You are on page 1of 8

608 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO.

2, JUNE 2006

Simulation Model for Discharging a Lead-Acid


Battery Energy Storage System for Load Leveling
Igor Papic, Member, IEEE

AbstractA battery energy storage system (BESS) stores energy practically all savings are achieved by reducing peak load. Under
at lower demand and sends saved energy back to the system during the electricity market conditions, the viability assessment of an
peak load. It thus represents a good solution for daily load leveling. investment in BESS is much more complex, especially with
The evaluation of the Ampere-hour capacity of the battery needed
for load leveling during a period of several hours is of great im- respect to load leveling. At this stage, it is important to point
portance when using BESS as an active power peaking station. A out the other possibilities of battery system usage and related
battery simulation model that was developed for this purpose is savings, in particular for solving different problems in utility
presented in the paper. The model takes into account the battery and industry distribution systems, as well as in railway supply.
voltage dependency on the capacity and current, and is based on In comparison with other available sources, the operating
the performed battery measurements at constant discharging cur-
rents. By using this model, which should prove to be a very effective time of BESS is limited; i.e., it can send to the network only an
tool for BESS capacity planning, the simulation of the character- exactly defined quantity of energy with respect to the operating
istic load leveling was performed and compared to the measured method. This results in a complex control of BESS that has
voltage and current profiles. to be computer-aided. All physical magnitudes are nonlinear,
Index TermsBattery energy storage system (BESS), discharg- time variant, and affected by various factors. An algorithm is
ing, lead-acid batteries, load leveling, simulation model. required to monitor the consumption of electric power, and in
case of excess consumption, switch on BESS or, during reduced
consumption, charge the battery cells. An algorithm usually
I. INTRODUCTION
consists of three parts. The first one is responsible for the col-
N electrical power systems it is desirous to level daily load
I diagrams as much as possible, and to adapt them to the
economically optimal operation of installed capacities, which
lection and processing of data, and forecast of consumption at
the end of a 15-min interval. If the anticipated consumption
exceeds the desired maximum value, the second part is carried
leads to cheaper energy of better quality. One of the possible out in order to control the supply of power from BESS to the
methods for load control is to store energy when there is less network, otherwise the third part that controls the process of cell
demand, and to inject the stored energy back into the network charging is put into operation. In the BESS planning phase, and
during peak load periods. The solution to the given problem later every time prior to connecting BESS to the network, the
could be a battery energy storage system (BESS). Such equip- consumption of electric power must be anticipated and battery
ment with rated power of several tens of MW is used around the system capacity checked.
world [1], [2]. A smaller BESS with lead-acid batteries and an In this paper, the simulation model for discharging lead-acid
insulated gate bipolar transistor (IGBT) converter is installed at batteries is presented. The behavior of a battery cell during the
the battery factory TAB Mezica in Slovenia [3]. This unit has discharging process can be described with different mathemati-
been successfully in operation since 1998. cal models [4], [5] based on certain parameters that have to be
The tariff system plays a decisive role when evaluating the experimentally determined. The model derived here uses a more
economic viability of BESS in an electric power system for peak direct approach; it is based on the interpolation among lead-acid
load leveling. When BESS is used in a classical tariff system, battery characteristics obtained by measurements during the dis-
savings are made in two ways. First, the peak power is reduced, charging process. The model was used during the planning pro-
and second, the share of more expensive energy; i.e., energy cess for the battery energy storage system at TAB Mezica in
that would be charged according to the critical tariff, is replaced Slovenia, and later for checking the overall performance of the
with the less expensive one stored during low tariff periods. It system when covering different load diagrams. The aforemen-
should be emphasized that savings in the classical tariff system tioned installation is briefly described in Section II, followed by
are much greater due to the reduction of peak power (95%) in a description of the simulation model derivation. The simulated
comparison with the use of less expensive electric power (5%). and measured results are compared. Simulations are performed
When consuming less expensive electric power, the efficiency of covering different patterns of daily load diagrams.
the battery system in the range from 75 to 85%, depending on the
operating method, should be taken into consideration. Hence, II. LOAD LEVELING AT TAB MEZ ICA
Manuscript received December 29, 2003; revised January 27, 2005. This work Since TAB Mezica produces lead-acid batteries and global
was supported in part by TAB Mezica, Slovenia, under Grant S-549. Paper no. trends show an increase in the use of batteries for leveling the
TEC-00372-2003. power consumption diagram, this factory decided to install its
The author is with the Faculty of Electrical Engineering, University of Ljubl-
jana, Ljubljana SI-1000, Slovenia (e-mail: igor.papic@fe.uni-lj.si). own pilot device. Their main objective was to level the daily di-
Digital Object Identifier 10.1109/TEC.2005.853746 agrams of electric power consumption. TAB receives its power

0885-8969/$20.00 2005 IEEE


SIMULATION MODEL FOR DISCHARGING
PAPIC: 609

Fig. 1. Voltage characteristics of OPzS battery discharging, depending on rated


capacity.

Fig. 3. Battery system consisting of 274 cells at TAB Mezica.

duration, together with the forecast of the load diagram, enables


the determination of the capability of load leveling with respect
to the necessary energy input and maximum load. The config-
uration of 274 OPzS cells in series with rated voltage of 548 V
and ten hour capacity of 2500 Ampere-hours (Ah) was selected.
The battery installation is shown in Fig. 3.
A monitoring system for the consumption of electric power
with an algorithm for forecasting 15-min peaks was developed.
This monitoring system calculates reference values for the bat-
tery system and controls its operation. During battery system
discharge, the converter is controlled by a closed loop active
power control system. When batteries are charged under the
given I-U characteristic, the converter is controlled by a current
closed loop control system.
As previously mentioned, the proper planning of the bat-
tery system capacity is crucial for full utilization of installed
Fig. 2. 300 kW IGBT converter at TAB Mezica. equipment. Also, later in the operation planning phase, battery
capacity must be permanently checked prior to covering certain
from the electric power network over two lines. The 20/0.4 kV patterns of load diagrams. In Section III, the battery discharging
transformation is conducted through two transformers, each 1 simulation model that can fulfill this task is described in detail.
MVA. Based on analyses of the network and operations of ma-
jor consumers (converters, mills, etc.) it was established that III. SIMULATION OF DISCHARGING BATTERY
peak power is exceeded by 200300 kW due to actions arising ENERGY STORAGE SYSTEM
from uncoordinated loads. Out of 22 production days, only 35
contributed to an unwanted increase in peak load. Furthermore, A. Model of Battery Energy Storage System for Load Leveling
the conclusion was reached that peak power leveling must be Modeling and simulation of the battery energy storage sys-
planned for at least 45 h a day. First, sample analyses of the tem operation were performed in the stability mode of the NE-
fluctuation in daily load were carried out and voltage measure- TOMAC (Network Torsion Machine Control) digital program
ments were made on OPzS lead-acid batteries exposed to the system that offers a wide range of options for simulating various
loads according to a certain current profile. Voltage characteris- electromagnetic and electromechanical phenomena in electri-
tics of OPzS battery discharging, depending on rated capacity, cal power supply systems. The BESS and load model, repre-
are shown in Fig. 1. sented as controllable impedances, are connected to the slack.
Second, a pilot battery system with a 300 kW IGBT converter As depicted in Fig. 4, the two supply transformers mentioned in
shown in Fig. 2 was put into operation in 1998. A detailed de- Section II are modeled with a single equivalent transformer
scription of the installation is given in [3]. Energy reserves to model from the program system library. The load model can
be used during load leveling, the desired life cycle, and battery represent an arbitrary load diagram pattern.
maintenance costs were taken into consideration when deter- Development of this BESS model is based on the fact that the
mining the properties of the battery. The calculation of the re- Ah of the battery are constant, irrespective of which trajectory in
quired battery capacity considering the given pattern and load the diagram of the battery cell voltage characteristics is followed
610 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO. 2, JUNE 2006

UI 10 = 2.01 1.45 103 Cp2500


+ 2.38 105 Cp2500
2
2.54 107 Cp2500
3

UI 5 = 2.00 9.46 104 Cp2500


+ 1.39 105 Cp2500
2
3.03 107 Cp2500
3

UI 3 = 1.99 8.81 104 Cp2500


+ 1.97 105 Cp2500
2
5.05 107 Cp2500
3

UI 1 = 1.94 1.25 103 Cp2500


1.10 105 Cp2500
2
4.16 107 Cp2500
3

UI 0.5 = 1.89 2.24 103 Cp2500


+ 2.27 105 Cp2500
2
1.24 106 Cp2500
3

Fig. 4. Simplified simulation model of supply network with BESS.


UI 0.33 = 1.86 1.88 103 Cp2500
+ 1.25 105 Cp2500
2
1.78 106 Cp2500
3

UI 0.25 = 1.84 3.74 103 Cp2500


during discharging. This property was confirmed also by on-site + 9.46 105 Cp2500
2
3.88 106 Cp2500
3
(1)
measurements. BESS is modeled as the controllable source of
active and reactive power, and is based on measured voltage where
characteristics of the OPzS batteries as a function of the capacity UI 10 battery voltage at constant discharging current 250 A
at different constant discharging currents. and 10-h discharging time as a function of the per-
Temperature dependency of the battery voltage is an impor- centage value of rated capacity;
tant aspect of BESS modeling. The battery system at TAB UI 5 battery voltage at constant discharging current 430 A
Mezica is installed inside the production hall where the am- and 5-h discharging time as a function of the per-
bient temperature does not vary significantly. As previously centage value of rated capacity;
mentioned, the battery model should be primarily used for de- UI 3 battery voltage at constant discharging current 625 A
termining the active power reference value when reducing peak and 3-h discharging time as a function of the per-
load of a certain load diagram that has to be determined by a centage value of rated capacity;
forecast. It is believed that the uncertainty of the forecast has UI 1 battery voltage at constant discharging current
stronger influence on overall accuracy than the voltage temper- 1300 A and 1-h discharging time as a function of
ature dependency. Therefore, we decided to exclude the temper- the percentage value of rated capacity;
ature dependency of the battery voltage from the model. UI 0.5 battery voltage at constant discharging current
Charging of the battery system is another important issue. 2050 A and 0.5-h discharging time as a function
At the start of simulation it is assumed that the battery is fully of the percentage value;
charged, since discharges are never more frequent than on con- UI 0.33 battery voltage at constant discharging current
secutive days, providing adequate time for full recharge. 2700 A and 0.33-h discharging time as a function of
As seen in Fig. 1, the battery manufacturer, TAB Mezica, gave the percentage value of rated capacity;
battery characteristics in a nonstandard manner. The battery ca- UI 0.25 battery voltage at constant discharging current
pacity is given on the abscissa-axis expressed as percentage 3100 A and 0.25-h discharging time as a function of
of the rated capacity (2500 Ah) at 10 hour discharging cur- the percentage value of rated capacity; and
rent (250 A). Voltage characteristics are normally given as the Cp2500 percentage value of rated 10-h capacity; for given
function of discharging time. The reason for this kind of repre- batteries 100% means 2500 Ah.
sentation of the battery characteristics lies in the possibility of It is evident from Fig. 1 that at currents higher than 250 A, the
easier determination of the already removed capacity at a certain actual capacity of the battery is lower than the rated capacity.
point of discharging. After that, the remaining capacity of the Maximal capacities for different discharging currents are given
battery can be determined for the next period of the discharging in Table I. In the last column the percentage values with regard
process. We can establish with certainty either that the battery to the 10 hour capacity (2500 Ah) are presented.
can still be discharged under a certain current, or that this is By multiplying voltage characteristics with the constant dis-
not possible due to battery exhaustion. On the abscissa-axis, the charging currents and the number of battery cells, power char-
battery removed capacity percentage is given. acteristics as a function of capacity are obtained:
Voltage characteristics at constant discharging currents, given
PI 10 = ns UI 10 I10
in Fig. 1, are interpolated by the third-order polynomials as
follows: PI 5 = ns UI 5 I5
SIMULATION MODEL FOR DISCHARGING
PAPIC: 611

TABLE I With (1), we obtain the voltage values for the two charac-
MAXIMAL BATTERY CAPACITIES FOR DIFFERENT DISCHARGING CURRENTS
teristic points at a given capacity of 50%: UI 5 = 1.950 V and
UI 3 = 1.932 V. After calculating power characteristics with (2)
at the same capacity value, the demanded power of 274 kW
ranges between PIk5 = 229.75 kW and PIk3 = 330.86 kW. Now,
the battery cell voltage and current can be calculated as follows:
  P k PIk5
U k = UIk5 UIk5 UIk3 = 1.942 V
PIk3 PIk5
Pk
Ik = = 514.93 A. (3)
ns U k
For different input power values, the appropriate closest
PI 3 = ns UI 3 I3 higher and lower power and voltage characteristics should
be used. By integrating the current during the simulation, online
PI 1 = ns UI 1 I1
corrections to the battery capacity are made:
PI 0.5 = ns UI 0.5 I0.5
k k 1 I k t
PI 0.33 = ns UI 0.33 I0.33 Cp2500 = Cp2500 + 100%, (4)
2500 Ah
PI 0.25 = ns UI 0.25 I0.25 (2) where t represents a time integration step; I k is the magni-
tude of the battery current in a certain integration step. It is
where assumed to be a constant value for the time integration step,
PI 10 power of the battery system at constant discharging which should be small enough to avoid numerical instability;
current 250 A and 10-h discharging time as a function generally, it depends on the time constants of the phenomena
of the percentage value of rated capacity; being simulated.
PI 5 power of the battery system at constant discharging This new battery capacity now serves as a basis for the calcu-
current 430 A and 5-h discharging time as a function lation of power characteristics for the next integration step. As
of the percentage value of rated capacity; previously mentioned, at the start of simulation it is assumed
PI 3 power of the battery system at constant discharging that the battery is fully charged.
current 625 A and 3-h discharging time as a function The limitations of the possible operation of the battery are
of the percentage value of rated capacity; included in the model. If the load current at a given capacity is
PI 1 power of the battery system at constant discharging too high, the inherent logic progressively reduces the loadin
current 1300 A and 1-h discharging time as a function so doing, the operating point follows the boundary line of the
of the percentage value of rated capacity; possible operating area. Without the mentioned logic, the bat-
PI 0.5 power of the battery system at constant discharging tery should be disconnected from the system, but in our case
current 2050 A and 0.5-h discharging time as a func- the battery is being further discharged at the reduced current in
tion of the percentage value of rated capacity; order to use the whole rated capacity (Table I). Under practi-
PI 0.33 power of the battery system at constant discharging cal operating conditions, there are two mechanisms for limita-
current 2700 A and 0.33-h discharging time as a tion of the battery current at given capacity. The first limitation
function of the percentage value of rated capacity; represents the rated power of the converter. Additionally, dur-
PI 0.25 power of the battery system at constant discharging ing battery discharging, the converter operates in active power
current 3100 A and 0.25-h discharging time as a control mode; the algorithm for the calculation of the power
function of the percentage value of rated capacity; reference value observes the dc voltage and appropriately re-
and duces the reference value in case the dc voltage is too low.
ns number of series connected battery cells. This algorithm is applied at the upper control level outside the
The active power that should be covered by batteries is the converter hardware.
input value. On the basis of this power, with linear interpolation By assuming that the battery is connected to the network over
between the appropriate two power and voltage characteristics, an IGBT converter, BESS also generates or absorbs reactive
the magnitude of the battery current and voltage in a certain in- power. It is assumed that the active power exchange with the
tegration step can be determined. To better illustrate the method system has priority, and that only the power difference, which
of linear interpolation, let us assume the following numerical can be calculated from the instantaneous active power demand
input values at the integration step k: and rated power of the converter, is available for the compensa-
1) P k = 274 kWdemanded power from the battery system tion of the reactive power. The reactive power reference value is
at the integration step k; the input value in the model and is supposed to be determined
k
2) Cp2500 = 50%capacity of the battery cells at the inte- at the upper control level, which observes the conditions at the
gration step k; point of the connection to the network where the power factor
3) ns = 274. should equal one.
612 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO. 2, JUNE 2006

Fig. 6. Comparison between the simulated and measured characteristic quan-


tities of BESS during load leveling operation.

used during the planning stage. The rated power of the converter
was 300 kW, with the battery system consisting of 274 series
connected OpzS battery cells.
Fig. 5. Flow chart of the BESS-model operations under the conditions of Fig. 6 shows the operation of the system during the load
digital simulation in an arbitrary integration step. leveling operation. The presented case reflects the characteristic
load diagram of TAB Mezica. The measured values of the active
power on the network side and the load power are presented
According to Fig. 5, the resumed operations with the BESS in the first graph. The reference power of 1.348 MW is set
model under the conditions of digital simulation in an arbitrary considering the peak power forecast during the peak daily tariff
integration step are as follows. for a certain day. During the higher daily tariff, the reference
1) Active and reactive power demand determination on the value may be increased by 15%. The second graph shows the
ac side of the system with BESS; measured power supplied from BESS; this power diagram was
2) Load current calculation of the battery by taking into ac- used as the input in the simulation model. The simulated and
count power and voltage characteristics at a given battery measured values of battery voltage and current are presented in
capacity; the third and fourth graph in Fig. 6. It is evident that the simulated
3) Consideration of the battery operation boundaries and pos- and measured data are in good agreement. The relative value of
sible load current reduction; the remaining battery capacity and the energy supplied by the
4) Calculation of the battery capacity change with regard to batteries are shown in the last graph in Fig. 6.
the actual load current and determination of the battery Further comparison between the simulated and measured data
capacity for the next integration step; was performed and the results were always similar to the ones
5) Calculation of available power for the reactive power com- represented in Fig. 6.
pensation; and
6) Actual covering of the active and reactive power by con-
C. Simulation of Supplying Different Load Patterns
sidering the stated limitations and battery condition.
In the next stage, the simulation of supplying different load
patterns was performed. The trace of the battery capacity during
B. Comparison of Simulation Results With Measured Data
discharging with variable load current depends on the type or
The purpose of the first set of simulations performed by the pattern of the load that should be covered by BESS. For the four
derived battery-discharging model is to compare the simulated different examples, it is assumed that BESS is used to supply the
results with the measured ones. When BESS at TAB Mezica same amount of energy (1.125 MWh), but in different operating
was put into operation, the measurement data were available. regimes. In the time frame of 4.5-h, the system consisting of 274
Therefore, it was possible to test the derived simulation model series connected battery cells follows different active power
SIMULATION MODEL FOR DISCHARGING
PAPIC: 613

Fig. 7. Characteristic quantities of BESS when supplying different load patterns.

patterns while being discharged; we assumed that there is no supplied from BESS equals 1.112 MWh and the remaining ca-
reactive power exchange with the system. pacity amounts to 10.8% of the rated value. In the second and
Results of the simulation with the developed BESS model third case, BESS operates without restrictions; at the end of the
are shown in Fig. 7. The actual and reference values of the operating cycle the supplied energy amounts to 1.125 MWh. In
time dependent load diagrams covered by BESS are given for both cases, the remaining capacity equals approximately 14%
different cases in the top graphs, followed by the battery voltage of the rated value. The results are represented in Figs. 7(b) and
and current traces. In the bottom graphs, the relative values (c). In the fourth case, shown in Fig. 7(d), at the interval be-
of the remaining battery capacity with regard to the rated 10 tween points A and B the load current has to be reduced again;
hour capacity (2500 Ah), and the energy being supplied by the with reduced load the system returns to the allowed operating
batteries, are shown. area. The supplied energy in this case amounts to 1.109 MWh
In the first case, the batteries are discharged by constant at 15.5% of the rated capacity.
power; by decreasing the battery capacity progressively, the Considering the required power of the converter, the first case
battery voltage drops and the current increases. In Fig. 7(a) we of discharging is preferable, but BESS in this case supplies less
can see that BESS at the interval between points A and B oper- energy than required and the remaining capacity is the lowest.
ates on the boundary line, which means that the load current is For the batteries, it is certainly most convenient if the load is
partly reduced. At the end of the 4.5 hour interval, the energy reduced toward the end of the discharging cycle, which can be
614 IEEE TRANSACTIONS ON ENERGY CONVERSION, VOL. 21, NO. 2, JUNE 2006

Fig. 8. Characteristic quantities of BESS during load leveling operation for different active power reference values. (a) 1.3 MW. (b) 1.4 MW.

observed in the second and third example of the discharging batteries are further discharging up to point C, where current
pattern. reduction starts again. BESS is due to the exhaustion untimely
switched off at point D. At that moment, the actual power at the
network side exceeds the reference value for 203 kW, and peak
D. Simulation of Supplying Characteristic Peak Load
load shaving is not successful.
The BESS model was also used for the simulation of a char- In the second case, shown in Fig. 8(b), the set reference
acteristic peak load supply. In the load model, the characteristic value equals 1.4 MW. During the whole observation period,
measured load diagram at the factory site between 7:00 and BESS operates in the normal operating area, peak load shaving
15:00 was implemented. The task of the fully charged BESS is successful, and the active power reference value was not
was to cover the load above the given reference value of the exceeded. At the end of the discharging cycle, the remaining
active power. The rated power of the converter was assumed capacity equals 40.7% of the rated value. The energy being
to be 300 kW, with the battery system again consisting of 274 supplied from BESS in the first case equals 1.252 MWh, and in
series connected OpzS battery cells. the second equals 0.740 MWh.
The simulation of the battery discharging was performed for
the two different reference values of the active power. The traces
of some characteristic BESS quantities are shown in Fig. 8. In
both cases, the load active power and the same active power IV. CONCLUSION
reduced by the amount contributed by BESS are shown in the The evaluation of the Ampere-hour capacity of the battery
top graphs. The actually supplied and demanded power from needed for load leveling during a period of several hours is
BESS are presented in the second graphs, followed by the battery very important when using BESS as an active power peaking
voltage and current traces. The relative value of the remaining station. The discharging simulation model of the battery that
battery capacity with regard to the rated 10 hour capacity Cp2500 , was developed for this purpose takes into account the battery
and the energy W being supplied by the batteries, are shown in voltage dependency on the capacity and current, and is based
the bottom graphs. on the performed battery measurements at constant discharging
BESS covers the load above the active power reference value currents. By using the aforementioned model, the simulation
that is, in the first case, set to 1.3 MW; this value is at 13:00 of the characteristic load leveling operation was performed and
increased by 15%, as seen in Fig. 8(a). Batteries are successfully compared to the measured voltage and current profiles. As pre-
supplying the load up to a point A, where the battery current viously mentioned, practically all savings when using BESS are
approaches the boundary of the permitted operating area. At this achieved by reducing peak load. The simulation results prove
point, the current reduction starts, which means that the actual the significance of the proper setting of the active power refer-
power at the network side exceeds the set reference value. At ence value for successful shaving of peak loads. The comparison
point B, the system returns to the normal operating area, and between the simulated results and the measured ones validated
SIMULATION MODEL FOR DISCHARGING
PAPIC: 615

the derived modelvery good agreement between both sets of REFERENCES


results was achieved.
[1] L. H. Walker, 10-MW GTO converter for battery peaking service, IEEE
The derived discharging model can also be used for the BESS Trans. Ind. Appl., vol. 26, no. 1, pp. 6372, 1990.
capacity planning where the load current profile plays a signifi- [2] C. D. Parker, Lead-acid battery energy-storage systems for electricity
cant role. After determining the required capacity according to supply networks, J. Power Sources, vol. 100, pp. 1828, 2001.

[3] I. Papic, P. Zunko, A. Krajnc, D. Povh, T. Schultheis, M. Weinhold,
the operating conditions of the system, suitable standard battery and R. Zurowski, 300 kW Battery energy storage system using an IGBT
cells available on the market may be selected. At this stage, it converter, in Proc. IEEE Power Eng. Soc. Summer Meeting, vol. 100,
no. 12, Elsevier, ISSN: 03787753, Jul. 1999, pp. 12141218.
is also important to make allowance for battery aging. For the [4] Z. M. Salameh, M. A. Casacca, and W. A. Lynch, A mathematical
integration of the model into a general capacity planning tool, model for lead-acid batteries, IEEE Trans. Energy Convers., vol. 7, no. 1,
battery manufacturers should provide voltage characteristics for pp. 9398, 1991.
[5] M. A. Casacca and Z. M. Salameh, Determination of lead-acid battery
different types and sizes of battery cells. These characteristics capacity via mathematical modeling techniques, IEEE Trans. Energy
could be classified according to the temperature ranges and the Convers., vol. 7, no. 3, pp. 442446, 1992.
type of positive plates used as building blocks of battery cells.
The usage of BESS under the new conditions of the open
electricity market should be pointed out as another problem. In
this case, it is, on the one hand, very difficult to perform the
viability assessment of the introduction of a new BESS into a
supply network, and on the other hand, the operation of existing
installations requires certain modifications. In addition to the
known planning uncertainties, we have to deal with the uncer-
tainties related to the variable prices of electricity. In particular, Igor Papic (S97A99M00) received the B.Sc.,
M.Sc., and Ph.D. degrees, all in electrical engineer-
the price of peak power is, under the new conditions, relatively ing, from the University of Ljubljana, Slovenia, in
lower than in the classical tariff system, which means that the 1992, 1995, and 1998, respectively.
savings are also smaller then before. This new problem arising From 1994 to 1996, he was with the Siemens
Power Transmission and Distribution Group in Erlan-
from ongoing worldwide deregulation and competition in dis- gen, Germany. Currently, he is an Associate Professor
tribution systems will be the main subject of our future work in on the Faculty of Electrical Engineering in Ljubljana.
this field. The devolved simulation model proved to be a very In 2001, he was a Visiting Professor at the University
of Manitoba, Winnipeg, MB, Canada. His research
effective tool for finding optimal operating solutions to existing interests include control and modeling of FACTS de-
and, hopefully, future battery storage systems. vices and power conditioners.

You might also like