Professional Documents
Culture Documents
AE010801-PT1I1-GD06-0755
date: 11/16/2015
PDVSA - ; Proyecto Ingeniera; Procura; Construccin y Arranque de la Infraestructura de page: 1/1
External Addressees
Chrono Name Action Chrono Name Action
Edmar Pena (e) Revised for
Construction
Edgar Torrealba (e) Revised for
Construction
Juan Vincent Santano (e) Revised for
Construction
Jesus Serrano (e) Revised for
Construction
Arelys Mota (e) Revised for
Construction
Raul Altuve (e) Revised for
Construction
Omar Santos (e) Revised for
Construction
Internal Addressees
Rojas Douglas/Planner and Controller (e)
Augusseau Jeremy/Project Controls Manager
(e)
McAdams Dick/Prinicipal Associate Subsea
(e)
Largman Rogerio/Principal Specialist (e)
Yousefi David/Installation Engineer (e)
Jewett Jeff/Subsea Project Manager (e)
Wright David/Onshore Project Manager (e)
Cremer Kevin/Dir Project Engineering (e)
Transmitted Documents
Piping ISO Pkg 022 - Gasducto-PAGMI Interconnect Spools
TF027337-002-NM-1350-022 rev.1 : Piping ISO Pkg 022 - Gasducto-PAGMI Interconnect Spools
INTERNAL
-------------------
X Rojas Douglas / Planner and Controller(e)
X Augusseau Jeremy / Project Controls Manager(e)
Murguia Elizabeth / Inspection Coordinator
Bradford Wade / Administrative Inspection Coordinator
Palmer Rick / Project QA/QC Manager
Chapa Isaac / HSE Manager
Grafing Austin / Procurement
Rios Ruben / Procurement
Ross Joe / Sub Contracts
Quinones Belkis / Admin Contracts
Hoggard Allison / Document Control Lead
X McAdams Dick / Prinicipal Associate Subsea(e)
Uppu Kalyan / Priniciple Specialist
X Largman Rogerio / Principal Specialist(e)
Feizkhah Kevin / Principal Specialist
Lyssy Jim / Senior Staff Specialist
Novosad Dawn / Instrument Engineer
Bratton Timothy / Mechanical Lead
Peterson Charles / Supervisor Engineer - Topsides
Nawagamuwa Chet / Project Engineer 1
X Yousefi David / Installation Engineer(e)
Babin Chelcie / Installation Engineer