Professional Documents
Culture Documents
15,800
80 15,400 16
14,000
70 14
Pressuredrop (bar)
Hold-up (m3)
60 55.0 56.1 12
53.3 53.9
50 46.6 10
41.8 41.3 8,400 8,400
40 8
30 6
4,600
20 4
???
10 2
0 0
Field test 95
Field Test 95 Shell
SRTCA Pipesim1
B&B Pipesim2
B&B-TD Pipesim3
B&J-rev Pipesim4
MB Pipesim5
OlgaS
10
66 %
Test: 7-1995 GWA only
40
50% 50%
Pressure drop (bar)
34 % NRA production only
32 %
28 % 29 % 30
25% 25%
11 %
20
?? -1 % 0%
0% 0%
Field Test
Field test 95
95 Shell
SRTCA Pipesim1
B&B Pipesim2
B&B-TD Pipesim3
B&J-rev Pipesim4
MB Pipesim5
OlgaS 10
NRA only
GWA + NRA
Onshore pressure 66.6 bara GWA only
-25% -25%
0
-45 % 10 20 30 40 50 60 70
Hold-up compared to SRTCA calculations
Throughput - Total Massflow (kt/d)
-50% -50%
11 12
Thousands
MLNG-Dua system
48,100
90
Offshore - 2 fields 80
Pressure drop 40,700
40
Hold-up
CGR - upto 60 bbl/mmscf
Pipelines - 38, 160 km 70
- 2 x 36, 120 km
Pressuredrop (bar)
60 30
Hold-up (m3)
Onshore - LNG plant 24,000 48.6 51.7 46 25,900
- Liquid stab 50
36.3
Liquid hold-up 40 20
25,000-80,000 m3 (7-20 %)
30
Ops. Hold-up variations
up to 20,000 m3 20 10
Pipeline Profile / Operations Induced Liquid Surge Concept Study - Example Project
KME
KMNW 24 x 25 Km
50
24 x 13 Km KBB (Operating Hub)
25
M1 E11
M1 start-up
MLNG 24 x 15 Km
0
KMSW ?? x 120 Km Limau
-25
Elevation (m)
-50
M3 EW
-75 Usukan Bay
-100
KK
-125
-150
0 25 50 75 100 125 150 175 200 225 250 275 300
Distance (km)
SM
KNDP-A
NOT TO SCALE
M3 - Subsea injection
Injection point slopes down to M1
M3 production & M1 shutdown Phase I - KBB field to shore, 120 km
M3-M1 leg fills-up with M3 liquid
Large scale Gas to Liquid plants SMDS
Liquid plug formed of 25 km 38 (18,000 m3) Base plan Full well stream transport to plant
15 16
Elevation (m)
-40
Water 800 bbl/d -60 Unmanned Platform LNG peakshaving plant
CO2 2.5 % -80
Increased reaction time to problems
-100
Maintenance
Reduced Availability
-120 Only one SMDS train in operation for
-140
some 30 days a year
0 20,000 40,000 60,000 80,000 100,000 120,000
Distance (m)
19 20
15,000
Two SMDS Trains + Dom gas Two SMDS Trains + Dom gas
10,000
80
5,000
70 0
0 5 10 15 20 25 0 5 10 15 20 25
Throughput (m m sm 3/d) Throughput (mmsm3/d)
21 22
Costs (MMUS$)
36 inch - Hydraulic in-stable, NOT acceptable
Adequate solution for secure supply for SMDS plant available
34 inch 245 Slugcatcher - 6000 m3 - limited linepack
32 inch 195 Slugcatcher - 4000 m3 - limited linepack
30 inch 165 Slugcatcher - 2000 m3 - no linepack Only an Integrated approach between Upstream & Downstream
Will result in a good match of production system and Plant
Avoid systems which are very difficult to operate
2 x 24 inch 195 Slugcatcher - 1500 m3 - Adequate Linepack
- Selected option
Integrated Upstream & Downstream project
resulted in optimum solution
25 26
Liquid flowback into the well (after unplanned shutdown) is not acceptable
27 28
Multiphase Flow Pipeline Systems widely applied in the Oil & Gas
Industry
Field experience & feedback to modelling tools is vital for progressing the
extended reach
29 30