

1.87

cum

0.9

cum

0.23

sqm

2.09

188

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

SSR).

BLD-ELEC-52

5.2
5.2.1

5.2.2

5.2.3

40mm dia G.I pipe Class 'B' (Civil SSR)


19mm dia G.I pipe
40mm x 19mm reducer
G.I Funel covered with wire mesh
25mm x 6mm x 200 mm length G.I
Strip (Flat) with 4 Nos. Holes of 12mm
dia.
600mm x600mm x 3.15mm thick
copper plate
Drilling of staggered holes of 12mm
dia to G.I pipe.
G.I Bolts, Nuts and Washers.
Hard Coke.
Salt.
Cost Iron cover 400 mm x 400mm x
50mm.
b) labour charges for fixing pipe
Skilled Electrician
Sundries such as Lugs and Saddles
Rate per each
G.I Wire and Strip
Supply and Run of No.8 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.8 SWG G.I wire 100 M Length
(0.104 Kg / Mtr)
U' Nails
b) labour charges
Helpers
Sundries.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of No.10 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.10 SWG G.I wire 100 M Length
(0.067 Kg / Mtr)
U' Nails
b) labour charges
Helpers
Sundries.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of No.12 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material

Mtr
Mtr
Each
Each
Each

2.5
0.3
1
1
1

kg

10.00

Each

16

Set
kg
kg
L.S

4
4
20

Nos

10.4
Kg
100Nos

1.5

day

6.7
Kg
100Nos

1.5

day

189

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

5.2.4

5.2.5

5.2.6

5.2.7

No.12 SWG G.I wire 100 M Length


(0.044 Kg / Mtr)
U' Nails
b) labour charges
Helpers
Sundries.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of No.14 SWG G.I wire
including cost of all accessories and
labour charges etc., complete.
a) Material
No.14 SWG G.I wire 100 M Length
(0.026 Kg / Mtr)
U' Nails
b) labour charges
Helpers
Sundries.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 25mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete.
a) Material
25mm x 6mm G.I Strip 100 M Length
(1.18 Kg / Mtr)
b) labour charges
Skilled Electrician
Helper
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 40mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete
a) Material
40mm x 6mm G.I Strip 100 M Length
(1.88 Kg / Mtr)
b) labour charges
Skilled Electrician
Helper
Sundries such as T&P.
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 50mm x 6mm G.I
Strip including cost of all accessories
and labour charges etc., complete.
a) Material
50mm x 6mm G.I Strip 100 M Length
(2.36 Kg / Mtr)
b) labour charges
Skilled Electrician
Helper

4.4
Kg
100Nos

1.5

day

2.6
Kg
100Nos

1.5

day

kg

118

Nos
Nos

2
2

kg

188

Nos
Nos

2
2

kg

236

Nos
Nos

2
2
190

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

BLD-ELEC-53

5.3
5.3.1

5.3.2

5.3.3

5.3.4

Sundries such as T&P.


C) Cost for 100 M
Rate per mtr c/100
Copper wire and Strip
Supply and Run of Zero gauge copper
wire including cost of all accessories
and labour charges etc., complete
a) Material
O' SWG Copper wire (0.455 Kg/Mtr.)
100 M Length
b) labour charges
Skilled Electrician
Semi skilled Electrician
Helper
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of No. 8 SWG copper
wire including cost of all accessories
and labour charges etc., complete.
a) Material
8 SWG Copper wire (0.1155 Kg/Mtr.)
100 M Length
b) labour charges
Skilled Electrician
Semi skilled Electrician
Helper
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of No. 14 SWG copper
wire including cost of all accessories
and labour charges etc., complete
a) Material
14 SWG Copper wire (0.028 Kg/Mtr.)
100 M Length
b) labour charges
Skilled Electrician
Semi skilled Electrician
Helper
Sundries such as T&P and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 25mm x 3mm
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
25mmx 3mm Copper strip (0.663 Kg /
Mtr) 100 M Length
b) labour charges
Skilled Electrician

Kg

45.5

Nos
Nos
Nos

1
1
1

Kg

11.55

Nos
Nos
Nos

1
1
1

Kg

2.8

Nos
Nos
Nos

1
1
1

Kg

66.3

Nos

2
191

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

5.3.5

BLD-ELEC-6
BLD-ELEC-61

6
6.1
6.1.1

6.1.2

Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 32mm x 6mm
copper strip including cost of all
accessories and labour charges etc.,
complete.
a) Material
32mmx 6mm Copper strip (1.697 Kg /
Mtr) 100 M Length
b) labour charges
Skilled Electrician
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
SERVICE MAINS & LTOH Lines
WPSC (Weather Prrof Single Core)
(PVC Cleats)
Supply and Run of 2 of 2.5 Sq.mm
WPSC (Whether Proof Single Core)
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
2.5 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr)
Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete for
service mains.
a) Material
6 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr)
Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled

Nos

LS

Kg

169.7

Nos
Nos

2
2

100 M
kg

2
6.7

100 Nos

day
day
day

1
1
1

100 M
kg

2
6.7

100 Nos

day
day

1
1
192

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.1.3

6.1.4

6.1.5

Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable
No.10 SWG G.I wire. (0.026 Kg / Mtr
)Length 100 RM
PVC Cleats
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 4 of 6 Sq.mm WPSC
Aluminium cable along with No.10
SWG G.I bearer wire on both sides
through PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
6 Sq.mm WPSC Aluminium cable
No.10 SWG GI Wire (6.7kg x 2) Length
200 RM
Binding wire
PVC Cleats / Separters 4 W.
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 4 of 10 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire on both
sides through PVC cleats with all
accessories including labour charges
etc., complete for service mains.
a) Material
10 Sq.mm WPSC Aluminium cable

day

100 M
kg

2
6.7

100 Nos

day
day
day

1
1
1

100 M
kg

4
13.4

kg
100 Nos

0.25
1

day
day
day

2
2
2

100 M

193

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.1.6

BLD-ELEC-62

6.2
6.2.1

No.10 SWG GI Wire (6.7kg x 2) Length


200 RM
Binding wire
PVC Cleats / Separters 4 W.
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 4 of 16 Sq.mm
WPSC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
for service mains.
a) Material
16 Sq.mm WPSC Aluminium cable
No.10 SWG GI Wire (6.7kg x 2) Length
200 RM
Binding wire
PVC Cleats / Separters 4 W.
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries such as insulation tapes and
rounding off
C) Cost for 100 M
Rate per mtr c/100
WPTC (Weather Prrof Twin Core)
Cable
Supply and Run of 1 of 6 Sq.mm WPTC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable
No.10 G.I wire. Length 100 RM
Insulation tapes
Aluminium link clips
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100

kg

13.4

kg
100 Nos

0.25
1

day
day
day

2
2
2

100 M
kg

4
13.4

kg
100 Nos

0.25
1

day
day
day

2
2
2

100 M
kg
each
box

1
6.7
2
2

day
day
day

1
1
1

194

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.2.2

6.2.3

6.2.4

Supply and Run of 1 of 10 Sq.mm


WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including
labour
charges
etc.,
complete.
a) Material
10 Sq.mm (7/18) wptc Aluminium
cable
No.10 G.I wire. Length 100 RM
Insulation tapes
Aluminium link clips
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 6 Sq.mm WPTC
Aluminium cable along with No.10
SWG G.I bearer wire through PVC
cleats with all accessories including
labour charges etc., complete.
a) Material
6 Sq.mm (7/18) wptc Aluminium cable
No.10 G.I wire. Length 100 RM
PVC insulation tapes
Link clips
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
Supply and Run of 2 of 10 Sq.mm
WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including labour charges etc., complete
a) Material
10 Sq.mm (7/18) wptc Aluminium
cable
No.10 G.I wire. Length 100 RM
PVC insulation tapes
Link clips
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries and rounding off
C) Cost for 100 M

100 M

kg
each
box

6.7
2
2

day
day
day

1
1
1

100 M
kg
each
box

2
6.7
4
2

day
day
day

1
1
1

100 M

kg
each
box

6.7
4
2

day
day
day

1
1
1

195

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.2.5

BLD-ELEC-63

6.3
6.3.1

6.3.2

Rate per mtr c/100


Supply and Run of 2 of 16 Sq.mm
WPTC Aluminium cable along with
No.10 SWG G.I bearer wire through
PVC cleats with all accessories
including
labour
charges
etc.,
complete.
a) Material
16 Sq.mm (7/18) wptc Aluminium
cable
No.10 G.I wire. Length 100 RM
PVC insulation tapes
Link clips
b) labour charges
Skilled Electrician
Semi skilled
Helper
Sundries and rounding off
C) Cost for 100 M
Rate per mtr c/100
L.T.O.H. Lines

100 M

kg
each
box

6.7
4
2

day
day
day

1
1
1

Supply and fixing of 3 phase, 4 wire


angle iron cross arm with 3 Nos shackle
/ pin insulators for phases and C.I
knob for neutral including cost and
conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm
kg
(1.5"x1.5"x1/4")
Drilling Holes
each
M.S Clamp 25mm x 6mm with bolts
each
and nuts
Pin insulators 100 x 80 mm (4"x3 1/2")
each
C.I Nob
each
Cutting of angle Iron and Welding
LS
including cost of flat Iron etc.,
b) labour charges
Skilled Electrician
day
Semi skilled
day
Rate per Each
Note : 1. Labour Charges considered for 8 jobs / day
Supply and fixing of single phase, 2
wire angle iron cross arm with 1 Nos
shackle / pin insulators for phases and
C.I knob for neutral including cost and
conveyance of all materials.
a) Material
Angle Iron 38 x 38 x 6 mm
(1.5"x1.5"x1/4" (0.61 mt))
Drilling Holes
M.S Clamp 25mm x 6mm with bolts
and nuts

4.27
6
1
3
1

0.125
0.125

kg

2.13

each
each

4
1

196

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.3

6.3.4

Pin insulators 100 x 80 mm (4"x3 1/2")


each
C.I Knob
each
Cutting of angle Iron and Welding
LS
including cost of flat Iron sundires.
b) labour charges
Skilled Electrician
day
Semi skilled
day
Rate per Each
Note : 1. Labour Charges considered for 10 jobs / day
Supply and fixing of stayset with 7/8
SWG (10to 15m long) guy insulator
with concreting 1:3:6 incluidng
excavation of pit and back filling
including cost and conveyance of all
materials and labolur charges etc.,
complete.
a) Material
Stay rod of 16mm dia (7/8 SWG)
each
1560mm length with bolts and nuts
with switch plate.
Stay tight set (Jum Bracket 300mm)
pair
Stay wire 7/20 weighing 4kgs
each
Cement Concrete 1:3:6 (As per Civil
cum
SSR)
Excavation of pit and back filling 1.5 x
cum
0.75 x 0.6 m (5'x2.5'x2')
Stay clamp with bolts and nuts
set
L.T guy insulator
each
b) labour charges
Skilled Electrician.
day
Man Mazdoor
day
Rate per Each
Note : 1. Labour Charges considered for 2 jobs / day
Supply and fixing of over head line
horizontal type safety device with
angle iron cross arm of size 50 x 50 x 6
mm, 1.52m length projection from
pole with 38 x 38 x 6 mm (1 1/2"x1
1/2" x 1/4") angle iron arm including
G.I wire for earth continuity and cost
of all accessories labour charges etc.,
complete.
a) Material
50 x 50 x 6 mm (2"x2"x1/4") Angle Iron
of 1.52 Mtr length
38 x 38 x 6 mm (1.5"x1.5"x1/4") Angle
Iron of 0.45 Mtr
Special Flat Iron Clamp 25x6mm with
bolts and nuts
No.8 SWG G.I wire 8m Length
b) labour charges
Skilled Electrician
Semi skilled

1
1

0.1
0.1

1
1
0.142
0.675
1
1
0.5
1

kg

5.32

kg

1.57

each

kg

0.8

day
day

0.25
0.25
197

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.5
6.3.5 (a)

6.3.5 (b)

6.3.5 (c)

Helper
day
Sundires such as bolts, nuts including
soldering.
Rate per Each
Note : 1. Labour Charges considered for 4 jobs / day
OH Conductors
Supply and erecting 7/2.00 AAAC (All
Aluminium Annealed Conductor) /
Squirrel (20 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete
a) Material
7/2.0 AAAC (Squirrel)
7/2.0 AAAC for binding and Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km
Supply and erecting 7/2.50 AAAC /
Weasel (34 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/2.5 AAAC / Weasel (34 Sq.mm)
7/2.5 AAAC for binding and Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km
Supply and erecting 7/3.15 AAAC /
Rabbit (55 Sq.mm) conductor for
Overhead line with stringing, binding
and suitable size of clamps for
Jumpering etc., complete.
a) Material
7/3.15 AAAC / Rabbit (55 Sq.mm)
7/3.15 AAAC for binding and
Jumpering.
Aluminium Clamps
b) labour charges
Skilled Electrician
Helper
For special T&P
Sundires and rounding off
Rate per km

0.5

km
km
each

1
0.1
10

day
day
LS

2
8

km
km
each

1
0.1
10

day
day
LS

2
8

km
km

1
0.1

each

10

day
day
LS

2
8

198

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.6

6.3.7

Supply and erecting of fibre / PVC


spacers for L.T Overhead line of 3 to 5
conductors.
a) Material
PVC spacer suitable for 3 to 5
each
conductos.
b) labour charges
Helper
day
Special T&P.
LS
Rate per km
Note : 1. Labour Charges considered for 5 jobs / day
Excavation of hard rock or Bituminous
road (BT) by chiselling for preparing pit
for poles / stay / earth plates / laying
pipes, including clearing the site by
removing debris and making the site to
original position.
a) Material
Cutting B.T road surface (As per Civil
SSR)
Excavation of WBM under B.T

6.3.8 (a)

Note : Rate shall be as per Civil SSR


Brick Masonry in CM (1:6) with
country Bricks traditional size 23 x 11
x 7 cms
Unit = 1cum
a) Material
Bricks traditional size 23 x 11 x 7 cms
2nd class
Cement Mortar 1:6
b) labour charges
st
Mason 1 class

cum

cum

Nos

512

cum

0.20

day

0.24

day

0.56

Mazdoor (unskilled)
Scaffolding charges
Add 25% extra on labour for isolated
work
Rate per cum
Plastering with CM (1:5), 12 mm thick

day

1.88

cum

0.15

Unit = 10 sqm
a) Material
Cement Mortor (1:5)
b) labour charges
st
Mason 1 class

6.3.8 (c)

0.2

Mason 2 class

nd

6.3.8 (b)

Mazdoor (unskilled)
Rate per cum
CRS Masonry in CM (1:6) 2nd Sort

day

0.6

day

0.96

Unit = 1cum
a) Material
199

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Coursed Rubble Stone


Bond Stones 7Nos 0.24 x 0.24 x 0.39 =
0.16cum
Cement Mortar 1:6
b) labour charges
st
Mason 1 class

cum
cum

0.94
0.16

cum

0.32

day

0.45

Mason 2 class

day

1.05

Mazdoor (unskilled)
Add 25% extra on labour for isolated
work
Rate per cum
Supply Transportation and unloading
the 9.1mtr long PSCC poles with 300kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.

day

2.32

nd

6.3.9 (a)

6.3.9 (b)

6.3.9 (c)

a) Material
9.1 Mtr PSCC pole of 300 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
Supply Transportation and unloading
the 9.1mtr long PSCC poles with 280kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
9.1 Mtr PSCC pole of 280 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
Supply Transportation and unloading
the 8.0mtr long PSCC poles with 200kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
8 Mtr PSCC pole of 200 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day

0.5

0.5

0.5

200

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

6.3.9 (d)

6.3.10
(a)

6.3.10
(b)

BLD-ELEC-7
BLD-ELEC-71

7
7.1
7.1.1

Supply, Transportation and unloading


the 8.0mtr long PSCC poles with 140kg
working load at site in good condition
for H.T. / L.T. lines support including
cost and conveyance of all materials
and labour charges etc., complete.
a) Material
8 Mtr PSCC pole of 140 Kg working
each
load
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 12 jobs /
6 Helpers / day
Supply Transportation and unloading
the RS Joist of 9.0 mtr long 175mm x
85mm size at site in good condition for
H.T. / L.T. lines support including cost
and conveyance of all materials and
labour charges etc., complete.
a) Material
175mm x 85mm, 9.0 Mtr long R.S.Joist
kg
(1mt = 19.6 Kg)
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 20 jobs /
6 Helpers / day
Supply Transportation and unloading
the RS Joist of 8.0 mtr long 150mm x
75mm size at site in good condition for
H.T. / L.T. lines support including cost
and conveyance of all materials and
labour charges etc., complete.
a) Material
150mm x 75mm, 8.0 Mtr long R.S.Joist
kg
(1mt = 15.0 Kg)
Transportation Charges @ 5% of Cost
Helper for Unloading
day
Rate per each
Note : 1. Unloading Charges considered for 20 jobs /
6 Helpers / day
STREET LIGHT LUMINARIES
FLOURESCENT LUMINAIRE
Supply of 1x40W weatherproof
flourescent
streetlight
fitting
comprising canopy of sheet Aluminium
in stove enamel finish with copper /
VPIT ballast, capacitor, tube and
starter etc., complete.
a) Material
1x40W WP flourscent street light
fitting.

each

0.5

176.4

0.33

120

0.33

201

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.1.2

7.1.3

BLD-ELEC-72

7.2
7.2.1

7.2.2

BLD-ELEC-73

7.3

Lamp cost of 40W


Sundries and rounding off
Rate per each
Supply of 2x11W CFL (Compacted
Flourescent Lamp), Street light fitting
with all standard accessories and 2 Nos
11W CFL, Lamp etc., complete.
a) Material
2x11W CFL street light fitting.
Cost of 11W CFL
Sundries and rounding off
Rate per each
Supply of 1x18W CFL, Street light
fitting with all standard accessories
and 1 No 18W CFL lamp etc., complete.
a) Material
1x18W CFL street light flourscent
fitting.
Lamp cost of 1x18W CFL
Sundries and rounding off
Rate per each
Mercury Vapour (M.V.) LUMINAIRE
Supply of single piece die cast
Aluminium body with 80W mercury
vapour luminaire with copper wound
ballast and capacitor including 80W
M.V.Lamp etc., complete.
a) Material
80W MV Lamp fitting single piece die
cast Aluminium body with copper
wound ballast and capacitor
80W MV lamp
Sundries and rounding off
Rate per each
Supply of single piece die cast
Aluminium body with 125W M.V.
luminaire with copper wound ballast
and capacitor including 125W HPMV
lamp etc., complete.
a) Material
125W MV Lamp fitting single piece die
cast Aluminium body with copper
wound ballast and capacitor
125W MV lamp
Sundries and rounding off
Rate per each
High Pressure Sodium Vapour (S.V.)
LUMINAIRE

each

each
each

1
1

each

each

each

each

each

each

202

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.3.1

7.3.2

7.3.3

BLD-ELEC-74

7.4
7.4.1

Supply of Integral street light luminaire


of 70W HPSV lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 70W HPSV lamp etc.,
complete.
a) Material
70W HPSV Lamp fitting single piece die
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
70W HPSV lamp
Sundries and rounding off
Rate per each
Supply of Integral street light luminaire
of 150W HPSV lamp fitting comprises
of single piece die cast Aluminium
body with copper wound ballast and
capacitor, Ignitor, with pot optics
including 150W HPSV lamp etc.,
complete.
a) Material
150W HPSV Lamp fitting single piece
die cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
156W HPSV lamp
Sundries and rounding off
Rate per each
Supply of Integral street light luminaire
of 250W HPSV lamp fitting comprises
of single piece die cast Aluminium
body with copper wound ballast and
capacitor, Ignitor, with pot optics
including 250W HPSV lamp etc.,
complete.
a) Material
250W HPSV Lamp fitting single piece
die cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
250W HPSV lamp
Sundries and rounding off
Rate per each
METAL HALIDE LUMINAIRE

each

each

each

each

each

each

Supply of Integral street light luminaire


of 70W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 70W MH
lamp etc.,
complete
a) Material
203

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.4.2

7.4.3

7.4.4

BLD-ELEC-75

7.5

70W MH Lamp fitting single piece die


cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
70W MH lamp
Sundries and rounding off
Rate per each
Supply of Integral street light luminaire
of 150W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 150W MH
lamp etc.,
complete.
a) Material
150W MH Lamp fitting single piece die
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
150W MH lamp
Sundries and rounding off
Rate per each
Supply of Integral street light luminaire
of 250W MH lamp fitting comprises of
single piece die cast Aluminium body
with copper wound ballast and
capacitor, Ignitor, with pot optics
including 250W MH
lamp etc.,
complete.
a) Material
250W MH Lamp fitting single piece die
cast Aluminium body with copper
wound ballast and capacitor, Ignitor,
with pot optics
250W MH lamp
Sundries and rounding off
Rate per each
Supply of integral street light luminaire
of 250W MH with IP-65 protection,
POT optics comprises of single piece
die cast Aluminium body with copper
wound ballast and capacitor with
250W MH lamp etc., complete.
a) Material
250W IP-65 MH Lamp fitting single
piece die cast Aluminium body with
copper wound ballast and capacitor
Lamp cost of 250W MH lamp
Sundries and rounding off
Rate per each
POST TOP LUMINAIRE

each

each

each

each

each

each

each

each

204

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.5.1

7.5.2

7.5.3

7.5.4

7.5.6

Supply of post top luminaire of


mushroom type with clear acrylic cover
and comprises of control gear capsule
die cast Aluminium alloy with VPIT /
copper ballast suitable for 9/11/13W
CFL with lamp etc., complete.
a) Material
1X9/11/13W CFL Lamp fitting
1X9/11/13W CFL Lamp
Sundries and rounding off
Rate per each
Supply of 125W HPMV integral post
top luminaire with Aluminium canopy
and acrylic diffuser with all standard
accessories and 125W HPMV lamp
etc., complete.
a) Material
125W HPMV post top Lamp fitting
Cost of 125W HPMV post top LAMP
Sundries and rounding off
Rate per each
Supply of 70W HPSV integral post top
luminaire with Aluminium canopy and
acrylic diffuser with all standard
accessories and 70W HPSV lamp etc.,
complete.
a) Material
70W HPSV post top Lamp fitting
Cost of 70W HPSV post top lamp
Sundries and rounding off
Rate per each
Supply of diamond / sphere type 80W
HPMV post top lantern luminaire with
all standard accessories including 80W
M.V. lamp etc., complete
a) Material
80W HPMV post top diamond / sphere
type Lamp fitting
80W HPMV post top diamond / sphere
type Lamp
Sundries and rounding off
Rate per each
Supply of diamond / sphere type 125W
HPMV post top lantern luminaire with
all standard accessories including
125W M.V. lamp etc., complete.
a) Material
125W HPMV post top Lamp fitting
125W HPMV post top Lamp
Sundries and rounding off
Rate per each

each
each

1
1

each
each

1
1

each
each

1
1

each

each

each
each

1
1

205

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.5.7

BLD-ELEC-76

7.6
7.6.1

7.6.2

BLD-ELEC-77

7.7
7.7.1

7.7.2

Supply of diamond / sphere type 70W


HPSV post top lantern luminaire with
all standard accessories including 70W
S.V. lamp etc., complete.
a) Material
70W HPSV diamond / sphere post top
Lamp fitting
70W HPSV diamond / sphere post top
Lamp
Sundries and rounding off
Rate per each
Well Glass Luminaires
Supply of 80W M.V integral wellglass
luminaries
with
all
standard
accessories and 80W MV lamp etc.,
complete.
a) Material
80W MV wellglass luminaries
80W MV wellglass luminaries lamp
Sundries and rounding off
Rate per each
Supply of 70W S.V. integral wellglass
luminaries
with
all
standard
accessories and 70W S.V. lamp etc.,
complete.
a) Material
70W SV wellglass luminaires
70W SV wellglass luminaries.
Sundries and rounding off
Rate per each
Flood Light Luminaires
Supply of 500W Halogen fitting with
all accessories including 500W Halogen
lamp etc., complete.
a) Material
500W halogen lamp fitting.
500W halogen lamp
Sundries and rounding off
Rate per each
Supply of 1000W Halogen fitting with
all accessories including 1000W
Halogen lamp etc., complete.
a) Material
1000W halogen lamp fitting.
1000W halogen lamp
Sundries and rounding off
Rate per each

each

each

each
each

1
1

each
each

1
1

each
each

1
1

each
each

1
1

206

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.7.3

7.7.4

BLD-ELEC-78

7.8
7.8.1

7.9.2

Supply of integral type flood light


metal halide luminaire of 250W
comprising of die cast Aluminium
housing and a heat resistant toughned
glass firmly fixed by means of gasket
and toggles with IP-65 protection
incluidng control gear housing and all
accessories with 250W MH-T lamp etc.,
complete.
a) Material
250W MH flood light fitting
250W MH lamp.
Sundries and rounding off
Rate per each
Supply of integral type flood light
metal halide luminaire of 400W
comprising of die cast Aluminium
housing and a heat resistant toughned
glass firmly fixed by means of gasket
and toggles with IP-65 protection
incluidng control gear housing and all
accessories with 400W MH-T lamp etc.,
complete.
a) Material
400W MH flood light fitting
400W MH flood light lamps
Sundries and rounding off
Rate per each
Labour Charges

each
each

1
1

each
each

1
1

Fixing of CFL luminaire (Down lights /


Mirror optic / Ornamental type fitting
with all necessary accessories in false
ceiling / on wall including giving
connections and all labour charges
etc., complete.
a) Material
23/0060 twin core flexible copper
M
cable
screws with rawal plugs
each
Aluminium flat / cement and sand etc.,
LS
labour charges.
b) Labour charges.
Skilled Electrician/carpenter
day
Semi skilled Electrician / Helper
day
Rate per each
Note : Labour Charges considered for15 fixtures / day
.
Fixing of 70W MH down light and
control gear box with necessary
accessories in false ceiling including
giving connections and all labour
charges etc., complete.

1
2

0.066
0.066

a) Material
207

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.9.3

7.9.4

7.9.5

23/0060 twin core flexible copper


cable
screws with rawal plugs
Aluminium flat / cement and sand etc.,
labour charges.
b) Labour charges
Skilled Electrician/carpenter
Semi skilled Electrician / Helper
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
Fixing of 40W tube light luminaire on
wall / Ceiling with / TW round blocks
with all accessories including giving
connections and all labour charges
etc., complete.

each
LS

day
day

0.125
0.125

a) Material
23/0060 twin core flexible copper
M
cable
screws with rawal plugs
each
T.W round blocks
each
Cement and sand etc.,
LS
b) Labour charges
Skilled Electrician/carpenter
day
Semi skilled Electrician / Helper
day
Rate per each
Note : Labour Charges considered for 10 fixtures /
day .
Fixing of 40W tube lights with 1/2 Mtr
conduit suspension arrangements from
ceiling with hooks etc., including giving
connections and all labour charges
etc., complete.
a) Material
20mm dia No.16 gauge conduit pipe .
23/0060 twin core flexible copper
cable
Anchor screws / Hooks / Sockets &
Check
b) Labour charges
Skilled Electrician/carpenter
Semi skilled Electrician / Helper
Rate per each
Note : Labour Charges considered for 6
fixtures / day .
Fixing of 40W street light luminaire to
the wall with 1.0 Mtr., 25mm dia GI
pipe bracket and anti tilting MS flat
etc., including giving connections and
labour charges etc., complete.
a) Material
25mm dia G.I pipe
23/0060 twin core flexible copper

1
2
2

0.1
0.1

M
each

1
1

each

day
day

0.166
0.166

M
M

1
2
208

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

7.9.6

7.9.7

7.9.8

cable
Pipe bending charges
M.S flat and welding charges
b) Labour charges
Skilled Electrician/carpenter
Mason
Semi skilled Electrician / Helper
Rate per each
Note : Labour Charges considered for 5
fixtures / day .
Fixing of CFL street light luminary with
1.0 Mtr., 25mm dia GI pipe bracket
and anti tilting MS flat etc., including
giving connections and labour charges
etc., complete.

LS
LS
day
day
day

a) Material
25mm dia G.I pipe
M
23/0060 twin core flexible copper
M
cable
Pipe bending charges
LS
M.S flat and welding charges
LS
b) Labour charges
Skilled Electrician/carpenter
day
Mason
day
Helper
day
Rate per each
Note : Labour Charges considered for 8
fixtures / day .
Fixing of mirror optic tube light
luminaire in false ceiling / pop with
necessary arrangment including giving
connections and all labour charges
etc., complete.
a) Material
28/0060 twin core flexible copper
M
cable
Aluminium flat (as per requirment)
LS
b) Labour charges for cutting P.O.P /
false ceiling and Fixing MOT
Skilled Electrician
day
Carpenter
day
Semi skilled Electrician / Helper
day
Rate per each
Note : Labour Charges considered for 8 Nos MOT
lights in a day
Fixing of MV / SV/MH luminaire on
wall with 1.0mt 40mm dia GI pipe
bracket and anti-tilting MS flat, 2.5
Sq.mm
flexible
copper
cable
etc.,including all labour charges for
mason work and giving connections
etc., complete.
a) Material
40mm G.I pipe for Bracket
M

0.2
0.2
0.2

1
2

0.125
0.125
0.125

0.125
0.125
0.125

1
209

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec8

8
8.1.1

Bldngs_Elec8-1

8.1.2

8.1.3

2.5 Sq.mm flexible copper cable


M
Pipe bending charges
LS
b) Labour charges for Antitiling MS
flat / welding charges & fixing
Skilled Electrician
day
Carpenter
day
Helper
day
Welder
day
Rate per each
Note : Labour Charges considered for 4Nos MV / SV /
MH in a day
INTERNAL LUMINAIRE
Supply and fixing of single fancy
bracket with glass shade and bulb of
approved colour and quality etc., by
field officers
a) Material
Single Fancy bracket
each
60W Bulb
each
b) Labour charges
Skilled Electrician
day
Helper
day
Sundires
LS
Rate per each
Note : Labour Charges considered for 25Jobs per Day
Supply and fixing of double fancy
bracket with glass shade and bulb of
approved colour and quality etc., by
field officers.
a) Material
Double Fancy bracket
each
60W Bulb
each
b) Labour charges
Skilled Electrician
day
Helper
day
Sundires
Rate per each
Note : Labour Charges considered for
20Jobs /Day
Supply and fixing 10" ceiling fittings
with glass doom and bulb apporved by
dept.,
officers
including
giving
connection etc., complete.
a) Material
10" Ceiling fitting with glass doom
each
60W Bulb
each
b) Labour charges
Skilled Electrician
day
Helper
day
Sundires
Rate per each

0.25
0.25
0.25
0.25

1
1
0.04
0.04

1
2
0.05
0.05

1
1
0.05
0.05

210

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.1.4

Bldngs_Elec8-2

8.2
8.2.1

8.2.2

8.2.3

8.2.4

Note : Labour Charges considered for


20 Jobs / Day
Supply and fixing of Bulk head fitting
with cast Aluminium enamel painted
body with water tight, clear glass with
wire guard hinged with lock and key
arrangements etc., complete with
lamp.
a) Material
Bulkhead fitting
60W Bulb
b) Labour charges
Skilled Electrician
Helper
Sundires such as TW block / screws,
cement etc.,
Rate per each
Note : Labour Charges considered for
12 Jobs / Day
Flourescent Luminaire
Supply and transportation of 1x11 W
mirror light with all standard
accessories diffuser and 1No 11W CFL
lamp etc., complete
a) Material
1x11W M.O. fitting
Cost of C.F.L.
Sundries and rounding off
Rate per each
Supply
and
Transportation
of
1x36/40W box type tube light
luminaire with copper / VPIT Choke,
condensor, starters etc., and 1No
36/40W tube etc., complete.
a) Material
1x40/36 box type T.L fitting
36/40 Tube
Sundries and rounding off
Rate per each
Supply
and
transportation
of
2x36/40W box type tube light
luminaire with 2Nos copper / VPIT
chokes, starters, with condensor and
2Nos 36/40W tube etc., complete.
a) Material
2x40/36 box type T.L fitting
36/40 FTL
Sundries and rounding off
Rate per each
Supply and Transportation of 1x40W
patty type tube light luminaire with
copper choke, starter etc., including
1No 40W tube etc., complete.

each
each

1
1

day
day

0.083
0.083

each
each

1
1

each
each

1
1

each
each

1
2

211

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec8-3

8.3
8.3.1

8.3.2

Bldngs_Elec8-4

8.4
8.4.1

8.4.2

a) Material
1x40 patty type T.L. fitting
40W FTL
Sundires and rounding off
Rate per each
INDUSTRIAL luminaire
Supply and Transportation of white
vitreous 1x36 / 40W industrial box
type luminaire with Copper / VPIT
Choke, Condensor, Starters etc., with
reflector including 1No 40W tube etc.,
complete.
a) Material
1x36/40W Industrial box type T.L.
fitting
36/40W FTL
Sundries and rounding off
Rate per each
Supply and Transportation of white
vitreous 2x36 / 40W industrial box
type luminaire with 2Nos Copper /
VPIT Choke, Condensor, Starters
etc.,complete with reflector including
2Nos 40W tube etc., complete.
a) Material
2x36/40W Industrial box type T.L.
fitting
36/40W FTL
Sundries and rounding off
Rate per each
MIRROR OPTIC luminaire
Supply and Transportation of 2x36 /
40W surface mounting mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror reflectors with VPIT chokes,
Starters, Condensor etc., complete
with
2Nos
36/40W
tubes
etc.,complete.
a) Material
2x36/40 Surface M.O.L fitting
40/36 FTL
Sundries and rounding off
Rate per each
Supply
and
transportation
of
2x36/40W recessed mounting mirror
optic (darklite) luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror reflector with VPIT
Chokes, Starter, Condensor etc.,
complete with 2Nos 36/40W tubes
etc., complete.

each
each

1
1

each

each

each

each

each
each

1
2

212

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.4.3

a) Material
2x36/40 Recessed M.O. L fitting
36/40 FTL
Sundries and rounding off
Rate per each
Supply and transportation of 2x11W
surface
mounting
mirror optic
luminaire with powder coated CRCA
sheet steel housing with Aluminium
mirror refector with VPIT Chokes and
2Nos 11W CFL lamps etc., complete.

8.4.4

a) Material
2x11W CFL surface M.O.L fitting
11W CFL
Sundries and rounding off
Rate per each
Supply and transportation of 2x11W
Recessed type luminaire with powder
coated CRCA sheet steel housing with
Aluminium mirror refector with VPIT
Chokes and 2Nos 11W CFL lamps etc.,
complete.

8.4.5

8.4.6

Bldngs_Elec8-5

8.5

a) Material
2x11W CFL recessed M.O.L fitting
11W cfl
Sundries and rounding off
Rate per each
Supply and transportation of 2x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 36w CFL lamps.
a) Material
2x36 CFL PS paralite Louvars fitting
36w CFL
Sundries and rounding off
Rate per each
Supply and transportation of 3x36w
CFL paralite louvre (P5) recessed low
glare mirror optic luminaire comprising
bright anodised Aluminium reflector
with VPIT Chokes and 3x36w CFL
lamps.
a) Material
3x36 CFL PS paralite Louvars fitting
36w CFL
Sundries and rounding off
Rate per each
T- 5 Luminaires.

each
each

1
2

each
each

1
2

each
each

1
2

each
each

1
2

each
each

1
3

213

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.5.1

8.5.2

Bldngs_Elec8-6

8.6
8.6.1

8.6.2

8.6.3

Supply and transportation of 1X28W


surface pendant mounting T- 5
extruded Aluminium with Aluminium
reflector luminaire with all standard
accessories and connections etc.,
complete with 1 No. 28 W tube
a) Material
1x28w pendant T5 lugs fitting
28w T5 FTL
Sundries and rounding off
Rate per each
Supply and transportation of 2X28W
recessed With 2 Nos. pendant
mounting low glare T- 5 mirror optic
luminaire with electronic Ballasts etc.,
complete 28w tubes.
a) Material
2x28w T5 M.O. fitting
28w T5 FTL
Sundries and rounding off
Rate per each
C.F.L. Down Lights
Supply and transportation of recessed
mounting 1x13W CFL down light with
all standard accessories with 1No. 13W
CFL lamp (D type) etc., complete.
a) Material
1x13W CFL Down light fitting
13W CFL
Sundries and rounding off
Rate per each
Supply and transportation of recessed
mounting 2x13W CFL down light with
all standard accessories with 2No. 13W
CFL lamp etc., complete.
a) Material
2x13W CFL Down light fitting
13W CFL
Sundries and rounding off
Rate per each
Supply and transportation of recessed
mounting 1x18W CFL down light with
all standard accessories with 1No. 18W
CFL lamp etc., complete.
a) Material
1x18W CFL Down light fitting
18W CFL
Sundries and rounding off
Rate per each

each
each

1
1

each
each

1
2

each
each

1
1

each
each

1
2

each
each

1
1

214

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.6.4

8.6.5

8.6.6

8.6.7

Bldngs_Elec8-7

8.7
8.7.1

Supply and transportation of recessed


mounting 2x18W CFL down light with
all standard accessories with 2No. 18W
CFL lamp etc., complete.
a) Material
2x18W CFL Down light fitting
18W CFL
Sundries and rounding off
Rate per each
Supply and Transportation recess
mounting 70W metal hallide down
lighter with control gear and 1No 70W
M.H lamp etc., complete.
a) Material
70W M.H down light fitting
70W M.H lamp
Sundries and rounding off
Rate per each
Supply and Transportation of Ceiling /
Wall
mounted
Circular
1x13W
luminaire with decorative acrylic
diffuser and 1 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
1x13W Circular CFL fitting
13W CFL
Sundries and rounding off
Rate per each
Supply and Transportation of Ceiling /
Wall
mounted
Circular
2x13W
luminaire with decorative acrylic
diffuser and 2 No. 13W CFL lamp
(circular type) etc., complete.
a) Material
2x13W Circular CFL fitting
13W CFL
Sundries and rounding off
Rate per each
HALOGEN DOWN LIGHTERS

each
each

1
2

each
each

1
1

each
each

1
1

each
each

1
2

each
each

1
1

Supply and Transportation of recess


mounting 12v, 50w adjustable halogen
down light with white / colour Shade
including transformer and 1No 50w
halogen lamp etc., complete.
a) Material
50w Halogen recessed mounting
50w Halogen bulb
Sundries and rounding off
Rate per each

215

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

8.7.2

Bldngs_Elec9
Bldngs_Elec9-1

9
9.1
9.1.1(a)

9.1.1(b)

9.1.2 (a)

Supply and Transportation of recess


mounting 12v, 50w Zoom type halogen
down light with white / colour Shade
including transformer and 1No 50w
halogen lamp etc., complete.
a) Material
50w Halogen zoom type down light.
50w Halogen bulb
Sundries and rounding off
Rate per each
AIR CONDITIONING & REFRIGERATION

each
each

1
1

Air-Conditioners
Supply and Transportation of Window
mounted type, Room Air-Conditioner
1.5 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
1.5 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per each
Supply and Transportation of Window
mounted type, Room Air-Conditioner
2.0 Ton confirming to IS : 1391,
Suitable for operation on 230V + 10%
50 Hz.., Single phase, A.C. Supply
capable for performing Cooling,
Dehumidifying, Air Circulating, Filtering
and Ventilation etc., complete.
a) Material
2.0 Ton A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per each
Supply and Transportation of 1.5 Ton
Split type Air-Conditiner, fitted with
Hermetically
sealed
compressor,
Operating on refrigerant R-22 / Non CFC High wall mounting confirming to
IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply
capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering
with cooling and condensing units,
with 5 Mtr of required size of copper
piping duly insulated and 3 core copper
flexible chord of required length etc.,
complete.
a) Material

2%

2%

216

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.1.2 (b)

9.1.3

9.1.4

9.1.5

1.5 Ton Split A.C Unit ABS (Plastic


Cabin)
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per Each
Supply and Transportation of 2.0 Ton
Split type Air-Conditiner, fitted with
Hermetically
sealed
compressor,
Operating on refrigerant R-22 / Non CFC High wall mounting confirming to
IS : 1391, suitable for operation on
230V, 50 Hz.., Single phase, A.C Supply
capable of performing Cooling,
Dehumidifying, Air Circulating, Filtering
with cooling and condensing units,
with 5 Mtr of required size of copper
piping duly insulated and 3 core copper
flexible chord of required length etc.,
complete.
a) Material
2.0 Ton Split ABS Plastic Cabin A.C Unit
ADD : Duties & Taxes as applicable
Transportation on Material
Rate per Each
Installation Charges for 1/0 / 1.5 / 2.0
Ton Window type room AirConditioner with insulating foam,
testing and commissioning etc.,
complete.
a) Material
Installation Charges of Window type
A.C.Unit. (as per observed Data)
Rate per Each
Installation Charges for 1.5 / 2.0 Ton
Split Air-Conditioner with foam,
insulation
for
copper
pipings
connected for the Indoor and outdoor
unit
including
testing
and
commissioning etc., complete.
a) Material
Installation Charges of 1/5 / 2.0 Ton
Split A.C.Unit. (As per observed Data )
Rate per Each
Supply, Fabrication and installation of
well seasoned T.W. frame of size 685 x
483 mm (27" x 19") ( with section size
of 75 x 100 mm (3" x 4" T.W.)) for 1.0 /
1.5 / 2.0 Ton Window A.C.Unit duly
making necessary provision in the wall
/ Window with cost and conveyance of
all materials etc., complete
a) Material
Well seasoned wooden frame for
Window A.C Units

2%

2%

cum

0.018

217

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.1.6

9.1.7

Bldngs_Elec9-2

9.2
9.2.1

b) Labour charges for fabrication &


Fixing
Carpenter
Mason
Helper
Making necessary provision in wall /
window with Hardware
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply, Fabrication and installation of
38 x 38 x 6 mm (1.5" x 1 1/2" x 1/4")
M.S. angle Iron frame suitable for
condensing Unit for Split A.C including
2 Coats of Red oxide the followed by 2
coats enamel paint etc., complete.
a) Material
38 x 38 x 6 mm (1.5" x 1 /12" x 1/4")
angle iron frame, 13 M length (1 Mtr =
3.5 Kgs)
Fabrication charges including Painting
b) Labour charges for Fixing
Carpenter
Mason
Helper
Sundires such as cement etc.
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
Supply and Installation of copper
tubing between indoor and outdoor
unit for split Air-Conditioner including
foaming etc., complete.
a) Material
Copper tubing between indoor and
outdoor units inlcuding foaming
b) Labour charges for cutting,
bending, welding etc.,
Welder
Helper
Rate per Metre
Note : Labour is Considered for 25 M /
day
REPAIRS TO AIR - CONDITIONERS
Replacement of defective compressor
by supply of 1.0 / 1.5 Ton brand new
sealed compressor ISI Mark
a) Material
Supply of brand new.1/ 1.5 Ton
compressor ISI Mark
b) Labour charges
Skilled Electrician

day
day
day
LS

0.5
0.5
0.5

kg

10.5

kg

10.5

day
day
day
LS

0.25
0.25
0.25

day
day

0.04
0.04

each

day

0.5
218

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.2.2

9.2.3

9.2.5

9.2.6

Helper
Transportation on Material
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of defective compressor
by supply of 2.0 Ton brand new sealed
compressor ISI Mark
a) Material
Supply of brand new 2.0 Ton
compressor by brand new ISI Mark
b) Labour charges
Skilled Electrician
Helper
Transportation on Material
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of old and Unserviceable
Fan Motor by supply and Installation of
new 1/6th H.P multi speed Fan Motor
suitable for 1.0 / 1.5 / 2.0 Ton Window
A.C.Unit.
a) Material
Supply of 1/6th H.P multispeed Fan
Motor for 1.0 / 1.5 / 2.0 T A.C.Unit.
b) Labour charges
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Replacement of Unserviceable fan
motor capacitor 6 mfd by new
capacitor for A.C machine of 1.0 1.5 /
Ton Capacity.
a) Material
6 MFD motor capacitor
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement
of
Unserviceable
Thermostat switch by supply and
installation of new thermostat switch
suitable for 1.0 / 1.5 / 2.0 Ton
A.C.Unit.
a) Material
Thermostat switch for 1.0 / 1.5 / 2.0
Ton A.C.Unit.

day

0.5
2%

each

day
day

0.5
0.5
2%

each

day
day

0.5
0.5

each

day

0.2

each

219

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.2.7

9.2.8

9.2.9

9.2.10

b) Labour charges for removing old


one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of Unserviceable starting
capacitor of 80 to 120 mfd. By new
approved make capacitor suitable for
compressor motor of 1.0 / 1.5 Ton A.C.
Unit.
a) Material
Starting capacitor of 80 to 120 mfd.
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of unserviceable running
capacitor of 36 mfd by new approved
make
capacitor
suitable
for
compressor motor of 1.0 / 1.5 Ton
A.C.Unit.
a) Material
Running capacitor 36 mfd
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of Unserviceable relay by
new approved make having pickup
voltage 220 Volts and dropout voltage
120 Volts suitable for 1.0 / 1.50 Ton
A.C. Unit.
a) Material
Relay having pickup 220V and dropout
voltage 120V
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of Unserviceable filter
and capillary tube by supply and
installation of new filter and capillary
tube including welding et., complete
for 1.0 / 1.5 / 2.0 Ton A.C.Unit.

day

0.2

each

day

0.2

each

day

0.2

each

day

0.2

a) Material

220

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.2.11

9.2.11(a)

Bldngs_Elec9-3

9.3
9.3.1

Bldngs_Elec9-4

9.6

Filter and capillary tube for 1.0 /


1.5/2.0 Ton A.C.Unit
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of Unserviceable air filter
by new air filter suitable for 1.50 Ton
A.C.Unit P.V.C. / NYLON for Window
A.C.
a) Material
PVC / Nylon Air Filter for Window type
A.C.Unit.
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement of Unserviceable air filter
by new air filter suitable for 1.50 Ton
A.C.Unit P.V.C. / NYLON for Split A.C.
a) Material
PVC / Nylon Air Filter for Split type
A.C.Unit.
b) Labour charges for removing old
one & fixing
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Refrigerators
Supply Refrigerator domestic type
approved make 165 to 310 Ltrs.
Storage capacity, suitable for operation
on 230 /250 Volts 50 Hz.. complete
with automatic temparture control
confirming to IS specifications No.
1476 / 79 with one year guarantee for
seale unit in refrigeration system
including cost and conveyance of all
materials and labour charges etc.,
complete.
a) Material
----- capacity refrigerator cost
Transportation @ 2% of Unit Cost
Loading, Unloading & Instalation @ 2%
of Unit Cost
Rate per Each
Stabilizers

each

day

0.2

each

day

0.2

each

day

0.2

each

1
2%
2%

221

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.6.1

9.6.2

9.6.3

Supply and erecting fully automatic


line voltage stabilizer for operation on
input voltage 200 to 250V. rated for
0.5 KVA maximum load and time delay
model with
Volt meter, selector
switch, 6A / 16A flush type, 5 pin
socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation
including
cost
and
conveyance of all mateials and all
labour charges etc., complete.
a) Material
0.5 KVA Stabilizer
b) Labour Charges
Semi skilled Electrician
Helper
Transportation Charges on Unit Cost
Rate per Each
Note : Labour is Considered for 23
jobs / day
Supply and erecting fully automatic
line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 1
KVA maximum load and time delay
model with
Volt meter, selector
switch, 6A / 16A flush type, 5 pin
socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation
including
cost
and
conveyance of all mateials and all
labour charges etc., complete.
a) Material
1 KVA Stabilizer
b) Labour Charges
Semi skilled Electrician
Helper
Transportation Charges on Unit Cost
Rate per Each
Note : Labour is Considered for 23
jobs / day
Supply and erecting fully automatic
line voltage stabilizer for operation on
input voltage 200 to 250V. rated for 3
KVA / 4 KVA / 5 KVA maximum load
and time delay model with Volt meter,
selector switch, 6A / 16A flush type, 5
pin socket for out put and with 3 core
flexible chord and 3 pin 6/16A plug top
suitable for refrigerator for continuous
operation
including
cost
and
conveyance of all mateials and all
labour charges etc., complete.

each

day
day

0.044
0.044
2%

each

day
day

0.044
0.044
2%

222

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec9-5

9.7
9.7.2

9.7.7

9.7.10

9.7.16

a) Material
3 KVA / 4 KVA / 5 KVA Stabilizer
b) Labour Charges
Skilled Electrician
Helper
Transportation Charges on Unit Cost
Rate per Each
Note : Labour is Considered for 10
jobs / day
Fans

each

day
day

0.1
0.1
2%

each

Supply of 900 mm (36") / 1200 mm


(48") / 1400 mm (56") sweep 230V, A.C
50 Hz.Ceiling fan with 3 Blades and
double ball bearings with all standard
accessories.
a) Material
900 mm (36") / 1200 mm (48") / 1400
mm (56") Ceiling Fan
Transportation Charges on Unit Cost
Rate per Each
Supply and erecting wall mounting fan
400mm (16") / 450 mm (18") sweep
A.C. 50Hz.. 1350 r.p.m oscillating type
with regulator.
a) Material
400mm (16") / 450 mm (18") wall
mounting Fan
b) Labour Charges
Semi Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply of pedastal fan (16") 400mm,
250 Volts, 50Hz. oscillating type
complete with all standard accessories.
a) Material
400mm (16") Pedastal Fan
Transportation Charges on Unit Cost
Rate per Each
EXHAUST FANS
Supply of fresh air exhaust fan of light
duty 250V A.C.50Hz.. 225 mm (9") /
300mm size (12") 1350 R.P.M Metallic
body plastic blades, wire mesh, etc.,
complete.
a) Material
225 mm (9") / 300mm (12") L.D.
Exhaust Fan
Transportation Charges on Unit Cost
Rate per Each

1%

each

day
day

0.1
0.1

each

1
2%

each

1
1%

223

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.7.18

9.7.24

9.7.25

9.7.26

9.7.33

Supply of fresh air exhaust fan of


Heavy duty 250V A.C.50Hz.. 300mm
size (12") / 375 mm (15") 900 R.P.M
etc., complete.
a) Material
300mm (12") / 375 mm (15") H.D.
Exhaust Fan
Transportation Charges on Unit Cost
Rate per Each
Supply and erecting fan hook of
12/15mm dia M.S. rod / bar grouted in
RCC slab with making the slab as
original.
a) Material
12/15mm plain M.S rod for Fan hook
Cement, Sand and Rounding off
b) Labour charges for grouting in RCC
slab, Fixing of Fan hook with
masonary work.
Mason
Helper
Rate per Each
Note : Labour is Considered for 6 jobs
/ day
Supply and erecting 19/20mm steel
tube down rod of one meter length
with bolts & nuts duly painted with
matching colour of fan complete
a) Material
19/20mm steel tube down rod with
bolts & nuts for fan with maching
colour.
b) Labour charges for Fixing
Helper
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and erecting resistance type
regulator
for
ceiling
fans
900/1200/1400mm sweep complete
erected on existing board.
a) Material
Resistance type Regulator
b) Labour charges.
Semi skilled Electrician
Rate per Each
Note : Labour is Considered for 10
jobs / day
Cleaning of Ceiling fan in existing
position .
Labour charges for cleaning greasing /
oilingoverhauling
Helper

each

1
1%

each
LS

day
day

0.166
0.166

day

0.1

day

0.1

day

0.2

224

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

9.7.34

9.7.35

9.7.36

Rate per Each


Note : Labour is Considered for 10 jobs / day by 2
helpers
Removing the ceiling fan and refixing
after overhauling and greasing the
bearings and replacement of wire
leads etc complete
a) Material
23/0060 twin core wire
M
b) Labour charges.
Removing and refixing of ceiling fan
after overhauling
Semi skilled Electrician
day
Helper
day
sundries
LS
Rate per Each
Note : Labour is Considered for 6 jobs
/ day
Labour Charges
Labour charges for Fixing of Ceiling fan
and regulator including transportation
and giving connections with twin core
wire etc., complete.
a) Material
23/0060 Twin Core wire
M
Unforseen item works, such as painting
LS
to down rod, screws etc.,
b) Labour charges.
Skilled Electrician
day
Helper
day
Rate per Each
Note : Labour is Considered for 8 fans
/ day
Labour charges for fixing of Exhaust fan
in wall with necessary connections and
masonary work of making hole,
finishing etc., complete
a) Material
23/0060 Twin flat wire
M
Cement
kg
b) Labour charges.
Skilled Electrician
day
Helper
day
Mason
day
Sundries such as Sand, Bolt, Nuts etc.,
LS
Rate per Each
Note :1. Labour is Considered for 6
jobs / day
2. Cost of louver shutter may be added
if required.
3. If hole is already made available,
labour charges of Mason shall be
deleted.

0.166
0.166

0.125
0.125

1
25
0.25
0.25
0.25

225

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec10

10
10.1.2

Bldngs_Elec10-1

10.1.5

Bldngs_Elec10-2

10.2
10.2.1

WATER HEATERS
Supply and Transportation of stove
enamelled storage / pressure type
vertical / Horizontal water heater with
copper tank 25 / 35 / 50 Ltrs. Capacity
with non return valve on inlet side and
dead weight pressure reducing valve
on outlet side 230/ 250V, single phase
2000
watts
heating
element,
thermostat control, fusible plug, pilot
lamp etc., erected and tested complete
with ISI specifications etc., including all
materials, transportation, and labour
charges complete.
a) Material
25 / 35 / 50 Ltrs. Water Heater
Transportation Charges on Unit Cost
Rate per Each
Labour charges for erection of storage
water heater with 2Nos Nylon / PVC /
Metalic hose pipe etc., on wall duly
making necessary fixing arrangments
including connections etc., complete.
a) Material
Flexible Nylon / PVC / Metallic hose
pipe
50 / 100 mm (2" / 4") long bolt and nut
with washers
Towards wooden plugs, cement etc.,
b) Labour charges.
Skilled Electrician
Helper
Semi skilled Mason
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
INSTANT WATER HEATERS

each

1
2%

each

each

LS
day
day
day

0.25
0.5
0.25

each

1
2%
2

Supply and erecting ISI Mark 3KW


Instant Water heater with multiple
safety system, rust free ABS plastic
body, 230V, 50Hz.., A.C. supply with
inlet and outlet connections with pvc/
nylon / metallic hose pipe, thermostat
control and thermal cutoff with 3 core
P.V.C. flexible wire leads duly tested
including cost of all materials and all
labour charges etc., complete.
a) Material
3KW Instant Water Heater
Transportation Charges on Unit Cost
Hose pipe PVC/ Nylon

each

226

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec10-3

10.4
10.4.1

10.4.2

10.4.5

Bldngs_Elec11
Bldngs_Elec11-1

11
11.1

T.W getting Bolt / Nuts, Cement, Sand


etc.
b) Labour charges.
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 4 jobs
/ day
REPAIRS TO WATER HEATERS.
Replacement of unserviceable heating
element by new one for 1.5 / 2.0 / 3.0
Kw water heater
a) Material
2/3 KW heating Element
b) Labour charges.
Skilled Electrician
Sundries and rounding off
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Replacement
of
Unserviceable
thermostat by new thermostat with
range 30 to 90 C. adjustable and
suitable for 25 to 50 Ltrs. Capacity.
a) Material
Thermostat range 30-90 Degree
suitable for 25 to 50 Ltrs.
b) Labour charges.
Skilled Electrician
Sundries and rounding off
Rate per Each
Replacing unserviceable pressure
release valve by new water heater of
15 to 50 Ltrs.capacity.
a) Material
Pressure release valve for 25 to 50 Ltrs
water heater
b) Labour charges.
Skilled Electrician
Sundries and rounding off
Rate per Each
WATER PUMPS

LS

day
day

0.25
0.25

each

day
LS

0.2

each

day
LS

0.2

each

day
LS

0.2

Mono-Block Pumps

227

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.1

11.1.2

Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 0.5HP exculding suction /
delivery pipe with nuts duly grouted on
existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
0.5HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 1HP exculding suction /
delivery pipe with nuts duly grouted on
existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
1 HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper

each

2%

day
day
day
LS

0.5
1
0.5

each

2%

day
day

0.5
1
228

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.3

11.1.4

Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 1.5 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
1.5 HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges.
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 230V,
Single phase, 50Hz.. 1440 RPM
A.C.Supply of 2.0 HP exculding suction
/ delivery pipe with nuts duly grouted
on existing C.C foundation and bolts,
spring washers of requisite size for
monoblock motor and pump (IS :
9079).
a) Material
2 HP, 230V, single phase A.C 50Hz.
1440 RPM with all accessories.
Including all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber

day
LS

0.5

each

2%
day
day
day
LS

0.5
1
0.5

each

2%

day
day
day

0.5
1
0.5
229

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.5

11.1.6

Sundries and rounding off


Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
3.0HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 3 HP, 415V, 50Hz., 2880 RPM
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 5 HP, 415V, 50Hz., 2880 RPM
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each

LS

each

1
2%

day
day
day
LS

1
1
1

each

1
2%

day
day
day
LS

1
1
1

230

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.7

11.1.8

Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
7.5HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 7.5 HP, 415V, 50Hz., 2880
RPM centrifugal mono block pump
with all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
Supply and erecting approved make
centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
10HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 10 HP, 415V, 50Hz., 2880 RPM
centrifugal mono block pump with all
taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each

each

2%

day
day
day
LS

1
1
1

each

2%

day
day
day
LS

1
1
1

231

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.1.9

Bldngs_Elec11-2

11.2
11.2.1

Supply and erecting approved make


centrifugal water pump with impeller,
priming funnel cork, companion
metallic flanges, with bolts and nuts
and mounted on a common shaft of
high efficient squirrel cage Induction
motor totally enclosed and fan cooled
type suitable to operate on 415V, 3
phase, 50Hz.. 2880 RPM A.C.Supply of
15HP exculding suction / delivery pipe
with nuts duly grouted on existing C.C
foundation and bolts, spring washers
of requisite size for monoblock motor
and pump (IS : 9079).
a) Material
3 phase, 15 HP, 415V, 50Hz., 2880 RPM
centrifugal Water pump with all taxes
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rounding off
Rate per Each
EJECTO PUMPS
Supply and erecting Ejecto type water
pump single phase, 0.5HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including
transportation
of
all
materials and labour charges etc.,
complete.
a) Material
0.5 HP, single phase, 230V, 50Hz.
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm
pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician
Helper
Fitter
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

each

1
2%

day
day
day
LS

1
3
1

each

each

2
2%

day
day
day
LS

0.5
1
0.5

232

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.2

11.2.3

Supply and erecting Ejecto type water


pump single phase, 1.0HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80feet
including
transportation
of
all
materials and labour charges etc.,
complete.
a) Material
1.0 HP, single phase, 230V, 50Hz.
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm
pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician
Helper
Fitter
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting Ejecto type water
pump single phase, 1.5HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including
transportation
of
all
materials and labour charges etc.,
complete.
a) Material
1.5 HP, single phase, 230V, 50Hz.
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm
pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician
Helper
Fitter
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

each

each

2
2%

day
day
day
LS

0.5
1
0.5

each

each

2
2%

day
day
day
LS

0.5
1
0.5

233

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.4

11.2.6

Supply and erecting Ejecto type water


pump single phase, 2.0HP single stage
with brass venturi and having suction
pipe 40mm dia, pressure pipe 32mm
dia and delivery pipe 32mm dia, with
maximum discharge head of 80 feet
including
transportation
of
all
materials and labour charges etc.,
complete.
a) Material
2.0 HP, single phase, 230V, 50Hz.
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm
pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician
Helper
Fitter
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting Ejecto type water
pump 3 phase, 3 HP single stage with
brass venturi and having suction pipe,
pressure pipe and delivery pipe, with
maximum discharge head of 80 feet ,
including transportation, and all
materials all labour charges etc.,
complete.
a) Material
3.0 HP, single phase, 230V, 50Hz.
Ejecto type pump set. Including all
taxes
M.S clamps suitable for 40mmx32mm
pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Electrician
Helper
Fitter
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

each

each

2
2%

day
day
day
LS

0.5
1
0.5

each

each

2
2%

day
day
day
LS

0.5
1
0.5

234

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.2.7

Bldngs_Elec11-3

11.3
11.3.1
(a)

Supply and erecting Ejecto type water


pump 3 phase, 5 HP single stage with
brass venturi and having suction pipe,
pressure pipe and delivery pipe, with
maximum discharge head of 80',
including transportation, and all
materials all labour charges etc.,
complete.
a) Material
3Ph, 5 HP 415V, 50Hz. Ejecto pump set
with all taxes
M.S clamps suitable for Air and
delivery pipes with nuts and bolts.
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
SUBMERSIBLE PUMPS (Bore well type)
Supply and erecting, ISI mark
submersible 1.0 HP,Single Phase
18stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V, 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
1HP,
Single
Phase
18
stage
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rouding off

each

each

2
2%

day
day
day
LS

0.5
1.5
0.5

each

each

2
2%

day
day
day
LS

0.5
1
0.5

235

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.1
(b)

11.3.1 (c)

Rate per Each


Note : Labour is Considered for 2 jobs
/ day
Supply and erecting, ISI mark
submersible 1.5 HP, Single Phase 20
stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V , 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
1.5HP, Single Phase 20 stage
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting, ISI mark
submersible 2.0 HP, Single Phase 30
stages pumpset suitable for 106 /
156mm dia borewell with high quality
water resistant and dynamically
balanced bronze impeller with
stainless steel shaft sleeves, pump
coupling and pivot of Single phase
250V , 50Hz.. A.C. power supply copper
winding with water proof insulation
and high precision strength not to be
effected by chemical in water and
suitable bronze bearings with nut and
bolts etc., with necessary H-type
clamp of suitable size and strength.
a) Material
2HP, Single Phase
30 stage
submerisible pump set including all
taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost

each

each

2
2%

day
day
day
LS

0.5
1
0.5

each

each

2
2%
236

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.2

11.3.3

b) Labour charges for erection of


pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Sundries and rouding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting, ISI mark
submersible 2.0 HP, 3 Phase, 3 stages
pumpset suitable for 156mm dia
borewell with high quality water
resistant and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
2HP, 3 Ph 3 stage submerisible pump
set including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 3.0 HP,3 Phase, 4 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.

day
day
day
LS

0.5
1
0.5

each

each

2
2%

day
day
day

1
2
1

LS

237

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.4

a) Material
3HP, 3 Ph 4 stage submerisible pump
set. Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump
set. Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each

each

each

2
2%

day
day
day

1
2
1

LS

each

each

2
2%

day
day
day

1
2
1

LS

238

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.5

11.3.6

Supply and erecting, ISI mark


submersible 3 HP, 3 Phase, 8 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump
set. Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 3 HP, 3 Phase, 9 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3HP, 3 Ph 6 stage submerisible pump
set Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper

each

each

2
2%

day
day
day

1
2
1

LS

each

each

2
2%

day
day

1
2
239

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.7

11.3.8

Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 6 stage submerisible pump
set including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 4 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
4HP, 3 Ph 12 stages submerisible pump
set Including all taxes
Special M.S. clamps with bolts and nuts
Transportation Charges on Unit Cost

day

LS

each

each

2
2%

day
day
day

1
2
1

LS

each

each

2
2%
240

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.10

11.3.11

b) Labour charges for erection of


pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 5 HP, 3 Phase, 8 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph, 5 HP, 8 St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 5 HP, 3 Phase, 13 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material

day
day
day

1
2
1

LS

each
each

1
2
2%

day
day
day

2
3
1

LS

241

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.12

Cost of 3 Ph, 5 HP, 8 St. S.M pumpset


Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 7.5 HP,3 Phase, 6 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3 Ph, 7.5 HP, 6 St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each

each
each

1
2
2%

day
day
day

2
3
1

LS

each
each

1
2
2%

day
day
day

2
3
1

LS

242

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.13

11.3.15

Supply and erecting, ISI mark


submersible 7.5 HP, 3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V , 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
3 Ph, 7.5 HP, 12 St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 10 HP,3 Phase, 12 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,10 H.P 12St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber

each
each

1
2
2%

day
day
day

2
3
1

LS

each
each

1
2
2%

day
day
day

2
3
1

243

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.3.16

11.3.17

Hire charges of tripod with winch 50%


of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 10 HP,3 Phase,16 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,10 H.P 16 St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply and erecting, ISI mark
submersible 15 HP, 3 Phase, 15 stages
pumpset suitable for 156mm dia
borewell with high quality wear
resistance and dynamically balanced
bronze impeller with stainless steel
shaft sleeves, pump coupling and pivot
of 3 phase 415V, 50Hz.. A.C. power
supply copper winding with water
proof insulation and high precision
strength not
to be effected by
chemical in water and suitable bronze
bearings with nut and bolts etc., with
necessary H-type clamp of suitable size
and strength.
a) Material
Cost of 3 Ph,15 H.P 15 St. S.M pumpset
Special Clamps with Bolts & Nuts
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery

LS

each
each

1
2
2%

day
day
day

2
3
1

LS

each
each

1
2
2%

244

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec11-4

11.4
11.4.1

Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
SUB MERSIBLE PUMPS (OPEN WELL)
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 3
HP pump erected with necessary Htype clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 3HP Submersible motor
Special clamps with nut and bolis
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each

day
day
day

2
4
1

LS

each
each

1
2

2%

day
day
day

1
2
1

LS

245

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.4.2

11.4.3

Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings, 5
HP pump erected with necessary Htype clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 5HP Submersible motor
Special clamps with nut and bolis
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
Rate per Each
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings,
7.5 HP pump erected with necessary
H-type clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 7.5HP Submersible motor
Special clamps with nut and bolis

each
each

1
2

2%

day
day
day

1
2
1

LS

each
each

1
2

246

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.4.4

Bldngs_Elec11-5

11.5

MS Girders across the open well to


support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
day
Helper
day
Plumber
day
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
LS
Rate per Each
Supply
and erecting ISI make
submersible pumpset suitable for
erection in open well with water
resistant
dynamically
balanced
impeller with stainless steel shaft
sleeves, pump coupling and pivot with
squirrel cage Induction Motor of 3
phase, 415V, 50Hz.., A.C.Supply, heavy
copper windings with water proof
insulation and high precision strength
not to be effected by chemicals in
water with suitable bronze bearings,
10 HP pump erected with necessary Htype clamps of suitable size and
strength including cost of all materials,
Transportation and labour charges
etc., complete.
a) Material
3 Ph, 10 HP Submersible motor
each
Special clamps with nut and bolis
each
MS Girders across the open well to
support delivery pipe clamps (as per
requirement)
Transportation Charges on Unit Cost
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
Skilled Fitter
day
Helper
day
Plumber
day
Hire charges of tripod with winch 50%
of Labour charges
Sundries and rouding off
LS
Rate per Each
Note:- Above rates of pumpsets are exculding
suction & delivery pipes
ACCESSORIES

2%

1
2
1

1
2

2%

1
3
1

247

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.5.1

11.5.2

11.5.2(a)

11.5.3

Providing cement concrete with 1:2:4


foundation for pump and motor with
required size and length of foundation
bolts and nuts including cost and
conveyance of all materials and labour
charges etc., complete.
a) Material
Rate as per Civil SSR, since it is a Civil
item.
Supplying and erecting D.O.L Starter
250V, Single phase, 50Hz. With SS
enclouser comprising of contactor
with bi-metalic relay with necessary
push buttons, transportation and all
labour charges etc., complete .
a) Material
D.O.L. Starter 1Ph, 250V
b) Labour charges for fixing and giving
connections.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supplying and erecting D.O.L Starter
400V, 3 phase, 50Hz. enclosed with no
volt coil and overload protection with
necessary materials, transportation
and all labour charges etc., complete
suitable upto 3/4/5 HP.
a) Material
D.O.L. Starter 3Ph, 415V upto 3/4/5HP
b) Labour charges for fixing and giving
connections.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable from
7.5 HP upto 15 HP motor totally
enclosed with over load protection and
No-volt
relay etc., to complete
including Transportation and all labour
charges.
a) Material

each

day
day

0.33
0.33

each

day
day

0.33
0.33

248

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.5.4

11.5.5

Semi automatic 3Ph, Induction motor


with enclosure (Including of all taxes
with Transportation)
b) Labour charges for fixing and giving
connections.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable upto
15 to 25 HP motor totally enclosed
with over load protection and No-volt
relay etc., to complete including
Transportation and all labour charges.
a) Material
Deduct
Cost of semi Automatic star - Delta
starter
Semi automatic 3Ph, Induction motor
with enclosure (Including of all taxes
with Transportation)
b) Labour charges.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and fixing of approved make
automatic operated 3ph, 415V star delta started suitable 10 to 12.5 HP
automatic star delta starter motor
totally enclosed with over load
protection and No-volt
relay to
complete including Transportation and
all labour charges .
a) Material
Cost of semi Automatic star - Delta
starter
Semi automatic 3Ph, Induction motor
with enclosure (Including of all taxes
with Transportation)
b) Labour charges.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each

each

day
day

0.5
0.5

each

each

day
day

0.5
0.5

each

each

day
day

0.5
0.5

249

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

11.5.6

11.5.7

Bldngs_Elec12

Bldngs_Elec13

12

13
13.1

Bldngs_Elec13-1

Note : Labour is Considered for 2 jobs


/ day
Supply and fixing of approved make
semi automatic hand operated 3ph,
415V star - delta started suitable for 15
HP fully automatic star delta motor
totally enclosed with over load
protection and No-volt
relay to
complete including Transportation and
all labour charges.
a) Material
Cost of semi Automatic star - Delta
starter
Semi automatic 3Ph, Induction motor
with `enclosure (Including of all
taxes with Transportation)
b) Labour charges.
Skilled Electrician
Helper
Sunries such, as bolts, nuts and
rounding off
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and erecting directly operated
single phasing preventer connected to
A.C. supply upto 45A range with
guarantee to operate on single phase
for one Year.
a) Material
Single phase parameter upto 45A
(Including all taxes and Transportation)
b) Labour charges.
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Bus Bars

each

each

day
day

0.5
0.5

each

day
day

0.2
0.2

For details, Please see after Chapter


20.
SWAGED POLES (Confirming to IS
2713 / 1980).
Fabrication, supply and transportation
of swaged poles up to site confirming
to IS 2713 / 1980 specifications. The
pole should be painted with primary
coat of red oxide and black bituminous
paint up to ground level with base
plate, including cost of all materials
etc., complete.
a) Material
Cost of swaged pole
250

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Add: Labour for handling


Transportation
charges,
loading
unloading as per Common SSR taking
250Km as average load considering
fabrication point at hyd and
Visakhapatnam.
Transportation charges upto 250Km
Breakup.
P.No. 156 of Common SSR (Civil)
Upto
20
Km
163.80 / Tonne
Upto 50 Km
Upto 80 Km
Beyond 106 Km
Loading
Unloading
Stacking

3.40 x 10
2.80 x 50
2.20 x 156
15.50 /
Tonne
12.00 /
Tonne
7.00 /
Tonne

Rate per Kg
D A T A F O R M . S S W A G E D P O L E S C O N F I R M I N G TO I.S : 2713 /1980
Data
No.

Specification of pole
length of pole.
as per IS 2713 / 1980

Overall

2
3

13.1.1
410 SP.2
13.1.2
410 SP.3
13.1.3
410 SP.5
13.1.4
410 SP.6
13.1.5
410 SP.11
13.1.6
410 SP.12
13.1.7
410 SP.26
13.1.8
410 SP.27
13.1.9
410 SP.41
13.1.10
410 SP.42
13.1.11
410 SP.50
13.1.12
410 SP.51
13.1.13
410 SP.59
13.1.14
410 SP.60
13.1.15
410 SP.73
13.1.16
410 SP.74
13.1.17
410 SP.77
13.1.18
410 SP.78
O.D and thickness
Pole in Kgs
of sections
Bottom
Middle

7 Mtrs.
7 Mtrs.
7.5 Mtrs.
7.5 Mtrs.
8 Mtrs.
8 Mtrs.
9 Mtrs.
9 Mtrs.
10 Mtrs.
10 Mtrs.
11 Mtrs.
11 Mtrs.
12 Mtrs.
12 Mtrs.
14.5 Mtrs.
14.5 Mtrs.
16 Mtrs.
16 Mtrs.
Weight of

Planting
depth in
mtrs.

Length of Sections
In Mtrs.
Botto Mid
Top
m
dle

5a

5b

5c

1.25
1.25
1.25
1.25
1.50
1.50
1.50
1.50
1.80
1.80
1.80
1.80
2.00
2.00
2.00
2.00
2.30
2.30
Weight of
Base plate
in Kgs.

4.00
4.00
4.50
4.50
4.50
4.50
5.00
5.00
5.20
5.20
5.60
5.60
5.80
5.80
6.50
6.50
7.00
7.00
Total
weigh
t in
Kgs.

1.50
1.50
1.50
1.50
1.75
1.75
2.00
2.00
2.40
2.40
2.70
2.70
3.10
3.10
4.00
4.00
4.50
4.50
Rate
/ Kg
inclu
ding
Tran

1.50
1.50
1.50
1.50
1.75
1.75
2.00
2.00
2.40
2.40
2.70
2.70
3.10
3.10
4.00
4.00
4.50
4.50
Total
cost
of
pole

251

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Top

6a
114.3x4.5
114.3x5.4
114.3x4.5
114.3x5.4
114.3x4.5
114.3x5.4
114.3x45
114.3x5.4
139.7x4.85
139.7x5.4
139.7x4.85
139.7x5.4
165.1x4.85
165.1x5.4
193.7x5.4
193.7x5.9
193.7x5.4
193.7x5.9
Bldngs_Elec13-2

13.2
13.2.1

13.2.2

Bldngs_Elec-

13.3

6b
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
88.9x4.05
88.9x4.85
114.3x4.5
114.3x4.5
114.3x4.5
114.3x4.5
139.7x4.5
139.7x4.5
165.1x4.85
165.1x5.4
165.1x4.85
165.1x5.4

6c
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
76.1x3.25
88.9x3.25
88.9x3.25
88.9x3.25
88.9x3.25
114.3x3.65
114.3x3.65
139.7x4.50
139.7x4.50
139.7x4.50
139.7x4.50

7
73
85
79
93
83
97
92
108
135
144
147
164
197
208
312
336
341
367

8
5
5
5
5
5
5
5
5
5
5
5
5
5
5
10
10
10
10

9
78
90
84
98
88
102
97
113
140
149
152
169
202
213
322
346
351
377

Kg

24.8

Kg

37.2

spor
tatio
n
and
Fabr
icati
on
10

11

Garden Posts
Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 4mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
4Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole
cap
Rate per Each
Fabrication and Supply of M.S. Poles
for garden posts with 'B' class 6 mtrs
long 60.25mm outer dia with base
plate and suitable pole cap including
cost and conveyance of all material
including fixing of luminaire and labour
charges etc., complete.
a) Material
6Mtrs 'B' Class M.S. pipe of 60.25mm
dia with base plate and suitable pole
cap
Rate per Each
Brackets

252

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13-3
13.3.1

13.3.2

13.3.3

Supply and fixing of 50mm dia 0.5 mtrs


single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
0.5Mtr length 50mm 'B' class pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and enamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Fitter
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and fixing of 50mm dia 0.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire
a) Material
2 x 0.5Mtr length 50mm 'B' class pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and enamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Fitter
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of 50mm dia 0.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 0.5Mtr length 50mm 'B' class pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and enamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Fitter
Rate per Each

Kg
Kg
job

2.55
5.4
1

day
day

0.2
0.2

Kg
Kg
job

5.1
5.4
1

day
day

0.33
0.33

Kg
Kg
job

7.65
5.4
1

day
day

0.5
0.5

253

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.3.4

13.3.5

13.3.6

Note : Labour is Considered for 2 jobs


/ day
Supply and fixing of 50mm dia 1 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire
a) Material
1Mtr length 50mm 'B' class M.S pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Fitter
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and fixing of 50mm dia 1 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
2 x 1Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of 50mm dia 1 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 1Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician

Kg
Kg
job

5.1
5.4
1

day
day

0.2
0.2

Kg

10.2

Kg
job

5.4
1

day
day

0.33
0.33

Kg

15.3

Kg
job

5.4
1

day

0.5
254

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.3.7

13.3.8

13.3.9

Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
single arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
double arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
2 x 1.5Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
triple arm M.S. pipe bracket with
sleeve and fasteners with necessary
angle including painting etc., complete
on existing pole including fixing of
luminaire.
a) Material
3 x 1.5Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.

day

0.5

Kg

7.65

Kg
job

5.4
1

day
day

0.2
0.2

Kg

15.3

Kg
job

5.4
1

day
day

0.33
0.33

Kg

22.95

Kg
job

5.4
1

255

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.3.10

13.3.11

b) Labour charges for fixing with Spl. T


&P
Skilled Electrician
Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
curved single arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
1.5 Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
For Moulding & making Suitable curve
on length
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and fixing of 50mm dia 1.5 mtrs
curved double arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
2 x 1.5 Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
For Moulding & making Suitable curve
on length
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

day
day

0.5
0.5

Kg

7.65

Kg
job

5.4
1

day
day
job

0.2
0.2
1

Kg

15.3

Kg
job

5.4
1

day
day
job

0.33
0.33
1

256

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.3.12

Bldngs_Elec13-4

13.4
13.4.1

Supply and fixing of 50mm dia 1.5 mtrs


curved triple arm M.S. pipe bracket
with sleeve and fasteners with
necessary angle including painting etc.,
complete on existing pole including
fixing of luminaire.
a) Material
3 x 1.5 Mtr length 50mm 'B' class M.S
pipe.
45cm length , 10cm dia and cap.
Painting with red oxid and anamel
paint.
b) Labour charges for fixing with Spl. T
&P
Skilled Electrician
Helper
For Moulding & making Suitable curve
on length
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Erection Charges for Swaged Poles

Kg

22.95

Kg
job

5.4
1

day
day
job

0.5
0.5
1

cum

0.54

cum
cum
M

0.54
0.054
6.2

each

day
day
day

0.33
2.67
0.33

Erection charges for 7 mtrs. to 8 mts


long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P painting of Pole CC 1:3:6
upto ground and 1:2:4 for Couping
work,
including
labour
and
transportation charges etc., complete
a) Material
Pit excavation 156 Cmx
60Cmx60cm.(Civil SSR)
C.C.work for pit 1:3:6 (Civil SSR)
Couping 1:2:4 (Civil SSR)
Painting with red oxid and enamel
paint.
Coil earthing
b) Labour charges
Skilled Electrician
Helper
Mason
Hire charges for Spl.T&P 40% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

257

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.2(a)

13.4.2(b)

Erection charges for 9 mtrs to 11 mtrs


long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P painting of Pole CC 1:3:6
upto ground and 1:2:4 for Couping
work,
including
labour
and
transportation charges etc., complete.
a) Material
Pit excavation 156 Cmx
60Cmx60cm.(Civil SSR)
C.C.work for pit 1:3:6 (Civil SSR)
Couping 1:2:4 (Civil SSR)
Painting with red oxid and enamel
paint.
Coil earthing
b) Labour charges
Skilled Electrician
Helper
Mason
Hire charges for Spl.T&P 40% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Erection charges for 12 Mts to 14Mts
long swaged pole including excavation
of pit, coil earthing, hire charges of
special T&P (Crane)painting of Pole CC
1:3:6 upto ground and 1:2:4 for
Couping work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 2.0x1.0x1.0Mtr
1:3:6 CC Work
couping 1:2:4
Painting with red oxid and alluminum
paint.
Coil earthing
b) Labour charges
Skilled Electrician
Helper
Mason
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 2 jobs
/ day

cum

0.72

cum
cum
M

0.72
0.054
8.35

each

day
day
day

0.33
2.67
0.33

cum
cum
cum
M

2
2
0.054
12

each

day
day
day

0.5
4
0.5

258

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.3

13.4.4

Erection charges for


16Mts long
swaged pole including excavation of
pit, coil earthing, hire charges of
special T&P (Crane)painting of Pole CC
1:3:6 upto ground and 1:2:4 for
Couping work, including labour and
transportation charges etc., complete.
a) Material
Pit excavation 2.30x1.0x1.0Mtr
1:3:6 CC Work
couping 1:2:4
Painting with red oxid and alluminum
paint.
Coil earthing
b) Labour charges
Skilled Electrician
Helper
Mason
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Erection charges for 7to 9Mts long
swaged pole on bridge kerb portion (
R.C.C. work with V.C.C. M.15 concrete
with 3 Nos 25x6 mm MS Special clamps
bolts with nuts and locking nuts
etc.including cost and con veyance of
all material and all labour charges etc.
complete with painting.
a) Material
Painting with red oxid and enamel
paint.
Coil earthing
3 Nos, 25 x 6 mm MS Special Clamps of
1 M Length each @ 1.18 Kg
VCC M 15 Concrete 0.5 x 0.3 x 0.9
b) Labour charges
Skilled Electrician
Helper
Mason
Fanrication of clamps
Hire charges for Spl.T&P 20% on labour
cost
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

cum
cum
cum
M

2.3
2.3
0.054
14

each

day
day
day

0.5
4
0.5

6.2

each
Kg

1
3.54

cum

0.135

day
day
day
kgs

0.33
2.67
0.33
3.54

259

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.4.5

13.4.6

13.4.7

Erection charges for 4 Mtrs. Long MS /


GI Garden post including excavation of
pit, concreting 1:3:6 and painting
including cost and conveyance of all
materials including fixing of luminaire
and labour charges etc., complete.
a) Material
Pit excavation (0.4x0.4x1.0 mtr)
Painting with red oxide and enamel
paint.
1:3:6 C.C work.
b) Labour charges
Mason
Helper
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Erection charges for 6Mtrs. Long MS /
GI Garden post including excavation of
pit, concreting 1:3:6 and painting
including cost and conveyance of all
materials including fixing of luminaire
and labour charges etc., complete.
a) Material
Pit excavation ( 0.45x0.45x1.25)
1: 3: 6 C.C. work
Painting with red oxide and enamel
paint
b) Labour charges
Mason
Helper
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Fabrication, supply and fixing of
luminaire carriage, made with 50mm
dia M.S. 'B' class pipe, moulded to 6
feet dia ring wheel, and 40mm dia M.S
support pieces on 4 sides inside the
wheel and necessary size of M.S pole
cap for fixing the ring wheel on the
156mm dia M.S. pole for fixing
floodlight and gear box with suitable
nut & bolts and painted with Red
Oxide and Aluminium paint including
cost & conveyance of all materials etc.,
complete.
a) Material
50mm 'B' class MS pipe of 5.7mts
(1Mt=5.106Kgs)
40mm 'B' glass pipe MS pipe of 3.6Mtr
(1Mt=3.61Kgs)
200mm MS pipe for pole cap.C-Class
(heavy) 0.3Mts (1Mt=31Kgs)

cum
M

0.16
2.5

cum

0.16

day
day

0.2
0.4

cum
cum
M

0.25
0.25
4.75

day
day

0.2
0.4

Kg

29.07

Kg

13

Kg

13

260

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec13-5

13.5
13.5.1

13.5.2

13.5.3

Special bolts and nuts 6" length.


Painting with red oxide and enamel
paint etc.,
b) Labour charges
Fitter
Helper
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
Accessories
Supply and fixing of 300mm x 260mm x
140mm No.16 gauge CRCA sheet box
with hinged door and locking
arrangements and din channel for
fixing 2Nos MCBs duly powder coated
with matching colour of poles including
fixing with necessary arrangments etc.,
complete.
a) Material
300x260x140mm 16 guage CRCA box
finished of item(as per 14.1.2)
Sundries as rounding off
Rate per Each
Supply and fixing of 300mm x 180mm x
140mm No.16 gauge CRCA sheet box
with hinged door and locking
arrangements and din channel for
fixing 2Nos MCBs duly powder coated
with matching colour of poles including
fixing with necessary arrangments etc.,
complete.
a) Material
300x180x140mm 16 guage CRCA sheet
box as per 14.1.2
Sundries as rounding off
Rate per Each
Supply and fixing of 1 No.10A SP MCB
in existing M.S. box with Din channel,
4way 63A connector including cost &
conveyance of all materials and labour
charges etc., complete.
a) Material
10A SP MCB
4Way connector.
b) Labour charges
Skilled Electrician
Rate per Each
Note : Labour is Considered for 15
jobs / day

each
Job

12
1

day
day

0.5
4

sqm

0.35

sqm

0.29

each
each

1
1

day

0.066

261

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

13.5.4

Bldngs_Elec14
Bldngs_Elec14-1

14

Supply and fixing of 2 Nos 10A SP


MCBs in existing M.S box with Din
channel, 4way 63A connector including
cost & conveyance of all materials and
labour charges etc., complete.
a) Material
10A SP MCB
4Way connector.
b) Labour charges
Skilled Electrician
Sundries such as screws, tape
Rate per Each
CONTROL PANEL AND METERING
EQUIPMENT

each
each

2
1

day

0.066

kg

1.56

14.1
14.1.1

1)

14.1.2

CONTROL PANEL
Supply, Transportation, fabrication and
erection of following guage CRCA sheet
steel enclosure for power control
cubicle panel / boxes etc., including
cutting, bending drilling, welding and
reveting etc., complete with cleaning
with 7 tank process and painting with
powder coating including cost and
conveyance of all materials and labour
charges.
14 SWG CRCA sheet steel enclosure
a) Material
14 SWG (2mm) CRCA sheet - 1 sft (Wt
of 8 x 4 feet sheet, 50Kg)
Transportation charges on Material
cost
Fabrication including cutting, bending,
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank
process
Painting with powder coating.
Erection charges
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
16 SWG CRCA sheet steel enclosure
a) Material
16 SWG (2mm) CRCA sheet - 1sft (Wt
of 8 x 4 feet sheet, 39Kg)
Transportation charges
Fabrication including cutting, bending,
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank
process
Painting with powder coating.
Erection charges

2%
30%

40%
40%
30%

kg

1.218
2%
30%

40%
40%
30%
262

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

14.1.3

Bldngs_Elec14-2

14.2
14.2.1

14.2.2

14.2.3

Sundires such as hardware etc.,


Rate per sft
Rate per sqm
18 SWG CRCA sheet steel enclosure
a) Material
18 SWG (2mm) CRCA sheet - 1 sft (Wt
of 8 x 4 feet sheet, 30Kg)
Transportation charges
Fabrication including cutting, bending,
drilling and Dust proof arrnagments
etc.,
Cleaning of cubicals in seven tank
process
Painting with powder coating.
Erection charges
Sundires such as hardware etc.,
Rate per sft
Rate per sqm
METERING EQUIPMENT
Supply and erection of 0-500V volt
meter of size 96x96mm on exisiting
box / panel board including
connections etc., complete.
a) Material
0-500 Voltmeter Analog / Degital
inclusive of all Taxes.
b) Labour charges for fixing &
Connections
Skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and erection of 0-100 / 200 /
400 / 600 /1000 - 5A CT Ammeter of
size 96x96mm on existing box / panel
board including connections etc.,
complete.
a) Material
96 x 96mm size Ammeter Analog /
Degital inclusive of all Taxes
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Supply and erection of frequency
meter of size 96x96mm on existing
box / panel board including
connections etc., complete.
a) Material
Frequency meter Analog / Degital
inclusive of all Taxes.

kg

0.937
2%
30%

40%
40%
30%

each

day

0.2

each

day

0.2

each

263

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

14.2.4

14.2.5

14.2.6

14.2.7

b) Labour charges for fixing and


connections.
Skilled Electrician
Rate per Each
Supply and erection of power factor
meter, 3 phase, 4 wire balanced or
unbalanced load 5A, 415V of size
96x96mm on existing box / panel
board including connections etc.,
complete.
a) Material
Power Factor meter Analog / Degital
inclusive of all Taxes.
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Supply and erection of L.T. 3phase
multifunction energy meter with 3
lines LCD display of size 96x96mm for
measuring all the parameters (voltage
/ Current / Power / frequency / power
factor / KW / KWH / KVAR/ KVARH) on
existing box panel board including
connections etc., complete.
a) Material
L.T. 3 Ph. Multifunction energy meter
Analog / Degital inclusive of all Taxes.
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and erection of selector switch
for voltmeter / Ammeter on the
existing box / panel including
connections etc., complete.
a) Material
Selector switch for Ammeter /
Voltmeter.
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Note : Labour is Considered for 5 jobs
/ day
Supply and erection of LED indicator
lamps on the existing box / panel
board.
a) Material
LED indicator lamp Analog
b) Labour charges for fixing and
connections.

day

0.2

each

day

0.2

each

day

0.33

each

day

0.2

each

264

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

14.2.8

14.2.9

14.2.10

Skilled Electrician
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and erection of LT current
transformer with bar primary 100/5A
to 1000 / 5A ratio in the existing box /
panel including connections etc.,
complete.
a) Material
L.T. C.T with bar primary 100 / 5A to
1000 / 5A
b) Labour charges for fixing and
connections.
Skilled Electrician
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and fixing of single phase
energy Meter,240V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
cost of single phase energy meter
b) Labour charges for fixing and
connections.
Skilled Electrician
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day
Supply and fixing of three phase
energy Meter,415V AC,50 HZ as per
IS13010 with 2.5-5 /5-10/10-20 Amps
range with 200% over load capacity
complete with connections etc.,
complete on the existing board.
a) Material
Cost of three phase energy meter
b) Labour charges for fixing and
connections.
Skilled Electrician
sunderies
Rate per Each
Note : Labour is Considered for 3 jobs
/ day

Bldngs_Elec15
Bldngs_Elec15-1

day

0.1

each

day

0.1

each

day

0.33

each

day

0.33

15
15.3

CABLES / CABLE GLANDS / LUGS


CABLE GLANDS

265

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.3.1

15.3.2

15.3.3

15.3.4

Supply and Fixing of heavy duty flange


type brass cable glands for 2 to 4 core,
2.5 Sq.mm to 6 Sq.mm PVC armoured
cable with brass washers complete.
a) Material
Brass cable gland for 2-4 core, 2.5
Sqmm to 6 Sq.mm armoured cable
b) Labour charges for fixing glands.
Semi skilled Electrician
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 2 to 4 core,
10 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland for 2-4 core, 10
Sqmm armoured cable
b) Labour charges for fixing glands.
Semi skilled Electrician
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 4 core, 16
Sq.mm / 3.5 core 25Sq.mm PVC
armoured cable with brass washers
complete.
a) Material
Brass cable gland suitabtle for 4core
16 Sq.mm / 3.5 core 25 Sq.mm
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Sundireis and Rounding off
Rate per Each
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 35
Sq.mm / 3.0 core 50Sq.mm PVC
armoured cable with brass washers
complete.
a) Material
Brass cable gland suitabtle for 3.5core
35 Sq.mm / 3 core 50 Sq.mm
armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Sundireis and Rounding off
Rate per Each

each

day

0.066

each

day

0.066

each

day

0.066

each

day

0.066

266

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.3.5

15.3.6

15.3.7

15.3.8

Note : Labour is Considered for 15


jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 50
Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
50 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 70
Sq.mm PVC armoured cable with brass
washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
70Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core, 95
Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
95 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
120 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
120 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper

each

day

0.066

each

day
day

0.066
0.066

each

day
day

0.066
0.066

each

day
day

0.066
0.066
267

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.3.9

15.3.10

15.3.11

15.3.12

Sundireis and Rounding off


Rate per Each
Note : Labour is Considered for 15
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
150 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
150 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
185 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
185 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
240 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
240 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundireis and Rounding off
Rate per Each
Note : Labour is Considered for 12
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
300 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
300 Sq.mm armoured cable

each

day
day

0.083
0.083

each

day
day

0.083
0.083

each

day
day

0.083
0.083

each

268

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.3.13

Bldngs_Elec15-2

b) Labour charges for fixing glands.


Skilled Electrician
Helper
Sundries, such as insulated tape.
Rate per Each
Note : Labour is Considered for 10
jobs / day
Supply and Fixing of heavy duty flange
type brass cable glands for 3.5 core,
400 Sq.mm PVC armoured cable with
brass washers complete.
a) Material
Brass cable gland suitabtle for 3.5core
400 Sq.mm armoured cable
b) Labour charges for fixing glands.
Skilled Electrician
Helper
Sundries, such as insulated tape.
Rate per Each
Note : Labour is Considered for 10
jobs / day

day
day

0.1
0.1

each

day
day

0.1
0.1

each

day
day

0.01
0.01

each

day
day

0.01
0.01

15.4
15.4.1

15.4.2

CABLE LUGS:
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable upto 16 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 16 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 25 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 25 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day

269

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.3

15.4.4

15.4.5

15.4.6

Supply and fixing of crimping type


copper lugs confirming to I.S
specifications for cable of 35 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 35 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 50 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 50 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 70Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs upto 70 Sq.mm.
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 95 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 95 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each

each

day
day

0.013
0.013

each

day
day

0.013
0.013

each

day
day

0.013
0.013

each

day
day

0.016
0.016

270

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.7

15.4.8

15.4.9

15.4.11

Note : Labour is Considered for 60


jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 120 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 120 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 150 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 150 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 185 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 185 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 30
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 240 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 240 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper

each

day
day

0.02
0.02

each

day
day

0.033
0.033

each

day
day

0.033
0.033

each

day
day

0.04
0.04
271

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.12

15.4.13

15.4.14

15.4.15

Sundries such as bolts and nuts.


Rate per Each
Note : Labour is Considered for 25
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 300 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 300 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20
jobs / day
Supply and fixing of crimping type
copper lugs confirming to I.S
specifications for cable of 400 Sq.mm
including nuts and bolts with
connections.
a) Material
Copper Lugs up to 400 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16
jobs / day
Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cables upto 16
Sq.mm including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 16 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 25 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 25 sqmm

each

day
day

0.05
0.05

each

day
day

0.062
0.062

each

day
day

0.01
0.01

each

1
272

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.16

15.4.17

15.4.18

b) Labour charges for crimping


Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 100
jobs / day
Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 35 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 35 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
Supply and fixing of crimping type
Aluminium lugs confirming to I.S
specifications for cable of 50 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 50 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 70 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 70 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 75
jobs / day

day
day

0.01
0.01

each

day
day

0.013
0.013

each

day
day

0.013
0.013

each

day
day

0.013
0.013

273

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.19

15.4.20

15.4.21

15.4.22

Supply and fixing of crimping type


aluminium lugs confirming to I.S
specifications for cable of 95 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 95 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 60
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 120 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 120 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 50
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 150 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 150 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 185 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 185 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.

each

day
day

0.016
0.016

each

day
day

0.02
0.02

each

day
day

0.04
0.04

each

day
day

0.04
0.04

274

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.4.24

15.4.25

15.4.26

Bldngs_Elec15-3

15.5

Rate per Each


Note : Labour is Considered for 25
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 240 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 240 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 25
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 300 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 300 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 20
jobs / day
Supply and fixing of crimping type
aluminium lugs confirming to I.S
specifications for cable of 400 Sq.mm
including nuts and bolts with
connections.
a) Material
Aluminium Lugs up to 400 sqmm
b) Labour charges for crimping
Semi Skilled Electrician
Helper
Sundries such as bolts and nuts.
Rate per Each
Note : Labour is Considered for 16
jobs / day
CABLE JOINTS

each

day
day

0.04
0.04

each

day
day

0.05
0.05

each

day
day

0.062
0.062

275

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.5.1

Providing and erecting epoxy staight


through joint out door / indoor for L.T,
PVC Armoured cable 1100V grade
complete with ferrule, bushings,
accessories and suitable clamps duly
erected and connected to the supply
for the following multi core cables
including cost and conveyance of
materials and all labour charges etc.,
complete.

(a)

2.5 Sq.mm to 16 Sq.mm


a) Material
Epoxy straight joint 2.5 to 16 Sq.mm
with accessories
b) Labour charges
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
25 Sq.mm to 50 Sq.mm
a) Material
Epoxy straight joint 25 to 50 Sq.mm
with accessories
b) Labour charges
Semi Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
70 Sq.mm to 95 Sq.mm
a) Material
Epoxy straight joint 70 to 95 Sq.mm
with accessories
b) Labour charges
Semi Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is Considered for 2 jobs
/ day
120 Sq.mm to 185 Sq.mm
a) Material
Epoxy straight joint 120 to 185 Sq.mm
with accessories
b) Labour charges
Semi Skilled Electrician
Helper
Sundries
Rate per Each

(b)

(c )

(d)

each

day
day

0.5
0.5

each

day
day

0.5
0.5

each

day
day

0.5
0.5

each

day
day

0.5
0.5

276

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

(e)

(f)

(g)

Bldngs_Elec15-4

15.6

15.6.1

Note : Labour is Considered for 2 jobs


/ day
240 Sq.mm
a) Material
Epoxy straight joint 240 Sq.mm with
accessories
b) Labour charges
Skilled Electrician
Helper
Sundries
Rate per Each
300 Sq.mm
a) Material
Epoxy straight joint 300 Sq.mm with
accessories
b) Labour charges
Skilled Electrician
Helper
Sundries
Rate per Each
400 Sq.mm
a) Material
Epoxy straight joint 400 Sq.mm with
accessories
b) Labour charges
Skilled Electrician
Helper
Sundries
Rate per Each
Labour Charges Laying of Cable
including cost of all Materials other
than Cable
Earth work excavation of Trench in
hard ground soil, laying of U.G cables
upto 50 Sq,mm on sand cushion
covering the cable with bricks and back
filling of Trench duly providing route
indicator embedded in C.C including
cost and conveyance of materials and
labour charges etc., complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m
Cost of bricks (Civil SSR)
Cost of sand (Civil SSR)
Cement (Civil SSR)
Cost of cable route indicator
Transportation charges of bricks and
sand
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand
and back filling the excavated soil.
Skilled Electrician

each

day
day

1
1

each

day
day

1
1

each

day
day

1
1

cum
1000 Nos

27
0.92

cum
Kg
each
LS

6
25
12

each

2.5

day

1
277

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.6.2

15.6.3

Helper
Man Mazdoor for concreting and
embedding of cable way indicators
Sundires and Rounding off
Rate per 100mts
Note : Labour Charges Considered for
100 Mts / day
Earth work excavation of Trench in
hard ground soil, laying of U.G cables
from 70 sqmm to 400 Sq,mm on sand
cushion covering the cable with bricks
and back filling of Trench duly
providing route indicator embedded in
C.C including cost and conveyance of
materials and labour charges etc.,
complete.
a) Material
Excavation of earth 100 x 0.3 X 0.9 m
Cost of bricks (Civil SSR)

day
day

2
2

cum
1000 Nos

27
0.92

Cost of sand (Civil SSR)


cum
6
Cement (Civil SSR)
Kg
25
Cost of cable route indicator
each
12
Transportation charges of bricks and
LS
sand
b) Labour charges for laying cable.
Man Mazdoor for spreading the sand
each
2.5
and back filling the excavated soil.
day
1.6
Skilled Electrician
day
3.3
Helper
Man Mazdoor for concreting and
day
2
embedding of cable way indicators
Sundires and Rounding off
Rate per 60mts
Note :1. Labour Charges Considered for 60 Mts / day
2. Cables shall be at a depth of not less than 600 mm in a trench. Sand filling
shall be provided at the bottom of trench before laying the cable. Bricks shall
be provided on either side of the laid cable. Sand filling shall be done to
cover the cable laid. bricks shall be provided onthe Top. earth filling shall be
done. cable identificaiton tags to be provided at every 8 mtrs length of cable
laid.
3. Only the cost of cables may be added for finished item.
Labour charges for run of U.G cable on
wall / existing pipe with necessary
fixing arrangments such as saddles,
clamps,wooden separators etc., (as
directed by departmental official) with
No.10 SWG G.I wire for eath
connections for the cables.
a) Material
Wooden separators
saddles of required size
12mm screws
No.10 SWG GI wire

each
100 nos
100 nos
kg

200
2
4
7
278

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

15.6.4

Bldngs_Elec16

16

Bldngs_Elec17

17

b) Labour charges
Skilled Electrician
Helper
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered for
100 Mts / day
Supply and laying of one number
double walled corrugated (DWC) HDPE
pipe of following sizes having
corrugation on the outer wall and plain
surface inner wall confirming to IS :
14930 Part - I and II complete with
necessary HDPE fittings for protection
of 1.1 KV grade U.G cable directly in
ground at a depth of 60Cms including
excavation and refilling the trench as
required.
a) 50mm outer dia nominal size
b) 78mm outer dia nominal size
c) 90mm outer dia nominal size
d) 120mm outer dia nominal size
a) Material
Double wall corrugated HDPE pipe
confirming to IS : 14930.
Snap-fit coupler
Excavation of earth work & Refilling for
a size of 1.0x0.3x0.6Mtr.
Rate per Metre

day
day

1
4

RM

each
cum

1
0.18

TEMPORARY ILLUMINATION
data shown seperately at the end.

Bldngs_Elec17-1
A

GENERATORS AND TRANSFORMERS


Supply, Transportation, erection and commissioning of following specifications
of D.G. Set consists of Engine and alternator which are directly coupled by
means of flexible cooping with guard and mounted on a common base plate of
Robust construction and complete with control panel having IP 53 protection.
Alternator : KIRLOSKAR / STAMFORD / CROMPTON on D.G.S & D approved
make. The alternator of the output rating shall be 1 Ph / 3 Ph, 240V / 415V, 50
Hz., A.C., 0.8 P.f lagging at 1500 RPM. The alternator is self excited, self
regulated, screen protected drip proof and shall confirm to IS : 13364 of 1992
with regulation of + 5% from no load to full load. degree of protections shall be
IP 21.
Diesel Engine : KIRLOSKAR / GREAVES / CUMMINS / ASHOK LEY LAND or
DGS&D approved. Diesel Engine start, developing suitable BHP output at 1500
RPM with class A2 Governing so as to enable the alternator to give required
KVA continuous output at 0.8 P.F. lagging at NTP conditions. the Diesel Engine
will be capable of providing 10% O/L for 1 Hr for every 11 HRs of continuous
running at full load. The Diesel Engine shall confirm to IS 10001 or IS 10002.
Control Panel : Control Panel shall be fabricated with 16 SWG CRCA sheet steel.
The control panel shall be totally enclosed, dust and vermin proof, floor
mounted / wall mounted type and shall be comprising the following
instruments and component.
1. Voltmeter with selector switch
2. Ammeter with Selector
279

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.1
17.1.3
(a)

17.1.3
(b)

Switch
3. MCCB / MCB incomer of suitable rating
4. P.F. Meter and frequency
Meter
5. Indication Lamp Set
6. KWH Meter of required
rating
7. Instrument and control fuses.
ACOUSTIC ENCLOSURE
Supply & providing & installation of acoustic enclosure (sound proof enclosure
cum container) for the above Genset with the following specification.
Construction : The panel of acoustic enclosure shall consists of self supporting
frame work put together with help of fasteners, which is for assembling and
dismantling. The vertical and Horizontal structure 8is to be fabricated with
14/16 SWG CRCA sheet and should be fixed on heavy duty MS Channel which
will form the base frame of the acoustic enclosure. the paneling of ht container
is to be carried out using 18 SWG CRCA sheets. the enclosure should be self
supporting type and does not require any grouting or separate foundation. But
it should be the independent of the DG set and to placed around the DG set.
The frame work shall also have provision for fitting hinged / sliding doors to
open either sides of the enclosure.
Generating Sets
Supply, Transportation, erection of 3
Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz.,
D.G.Set.
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Ph Air-Cooled 20KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
20KVA Air Cooled, 3Ph, 451V, 50Hz.,
D.G.Set
cost of acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each

each

1
10%
2%

each

each

1
10%
5%
2%

280

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.1.3 (c)

17.1.3
(d)

17.1.3
(e)

17.1.3 (f)

Supply, Transportation, erection of 3


Ph Air-Cooled 25KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
3Ph, 415V, 50Hz., 25 KVA Air Cooled
D.G.Set
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Ph Air-Cooled 25KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
3Ph, 415V, 50Hz., 25 KVA Air Cooled
D.G.Set
Cost of Acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Ph Air-Cooled 40KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., as per specifications mentioned
above.
a) Material
40KVA, 3Ph,415V,D.G.Set
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2% on unit cost
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Ph Air-Cooled 40KVA, D.G.Set with
alternator, Diesel Engine, Control panel
etc., with acoustic enclosure as per
specifications mentioned above.
a) Material
40KVA, 3Ph,415V,D.G.Set
Cost of Acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.

each

1
10%
2%

each

each

1
10%
5%
2%

each

1
10%
2%

each
each

1
1
10%

281

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.1.3
(g)

17.1.3
(h)

17.1.3 (i)

17.1.3 (j)

cost
of acoustic enclosure
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water cooled / Air Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., as per
specifications mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water Cooled / Air-Cooled
63KVA, D.G.Set with alternator, Diesel
Engine, Control panel etc., with
acoustic enclosure as per specifications
mentioned above.
a) Material
63KVA, 3Ph, 415V, D.G Set
Cost of Acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation , erection of 3
Phase Water cooled 125 KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., as per specifications
mentioned above.
a) Material
125KVA, Water Cooled, 3Ph, 415V
D.G.Set.
Erection and commissioning charges @
10% of the cost of the set.
Transportation at 2%
Sundires and Rounding off
Rate per Each
Supply, Transportation, erection of 3
Phase Water-Cooled 125KVA, D.G.Set
with alternator, Diesel Engine, Control
panel etc., with acoustic enclosure as
per specifications mentioned above.

5%
2%

each

1
10%
2%

each
each

1
1
10%
5%
2%

each

1
10%
2%

a) Material
282

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Bldngs_Elec17-2

17.2
17.2.1

(a)

125KVA, Water Cooled, 3Ph, 415V


D.G.Set.
Cost of Acoustic enclosure
Erection and commissioning charges :
the
cost of the DG set.
cost
of acoustic enclosure
Transportation at 2%
Sundires and Rounding off
Rate per Each
Transformers

each

each

1
10%
5%
2%

Supply, transportation, erection and


commissioning
of
following
specifications of 3 Phase, 50 Hz., Oil
immersed and naturally cooled, out
door / Indoor type copper wound
transformer connected delta on H.V.
side and star on L.V side with
additional neutral brought out on load
side, rating 11000 / 433 volts with HV
tapping + 2.5% cotinuously rated for
full load and temparature rise not
exceeding 450 C by thermometer in oil
and 500 C by the resistance of the
winding after continuous run on full
load rating complete with the
following standard mounting.
63 KVA, 3Ph, aluminium wound
Tansformer, CSP type (Core Self
Protection)
a) Material
each

(b)

63KVA Aluminium wound CSP type


Transformer
Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
100 KVA, 3Ph, aluminium wound
Tansformer, CSP type
a) Material

2%
10%

each

(c )

100 KVA Aluminium wound CSP type


Transformer
Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
100 KVA, 3Ph,
copper wound
Tansformer

2%
10%

283

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

a) Material
each

(d )

100 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
160 KVA, 3Ph,
copper wound
Tansformer
a) Material

2%
10%

each

(e)

160 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
200 KVA, 3Ph,
copper wound
Tansformer
a) Material

10%

200 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
250 KVA, 3Ph,
copper wound
Tansformer
a) Material

10%

250 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
315 KVA, 3Ph,
copper wound
Tansformer
a) Material

1
2%
10%

each

(h)

1
2%

each

(g)

1
2%

each

(f)

315 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
500 KVA, 3Ph,
copper wound
Tansformer
a) Material

1
2%
10%

each

500 KVA Copper wound Transformer


284

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

(i)

2%

Transportation including loading and


unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
630 KVA, 3Ph,
copper wound
Tansformer
a) Material

10%

each

(j)

630 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
1000 KVA, 3Ph,
copper wound
Tansformer
a) Material

2%
10%

each

Bldngs_Elec17-3

17.3
17.3.7

1000 KVA Copper wound Transformer


Transportation including loading and
unloading
(b) Labour charges for erection and
commissioning.
Rate per Each
CIRCUIT BREAKER
Supply and errecting Air circuit Breaker
(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release
suitable for
operational voltage 415V, 630A,
erected in position on provided panel
boards in an approved manner with
necessary material complete
a) Material
630A, 415V Fixed type 3 pole ACB
Shunt release
U/V release
Earth fault release
Transportation @ 2% on Unit Cost
b) Labour charges for installation @
5%
Rate per Each

1
2%
10%

each
each
each
each

1
1
1
1
2%
5%

285

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.3.8

17.3.9

Bldngs_Elec17-4

17.4
17.4.1

Supply and errecting Air circuit Breaker


(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release
suitable for
operational voltage 415V, 800A,
erected in position on provided panel
boards in an approved manner with
necessary material complete.
a) Material
800A, 415V Fixed type 3 pole ACB
Shunt release Coil.
U/V release Coil.
Earth fault release
Transportation @ 2% on Unit Cost
b) Labour charges for installation @
5%
Rate per Each
Supply and errecting Air circuit Breaker
(ACB) manually operated non drawout
type with 6 way secondary isolating
contacts necessary micro switches for
over load and short circuit indicator,
door interlocking, shunt release, under
voltage release as well as 10%-20%
earth fault release
suitable for
operational voltage 415V, 1000A,
erected in position on provided panel
boards in an approved manner with
necessary material complete.
a) Material
1000A, 415V, Fixed type 3 pole ACB.
Shunt release
U/V release
Earth fault release
Transportation @ 2% on Unit Cost
b) Labour charges for installation @
5%
Rate per Each
SUB - STATION EQUIPMENT
Supply and fixing printed instructions
chart both in English and Telugu and
duly framed with front glass for
treatment of person suffering from
Electric shock.
a) Material
Printed insturction chart both of size
0.9 x 0.6 M in English and Telugu.

each
each
each
each

1
1
1
1
2%
5%

each
each
each
each

1
1
1
1
2%
5%

each

286

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.2

17.4.3

17.4.4

17.4.5

17.4.6

Towards making wooden frame with


front glass including cost of material
and labour on unti cost of Item 1.
Rate per Each
Supply of pair of rubber hand gloves
suitable for working 11/22 KV supply.
a) Material
Rubber hand gloves suitable for
working on 11/22 KV supply
Rate per Each Pair
Supply of 11KV, ISI, approved rubber
mat of thickness, required length and
breadth.
a) Material
6mm thick, ISI make Rubber mat
suitable for working on 11/22 KV
Sundries and rounding off
Rate per sqmt
Supply of standard 18"x12"x8" first aid
box with all standard contents.
a) Material
18" x 12" x 8" size First Aid box.
Set of Cotton, band aid cloth Antiseptic
cream etc.,
Rate per Each
Supply of G.I sheet bucket of round
bottom of 13 Ltrs. Capacity with
printed letters and filled with sand and
arranged to existing stand or hook.
a) Material
13 Ltrs. Capacity G.I. bucket.
Painting with 2 coats of red color
enamell paint on out side.
Cost of sand
Sundires for printing letter etc.,
Rate per Each
Supply of Tranformer oil tested and
having good resistance to high electric
stress di-electric strength 50KV, low
viscocity, low pour point, high flash
point and excellent thermal properties
for efficient heat transfer and cooling
as per IS 335-1972.
a) Material
Transformer Oil having
strength of 50 KV
Sundries and rounding off
Rate per Lt

Dielectric

150%

each

each

each
set

1
1

each
sqm

1
0.5

cum

0.13

287

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.7

17.4.8

17.4.9

Providing floor mounting stand for


keeping 4Nos of bucket 1500mm
length, 900mm height made out of
40x40x6mm angle iron welded with 4
hooks and duly painted with one coat
of red lead and two coats of enamel
paint.
a) Material
1500mm length, 900mm height Floor
mounting stand fabricated with
40x40x6mm angle iron welded with 4
Nos Hooks. (1Mtr = 3.5Kg) (5x3.5Kgs =
17.5Kgs)
Fabrication cost of hooks including
painting (on cost of material)
Sundries and rounding off
Rate per Each
Supply and erecting ABC Powder
(stored pressure type) fire extinguisher
5kg conforming to IS 2171-85 with
necessary clamps made from 50x6mm
MS flat with nuts & bolts grouted in
wall complete.
a) Material
ABC Powder Stored pressure type fire
extengensher of 5 Kg capacity .
50 x6mm M.S Apl. Clamps with bolt &
nut.
(b) Labour charges for erection.
Helper
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs
/ day
Supply and erecting ABC Powder
(stored pressure type) fire extinguisher
10kg conforming to IS 2171-85 with
necessary clamps made from 50x6mm
MS flat with nuts & bolts grouted in
wall complete.
a) Material
ABC Powder Stored pressure type fire
extengensher of 10 Kg capacity .
50 x6mm M.S Apl. Clamps with bolt &
nut.
(b) Labour charges for erection.
Helper
Sundires and Rounding off
Rate per Each
Note : Labour is considered for 5 jobs
/ day

kg

17.5

50%

each

each

day

0.2

each

each

day

0.2

288

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.10

17.4.11

Supply and erecting fencing of section


having size 2450 mm in height from
ground level and 1200mm width by
using angle iron size 50x50x6mm
erected in CC foundation 15x15x40cms
deep. The section of the frame shall
be fitted with flat iron supports of size
25x6mm on top, bottom and middle
and chain link jali of 8 SWG G.I to the
angle iron at every distance of 30 cms
by iron studs complete duly painted
with one coat of red oxide and two
coats of aluminium paint.
a) Material
50x50x6mm Angle Iron (1 Mt. = 4.37
Kg) 4.8 m Length
25x6mm M.S Flat (1 Mt. 1.18 Kg) 3.6 M
length
Chain link Mesh (Civil SSR)
Fabrication of Frame with angles, Flat
and chain link mesh
C.C.Work M 15 using 20 mm metal (15
x 15 x 40) x 2 As per Civil SSR
Painting with one coat of red oxide and
two coat of alluminium paint.
Sundires and Rounding off
Rate per Each
Supply and erecting 50x50x6mm angle
iron as corner support to be fixed
away from the fence support fixed at
the middle of the fencing frame and
the other side in CC foundation of
15x15x40 cms complete duly painted
with one coat of red oxide and two
coats of aluminium paint.
a) Material
50x50x6mm Angle. (1 mt. 4.37 Kg) 2m
Length
C.C.Work M 15 using 20 mm metal (15
x 15 x 40) x 2 As per Civil SSR
Painting with one coat of red oxide and
two coats of Aluminium paint (on cost
of Item 1)
Sundires and Rounding off
Rate per Each

kg

20.97

kg

4.25

sqm
kg

2.4
25.22

cum

0.018

sqm

5.88

kg

8.74

cum

0.018
10%

289

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.4.12

Bldngs_Elec17-5

Supply and erecting double leaf hinged


door each 150cms width x 185cms
height using 38.1 mm dia B grade ISI
marked G.I pipe from all four sides
with necessary bends with cross
supports of angle iron 40 x 40 x 6mm
with the door leaf covered with chain
link mesh of No. 8 SWG G.I wire with
necessary flat iron covering all around
frame. The door shall have heavy
latches, and side channels of
100x50x5mm locking arrangement
with lock of
medium size with
duplicate keys, the fencing completely
erected with anti corrosive red oxide
paint and two coats of prescribed
enamel paint / silver paint.
The
channel iron of size 100x50mm x
2.5Mtr. length shall be provided and
erected at both sides of gate with C.C
work
a) Material
38.1mm dia
B Class G.I pipe.
(1.85 x 4 Nos + 1.5x 4Nos = 13.4 Mt or
say 14 Mtrs.)
( civil SSR)
25x6mm M.S. Flat (1.18 Kgs / Mt) 17
M length
1000x50mm Channle (1mt = 8.74 Kg) 5
M length
4 Nos x 2.38M Length, 40 x 40 x 6 mm
M.S. Angle Iron ( 1 Mtr = 3.5 Kg) 9.52
M length
Steel Aldrop with bolts and Nuts.
Chain link mesh of 8 SWg G.I (Civil SSR)
Medium size lock and Key
Fabrication charges including welding
etc., complete.
Painting Charges
b) Labour charges for erection
including cost of hinges on items 1-6.
Sundireis and Rounding off
Rate per Each

RM

14

kg

20.06

kg

43.7

kg

33.32

each
sqm
each
kg

1
5.55
1
118

sqm
5%

17.5
17.5.1
(a)

SUB-STATION MAINTENANCE
Filteration of transformer oil as per ISS
for removal of moisture, carbon slurry
etc. by means of circulating oil
through vaccum pump from heating
elements and filters to withstand the
dielectric strength of the oil above
40KV beyond one minute tested in oil
testing Kit.
On site.
a) Material
Labour charges for filterations at site

Data
shall be
arrived
based on
observed
Data

290

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.5.1
(b)

17.5.3

17.5.4

Rate per Each


Filteration of transformer oil as per ISS
for removal of moisture, carbon slurry
etc. by means of circulating oil
through vaccum pump from heating
elements and filters to withstand the
dielectric strength of the oil above
40KV beyond one minute tested in oil
testing Kit.
At Factory.
a) Material
Labour charges for filterations at site
Rate per Each
Carryout
routine maintenance,
servicing and testing of 630A to 1000A
L.T.ACB by cleaning fixed contacts,
moving contacts and arcchutes
including servicing and putting the ACB
in perfect working condition after
detting all relay and ON, OFF
mechanism etc.
a) Material
Removing the existing ACB and
servicing and testing of 630A to 1000A
L.T.ACB.
Clearing of fixed contacts, moving
contacts and arcchutes
Refix the ACB inposition and testing
and commissioning charges.
b) Labour charges for entire job
Skilled Electrician
day
Semi Skilled Electrician
day
Helper
day
Sundries and Rounding
Rate per Each
Note :Job requires 3 days. Keeping this labour
arrived.
Carryout routine maintenance and
servicing of LT.Cubical panel board
having approximately 15 to 22 Nos of
switches by cleaning with power
blower and servicing the contacts,
tightning the connection of incoming
and outgoing cables, and clicking the
operating mechanism for smooth
functioning of switches and putting
them in smooth working condition.

Data
shall be
arrived
based on
observed
Data

3
3
6

a) Material
Removing all the doors of switches,
busbar chamber and back doors.
Clearing by using power blower.
Tightening all the terminations and
cleaning and servicing the contacts of
switches.
291

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for entire job


Skilled Electrician
day
Semi Skilled Electrician
day
Helper
day
Sundries and Rounding
Rate per Each
Note :Job requires 3 days. Keeping this labour
arrived.
Bldngs_Elec17-6

2
1
2

17.6
17.6.1

17.6.3

17.6.5

PROTECTIVE GEAR
Supply and erecting approved make
11KV, 5KA metal oxide
lightning
arrestors suitable for 11 KV supply with
necessary materials on existing cross
arm.
a) Material
Cost of 11 KV 5KA metal oxide lighting
arrester.
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 3 jobs /
day
Supply and erecting porcelain disc type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain disc type insulator
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
Supply and erecting porcelain pin type
insulator suitable for 11KV line with
suitable hardware on existing cross
arms.
a) Material
Cost of porcelain pin type insulator
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day

each

day
day

0.33
0.33

each

day
day

0.125
0.25

each

day
day

0.125
0.25

292

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.6.6

17.6.8

17.6.10

Supply and erecting porcelain post


type insulator suitable for 11KV line
with suitable hardware on existing
cross arms.
a) Material
Cost of porcelain post type insulator
suitable for 11 KV
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries
Rate per Each
Note : Labour is considered for 8 jobs /
day
Supply and fixing of lightning
protective system conforming to IS :
2309 with all standard accessories such
as metal globe finials on the top of the
builiding with 25.4 mm dia 3.0 mtrs.
Length of 'B' class G.I pipe etc.,
complete without down conductors
and earthing
a) Material
Lightning protective system with all
standard accessories such as metallic
globe, finials etc.,
25.4 mm B Class GI Pipe, ISI Mark
b) Labour charges
i) for fixing the System on G.I pipe.
ii) for fixing on top of the building with
C.C work / Clamping arrangement.
Skilled Electrician
Helper
Sundries and Rounding off
Rate per Each
Supply and erecting approved made
11KV, 400A
A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11KV, 400A A.B switch wth all
standard accessories.
b) Labour charges for erection.
Skilled Electrician
Semi Skilled Electrician
Helper
Sundries and Rounding off
Rate per Each

each

day
day

0.125
0.25

each

day
day

1
1

each

day
day
day

1
1
1

293

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.6.11

17.6.12

17.6.13

17.6.14

Supply and erecting approved made


11KV, 200A
A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11KV, 200A A.B switch wth all
standard accessories.
b) Labour charges for erection.
Skilled Electrician
Semi Skilled Electrician
Helper
Sundries and Rounding off
Rate per Each
Supply and erecting approved made
11KV, 200A (Tilting) A.B switch with all
standard accessories etc., complelte
with cost and conveyance of all
materials and labour charges.
a) Material
Cost of 11kV, 200A (Tilting) A.B switch
wth all standard accessories.
b) Labour charges for erection.
Skilled Electrician
Semi Skilled Electrician
Helper
Sundries and Rounding off
Rate per Each
Supply and erecting 11KV, H.G (Horn
Gap) fuse set including all standard
accessories etc., complete with cost
and conveyance of all materials and
labour charges.
a) Material
Cost of 11KV, H.G. fuse set wth all
standard accessories.
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries and Rounding off
Rate per Each
Supply and erecting of bank of
metalised polypropylene condensors
with the standard capacities of
2,3,5,7,10,12.5 and 15 KVAR units for
PF correction for operation on 3 phase
50 Cycles 400 / 440V (+10%) with
externally discharging resistances,
earthig terminals etc., complete.
a) Material
Cost of MPP capacitor operation on 3
Ph. 415V.
b) Labour charges for erection.

each

day
day
day

1
1
1

each

day
day
day

1
1
1

each

day
day

1
1

Kvar

294

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

17.6.15

Skilled Electrician
Helper
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day
Supply and erecting of bank of
mixdielectric condensors with the
standard capacities of 2,3,5,7,10,12.5
and 15 KVAR units for PF correction for
operation on 3 phase 50 cycles
400/440V (+10%) with externally
discharging
resistances,
earthing
terminals etc., complete.
a) Material
Cost of of mixed Dielectric capacitor
operation on 3 Ph. 415V.
b) Labour charges for erection.
Skilled Electrician
Helper
Sundries and Rounding off
Rate per Kvar
Note : Labour considered for 25 jobs /
day

Bldngs_Elec18

0.04
0.08

Kvar

day
day

0.04
0.08

kg

0.3

18

18.1.1
Bldngs_Elec18-1

day
day

Repairs to Motors and Rewinding


Datas of 11.6.1 to 11.6.4 are hold good
and be adopted.
Rewinding the motor of the table /
pedestal / cabin fan of all types, and
makes and overhauling including minor
repairs, testing for the original speed
and consumption with guarantee for
one year including tansporation from
site and back.
a) Material
Copper enamelled winding wire of fine
quality.
Labour charges towards removing
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape,
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire
Rate per Each

50%

100%

40%

kg

0.3

295

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.2

18.1.3

18.1.4

Rewinding the motor of the ceiling fan


of 1200mm / 1400mm of all types and
makes and over hauling including
minor repairs and testing for original
speed and consumption
a) Material
35 / 36 Copper enamelled winding wire
of fine quality.
Labour charges towards removing
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape,
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire
Rate per Each
Rewinding the motor of the exhaust
fan of light duty 225/300mm of
900/1400 RPM of all types and makes
and over hauling including minor
repairs and testing for original speed
and consumption
a) Material
23 / 24 / 28 Copper enamelled winding
wire of fine quality.
Labour charges towards removing
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the
coils complete with connections etc.,
complete.(on cost of winding wire)
Sundries such as sleeves cotton tape,
minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire
Rate per Each
Rewinding the motor of the exhaust
fan of heavy duty 375mm of 900/1400
RPM of all types and makes and over
hauling including minor repairs and
testing for original speed and
consumption
a) Material
23 / 24 / 28 Copper enamelled winding
wire of fine quality.
Labour charges towards removing
unserviceable winding wire and
cleaning. (on cost of winding wire)
Labour charges towards rewinding the
coils complete with connections etc.,
complete.(on cost of winding wire)

kg

0.2
50%

100%

40%

kg

0.2

kg

0.05
50%

100%

40%

kg

0.05

kg

0.45
50%

100%

296

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.5

18.1.6

18.1.7

Sundries such as sleeves cotton tape,


minolex paper, solution etc., with
transportion charges.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor upto 1 HP
single phase upto 1400 RPM of all
types and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 2 HP single
phase 1400 RPM of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original
speed
and
no
load
consumption.
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 3 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality

40%

kg

0.45

kg

2.7
5%

12%

2%

kg

2.7

kg

3.2
5%

12%

2%

kg

3.2

kg

4.5

297

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.8

18.1.9

Labour charges towards removing of


old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 5 HP three
phase 1400 RPM of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original
speed
and
no
load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 7.5 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each

5%

12%

2%

kg

4.5

kg

5.7
5%

12%

2%

kg

5.7

kg

6.5
5%

12%

2%

kg

6.5

298

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.10

18.1.11

18.1.12

Rewinding of electric motor 10 HP


three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 12.50 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 15 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption .
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)

kg

10
5%

12%

2%

kg

10

kg

12
5%

12%

2%

kg

12

kg

15
5%

299

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.1.13

18.1.14

Bldngs_Elec18-2

Labour charges towards rewinding


copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of electric motor 20 HP
three phase 1400 RPM of all types
and makes with copper wire,
overhauling with minor repairs, testing
for the original speed and no load
consumption.
a) Material
Suitable guage copper winding wire
fine quality
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost towards old winding wire
Rate per Each
Rewinding of submersible motor upto
15 HP three phase of all types and
makes with copper wire, overhauling
with minor repairs, testing for the
original
speed
and
no
load
consumption .
a) Material
PVC insulated copper winding wire of
suitable guage.
Labour charges towards removing of
old unserviceable winding wire.(on
cost of winding wire)
Labour charges towards rewinding
copper
coils
complete
with
connections.(on cost of winding wire)
Sundries such as sleeves, cotton tape,
minolex paper solution etc., with
transportation.
Less cost for winding wire
Rate per Each

12%

2%

kg

15

kg

18
5%

12%

2%

kg

18

kg

18
10%

15%

5%

kg

18

18.2
Bearings

300

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

18.2.1

Replacing the existing bearing of


approved make for electric motor
single phase / 3 phase AC upto 1 HP of
all types with due alignment of the
shaft and tested.
a) Material
Ball Bearings suitable for 1 HP Motor
inclusive of taxes
Labour charges for removing the
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)

18.2.2

50%

each

1
50%

Transportation and Rounding off


Rate per Each
Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 5 to 7.5
HP of all types with due alignment of
the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP
Motor inclusive of taxes
Labour charges for removing the
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)

18.2.4

Transportation and Rounding off


Rate per Each
Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 2 to 3
HP of all types with due alignment of
the shaft and tested.
a) Material
Ball Bearings suitable for 2 to 3 HP
Motor inclusive of taxes
Labour charges for removing the
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)

18.2.3

each

each

1
50%

Transportation and Rounding off


Rate per Each
Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 10 to
12.5 HP
of all types with due
alignment of the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP
Motor inclusive of taxes

each

301

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

Labour charges for removing the


existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)

18.2.5

Transportation and Rounding off


Rate per Each
Replacing the existing bearing of
approved make for electric motor
single phase / 3 phase AC upto 15 to
20 HP of all types with due alignment
of the shaft and tested.
a) Material
Ball Bearings suitable for 5 to 7.5 HP
Motor inclusive of taxes
Labour charges for removing the
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)

18.2.6

18.2.7

18.2.8

50%

Transportation and Rounding off


Rate per Each
Replacing the ball bearing of table /
cabin / pedestal / ceiling / exhaust fan
complete with alignment of shaft and
tested.
a) Material
Ball Bearings suitable for table / cabin /
ceiling / Exhaust Fan inclusive of taxes
Labour charges for removing the
existing unserviceable bearing and
fixing the new ball bearing with special
T&P. (on cost of Ball Bearing)
Transportation and Rounding off
Rate per Each
Replacing the ball bearing of bush /
rubber / ring washers for fan mortar
complete with alignment of shaft and
tested.
a) Material
Cost of GM / Bush / Rubber / Ring
washer etc.,
Labour charges for removing the
existing unserviceable bush/ ring
washer and fixing the new with special
T&P.(on cost of material)
Rounding Off
Rate per Each
Replacing the existing capacitor of
table / cabin / pedestal / ceiling /
exhaust fan complete with wiring.
a) Material
Cost of 2.5 / 3.5 mfd condensor
suitable for ceiling / pedastal Exhaust
Fan

each

1
50%

each

1
50%

each

1
50%

each

302

STANDARD DATA BOOK -ELECTRICAL ITEMS FOR BUILDINGS

b) Labour charges for removing and


refixing
Semi Skilled Electrician
Rounding Off
Rate per Each
Note : Labour considered for 10 jobs /
day

day

0.1

303

STANDARD DATA-ELECTRICAL ITEMS BUS BARS

12
12.1
12.1.1

BUS BARS
Copper Bus Bars
Supply and fabrication and erection of following sizes of 4Nos of copper bus bars in the existing sheet steel enclosure with resin cast
insulator supports etc., complete including cost and conveyance of all materials all labour charges.

D.No.

Size of each bar


in mm

No.of 1
mtr
bars

Current
rating in
each bar

Weight /
mtr in Kg

a
b

20x3
20x6

4 Nos
4 Nos

220A
300A

0.529 Kg
1.072

25x3

4 Nos

270A

0.663

25x6

4 Nos

350A

1.34

30x6

4 Nos

400A

1.608

40x6

4 Nos

520A

2.144

50x6

4 Nos

630A

2.68

60x6

4 Nos

760A

3.216

75x6

4 Nos

970A

4.02

100x6

4 Nos

1380A

5.36

Rate per Kg

Cost of
copper
bars

Cost of
8Nos.
Resin cast
insulator.
@ Rs.35/Each

Labour charges for


fabrication and
fixing of insulators
providing with PVC
heat shrinkable
sleeves.

Total
Amount
mtr

Rounding
off

Note : Labour Charges @ 20 % on Copper cost is allowed

304

STANDARD DATA-ELECTRICAL ITEMS BUS BARS

12.2
12.2.1

Aluminum Bus
Bars
Supply and fabrication and erection of following sizes of 4Nos of aluminum bus bars in the existing sheet steel enclosure with resin
cast insulator supports etc., complete including cost and conveyance of all materials all labour charges.

D.No.

Size of each bar


in mm

No.of 1
mtr
bars

Current
rating in
each bar

Weight /
mtr in Kg

20x3

4 Nos

145A

0.161 Kg

20x6

4 Nos

195A

0.322

25x3

4 Nos

180A

0.201

25x6

4 Nos

230A

0.402

40x6

4 Nos

350A

0.644

50x6

4 Nos

425A

0.805

60x6

4 Nos

500A

0.966

75x6

4 Nos

680A

1.207

100x6

4 Nos

900A

1.61

Rate per Kg

Cost of
copper
bars

Cost of
8Nos.
Resin cast
insulator.
@ Rs.35/Each

Labour charges for


fabrication and
fixing of insulators
providing with PVC
heat shrinkable
sleeves.

Total
Amount
mtr

Rounding
off

Note : Labour charges are as per the rates allowed for Copper bus bar since, there is no difference in the requirement of Labour

305

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

DATA ANALYSIS FOR TEMPORARY ILLUMINATION

Data
No.

1
16
16.1

16.2

Mainten
ance
50% of
deprecia
tion

Interest
@ 12%
on
Capital
cost/days
in a year

Description

Capital Cost

Life in
days

Depreciation:
Capital cost
/Life in days

2
TEMPORARY ILLUMINATION
Hire
charges
for
Temporary
illumination, consisting of 6.2 strip
lights (navar patta) complete with
1000 Nos required wire leads duly
erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of 6.2 strip
lights (navar patta) complete with
1000 Nos required wire leads duly
erected
and
dismantled
with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

1000 Nos
bulbs & 30
Mtrs 7/20
service wire

1 year i.e
60 days

1.Skill
electrician
1.Helper

1000 Nos
bulbs & 30
Mtrs 7/20
service wire

1 year i.e
60 days

1.Skill
electrician
1.1Helper

Labour
charges

Storage
charges
@ 1%
on
capital
cost/N
o.of
days in
a year
9

Transport
ation
charges @
2% on
capital
cost/No.o
f days in a
year

Hire
charges
per day

10

11

306

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.3

16.4

16.5 a

16.5 b

Hire
charges
for
Temporary
illumination, consisting of tube light
with patti type 4'-40W complete with
required wire leads duly erected and
dismantled
without
scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of tube light
with patti type 4'-40W complete with
required wire leads duly erected and
dismantled with scaffolding including
cost and conveyance of all materials
and labour charges etc., complete for
one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
1000W hallogen with lamp complete
with required wire leads duly erected
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
500W hallogen with lamp complete
with required wire leads duly erected
and dismantled without scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.

1 No tube
light, 4 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.06 Skill
electrician
0.06Helper

1 No tube
light, 4 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.06 Skill
electrician
0.10Helper

1 No 1000W
Halogen, 30
Mtrs 7/20
service wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.25Helper

1 No 500W
Halogen, 30
Mtrs 7/20
service wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.25Helper

307

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.5 c

16.5 5

16.6 a

16.6 b

Hire
charges
for
Temporary
illumination, consisting of flood light
250W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
400W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
1000W hallogen with lamp complete
with required wire leads duly erected
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire
charges
for
Temporary
illumination, consisting of flood light
500W hallogen with lamp complete
with required wire leads duly erected
and dismantled with scaffolding
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.

1 No 250W
Metal halide,
30 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.25Helper

1 No 400W
Metal halide,
30 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.25Helper

1 No 1000W
Halogen, 30
Mtrs 7/20
service wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.30Helper

1 No 500W
Halogen, 30
Mtrs 7/20
service wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.30Helper

308

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.6 c

16.6 d

16.7

16.8

Hire
charges
for
Temporary
illumination, consisting of flood light
250W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of flood light
400W metal halide fitting with lamp
complete with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of white /
colour series light 6.2v complete with
1000 Nos. with required wire leads
duly erected and dismantled without
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Hire
charges
for
Temporary
illumination, consisting of white /
colour series light 6.2v complete with
1000 Nos. with required wire leads
duly erected and dismantled with
scaffolding including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

1 No 250W
Metal halide,
30 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.30Helper

1 No 400W
Metal halide,
30 Mtrs
7/20 service
wire

3years i.e
3 x 60 =
180 days

0.25 Skill
electrician
0.30
Helper

1000 Nos
bulbs & 30
Mtrs 7/20
service wire

1 year i.e
60 days

0.5 Skill
electrician
0.5Helper

1000 Nos
bulbs & 30
Mtrs 7/20
service wire

1 year i.e
60 days

0.5 Skill
electrician
1.0 Helper

309

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.9

16.10

16.1

16.12

Hire charges for Providing and fixing


rotating machine to give running
effect to strip lights and miniature
lights upto a load of 10KW with
required wire leads duly dismantled
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire charges for Providing oscillating
type pedestal fan 16" / 18" with
connected wire leads duly dismantled
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire charges for Providing air cooler
connected with necessary mains
switch gear with continues earth lead
during function
duly dismantled
including cost and conveyance of all
materials and labour charges etc.,
complete for one day.
Hire charges for Providing 1.5 ton/2.0
ton capacity window air conditioning
unit complete with suitable stabilizer
with temporary frame and fabrication
work and required materials achieve
cooling, temperature connected with
necessary mains switch gear with
continues earth lead during function
duly dismantled including cost and
conveyance of all materials and
labour charges etc., complete for one
day.

Cost of 10
KW rotating
machine

5 years
i.e 5 x 30
= 150
days

0.25
Helper

18" pedestal
fan, 30
Mtrs 7/20
service wire

3years i.e
3 x 40 =
120 days

0.10
Helper

Air cooler,
30 Mtrs
7/20 service
wire

3years i.e
3 x 40 =
120 days

0.20 semiskilled
electrician

Air
conditioned,
stabilizer

8years
i.e. 8 x 15
= 120
days

1 skilled
electrician,
2 Helpers,
1 carpenter

310

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.1

16.14 a

16.14 b

Hire charges for Providing temporary


plug point with 5 pin 6 Amps/16 Amps
with necessary mains switch gear with
continues earth lead during function
duly dismantled including cost and
conveyance of all materials and
labour charges etc., complete for one
day.
Note : 1) The rates are for one
glowing/working day.
2) Allow 50% of rate for each day upto
3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3
days, but not exceeding 15 days,
allow 25 % rate of glowing/working
days
4) For more than 15 days allow 10%
per day but total rental charges shall
not exceeded 80% of capital cost of
item.
Hire charges for supply and
maintaining 125 KVA, 415 voltage, 50
C/s AC generating set with all
standard accessories such as control
panel, batteries etc complete for one
day excluding cost of fuel.
Hire charges for supply and
maintaining 82.5 KVA, 415 voltage, 50
C/s AC generating set with all
standard accessories such as control
panel, batteries etc complete for one
day excluding cost of fuel.

16 Amps 5 in
one power
plug, 30
Mtrs 7/20
service wire

3years i.e
3 x 40 =
120 days

0.05 semiskilled
electrician

125 KVA DG
Set, 200
Amps main
switch

10years
i.e 10 x
60 = 600
days

1.Skill
Electrician

82.5 KVA DG
Set, 200
Amps main
switch

10years
i.e 10 x
60 = 600
days

1.Skill
Electrician,

311

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.14 c

16.14 d

16.14 e

16.2

Hire charges for supply and 62.5 KVA DG


10years
maintaining 62.5 KVA, 415 voltage, 50
Set, 200
i.e 10 x
C/s AC generating set with all
Amps main
60 = 600
standard accessories such as control
switch
days
panel, batteries etc complete for one
day excluding cost of fuel.
Hire charges for supply and
30 KVA DG
10years
maintaining 30 KVA, 415 voltage, 50
Set, 100
i.e 10 x
C/s AC generating set with all
Amps main
60 = 600
standard accessories such as control
switch
days
panel, batteries etc complete for one
day excluding cost of fuel.
Hire charges for supply and 5 to 15 KVA
10years
maintaining 5 to 15 KVA, 415 voltage,
DG Set, 63
i.e 10 x
50 C/s AC generating set with all
Amps main
60 = 600
standard accessories such as control
switch
days
panel, batteries etc complete for one
day excluding cost of fuel.
Hire charges for supply and 125 KVA DG
10years
maintaining of 125 KVA DG set with Set, acoustic
i.e 10 x
acoustic enclosure as per IS
enclosure,
60 = 600
specification with DCM 4 wheeler
200 Amps
days
vehicle with all standard accessories main switch
such as control panel, batteries etc
with 4
complete for one day excluding cost
wheeler
of fuel.
DCM vehicle.
NOTE: 1) The above rates are applicable per one day only.
2) For subsequent days the above rte shall be reduced by 25% after 8th day
reduce the rate by 50%
3) Diesel cost will be paid extra for running hours at the prevailing rates.
4) For test run,. The minimum req2uirement of the fuel shall be born by the
contractor.
5) The D.G.set should be in good condition and the life of set shall not b e beyond
10 years

1.Skill
Electrician,

1.Skill
Electrician,

1.Skill
Electrician,

1.Skill
Electrician,

312

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.16 a

16.16 b

16.16 c

16.16 d

16.16 e

16.16 f

16.16 g

Hire charges for supply and


maintaining towards supply and run
of 2 of 2.5 sq mm to 6 sq mm
VIR/WPTC/WPSC cable with necessary
terminations etc., complete for one
day.
Hire charges for supply and
maintaining towards supply and run
of 2 of 10 sq mm VIR/WPTC/WPSC
cable with necessary terminations
etc., complete for one day.
Hire charges for supply and
maintaining towards supply and run
of 35 sq mm x 3 1/2 core UG cable
with necessary terminations etc.,
complete for one day.
Hire charges for supply and
maintaining towards supply and run
of 50 sq mm x 3 1/2 core UG cable
with necessary terminations etc.,
complete for one day.
Hire charges for supply and
maintaining towards supply and run
of 95 sq mm x 3 1/2 core UG cable
with necessary terminations etc.,
complete for one day.
Hire charges for supply and
maintaining towards supply and run
of 120 sq mm x 3 1/2 core UG cable
with necessary terminations etc.,
complete for one day.
Hire charges for supply and
maintaining towards supply and run
of 185 sq mm x 3 1/2 core UG cable
with necessary terminations etc.,
complete for one day.

2 of 6 sq mm
WPTC cable
1 mtr

3years i.e
3 x 60 =
180 days

0.015
Helper

2 of 10 sq
mm WPTC
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.02
Helper

35 sq mm x
3 1/2 UG
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.05
Helper

50 sq mm x
3 1/2 UG
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.05
Helper

95 sq mm x
3 1/2 UG
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.05
Helper

120 sq mm x
3 1/2 UG
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.05
Helper

185 sq mm x
3 1/2 UG
cable 1 mtr

3years i.e
3 x 60 =
180 days

0.05
Helper

313

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.2

16.18 a

16.18 b

16.18 c

Hire charges for providing industrial


type panel board consisting of bus bar
chamber
with
200/250
amps
incoming TP/MCCB as incomers
switch, 12 nos 100 amps fuse unit,
earth wire erected and dismantled all
accessories etc., complete for
distribution for one day.
Hire charges for supply and
maintaining towards supply and fixing
of 100 amps 4 pole change over
switch/TPN
switches
including
erection
and dismantled all
accessories etc., complete for one
day.
Hire charges for supply and
maintaining towards supply and fixing
of 200 amps 4 pole change over
switch/TPN
switches
including
erection
and dismantled all
accessories etc., complete for one
day.
Hire charges for supply and
maintaining towards supply and fixing
of 400 amps 4 pole change over
switch/TPN
switches
including
erection
and dismantled all
accessories etc., complete for one
day.

250 Amps
bus bar, 250
TPN/MCCB,
12 nos 100
Amps fuse
units

10years
i.e 10 x
15 = 150
days

0.5 Skilled
electrician,
1 Helper

100 Amps
COS/ TPN

10years
i.e 10 x
15 = 150
days

0.125
Skilled
electrician,
0.125
Helper

200 Amps
COS/ TPN

10years
i.e 10 x
15 = 150
days

0.125
Skilled
electrician,
0.125
Helper

400 Amps
COS/ TPN

10years
i.e 10 x
15 = 150
days

0.2 Skilled
electrician,
0.2 Helper

314

STANDARD DATA-ELECTRICAL ITEMS TEMPORARY ILUMINATION

16.19 a

16.19 b

Hire charges for supply and erection 24 Mtrs 80/


15years
and dismantle of 4 pole structure of 4
50mm C
i.e 15 x
of 20' GI pipe of 50/80mm structure class GI pipe, 12 = 180
complete necessary cross arms and
50/50 MS
days
hardware
materials
for
fixing
cross arms
halogen/ metal halide fitting with weight of 72
suitable
earthing
arrangements Kgs & 1 No.
including cost conveyance of all coil earthing
materials and labour charges for
maintaining one day.
Hire charges for supply and erection
36 Mtrs
15years
and dismantle of 4 pole structure of 4 80/50mm C
i.e 15 x
of 30' GI pipe of 50/80mm structure class GI pipe, 12 = 180
complete necessary cross arms and
50/50 MS
days
hardware
materials
for
fixing
cross arms
halogen/ metal halide fitting with weight of 72
suitable
earthing
arrangements
Kgs & 1
including cost conveyance of all
No.coil
materials and labour charges for
earthing
maintaining one day.
NOTE: 1) The rates are for one glowing/working day.
2) Allow 50% of rate for each day upto 3 days (i.e. 2nd and 3rd day)
3) For each additional day after 3 days, but not exceeding 15 days, allow 25 % rate
of glowing/working days
4) For more than 15 days allow 10% per day but total rental charges shall not
exceeded 80% of capital cost of item.
Note : Service Tax and VAT as applicable shall be extra
for all Items.

0.5 fitter,
0.5 skilled
electrician,
2 Helpers,
54 Cum.

0.5 fitter,
0.5 skilled
electrician,
2 Helpers,
54 Cum.

315

STANDARD DATA-ANNEXURE

GOVERNMENT OF ANDHRA PRADESH


ABSTRACT
Irrigation & CAD Department Adoption of Revision and Updating of Andhra Pradesh Standard data in all
Engineering/Public Works Department and other organisations Orders Issued.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - IRRIGATION & CAD (PW- REFORMS) DEPARTMENT
G.O.Ms. No. 49

Dated: the 2nd March, 2009


Read the following:1. G.O.Rt.No.7326 , GA (GPM/AR) Department dated 26.10.2005
2. From the Director General D.O.Letter.No.CGG/AP Standard Data/2006-07, dated
8.12.2006
3. Govt.Memo.No.36710/Reforms/I&CAD(PW) Dept., dated 22.6.2007
4. U.O.Note.No.36710/Reforms/2005, I&CAD (PW) Dpt., dt.29.6.2007
5. Govt.Memo.No.36710/Reforms/2005, I&CAD Dept., dated 10.3.2008
6. From ENC (AW)/IW I&CAD Dept., Letter.No.ENC/IW/P&M/EE.1/DEE.8 /19200-98, dated
21.4.2008

ORDER:
The basic components for preparing any estimate are Standard Specifications, Standard Data,
and Schedule of Rates for construction materials, skilled and un-skilled labour and hire charges of
machinery utilized on works. To get the work done, as per the standard specifications, required
quantities of recommended materials, requirement of specific need based manpower, deployment of
proper utility based machinery and duration of its utilization are to be observed and quantified for
each unit of work, and this is called Standard Data. Thus, the Standard Data gives the details of
various inputs in terms of quantities required for one Unit of any work. Schedule of rates for material,
skilled and unskilled labour are fixed and revised by the Board of Chief Engineers once in a year and
these are called Standard Schedule of Rates. When the Standard Schedule of Rates and Hire charges
of machinery are incorporated in the inputs of Standard Data and Standard Schedule of Rates it will
have direct bearing on the preparation of project Estimates and consequent finalization of Tenders.
2. The existing AP Standard Data for various construction items were based on observations made
several decades back mostly by utilizing manpower for execution of all items of works, and
deployment of machinery was at the barest minimum. The advent of latest machinery and their
extensive use has changed the structure and methodology of data formulation and rate structure.
There is a need to revise the present Standard Data for all items of worksdealing with Public works.
Realizing the urgency and importance to haverealistic data, Government in the GO.Rt.No.7326 G.A
(GPM & AR) Departmentdated 26-10-2005 constituted a High Level Committee under the
chairmanshipof Special Chief Secretary, General Administration (GPM&AR) Department, to advise on
Updating and Revising the A.P.Standard Data. A project for Standard Data (revision) and Schedule of
Rates was conceived and entrusted to the Centre for Good Governance. Keeping in view the strategy,
factors considered and classification of works, a number of High Level Committee meetings and
review meetings were conducted at Centre for Good Governance/ A.P.Secretariat and in the offices of
concerned Engineers-in-Chief I&CAD, Public Health, Panchayati Raj and Roads & Buildings
Departments etc. Their specific views, suggestions and recommendations were taken into account,
besides collecting the data from various sources while finalizing the Draft AP standard Data and
Standard Schedule of Rates. This has been cleared by the Board of Chief Engineers and finally by the
High level Committee. The Standard Data has been revised and updated in four parts considering
nature of work, location of work and magnitude of work as indicated below.
1. PART I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
3.
The revision of Standard Data and Schedule of Rates in respect of works items of Irrigation
Department has been taken up by the SPIU (Irrigation) and completed as per the C.W.C guidelines and
B.I.S standards and also observations and recommendations made by the High Level Committee. In
316

STANDARD DATA-ANNEXURE

respect of other Departments, MORTH data is adopted for Roads & Bridges, where higher capacity
machinery can be deployed and MORD data is adopted for Roads & Bridges in Rural areas. For other
works data as per MORTH, MORD, and C.P.W.D. etc., is adopted. The comparative estimates have
been prepared by the T.R. &B Dept. , Engineering-in-Chief (Irrigation) and MA & UD Department for
various types of works of a magnitude of Rs.15-20 crores, based upon the earlier data and the newly
revised and proposed data .
4.
After detailed deliberations and discussion on the above issue, the Govt. accept the
recommendations of Board of Chief Engineers and High level Committee and accordingly issue the
orders for adoption of the Revised and Updated Standard data in all Engineering/ Public works
Department and other organisations in four parts considering nature of work, location of work and
magnitude of work as indicated below. The four parts of Standard Data booklets are forwarded to
Engineer-in-Chief (AW), who in turn will publish the authenticated version and circulate a copy to all
works Departments.
1. PART I : Irrigation & Command Area Development.
2. PART- II : Roads & Bridges.
3. PART-III : Buildings
4. PART-IV : Drinking Water Supply Schemes.
5.
The Revised Data now approved is to be adopted by all Engineering Departments/ all Public
Works Department and other organisations, duly superseding all the earlier orders issued on the
subject. 6. These orders shall come into force from the date of issue.
7.
This order issues with the concurrence
U.O.No.5532/520/Exp.PW.I Dept/08, dated 13-5-2008.

of

Finance

Department

vide

their

(BY ORDER AND IN THE NAME OF THE GOVERNOR OF ANDHRA PRADESH)


RAJIV RANJAN MISHRA
SECRETARY TO GOVERNMENT
To
All the Engineer-in-Chief of Irrigation & CAD Department.
All the Chief Engineers of Irrigation & CAD Department.
The Commissioner, Commissioner of Tenders,
The Engineer-in-Chief, PR &RD Department, Hyderabad.
The Engineer-in-Chief (R&B) Admn.,Dept., Hyderabad.
The Engineer-in-Chief (PH) Hyderabad.
Copy to:
All the Collectors & Dist. Magistrate of Andhra Pradesh
All Sections in Irrign. & CAD (PW/Irrgn.) Dept.
The Accountant General Andhra Pradesh Hyderabad.
The G.A. (Cabinet) Dept. w.r.t. U.O.No.79/2009, dated 17-2-2009.
The G.A. (GPM&AR) Dept.
The Finance (W&P) Dept.
The P.S. to Ministers (PR & RD/ MA &UD/ T.R. & B / Housing )
The P.S. to Prl. Secy. (SKJ)/ P.S. to Secretary (AD)/ P.S. to Secretary (RRM)
The P.S. to Prl. Secretary, Housing/P.S. to Prl. Secy, M.A. & U.D. / P.S. to
Secretary, T.R.& B / P.S. to Prl. Secretary, PR & RD./P.S. to Secretary , Housing.
All the Advisors of Irrgn. & CAD Dept.
SF/SC.
// FORWARDED::BY ORDER//
SECTION OFFICER

317

You might also like