You are on page 1of 95

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN JASA


PEMASANGAN INSTALASI LISTRIK

NO

JENIS PEKERJAAN

HARGA
SATUAN
(Rp.)

BIAYA
(Rp.)

JUMLAH
DIBULATKAN
(Rp.)

1 hari
1 hari

17250
8000

17250
8000

Uang Makan 1 hari

7000

7000
32250

2
DASAR UPAH
- Pekerja (pembantu tukang) upah minim
- Tukang
- Kepala Tukang
- Mandor
- Teknisi
- Supervisi
- Tenaga Ahli (Expert)
1 PEKERJA
Upah
Transfort

32250
32250

2 TUKANG
Upah

1 hari

24500

24500

Transfort 1 hari
Uang Makan 1 hari

8000
8000

8000
8000
40500

40500
40500

3 TEKNISI
Upah
1 hari
Transfort 1 hari
Uang Makan 1 hari

38250
8000
10000

38250
8000
10000
56250

56250

56250
56250

4 TENAGA AH
Upah
1 hari
Transfort 1 hari
Uang Makan 1 hari

93500
15000
15000

93500
15000
15000
123500

123500

123500
5 SUPERVISI
Upah
1 hari
Transfort 1 hari
Uang Makan 1 hari

139750
15000
20000

139750
15000
20000
174750

168750
174750
168750

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA


ANALISA HARGA SATUAN
PEKERJAAN PEMASANGAN INSTALASI GARDU
Belum termasuk resiko,over head,keuntungan 10 % dan PPN 10 %
2004
NO

JENIS PEKERJAAN

HARGA

BIAYA

JUMLAH

SATUAN

( Rupiah )

DIBULATKAN

( Rupiah )
1
1a

( Rupiah )
4

PEKERJAAN PEMASANGAN INSTALASI GARDU


1.1 Pemasangan kubikel LBS/PT/B1
- Tenaga Ahli

- Pengadaan

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

2 Pekerja

32,250

64,500.00

4 Buah

3,738

14,952.00
206,764.50

206,760.00

1.2 Pemasangan Kubikel PGDB/PGDT


- Tenaga Ahli

- Pengadaan

0.50 Hari

123,500

61,750.00

4 Tukang

40,500

162,000.00

2 Pekerja

32,250

64,500.00

3 Buah

3,738

11,214.00
299,464.00

299,460.00

1.3 Pemasangan SACO


- Tenaga Ahli

- Pengadaan

0.50 Hari

123,500

61,750.00

4 Tukang

40,500

162,000.00

2 Pekerja

32,250

64,500.00

4 Buah

3,738

14,952.00
303,202.00

303,200.00

1.4 Pemasangan RMU.3 dan 4 Terminal(Panel Kontrol UPD)


- Tenaga Ahli

- Pengadaan

0.50 Hari

123,500

61,750.00

4 Tukang

40,500

162,000.00

1 Pekerja

32,250

32,250.00

4 Buah

3,738

14,952.00
270,952.00

270,950.00

1.5 Pemasangan RMU ( LBS,LBS,PB) ( Beton,Kiosk,Portal)


- Tenaga Ahli

- Pengadaan

0.50 Hari

123,500

61,750.00

4 Tukang

40,500

162,000.00

2 Pekerja

32,250

64,500.00

4 Buah

3,738

14,952.00
303,202.00

303,200.00

1.6 Pemasangan ( Peletakan ke posisi sebenarnya ) Trafo 100 kVA s/d 315 KVA
- Tenaga Ahli

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

3 Pekerja

32,250

96,750.00
224,062.50

1.7 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 400 kVA s/d 630 kVA
- Tenaga Ahli

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

5 Pekerja

32,250

161,250.00

224,060.00

288,562.50

288,560.00

1.8 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.000 kVA s/d 1.250 KVA
- Tenaga Ahli

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

8 Pekerja

32,250

258,000.00
385,312.50

385,310.00

1.9 Pemasangan ( Peletakan ke posisi sebenarnya )Trafo 1.600 kVA s/d 2.000 KVA
- Tenaga Ahli

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

12 Pekerja

32,250

387,000.00
514,312.50

1.10

- Tenaga Ahli

0.25 Hari
2 Tukang

1.11

123,500

30,875.00

40,500

81,000.00

32,250

111,875.00

123,500

15,437.50

40,500

81,000.00

32,250

96,437.50

0.13 Hari
2 Tukang

0.13 Hari

123,500

15,437.50

2 Tukang

40,500

81,000.00

1 Pekerja

32,250

32,250.00
128,687.50

- Pengadaan

0.38 Hari

123,500

46,312.50

2 Tukang

40,500

81,000.00

4 Pekerja

32,250

129,000.00
256,312.50

0.13 Hari
2 Tukang

123,500

15,437.50

40,500

81,000.00
96,437.50

0.13 Hari

123,500

15,437.50

2 Tukang

40,500

81,000.00

3 Pekerja

32,250

96,750.00
193,187.50

0.67 Hari

123,500

82,333.33

0.67 Tukang

40,500

27,000.00

0.33 Pekerja

32,250

10,750.00
120,083.33

120,080.00

Single Core TM 3 x ( 1x 25 mm2 ) di Trafo


- Tenaga Ahli

0.67 Hari

123,500

82,333.33

0.67 Tukang

40,500

27,000.00

0.33 Pekerja

32,250

10,750.00
120,083.33

1.18

193,180.00

Single Core TM 3 x ( 1x 25 mm2 ) di MV Cell


- Tenaga Ahli

1.17

96,430.00

L.V.S.B Outdoor untuk gardu Portal


- Tenaga Ahli

1.16

256,310.00

L.V.C.B Outdoor untuk gardu CANTOL


- Tenaga Ahli

1.15

128,680.00

Pemasangan LBS untuk Gardu Beton Open Type


- Tenaga Ahli

1.14

96,430.00

Rak TR 6 & 8 Jurusan


- Tenaga Ahli

1.13

111,870.00

Rak TR 4 Jurusan
- Tenaga Ahli

1.12

514,310.00

Bracket (Kabel Tray) dan Grounding

Single Core TR 7 x ( 1x 240 mm2 ) di Trafo


- Tenaga Ahli

0.25 Hari

123,500

30,875.00

120,080.00

0.13 Tukang

40,500

0.13 Pekerja

32,250

5,062.50
4,031.25
39,968.75

1.19

- Tenaga Ahli

0.25 Hari

123,500

30,875.00

0.13 Tukang

40,500

5,062.50

0.13 Pekerja

32,250

4,031.25
39,968.75

1.20

0.13 Hari

123,500

15,437.50

1 Tukang

40,500

40,500.00

2 Pekerja

32,250

64,500.00

- Pengad/Pem

1 Meter

15,600

15,600.00

- Pengad/Pem

1 Buah

1,950

1,950.00
137,987.50

137,980.00

IndikatormGangguan Tanah/GFD
- Tenaga Ahli

0.13 Hari
2 Tukang

123,500

15,437.50

40,500

81,000.00
96,437.50

1.22

39,960.00

Pengadaan Penyangga Kabel TM 20 kV


- Tenaga Ahli

1.21

39,960.00

Single Core TR 7 x ( 1x 240 mm2 ) di TR

96,430.00

Pemasangan Instalasi Heater Kubikel


- Tenaga Ahli

0.13 Hari
1 Tukang

123,500

15,437.50

40,500

40,500.00
55,937.50

55,930.00

1.23

Pengadaan Ka

1 Meter

2,210

2,210.00

2,210.00

1.24

Pembersihan

2 Pekerja

26,250

52,500.00

52,500.00

1.25

Bantuan Tena

2 Tukang

37,500

75,000.00

Pengopersian

2 Pekerja

26,250

52,500.00

1.b

127,500.00

127,500.00

26,250

26,250.00

PEKERJAAN PEMBONGKARAN INSTALASI GARDU


1 No: 1 s/d 19 sama dengan Pekerjaan Pemasangan
2 Pembongkaran Terminal Ind1 Pekerja

II

26,250

PEMASANGAN APP TYPE KHUSUS IB,IC DAN IIF


2.1 Dengan Pondasi
- Galian tana

0.13 m3

20,386

2,650.18

- Pasang Bat

0.26 m3

201,578

52,410.28

- Pasang Ang

4 Buah

3,738

14,952.00

- Pasang Fish

4 Buah

1,430

5,720.00

- Plesteran 1

2.27 m2

10,777

24,463.79

- Acian Beton

2.27 m2

4,420

10,033.40

- Jasa Pelaks

0.5 Hari
3 Tukang

- Jasa Pelaks

0.13 Hari
2 Tukang

123,500

61,750.00

40,500

121,500.00

123,500

16,055.00

40,500

81,000.00
390,534.65

2.2 Dengan Strain Hook


- Pasang Stra
- Tenaga Ahli

4 Buah

6,500

26,000.00

123,500

15,437.50

1 Tukang

40,500

40,500.00

2 Pekerja

32,250

64,500.00

0.13 Hari

390,530.00

146,437.50
III

146,430.00

PEKERJAAN PEMELIHARAAN INSTALASI GARDU


3.1 Kubikel TM
- Tenaga Ahli
- Tukang
- Majun
- YC.8513 ( M
- Pasline Put

0.13 Hari
2 Tukang
0.5 Kg
0.5 Liter
0.25 Kg

123,500

15,437.50

40,500

81,000.00

8,000

4,000.00

75,000

37,500.00

87,500

21,875.00
159,812.50

159,810.00

3.2 Kubikel pengukuran ( PGDB )


- Tenaga Ahli
- Tukang

0.13 Hari
2 Tukang

- Majun

0.5 Kg

- YC.8513 ( M

0.5 Liter

- Pasline Put

0.25 Kg

123,500

15,437.50

40,500

81,000.00

8,000

4,000.00

75,000

37,500.00

87,500

21,875.00
159,812.50

159,810.00

3.3 Trafo Distribusi


- Tenaga Ahli
- Tukang

0.13 Hari
2 Tukang

- Majun

0.5 Kg

- YC.8513 ( M

0.5 Liter

123,500

15,437.50

40,500

81,000.00

8,000

4,000.00

75,000

37,500.00
137,937.50

137,930.00

3.4 Rak TR
- Tenaga Ahli
- Tukang
- Majun
- YC.8513 ( M
- Pasline Put

0.13 Hari
1 Tukang
0.25 Kg
0.5 Liter
0.25 Kg

123,500

15,437.50

40,500

40,500.00

8,000

2,000.00

75,000

37,500.00

87,500

21,875.00
117,312.50

117,310.00

3.5 Detektor gangguan tanah/GFD


- Tukang
- YC.8513 ( M

1 Tukang
0.5 Kg

40,500

40,500.00

75,000

37,500.00
78,000.00

78,000.00

3.6 Pembersihan Ruangan Gardu


- Alat Vacum

1 Buah

13,000

- Bahan Bakar

1 Liter

2,600

13,000.00
2,600.00

- Instalator

1 Tukang

40,500

40,500.00
56,100.00

IV

PEKERJAAN LAIN - LAIN

4.1

Pemasangan Gardu Besi/Kios berikut Pondasi

Pekerjaan Pe

Pasang Boupl

Galian Tanah

1 Lokasi

130,000

130,000.00

8,398

142,766.00

9 m3

20,386

183,474.00

Urugan Pasir

0.5 m3

49,842

24,921.00

Pondasi Beton

4.6 m3

689,193

3,170,287.80

Pantek Pipa A

130,000

520,000.00

Plesteran 1:2

35 m2

10,738

375,830.00

Acian Beton

35 m2

4,420

154,700.00

Pasang Arde K

10 Kg

2,925

29,250.00

Beton Lantai

6 m2

23,375

140,250.00

17 Meter

4 Batang

56,100.00

Pekerjaan Stel Kios


- Pelaksana

Pembuangan t

1 Ten.Ahl.Md

123,500

123,500.00

2 Tukang

40,500

81,000.00

3 Pekerja

32,250

96,750.00

9 M3

21,125

190,125.00

Angkutan Truk dengan Kap.3.m3

5,362,853.80

5,362,850.00

2 Pemasangan Gardu Kios Compact berikut Pondasi


a

Pekerjaan Pe

1 Lokasi

Pasang Boupl

9 Meter

130,000

130,000.00

8,398

Galian Tanah

75,582.00

4.5 m3

7,878

Urugan Pasir

35,451.00

0.25 m3

49,842

12,460.50

Pondasi Beton

Pantek Pipa A

2.3 m3

689,193

1,585,143.90

130,000

Plesteran 1:2

520,000.00

18 m2

10,738

193,284.00

Acian Beton

18 m2

4,420

79,560.00

Pasang Arde K

10 Kg

2,925

29,250.00

Beton Lantai

3 m2

23,375

70,125.00

Pekerjaan Stel Kios


123,500

123,500.00

- Pelaksana

4 Batang

1 Ten.Ahl.Md
2 Tukang

40,500

81,000.00

6 Pekerja

32,250

193,500.00

112,500

98,437.50

Sewa Mobil C

0.88 Hari

Pembuangan t

4.5 Rit

Angkutan Truk dengan Kap.3 m3

0.00
3,227,293.90

3 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m


dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2)
4 Pengadaan Gardu Susun GRC 400 KVA Kososng (1,5x2,5x3,9)m
dan saluran kabel GRC 630 KVA Kosong (1,5x2,5x4,2)

3,227,290.00
39,000,000.00
650,000.00
43,225,000.00
650,000.00

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA


ANALISA HARGA SATUAN
PEKERJAAN SALURAN KABEL TEGANGAN RENDAH
Belum termasuk resiko, over head, keuntungan 10 % dan PPN 10 %
2004
NO.

URAIAN PEKERJAAN

1.

PEKERJAAN GALIAN, URUGAN DAN PEMADATAN

1.1

GALIAN URUGAN DAN PEMADATAN

HARGA

JUMLAH

JUMLAH

SATUAN

BIAYA

DIBULATKAN

(RUPIAH)

(RUPIAH)

(RUPIAH)

PADA TANAH BIASA / TANAH RUMPUT


a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

GALIAN TAN =

0.32 m3

20,386.15

6,523.57

URUGAN TAN=

0.24 m3

9,464.00

2,271.36

PEMADATAN =

0.40 m2

3,713.30

1,485.32
10,280.25

b.

3 Jalur (1,00 x 0,50 x 0,80 )


-

GALIAN TAN =

0.40 m3

20,386.15

8,154.46

URUGAN TAN=

0.30 m3

9,464.00

2,839.20

PEMADATAN =

0.50 m2

3,713.30

1,856.65
12,850.31

c.

4 Jalur (1,00 x 0,65 x 0,80 )


-

GALIAN TAN =

0.52 m3

20,386.15

10,600.80

URUGAN TAN=

0.39 m3

9,464.00

3,690.96

PEMADATAN =

0.65 m2

3,713.30

2,413.65
16,705.40

d.

GALIAN PENYUNTIKAN KABEL PADA


TANAH BIASA/TN.RUMPUT (1,50 x 0,50 x 0,80 )
-

GALIAN TAN =

0.60 m3

20,386.15

12,231.69

URUGAN TAN=

0.45 m3

9,464.00

4,258.80

PEMADATAN =

0.75 m2

3,713.30

2,784.98
19,275.47

e.

GALIAN LUBANG SAMBUNGAN PADA


TANAH BIASA/TN.RUMPUT
( 1 s/d 2 Jalur = 1,50 X 0,50 X 0,80 )
-

GALIAN TAN =

0.72 m3

20,386.15

14,678.03

URUGAN TAN=

0.45 m3

9,464.00

4,258.80

PEMADATAN =

0.75 m2

3,713.30

2,784.98
21,721.80

f.

GALIAN LUBANG SAMBUNGAN PADA


TANAH BIASA/TANAH RUMPUT
( 3 s/d 4 Jalur = 1,50 X 0,85 X 0,80 )
-

GALIAN TAN =

1.02 m3

20,386.15

20,793.87

URUGAN TAN=

0.77 m3

9,464.00

7,239.96

PEMADATAN =

1.28 m2

3,713.30

4,734.46
32,768.29

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA

TANAH BIASA/TANAH RUMPUT


(2,00 X 1,50 X 3,00 )
-

HS SAMA DENGAN HS SKTM

0.00

Catatan :
- Rp. 20.386,15 -HS.Sipil Hal.2-No.02
- Rp. 9.464, -HS.DKI Hal.2-TN.10
- Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 TN.24
1.2.

GALIAN URUGAN DAN PEMADATAN


PADA TANAH KERAS / TANAH KORAL

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

GALIAN TAN =

0.32 m3

24,233.23

7,754.63

URUGAN TAN=

0.24 m3

9,464.00

2,271.36

PEMADATAN =

0.40 m2

3,713.30

1,485.32
11,511.31

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

GALIAN TAN =

0.40 m3

24,233.23

9,693.29

URUGAN TAN=

0.30 m3

9,464.00

2,839.20

PEMADATAN =

0.50 m2

3,713.30

1,856.65
14,389.14

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

GALIAN TAN =

0.52 m3

24,233.23

12,601.28

URUGAN TAN=

0.39 m3

9,464.00

3,690.96

PEMADATAN =

0.65 m2

3,713.30

2,413.65
18,705.88

d.

GALIAN PENYUNTIKAN KABEL PADA


TANAH KERAS / KORAL
-

GALIAN TAN =

0.60 m3

24,233.23

14,539.94

URUGAN TAN=

0.45 m3

9,464.00

4,258.80

PEMADATAN =

0.75 m2

3,713.30

2,784.98
21,583.71

e.

GALIAN LUBANG SAMBUNGAN PADA


TANAH KERAS / KORAL
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

GALIAN TAN =

0.72 m3

24,233.23

URUGAN TAN=

0.54 m3

9,464.00

17,447.93
5,110.56

PEMADATAN =

0.90 m2

3,713.30

3,341.97
25,900.46

f.

GALIAN LUBANG SAMBUNGAN PADA


TANAH KERAS / KORAL
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

GALIAN TAN =

1.02 m3

24,233.23

24,717.89

URUGAN TAN=

0.77 m3

9,464.00

7,239.96

PEMADATAN =

1.28 m2

3,713.30

4,734.46
36,692.31

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA


TANAH KERAS / KORAL
( 2,00 x 1,50 x 3,00 )
-

HS SAMA DENGAN HS SKTM

0.00

Catatan :
- Rp. 24.233,23 HS.Sipil Hal.1 No.06
1.3.

GALIAN URUGAN DAN PEMADATAN


PADA CONBLOK / INTERBLOK

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

BONGKAR CO=

0.60 m2

1,600.20

960.12

GALIAN TAN =

0.30 m3

24,233.23

7,173.04

URUGAN TAN=

0.16 m3

9,464.00

1,514.24

PEMADATAN =

0.40 m2

3,713.30

1,485.32
11,132.72

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

BONGKAR CO=

0.70 m2

1,600.20

1,120.14

GALIAN TAN =

0.37 m3

24,233.23

8,966.30

URUGAN TAN=

0.20 m3

9,464.00

1,892.80

PEMADATAN =

0.50 m2

3,713.30

1,856.65
13,835.89

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

BONGKAR CO=

0.85 m2

1,600.20

1,360.17

GALIAN TAN =

0.48 m3

24,233.23

11,656.18

URUGAN TAN=

0.26 m3

9,464.00

2,460.64

PEMADATAN =

0.65 m2

3,713.30

2,413.65
17,890.64

d.

GALIAN PENYUNTIKAN KABEL PADA


CONBLOK / INTERBLOK ( 1,50 X 0,50 X 0,80 )
-

BONGKAR CO=

1.05 m2

1,600.20

1,680.21

GALIAN TAN =

0.56 m3

24,233.23

13,449.44

URUGAN TAN=

0.30 m3

9,464.00

2,839.20

PEMADATAN =

0.75 m2

3,713.30

2,784.98
20,753.83

e.

GALIAN LUBANG SAMBUNGAN PADA


CONBLOK / INTERBLOK ( 1,50 X 0,60 X 0,80 )
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

BONGKAR CO=

1.20 m2

1,600.20

1,920.24

GALIAN TAN =

0.67 m3

24,233.23

16,139.33

URUGAN TAN=

0.36 m3

9,464.00

3,407.04

PEMADATAN =

0.90 m2

3,713.30

3,341.97
24,808.58

f.

GALIAN LUBANG SAMBUNGAN PADA


CONBLOK / INTERBLOK ( 1,50 X 0,85 X 0,80 )
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

BONGKAR CO=

1.58 m2

1,600.20

2,520.32

GALIAN TAN =

0.94 m3

24,233.23

22,864.05

URUGAN TAN=

0.51 m3

9,464.00

4,826.64

PEMADATAN =

1.28 m2

3,713.30

4,734.46
34,945.47

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA


CONBLOK / INTERBLOK ( 1,50 X 0,85 X 0,80 )
( 2,00 x 1,50 x 3,00 )

HS SAMA DENGAN HS SKTM

0.00

Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
1.4.

GALIAN URUGAN DAN PEMADATAN


PADA UBIN BADAK / KERAMIK / FLOOR BETON BIASA

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

BONGKAR U.B
=

0.60 m2

1,600.20

960.12

GALIAN TAN =

0.29 m3

24,233.23

6,979.17

URUGAN TAN=

0.17 m3

9,464.00

1,571.02

PEMADATAN =

0.40 m2

3,713.30

1,485.32
10,995.63

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

BONGKAR U.B
=

0.70 m2

1,600.20

1,120.14

GALIAN TAN =

0.36 m3

24,233.23

8,723.96

URUGAN TAN=

0.21 m3

9,464.00

1,987.44

PEMADATAN =

0.50 m2

3,713.30

1,856.65
13,688.19

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

BONGKAR U.B
=

0.85 m2

1,600.20

1,360.17

GALIAN TAN =

0.47 m3

24,233.23

11,341.15

URUGAN TAN=

0.27 m3

9,464.00

2,583.67

PEMADATAN =

0.65 m2

3,713.30

2,413.65
17,698.64

d.

GALIAN PENYUNTIKAN KABEL PADA


UBIN BADAK / F.BETON BIASA ( 1,50 X 0,50 X 0,80 )
-

BONGKAR U.B
=

1.05 m2

1,600.20

1,680.21

GALIAN TAN =

0.54 m3

24,233.23

13,085.94

URUGAN TAN=

0.32 m3

9,464.00

2,981.16

PEMADATAN =

0.75 m2

3,713.30

2,784.98
20,532.29

e.

GALIAN LUBANG SAMBUNGAN PADA


UBIN BADAK / F.BETON BIASA
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

BONGKAR U.B
=

1.20 m2

1,600.20

1,920.24

GALIAN TAN =

0.65 m3

24,233.23

15,703.13

URUGAN TAN=

0.38 m3

9,464.00

3,577.39

PEMADATAN =

0.90 m2

3,713.30

3,341.97
24,542.74

f.

GALIAN LUBANG SAMBUNGAN PADA


UBIN BADAK / F.BETON BIASA
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

BONGKAR U.B
=

1.78 m2

1,600.20

2,840.36

GALIAN TAN =

0.92 m3

24,233.23

22,246.11

URUGAN TAN=

0.54 m3

9,464.00

5,067.97

PEMADATAN =

1.28 m2

3,713.30

4,734.46
34,888.89

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA


UBIN BADAK / F.BETON BIASA ( 2,00 x 1,50 x 3,00 )

HS SAMA DENGAN HARGA SKTM

0.00

Catatan :
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
1.5.

GALIAN URUGAN DAN PEMADATAN


PADA FLOOR BETON COR

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

BONGKAR F =

0.04 m2

212,815.30

8,938.24

GALIAN TAN =

0.29 m3

24,233.23

7,076.10

URUGAN TAN=

0.15 m3

9,464.00

1,438.53

PEMADATAN =

0.40 m2

3,713.30

1,485.32
18,938.19

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

BONGKAR F =

0.05 m2

212,815.30

10,427.95

GALIAN TAN =

0.37 m3

24,233.23

8,845.13

URUGAN TAN=

0.19 m3

9,464.00

1,798.16

PEMADATAN =

0.50 m2

3,713.30

1,856.65
22,927.89

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

BONGKAR F =

0.60 m2

212,815.30

126,625.10

GALIAN TAN =

0.47 m3

24,233.23

11,498.67

URUGAN TAN=

0.25 m3

9,464.00

2,337.61

PEMADATAN =

0.75 m2

3,713.30

2,784.98
143,246.35

d.

GALIAN PENYUNTIKAN KABEL PADA


FLOOR BETON COR ( 1,50 x 0,50 x 0,80 )
-

BONGKAR F =

0.07 m2

212,815.30

15,641.92

GALIAN TAN =

0.55 m3

24,233.23

13,267.69

URUGAN TAN=

0.29 m3

9,464.00

2,697.24

PEMADATAN =

0.75 m2

3,713.30

2,784.98
34,391.83

e.

GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON COR
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

BONGKAR F =

1.08 m2

212,815.30

230,691.79

GALIAN TAN =

0.66 m3

24,233.23

15,921.23

URUGAN TAN=

0.34 m3

9,464.00

3,236.69

PEMADATAN =

0.90 m2

3,713.30

3,341.97
253,191.68

f.

GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON COR
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

BONGKAR F =

0.11 m2

212,815.30

23,409.68

GALIAN TAN =

0.93 m3

24,233.23

22,553.87

URUGAN TAN=

0.48 m3

9,464.00

4,585.31

PEMADATAN =

1.28 m2

3,713.30

4,734.46
55,283.32

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA


FLOOR BETON COR ( 2,00 x 1,50 x 3,00 )

HS SAMA DENGAN HARGA SKTM

0.00

Catatan :
- Rp. 212.815,30-- HS.DKI hAL.33 - bkr.03
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
1.6.

GALIAN URUGAN DAN PEMADATAN


PADA FLOOR BETON BERTULANG

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

BONGKAR F =

0.01 m2

295,701.25

1,774.21

GALIAN TAN =

0.28 m3

24,233.23

6,785.30

URUGAN TAN=

0.16 m3

9,464.00

1,514.24

PEMADATAN =

0.40 m2

3,713.30

1,485.32
11,559.07

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

BONGKAR F =

0.01 m2

295,701.25

2,069.91

GALIAN TAN =

0.35 m3

24,233.23

8,481.63

URUGAN TAN=

0.20 m3

9,464.00

1,892.80

PEMADATAN =

0.50 m2

3,713.30

1,856.65
14,300.99

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

BONGKAR F =

0.09 m2

295,701.25

25,134.61

GALIAN TAN =

0.46 m3

24,233.23

11,026.12

URUGAN TAN=

0.26 m3

9,464.00

2,460.64

PEMADATAN =

0.65 m2

3,713.30

2,413.65
41,035.01

d.

GALIAN PENYUNTIKAN KABEL PADA


FLOOR BETON BERTULANG ( 1,50 x 0,50 x 0,80 )
-

BONGKAR F =

1.11 m2

295,701.25

326,749.88

GALIAN TAN =

0.53 m3

24,233.23

12,722.45

URUGAN TAN=

0.30 m3

9,464.00

2,839.20

PEMADATAN =

0.75 m2

3,713.30

2,784.98
345,096.50

e.

GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON BERTULANG
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

BONGKAR F =

1.12 m2

295,701.25

331,185.40

GALIAN TAN =

0.63 m3

24,233.23

15,266.93

URUGAN TAN=

0.36 m3

9,464.00

3,407.04

PEMADATAN =

0.90 m2

3,713.30

3,341.97
353,201.34

f.

GALIAN LUBANG SAMBUNGAN PADA


FLOOR BETON BERTULANG
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

BONGKAR F =

0.16 m2

295,701.25

46,572.95

GALIAN TAN =

0.89 m3

24,233.23

21,628.16

URUGAN TAN=

0.51 m3

9,464.00

4,826.64

PEMADATAN =

1.28 m2

3,713.30

4,734.46
77,762.20

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA

FLOOR BETON BERTULANG ( 2,00 x 1,50 x 3,00 )


HS SAMA DENGAN HARGA SKTM

0.00

Catatan :
- Rp. 295.701.25,- - HS.SIPIL Hal.36 - BKR.04
Pekerjaan Bongkar di tambah 10 Cm kiri dan kanan dari lebar galian
1.7.

GALIAN URUGAN DAN PEMADATAN


PADA A S P A L / H O T M I X

a.

1 s/d 2 jalur ( 1,00 x 0,40 x 0,80 )


-

BONGKAR AS=

0.40 m2

11,766.92

4,706.77

GALIAN TAN =

0.30 m3

40,751.00

12,225.30
16,932.07

b.

3 jalur ( 1,00 x 0,50 x 0,80 )


-

BONGKAR AS=

0.50 m2

11,766.92

5,883.46

GALIAN TAN =

0.38 m3

40,751.00

15,281.63
21,165.09

c.

4 jalur ( 1,00 x 0,65 x 0,80 )


-

BONGKAR AS=

0.65 m2

11,766.92

7,648.50

GALIAN TAN =

0.49 m3

40,751.00

19,866.11
27,514.61

d.

GALIAN PENYUNTIKAN KABEL PADA


ASPAL / HOTMIX ( 1,50 x 0,50 x 080 )
-

BONGKAR AS=

0.75 m2

11,766.92

8,825.19

GALIAN TAN =

0.56 m3

40,751.00

22,922.44
31,747.63

e.

GALIAN LUBANG SAMBUNGAN PADA


AS PAL / H OT M I X
( 1 s/d 2 jalur = 1,50 x 0,60 x 0,80 )
-

BONGKAR AS=

0.90 m2

11,766.92

10,590.23

GALIAN TAN =

0.68 m3

40,751.00

27,506.93
38,097.15

f.

GALIAN LUBANG SAMBUNGAN PADA


AS PAL / H OT M I X
( 3 s/d 4 jalur = 1,50 x 0,85 x 0,80 )
-

BONGKAR AS=

1.28 m2

11,766.92

15,002.82

GALIAN TAN =

0.96 m3

40,751.00

38,966.11
53,968.93

g.

GALIAN LUBANG PENGEBORAN MANUAL PADA


AS PAL / H OT M I X
-

1.8.

HS SAMA DENGAN HS SKTM

POMPONGAN
-

Pekerja

0.33 Pekerja

Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07
- Rp.40.751,- - HS Sipil Hal.2 No.07
2
2.1.

PENARIKAN , PENYAMBUNGAN DAN TERMINASI KABEL


Penarikan Kabel 4 x 16 S/D 50 mm2

32,250.00

10,750.00

10,750.00

Gelar Kabel / hari = 750 meter


-

Teknisi

1.00 orang

Mandor

1.00 Mandor

123,500.00
56,250.00

56,250.00

Pekerja

65.00 Pekerja

32,250.00

2,096,250.00

Rp.3.575,- --HS DKI Hal.33--BKR-09

123,500.00

2,276,000.00
750

2.2.

Penarikan Kabel 4 x 70 s/d 150 mm2

3,034.67

3,034.67

Gelar Kabel / hari = 600 meter


-

Tenaga Ahli Muda

1.00 Orang

123,500.00

Teknisi

1.00 Orang

56,250.00

123,500.00
56,250.00

Pekerja

65.00 Pekerja

32,250.00

2,096,250.00
2,276,000.00
600.00
3,793.33

2.3.

3,793.33

Penyambungan Kabel
-

Tenaga Ahli Muda

0.25 Orang

123,500.00

30,875.00

Tukang / Instalator

1.00 Tuk./ Ins

40,500.00

40,500.00

Pekerja

1.00 Pekerja

32,250.00

32,250.00
103,625.00

2.4.

Terminasi Kabel Indoor


-

Tenaga Ahli Muda

0.25 Orang

123,500.00

30,875.00

Tukang / Instalator

1.00 Tuk./ Ins

40,500.00

40,500.00

Pekerja

1.00 Pekerja

32,250.00

32,250.00
103,625.00

2.5.

Terminasi Kabel Outdoor


-

Tenaga Ahli Muda

0.25 Orang

123,500.00

30,875.00

Tukang / Instalator

1.00 Tuk./ Ins

40,500.00

40,500.00

Pekerja

2.00 Pekerja

32,250.00

64,500.00
135,875.00

3.

MATERIAL PELENGKAP BERIKUT PEMASANGAN


-

Keramik Tanda Peringatan Kabel PLN

845.00

850.00

Ukuran (22,5 x 30 x 4) Cm - Sertifikat LMK


-

Batu Merah

137.00

140.00

Pasir Urug Darat

49,959.00

49,960.00

Buis Beton O 20 Cm

11,102.00

11,100.00

Papan Penahan Tanah

PVC O 4" type AW

5,107.00

5,110.00

20,215.00

20,220.00

Catatan :
Rp. 5.107 = Rp.572.000,- (Harga Papan / M3)
4 x 28 lembar papan / M3
4.
4.1.

PENGEBORAN / CROSSING
Pengeboran dgn menggunakan Bor Manual/Hari dapat 8 M
-

Teknisi

1.00 Orang

56,250.00

Tukang Kayu

1.00 T.kayu

40,500.00

40,500.00

Pekerja

5.00 Pekerja

32,250.00

161,250.00

Papan penahan tanah (2x3x2) + (3x1,5x2)x2x0,03 =


572,000.00

720,720.00

3,250.00

39,000.00

2,600.00

2,600.00

(12 + 9) x 2 = =
-

Dolken 5/7

Paku

1.26 M3
12.00 Batang
1.00 Kg

56,250.00

258,000.00

1,020,320.00
8.00
4.2.

Pengeboran dengan menggunakan Mesin Khusus

Sesuai

127,540.00

127,540.00

Kontrak
5
5.1.

PERBAIKAN BEKAS GALIAN ( BERIKUT MATERIAL )


T.Biasa/T.Rumput (perbaikan/pemadatan sudah termasuk
dlm pek galian)

5.2.

T.Keras/Koral (perbaikan/pemadatan sudah termasuk


dlm pek galian)

5.3.

Conblok (Interblok) / M2

22,697.00

22,700.00

5.4.

Ubin Badak

26,707.00

26,710.00

5.5.

Floor Beton Biasa

14,053.00

14,050.00

5.6.

Floor Beton Cor

26,083.00

26,080.00

5.7.

Floor Beton Bertulang

75,200.00

75,200.00

5.8.

Shat Sheet

10,920.00

10,920.00

5.9.

Aspal Biasa / Penetrasi


Penetrasi tebal 5 Cm

13,314.00

13,314.00

Macadam tebal 20 Cm

17,186.00

17,186.00

Sirtu Tebal 30 Cm

16,190.00

16,190.00
46,690.00

5.10.

Hotmix tebal 3 Cm

12,517.00

12,517.00

3,188.00

3,188.00

Penetrasi tebal 5 Cm

13,314.00

13,314.00

Macadam 20 Cm

17,186.00

17,186.00

Sirtu 32 Cm

16,190.00

16,190.00

Tack Coating

62,395.00
5.11.

20,744.00

Tack Coating
Penetrasi tebal 5 Cm
Macadam 20 Cm
Sirtu 32 Cm

= 32/30

20,744.00

3,188.00

3,188.00

13,314.00

13,314.00

17,186.00

17,186.00

16,190.00

16,190.00
70,622.00

28,972.00

Tack Coating

28,972.00

3,188.00

3,188.00

Penetrasi tebal 5 Cm

13,314.00

13,314.00

Macadam 20 Cm

17,186.00

17,186.00

16,190.00

16,190.00

Sirtu 28 Cm

= 28/30

78,850.00

5.14.

70,620.00

Aspal Hotmix 7/5/20/28


Hotmix tebal 7 Cm

5.13.

62,390.00

Aspal Hotmix 5/5/20/28


Hotmix tebal 5 Cm

5.12.

46,690.00

Aspal Hotmix 3/5/20/32

78,850.00

Perbaikan Keramik
-

Pasang Keramik 10 x 20

1.00 m2

37,999.00

38,000.00

Pasang Keramik 20 x 20

1.00 m2

40,742.00

40,740.00

Pasang Keramik 30 x 20

1.00 m2

33,440.00

43,470.00

Perbaikan rumput disesuaikan dgn HS DKI/Pertanaman


( Dalam bestek biaya perbaikan rumput/taman tidak
dicantumkan dan akan dibayar sesuai realisasi berdasarkan
bukti yang dapat dipertanggung jawabkan ).

7880 - Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3


3445 - Rp. 11.139,9 =6xRp.1068-HS.DKI HAl.3
2140 - Rp. 20.386,15 -HS.Sipil Hal.2-No.02
- Rp. 30.579,- (300/200)x7878 HS. Sipil H
- Rp. 9.464, -HS.DKI Hal.2-TN.10

2136
4408.24
7878
11817
3445

- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07


- Rp.40.751,- - HS Sipil Hal.2 No.07
- Rp. 1.856.65 - HS.DKI Hal.3 TN.24

21093.75

42187.5

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA


ANALISA HARGA SATUAN
PEKERJAAN : SUTR DAN SAMBUNGAN LISTRIK
Belum Termasuk resiko, over head, keuntungan 10 % dan PPN 10 %
2004
HARGA
NO.

JENIS PEKERJAAN

1
1
1.1

BIAYA

SATUAN
2

JUMLAH
DIBULATKAN

(RUPIAH)

(RUPIAH)

(RUPIAH)

PENANAMAN TIANG BESI 9 METER


Tiang Besi 9 meter 200 daN
- Pengebora 0.33333333 Mandor

56,250.00

18,750.00

Mendirika 1.66666667 Tukang

40,500.00

67,500.00

0.33333333
1.66666667
86,250.00

1.2

Tiang Besi 9 meter 350 daN


- Pengebora 0.33333333 Mandor
Mendirika

2 Tukang

56,250.00

18,750.00

40,500.00

81,000.00

0.33333333
2
99,750.00

1.3

Tiang Besi 9 meter 500 daN


- Pengebora 0.33333333 Mandor
Mendirika

2 Tukang

56,250.00

18,750.00

40,500.00

81,000.00

0.33333333
2
99,750.00

1.4

Tiang Besi 9 meter 800 daN


- Pengebora 0.33333333 Mandor

56,250.00

18,750.00

Mendirika 2.66666667 Tukang

40,500.00

108,000.00

0.33333333
2.66666667
126,750.00

1.5

Tiang Besi 9 meter 1.200 daN


- Pengebora 0.33333333 Mandor

56,250.00

18,750.00

Mendirika 3.33333333 Tukang

40,500.00

135,000.00

0.33333333
3.33333333
153,750.00

PENGECATAN TIANG BESI 9 METER

2.1

Tiang Besi 9 3.175 m2

10,257.00

32,566.00

32,570.00

2.2

Tiang Besi 9 3.954 m2

10,257.00

40,556.00

40,560.00

2.3

Tiang Besi 9 4.376 m2

10,257.00

44,885.00

44,890.00

2.4

Tiang Besi 9 5.506 m2

10,257.00

56,475.00

56,480.00

2.5

Tiang Besi 9 6.423 m2

10,257.00

65,881.00

65,890.00

3
3.1

PENANAMAN TIANG BETON 9 METER


Tiang Beton 9 meter 200 daN
- Pengebora 0.33333333 Mandor

56,250.00

18,750.00

Mendirika 2.66666667 Tukang

40,500.00

108,000.00

0.33333333
2.66666667
126,750.00

3.2

Tiang beton 9 meter 350 daN


- Pengebora 0.33333333 Mandor

56,250.00

18,750.00

Mendirika 3.33333333 Tukang

40,500.00

135,000.00

0.33333333
3.33333333
153,750.00

3.3

Tiang beton 9 meter 500 daN


- Pengebora

0.5 Mandor

56,250.00

28,125.00

0.5

Mendirika

4 Tukang

40,500.00

162,000.00

4
190,125.00

3.4

Tiang beton 9 meter 800 daN


- Pengebora

0.5 Mandor

56,250.00

28,125.00

Mendirika

4.5 Tukang

40,500.00

182,250.00

0.5
4.5
210,375.00

3.5

Tiang beton 9 meter 1.200 daN


- Pengebora

0.5 Mandor

56,250.00

28,125.00

Mendirika

5 Tukang

40,500.00

202,500.00

0.5
5
230,625.00

4
4.1

PEMBUATAN PONDASI TIANG BESI/BETON 9 METER


Pondasi Tiang 9 meter Type A
- Galian Tan 0.60 m3

7,878.00

47,268.00

- Sirtu dipad 0.60 m3

89,842.00

29,905.00

- Beton Block0.03 m3

687,193.00

20,616.00

- Urugan Pasi0.03 m3

49,842.00

1,495.00
99,280.00

4.2

Ponsdasi Tiang 9 meter Type B


- Galian Tan 0.50 m3

7,878.00

3,939.00

- Beton Tumb0.38 m3

216,242.00

82,172.00

- Beton Block0.03 m3

687,193.00

20,616.00

- Urugan Pasi0.03 m3

49,842.00

1,495.00
108,220.00

4.3

Pondasi Tiang 9 meter Type C


- Galian Tan 0.60 m3

7,878.00

4,727.00

- Beton Tumb0.54 m3

216,242.00

116,771.00

- Beton Block0.03 m3

687,193.00

20,616.00

- Urugan Pasi0.03 m3

49,842.00

1,495.00
143,610.00

4.4

Pondasi Tiang 9 meter Type D


- Galian Tan 0.50 m3

7,878.00

3,939.00

- Beton Tumb0.38 m3

216,242.00

82,172.00

- Beton Block0.10 m3

687,193.00

68,719.00

- Urugan Pasi0.03 m3

49,842.00

1,495.00
156,330.00

4.5

Pondasi Tiang 9 meter Type E


- Galian Tan 0.60 m3

7,878.00

4,727.00

- Beton Tumb0.54 m3

216,242.00

116,771.00

- Beton Block0.20 m3

687,193.00

137,439.00

- Urugan Pasi0.03 m3

49,842.00

1,495.00
260,430.00

5
5.1

PEMASANGAN/PERBAIKAN KUTR
Pemasangan KUTR 4 Kawat BC 25/50 mm2
- Penarikan

0.5 Mandor

56,250.00

28,125.00

2 Tukang

40,500.00

81,000.00

1.5 Pekerja

32,250.00

48,375.00
157,500.00

5.2

Pemasangan Twisted Cable 3 x 35 s/d 70 mm2 + N


- Penarikan

0.33333333 Mandor

56,250.00

18,750.00

1.33333333 Tukang

40,500.00

54,000.00

1.33333333 Pekerja

32,250.00

43,000.00
115,750.00

5.3

Pemasangan SL 1 Phase Twisted/Kawat Udara


- Sambungan

0.25 Mandor

56,250.00

14,062.50

1 Tukang

40,500.00

40,500.00
54,562.50

5.4

Pemasangan SL 3 Phase Twisted/Kawat Udara


- Sambungan

0.5 Mandor

56,250.00

28,125.00

1 Tukang

40,500.00

40,500.00
68,625.00

5.5

Perbaikan K Sama dengan pasang

157,500.00

157,500.00

157,500.00

5.6

Perbaikan KUSama dengan pasang

115,750.00

115,750.00

115,750.00

5.7

Pemasangan / Montage Joint Sleve Uk.35 s/d 70 mm2 Set (4 Bh)


0.125 Mandor

56,250.00

7,031.25

0.125 Tukang

40,500.00

5,062.50
12,093.75

5.8

Pemasangan / Montage Conector Uk.35 s/d 70 mm2 Set (4 Bh)


0.0625 Mandor

56,250.00

3,515.63

0.125 Tukang

40,500.00

5,062.50
8,578.13

5.9

Pemasangan / Perbaikan Jumper SUTR/Phase (Buah)


- Mandor Pe 0.08333333 Mandor

56,250.00

4,687.50

- Tukang

0.08333333 Tukang

40,500.00

3,375.00

- Pekerja

0.08333333 Pekerja

32,250.00

2,687.50
10,750.00

5.10

Pemasangan Suspension Assemby (Set)


- Mandor Pe 0.08333333 Mandor

56,250.00

4,687.50

- Tukang

40,500.00

10,125.00

32,250.00

16,125.00

0.25 Tukang

- Pekerja

0.5 Pekerja

30,937.50
5.11

Pemasangan Dead End Essembly (Set)


- Mandor Pe 0.08333333 Mandor

56,250.00

4,687.50

- Tukang

0.33333333 Tukang

40,500.00

13,500.00

- Pekerja

0.66666667 Pekerja

32,250.00

21,500.00
39,687.50

5.12

Pemasangan Pelindung Listrik & Mekanik (Bundle end Protection)


- Mandor Pe 0.08333333 Mandor

56,250.00

4,687.50

- Tukang

40,500.00

10,125.00

32,250.00

16,125.00

- Pekerja

0.25 Tukang
0.5 Pekerja

30,937.50
5.13

Pemasangan/Penanaman Pipa Arde (1,5 inc per 1,5 mtr) perbatang


Pengadaan pip

0.25 Pemasangan

26,000.00

6,500.00

0.25 Pemasangan

50,718.00

12,680.00
19,180.00

5.14

Pemasangan Pipa Arde (1,5 inc) & (6) pengikat (3) dipipa (3) dikabel
0.25 Mandor

56,250.00

14,062.50

0.5 Tukang

40,500.00

20,250.00
34,312.50

5.15

Pemasangan Pipa Opstyg (2,5) & (6) pengikat (3) dipipa (3) dikabel

0.25 Mandor

56,250.00

14,062.50

0.5 Tukang

40,500.00

20,250.00
34,312.50

PERBAIKAN PONDASI DAN TIANG MIRING 9 METER


( BESI DAN BETON )

6.1

Pondasi Tiang 9 meter Type A


- Galian tan

0.42 m3

7,878.00

3,309.00

- Sirtu dipad 0.42 m3

49,842.00

20,934.00
24,240.00

6.2

Pondasi Tiang 9 meter Type B


- Galian tan

0.35 m3

7,878.00

2,727.00

- Beton tumb 0.27 m3

216,242.00

58,385.00
61,140.00

6.3

Pondasi Tiang 9 meter Type C


- Galian tan

0.42 m3

7,878.00

3,309.00

- Beton tumb 0.38 m3

216,242.00

82,172.00
85,480.00

6.4

Pondasi Tiang 9 meter Type D


- Galian tan

0.35 m3

7,878.00

2,752.00

- Beton tumb 0.27 m3

216,242.00

58,385.00
61,143.00

6.5

Pondasi Tiang 9 meter Type E


- Galian tan

0.42 m3

7,878.00

3,309.00

- Beton tumb 0.38 m3

216,242.00

82,172.00
85,480.00

PEMBONGKARAN TIANG BESI

7.1

Pembongkaran
Sama Dengan Pasang

86,250.00

86,250.00

86,250.00

7.2

Pembongkaran
Sama Dengan Pasang

99,750.00

99,750.00

99,750.00

7.3

Pembongkaran
Sama Dengan Pasang

99,750.00

99,750.00

99,750.00

7.4

Pembongkaran
Sama Dengan Pasang

126,750.00

126,750.00

126,750.00

7.5

Pembongkaran
Sama Dengan Pasang

153,750.00

153,750.00

153,750.00

7.6

Pembongkaran Drak Skur sama dengan pa 86,250.00

86,250.00

86,250.00

7.7

Pembongkaran Drak Skur sama dengan pasang arde KUTR

7.8

Bongkar Pasang Box SKTR

1 / 4 Pemasang
Panel Utama

26,000.00

6,500.00

1 Mandor

56,250.00

56,250.00

1 Tukang

40,500.00

40,500.00

1 Pekerja

32,250.00

32,250.00

0.5 Mandor

56,250.00

28,125.00

1 Tukang

40,500.00

40,500.00

1 Pekerja

32,250.00

32,250.00

6,500.00

129,000.00
7.9

Panel Pembag

100,875.00
8

PEMBONGKARAN TIANG BETON

8.1

Pembongkaran
Sama Dengan Pasang

126,750.00

126,750.00

126,750.00

8.2

Pembongkaran
Sama Dengan Pasang

153,750.00

153,750.00

153,750.00

8.3

Pembongkaran
Sama Dengan Pasang

190,125.00

190,125.00

190,125.00

8.4

Pembongkaran
Sama Dengan Pasang

210,375.00

210,375.00

210,375.00

8.5

Pembongkaran
Sama Dengan Pasang

230,625.00

230,625.00

230,625.00

PEMBONGKARAN KUTR

9.1

Kawat Udara Sama Dengan Pasang

157,500.00

157,500.00

157,500.00

9.2

Twisted kabel Sama Dengan Pasang

115,750.00

115,750.00

115,750.00

9.3

Pembongkara0.08333333 Mandor

56,250.00

4,687.50

8 Tukang

40,500.00

324,000.00
328,687.50

10

PERBAIKAN LISTRIK (SL)

10.1

SL 1 Phase Tw0.50

Pasang

18,644.00

9,347.00

9,350.00

10.2

SL 3 Phase Tw0.50

Pasang

24,375.00

12,188.00

12,190.00

11

PEMBONGKARAN 7 REHABILITASI SAMBUNGAN LISTRIK SL

11.1

SL 1 Phase Twisted / Kawat 1 Pasang

18,694.00

18,694.00

18,690.00

11.2

SL 3 Phase Twisted / Kawat 1 Pasang

24,375.00

24,375.00

24,380.00

11.3

Rehabilitasi SL 1 Phase akibat penggeseran tiang


9,347.00

9,350.00

- Pelaksana
12
12.1

1 / 2 Pasang

18,694.00

PEKERJAAN LAIN - LAIN


Menyetel KWH meter 1 phase pada tutup OK.I & memasang MCB
- Mandor Pe 0.04545455 Mandor

53,250.00

2,420.45

- Tukang

37,500.00

10,227.27

0.27272727 Tukang

12,647.73
12.2

Menyetel KWH meter 3 phase pada tutup OK.III & memasang MCB
1

0.2 Mandor

56,250.00

11,250.00

0.4 Tukang

40,500.00

16,200.00
27,450.00

12.3

Pemasangan APP Type Khusus I A


- Pelaksana

0.5 Mandor

56,250.00

28,125.00

1 Tukang

40,500.00

40,500.00
68,625.00

12.4

Pemasangan Box TR
- Galian Pon

0.41 m3

- Pondasi Ba

0.135 m3

- Pelaksana

7,878.00

3,230.00

201,578.00

27,213.00

0.5 Mandor

56,250.00

28,125.00

1 Tukang

40,500.00

40,500.00
99,068.00

12.5

Potong Cabang pohon dengan minimal dari hantaran


- Pekerjaan

0.33333333 Mandor

56,250.00

18,750.00

1 Tukang

40,500.00

40,500.00

1 Pekerja

32,250.00

32,250.00
91,500.00

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA


ANALISA HARGA SATUAN
PEKERJAAN SALURAN KABEL TEGANGAN MENENGAH
Biaya belum termasuk resiko,overhead,keuntungan 10% dan PPN 10%
2004

I
1

NO

URAIAN PEKERJAAN

01

02

HARGA

JUMLAH

JUMLAH

SATUAN

BIAYA

DIBULATKAN

(Rp.)

(Rp.)

(Rp.)

03

04

05

PEKERJAAN GALIAN-URUGAN DAN PEMADATAN


TANAH BIASA/TANAH RUMPUT
a 1 dan 2 jalur (1,00 x0,50 x 1,30 )
- Galian Tanah=

0.65 m3

20,386.15

13,251.00

- Urugan Tanah
=

0.4 m3

9,464.00

3,785.60

- Pemadatan =

0.4 m2

3,713.30

1,485.32
18,521.92

18,522

b 3 Jalur (1,00 x 0,60 x1,20)


- Galian Tanah=

0.72 m3

20,386.15

14,678.03

- Urugan Tanah
=

0.6 m3

9,464.00

5,678.40

- Pemadatan =

0.6 m2

3,713.30

2,227.98
22,584.41

22,584

c 4 Jalur (1,00
- Galian Tanah=

0.96 m3

20,386.15

19,570.70

- Urugan Tanah
=

0.8 m3

9,464.00

7,571.20

- Pemadatan =

0.8 m2

3,713.30

2,970.64
30,112.54

30,113

d 5 dan 6 Jalur
- Galian Tanah=

0.84 m3

20,386.15

17,124.37

- Urugan Tanah
=

0.6 m3

9,464.00

5,678.40

- Pemadatan =

0.6 m2

3,713.30

2,227.98
25,030.75

25,031

e 7 dan 8 Jalur (1,00 x 0,80 x1,40)


- Galian Tanah=

1.12 m3

20,386.15

22,832.49

- Urugan Tanah
=

0.8 m3

9,464.00

7,571.20

- Pemadatan =

0.8 m2

3,713.30

2,970.64
33,374.33

33,374

f 9 dan 10 Jalur (1,00 x 1,00 x1,40)


- Galian Tanah=

1.4 m3

20,386.15

28,540.61

- Urugan Tanah
=

1 m3

9,464.00

9,464.00

- Pemadatan =

1 m2

3,713.30

3,713.30
41,717.91

41,718

g 11 dan 12 Jalur (1,00 x 1,00 x1,40)


- Galian Tanah=

1.66 m3

20,386.15

33,841.01

- Urugan Tanah
=

0.2 m3

9,464.00

1,892.80

- Pemadatan =

0.2 m2

3,713.30

742.66
36,476.47

36,476

h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Galian Tanah=

1.6 m3

20,386.15

32,617.84

- Urugan Tanah
=

1 m3

9,464.00

9,464.00

- Pemadatan =

1 m2

3,713.30

3,713.30
45,795.14

45,795

i Penyuntikan Kabel (1,50 x 0,50 x 1,10 )


- Galian Tanah=

0.825 m3

20,386.15

16,818.57

- Urugan Tanah
=

0.75 m3

9,464.00

7,098.00

- Pemadatan =

0.75 m2

3,713.30

2,784.98
26,701.55

26,702

j Galian Lub.Sambungan 1 s/d 2 jalur(2,00x


- Galian Tanah=

3.12 m3

20,386.15

63,604.79

- Urugan Tanah
=

2.6 m3

9,464.00

24,606.40

- Pemadatan =

2.6 m2

3,713.30

9,654.58
97,865.77

97,866

k Galian Lub.Pengeboran Manual (2,00 x 1,


- Galian Tanah=

9 m3

30,579.00

275,211.00

- Urugan Tanah
=
- Pemadatan =

8.4 m3

9,464.00

79,497.60

3 m2

11,139.90

33,419.70
388,128.30

388,128

Catatan :
- Rp. 3.713,3 = 2xRp.1068-HS.DKI Hal.3 TN.24

2136

- Rp. 11.139,9 =6xRp.1068-HS.DKI HAl.3 TN.24

4408.24

- Rp. 20.386,15 -HS.Sipil Hal.2-No.02

7878

- Rp. 30.579,- (300/200)x7878 HS. Sipil Hal.2 No.02

11817

- Rp. 9.464, -HS.DKI Hal.2-TN.10


2

3445

TANAH KERAS/TANAH KORAL


a 1 dan 2 Jalur (1,00x0,50x1,30)
- Galian Tana =

0.65 m3

24,233.23

15,751.60

- Urugan Tana=

0.4 m3

9,464.00

3,785.60

- Pemadatan =

0.4 m2

3,713.30

1,485.32
21,022.52

21,022.52

b 3 Jalur (1,00x0,60x1,20)
- Galian Tana =

0.72 m3

24,233.23

17,447.93

- Urugan Tana=

0.6 m3

9,464.00

5,678.40

- Pemadatan =

0.6 m2

3,713.30

2,227.98
25,354.31

25,354.31

c 4 Jalur (1,00x0,80x1,20)
- Galian Tana =

0.96 m3

24,233.23

23,263.90

- Urugan Tana=

0.8 m3

9,464.00

7,571.20

- Pemadatan =

0.8 m2

3,713.30

2,970.64
33,805.74

33,805.74

d 5 dan 6 Jalur (1,00x0,60x1,20)


- Galian Tana =

0.84 m3

24,233.23

20,355.91

- Urugan Tana=

0.6 m3

9,464.00

5,678.40

- Pemadatan =

0.6 m2

3,713.30

2,227.98
28,262.29

e 7 dan 8 Jalur (1,00x0,80x1,40)


- Galian Tana =

1.12 m3

24,233.23

27,141.22

28,262.29

- Urugan Tana=

0.6 m3

9,464.00

- Pemadatan =

0.8 m2

3,713.30

5,678.40
2,970.64
35,790.26

35,790.26

f 9 dan 10 Jalur (1,00x100x1,40)


- Galian Tana =

1.4 m3

24,233.23

33,926.52

- Urugan Tana=

1 m3

9,464.00

9,464.00

- Pemadatan =

1 m2

3,713.30

3,713.30
47,103.82

47,103.82

g 11 dan 12 Jalur (1,00x1,20x1,40)


- Galian Tana =

1.68 m3

24,233.23

40,711.83

- Urugan Tana=

1.2 m3

9,464.00

11,356.80

- Pemadatan =

1.2 m2

3,713.30

4,455.96
56,524.59

56,524.59

h 13,14 dan 15 Jalur (1,00x1,00x1,60)


- Galian Tana =

1.6 m3

24,233.23

38,773.17

- Urugan Tana=

1 m3

9,464.00

9,464.00

- Pemadatan =

1 m2

3,713.30

3,713.30
51,950.47

51,950.47

i Penyuntikan Kabel (1,50x0,50x1,10)


- Galian Tana =

0.825 m3

24,233.23

19,992.41

- Urugan Tana=

0.75 m3

9,464.00

7,098.00

- Pemadatan =

0.75 m2

3,713.30

2,784.98
29,875.39

29,875.39

j Galian Lub. Sambungan 1s/d2 Jalur ( 2,00x1,30x1,20 )


- Galian Tana =

3.12 m3

24,233.23

75,607.68

- Urugan Tana=

2.6 m3

9,464.00

24,606.40

- Pemadatan =

2.6 m2

3,713.30

9,654.58
109,868.66

109,868.66

k Galian Lub. Pengeboran Manual ( 2,00x1,50x3,00 )


- Galian Tana =

9 m3

24,233.23

218,099.07

- Urugan Tana=

2.6 m3

9,464.00

24,606.40

- Pemadatan =

2.6 m2

3,713.30

9,654.58
252,360.05

252,360.05

l Galian Lub. Sambungan 1s/d2 Jalur ( 2,00x1,30x1,20 )


- Galian Tana =

3.12 m3

24,233.23

75,607.68

- Urugan Tana=

2.6 m3

9,464.00

24,606.40

- Pemadatan =

2.6 m2

3,713.30

9,654.58
109,868.66

109,868.66

m Galian Lub. Pengeboran Manual ( 2,00x1,50x300 )


- Galian Tana =

9 m3

36,349.84

327,148.56

- Urugan Tana=

8.4 m3

9,464.00

79,497.60

- Pemadatan =

3 m2

3,713.30

11,139.90
417,786.06

Catatan:
- Rp. 24.233,23 HS.Sipil Hal.1 No.06
- Rp. 36.349,84. 300/200xRp.10.504 HS. Sipil Hal.1-No.06
3

CONBLOCK/INTERBLOCK
a 1 dan 2 Jalur (1,00x0,40x1,20)
- Bongkar Con=

0.6 m2

1,600.20

960.12

417,786.06

- Galian Tana =

0.456 m3

24,233.23

11,050.35

- Urugan Tan =

0.32 m3

9,464.00

3,028.48

- Pemadatan =

0.4 m2

3,713.30

1,485.32
16,524.27

16,524.27

b 3 Jalur (1,00x0,60x1,20)
- Bongkar Con=

0.8 m2

1,600.20

1,280.16

- Galian Tana =

0.654 m3

24,233.23

15,848.53

- Urugan Tan =

0.48 m3

9,464.00

4,542.72

- Pemadatan =

0.6 m2

3,713.30

2,227.98
23,899.39

23,899.39

c 4 Jalur (1,00x0,80x1,20)
- Bongkar Con=

1 m2

1,600.20

1,600.20

- Galian Tana =

0.912 m3

24,233.23

22,100.71

- Urugan Tan =

0.64 m3

9,464.00

6,056.96

- Pemadatan =

0.8 m2

3,713.30

2,970.64
32,728.51

32,728.51

d 5 dan 6 Jalur (1,00x0,60x1,40)


- Bongkar Con=

0.8 m2

1,600.20

1,280.16

- Galian Tana =

0.804 m3

24,233.23

19,483.52

- Urugan Tan =

0.48 m3

9,464.00

4,542.72

- Pemadatan =

0.6 m2

3,713.30

2,227.98
27,534.38

27,534.38

e 7 dan 8 Jalur (1,00x0,80x1,40)


- Bongkar Con=

1 m2

1,600.20

1,600.20

- Galian Tana =

1.072 m3

24,233.23

25,978.02

- Urugan Tan =

0.64 m3

9,464.00

6,056.96

- Pemadatan =

0.8 m2

3,713.30

2,970.64
36,605.82

36,605.82

f 9 dan 10 Jalur (1,00x1,00x1,40)


- Bongkar Con=

1.2 m2

1,600.20

1,920.24

- Galian Tana =

1.34 m3

24,233.23

32,472.53

- Urugan Tan =

0.8 m3

9,464.00

7,571.20

- Pemadatan =

1 m2

3,713.30

3,713.30
45,677.27

45,677.27

g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)


- Bongkar Con=

1.4 m2

1,600.20

2,240.28

- Galian Tana =

1.608 m3

24,233.23

38,967.03

- Urugan Tan =

0.96 m3

9,464.00

9,085.44

- Pemadatan =

1.2 m2

3,713.30

4,455.96
54,748.71

54,748.71

h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Bongkar Con=

1.2 m2

1,600.20

1,920.24

- Galian Tana =

1.54 m3

24,233.23

37,319.17

- Urugan Tan =

0.8 m3

9,464.00

7,571.20

- Pemadatan =

1 m2

3,713.30

3,713.30
50,523.91

i Penyuntikan Kabel (1,50 x 0,50 x 1,10)


- Bongkar Con=

1.05 m2

1,600.20

1,680.21

- Galian Tana =

0.78 m3

24,233.23

18,901.92

- Urugan Tan =

0.63 m3

9,464.00

5,962.32

50,523.91

- Pemadatan =

0.75 m2

3,713.30

2,784.98
29,329.42

29,329.42

j Galian Lub.Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)


- Bongkar Con=

3 m2

1,600.20

4,800.60

- Galian Tana =

2.964 m3

24,233.23

71,827.29

- Urugan Tan =

2.444 m3

9,464.00

23,130.02

- Pemadatan =

2.6 m2

3,713.30

9,654.58
109,412.49

109,412.49

k Galian Lub.Pengeboran Manual (2,00 x 1,50 x 3,00)


- Bongkar Con=

3.4 m2

1,600.20

5,440.68

- Galian Tana =

8.82 m3

36,349.84

320,605.59

- Urugan Tan =

8.22 m3

9,464.00

77,794.08

- Pemadatan =

3 m2

3,713.30

11,139.90
414,980.25

414,980.25

Catatan :
- Rp. 1.600,2 --HS DKI Hal.38 BKR.59
- Pekerjaan bongkar di tambah 10 cm kiri dan kanan dari lebar
galian.
4

UBIN BADAK/KERAMIK/FLOOR BETON BIASA


a 1 dan 2 Jalur (1,00 x 0,40 x 1,20 )
- Bongkar Ubi =

0.6 m2

1,600.20

960.12

- Galian Tana =

0.446 m3

24,233.23

10,808.02

- Urugan Tan =

0.328 m3

9,464.00

3,104.19

- Pemadatan =

0.4 m2

3,713.30

1,485.32
16,357.65

16,357.65

b 3 Jalur (1,00 x 0,60 x 1,20 )


- Bongkar Ubi =

0.8 m2

1,600.20

1,280.16

- Galian Tana =

0.672 m3

24,233.23

16,284.73

- Urugan Tan =

0.492 m3

9,464.00

4,656.29

- Pemadatan =

0.6 m2

3,713.30

2,227.98
24,449.16

24,449.16

c 4 Jalur (1,00
- Bongkar Ubi =

1 m2

1,600.20

1,600.20

- Galian Tana =

0.896 m3

24,233.23

21,712.97

- Urugan Tan =

0.656 m3

9,464.00

6,208.38

- Pemadatan =

0.8 m2

3,713.30

2,970.64
32,492.20

32,492.20

d 5 dan 6 Jalur (1,00 x 0,60 x 1,40 )


- Bongkar Ubi =

0.8 m2

1,600.20

1,280.16

- Galian Tana =

0.792 m3

24,233.23

19,192.72

- Urugan Tan =

0.492 m3

9,464.00

4,656.29

- Pemadatan =

0.6 m2

3,713.30

2,227.98
27,357.15

27,357.15

e 7 dan 8 Jalur (1,00 x 0,80 x 1,40 )


- Bongkar Ubi =

1 m2

1,600.20

1,600.20

- Galian Tana =

1.056 m3

24,233.23

25,590.29

- Urugan Tan =

0.656 m3

9,464.00

6,208.38

- Pemadatan =

0.8 m2

3,713.30

2,970.64
36,369.51

f 9 dan 10 Jalur (1,00 x 1,00 x 1,40 )

36,369.51

- Bongkar Ubi =

1.2 m2

1,600.20

1,920.24

- Galian Tana =

1.32 m3

24,233.23

31,987.86

- Urugan Tan =

0.82 m3

9,464.00

7,760.48

- Pemadatan =

1 m2

3,713.30

3,713.30
45,381.88

45,381.88

g 11 dan 12 Jalur (1,00 x 1,20 x 1,40 )


- Bongkar Ubi =

1.4 m2

1,600.20

2,240.28

- Galian Tana =

1.584 m3

24,233.23

38,385.44

- Urugan Tan =

0.984 m3

9,464.00

9,312.58

- Pemadatan =

1.2 m2

3,713.30

4,455.96
54,394.25

54,394.25

h 13, 14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Bongkar Ubi =

1.2 m2

1,600.20

1,920.24

- Galian Tana =

1.52 m3

24,233.23

36,834.51

- Urugan Tan =

0.82 m3

9,464.00

7,760.48

- Pemadatan =

1 m2

3,713.30

3,713.30
50,228.53

50,228.53

i Penyuntikan Kabel (1,50 x 0,50 x 1,10)


- Bongkar Ubi =

1.05 m2

1,600.20

1,680.21

- Galian Tana =

0.765 m3

24,233.23

18,538.42

- Urugan Tan =

0.6525 m3

9,464.00

6,175.26

- Pemadatan =

0.75 m2

3,713.30

2,784.98
29,178.87

29,178.87

i Galian Lub. Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)


- Bongkar Ubi =

3 m2

1,600.20

4,800.60

- Galian Tana =

2.912 m3

24,233.23

70,567.17

- Urugan Tan =

2.522 m3

9,464.00

23,868.21

- Pemadatan =

2.6 m2

3,713.30

9,654.58
108,890.55

108,890.55

k Galian Lub. Pengeboran (2,00 x 1,50 x 3,00)


- Bongkar Ubi =

3.4 m2

1,600.20

5,440.68

- Galian Tana =

8.75 m3

36,349.84

318,061.10

- Urugan Tan =

8.31 m3

9,464.00

78,645.84

- Pemadatan =

3 m2

3,713.30

11,139.90
413,287.52

413,287.52

FLOOR BETON COR


a 1 dan 2 Jalur (1,00 x 0,40 x 1,20)
- Bongkar Flo =

0.042 m3

212,815.30

8,938.24

- Galian Tana =

0.452 m3

24,233.23

10,953.42

- Urugan Tan =

0.312 m3

9,464.00

2,952.77

- Pemadatan =

0.42 m2

3,713.30

1,559.59
24,404.02

24,404.02

b 3 Jalur (1,00
- Bongkar Flo =

0.056 m3

212,815.30

11,917.66

- Galian Tana =

0.678 m3

24,233.23

16,430.13

- Urugan Tan =

0.468 m3

9,464.00

4,429.15

- Pemadatan =

0.6 m2

3,713.30

2,227.98
35,004.92

c 4 Jalur (1,00 x 0,80 x 1,20)


- Bongkar Flo =

0.07 m3

212,815.30

14,897.07

35,004.92

- Galian Tana =

0.904 m3

24,233.23

21,906.84

- Urugan Tan =

0.624 m3

9,464.00

5,905.54

- Pemadatan =

0.8 m2

3,713.30

2,970.64
45,680.09

45,680.09

d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)


- Bongkar Flo =

0.056 m3

212,815.30

11,917.66

- Galian Tana =

0.798 m3

24,233.23

19,338.12

- Urugan Tan =

0.468 m3

9,464.00

4,429.15

- Pemadatan =

0.6 m2

3,713.30

2,227.98
37,912.91

37,912.91

e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)


- Bongkar Flo =

0.07 m3

212,815.30

14,897.07

- Galian Tana =

1.064 m3

24,233.23

25,784.16

- Urugan Tan =

0.624 m3

9,464.00

5,905.54

- Pemadatan =

0.8 m2

3,713.30

2,970.64
49,557.40

49,557.40

f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)


- Bongkar Flo =

0.084 m3

212,815.30

17,876.49

- Galian Tana =

1.33 m3

24,233.23

32,230.20

- Urugan Tan =

0.728 m3

9,464.00

6,889.79

- Pemadatan =

1 m2

3,713.30

3,713.30
60,709.77

60,709.77

g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)


- Bongkar Flo =

0.098 m3

212,815.30

20,855.90

- Galian Tana =

1.596 m3

24,233.23

38,676.24

- Urugan Tan =

0.936 m3

9,464.00

8,858.30

- Pemadatan =

1.2 m2

3,713.30

4,455.96
72,846.40

72,846.40

h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Bongkar Flo =

0.084 m3

212,815.30

17,876.49

- Galian Tana =

1.53 m3

24,233.23

37,076.84

- Urugan Tan =

0.78 m3

9,464.00

7,381.92

- Pemadatan =

1 m2

3,713.30

3,713.30
66,048.55

66,048.55

i Penyuntikan Kabel (1,50 x 0,50 x 1,10)


- Bongkar Flo =

0.0735 m3

212,815.30

15,641.92

- Galian Tana =

0.7725 m3

24,233.23

18,720.17

- Urugan Tan =

0.6225 m3

9,464.00

5,891.34

- Pemadatan =

0.75 m2

3,713.30

2,784.98
43,038.41

43,038.41

j Galian Lub. Sambungan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)


- Bongkar Flo =

0.21 m3

212,815.30

44,691.21

- Galian Tana =

2.938 m3

24,233.23

71,197.23

- Urugan Tan =

2.418 m3

9,464.00

22,883.95

- Pemadatan =

0.6 m2

3,713.30

2,227.98
141,000.37

k Galian Lub. Pengeboran Manual (2,00 x 1,50 x 3,00)


- Bongkar Flo =

0.238 m3

212,815.30

50,650.04

- Galian Tana =

8.79 m3

24,233.23

213,010.09

- Urugan Tan =

8.19 m3

9,464.00

77,510.16

141,000.37

- Pemadatan =

3 m2

3,713.30

11,139.90
352,310.19

352,310.19

Catatan :
- Rp. 212.815,30-- HS.DKI hAL.33 - bkr.03
6

79970

FLOOR BETON BERTULANG


a 1 dan 2 (1,00 x 0,40 x 1,20)
- Bongkar Flo =

0.06 m3

295,701.25

17,742.08

- Galian Tana =

0.44 m3

24,233.23

10,662.62

- Urugan Tan =

0.32 m3

9,464.00

3,028.48

- Pemadatan =

0.3 m2

3,713.30

1,113.99
32,547.17

32,547.17

b 3 Jalur (1,00 x 0,60 x 1,20)


- Bongkar Flo =

0.08 m3

295,701.25

23,656.10

- Galian Tana =

0.66 m3

24,233.23

15,993.93

- Urugan Tan =

0.48 m3

9,464.00

4,542.72

- Pemadatan =

0.6 m2

3,713.30

2,227.98
46,420.73

46,420.73

c 4 Jalur (1,00 x 0,80 x 1,20)


- Bongkar Flo =

0.1 m3

295,701.25

29,570.13

- Galian Tana =

0.88 m3

24,233.23

21,325.24

- Urugan Tan =

0.64 m3

9,464.00

6,056.96

- Pemadatan =

0.8 m2

3,713.30

2,970.64
59,922.97

59,922.97

d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)


- Bongkar Flo =

0.08 m3

295,701.25

23,656.10

- Galian Tana =

0.78 m3

24,233.23

18,901.92

- Urugan Tan =

0.48 m3

9,464.00

4,542.72

- Pemadatan =

0.6 m2

3,713.30

2,227.98
49,328.72

49,328.72

e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)


- Bongkar Flo =

0.1 m3

295,701.25

29,570.13

- Galian Tana =

1.04 m3

24,233.23

25,202.56

- Urugan Tan =

0.64 m3

9,464.00

6,056.96

- Pemadatan =

0.8 m2

3,713.30

2,970.64
63,800.28

63,800.28

f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)


- Bongkar Flo =

0.12 m3

295,701.25

35,484.15

- Galian Tana =

1.3 m3

24,233.23

31,503.20

- Urugan Tan =

0.8 m3

9,464.00

7,571.20

- Pemadatan =

1 m2

3,713.30

3,713.30
78,271.85

78,271.85

g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)


- Bongkar Flo =

0.14 m3

295,701.25

41,398.18

- Galian Tana =

1.56 m3

24,233.23

37,803.84

- Urugan Tan =

0.96 m3

9,464.00

9,085.44

- Pemadatan =

1.2 m2

3,713.30

4,455.96
92,743.41

h 13,14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Bongkar Flo =

0.12 m3

295,701.25

35,484.15

92,743.41

- Galian Tana =

1.5 m3

24,233.23

36,349.85

- Urugan Tan =

0.8 m3

9,464.00

7,571.20

- Pemadatan =

1 m2

3,713.30

3,713.30
83,118.50

83,118.50

i Penuntikan Kabel (1,50 x 0,50 x 1,10)


- Bongkar Flo =

0.105 m3

295,701.25

31,048.63

- Galian Tana =

0.75 m3

24,233.23

18,174.92

- Urugan Tan =

0.6 m3

9,464.00

5,678.40

- Pemadatan =

1.75 m2

3,713.30

6,498.28
61,400.23

61,400.23

j Galian Lub. Sumbangan 1 s/d 2 Jalur (2,00 x 1,30 x 1,20)


- Bongkar Flo =

0.3 m3

295,701.25

88,710.38

- Galian Tana =

2.86 m3

24,233.23

69,307.04

- Urugan Tan =

2.34 m3

9,464.00

22,145.76

- Pemadatan =

2.6 m2

3,713.30

9,654.58
189,817.75

189,817.75

k Galian Lub. Pengeboran Manual (2,00 x 1,50 x 3,00)


- Bongkar Flo =

0.34 m3

295,701.25

100,538.43

- Galian Tana =

8.7 m3

24,233.23

210,829.10

- Urugan Tan =

8.1 m3

9,464.00

76,658.40

- Pemadatan =

3 m2

3,713.30

11,139.90
399,165.83

399,165.83

Catatan :
- Rp. 295.701.25,- - HS.SIPIL Hal.36 - BKR.04
7

ASPAL BIASA/HOTMIX
a 1 dan 2 Jalur (1,00 x 1,40 x 1,20)
- Bongkar Asp=

0.4 m2

11,766.92

4,706.77

- Galian Tana =

0.26 m3

40,751.00

10,595.26

- Galian Tana =

0.2 m3

24,233.23

4,846.65

- Urugan Tan =

0.12 m3

9,464.00

1,135.68

- Pemadatan =

0.4 m2

1,856.65

742.66
22,027.01

22,027.01

b 3 Jalur (1,00 x 0,60 x 1,20)


- Bongkar Asp=

0.6 m2

11,766.92

7,060.15

- Galian Tana =

0.39 m3

40,751.00

15,892.89

- Galian Tana =

0.3 m3

24,233.23

7,269.97

- Urugan Tan =

0.18 m3

9,464.00

1,703.52

- Pemadatan =

0.6 m2

1,856.65

1,113.99
33,040.52

33,040.52

c 4 Jalur (1,00 x 0,80 x 1,20)


- Bongkar Asp=

0.8 m2

11,766.92

9,413.54

- Galian Tana =

0.52 m3

40,751.00

21,190.52

- Galian Tana =

0.4 m3

24,233.23

9,693.29

- Urugan Tan =

0.24 m3

9,464.00

2,271.36

- Pemadatan =

0.8 m2

1,856.65

1,485.32
44,054.03

d 5 dan 6 Jalur (1,00 x 0,60 x 1,40)


- Bongkar Asp=

0.6 m2

11,766.92

7,060.15

- Galian Tana =

0.39 m3

40,751.00

15,892.89

44,054.03

- Galian Tana =

0.42 m3

24,233.23

10,177.96

- Urugan Tan =

0.18 m3

9,464.00

1,703.52

- Pemadatan =

0.6 m2

1,856.65

1,113.99
35,948.51

35,948.51

e 7 dan 8 Jalur (1,00 x 0,80 x 1,40)


- Bongkar Asp=

0.8 m2

11,766.92

9,413.54

- Galian Tana =

0.52 m3

40,751.00

21,190.52

- Galian Tana =

0.56 m3

24,233.23

13,570.61

- Urugan Tan =

0.24 m3

9,464.00

2,271.36

- Pemadatan =

0.8 m2

1,856.65

1,485.32
47,931.34

47,931.34

f 9 dan 10 Jalur (1,00 x 1,00 x 1,40)


- Bongkar Asp=

1 m2

11,766.92

11,766.92

- Galian Tana =

0.65 m3

40,751.00

26,488.15

- Galian Tana =

0.7 m3

24,233.23

16,963.26

- Urugan Tan =

0.3 m3

9,464.00

2,839.20

- Pemadatan =

1 m2

1,856.65

1,856.65
59,914.18

59,914.18

g 11 dan 12 Jalur (1,00 x 1,20 x 1,40)


- Bongkar Asp=

1.2 m2

11,766.92

14,120.30

- Galian Tana =

0.78 m3

40,751.00

31,785.78

- Galian Tana =

0.84 m3

24,233.23

20,355.91

- Urugan Tan =

0.36 m3

9,464.00

3,407.04

- Pemadatan =

1.2 m2

1,856.65

2,227.98
71,897.02

71,897.02

h 13, 14 dan 15 Jalur (1,00 x 1,00 x 1,60)


- Bongkar Asp=

1 m2

11,766.92

11,766.92

- Galian Tana =

0.65 m3

40,751.00

26,488.15

- Galian Tana =

0.9 m3

24,233.23

21,809.91

- Urugan Tan =

0.3 m3

9,464.00

2,839.20

- Pemadatan =

1 m2

1,856.65

1,856.65
64,760.83

64,760.83

i Penyuntikan Kabel ( 1,50 x 0,50 x 1,10 )


- Bongkar Asp=

0.75 m2

11,766.92

8,825.19

- Galian Tana =

0.4875 m3

40,751.00

19,866.11

- Galian Tana =

0.3 m3

24,233.23

7,269.97

- Urugan Tan =

0.225 m3

9,464.00

2,129.40

- Pemadatan =

0.75 m2

1,856.65

1,392.49
39,483.16

39,483.16

j Galian Lub. Sambungan 1 s/d Jalur ( 2,00 x 1,30 x 1,20 )


- Bongkar Asp=

2.6 m2

11,766.92

30,593.99

- Galian Tana =

1.69 m3

40,751.00

68,869.19

- Galian Tana =

1.3 m3

24,233.23

31,503.20

- Urugan Tan =

0.78 m3

9,464.00

7,381.92

- Pemadatan =

2.6 m2

1,856.65

4,827.29
143,175.59

k Galian Lub. Pengeboran Manual ( 2,00 x 1,50 x 3,00 )


- Bongkar Asp=

3 m2

11,766.92

35,300.76

- Galian Tana =

1.95 m3

40,751.00

79,464.45

- Galian Tana =

6.9 m3

24,233.23

167,209.29

143,175.59

- Urugan Tan =

6.3 m3

9,464.00

- Pemadatan =

3 m2

1,856.65

59,623.20
5,569.95
347,167.65

347,167.65

10,750.00

10,750.00

POMPONGAN
- Pekerja

0.3

pekerja

32,250.00

Catatan :
- Rp.11.766.92,- - HS.DKI Hal.36 - BRK.07

3575

- Rp.40.751,- - HS Sipil Hal.2 No.07

15769

- Rp. 1.856.65 - HS.DKI Hal.3 TN.24

1068

II

PENARIKAN DAN PENYAMBUNGAN

1 a

Penarikan/Penggelaran Kabel 3 x 150 mm2


1 Hari / 8 Jam = 600 Meter
- Tenaga Ahl

1 Tenaga.Ah.Muda

- Teknisi

1 Teknisi

123,500.00
56,250.00

123,500.00
56,250.00

- Pekerja

75 Pekerja

32,250.00

2,418,750.00
2,598,500.00

Biaya Penggelaran Kabel / Meter

2.598.500 / 600

4,330.83

4,330.00

b Penarikan/Penggelaran Kabel 3 x 240 mm2


1 Hari / 8 Jam = 500 Meter
- Tenaga Ahl

1 Tenaga.Ah.Muda

- Teknisi

1 Teknisi

123,500.00
56,250.00

123,500.00
56,250.00

- Pekerja

75 Pekerja

32,250.00

2,418,750.00
2,598,500.00

Biaya Penggelaran Kabel / Meter

2.598,500 / 500

5,197.00

5,190.00

c Penarikan/Penggelaran Kabel 3 x 300 mm2


1 Hari / 8 Jam = 500 Meter
- Tenaga Ahl

1 Tenaga.Ah.Muda

123,500.00

123,500.00

- Teknisi

1 Teknisi

56,250.00

56,250.00

- Pekerja

75 Pekerja

32,250.00

2,418,750.00
2,598,500.00

Biaya Penggelaran Kabel / Meter


2

= 2.598.500 / 500

5,197.00

5,190.00

Penyambungan SKTM 20 KV 3 x 150 / 240 / 300 mm2


a Dengan Pola S / E
1 Hari / 6 Jam = 1 Set
- Tenaga Ahli

0.5 Tenaga.Ah.Muda

- Tukang

0.5 Tukang

123,500.00

61,750.00

40,500.00

20,250.00
82,000.00

- Supervisi

Pabrikan

174,750.00

Main Kontraktor 50%

169,375.00
426,125.00

Terminasi Kabel Indoor 20 KV 3 x 150,3 x 240,3 x 300 mm2


a Dengan Pola S / E
1 Hari / 4 Jam = 1 Set
- Tenaga Ahli

0.5 Tenaga.Ah.Muda

- Tukang

0.5 Tukang

123,500.00

61,750.00

40,500.00

20,250.00
82,000.00

- Supervisi

Pabrikan
Main Kontraktor 50%

174,750.00
169,375.00

426,125.00

426,125.00

426,125.00

b Terminasi Kabel Outdoor 20 KV 3 x 150,3 x 240,3 x 300 mm2


Dengan Pola S / E
1 Hari / 4 Jam = 1 Set
- Tenaga Ahli

0.5 Tenaga.Ah.Muda

- Tukang

0.5 Tukang

123,500.00

61,750.00

40,500.00

20,250.00
82,000.00

- Supervisi

Pabrikan

174,750.00

Main Kontraktor 50%

169,375.00
426,125.00

III

426,125.00

MATERIAL PELENGKAP
a Pengadaan dan Pemas.Patok Tanda Kabel 20 KV PLN
- Beton Bertulang 1:2:3

- Angkatan ( Rit )

0.012 m3
1/

687,193.00

8,246.00

65,000.00

1,625.00

40 Buah

9,871.00

9,870.00

b Pengadaan dan Pemasangan Tanda Mof Kabel 20 KV


- Beton Bertulang 1:2:3

- Angkatan ( Rit )

0.012 m3
1/

687,193.00

8,246.00

65,000.00

1,625.00

40 Buah

9,871.00
c Pengadaan & Pemasangan Batu Bata Merah ( 5x10x20 )

9,870.00
136.00

d Pengad. & Pemas.Timah Lebel Uk.(5cm x 25cm x 1,2mm)


- Harga Timah

= Rp.5.200.000/Ton

867.00

- 1 Ton timah Dpt = 6.000 buah Timah lebel


- Bahan timah
- Pekerja

= Rp.5.200.000/6.000 buah

- Angkutan ( Rit ) =

2/
1/

60 Buah

32,250.00

1,075.00

4,000 Buah

65,000.00

16,250.00
18,192.00

18,192.00

Catatan :
- Beton 1:2:3 / m3 (100 kg) Rp.687.193,- HS.SIPIL No.34
- Angkutan Rp. 65.000,-/Rit HS.DKI Hal.122 - 15007
- Rp.137,- (Harga Batu Bata Rp.130 + ongkos Pasang Rp.7,-)
e Pengad. & Pemasangan Keramik Tanda Peringan Kabe
- Bahan (0,225 x 0,30) + Produksi

449.00

449.00

- Biaya Penyusutan

104.00

104.00

- Angkutan dari pabrik ke lokasi pekerjaan

260.00

260.00

- Ongkos Pasang

98.00

(*) Catatan :

96.00
909.00

Sumber Analisa dan Pabrikan


f Pengadaan/pemasangan pasir urug darat sepanjang gal
dan lubang sambungan kabel 20 KV PLN.

49,959.00

g Pengad.&Pemas.pipa Buis Beton Konstruksi Khusus O 20cm/mtr

11,102.00

h Pengad.& Pemas.Pipa Pralon O 6 Insi type AW / meter

33,215.00

i Pengad.& Pemasangan Besi Kanal UNP 120.55.7 Double


- UNP .120.55.7 =

26.80 Kg/Mtr Double

j Pengad.& Pemasangan Besi Kanal UNP 140.60.7 Double

112,533.00

910.00

- UNP .140.60.7 =

32.00 Kg/Mtr Double

134,368.00

Catatan :
- Rp. 4.200,- Hs Sipil No.44
- Rp. 49.960,- Hs.Sipil No.7
- Rp. 11.100,- HS.Sipil No.50
- Rp. 33.220,- Hs.Sipil No.45
IV

PENGEBORAN CROSSING JALAN


a Crossing / Boring Manual
Boring Manual = 1 Hari = 8 meter
- Mandor

Mandor

56,250.00

- Tukang Kayu1

Tk.Kayu

40,500.00

40,500.00

- Pekerja

Pekerja

32,250.00

161,250.00

56,250.00

- Papan Pena 1.26

m3

572,000.00

720,720.00

- Dolken 5/7 12

batang

3,250.00

39,000.00

- Paku

kg

2,600.00

2,600.00
1,020,320.00

Harga Pengeboran

127,570.00

127,540.00

127,540.00

b Boring Mesin(Lihat HS.Boring Mesin/sesuai Kontrak)


c Ijin Boring Jalan Tol Jasa Marga (4 Jalur)

91,130.00

d Ijin Boring Rel Kereta Api/PJKA (Dalam Bestek sewa lahan


tidak dicantumkan dan akan di bayar sesuai realisasi
berdasarkan bukti yang dapat diPertanggungJawabkan

- Biaya Penguatan 1 Spoor

2,073,500.00

- Biaya Penguatan 2 Spoor

3,822,000.00

- Biaya Penguatan 3 Spoor

5,505,500.00

- Biaya Penguatan 4 Spoor

7,252,700.00

PERBAIKAN BEKAS GALIAN KABEL ( BERIKUT MATERIAL )


a Tanah Biasa/Tanah Rumput ( Pekerjaan Perbaikan/pemadatan
sudah termasuk dalan pekerjaan galian )
b Tanah Keras/Koral ( Pekerjaan perbaikan / pemadatan sudah
pekrjaan galian
c Conblock/Interblock
- Pengadaan Conblock/Interblock
640.00

9,594.00

- Ongkos Kerj =

Abu-abu se=

15 buah
1 m2

5,005.00

5,005.00

- Lapisan Pas =

1 m2

12,961.00

3,240.00

- Lapisan Sirt =

1 m2

16,189.00

(*) Rp. 640 = Rp. 31.980/50 buah

4,857.00
22,696.00

22,700.00

d Ubin Badak
- Ubin badak =

1 m2

26,707.00

Alas Pasir Tebal 5 cm

26,707.00
26,707.00

26,710.00

e Floor Beton Biasa


- Lap.F.Beton =

1.00 m2/(5/100)

216,242.00

- Lapisan Pas =

1.00 m2/(5/20)

12,961.00

10,812.10

0.05

3,240.25
14,052.35

0.25
14,052.35

Catatan : (*)
- Lapisan Pasir tebal 20 cm/m2 Rp.12.960 - HS.SKI Hal.36-LBJ.03
- Lapisan Sirtu tebal 30 cm/m2 Rp.16.190-HS.DKI Hal.25-LBJ.13
- Rp. 216.240,- Hs. Sipil No.136
- Rp. 233.750,- Hs. Sipil No. 27
- Rp. 687.190 - Hs. Sipil No. 34
- Rp. 26.710 Hs. DKI Lt.03 +LBJ.04(16.960 + 9.750)
- Rp. 572.000,- Hs.DKI Hal.108 - 3007
- Rp. 3.250,- Hs.DKI Hal.108 - 3034
- Rp. 2.600,- Hs.DKI Hal.118 - 12001
- Rp. 31.980,- Hs.DKI Hal. 31 - TBJ.04
- Rp. 5.000,- Hs.DKI Hal.31 - TBJ.04
f Floor Beton Cor
- Lap.Floor Bet=

1.00 m2/(7/100)

233,753.00

11,687.65

0.05

- Lapisan Pasir=

1.00 m2/(15/20)

12,961.00

9,720.75

0.75

21,408.40

21,408.40

g Beton Bertulang
- Lap.Floor C =

1.00 m2/(10/100)

687,193.00

68,719.30

- Lapisan Pasir=

1.00 m2/(10/20)

12,961.00

6,480.50

h Shand sheet =

1.00 m2

0.1
0.5

75,199.80

75,199.80

10,920.00

10,926.00

10,930.00

i Aspal Biasa/Penetrasi : 5/20/30


- Lapisan Pen=

1.00 m2

13,313.00

13,313.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2

16,190.00

16,190.00
46,689.00

46,700.00

j Aspal Hotmix : 5/5/20/30 ( Jalan kelas III )


- Lapisan Hot =

1.00 m2

20,744.00

- Lapisan teba=

1.00 m2

3,188.00

20,744.00
3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2

16,190.00

16,190.00
70,622.00

70,630.00

k Aspal Hotmix : 5/5/20/40 ( Jalan kelas II )


- Lapisan Hot =

1.00 m2

20,744.00

- Lapisan teba=

1.00 m2

3,188.00

20,744.00
3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2

22,024.00

22,024.00
76,456.00

l Aspal Hotmix : 5/5/20/70 ( Crossing Open Cut Jalan kelas II )


- Lapisan Hot =

1.00 m2

20,744.00

- Lapisan teba=

1.00 m2

3,188.00

20,744.00
3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2 (70/40)

22,024.00

38,541.00

76,460.00

92,973.00

92,980.00

m Aspal Hotmix : 7/5/20/40 ( Jalan kelas I )


- Lapisan Hot =

1.00 m2

28,972.00

- Lapisan teba=

1.00 m2

3,188.00

28,972.00
3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2

22,024.00

22,024.00
84,684.00

84,680.00

n Aspal Hotmix : 7/5/20/70 ( Crossing Open Cut Jalan kelas I )


- Lapisan Hot =

1.00 m2

28,972.00

- Lapisan teba=

1.00 m2

3,188.00

28,972.00
3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2 (70/40)

22,024.00

38,541.00
101,201.00

101,201.00

o Aspal Hotmix : 7/5/20/30 ( Jalan kelas IV )


- Lapisan Hot =

1.00 m2

12,517.00

12,517.00

- Lapisan teba=

1.00 m2

3,188.00

3,188.00

- Lapisan Pen=

1.00 m2

13,314.00

13,314.00

- Lapisan Ma =

1.00 m2

17,186.00

17,186.00

- Lapisan Sir =

1.00 m2

16,190.00

16,190.00
62,395.00

62,390.00

p Ubin Keramik
- Pasang Kera=

1.00 m2

37,999.00

37,999.00

38,000.00

- Pasang Kera=

1.00 m2

40,742.00

40,742.00

40,740.00

- Pasang Kera=

1.00 m2

43,472.00

43,472.00

43,470.00

q Rumput / Taman
- Perbaikan rumput/taman disesuaikan dengan HS.DKI/Pertamanan
( Dalam bestek biaya perbaikan rumput/taman tidak dicantumkan dan
akan dibayar sesuai realisasi berdasarkan bukti yang dapat

di

pertanggung jawabkan )
Catatan (*)
- Rp. 13.320 Hs.DKI hal.30 LAJ.04 - Rp. 12.520,21 Hs.DKI Hal.49
- Rp. 17.200 Hs.DKI hal.36 LBJ.07 - Rp. 20.745 Hs.DKI Hal.49

- Rp. 38.000 - HS.Sipil No.84

- Rp. 40740 - HS.Sipil No.80

- Rp. 10.920, - Hs.DKI hal.36 LBJ.17 - Rp. 28.970 Hs.DKI Hal.49

- Rp. 43.470 - HS.Sipil No.81

- Rp. 16.200 Hs.DKI hal.36 LBJ.13 - Rp. 22.025 Hs.DKI Hal.36 LBJ.14
- Rp. 3.200 - Hs.DKI hal.30 LBJ.07
VI

PERBAIKAN BEKAS GALIAN PADA LUB.SAMBUNGAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

VII

PERBAIKAN BEKAS GALIAN PADA LUB.PENGEBORAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

VIII

PERBAIKAN BEKAS GALIAN PADA LUB.PENYUNTIKAN


- HS. sama dengan HS. Perbaikan Bekas Galian Kabel

IX

PEKERJAAN LAIN-LAIN
a Pembuangan tanah bekas galian dengan truck kapasitas

21,125.00

21,130.00

32,250.00

32,250.00

32,250.00

64,500.00

3 s/d 4m3 jarak>20 Km (Volume yang di buang =Lebar galianx


(tinggi lapisan pasir urug + lapisan penutup galian)xpanjang
(trace galian)
b Penjagaan
- 1 Pekerja/Hari
c Penyediaan tenaga untuk bantu pengujian kabel TM PLN
- Pekerja

2 Pekerja

32,250.00

- Instalatir

2 Instalatir

13,000.00

26,000.00
90,500.00

90,500.00

d Pemasangan arrester 20 KV termasuk pentanahan


( Sama dengan HS.SUTM )

- Pmasangan arresterdan pengadaan dudukan arreter

118,872.00

- Pengadaan/Pemasangan pipa arde 0 1,5 inci - 6 mtr

76,713.00

118,872.00
76,713.00
195,585.00

195,585.00

BIAYA PENGURUSAN IJIN


1 Pemda DKI
a SPS BKJS ( Pengawasan,Perencanaan) 60% RAB perbaikan
b Q. Control pada hotmix/km 1,000/

100 x 1 Titik

58,570.00

585,700.00

585,700.00

c Q. Control pada hotmix/km 1,000/

100 x 1 Titik

10,790.00

107,900.00

107,900.00

75,660.00

151,320.00

151,320.00

501,260.00

501,260.00

501,260.00

130.00

130.00

130.00

65.00

65.00

65.00

65.00

65.00

d Proctor ( b + c )/ Km
e SPS.DTK ( Trace dan Gambar )
f Pengurusan
2 Diluar Pemda DKI dan Instalasi lain
a Biaya Restribusi
b Pengurusan
3

Perum Otorita Jatiluhur/ Pengairan


a Biaya sewa lahan (Dalam bestek sewa lahan tidak dicantumkan
dan akan dibayar sesuai realisasi berdasarkan bukti - bukti
yang dapat dipertanggungjawabkan)
b Pengurusan ke Jatiluhur Purwakarta

65.00

Catatan :
Rp- Rp 21.25,- HS.DKI hal.5-AG.11
XI

PENGANGKUTAN KABEL
1 Angkutan kabel TM./Meter

a Angkutan SKTM 10 - 50 meter

86,125.00

86,125.00

b Angkutan SKTM 50 - 100 meter

105,625.00

105,625.00

c Angkutan SKTM 100 - 200 meter

105,625.00

105,625.00

160,225.00

160,225.00

a Angkutan SKTM 1 Haspel

Angkutan kabel TM./ haspel

160,255.00

160,255.00

b Angkutan SKTM 2 Haspel

290,225.00

290,225.00

c Angkutan SKTM 3 Haspel


XII

DIREKSI KEET
a Pengdaan dan Pemasangan Diteksi Kett 2 x 4 meter = 8 m2
untuk pekerjaan dengan masa kerja :

- 1 s/d 30 HKL = 1/3 x 8 m2

148,772.00

396,725.00

396,725.00

- 31 s/d 180 HKL = 1/2 x 8 m2

148,772.00

595,088.00

595,088.00

- 181 s/d 360 HKL = 1/1 x m2

148,772.00

1,190,176.00

1,190,176.00

b Pengadaan dan Pemasangan Pagar dari seng


Gelombang ( 1,80 mtr/2 )
- Seng gelombang ( 180 x 90 x 0,2 ) = 2.00 lembar

11,050.00

22,100.00

- Kaso 5/7 = 2.50 batang

6,319.00

15,798.00

- Paku

= 0.06 KG.

2,600.00

156.00

- Cat

= 1.00 KG.

9,100.00

9,100.00

= 0.75

9,750.00

7,313.00

- Pekerja

- Tukang Kayu = 0.075

13,000.00

975.00
55,442.00

Harga pagar pengaman per meter = Rp. 72.45/1,80 = Rp.40.25,karena dianggap 3 kali pakai rusak maka harga pagar pengaman /meter
menjadi Rp.40.040/3
Catatan :
- HS. Angkutan kabel TM sesuai HS.Biaya Jasa Angkutan
- Rp. 193.400,- HS.Sipil No.143 - Rp.14.365,- HS.DKI Hal.118/11035
- 1/3 Direksi Keet dianggap 3 kali pakai Rp.11.830,- HS DKI Hal. 111/6001
- 1/2 Direksi Keet dianggap 2 kali pakai - Rp.2.600 HS.DKI Hal.118-12001
- Rp.8.215 = Rp.591.500/72 batang - HS.DKI Hal.108 - 3027
XIII

DOKUMENTASI
a Foto dokumentasi 2 x 36 lembar berwarna
- Film = 1 rool

10,400.00

- Cuci film = 1 roll


- Cetak 2 x 36 = 72 lembar

10,400.00

2,600.00

2,600.00

520.00

37,440.00
50,440.00

50,440.00

b Foto dokumentasi perlembar berwarna


- Film = 1 rool

10,400.00

- Cuci film = 1 roll


- Cetak 1 x 36 = 72 lembar

10,400.00

2,600.00

2,600.00

520.00

18,720.00
31,720.00

881.00

c As.build drawing 1 : 200 (1 kalkir + 5 blue print + 1 film )


Sesuai panjang galian, kanal dan crossing.
- Mengambar 1 km Trace
- Tenaga Ahli Muda (D - 2) = 2 jam/ 1 orang

11,089.00

22,178.00

- Petugas Survey (E - 5) = 8 jam/1 orang

9,620.00

76,960.00

- Pekerja = 2 Orang

9,750.00

19,500.00

- Tukang Gambar ( E - 5 ) = 32 Jam

9,620.00

307,840.00

- Kertas kalkir ukuran =

3,900.00

19,500.00

3,120.00

15,600.00

- Cetak Blue Print

0.30 x 5

= 5 lembar

- Cetak film Ukuran = 0.30 x 5

19,500.00

97,500.00
559,078.00

Biaya Menggambar / Meter = 559.078/1.000 =

559.00

d As.Build Drawing 1:5000 (1 kalkir + 5 blue print) print gambar spindle


- Tenaga Ahli Muda ( D - 2 ) = 1 jam /1 Orang

11,089.00

11,089.00

- Tukang Gambar (E - 5 ) = 16 Jam/1 Orang

9,620.00

153,920.00

559.00

13,000.00

13,000.00

- Kertas Kalkir Ukuran = 1 Meter

3,900.00

3,900.00

- Cetak Blue Print

1,950.00

9,750.00
191,659.00

Catatan (*)
- Rp.10.400,- Hs.DKI Hal.122 - 15001
- Rp.2.600,- Hs.DKI Hal.122 - 15002
- Rp.520,- Hs.DKI Hal.122 - 15003

191,659.00

0.65

0.72

5.835

0.825

3.12

3713.3
11139.9

0.65

1.5
14196
5569.5

9
14197.5

10504
15756

33585.72

0.072

0.096

0.06
0.44
0.32
0.39981273

0.03

10812.1

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA


ANALISA HARGA SATUAN
PEKERJAAN : SALURAN UDARA TEGANGAN MENENGAH
Belum termasuk resiko,over head,keuntungan 10% dan PPN 10%
2004
HARGA
NO URAIAN PEKERJAAN
1

PEKERJAAN PEMASANGAN

TIANG TUNGGAL

1.a

(Rp.)

(Rp.)

(Rp.)

1/3 Teknisi

56,250

18,750.00

2 Tukang

32,250

64,500.00

Tiang besi 11 meter 350 daN


-Mendirikan T

83,250.00

1/3 Teknisi

56,250

18,750.00

2 1/3 Tukang

32,250

75,250.00
94,000.00

1.c

1/2 Teknisi

56,250

28,125.00

3 1/2 Tukang

32,250

112,875.00
141,000.00

1/2 Teknisi

56,250

28,125.00

3 1/2 Tukang

32,250

112,875.00
141,000.00

1/2 Teknisi

56,250

28,125.00

4 Tukang

32,250

129,000.00
157,125.00

1/2 Teknisi

56,250

28,125.00

4 1/2 Tukang

32,250

145,125.00
173,250.00

157,120.00

173,250.00

Tiang beton 11 meter 350 daN


-Mendirikan T

1/2 Teknisi

56,250

28,125.00

5 1/2 Tukang

32,250

177,375.00
205,500.00

1.h

141,000.00

Tiang beton 11 meter 200 daN


-Mendirikan T

1.g

141,000.00

Tiang besi 13 meter 500 daN


-Mendirikan T

1.f

94,000.00

Tiang besi 13 meter 350 daN


-Mendirikan T

1.e

83,250.00

Tiang besi 11 meter 500 daN


-Mendirikan T

1.d

JUMLAH
DIBULATKAN

Tiang besi 11 meter 200 daN


-Mendirikan T

1.b

BIAYA

SATUAN

205,500.00

Tiang beton 11 meter 500 daN


Tiang beton 11 meter 350 daN
-Mendirikan T

1.i

1/2 Teknisi

56,250

28,125.00

6 Tukang

32,250

193,500.00

Tiang beton 11 meter 800 daN


-Mendirikan T

221,625.00

1/2 Teknisi

56,250

28,125.00

6 Tukang

32,250

193,500.00
221,625.00

1.j

Tiang beton 13 meter 350 daN


-Mendirikan T

1/2 Teknisi

56,250

28,125.00

7 Tukang

32,250

225,750.00

221,620.00

221,620.00

253,875.00
1.k

Tiang beton 13 meter 500 daN


-Mendirikan T

1/2 Teknisi

56,250

28,125.00

7 Tukang

32,250

225,750.00
253,875.00

253,870.00

253,870.00

PEMASANGAN TIANG BESI & BETON DOUBLE


( 2 X Biaya Pemasangan Tiang Tunggal )

3
3.a

PEMBUATAN PONDASI TIANG BESI & BETON


Pondasi Tiang 11 meter Type A

- Galian Tanah

- Galian tana

0.9 M3

20,386

18,347.54

- Urugan Tanah

- Sirtu dipada

0.67 M3

49,959

33,472.53

- Pemadatan

- Beton block

0.03 M3

687,193

20,615.79

- Urugan pasi

0.03 M3

49,959

1,498.77
73,934.63

3.b

- Galian tana

0.6 M3

20,386

12,231.69

- Beton Tumbu

0.47 M3

216,242

101,633.74

- Beton block

0.03 M3

687,193

20,615.79

- Urugan pasi

0.03 M3

49,959

1,498.77
135,979.99

3.c

- Galian tana

0.08 M3

20,386

1,630.89

- Beton Tumbu

0.67 M3

216,242

144,882.14

- Beton block

0.03 M3

687,193

20,615.79

- Urugan pasi

0.03 M3

49,959

1,498.77

0.8 M3

20,386

16,308.92

0.47 M3

216,242

101,633.74

- Beton block

0.1 M3

687,193

68,719.30

- Urugan pasi

0.03 M3

49,959

- Beton Tumbu

1,498.77
188,160.73

0.8 M3

20,386

16,308.92

0.67 M3

216,242

144,882.14

- Beton block

0.2 M3

687,193

137,438.60

- Urugan pasi

0.03 M3

49,959

- Beton Tumbu

1,498.77
300,128.43

290,120.00

Pondasi Tiang 13 meter Type A


- Galian tana

0.9 M3

20,386

18,347.54

- Beton Tumbu

0.78 M3

216,242

168,668.76

- Beton block

0.03 M3

687,193

20,615.79

- Urugan pasi

0.03 M3

49,959

1,498.77
209,130.86

3.g

188,160.00

Pondasi Tiang 11 meter Type E


- Galian tana

3.f

173,300.00

Pondasi Tiang 11 meter Type D


- Galian tana

3.e

135,970.00

Pondasi Tiang 11 meter Type C

168,627.59
3.d

73,930.00

Pondasi Tiang 11 meter Type B

Pondasi Tiang 13 meter Type B


- Galian tana
- Beton Tumbu

0.9 M3

20,386

18,347.54

0.54 M3

216,242

116,770.68

68,170.00

- Beton block

0.03 M3

687,193

- Urugan pasi

0.03 M3

49,959

20,615.79
1,498.77
157,232.78

3.h

- Galian tana

0.9 M3

20,386

18,347.54

- Beton Tumbu

0.78 M3

216,242

168,668.76

- Beton block

0.03 M3

687,193

20,615.79

- Urugan pasi

0.03 M3

49,959

1,498.77
209,130.86

3.i

0.9 M3

20,386

18,347.54

0.54 M3

216,242

116,770.68

- Beton block

0.1 M3

687,193

68,719.30

- Urugan pasi

0.03 M3

49,959

- Beton Tumbu

1,498.77
205,336.29

194,080.00

Pondasi Tiang 13 meter Type E


- Galian tana
- Beton Tumbu

0.9 M3

20,386

18,347.54

0.78 M3

216,242

168,668.76

- Beton block

0.2 M3

687,193

137,438.60

- Urugan pasi

0.03 M3

49,959

1,498.77
325,953.67

3.k

197,880.00

Pondasi Tiang 13 meter Type D


- Galian tana

3.j

145,980.00

Pondasi Tiang 13 meter Type C

314,700.00

PEMASANGAN TIANG BESI & BETON DOUBLE


( 2 X Biaya pemasangan Tiang Tunggal )

PEKERJAAN PENGECATAN TIANG BESI ( Pek. Pemeliharaan )

4.a

Tiang Besi 11 Meter 200 da 5.09 M2

10,257

52,208.00

52,210.00

4.b

Tiang Besi 11 Meter 350 da 5.48 M2

10,257

56,208.00

56,210.00

4.c

Tiang Besi 11 Meter 500 da 5.84 M2

10,257

59,901.00

59,900.00

4.d

Tiang Besi 11 Meter 800 da 6.99 M2

10,257

71,696.00

71,700.00

4.e

Tiang Besi 11 Meter 1200

10,257

85,236.00

85,240.00

4.f

Tiang Besi 11 Meter 200 d 10.18 M2

10,257

104,416.00

104,420.00

4.g

Tiang Besi 11 Meter 200 d 10.96 M2

10,257

112,417.00

112,420.00

4.h

Tiang Besi 11 Meter 200 d 11.68 M2

10,257

119,802.00

119,800.00

4.i

Tiang Besi 13 Meter 200 da 6.17 M2

10,257

63,286.00

63,290.00

4.j

Tiang Besi 13 Meter 350 da 6.88 M2

10,257

70,568.00

70,570.00

4.k

Tiang Besi 13 Meter 500 da 8.68 M2

10,257

68,517.00

68,520.00

4.l

Tiang Besi 13 Meter 800 da 8.50 M2

10,257

87,185.00

87,190.00

4.m

Tiang Besi 13 Meter 1200

10.12 M2

10,257

103,801.00

103,800.00

4.n

Tiang Besi 13 Meter 200 d 12.34 M2

10,257

126,571.00

126,570.00

4.o

Tiang Besi 13 Meter 350 d 13.76 M2

10,257

141,136.00

141,140.00

4.p

Tiang Besi 13 Meter 500 d 17.36 M2

10,257

178,062.00

178,060.00

5
5.a

8.31 M2

PEMASANGAN / PENGADAAN TRAVERS


Travers tunggal: UNP 12-1800 mm
- Pemasangan
- Pengadaan

1/12 Teknisi

56,250

4,687.50

2/ 3 Tukang

40,500

27,000.00

1 Buah

39,000

39,000.00
70,687.50

5.b

Travers tunggal: UNP 12-2200 mm


- Pemasangan

1/ 6 Teknisi

56,250

9,375.00

70,680.00

1 1/ 2 Tukang
- Pengadaan

1 Buah

40,500
49,634

60,750.00
49,634.00
119,759.00

5.c

- Pemasangan
- Pengadaan

1/ 6 Teknisi

56,250

9,375.00

1 1/ 2 Tukang

40,500

60,750.00

1 Buah

54,600

54,600.00
124,725.00

5.d

1/12 Teknisi

56,250

4,687.50

1/ 4 Tukang

40,500

10,125.00

1/ 2 Pekerja

32,250

16,125.00

1/12 Teknisi

56,250

4,687.50

1/ 3 Tukang

40,500

13,500.00

2/ 3 Pekerja

32,250

21,500.00

1/12 Teknisi

56,250

4,687.50

1/ 3 Tukang

40,500

13,500.00

1/ 2 Pekerja

32,250

16,125.00

1/12 Teknisi

56,250

4,687.50

1/ 3 Tukang

40,500

13,500.00

1/ 2 Pekerja

32,250

16,125.00

1/10 Teknisi

56,250

5,625.00

1/10 Tukang

40,500

4,050.00
9,675.00

1/ 8 Teknisi

56,250

1/ 8 Tukang

40,500

7,031.25
5,062.50
12,093.75

1 Teknisi

56,250

56,250.00

6 Tukang

40,500

243,000.00

2 Pekerja

32,250

64,500.00
363,750.00

PEMASANGAN PIPA ARDE (1,5 Inc per 6 m

26,000

26,000.00

PENGADAAN PIPA ARDE (1,5 Inc per 6 mt

50,718

50,718.00
76,718.00

10
10.a

12,090.00

PEMASANGAN POLE TOP SWITCH


- Pemasangan

9,670.00

PEMASANGAN HANG ISOLATOR


- Pemasangan

34,310.00

PEMASANGAN PIN ISOLATOR


- Pemasangan

34,310.00

Pemasangan Daed End Assembly

34,312.50
6

39,680.00

Pemasangan Large Angle Assembly

34,312.50
5.g

30,930.00

Pemasangan Small Angle Assembly

39,687.50
5.f

124,720.00

Pemasangan Suspensi Assembly

30,937.50
5.e

119,750.00

Travers tunggal: UNP 12-2400 mm

PENARIKAN KAWAT HANTARAN/Gawang (Jarak Mx.40 m)


Kawat A3C 3 x 35 s/d 150 mm2
- Penarikan

1/ 3 Teknisi

56,250

18,750.00

2 Tukang

40,500

81,000.00

363,750.00

76,720.00

1 1/ 3 Pekerja

32,250

43,000.00
142,750.00

10.b

- Penarikan

1/ 2 Teknisi

56,250

28,125.00

3 Tukang

40,500

121,500.00

2 Pekerja

32,250

64,500.00
214,125.00

10.c

142,750.00

Kawat A3C 3 x 35 s/d 150 mm2

214,120.00

SUTM Twisted Kabel 20 kV


- Penarikan

1/ 2 Teknisi

56,250

28,125.00

4 Tukang

40,500

162,000.00

5 Pekerja

32,250

161,250.00
351,375.00

10.d

Pemasangan Terminal Outdoor 150 S/D 300 mm2/Set(=HS.SKTM)

10.e

Pemasangan Kawat Pengikat Hantaran Isolator


1/10 Tukang

40,500

4,050.00

351,370.00
187,343.00

4,050.00

11 PEMASANGAN JUMPE /PHASE


- Mandor Pengaw

1/12 Teknisi

56,250

4,687.50

- Tukang

1/12 Tukang

40,500

3,375.00

- Pekerja

1/12 Pekerja

32,250

2,687.50
10,750.00

10,750.00

12 PEMASANGAN LBS TIANG SUTM


- Tenaga Ahli

- Sewa Crane

1/ 2 Hari

112,500

56,250.00

4 Tukang

40,500

162,000.00

2 Pekerja

32,250

64,500.00

6 Jam

39,000

234,000.00
516,750.00

516,750.00

13 PENGADAAN DAN PEMASANGAN TANDA KILAT 20MKV


( 20 cm X 30 cm ), Tebal Plat 4mm
- Pengadaan

11,050

- Ongkos pasang

11,050.00

1,950

1,950.00
13,000.00

13,000.00

14 PENGADAAN DAN PEMASANGAN PENGHALANG PANJAT


- Pengadaan

29,445

- Ongkos pasang

29,445.00

1,950

1,950.00

- Pengelasan + Bahan

31,395.00

31,400.00

15 PEMASANGAN ARRESTER DAN PENGADAAN DUDUKAN


- Tenaga Ahli

112,500

14,062.50

- Tukang

1 Tukang

40,500

40,500.00

- Pekerja

1/ 2 Pekerja

32,250

16,125.00

1 set

56,628

56,628.00

1/ 2 Rit

65,000

- Dudukan Arr
- Angkutan

1/ 8 Hari

32,500.00
159,815.50

16 PEMASANGAN CUT OUT DAN PENGADAAN DUDUKAN


- Tenaga Ahli

112,500

14,062.50

- Tukang

1 Tukang

40,500

40,500.00

- Pekerja

1/ 2 Pekerja

32,250

16,125.00

1 set

56,628

56,628.00

1/ 2 Rit

65,000

32,500.00

- Dudukan Arr
- Angkutan

1/ 8 Hari

159,810.00

159,815.50
16A

159,810.00

PEMASANGAN TREE GUARD 1 GAWANG


- Teknisi

1/ 3 Teknisi

56,250

18,750.00

- Instalator

1 1/ 3 Tukang

40,500

54,000.00

- Pekerja

1 1/ 3 Pekerja

32,250

43,000.00
115,750.00

115,750.00

17 PEMELIHARAAN JARINGAN
- Majun

1/ 4 Kg

8,000

2,000.00

- YC 8513 ty

1/ 2 Ltr

75,000

37,500.00

- Pasline

1/ 4 Kg

87,500

21,875.00

- Mandor Pe

1/ 2 Teknisi

56,250

28,125.00

- Angkutan

1/ 2 Rit

65,000

32,500.00
122,000.00

122,000.00

18 PEMELIHARAAN CUT OUT


- Majun

1/25 Kg

8,000

320.00

- YC 8513 ty

3/10 Ltr

75,000

22,500.00

- Pasline

1/ 4 Kg

87,500

21,875.00

- Mandor Pe

1/ 3 Teknisi

56,250

18,750.00

- Angkutan

1/ 3 Rit

65,000

21,666.67
85,111.67

85,110.00

19 PEMELIHARAAN GARDY/BOX SEKERING


- Majun

1/ 4 Kg

8,000

2,000.00

- YC 8513 ty

1/ 2 Ltr

75,000

37,500.00

- Pasline

1/ 4 Kg

87,500

21,875.00

- Mandor Pe

1/ 2 Teknisi

56,250

28,125.00

- Angkutan

1/ 2 Rit

65,000

32,500.00
122,000.00

122,000.00

20 PEMELIHARAAN RAK TR PADA GARDU PORTAL


- Majun

1/ 4 Kg

8,000

2,000.00

-Spirtus

1/ 2 Ltr

7,150

3,575.00

- Pasline

1/ 4 Kg

87,500

21,875.00

- Mandor Pengawa

1/ 2 Teknisi

56,250

28,125.00

- Tukang

2 Tukang

40,500

81,000.00

- Pekerja

2 Pekerja

32,250

64,500.00
201,075.00

201,070.00

21 PEMELIHARAAN LBS di SUTM


- Majun

1/ 4 Kg

8,000

2,000.00

- YC 8513 ty

1/ 2 Ltr

75,000

37,500.00

- Pasline

1/ 4 Kg

87,500

21,875.00

- Mandor Pengawa

1/ 2 Teknisi

56,250

28,125.00

- Tukang

1/ 2 Tukang

40,500

20,250.00

- Pekerja

1/ 2 Pekerja

32,250

16,125.00
125,875.00

125,870.00

22 PENGADAAN DAN PEMASANGAN NOMOR GARDU


- Pengadaan
- Ongkos Pasang

26,936

26,936.00

1,950

1,950.00
28,886.00

II

PEKERJAAN PEMBONGKARAN

PEMBONGKARAN TIANG BESI DAN BETON

28,890.00

( sama dengan biaya pemasangan )


2

PEMBONGKARAN TIANG BESI DAN BET sama dengan pemas tiang


DOUBLE ( sama dengan biaya pemasang double yang sesuai ukuran

PEMBONGKARAN LBS TIANG SUTM ( sama


sama dgn by pemasangan

PEMBONGKARAN ARRESTER

20,580.00

- Mandor Pengawa

1/ 6 Teknisi

56,250

9,375.00

- Tukang

1/ 3 Tukang

40,500

13,500.00

- Pekerja

1/ 6 Pekerja

32,250

5,375.00

- Angkutan

1/ 6 Rit

65,000

10,833.33
39,083.33

- Mandor Pengawa

1/ 6 Teknisi

56,250

9,375.00

- Tukang

1/ 3 Tukang

40,500

13,500.00

- Pekerja

1/ 6 Pekerja

32,250

5,375.00

- Angkutan

1/ 6 Rit

65,000

10,833.33
39,083.33

1/ 2 Teknisi

56,250

28,125.00

- Tukang

2 Tukang

40,500

81,000.00

- Pekerja

1 Pekerja

32,250

32,250.00
141,375.00

PENGISIAN

1/ 2 Teknisi

56,250

28,125.00

1/ 2 Tukang

40,500

20,250.00

1/ 4 Pekerja

32,250

PEMBONGKA

141,370.00

8,062.50
56,437.50

39,080.00

PEMBONGKARAN RAK TR PADA GARDU PORTAL


- Mandor Pe

39,080.00

PEMBONGKARAN CUT OUT

1/ 2 Teknisi

56,250

28,125.00

1/ 2 Tukang

40,500

20,250.00

1/ 4 Pekerja

32,250

56,430.00

8,062.50
56,437.50

56,430.00

Bongkar PIN ISOLATOR

= biaya pasang

3,575

4,290.00

4,290.00

10

Bonkar HANG ISOLATOR = Biaya pasang

4,472

5,366.00

5,370.00

11

Bongkar Arde

=Biaya pas

76,713

92,056.00

92,060.00

12

Bongkar Pole Top Switch

= Biaya pasan

132,860

159,432.00

159,430.00

13

Bongkar SUTM A3C

= Biaya Pasan

46,579

55,895.00

55,900.00

14

Bongkar SUTM A3CS

= Biaya Pasan

71,500

85,800.00

85,800.00

15

Bongkar SUTM Twisted

= Biaya Pasan

122,125

134,550.00

134,550.00

III.

PEKERJAAN PERBAIKAN

PERBAIKAN TIANG BESI/BETON MIRING


BERIKUT PONDASI

1.a

Pondasi Tiang 11 meter Type A


- Galian tana

0.63 m3

20,386

12,843.27

- Sirtu dipada

0.55 m3

49,959

27,477.45
40,320.72

40,320.00

1.b

Pondasi Tiang 11 meter Type B


- Galian tana

0.55 m3

20,386

11,212.38

- Beton Tumbu

0.33 m3

216,242

71,359.86
82,572.24

1.c

- Galian tana

0.65 m3

20,386

13,251.00

- Beton Tumbu

0.47 m3

216,242

101,633.74
114,884.74

1.d

- Galian tana

0.56 m3

20,386

11,416.24

- Beton Tumbu

0.33 m3

216,242

71,359.86

- Galian tana

0.56 m3

20,386

11,416.24

- Beton Tumbu

0.47 m3

216,242

101,633.74

- Galian tana

0.63 m3

20,386

12,843.27

- Sirtu dipada

0.55 m3

49,959

27,477.45

- Galian tana

0.42 m3

20,386

8,562.18

- Beton Tumbu

0.38 m3

216,242

82,171.96

- Galian tana

0.63 m3

20,386

- Beton Tumbu

0.55 m3

216,242

12,843.27
118,933.10

131,770.00

Pondasi Tiang 13 meter Type D


- Galian tana

0.63 m3

20,386

12,843.27

- Beton Tumbu

0.38 m3

216,242

82,171.96
95,015.23

1.j

90,730.00

Pondasi Tiang 13 meter Type C

131,776.37
1.i

40,320.00

Pondasi Tiang 13 meter Type B

90,734.14
1.h

113,040.00

Pondasi Tiang 13 meter Type A

40,320.72
1.g

82,770.00

Pondasi Tiang 11 meter Type E

113,049.98
1.f

114,880.00

Pondasi Tiang 11 meter Type D

82,776.10
1.e

82,570.00

Pondasi Tiang 11 meter Type C

95,010.00

Pondasi Tiang 13 meter Type E


- Galian tana

0.56 m3

20,386

11,416.24

- Beton Tumbu

0.47 m3

216,242

101,633.74
113,049.98

113,040.00

PERBAIKAN KAWAT KENDOR A3C 3x35 s/d 150 mm2


( 3 Hantaran )

-Perbaikan 1 s/d 5 Gawang 1.2 Pasang

46,579

55,895.00

55,900.00

-Perbaikan 6 s/d 10 Gawan 1.1 Pasang

46,579

55,895.00

55,900.00

PERBAIKAN KAWAT KENDOR A3C3 3x35 s/d 150 mm2


( 3 hantaran )

- Perbaikan 1 s/d 5Gawang 1.2 Pasang

89,375

107,250.00

107,250.00

- Perbaikan 6 s/d 10 Gawa 1.1 Pasang

89,375

98,313.00

98,310.00

PERBAIKAN SUTM TWISTED 3x70 s/d 90 MM2 ( Gawang )


- Perbaikan 1 s/d 5Gawang 1.2 Pasang

112,125

134,550.00

134,550.00

- Perbaikan 6 s/d 10 Gawa 1.1 Pasang

112,125

134,550.00

134,550.00

PERBAIKAN JEMPER SUTM/ Phase


- Tenaga Ahli

3/8 Hari
0.66 Tukang

112,500

42,187.50

40,500

26,730.00
68,917.50

68,910.00

PERBAIKAN TRAVES UNP 12 - 1800 mm

10,023

10,023.00

10,020.00

PERBAIKAN TRAVES UNP 12 - 2200 mm

22,204

22,204.00

22,200.00

PERBAIKAN TRAVES UNP 12 - 2400 mm

22,204

22,204.00

22,200.00

PERBAIKAN ISOLATOR TUMPU MIRING s

3,575

3,575.00

3,580.00

IV

LAIN - LAIN

PEMBERSIH BENAMG LAYANGAN SUTM/GAWANG


- Pembersihan

1/5 Teknisi

56,250

11,250.00

2/5 Tukang

40,500

16,200.00
27,450.00

- Pemangkasan

27,450.00

PEMANGKASAN CABANG POHON SUTM/GAWANG


1/5 Teknisi

56,250

11,250.00

4/5 Tukang

40,500

32,400.00

1 1/3 Pekerja

32,250

43,000.00

FOTO DOKUMENTASI : 36 LEMBAR

86,650.00

1 Rol Film

10,400

1 Cuci Film

2,600

2,600.00

1 Cetak 2x

520

18,720.00

86,650.00

10,400.00

31,720.00

31,720.00

0.65 m3

0.4 m3

0.4 m2

ASOSIASI KONTRAKTOR LISTRIK DAN MEKANIKAL INDONESIA

ANALISA HARGA SATUAN


JASA PEKERJAAN ANGKUTAN
Biaya Belum termasuk resiko,overhead, keuntungan 10% dan PPN 10%
2004
HARGA
NO

URAIAN PEKERJAAN

BIAYA

SATUAN

JUMLAH
DIBULATKAN

(RUPIAH)

(RUPIAH)

(RUPIAH)

BIAYA ANGKUTAN

1.1

Pick Up

Per Rit

65,000.00

1.2

Truck Kecil /2 - 4 Ton

Per Rit

84,500.00

84,500.00

1.3

Truck Kecil /5 - 7 Ton

Per Rit

130,000.00

130,000.00

1.4

Truck Tronton /> 7 Ton

Per Rit

214,500.00

214,500.00

1.5

Sepeda Motor

Per Rit

7,150.00

7,150.00

1.6

Forklift 5 Ton

Per Rit

14,300.00

14,300.00

1.7

Forklift 10 Ton

Per Jam

21,450.00

21,450.00

1.8

Crane

Per Jam

42,900.00

42,900.00

65,000.00

ANGKUTAN KU

1 Rit

84,500.00

- Truck Kecil /

Jam

14,300.00

42,900.00

- Forklift 5 Ton

Mandor

56,250.00

168,750.00

0.33

Pekerja

32,250.00

- Pelaksana

84,500.00

10,750.00
306,900.00

ANGKUTAN TRAFO 100 S/D 315 KVA


-Truck Kecil /

Rit

84,500.00

84,500.00

-Forklift 10 T

Jam

21,450.00

64,350.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Pelaksana

209,225.00
4

-Truck Kecil /

Rit

84,500.00

84,500.00

-Forklift 10 T

Jam

21,450.00

64,350.00

- Pelaksana

Mandor

56,250.00

56,250.00

Pekerja

32,250.00

64,500.00
269,600.00

ANGKUTAN TRAFO 400 s/d 1.250 KVA


-Truck Kecil /

Rit

84,500.00

84,500.00

-Forklift 10 T

Jam

21,450.00

64,350.00

=- Pelaksana

Mandor

56,250.00

56,250.00

Pekerja

32,250.00

64,500.00
269,600.00

209,225.00

ANGKUTAN TRAFO 400 s/d 630 KVA

269,600.00
5

306,900.00

269,600.00

ANGKUTAN TRAFO 1.000 s/d 1.250 KVA


Truck Tronton

Rit

214,500.00

214,500.00

-Forklift 10 T

Jam

21,450.00

64,350.00

-Pelaksana

Mandor

56,250.00

56,250.00

Pekerja

32,250.00

64,500.00
399,600.00

321,100.00

ANGKUTAN RAK TR DAN PERLENGKAPANNYA


Pick Up
- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

ANGKUTAN SKTM 10 - 50 METER


Pick Up

Rit

65,000.00

65,000.00

- Pelaksana

Mandor

56,250.00

28,125.00

0.67

Pekerja

32,250.00

21,500.00
114,625.00

Truck kecil / 2

Rit

84,500.00

84,500.00

- Pelaksana

Mandor

56,250.00

112,500.00

Pekerja

32,250.00

64,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Forklift 10 T

Mandor

56,250.00

168,750.00

- Pelaksana

Pekerja

32,250.00

64,500.00

- Truck Besar

Rit

130,000.00

130,000.00

- Forklift 10 To

Mandor

56,250.00

168,750.00

0.50

Pekerja

32,250.00

16,125.00
314,875.00

- Truck Besar

Rit

214,500.00

214,500.00

- Forklift 10 To

Mandor

56,250.00

168,750.00

0.50

Pekerja

32,250.00

16,125.00
399,375.00

- Pelaksana

Rit

65,000.00

65,000.00

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00
141,500.00

141,500.00

ANGKUTAN ISOLATOR 1 s/d 10 PETI


-Pick Up
- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

16

399,375.00

ANGKUTAN POLE TOP SWITCH 1 s/d 2 BUAH


-Pick Up

15

314,875.00

ANGKUTAN SKTM 3 HASPEL

- Pelaksana
14

317,750.00

ANGKUTAN SKTM 2 HASPEL

- Pelaksana
13

144,875.00

ANGKUTAN SKTM 1 HASPEL

317,750.00
12

261,500.00

ANGKUTAN SKTM 100 - 200 METER

144,875.00
11

114,625.00

ANGKUTAN SKTM 50 - 100 METER

261,500.00
10

125,375.00

125,375.00

ANGKUTAN FITTING 1 s/d 30 SET


-Pick Up
- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

125,375.00

17

ANGKUTAN KAWAT A3C 150 mm2 50 - 150 METER


- Pick Up

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

ANGKUTAN KAWAT A3C 150 mm2 150 - 250 METER

125,375.00

- Pelaksana
18

-Truck kecil /
- Pelaksana

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
144,875.00

19

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00
177,125.00

ANGKUTAN TIANG BESI 9/800 DAN (2 S/D 4 BT)


- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00
193,250.00

27

177,125.00

ANGKUTAN TIANG BESI 9/500 DAN (7 S/D 10 BT)

177,125.00
26

161,000.00

ANGKUTAN TIANG BESI 9/500 DAN (2 S/D 6 BT)

177,125.00
25

161,000.00

ANGKUTAN TIANG BESI 9/350 DAN (7 S/D 15 BT)

161,000.00
24

144,875.00

ANGKUTAN TIANG BESI 9/350 DAN (3 S/D 6 BT)

161,000.00
23

144,875.00

ANGKUTAN TIANG BESI 9/200 DAN (10 S/D 20 BT)

144,875.00
22

125,375.00

ANGKUTAN TIANG BESI 9/200 DAN (5 S/D 9 BT)

144,875.00
21

144,875.00

ANGKUTAN TIANG BESI 9/200 DAN (1 S/D 4 BT)


- Pick Up

20

125,375.00

ANGKUTAN TIANG BESI 9/800 DAN (5 S/D 8 BT)

193,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00
193,250.00

28

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00
161,000.00

29

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00
161,000.00

ANGKUTAN TIANG BESI 11/500 DAN (2 S/D 4 BT)


- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00
177,125.00

37

161,000.00

ANGKUTAN TIANG BESI 11/350 DAN (7 S/D 15 BT)

161,000.00
36

144,875.00

ANGKUTAN TIANG BESI 11/350 DAN (2 S/D 6 BT)

161,000.00
35

144,875.00

ANGKUTAN TIANG BESI 11/200 DAN (9 S/D 20 BT)

144,875.00
34

125,375.00

ANGKUTAN TIANG BESI 11/200 DAN (4 S/D 8 BT)

144,875.00
33

193,250.00

ANGKUTAN TIANG BESI 11/200 DAN (1 S/D 3 BT)


- Pick Up

32

177,125.00

ANGKUTAN TIANG BETON 9/500 DAN (1 S/D 4 BT)

193,250.00
31

161,000.00

ANGKUTAN TIANG BETON 9/350 DAN (1 S/D 5 BT)

177,125.00
30

193,250.00

ANGKUTAN TIANG BETON 9/200 DAN (1 S/D 6 BT)

ANGKUTAN TIANG BESI 11/500 DAN (5 S/D 10 BT)

177,125.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00
177,125.00

38

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00
193,250.00

39

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

96,750.00
209,375.00

ANGKUTAN TIANG BESI 13/1200 DAN (1 S/D 6 BT)


- Truck Kecil

Rit

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

84,500.00
28,125.00

3.50

Pekerja

32,250.00

112,875.00
225,500.00

47

193,250.00

ANGKUTAN TIANG BESI 13/500 DAN (1 S/D 6 BT)

209,375.00
46

177,125.00

ANGKUTAN TIANG BESI 13/500 DAN (1 S/D 8 BT)

193,250.00
45

161,000.00

ANGKUTAN TIANG BESI 13/350 DAN (1 S/D 8 BT)

177,125.00
44

193,250.00

ANGKUTAN TIANG BESI 13/1200 DAN (1 S/D 10 BT)

161,000.00
43

193,250.00

ANGKUTAN TIANG BESI 11/1200 DAN (4 S/D 7 BT)

193,250.00
42

120,250.00

ANGKUTAN TIANG BESI 11/200 DAN (2 S/D 3 BT)

193,250.00
41

193,250.00

ANGKUTAN TIANG BESI 11/800 DAN (4 S/D 8 BT)

193,250.00
40

177,125.00

ANGKUTAN TIANG BESI 11/800 DAN (2 S/D 3 BT)

ANGKUTAN TIANG BETON 11/200 DAN (1 S/D 4 BT)

225,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00
161,000.00

48

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00
177,125.00

49

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

64,500.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

96,750.00

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Truck Kecil

Rit

84,500.00

84,500.00

- Pelaksana

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
144,875.00

ANGKUTAN KABEL TWISTED 3x70+50 mm2 1 HASPEL


- Pick Up

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

- Pekerja

Pekerja

32,250.00

32,250.00

- Sewa Forklif

Jam

14,300.00

- Pelaksana

28,600.00
153,975.00

56

125,375.00

ANGKUTAN KABEL TWISTED 3x70+50 mm2 (250 S/D 500 MTR)

144,875.00
55

209,375.00

ANGKUTAN KABEL TWISTED 3x70+50 mm2 (10 S/D 250 MTR)


- Pick Up

54

193,250.00

ANGKUTAN TIANG BETON 13/500 DAN (1 S/D 2 BT)

209,375.00
53

115,380.00

ANGKUTAN TIANG BETON 13/350 DAN (1 S/D 2 BT)

193,250.00
52

193,250.00

ANGKUTAN TIANG BETON 13/200 DAN (1 S/D 3 BT)

177,125.00
51

177,125.00

ANGKUTAN TIANG BETON 11/500 DAN (1 S/D 3 BT)

193,250.00
50

161,000.00

ANGKUTAN TIANG BETON 11/350 DAN (1 S/D 3 BT)

ANGKUTAN KABEL TWISTED 3x70+50 mm2 2 HASPEL


- Truck Kecil /

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

- Pekerja

Pekerja

32,250.00

32,250.00

- Sewa Forklif

Jam

14,300.00

28,600.00

- Pelaksana

153,975.00

173,475.00
57

ANGKUTAN KABEL TWISTED 3x70+50 mm2 3 - 4 HASPEL


- Truck Kecil /

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

- Pekerja

Pekerja

32,250.00

32,250.00

- Sewa Forklif

Jam

14,300.00

42,900.00

- Pelaksana

187,775.00
58

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Pelaksana

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
144,875.00

- Pelaksana
- Forklift 5 To

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

Jam

14,300.00

28,600.00
173,475.00

173,475.00

ANGKUTAN BC 25 - 50 mm2 5 - 8 HASPEL


- Truck Kecil /
- Pelaksana
- Forklift 5 To

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

Jam

14,300.00

57,200.00
182,575.00

62

144,875.00

ANGKUTAN BC 25 - 50 mm2 2 - 4 HASPEL


- Truck Kecil /

61

125,375.00

ANGKUTAN BC 25 - 50 mm2 S/D 500 Kg - 1 Ton


- Truck Kecil /

60

187,775.00

ANGKUTAN BC 25 - 50 mm2 S/D 500 Kg


- Pick Up

59

173,475.00

162,830.00

ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,


4x150 mm S/D 50 METER
- Pick Up
- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

63

125,375.00

ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,


4x150 mm S/D 200 METER
- Truck Kecil /
- Pelaksana

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
144,875.00

64

144,875.00

ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,


4x150 mm2, 200- 300 METER
- Truck Kecil /
- Pelaksana

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
144,875.00

65

ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,


4x150 mm2, 1 - 2 HASPEL
- Truck Kecil /

Rit

84,500.00

84,500.00

144,875.00

- Pelaksana
- Forklift 5 To

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

Jam

14,300.00

28,600.00
173,475.00

66

173,475.00

ANGKUTAN KABEL NYFGBY 4x95 mm2, 4x120 mm2,


4x150 mm2, 3 - 4 HASPEL
- Truck Kecil /
- Pelaksana
- Forklift 5 To

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

Jam

14,300.00

42,900.00
187,775.00

67

- Pelaksana
- Sepeda Mot

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00

Rit

7,150.00

7,150.00
67,525.00

68

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

32,250.00
125,375.00

- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00
173,750.00

173,750.00

ANGKUTAN UPS 100 KVA, 1 BUAH


- Tuck Kecol /
- Pelaksana

Rit

84,500.00

84,500.00

0.50

Mandor

56,250.00

28,125.00

2.50

Pekerja

32,250.00

80,625.00
193,250.00

72

86,130.00

ANGKUTAN UPS 40 KVA, 1 BUAH


- Pick Up

71

125,375.00

ANGKUTAN APP TYPE KHUSUS IB,IC,IIF : ( 1 - 4 Buah)


- Pick Up

70

67,525.00

ANGKUTAN APP 1.A (1 - 6 Buah)


- Pick Up

69

187,775.00

ANGKUTAN APP TYPE KHUSUS IB,IC,IFF: (1 - 4 Buah)

193,250.00

ANGKUTAN GENSET 10 S/D 50 KVA, 1 BUAH


- Pick Up
- Pelaksana

Rit

65,000.00

65,000.00

0.50

Mandor

56,250.00

28,125.00

1.50

Pekerja

32,250.00

48,375.00
141,500.00

73

ANGKUTAN PERALATAN KONTROL

a.

Pengangkutan Lemari Spindel


a). Pick Up

Rit

65,000.00

65,000.00

b). Sewa Forkl

Jam

14,300.00

42,900.00

0.50

Mandor

56,250.00

28,125.00

Pekerja

32,250.00

96,750.00

- Pelaksana

141,500.00

232,775.00

232,775.00

b.

Pengangkutan Lemari RTU = Angkutan Lemari Spindel 148,525.00

148,525.00

c.

Pengangkutan Lemari MDF = Angkutan Lemari Spindel 148,525.00

148,525.00

d.

Pengangkutan Lemari Rectifi= Angkutan Lemari Spindel 148,525.00

148,525.00

e.

Pengangkutan Lemari Box R= Angkutan Lemari Spindel 148,525.00

148,525.00

f.

Pengangkutan Lemari Box = Angkutan Lemari Spindel 148,525.00

148,525.00

g.

Pengangkutan Lemari Box = Angkutan Lemari Spindel 148,525.00

148,525.00

You might also like