Professional Documents
Culture Documents
2, JUNE 2006
AbstractA battery energy storage system (BESS) stores energy practically all savings are achieved by reducing peak load. Under
at lower demand and sends saved energy back to the system during the electricity market conditions, the viability assessment of an
peak load. It thus represents a good solution for daily load leveling. investment in BESS is much more complex, especially with
The evaluation of the Ampere-hour capacity of the battery needed
for load leveling during a period of several hours is of great im- respect to load leveling. At this stage, it is important to point
portance when using BESS as an active power peaking station. A out the other possibilities of battery system usage and related
battery simulation model that was developed for this purpose is savings, in particular for solving different problems in utility
presented in the paper. The model takes into account the battery and industry distribution systems, as well as in railway supply.
voltage dependency on the capacity and current, and is based on In comparison with other available sources, the operating
the performed battery measurements at constant discharging cur-
rents. By using this model, which should prove to be a very effective time of BESS is limited; i.e., it can send to the network only an
tool for BESS capacity planning, the simulation of the character- exactly defined quantity of energy with respect to the operating
istic load leveling was performed and compared to the measured method. This results in a complex control of BESS that has
voltage and current profiles. to be computer-aided. All physical magnitudes are nonlinear,
Index TermsBattery energy storage system (BESS), discharg- time variant, and affected by various factors. An algorithm is
ing, lead-acid batteries, load leveling, simulation model. required to monitor the consumption of electric power, and in
case of excess consumption, switch on BESS or, during reduced
consumption, charge the battery cells. An algorithm usually
I. INTRODUCTION
consists of three parts. The first one is responsible for the col-
N electrical power systems it is desirous to level daily load
I diagrams as much as possible, and to adapt them to the
economically optimal operation of installed capacities, which
lection and processing of data, and forecast of consumption at
the end of a 15-min interval. If the anticipated consumption
exceeds the desired maximum value, the second part is carried
leads to cheaper energy of better quality. One of the possible out in order to control the supply of power from BESS to the
methods for load control is to store energy when there is less network, otherwise the third part that controls the process of cell
demand, and to inject the stored energy back into the network charging is put into operation. In the BESS planning phase, and
during peak load periods. The solution to the given problem later every time prior to connecting BESS to the network, the
could be a battery energy storage system (BESS). Such equip- consumption of electric power must be anticipated and battery
ment with rated power of several tens of MW is used around the system capacity checked.
world [1], [2]. A smaller BESS with lead-acid batteries and an In this paper, the simulation model for discharging lead-acid
insulated gate bipolar transistor (IGBT) converter is installed at batteries is presented. The behavior of a battery cell during the
the battery factory TAB Mezica in Slovenia [3]. This unit has discharging process can be described with different mathemati-
been successfully in operation since 1998. cal models [4], [5] based on certain parameters that have to be
The tariff system plays a decisive role when evaluating the experimentally determined. The model derived here uses a more
economic viability of BESS in an electric power system for peak direct approach; it is based on the interpolation among lead-acid
load leveling. When BESS is used in a classical tariff system, battery characteristics obtained by measurements during the dis-
savings are made in two ways. First, the peak power is reduced, charging process. The model was used during the planning pro-
and second, the share of more expensive energy; i.e., energy cess for the battery energy storage system at TAB Mezica in
that would be charged according to the critical tariff, is replaced Slovenia, and later for checking the overall performance of the
with the less expensive one stored during low tariff periods. It system when covering different load diagrams. The aforemen-
should be emphasized that savings in the classical tariff system tioned installation is briefly described in Section II, followed by
are much greater due to the reduction of peak power (95%) in a description of the simulation model derivation. The simulated
comparison with the use of less expensive electric power (5%). and measured results are compared. Simulations are performed
When consuming less expensive electric power, the efficiency of covering different patterns of daily load diagrams.
the battery system in the range from 75 to 85%, depending on the
operating method, should be taken into consideration. Hence, II. LOAD LEVELING AT TAB MEZ ICA
Manuscript received December 29, 2003; revised January 27, 2005. This work Since TAB Mezica produces lead-acid batteries and global
was supported in part by TAB Mezica, Slovenia, under Grant S-549. Paper no. trends show an increase in the use of batteries for leveling the
TEC-00372-2003. power consumption diagram, this factory decided to install its
The author is with the Faculty of Electrical Engineering, University of Ljubl-
jana, Ljubljana SI-1000, Slovenia (e-mail: igor.papic@fe.uni-lj.si). own pilot device. Their main objective was to level the daily di-
Digital Object Identifier 10.1109/TEC.2005.853746 agrams of electric power consumption. TAB receives its power
TABLE I With (1), we obtain the voltage values for the two charac-
MAXIMAL BATTERY CAPACITIES FOR DIFFERENT DISCHARGING CURRENTS
teristic points at a given capacity of 50%: UI 5 = 1.950 V and
UI 3 = 1.932 V. After calculating power characteristics with (2)
at the same capacity value, the demanded power of 274 kW
ranges between PIk5 = 229.75 kW and PIk3 = 330.86 kW. Now,
the battery cell voltage and current can be calculated as follows:
P k PIk5
U k = UIk5 UIk5 UIk3 = 1.942 V
PIk3 PIk5
Pk
Ik = = 514.93 A. (3)
ns U k
For different input power values, the appropriate closest
PI 3 = ns UI 3 I3 higher and lower power and voltage characteristics should
be used. By integrating the current during the simulation, online
PI 1 = ns UI 1 I1
corrections to the battery capacity are made:
PI 0.5 = ns UI 0.5 I0.5
k k 1 I k t
PI 0.33 = ns UI 0.33 I0.33 Cp2500 = Cp2500 + 100%, (4)
2500 Ah
PI 0.25 = ns UI 0.25 I0.25 (2) where t represents a time integration step; I k is the magni-
tude of the battery current in a certain integration step. It is
where assumed to be a constant value for the time integration step,
PI 10 power of the battery system at constant discharging which should be small enough to avoid numerical instability;
current 250 A and 10-h discharging time as a function generally, it depends on the time constants of the phenomena
of the percentage value of rated capacity; being simulated.
PI 5 power of the battery system at constant discharging This new battery capacity now serves as a basis for the calcu-
current 430 A and 5-h discharging time as a function lation of power characteristics for the next integration step. As
of the percentage value of rated capacity; previously mentioned, at the start of simulation it is assumed
PI 3 power of the battery system at constant discharging that the battery is fully charged.
current 625 A and 3-h discharging time as a function The limitations of the possible operation of the battery are
of the percentage value of rated capacity; included in the model. If the load current at a given capacity is
PI 1 power of the battery system at constant discharging too high, the inherent logic progressively reduces the loadin
current 1300 A and 1-h discharging time as a function so doing, the operating point follows the boundary line of the
of the percentage value of rated capacity; possible operating area. Without the mentioned logic, the bat-
PI 0.5 power of the battery system at constant discharging tery should be disconnected from the system, but in our case
current 2050 A and 0.5-h discharging time as a func- the battery is being further discharged at the reduced current in
tion of the percentage value of rated capacity; order to use the whole rated capacity (Table I). Under practi-
PI 0.33 power of the battery system at constant discharging cal operating conditions, there are two mechanisms for limita-
current 2700 A and 0.33-h discharging time as a tion of the battery current at given capacity. The first limitation
function of the percentage value of rated capacity; represents the rated power of the converter. Additionally, dur-
PI 0.25 power of the battery system at constant discharging ing battery discharging, the converter operates in active power
current 3100 A and 0.25-h discharging time as a control mode; the algorithm for the calculation of the power
function of the percentage value of rated capacity; reference value observes the dc voltage and appropriately re-
and duces the reference value in case the dc voltage is too low.
ns number of series connected battery cells. This algorithm is applied at the upper control level outside the
The active power that should be covered by batteries is the converter hardware.
input value. On the basis of this power, with linear interpolation By assuming that the battery is connected to the network over
between the appropriate two power and voltage characteristics, an IGBT converter, BESS also generates or absorbs reactive
the magnitude of the battery current and voltage in a certain in- power. It is assumed that the active power exchange with the
tegration step can be determined. To better illustrate the method system has priority, and that only the power difference, which
of linear interpolation, let us assume the following numerical can be calculated from the instantaneous active power demand
input values at the integration step k: and rated power of the converter, is available for the compensa-
1) P k = 274 kWdemanded power from the battery system tion of the reactive power. The reactive power reference value is
at the integration step k; the input value in the model and is supposed to be determined
k
2) Cp2500 = 50%capacity of the battery cells at the inte- at the upper control level, which observes the conditions at the
gration step k; point of the connection to the network where the power factor
3) ns = 274. should equal one.
612 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO. 2, JUNE 2006
used during the planning stage. The rated power of the converter
was 300 kW, with the battery system consisting of 274 series
connected OpzS battery cells.
Fig. 5. Flow chart of the BESS-model operations under the conditions of Fig. 6 shows the operation of the system during the load
digital simulation in an arbitrary integration step. leveling operation. The presented case reflects the characteristic
load diagram of TAB Mezica. The measured values of the active
power on the network side and the load power are presented
According to Fig. 5, the resumed operations with the BESS in the first graph. The reference power of 1.348 MW is set
model under the conditions of digital simulation in an arbitrary considering the peak power forecast during the peak daily tariff
integration step are as follows. for a certain day. During the higher daily tariff, the reference
1) Active and reactive power demand determination on the value may be increased by 15%. The second graph shows the
ac side of the system with BESS; measured power supplied from BESS; this power diagram was
2) Load current calculation of the battery by taking into ac- used as the input in the simulation model. The simulated and
count power and voltage characteristics at a given battery measured values of battery voltage and current are presented in
capacity; the third and fourth graph in Fig. 6. It is evident that the simulated
3) Consideration of the battery operation boundaries and pos- and measured data are in good agreement. The relative value of
sible load current reduction; the remaining battery capacity and the energy supplied by the
4) Calculation of the battery capacity change with regard to batteries are shown in the last graph in Fig. 6.
the actual load current and determination of the battery Further comparison between the simulated and measured data
capacity for the next integration step; was performed and the results were always similar to the ones
5) Calculation of available power for the reactive power com- represented in Fig. 6.
pensation; and
6) Actual covering of the active and reactive power by con-
C. Simulation of Supplying Different Load Patterns
sidering the stated limitations and battery condition.
In the next stage, the simulation of supplying different load
patterns was performed. The trace of the battery capacity during
B. Comparison of Simulation Results With Measured Data
discharging with variable load current depends on the type or
The purpose of the first set of simulations performed by the pattern of the load that should be covered by BESS. For the four
derived battery-discharging model is to compare the simulated different examples, it is assumed that BESS is used to supply the
results with the measured ones. When BESS at TAB Mezica same amount of energy (1.125 MWh), but in different operating
was put into operation, the measurement data were available. regimes. In the time frame of 4.5-h, the system consisting of 274
Therefore, it was possible to test the derived simulation model series connected battery cells follows different active power
SIMULATION MODEL FOR DISCHARGING
PAPIC: 613
patterns while being discharged; we assumed that there is no supplied from BESS equals 1.112 MWh and the remaining ca-
reactive power exchange with the system. pacity amounts to 10.8% of the rated value. In the second and
Results of the simulation with the developed BESS model third case, BESS operates without restrictions; at the end of the
are shown in Fig. 7. The actual and reference values of the operating cycle the supplied energy amounts to 1.125 MWh. In
time dependent load diagrams covered by BESS are given for both cases, the remaining capacity equals approximately 14%
different cases in the top graphs, followed by the battery voltage of the rated value. The results are represented in Figs. 7(b) and
and current traces. In the bottom graphs, the relative values (c). In the fourth case, shown in Fig. 7(d), at the interval be-
of the remaining battery capacity with regard to the rated 10 tween points A and B the load current has to be reduced again;
hour capacity (2500 Ah), and the energy being supplied by the with reduced load the system returns to the allowed operating
batteries, are shown. area. The supplied energy in this case amounts to 1.109 MWh
In the first case, the batteries are discharged by constant at 15.5% of the rated capacity.
power; by decreasing the battery capacity progressively, the Considering the required power of the converter, the first case
battery voltage drops and the current increases. In Fig. 7(a) we of discharging is preferable, but BESS in this case supplies less
can see that BESS at the interval between points A and B oper- energy than required and the remaining capacity is the lowest.
ates on the boundary line, which means that the load current is For the batteries, it is certainly most convenient if the load is
partly reduced. At the end of the 4.5 hour interval, the energy reduced toward the end of the discharging cycle, which can be
614 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO. 2, JUNE 2006
Fig. 8. Characteristic quantities of BESS during load leveling operation for different active power reference values. (a) 1.3 MW. (b) 1.4 MW.
observed in the second and third example of the discharging batteries are further discharging up to point C, where current
pattern. reduction starts again. BESS is due to the exhaustion untimely
switched off at point D. At that moment, the actual power at the
network side exceeds the reference value for 203 kW, and peak
D. Simulation of Supplying Characteristic Peak Load
load shaving is not successful.
The BESS model was also used for the simulation of a char- In the second case, shown in Fig. 8(b), the set reference
acteristic peak load supply. In the load model, the characteristic value equals 1.4 MW. During the whole observation period,
measured load diagram at the factory site between 7:00 and BESS operates in the normal operating area, peak load shaving
15:00 was implemented. The task of the fully charged BESS is successful, and the active power reference value was not
was to cover the load above the given reference value of the exceeded. At the end of the discharging cycle, the remaining
active power. The rated power of the converter was assumed capacity equals 40.7% of the rated value. The energy being
to be 300 kW, with the battery system again consisting of 274 supplied from BESS in the first case equals 1.252 MWh, and in
series connected OpzS battery cells. the second equals 0.740 MWh.
The simulation of the battery discharging was performed for
the two different reference values of the active power. The traces
of some characteristic BESS quantities are shown in Fig. 8. In
both cases, the load active power and the same active power IV. CONCLUSION
reduced by the amount contributed by BESS are shown in the The evaluation of the Ampere-hour capacity of the battery
top graphs. The actually supplied and demanded power from needed for load leveling during a period of several hours is
BESS are presented in the second graphs, followed by the battery very important when using BESS as an active power peaking
voltage and current traces. The relative value of the remaining station. The discharging simulation model of the battery that
battery capacity with regard to the rated 10 hour capacity Cp2500 , was developed for this purpose takes into account the battery
and the energy W being supplied by the batteries, are shown in voltage dependency on the capacity and current, and is based
the bottom graphs. on the performed battery measurements at constant discharging
BESS covers the load above the active power reference value currents. By using the aforementioned model, the simulation
that is, in the first case, set to 1.3 MW; this value is at 13:00 of the characteristic load leveling operation was performed and
increased by 15%, as seen in Fig. 8(a). Batteries are successfully compared to the measured voltage and current profiles. As pre-
supplying the load up to a point A, where the battery current viously mentioned, practically all savings when using BESS are
approaches the boundary of the permitted operating area. At this achieved by reducing peak load. The simulation results prove
point, the current reduction starts, which means that the actual the significance of the proper setting of the active power refer-
power at the network side exceeds the set reference value. At ence value for successful shaving of peak loads. The comparison
point B, the system returns to the normal operating area, and between the simulated results and the measured ones validated
SIMULATION MODEL FOR DISCHARGING
PAPIC: 615