3.0 Responsibilities
3.1 Initiator
The Initiator is responsible for raising the non-conformance or hazard with local
management using the standard form. He is also responsible for discussing the
non-conforming situation with the Area Authority to clarify the problem.
Only persons defined as competent by the Management can act as Area Authority.
The Area Authority carries out the risk assessment for the hazard or non-
conformance and fills in the box on the form.
Based on the risk rating, he defines corrective or preventive actions and assigns
people to the task. He also specifies the completion date.
The HSE Department maintains a database of all actions raised. A monthly report
is also prepared for Management indicating the status of all actions.
Every six months the HSE Department carries out an Audit to assess conformance
with the procedure and guidance.
The Senior HSE member retains all audit reports for a period of two years.
Once a year the HSE General Manager summarises the effectiveness of the
System for the MDs at the HSE Management Review.
Issue 2.1 January 2005 Next Revision Date - 31/12/07 Page 1of 5
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-08
Paper Copy Valid one month from Print Date
The Field Manager reviews the corrective action forms monthly at the Field HSE
Committee meeting.
4.0 Procedure
4.1 Initiation
Reporting method and priority depends on the potential severity of the event.
Guidelines for reporting are shown in Appendix 2.
Having identified that work is needed the Initiator should discuss the problem
with the Area Authority. The Area Authority then carries out a risk assessment of
the situation to determine the priority for action.
He circles the most appropriate box on the form taking into account both potential
severity and the frequency or likelihood of a problem occurring. These categories
then describe the scale of the corrective or preventive action needed.
Preventive actions are aimed at the underlying causes and should prevent the same
fault occurring in other areas.
C Corrective Action
D Record only
He then identifies the relevant corrective actions, assigns people to action them
and specifies the completion date.
Issue 2.1 January 2005 Next Revision Date - 31/12/07 Page 2of 5
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-08
Paper Copy Valid one month from Print Date
The Area Authority then distributes the form to the copyholders specified and to
those responsible for any actions.
Original Initiator,
Copy 1 Area Authority,
Copy 2 Field Manager, Division Manager
Copy 3 HSE Department
The HSE Department assign a unique serial number to each Corrective Action
Form and enter the details in a Corrective Action Database for analysis and
follow-up.
The Area Authority prepares a monthly status report of all Corrective Actions
raised for the HSE Committee Meeting.
Every six months the HSE Department carry out an audit of the system and report
their findings to Management.
4.6 Closure
Once the actions on the form are completed the Area Authority passes the form
the Field or Division Manager for comment and signing off.
5.0 Administration
The Area Authority keeps these completed and closed Corrective Action Forms in
a file for a minimum of two years.
In the event of any situation being discovered that could have been the result of an
accident or incident, then this should still be reported through the
Accident/Incident Reporting and Investigation Procedure.
Issue 2.1 January 2005 Next Revision Date - 31/12/07 Page 3of 5
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-08
Paper Copy Valid one month from Print Date
Appendix 1
Immediate Corrective
Potential A Action
Severity
+ Investigation
Major C B A A A
+ Preventive Action Plan
Serious B B A A A Immediate Corrective
B
Action
Minor D C B A A
+ Preventive Action Plan
Negligible D D C B B C Corrective Action
Negligible Rare Often Routine Continuous D Record Only
Likelihood or Frequency
Preventive Actions
Field Comments:
Manager
Original Iinitiator Copy 1 Area Authority Copy 2 Field Manager Copy 3 - HSE
Issue 2.1 January 2005 Next Revision Date - 31/12/07 Page 4of 5
HSE Procedures
SUEZ OIL COMPANY Cairo-HSE-P-08
Paper Copy Valid one month from Print Date
Major Fatality More than $50000 Long term (>2 year) damage and poor Immediate Report verbally to MDs.
potential for recovery to normal state and
Broken Bones costing more than $50000 in direct loss or A/I written report faxed to MDs/O-
clean up costs. 1/HSE within 1 day.
Disabling Injuries
Invoke major emergency plan.
Serious LTIs $5000-$50000 Leads to immediate environmental damage A/I written report faxed to MDs/O-
lasting for up to 2 years and costing $5000 to 1/HSE within 1 day.
Strains $50000 in immediate clean up or control
costs.
Serious Cuts
Non-compliance with legal requirement.
MTCs
Minor Small cuts self treated Less than $5000 Monitoring or clean up costs less than $5000. A/I written report faxed to O-1/HSE
without LT. within 3 days.
High Potential Injury Accident Any event that could Immediate Report verbally to MDs.
or Incident lead to Fatality, Broken
Bones, Disabling A/I written report faxed to MDs/O-
Injuries 1/HSE within 1 day.
High Potential Other Loss Any event that could Any event that could lead to major scale A/I written report faxed to MDs/O-
Accident or Incident lead to major scale 1/HSE within 3 days.
Other Incident No injury No Property, Process, No discharge, spillage or breach of legislation Report through A/I system
Production loss, depending on potential.
Damage
Major potential as major accident,
serious potential as serious accident
etc.
Issue 2.1 January 2005 Next Revision Date - 31/12/07 Page 5of 5