1.0 COMPUTATION OF No.

OF BULBS FOR THE ADMINISTRATION BLOCK

S/No. SPACE DIMENSION AREA No. Of Bulbs


N=(E*A)/(FUM)
L/M W/M LxW/M2

Ground Floor

1 Office 1 3.00 4.00 12.00 2.08

2 Offfice 2 3.10 4.00 12.40 2.15

3 Wash Office 3.10 4.00 12.40 2.15

4 Field Assistant 1 3.00 4.00 12.00 2.08

5 Field Assistant 2 3.00 4.00 12.00 2.08

6 Office 3 3.55 4.00 14.20 2.47

7 Trainer,s Office 3.00 4.00 12.00 2.08

8 Library & Data centre 6.40 4.00 25.60


5.20 2.30 11.96 6.52

9 Store 3.00 4.00 12.00 2.08

10 Trainees Office 6.55 4.00 26.20 4.55

11 Wash rooms for FPC (2No.) 1.20 1.90 4.56 0.73

12 General Lavatories 6.40 4.00 25.60 4.10

13 Tea Room 2.80 1.50 4.20 0.73

14 Office 4& Reception 3.75 7.60 28.50 4.95


2.45 2.20 5.39 0.94

15 Stair case 2.45 5.20 12.74 2.04

16 Ramp 2.70 10.10 27.27 4.37

17 Corridor 22.40 1.50 33.60 8.08

18 Verandah 5.20 1.30 6.76 0.59

Page 1 of 14
1.0 COMPUTATION OF No. OF BULBS FOR THE ADMINISTRATION BLOCK

Total No. of Bulbs 54.78


S/No. SPACE DIMENSION AREA No. Of Bulbs
L/M W/M LxW/M2 N=(E*A)/(FUM)
First Floor

1 Project's Manager 3.00 4.00 12.00 2.08

2 Asistant Project's Manager 3.10 4.00 12.40 2.15

3 Project's Supervisor 1 3.10 4.00 12.40 2.15

4 Project's Supervisor 2 3.00 4.00 12.00 2.08

5 Cash Office 3.00 4.00 12.00 2.08

6 Accounts 3.55 4.00 14.20 2.47

7 Warden 3.00 4.00 12.00 2.08

8 Board room 6.40 4.00 25.60


5.20 2.30 11.96 6.52

9 Secretary 3.00 4.00 12.00 2.08

10 Field Project's Coordinator 6.75 4.00 27.00 4.69

11 Wash rooms for FPC (2No.) 1.20 1.90 4.56 0.73

12 General Lavatories 6.40 4.00 25.60 4.10

13 Store 2.80 1.50 4.20 0.73

14 Regional Cordinator 3.75 7.60 28.50 4.95


2.45 2.20 5.39 0.94

15 Stair case 2.45 5.20 12.74 2.04

16 Ramp 2.70 10.10 27.27 4.37

17 Corridor 22.40 1.50 33.60 8.08

Page 2 of 14
1.0 COMPUTATION OF No. OF BULBS FOR THE ADMINISTRATION BLOCK

18 Verandah 5.20 1.30 6.76 0.59

Total No. of Bulbs 54.92


Notes

Page 3 of 14
1.0 COMPUTATION OF No. OF BULBS FOR THE ADMINISTRATION BLOCK

ASSUMED

FACTORS
FLOURESCENT TUBES
E 200
UF 0.8
MF 0.6
F 2400

STAIRCASE FITTING
E 100
UF 0.8
MF 0.6
F 1300

LOBBY FITTING
E 150
UF 0.8
MF 0.6
F 1300

VERANDAH FITTING
E 100
UF 0.8
MF 0.6
F 2400

Page 4 of 14
1.0 COMPUTATION OF No. OF BULBS FOR THE ADMINISTRATION BLOCK

ASSUMED
FACTORS
FLOURESCENT TUBES
E 200
UF 0.8
MF 0.6

F 2400

STAIRCASE FITTING
E 100
UF 0.8
MF 0.6
F 1300

LOBBY FITTING
E 150
UF 0.8
MF 0.6
F 1300

VERANDAH FITTING
E 100
UF 0.8

MF 0.6
F 2400

Page 5 of 14
1.0 COMPUTATION OF No. OF BULBS FOR THE ADMINISTRATION BLOCK

Page 6 of 14
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

PROJECT: PROPOSED ADMINISTRATION BLOCK FOR UNITED NATIONS HIGH COMMISSION FOR REFUGEES

TASK: ELECTRICAL CALCULATIONS

DATE OF SUBMISSION: 12TH.03.2017

S/N LOCATION Description Power Operating Amperage (P/V) / A


rating (W) voltage (V)
1 Ground floor LED panel light 36 240 0.15
2 LED T8 Tube 18 240 0.08
3 LED downlight 12 240 0.05
4 Seurity Lights 12 240 0.05
5 Desktop computers 160 240 0.67
6 Laptops 100 240 0.42
7 Airconditioner 1000 240 4.17
8 Wall fan 30 240 0.13
9 LED TV monitor 100 240 0.42
10 Handryer 1800 240 7.50
11 Cooker 3000 240 12.50
12 Microwave 1000 240 4.17
13 Mobile Phone 4 240 0.02
14 Fridges 200 240 0.83
15 Extraction Fan 1000 240 4.17
16 Ink Jet Printer 20 240 0.08
17 Electric Kettle 2000 240 8.33
18 Photocopier 2400 240 10.00
TOTAL POWER RATINGS FOR GROUND FLOOR
CARRIED TO COLLECTION <<<<<<<<<<<<<<<<<<<<<<<>>>>>>>>>>>>>>>>>>>>>>>>
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

PROJECT: PROPOSED ADMINISTRATION BLOCK FOR UNITED NATIONS HIGH COMMISSION FOR REFUGEES

TASK: ELECTRICAL CALCULATIONS

DATE OF SUBMISSION: 12TH.03.2017

S/N LOCATION Description Power Operating Amperage (P/V) / A


rating (W) voltage (V)

19 First Floor LED panel light 36 240 0.15


20 LED T8 Tube 18 240 0.08
21 LED downlight 12 240 0.05
22 Seurity Lights 12 240 0.05
23 Desktop computers 160 240 0.67
24 Laptops 100 240 0.42
25 Airconditioner 1000 240 4.17
26 Wall fan 30 240 0.13
27 LED TV monitor 100 240 0.42
28 Handryer 1800 240 7.50
29 Cooker 3000 240 12.50
30 Microwave 1000 240 4.17
31 Mobile Phone 4 240 0.02
32 Fridges 200 240 0.83
33 Extraction Fan 1000 240 4.17
34 Ink Jet Printer 20 240 0.08
35 Photocopier 2400 240 10.00
TOTAL POWER RATINGS FOR FIRST FLOOR
CARRIED TO COLLECTION <<<<<<<<<<<<<<<<<<<<<<<>>>>>>>>>>>>>>>>>>>>>>>>
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

PROJECT: PROPOSED ADMINISTRATION BLOCK FOR UNITED NATIONS HIGH COMMISSION FOR REFUGEES

TASK: ELECTRICAL CALCULATIONS

DATE OF SUBMISSION: 12TH.03.2017

S/N LOCATION Description Power Operating Amperage (P/V) / A


rating (W) voltage (V)

COLLECTION

Total from Page 1/3

Total from Page 2/3

GRAND TOTAL FOR GROUND AND FIRST FLOOR


POWER RATING

CONCLUSIONS
From the tables above:
Ground floor = 76.98A therefore we shall use an 80A Circuit Breaker
First floor = 54.07A therefore we shall use a 63A Circuit Breaker

Since the total Amperage for the Entire Building is 131.04A, we therefore recommend the available 200A Main Distribution Board
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

ISSION FOR REFUGEES

Total Number of Total Amperage


appliances (A)
18.00 2.70
30.00 2.25
27.00 1.35
6.00 0.30
5.00 3.33
5.00 2.08
1.00 4.17
5.00 0.63
1.00 0.42
2.00 15.00
1.00 12.50
1.00 4.17
10.00 0.17
1.00 0.83
2.00 8.33
5.00 0.42
1.00 8.33
1.00 10.00

>>>>>>>>>>>>>>>> 76.98
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

ISSION FOR REFUGEES

Total Number of Total Amperage


appliances (A)
Page 1 of 3
PAGE 1 of 3
24.00 3.60
30.00 2.25
26.00 1.30
0.00 0.00
14.00 9.33
5.00 2.08
0.00 0.00
8.00 1.00
1.00 0.42
2.00 15.00
0.00 0.00
0.00 0.00
10.00 0.17
0.00 0.00
2.00 8.33
7.00 0.58
1.00 10.00

>>>>>>>>>>>>>>>> 54.07
2.0 COMPUTATION OF THE CIRCUIT BREAKER RATING FOR THE ENTIRE BLOCK

ISSION FOR REFUGEES

Total Number of Total Amperage


appliances (A)
Page 2 of 3

76.98

54.07

131.04

0A Main Distribution Board

Page 3 of 3
3.0

3.1

3.2
SUPPLY CABLE SIZING

MAIN SUPPLY

The main supply for this project is three phase.


For three phase (3ph), cable sizing =[3x2xPxIxl]1/2 % allowance for voltage drop.

Where: Is the specific resistance of resistivity of the conductor, and is 11.2 for copper.
P
I is the load current
D is the distance in Ft

The dimensions of the conductor area are Circular Mil (CM)=5.067x10 -4 SMM (Square milimetres)

I=199.691A D=30Ft and p=11.2

Conductor size =[3x2x199.691x11.2x30/3]1/2


= 77,475.99Cm
=77,475.99x5.067-4
= 39.25SMM

We use a 50smm cable since it is the available size in the market.

GROUND FLOOR SUPPLY


For Single Phase, cable size = (2**I*L) /% allowance for voltage drop. The distance of the
cable is 50Ft and the load current is 76.975A.