Professional Documents
Culture Documents
I to coat and bond loose material particles on the surface of the base,
II to harden or toughen the base surface to provide a work platform for construction
equipment,
III to plug capillary voids in the base course surface to prevent migration of
moisture,
IV to provide adhesion between the base course and succeeding asphalt course.
Without tack coat the asphalt layers in a road way may separate which reduces the
structural integrity of the road and may also allow water to penetrate the structure.
I The higher the viscosity of the tack layer, the more shear strength the
overall structure will have.
II Help the overlay adhere to the underlying, weathered pavement surface
III To achieve uniform coverage over the entire surface to be paved
Asphalt pavement, to keep in simple terms, is primarily rock and/or stone and gravel, along
with a binder. The rock, or aggregate, is held together with this binder also known as asphalt
cement. The binder is created from the distillation process of certain crude oils. Maintaining
this binder is essential in prolonging the deterioration of asphalt surfaces. Rain, U.V. rays, and
chemicals, as they are introduced into the asphalt, will degrade the binder and thus begin the
degradation process of the asphalt. This will continue and create a surface that turns brittle. To
reduce the effects of these elements, it is important to implement a maintenance program that
utilizes sealcoating to extend the life of your parking lot or driveway.
Sealcoating will
I provide a layer of protection blocking out the elements: water, oils, and U.V. damage.
II provides a slip resistant surface with a deep black finish that beautifies the parking lot or
driveway.
Excavations below the ground level arising out of removal of trees, stumps, etc., should be filled
in layers with suitable material and compacted to the specified density given by the Engineer.
Ant-hills both above and below the ground shall be removed by excavating to a suitable depth as
directed by the Engineer. Cavities in the ground after removal of ant-hills shall be filled with
appropriate material and properly compacted to the specified density.
Obtain materials (soil) for embankment from approved sources. Preference should be given to
materials that are suitable and become available from nearby road excavation.
The embankment shall be built sufficiently wider
(about 300 mm on either side of Roadway) than the specified formation width so that surplus
material at the edges may be trimmed to ensure proper compaction of the edges and side slopes.
For embankment less than 1.0 m high over natural ground, the ground surface should be
loosened up to a minimum depth of 150 mm by ploughing or scarifying and compacted to
the specified density.
If the granular/ black topped surface lies within 0.50 m - 1 m of the new sub-grade level, the
same should be scarified to a depth of at least 50 mm for achieving bond between old and
new material.
For embankment over ground not capable of supporting equipment, successive loads of
embankment materials should be spread in a uniformly distributed layer of adequate
thickness to support the equipment and to construct the lower portion of the embankment.
The size of the coarse material in the mixture of earth used for embankment construction should
ordinarily not exceed 75 mm.
The soil should be spread over the entire width of the embankment in layers not exceeding 150
mm compacted thickness. The clods should be broken to less than 75 mm size. Each layer at a
moisture content within 2 % of the optimum moisture content.
Each layer should be compacted to at least 97 percent of the Standard Proctor Density.
The top 300 mm of the embankment constituting the sub grade should be compacted to 100 percent
Standard Proctor Density.
When the width of the widened portions is insufficient to permit the use of conventional rollers,
compaction shall be carried out with the help of small vibratory rollers/ plate compacters/ power
rammers or any other equipment approved by the Engineer.
The material used in embankment, sub-grade, shoulders, etc. shall be soil, moorum, gravel, a
mixture of these.
Rock when encountered in road excavation shall be removed upto the formation level. Where
unstable shales or other unsuitable materials are encountered at the formation level, these shall be
excavated to the extent of 500 mm below the formation level.
If the subgrade soil does not possess the requisite engineering properties like highly plastic black
cotton soil and other weak soils yielding very low soaked CBR values, the same should be improved
in strength (CBR) and workability by treatment with additives like lime/cement etc. as described
in sub-sections 403 and 404 or by mechanical stabilization.
Any fill material which yields a maximum dry laboratory unit weight of less than 16.5 kN/
m3 determined as per IS:2720 (Part 7) shall be considered unsuitable for use in subgrade.
Atterberg limits: the material passing 425 micron sieve when tested according to IS: 2720
(part 5) shall have liquid limit and plasticity index not more than 25 and 6 percent respectively.
Surface Regularity
The maximum permitted difference between the sub-base and 3 m straight edge shall be 12 mm
for longitudinal profile and 10 mm for cross profile. The cross profile should conform to the
required camber.
TABLE 401.2 : QUALITY CONTROL TESTS PRIOR TO CONSTRUCTION of GSB & Embankment.
TABLE 401.3 : QUALITY CONTROL TESTS DURING CONSTRUCTION of GSB & Embankment.
Lime treatment is generally adopted for silty clays and clayey soils, including black cotton soils.
Reduction
in plasticity index and development of strength in lime soil mixes depend upon the type and content
of
clay in the soil.
For soils which do not respond to lime treatment and where comparatively higher and faster
development
of strength and durability characteristics is needed, especially for waterlogged and high rainfall areas,
soil stabilization with cement is resorted to. Granular and sandy soils are most suitable for cement
stabilization
Compaction of cement stabilized material shall be completed within two hours of its mixing.
The compacted soil-cement mix should be cured by moist curing with water for a period of 7 days
after which subsequent pavement courses should be laid to prevent the surface from drying out
and becoming friable.
WBM-The road whose wearing course consists of clean crushed aggregates,
mechanically interlocked by rolling and bound together with filler material and
water laid on a well compacted base course, is called water bound macadam
(W.B.M) road.
Water bound macadam is superior in quality because the materials are carefully
graded and the resulting mass is almost void less compacted mass
The stone pieces used in water bound macadam road are keyed together by
means of sand and clay and no other cementing material is used. When a fast
moving vehicle passes over a W.B.M. road, the slurry of sand and clay is sucked
out by pneumatic wheel tires, the stone pieces get disturbed and finally road
surface is disintegrated. Due to this, the W.B.M. roads are not suitable for fast
moving vehicles with pneumatic wheels but suited for slow moving iron wheeled
traffic such as tongas, bullock carts etc.
Coarse aggregate can be crushed or broken stone, crushed slag, over burnt
brick aggregate, kankar, laterite meeting the prescribed requirements
Rolling shall proceed from inner edge to outer edge at the super-elevated portions and
from the edges towards the centre in other portions. The edge should be first compacted with
roller running forward and backward.
Continue dry rolling and brooming till no more screenings(Moorum or Gravel) can be forced into the
voids of coarse
Aggregates
The process of water sprinkling, sweeping and rolling should continue till the resulting slurry
forms a wave ahead of roller
Where
the surface irregularity exceeds the tolerances, the WBM layer should be scarified to its full depth
over the affected area and corrected by adding or removing and replacing with fresh material
TESTS for WBM :Aggregate Impact Value / Flakiness Index / Soundness Test with NaSO4 & MgSO4
/ Grading Requirements as per 405.2
WMM
For heavily trafficked highways, the granular bases are constructed using Wet Mix Macadam (WMM). The
WMM is a specification in which well graded aggregate is mixed with water in a mixer and the mix is laid by
a paver and rolled by a roller.
SHOULDER
The construction of shoulders (whether hard/gravel or earth with brick or stone block edging) on
either side of the road pavement
In order to shed off surface water, the required cross-fall should be maintained during all stages
of construction. Normally cross-fall on shoulder should be 1 per cent higher than the camber on
the main carriageway.
Do not compact the shoulder layer before the
compaction of the adjoining pavement layer
The prime coat should be applied only on the top most granular base layer, over which bituminous
treatment is to be applied. The granular base surface should be swept clean of dust and loose
particles and where required, lightly and uniformly sprinkled with water to moist the surface.
A very thin layer of coarse sand may be applied to the surface of the primer to prevent it from
getting picked up under the wheels of vehicles delivering materials for construction of bituminous
layer
Bituminous Macadam
Apply tack coat over the base preparatory to laying of the bituminous macadam.
Commence initial rolling with 80-100 kN rollers (three-wheel or tandem type), beginning from
the edge and progressing towards the centre longitudinally. On super elevated portions, rolling
should progress from lower to upper edge parallel to centre line of pavement
Any high spots or depressions noticed after the roller has passed over the whole area once should
be corrected by removing or adding premixed material. Rolling should recommence thereafter.
Cover the bituminous macadam with the wearing course within a period of 48 hours. If there is
any delay in providing wearing course the bituminous macadam surface should be covered with
a seal coat before opening to traffic.
SEAL COAT
Apply seal coat immediately after laying the bituminous course. The surface should be clean and
free of dust and extraneous material before application of the seal coat.
(i) Apply heated bitumen with a temperature between 150 0C and 1630C uniformly with the
help of a bitumen sprayer.
(ii) Immediately thereafter, spread stone chips over the bitumen layer at a uniform rate,
preferably, with the help of a mechanical grit spreader so as to cover the surface completely.
(iii) Commence rolling with 80-100 kN rollers (3-wheel or tandem type), beginning from the
edge and progressing towards the centre longitudinally. On super elevated portions, rolling
should progress from lower to upper edge parallel to centre line of pavement. If required,
spread additional chips by hand to make up irregularities. Continue rolling operations until
all aggregate particles are firmly embedded and present a uniform closed surface.
HANDFEEL TESTS
bricks
(i) In efflorescence test, a sample brick is soaked in water for 24 hours and its appearance after
removal
from water, should be free from white patches, the total area not exceeding 50%. In case the
surface area exhibiting, patches exceed 50% of total area both the brick and water samples shall be
subjected to further testing for ascertaining suitability.
(ii) In water absorption test, a brick should not absorb more than 1/5 th of its dry weight after
immersion
in water for 24 hours.
(iii) Bricks are considered good when clear ringing sound is heard when two bricks are struck against
each other. A sample brick should not break when dropped flat on hard ground from a height of
about 1 m.
Correct firing promotes toughness. The bricks should not be under-burnt. A well burnt brick
when scratched with a finger nail should leave no impression.
Cement
(i) Thrust a hand into a cement bag. It must give cool feeling. There should be no lump inside.
(ii) Take a pinch of cement and feel between the fingers. It should give a smooth and not a gritty
feeling.
(iii) Take a handful of cement and throw it in a bucket full of water. The particles should float for
sometime before they sink.
(iv) Take about 100 gm of cement and mix it with water to make a stiff paste. Make a cake with sharp
edges. Put it on a glass plate and slowly take it under water in a bucket, without disturbing the
shape of cake. After 24 hours, the cake should retain its original shape and gain some strength.
(vii) Fineness: In the sieve test, 100 gm cement is correctly weighed and placed on 90 micron sieve.
Air
set lumps, if any, are broken down with fingers. The sample is sieved for 15 minutes and the
residue left on the sieve is weighed. The amount of residue should not exceed 10% for OPC.
(i) Presence of Silt or Clay: Rub a sample of sand between damp hands and note the discolouration
caused on the palm. If the sand is clear, the palm would be stained slightly. If the hands stay dirty
after sand has been thrown away, it indicates too much of silt or clay.
(ii) Sedimentation: Place, without drying, a sample of sand in a 200 ml measuring cylinder upto 100
ml mark. Add clean water upto 150 ml mark. Shake the contents vigorously and allow it to settle
for 3 hours. The height of the silt visible as a layer above the sand is expressed as a percentage of
the sand below.
Coarse Aggregate
(i) If the aggregates of a known quantity absorb more than 10 percent of their weight after 24 hours
immersion in water, they are considered porous and are avoidable.
(ii) If Mica inclusions persist on the surface, the stone aggregates shall be rejected as presence of
Mica
affects durability of concrete
Concrete
Workability: Take a handful of concrete in left hand and make a round ball with both hands. If a
ball can be maintained for a while, it is indicative of a workable mix. Any low or high content of
water cannot make a good ball of concrete.
If aggregates are suspect of likely positive ASR on the basis of past performance or any evidence,
it is always recommended that the aggregates are tested as per IS:2386 part 7(Alkali Aggregate
Reactivity) before they are approved for the use for making concrete
Penetration Resistance for all 3 150mm increments shall be recorded & SPT Value calculated from it.
SPT & Vane Shear Test shall be carried out as field test in case of Cohesive Soils
Field Record shall contain date cum time of boring , Location of boring wrt permanent benchmark &
Elevation of Ground Surface wrt Permanent Benchmark.
TERMINATION OF DRILLING
Weathered Rock- 10 m below soil-rock interface.
Soft Rock - 6 m below soft rock
Hard Rock - 3 m below hardrock
In case rock is never met even after drilling 15 metres , the matter shall be brought to the Design
Consultant.
Sub-consultant shall provide setting-out details with N-E of all boreholes & reduced level at top of
borehole.
Sub-consultant shall submit to client within 3 days , complete details of each borehole drilling after its
completion.