You are on page 1of 5

STEAM BLOW OUT

1.0 OBJECTIVE
The purpose of steam blowing is to dislodge scales, remove loose material, iron pieces,
weld slag etc., that might have been entrapped inside the piping of Superheaters and
other station steam piping during erection. Failure to ensure absolute cleanliness of the
steam piping may result in damage to the Turbine blades, Valves etc. The steam blow
out operation is carried out after Boiler acid cleaning.
2.0 BASIC TECHNIQUE
2.1 The steam blow out is carried out by the puffing method. The dynamic disturbance
available in this method will give a thermal shock to the system being purged to dislodge
the scale etc., which will be subsequently carried away by the expanding steam.
2.2 For the steam blowing to be effective, the ratio of the kinetic energy at steam
blowing conditions to MCR conditions should be greater than one(1).This is determined
by what is called the DISTURBANCE FACTOR and is calculated by using the following
formula
:
Disturbance Factor, K = Vb x Fb2/Vm x Fm2
Where,
Vb = Specific volume of the steam at blowing pressure
Fb = Mass flow rate of steam at the blowing pressure
Vm = Specific volume of the steam at Boiler MCR condition
Fm = Mass flow rate of steam at Boiler MCR condition.
Before the steam blowing operation the blowing pressure should be decided/calculated
to give the required Disturbance Factor. The pressure normally adopted is 40 Kg/cm2.
2.3 During the blow out operation the cleanliness of the piping is determined by the use
and study of Target Plates made of specified material (MS, SS, Aluminum or others)
located in an assembly in the steam blow path, in the temporary exhaust piping at a
location nearest possible to the permanent pipe work.
3.0 THE SCHEME
The steam blow out operation is carried out in stages to include the maximum possible
length of steam piping. In order to achieve effective cleaning, all the station piping is
sectionalised and steam blown. Turbine is bypassed during steam blowing . The stages
normally followed are;

Superheater : The superheater and main steam pipes are are steam blown
through to the turbine main steam chests, and from there to atmosphere using

temporary pipe work. The turbine steams valve are replaced by temporary
blanks.
Superheater and reheater : After superheater steam blowing is complete, the
temporary pipe work is rearranged so that the turbine main steam chest
discharge pipe work is replaced with temporary connections to the cold reheat
steam pipes, discharging to atmosphere using the turbine reheat intercept
steam chests, and temporary pipe work.

4.0 PREPARATIONS, PRECAUTIONS & CHECKS


4.1 Boiler acid cleaning and passivation operation are satisfactorily completed. All the
temporary piping for acid cleaning is removed and permanent pipe connections
restored, Drum intervals are fixed and hydro test conducted.
4.2 Main steam and all the station steam piping erection are completed, with all
supports and hangers provided as per drawing
4.3 Temporary piping for blow out erected. Temporary blanks installed wherever
applicable.
4.4 Temporary blow out piping checked for proper anchoring and safe discharge outside
the building. They should be able to withstand the excessive reaction forces of steam
blowing. The exhaust area suitably fenced and CAUTION notice displayed prominently.
4.5 The diameter of the temporary piping should not be less than the diameter of the
respective lines to be steam blown.
4.6 All the permanent and temporary piping included in the scheme of blow out are
adequately insulated before commencing the steam blow out operation.
4.7 Electrically operated Temporary blow out valve, if used, should be installed on the
Main steam line and its operation checked. For the blow out to be effective these valves
be fast acting with an actuation time of about 30 to 40 seconds.
4.8 All Flow nozzles, Strainers, Orifice plates, Control valves and Attemporators are
removed and temporary spool pieces fixed in place. NRV flaps should be removed from
NRVs in the steam blowing path.
4.9 Hydrostatic test plugs should be removed and all the safety valves are thoroughly
cleaned and assembled.
4.10 The target plate fixing arrangement erected and checked. Sufficient quantity of
target plates of the specified material are available.
4.11 Sufficient quantity of DM water available and the DM Plant is in operation.
4.12 The Boiler is ready in all aspects, including, protections, interlocks, instrumentation,
chemical dozing etc., for Light up and raising pressure.

4.13 Ensure that no loose debris or other material are left inside permanent or
temporary piping.
4.14 Drains going to any Vessel should be left open to atmosphere, preferably outside
the TG Hall.
4.15 Before beginning the steam blow out determine/decide on the pressure for the
blow out to achieve correct disturbance factor.
5.0 STEAM BLOWING PROCEDURE
5.1 Boiler is started up, following normal startup procedures. All the normal
recommendations and permitted operational limitation should be strictly observed.
5.2 Light up the Boiler and raise the steam pressure slowly as per O & M procedures up
to 20 25 Kg/cm2. Warm up the line by opening the bypass of Boiler steam stop valve
and then open the Boiler stop valve. Boiler fires are put off and electrically operated
temporary valves are opened and valves are closed at 10 kg/cm2 start up vent to be
closed during the above period. During 1st blow, the boiler associate and station piping
are completely inspected for any abnormality.
5.3 After inspection, light up the Boiler and raise the pressure to the predetermined
value 40 Kg/cm2, for the first stage of the blow.
5.4 Kill the Boiler fire. Open the electric operated temporary valves EOTVs and give blow
till the pressure drops to a specified value, so that the saturation temperature change is
limited to a maximum of 40C (This is to prevent undue thermal stresses in the Drum
and Headers). Close the EOTVs.
5.5 During steam blowing, the following observations are recorded.
i) Drum level swings.
ii) Steam pressure drop at various sections.
iii) Steam temperature at various sections.
iv) Duration of steam blow.
5.6 After EOTVs are closed at stop steam blowing, boiler is relighted up and conditions
are re-established for next blow. The standard practice is to limit the number of blows
per day to 6 to 8 at an interval of 1 hrs. for each blow, with overnight cooling.
5.7 Continue steam blowing until Target Plate is clean (decided by completion criteria
see clause 6.0 ). Use Target Plates after every three (3) or four (4) blows and for every
blow in the last stage.
5.8 After First stage completion, prepare for the second stage operation.
5.9 Complete second stage at specified pressure till target plate is clean

5.10 Prepare for the next stage steam blowing.


5.11 Complete all stages of steam blowing one by one.
5.12 Each stage will normally be steam blown at specified pressure.
5.13 After completion of steam blowing remove the temporary piping and blanks, install
Flow nozzles, Control valves etc., and reweld piping as per drawing.
6.0 TARGET PLATE ANALYSIS & COMPLETION CRITERIA
The number of impacts found on the Target plates give indication of the pipe cleanliness.
The highest velocity of steam is in the centre of the pipe. Hence judgement should be
made for the end point of steam blowing in the central zone of the target plate. The
piping shall be considered clean if number of impacts on an area of 40mmX40mm:
No impact with a size > 1mm
Less than 4 impacts with a size > 0.5mm
Less than 10 impacts with a size > 0.2mm
However, it is best that such completion criteria be discussed and finalized, before start
of the steam blow out operation.
7.0 STEAM BLOWING OF MISC. STEAM LINES
Steam lines like ; steam headers to various HP, MP and LP consumers are to be steam
blown by continuous blowing method. The parameters of steam blowing for these lines
will be different and should be strictly followed.
HP Steam consumers for turbine drives, the line shall be steam blown till the target
plates are clear. In other areas steam lines shall be steam blown till the steam quality
at outlet is clear.
8.0 SAFETY
8.1 Personnel not in volved in the steam blow operation should be moved away from
the area.
8.2 Adequate communication system should be setup to warn personnel when each
blow is about to commence and on completion.
8.3 Personnel should be stationed at strategic points and in case of any
abormality/emergency situation blow out to be stopped and problem investigated /
corrected before commencing steam blow out.
8.4 All personnel in the vicinity of steam blow out must wear ear plug.

8.5 While fixing and removing target plate , the steam supply will be isolated by closing
stop valve and its bypass and permit for work will be issued.
9.0 STEAM PARAMETERS FOR STEAM BLOWING
HHP Steam lines : Pressure / Temperature : 40 kg/cm2/ 400 deg C
HP Steam lines : Pressure / Temperature : 30 kg/cm2 / 350 deg C
MP Steam lines : Pressure / Temperature : 10 kg/cm2 / 250 deg C
LP Steam lines : Pressure / Temperature : 5 kg/cm2 / 250 deg C
9,0 REFERENCES
9.1 VGB Guide line for steam blowing ( VGB-R513e)
PROTOCOL
Site : Job No.
Date :
1. Circuit included :
2. Steam pressure before blowing : bar (g)
3. Steam pressure after blowing : bar (g)
4. Duration of each blow : minutes
5. Time interval between two blows : hrs.
6. Total Nos. of blows : nos.
7. Number of targets checked : nos.
8. Material of targets plate :
9. Condition of final target plate after blowing :
Result
Accepted / Not Accepted
Remarks
Signatures

You might also like