Professional Documents
Culture Documents
RISKS
Risk = an uncertain event or condition that, if occurs, has a positive or negative effect on
project objectives
Have a cause, an if it occurs, a consequence
Can be identified, anticipated, or beyond imagination
Sources of project risk can be internal, but some are external as well (ex. Inflation, market,
exchange rates, government regulations, etc.)
Another useful tool is a risk profile a list of questions that address traditional areas of
uncertainty on a project
o The questions have been developed and refined from previous, similar projects but
more tailored to the type of project in question
o Heres a partial example of a risk profile:
Contingency Planning
Contingency plan = alternative plan that will be used if a possible foreseen risk event
becomes a reality
A key distinction between a risk response and a contingency plan is that a response is part
of the actual implementation plan and action is taken before the risk can materialize, while
a contingency plan is not part of the initial implementation plan and only goes into effect
after the risk is recognized
The plan answers the questions: what, where, when and how much action will take place
It evaluates alternative remedies for possible foreseen events before the risk event occurs
and selects the best plan among alternatives
Risk response matrices are useful for summarizing how the project team plans to manage
risks that have been identified
First step is to identify whether to reduce, share, transfer or accept the risk
The next step is to identify contingency plans in case the risk still occurs
Next, the team needs to discuss what would trigger implementation of the
contingency plan
Finally, they need to assign the individual responsible for monitoring the
potential risk and initiating the contingency plan
Technical Risks
o These risks are problematic and are often the kind that cause the project to be shut
down
o In addition to contingency/back-up plans, managers need to develop methods to
quickly assess whether technical uncertainties can be resolved
Schedule Risks
o Often organizations will defer the threat of a project coming in late until it surfaces
o Here contingency funds are set aside to expedite or crash the project to get it
back on track
o Crashing, or reducing project duration, is accomplished by shortening (compressing)
one or more activities on the critical path
Cost Risks
o Projects of long duration need some contingency for price changes (which are
usually upward)
o On cost sensitive projects, price risks should be evaluated item by item
Funding Risks
o Manager smust also consider the possibility of the project being cut by 25%, costs
exceed available funds, or the project being canceled before completion.
Opportunity Management
An opportunity is an event that can have a positive impact on project object
Opportunities are identified, assessed in terms of likelihood and impact, responses are
determined, and even contingency plans and funds can be established to take advantage
of the opportunity if it occurs
Four different types of response to an opportunity:
o Exploit
Eliminate the uncertainty associated with an opportunity to ensure that it
definitely happens
o Share
Allocating some or all of the ownership of an opportunity to another party
who is best able to capture the opportunity for the benefit of the project
o Enhance
The opposite of mitigation
Action is taken to increase the probability and/or positive impact of the
opportunity
o Accept
Willingness to take advantage of it if it occurs
Time Buffers
Used to cushion against potential delays in the project
The more uncertain the project, the more time should be reserved for the schedule
The strategy is to assign extra time at critical moments in the projects
Example: buffers are added to
o Activities with severe risks
o Merge activities that are prone to delays due to one or more preceding activities
being late
o Noncritical activities to reduce the likelihood that they will create another critical
path
o Activities that require scarce resources to ensure that the resources are available
when needed
In the face of overall schedule uncertainty, buffers are sometimes added to the end of the
project
Time buffers usually require authorization from top management