TRAFFIC APPRAISAL:
Current traffic scenario:
The Various Surveys Conducted are as follows.
(I)
(ii)
Pedestrian traffic count at all the nodal points for two days during identified
peak hours.
(iii)
compare with working day and non working day pedestrian movement
(iv)
(iv)
This Survey was conducted for all nodal points for 2 days during identified
peak hours. The identified peak hour is 8.00 A.Mto 9.00 A.M of the day. The Volume
of Pedestrians crossing the Road (per Hr) is Presented in below table
PEDESTRAIN FLOW
2395
2364
2256
1755
1264
944
(I)
This survey was conducted on 01.08.2013 between 8.00 hrs and 9.00 hrs.
Pedestrains crossing the road were enquired by the Consultant and origin and
destination points of the pedestrians are noted. From this survey we can find out
(i)
(ii)
BIKE
AUTO
ALAGAR KOVIL
01.08.201
ROAD
3
04.08.201
1684
266
1609
256
MEENAKSHI
01.08.201
COLLEGE ROAD
3
04.08.201
3600
768
3
01.08.201
4208
734
466
208
PANAGAL ROAD
BYPASS ROAD
3
04.08.201
3
01.08.201
861
179
3
04.08.201
1668
314
1825
235
4500
4000
3500
3000
BIKE
2500
AUTO
2000
BUS
1500
CYCLE
CAR
Axis Title
TRUCK
1000
500
0
ROAD DIRECTION
(I)
To avoid the above time delay, pedestrain subway has been proposed. The full
time delay will be avoided when pedestrain subway constructed.
Considering the large number of pedestrian movement near the Government Rajaji
Hospital, the authorities provided a subway.
Rajaji hospital near bus stop so cross road pedestrian use the bus stop .
Poor maintenance of these facilities, pedestrians continue to cross the road in these
places.
CAPACITY ANALYSIS:
Capacity Analysis of Proposed Subway:
Evaluation of the capacity of the proposed subway is done with the
basic promise of the pedestrians. The traffic projection for 20 years was
done.and width of stair case in the measurement used