Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
PROJECT NUMBER.
NU A-6003.1 EOT (Rev- I) Mar -17 1055 03-Aug-14 A 14-Dec-17

MOBILIZATION
MOBILIZATIO 1053 03-Aug-14 A 14-Dec-17
MOB-01 Letter of Award 0 03-Aug-14 A
MOB-11 Site Handing Over 0 03-Aug-14 A
MOB-21 Mobilization Manpower & Equipment) 299 14-Aug-14 A 15-Jun-17
MOB-31 Temporary Services / Facilites 55 20-Aug-14 A 25-Oct-14 A
MOB-51 Receipt of Revised Route Approval 0 23-Sep-14 A
DMB-41 Demobilization 30 11-Nov-17 14-Dec-17
HOME OFFICE
OFFIC SERVICES 413 03-Aug-14 A 13-Feb-16 A
APPLY & RECEIPT
REC of NOC's 102 23-Sep-14 A 19-Jan-15 A
Jaffer Jadeed - Zakher 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ AADC Water 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ AADC Electricity 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ TRANSCO 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ ETISALAT 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ ADSSC 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ Municipality Irrigation 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ Roads 30 02-Nov-14 A 06-Dec-14 A
NOC-JJZ ADNOC 30 02-Nov-14 A 06-Dec-14 A
Udgat Almuwaiji
Almuw 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA AADC Water 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA AADC Electricity 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA TRANSCO 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA ETISALAT 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA ADSSC 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA Municipality Irrigation 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA Roads 30 23-Nov-14 A 27-Dec-14 A
NOC-UDA ADNOC 30 23-Nov-14 A 27-Dec-14 A
Natlah to Inte
Intercontiental R/A 30 19-Oct-14 A 22-Nov-14 A
NOC-NT AADC Water 30 19-Oct-14 A 22-Nov-14 A
NOC-NT AADC Electricity 30 19-Oct-14 A 22-Nov-14 A
NOC-NT TRANSCO 30 19-Oct-14 A 22-Nov-14 A
NOC-NT ETISALAT 30 19-Oct-14 A 22-Nov-14 A
NOC-NT ADSSC 30 19-Oct-14 A 22-Nov-14 A
NOC-NT Municipality Irrigation 30 19-Oct-14 A 22-Nov-14 A
NOC-NT Roads 30 19-Oct-14 A 22-Nov-14 A
NOC-NT ADNOC 30 19-Oct-14 A 22-Nov-14 A
Adgat Almuwaiji
Almuw 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA AADC Water 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA AADC Electricity 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA TRANSCO 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA ETISALAT 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA ADSSC 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA Municipality Irrigation 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA Roads 60 19-Oct-14 A 27-Dec-14 A
NOC-ADA ADNOC 60 19-Oct-14 A 27-Dec-14 A
Shk Khalifa S
Shabiya 70 23-Sep-14 A 13-Dec-14 A
NOC-SK AADC Water 70 23-Sep-14 A 13-Dec-14 A
NOC-SK AADC Electricity 70 23-Sep-14 A 13-Dec-14 A
NOC-SK TRANSCO 70 23-Sep-14 A 13-Dec-14 A
NOC-SK ETISALAT 70 23-Sep-14 A 13-Dec-14 A
NOC-SK ADSSC 70 23-Sep-14 A 13-Dec-14 A
NOC-SK Municipality Irrigation 70 23-Sep-14 A 13-Dec-14 A
NOC-SK Roads 70 23-Sep-14 A 13-Dec-14 A
NOC-SK ADNOC 70 23-Sep-14 A 13-Dec-14 A
Sanaiya (Naglah)
(Nag 60 05-Nov-14 A 13-Jan-15 A
NOC-SA AADC Water 60 05-Nov-14 A 13-Jan-15 A
NOC-SA AADC Electricity 60 05-Nov-14 A 13-Jan-15 A
NOC-SA TRANSCO 60 05-Nov-14 A 13-Jan-15 A
NOC-SA ETISALAT 60 05-Nov-14 A 13-Jan-15 A
NOC-SA ADSSC 60 05-Nov-14 A 13-Jan-15 A
NOC-SA Municipality Irrigation 60 05-Nov-14 A 13-Jan-15 A
NOC-SA Roads 60 05-Nov-14 A 13-Jan-15 A
NOC-SA ADNOC 60 05-Nov-14 A 13-Jan-15 A
Al Saad 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS AADC Water 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS AADC Electricity 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS TRANSCO 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS ETISALAT 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS ADSSC 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS Municipality Irrigation 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS Roads 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS ADNOC 60 11-Nov-14 A 19-Jan-15 A
NOC-ALS DOT 60 11-Nov-14 A 19-Jan-15 A
Abusamrah 90 23-Sep-14 A 05-Jan-15 A
NOC-AB AADC Water 90 23-Sep-14 A 05-Jan-15 A
NOC-AB AADC Electricity 90 23-Sep-14 A 05-Jan-15 A
NOC-AB TRANSCO 90 23-Sep-14 A 05-Jan-15 A
NOC-AB ETISALAT 90 23-Sep-14 A 05-Jan-15 A
NOC-AB ADSSC 90 23-Sep-14 A 05-Jan-15 A
NOC-AB Municipality Irrigation 90 23-Sep-14 A 05-Jan-15 A
NOC-AB Roads 90 23-Sep-14 A 05-Jan-15 A

Actual Work 1 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
NOC-AB ADNOC 90 23-Sep-14 A 05-Jan-15 A
Remah 60 13-Oct-14 A 21-Dec-14 A
NOC-RE AADC Water 60 13-Oct-14 A 21-Dec-14 A
NOC-RE AADC Electricity 60 13-Oct-14 A 21-Dec-14 A
NOC-RE TRANSCO 60 13-Oct-14 A 21-Dec-14 A
NOC-RE ETISALAT 60 13-Oct-14 A 21-Dec-14 A
NOC-RE ADSSC 60 13-Oct-14 A 21-Dec-14 A
NOC-RE Municipality Irrigation 60 13-Oct-14 A 21-Dec-14 A
NOC-RE Roads 60 13-Oct-14 A 21-Dec-14 A
NOC-RE ADNOC 60 13-Oct-14 A 21-Dec-14 A
NOC-RE DOT 60 13-Oct-14 A 21-Dec-14 A
CONSTRUCTION DOCUMENTATION
CONSTRUCTI 81 21-Aug-14 A 05-Mar-15 A
SUBMISSION 60 21-Aug-14 A 15-Feb-15 A
PLN-11 Planning Package 55 21-Aug-14 A 15-Feb-15 A
HSE-21 HSE Plan 15 21-Aug-14 A 07-Sep-14 A
QUA-31 Quality Plan 60 21-Aug-14 A 01-Nov-14 A
APPROVAL 66 08-Sep-14 A 05-Mar-15 A
HSE-31 HSE Plan 21 08-Sep-14 A 01-Oct-14 A
QUA-41 Quality Plan 21 02-Nov-14 A 25-Nov-14 A
PLN-21 Planning Package 21 16-Feb-15 A 05-Mar-15 A
SUB-CONTRACTOR
SUB-CONTRA 239 28-Sep-14 A 05-Dec-15 A
SUBMISSION 225 28-Sep-14 A 30-May-15 A
SUB-51 Instrumentation works Sub-Contractor 7 28-Sep-14 A 06-Oct-14 A
SUB-11 Soil Investigation Subcontractor 7 27-Oct-14 A 04-Nov-14 A
SUB-41 Hypochlorination unit Sub-Contractor 7 11-Dec-14 A 18-Dec-14 A
SUB-21 NDRC Sub-Contractor 7 15-Jan-15 A 21-Jan-15 A
SUB-61 Reinstatement Sub-Contractor 7 15-May-15 A 18-May-15 A
SUB-31 Surge Protection Sub-Contractor 7 20-May-15 A 30-May-15 A
APPROVAL 232 09-Oct-14 A 05-Dec-15 A
SUB-111 Instrumentation works Sub-Contractor 21 09-Oct-14 A 10-Dec-14 A
SUB-71 Soil Investigation Subcontractor 21 05-Nov-14 A 25-Nov-14 A
SUB-101 Hypochlorination unit Sub-Contractor 21 13-Jan-15 A 05-Dec-15 A
SUB-81 NDRC Sub-Contractor 8 22-Jan-15 A 01-Apr-15 A
SUB-121 Reinstatement Sub-Contractor 21 04-Feb-15 A 10-Aug-15 A
SUB-91 Surge Protection Sub-Contractor 21 01-Jun-15 A 10-Jun-15 A
MATERIAL SU
SUBMISSION 145 03-Aug-14 A 21-Jul-15 A
MAS-11 HDPE Pipes and Fittings 40 03-Aug-14 A 13-Oct-14 A
MAS-21 Ductile Iron Pipes & Fittings 40 03-Aug-14 A 06-Dec-14 A
MAS-141 Aluminum Ladder 40 03-Aug-14 A 23-Sep-14 A
MAS-201 MDPE Pipe 45 14-Aug-14 A 07-Oct-14 A
MAS-271 Concrete 40 18-Sep-14 A 25-Oct-14 A
MAS-151 Aluminum Sealing Flange 40 25-Sep-14 A 26-Oct-14 A
MAS-101 Automatic Float Air Release Valve & Vaccum Valve 30 30-Sep-14 A 26-Oct-14 A
MAS-71 Gate Valve 40 01-Oct-14 A 26-Oct-14 A
MAS-91 Butterfly Valve 30 01-Oct-14 A 01-Jul-15 A
MAS-211 House Connection Fittings 40 01-Oct-14 A 21-Jul-15 A
MAS-121 Fire Hydrants 40 19-Oct-14 A 11-Jul-15 A
MAS-111 Isolating Valve 30 25-Oct-14 A 26-Oct-14 A
MAS-131 D.I Access Cover and Frame 40 25-Oct-14 A 09-Nov-14 A
MAS-161 Aluminum Vent Pipe 40 25-Oct-14 A 11-Dec-14 A
MAS-171 Bronze Chamber Indication Plate 40 29-Oct-14 A 23-Nov-14 A
MAS-181 Bronze Owner Information Plate 40 29-Oct-14 A 23-Nov-14 A
MAS-51 Dismantling Joints 40 20-Nov-14 A 20-Nov-14 A
MAS-61 Flanged Adaptors 40 20-Nov-14 A 20-Nov-14 A
MAS-241 Warning Tape 40 24-Nov-14 A 25-Nov-14 A
MAS-251 GRP Water Meter Box 30 24-Nov-14 A 25-Nov-14 A
MAS-191 UPVC Pipe 40 26-Nov-14 A 08-Mar-15 A
MAS-261 Reinforcement Steel 40 26-Nov-14 A 02-Mar-15 A
MATERIAL APP
APPROVAL 367 14-Sep-14 A 13-Feb-16 A
MAS-371 HDPE Pipes & Fittings 21 14-Sep-14 A 04-Mar-15 A
MAS-501 Aluminum Ladder 21 15-Sep-14 A 30-Sep-14 A
MAS-381 Ductile Iron Pipes & Fittings 21 12-Oct-14 A 23-Nov-14 A
MAS-521 Aluminum Vent Pipe 21 23-Oct-14 A 16-Nov-14 A
MAS-631 Concrete 21 25-Oct-14 A 20-Nov-14 A
MAS-531 Bronze Chamber Indication Plate 21 29-Oct-14 A 17-Nov-14 A
MAS-541 Bronze Owner Information Plate 21 29-Oct-14 A 17-Nov-14 A
MAS-561 MDPE Pipe 21 12-Nov-14 A 09-Mar-15 A
MAS-431 Gate Valve 21 17-Nov-14 A 22-Mar-15 A
MAS-471 Isolating Valve 21 19-Nov-14 A 22-Mar-15 A
MAS-411 Dismantling Joints 21 20-Nov-14 A 31-Jan-15 A
MAS-421 Flanged Adaptors 21 20-Nov-14 A 01-Feb-15 A
MAS-491 D.I Access Cover and Frame 21 23-Nov-14 A 21-Jan-15 A
MAS-511 Aluminum Sealing Flange 21 25-Nov-14 A 04-Feb-15 A
MAS-601 Warning Tape 21 03-Dec-14 A 07-Jan-15 A
MAS-461 Automatic Float Air Release Valve & Vaccum Valve 21 17-Dec-14 A 22-Mar-15 A
MAS-611 GRP Water Meter Box 21 14-Feb-15 A 13-Feb-16 A
MAS-621 Reinforcement Steel 21 03-Mar-15 A 26-Mar-15 A
MAS-551 UPVC Pipe 21 09-Mar-15 A 23-Mar-15 A
MAS-571 House Connection Fittings 21 25-May-15 A 12-Aug-15 A
MAS-451 Butterfly Valve 21 02-Jul-15 A 04-Nov-15 A
MAS-481 Fire Hydrants 21 07-Jul-15 A 15-Aug-15 A
PROCUREMENT AND DELIVERY
PROCUREM 528 08-Nov-14 A 05-Apr-17

Actual Work 2 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
MATERIAL OR
ORDER 519 08-Nov-14 A 20-Jan-16 A
MAS-1421 HDPE Pipes & Fittings 01st Lot 20 08-Nov-14 A 30-Nov-14 A
MAS-1101 D.I Fittings (China for Alsaad / Abusamrah / Remah Area) 30 04-Dec-14 A 23-Dec-14 A
MAS-1131 Dismantling Joints 15 04-Dec-14 A 23-Dec-14 A
MAS-1141 Flanged Adaptors 15 04-Dec-14 A 23-Dec-14 A
MAS-1311 D.I Pipes (France for Natlah Area) - 01st Lot 30 04-Dec-14 A 23-Dec-14 A
MAS-1401 D.I Fittings (France for Natlah Area) - 01st Lot 30 04-Dec-14 A 23-Dec-14 A
MAS-1371 D.I Pipes (China for Alsaad / Abusamrah / Remah Area) - 0 30 04-Dec-14 A 23-Dec-14 A
MAS-1321 Warning Tape 15 23-Dec-14 A 30-Dec-14 A
MAS-1151 Gate Valve 15 29-Dec-14 A 07-Jan-15 A
MAS-1181 Automatic Float Air Release Valve & Vaccum Valve 15 07-Jan-15 A 20-May-15 A
MAS-1191 Isolating Valve 15 07-Jan-15 A 20-May-15 A
MAS-1341 Reinforcement Steel 15 25-Mar-15 A 11-Apr-15 A
MAS-1221 Aluminum Ladder 15 20-Apr-15 A 06-May-15 A
MAS-1251 Bronze Chamber Indication Plate 15 02-May-15 A 05-May-15 A
MAS-1361 D.I Fittings (France for Natlah Area) - 02nd Lot 15 03-May-15 A 14-May-15 A
MAS-1351 D.I Pipes (France for Natlah Area) - 02nd Lot 15 05-May-15 A 14-May-15 A
MAS-1391 D.I Fittings (China for Alsaad / Abusamrah / Remah Area) 15 05-May-15 A 14-May-15 A
MAS-1431 HDPE Pipes & Fittings 02nd Lot 10 05-May-15 A 14-May-15 A
MAS-1261 Bronze Owner Information Plate 15 10-May-15 A 12-May-15 A
MAS-1381 D.I Pipes (China for Alsaad / Abusamrah / Remah Area) - 0 15 12-May-15 A 14-May-15 A
MAS-1241 Aluminum Vent Pipe 15 14-May-15 A 14-May-15 A
MAS-1211 D.I Access Cover and Frame 15 15-May-15 A 20-May-15 A
MAS-1231 Aluminum Sealing Flange 15 15-May-15 A 20-May-15 A
MAS-1331 GRP Water Meter Box 15 06-Jun-15 A 22-Jun-15 A
MAS-1281 MDPE Pipe 15 30-Jul-15 A 10-Sep-15 A
MAS-1291 House Connection Fittings (1st Lot) 15 30-Jul-15 A 30-Jul-15 A
MAS-1271 UPVC Pipe 15 04-Aug-15 A 18-Aug-15 A
MAS-1201 Fire Hydrants 15 08-Aug-15 A 20-Aug-15 A
MAS-1171 Butterfly Valve 15 01-Nov-15 A 08-Dec-15 A
MAS-1531 House Connection Fittings (2nd Lot) 1 20-Jan-16 A 20-Jan-16 A
MATERIAL MA
MANUFACTURE AND DELIVERY 492 24-Dec-14 A 05-Apr-17
MAS-1121 D.I Fittings (China for Alsaad / Abusamrah / Remah Area) 150 24-Dec-14 A 30-Jun-15 A
MAS-1441 D.I Pipes (France for Natlah Area) - 01st Lot 100 24-Dec-14 A 20-Aug-15 A
MAS-1521 D.I Fittings (France for Natlah Area) - 01st Lot 150 24-Dec-14 A 20-Aug-15 A
MAS-1471 D.I Pipes (China for Alsaad / Abusamrah / Remah Area) - 0 100 24-Dec-14 A 30-Jun-15 A
MAS-961 Warning Tape 60 14-Jan-15 A 30-Jul-15 A
MAS-1501 HDPE Pipes & Fittings 01st Lot 90 21-Jan-15 A 20-May-15 A
MAS-791 Gate Valve 120 01-Mar-15 A 10-Oct-15 A
MAS-781 Flanged Adaptors 120 25-Mar-15 A 10-May-15 A
MAS-981 Reinforcement Steel 10 12-Apr-15 A 31-Jan-16 A
MAS-771 Dismantling Joints 120 06-May-15 A 08-May-15 A
MAS-1511 HDPE Pipes & Fittings 02nd Lot 40 15-May-15 A 06-Mar-16 A
MAS-851 D.I Access Cover and Frame 110 20-May-15 A 10-Dec-15 A
MAS-821 Automatic Float Air Release Valve & Vaccum Valve 120 21-May-15 A 07-Jun-16 A
MAS-1461 D.I Fittings (France for Natlah Area) - 02nd Lot 217 30-May-15 A 26-Apr-16 A
MAS-1481 D.I Pipes (China for Alsaad / Abusamrah / Remah Area) - 0 151 30-May-15 A 06-Jul-16 A
MAS-1491 D.I Fittings (China for Alsaad / Abusamrah / Remah Area) 197 30-May-15 A 28-Aug-16 A
MAS-1451 D.I Pipes (France for Natlah Area) - 02nd Lot 171 30-May-15 A 30-Jul-16 A
MAS-891 Bronze Chamber Indication Plate 60 31-May-15 A 29-Mar-16 A
MAS-871 Aluminum Sealing Flange 60 01-Jun-15 A 29-Mar-16 A
MAS-881 Aluminum Vent Pipe 60 01-Jun-15 A 29-Mar-16 A
MAS-901 Bronze Owner Information Plate 60 11-Jun-15 A 29-Mar-16 A
MAS-861 Aluminum Ladder 60 17-Jun-15 A 29-Mar-16 A
MAS-971 GRP Water Meter Box 120 23-Jun-15 A 23-Jun-15 A
MAS-931 House Connection Fittings (1st Lot) 90 01-Aug-15 A 30-Dec-15 A
MAS-841 Fire Hydrants 25 22-Aug-15 A 15-Oct-16 A
MAS-911 UPVC Pipe 60 22-Aug-15 A 29-Mar-16 A
MAS-921 MDPE Pipe 60 23-Aug-15 A 30-Sep-15 A
MAS-831 Isolating Valve 120 22-Nov-15 A 07-Jun-16 A
MAS-811 Butterfly Valve 50 09-Dec-15 A 17-Oct-16 A
MAS-951 House Connection Fittings (2nd Lot) 20 21-Jan-16 A 05-Apr-17
FREE ISSUE MATERIALS 154 30-Nov-14 A 05-Dec-15 A
A2150 Request for Free Issue Material 0 30-Nov-14 A
A2170 Inspection 0 22-Nov-15 A
A2190 Receipt of Free Issue Material 0 05-Dec-15 A
CONSTRUCTION AND COMMISIONING
CONSTRUCT 1055 03-Aug-14 A 14-Dec-17
PRECASTING WORKS AND HOUSE CONNECTION SURVEY WORKS 522 NOS 674 21-Mar-15 A 14-May-17
A4250 Survey works for House Connections 522 Nos 1 21-Mar-15 A 29-Jul-15 A
A4260 Shop Drawings for House Connections 522 Nos 1 05-Apr-15 A 15-Aug-15 A
A4210 Protection Slab Precasting Works 200 12-May-15 A 23-Mar-17
A4310 Precasting of Valve Chamber Top Slab 215 20-Jan-16 A 11-Apr-17
A4240 Pull Box / Stop Valve Box Precasting Works 150 02-Apr-16 A 03-Apr-17
A4220 Marker Post Precasting Works 45 23-Mar-17 14-May-17
A4230 Air Valve Precasting Works 45 23-Mar-17 14-May-17
BULK CONNECTIONS
CONNE (WATER PIPELINES) 1037 03-Dec-14 A 23-Nov-17
NEW NETWORK
NETWO FOR JAFFER JADEED - ZAKHER 854 03-Dec-14 A 06-May-17
PIPELINE (HDPE - 600 Meter) 168 03-Dec-14 A 04-Apr-17
A2290 Survey and Trial Pit Works 15 03-Dec-14 A 20-Dec-14 A
A2301 Setting Out Handover to TPD 3 21-Dec-14 A 18-Jan-15 A
A2291 Prepare and Submission of Shop drawings 7 03-Jan-15 A 20-Jan-15 A

Actual Work 3 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A2292 Approval of Shop drawings 21 09-Jan-15 A 02-Feb-15 A
A1070 Trench Excavation 15 26-Jan-15 A 28-Mar-17
A2180 Sand Bedding 15 28-Jan-15 A 30-Mar-17
A1080 Pipe Laying, Jointing and Fittings Installation 15 29-Jan-15 A 01-Apr-17
A2240 Post Bedding 15 31-Jan-15 A 02-Apr-17
A2250 Installation of Warning Tape 15 24-Feb-15 A 03-Apr-17
A1100 Full Backfilling and Reinstatement 15 25-Feb-15 A 04-Apr-17
VALVE CH
CHAMBER (04 No's) 140 22-Dec-15 A 06-Mar-16 A
A5030 Excavation 5 22-Dec-15 A 24-Jan-16 A
A5040 Blinding Concrete 1 28-Dec-15 A 25-Jan-16 A
A5050 Shuttering and Steel Fixing Works 12 29-Dec-15 A 08-Feb-16 A
A5060 Concrete Works 1 12-Jan-16 A 07-Feb-16 A
A5070 Installation of Valves and Fittings 3 13-Jan-16 A 10-Feb-16 A
A5080 Wall Concrete 10 14-Jan-16 A 22-Feb-16 A
A5090 Painting / Coating / Waterproofing 5 16-Jan-16 A 28-Feb-16 A
A5120 Backfilling 7 17-Jan-16 A 01-Mar-16 A
A5100 Installation of Ladder 2 18-Jan-16 A 01-Mar-16 A
A5110 Installation of Pre-Cast Cover Slab 2 19-Jan-16 A 03-Mar-16 A
A5130 Installation of Manhole Cover 2 20-Jan-16 A 06-Mar-16 A
NDRC WORKS
WO (01 No) 62 22-Nov-15 A 11-Feb-16 A
A5140 Prepare & Submission of Drawings and Documents for all 32 22-Nov-15 A 29-Dec-15 A
A5150 Obtain Approval for All Locations 30 30-Dec-15 A 05-Jan-16 A
A5160 NDRC Work 20 20-Jan-16 A 11-Feb-16 A
ASPHALT WORKS (01 No) 1 15-Dec-15 A 20-Dec-15 A
A5190 ASPHALT Works 1 15-Dec-15 A 20-Dec-15 A
TESTING & PRE-COMMISIONING 268 06-Jun-16 A 13-Apr-17
A5010 Preparation Works 5 06-Jun-16 A 11-Jun-16 A
A2300 Pillar Fire Hydrant and underground services 3 06-Nov-16 A 10-Apr-17
A5020 Hydrotesting 2 05-Apr-17 06-Apr-17
A2320 Flushing and Disinfection 3 11-Apr-17 13-Apr-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (03 No's)
SHUTDOW 19 15-Apr-17 06-May-17
A4980 Preparation Works 14 15-Apr-17 30-Apr-17
A4990 Submission of Documents and Request for Shutdown 0 17-Apr-17
A5500 Obtain Approval 7 17-Apr-17 24-Apr-17
A5000 Shutdown 10 25-Apr-17 06-May-17
ASBUILT 29 03-Apr-17 06-May-17
A4950 Prepare and Submission of AS Built drawings 29 03-Apr-17 06-May-17
UDGAT EL M
MUWAIJI WATER NETWORK 999 17-Dec-14 A 22-Oct-17
PIPELINE (HDPE - 3000 Meter) 245 17-Dec-14 A 08-Jun-17
A6700 Survey and Trial Pit Works 20 17-Dec-14 A 04-Feb-15 A
A6760 Handover Setting Out to TPD 4 18-Jan-15 A 08-Jun-15 A
A6710 Prepare and Submission of Shop drawings 5 20-Jan-15 A 10-Jun-15 A
A6720 Approval of Shop drawings 12 26-Jan-15 A 08-Jun-15 A
A6640 Trench Excavation 60 18-Feb-15 A 31-May-17
A6670 Sand Bedding 60 21-Feb-15 A 01-Jun-17
A6650 Pipe Laying, Jointing and Fittings Installation 60 22-Feb-15 A 04-Jun-17
A6680 Post Bedding 60 16-Mar-15 A 06-Jun-17
A6690 Installation of Warning Tape 60 17-Mar-15 A 07-Jun-17
A6660 Full Backfilling and Reinstatement 60 18-Mar-15 A 08-Jun-17
HOUSE CONNECTIONS
CO 419 02-Apr-16 A 02-Aug-17
A8190 Excavation for MDPE Pipe (3500 M) 30 02-Apr-16 A 19-Jul-17
A8200 Laying and Warning Tape and Backfilling for MDPE 30 03-Apr-16 A 22-Jul-17
A8210 Stop Valves Box installed 5 23-Jul-17 27-Jul-17
A8220 Tapping Saddles (134 Nos) 5 29-Jul-17 02-Aug-17
VALVE CH
CHAMBER (12 No's) 81 23-Apr-16 A 23-Jul-17
A6830 Excavation 10 23-Apr-16 A 25-Jun-17
A6840 Blinding Concrete 5 04-May-16 A 26-Jun-17
A6850 Shuttering and Steel Fixing Works 15 10-May-16 A 28-Jun-17
A6860 Concrete Works 5 28-May-16 A 29-Jun-17
A6870 Installation of Valves and Fittings 5 02-Jun-16 A 02-Jul-17
A6880 Wall Concrete 10 08-Jun-16 A 05-Jul-17
A6890 Painting / Coating / Waterproofing 5 26-Jun-16 A 10-Jul-17
A6920 Backfilling 7 02-Jul-16 A 16-Jul-17
A6900 Installation of Ladder 5 10-Jul-16 A 20-Jul-17
A6910 Installation of Pre-Cast Cover Slab 5 16-Jul-16 A 22-Jul-17
A6930 Installation of Manhole Cover 4 21-Jul-16 A 23-Jul-17
NDRC WORKS
WO (11 No's) 30 02-Jan-16 A 04-Feb-16 A
A6960 NDRC Work 30 02-Jan-16 A 04-Feb-16 A
TESTING & PRE-COMMISIONING 8 24-Jul-17 01-Aug-17
A6730 Pillar Fire Hydrant and underground services 6 24-Jul-17 30-Jul-17
A6810 Preparation Works 2 24-Jul-17 25-Jul-17
A6820 Hydrotesting 3 24-Jul-17 26-Jul-17
A6740 Flushing and Disinfection 2 31-Jul-17 01-Aug-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (03 No's)
SHUTDOW 19 01-Oct-17 22-Oct-17
A6780 Preparation Works 8 01-Oct-17 09-Oct-17
A6790 Submission of Documents and Request for Shutdown 0 01-Oct-17
A6970 Obtain Approval 9 01-Oct-17 10-Oct-17
A6800 Shutdown 10 11-Oct-17 22-Oct-17
ASBUILT 10 11-Oct-17 22-Oct-17
A6750 Prepare and Submission of AS Built drawings 10 11-Oct-17 22-Oct-17
ADGAT ALMUWAIJI
ALMU AREA WATER NETWORK 1014 30-Dec-14 A 28-Oct-17
PIPELINE (HDPE - 8750 Meter) 368 30-Dec-14 A 12-Jun-17
A6340 Survey and Trial Pit Works 20 30-Dec-14 A 04-Feb-15 A

Actual Work 4 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A6400 Setting out Handover to TPD 3 25-Jan-15 A 17-May-15 A
A6350 Prepare and Submission of Shop drawings 5 12-Feb-15 A 31-May-15 A
A6360 Approval of Shop drawings 12 21-Feb-15 A 17-May-15 A
A6280 Trench Excavation 150 08-Apr-15 A 03-Jun-17
A6310 Sand Bedding 150 09-Apr-15 A 05-Jun-17
A6290 Pipe Laying, Jointing and Fittings Installation 150 11-Apr-15 A 06-Jun-17
A6320 Post Bedding 150 12-Apr-15 A 07-Jun-17
A6330 Installation of Warning Tape 150 13-Apr-15 A 08-Jun-17
A6300 Full Backfilling and Reinstatement 150 14-Apr-15 A 12-Jun-17
HOUSE CONNECTIONS
CO 312 10-Jan-16 A 30-Jul-17
A8230 Excavation for MDPE Pipe (6000 M) 150 10-Jan-16 A 15-Jun-17
A8240 Laying and Warning Tape and Backfilling for MDPE 150 12-Jan-16 A 18-Jun-17
A8250 Stop Valves Box installed 23 19-Jun-17 15-Jul-17
A8260 Tapping Saddles 36 19-Jun-17 30-Jul-17
VALVE CH
CHAMBER (47 No's) 186 22-Nov-15 A 02-Aug-17
A6470 Excavation 16 22-Nov-15 A 01-Jul-17
A6480 Blinding Concrete 7 23-Nov-15 A 12-Jul-17
A6490 Shuttering and Steel Fixing Works 15 24-Nov-15 A 13-Jul-17
A6500 Concrete Works 8 25-Nov-15 A 15-Jul-17
A6510 Installation of Valve 8 26-Nov-15 A 17-Jul-17
A6520 Wall Concrete 10 27-Nov-15 A 22-Jul-17
A6530 Painting / Coating / Waterproofing 7 28-Nov-15 A 29-Jul-17
A6560 Backfilling 8 30-Nov-15 A 01-Aug-17
A6540 Installation of Ladder 7 02-Dec-15 A 02-Aug-17
A6550 Installation of Pre-Cast Cover Slab 10 05-Dec-15 A 02-Aug-17
A6570 Installation of Manhole Cover 3 10-Dec-15 A 02-Aug-17
NDRC WORKS
WO (13 No's) 30 20-Jan-16 A 23-Feb-16 A
A6600 NDRC Work 30 20-Jan-16 A 23-Feb-16 A
ASPHALT WORKS (02 No's) 10 15-Jul-15 A 23-Feb-16 A
A6630 ASPHALT Works 10 15-Jul-15 A 23-Feb-16 A
TESTING & PRE-COMMISIONING 52 14-Feb-17 A 02-Aug-17
A6370 Pillar Fire Hydrant and underground services 2 14-Feb-17 A 31-Jul-17
A6450 Preparation Works 2 27-Jul-17 30-Jul-17
A6460 Hydrotesting 2 27-Jul-17 30-Jul-17
A6380 Flushing and Disinfection 2 01-Aug-17 02-Aug-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (13 No's)
SHUTDOW 70 08-Aug-17 28-Oct-17
A6420 Preparation Works 35 08-Aug-17 17-Sep-17
A6430 Submission of Documents and Request for Shutdown 0 12-Aug-17
A6990 Obtain Approval 40 12-Aug-17 26-Sep-17
A6440 Shutdown Works 26 28-Sep-17 28-Oct-17
ASBUILT 9 18-Oct-17 28-Oct-17
A6390 Prepare and Submission of AS Built drawings 9 18-Oct-17 28-Oct-17
REPLACEME
REPLACEMENT OF DETERIORATED 1000 MM GRP LINE FROM NATLAH P/S TO I 977 16-Dec-14 A 26-Sep-17
PIPELINE (D.I - 5000 Meter) 645 16-Dec-14 A 19-Apr-17
A5260 Survey and Trial Pit Works 40 16-Dec-14 A 29-Jan-15 A
A5270 Prepare and Submission of Shop drawings 10 08-Jan-15 A 17-Feb-15 A
A5290 Settingout Handover to TPD 5 11-Jan-15 A 07-Feb-15 A
A5280 Approval of Shop drawings 21 14-Jan-15 A 14-Mar-15 A
A5200 Trench Excavation 237 03-Oct-15 A 13-Apr-17
A5230 Sand Bedding 237 04-Oct-15 A 15-Apr-17
A5210 Pipe Laying, Jointing and Thrust Block Works 237 05-Oct-15 A 16-Apr-17
A5240 Post Bedding 237 05-Oct-15 A 17-Apr-17
A5250 Installation of Warning Tape 237 06-Oct-15 A 18-Apr-17
A5220 Full Backfilling and Reinstatement 247 07-Oct-15 A 19-Apr-17
VALVE CH
CHAMBER (06 Nos + LINE ANCHORS) 154 08-Nov-16 A 06-May-17
A5390 Excavation 3 08-Nov-16 A 26-Mar-17
A5400 Blinding Concrete 2 08-Nov-16 A 28-Mar-17
A5410 Shuttering and Steel Fixing Works 7 01-Feb-17 A 05-Apr-17
A5420 Concrete Works 3 09-Feb-17 A 09-Apr-17
A5430 Installation of Valves and Fittings 3 10-Apr-17 12-Apr-17
A5440 Wall Concrete 3 13-Apr-17 16-Apr-17
A5510 Concrete for Line Anchors 5 13-Apr-17 18-Apr-17
A5450 Painting / Coating / Waterproofing 5 17-Apr-17 22-Apr-17
A5480 Backfilling 5 23-Apr-17 27-Apr-17
A5460 Installation of Ladder 2 29-Apr-17 30-Apr-17
A5470 Installation of Pre-Cast Cover Slab 3 01-May-17 03-May-17
A5490 Installation of Manhole Cover 2 04-May-17 06-May-17
TESTING & PRE-COMMISIONING 6 03-May-17 09-May-17
A5370 Preparation Works 3 03-May-17 06-May-17
A5380 Hydrotesting 3 03-May-17 06-May-17
A5300 Flushing and Disinfection 3 07-May-17 09-May-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (05 Nos)
SHUTDOW 31 14-Aug-17 18-Sep-17
A5340 Preparation Works 15 14-Aug-17 30-Aug-17
A5350 Submission of Documents and Request for Shutdown 0 14-Aug-17
A5520 Obtain Approval 18 14-Aug-17 03-Sep-17
A5360 Shutdown 13 04-Sep-17 18-Sep-17
ASBUILT 7 19-Sep-17 26-Sep-17
A5310 Prepare and Submission of AS Built drawings 7 19-Sep-17 26-Sep-17
REPLACEME
REPLACEMENT OF DETERIORATED 9" & 15" AC PIPELINE REMAH 960 06-Jan-15 A 26-Aug-17
PIPELINE (D.I - 10,000 Meter) 605 06-Jan-15 A 15-Apr-17
A7060 Survey and Trial Pit Works 25 06-Jan-15 A 10-Mar-15 A
A7090 Settingout Handover to TPD 5 17-Feb-15 A 19-Mar-15 A
A7070 Prepare and Submission of Shop drawings 15 23-Feb-15 A 22-Mar-15 A

Actual Work 5 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A7080 Approval of Shop drawings 12 24-Feb-15 A 19-Mar-15 A
A7000 Trench Excavation 175 01-Aug-15 A 09-Apr-17
A7030 Sand Bedding 175 02-Aug-15 A 10-Apr-17
A7010 Pipe Laying, Jointing and Thrust Block Works 175 03-Aug-15 A 11-Apr-17
A7040 Post Bedding 175 04-Aug-15 A 12-Apr-17
A7050 Installation of Warning Tape 175 05-Aug-15 A 13-Apr-17
A7020 Full Backfilling and Reinstatement 175 06-Aug-15 A 15-Apr-17
HOUSE CONNECTIONS
CO 17 23-Mar-17 11-Apr-17
A8270 Excavation for MDPE Pipe (1300 M) 15 23-Mar-17 09-Apr-17
A8280 Laying and Warning Tape and Backfilling for MDPE 15 23-Mar-17 09-Apr-17
A8290 Stop Valves Box installed 2 10-Apr-17 11-Apr-17
A8300 Tapping Saddles (21 Nos) 2 10-Apr-17 11-Apr-17
VALVE CH
CHAMBER (01 No) 207 14-Jan-16 A 29-Apr-17
A7190 Excavation 5 14-Jan-16 A 28-Mar-17
A7200 Blinding Concrete 2 16-Jan-16 A 30-Mar-17
A7210 Shuttering and Steel Fixing Works 5 17-Jan-16 A 05-Apr-17
A7220 Concrete Works 3 18-Jan-16 A 09-Apr-17
A7230 Installation of Valves and Fittings 2 19-Jan-16 A 11-Apr-17
A7240 Wall Concrete 15 20-Jan-16 A 12-Apr-17
A7250 Painting / Coating / Waterproofing 3 21-Jan-16 A 16-Apr-17
A7280 Backfilling 4 25-Jan-16 A 20-Apr-17
A7260 Installation of Ladder 2 26-Jan-16 A 23-Apr-17
A7270 Installation of Pre-Cast Cover Slab 3 27-Jan-16 A 26-Apr-17
A7290 Installation of Manhole Cover 2 28-Jan-16 A 29-Apr-17
NDRC WORKS
WO (06 No's) 30 24-Feb-16 A 29-Mar-16 A
A7320 NDRC Work 30 24-Feb-16 A 29-Mar-16 A
ASPHALT WORKS (10 No's) 20 10-Aug-15 A 17-Mar-16 A
A7350 ASPHALT Works 20 10-Aug-15 A 17-Mar-16 A
TESTING & PRE-COMMISIONING 61 26-Feb-17 A 07-May-17
A7170 Preparation Works 6 26-Feb-17 A 29-Apr-17
A7180 Hydrotesting 6 01-Mar-17 A 02-May-17
A7100 Flushing and Disinfection 4 03-May-17 07-May-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (9 No 's)
SHUTDOW 54 25-Jun-17 26-Aug-17
A7140 Preparation Works 30 25-Jun-17 29-Jul-17
A7150 Submission of Documents and Request for Shutdown 0 27-Jun-17
A7620 Obtain Approval 36 27-Jun-17 07-Aug-17
A7160 Shutdown 16 08-Aug-17 26-Aug-17
ASBUILT 10 15-Aug-17 26-Aug-17
A7110 Prepare and Submission of AS Built drawings 10 15-Aug-17 26-Aug-17
REPLACEME
REPLACEMENT OF DETERIORATED 9" & 15" AC PIPELINE ALSAAD 894 14-Jan-15 A 10-Jun-17
PIPELINE (D.I - 2300 Meter) 605 14-Jan-15 A 01-May-17
A7780 Survey and Trial Pit Works 20 14-Jan-15 A 16-Feb-15 A
A7810 Settingout Handover to TPD 3 14-Feb-15 A 02-May-15 A
A7790 Prepare and Submission of Shop drawings 7 17-Feb-15 A 03-May-15 A
A7800 Approval of Shop drawings 12 01-Mar-15 A 05-May-15 A
A7720 Trench Excavation 30 20-Jul-15 A 26-Apr-17
A7750 Sand Bedding 30 21-Jul-15 A 27-Apr-17
A7730 Pipe Laying, Jointing and Thrust Block Works 30 22-Jul-15 A 27-Apr-17
A7740 Full Backfilling and Reinstatement 30 22-Jul-15 A 01-May-17
A7760 Post Bedding 30 22-Jul-15 A 29-Apr-17
A7770 Installation of Warning Tape 30 22-Jul-15 A 30-Apr-17
HOUSE CONNECTIONS
CO 5 26-Apr-17 01-May-17
A8310 Excavation for MDPE Pipe (242 M) 5 26-Apr-17 01-May-17
A8320 Laying and Warning Tape and Backfilling for MDPE 2 26-Apr-17 27-Apr-17
A8330 Stop Valves Box installed 1 29-Apr-17 29-Apr-17
A8340 Tapping Saddles (03 Nos) 1 30-Apr-17 30-Apr-17
NDRC WORKS
WO (02 Nos) 20 23-Mar-17 15-Apr-17
A8040 NDRC Work 20 23-Mar-17 15-Apr-17
TESTING & PRE-COMMISIONING 292 31-May-16 A 06-May-17
A7890 Preparation Works 7 31-May-16 A 07-Jun-16 A
A7900 Hydrotesting 7 02-Jul-16 A 02-May-17
A7820 Flushing and Disinfection 3 03-May-17 06-May-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (05 No's)
SHUTDOW 30 07-May-17 10-Jun-17
A7860 Preparation Works 18 07-May-17 27-May-17
A7870 Submission of Documents and Request for Shutdown 0 07-May-17
A7910 Obtain Approval 20 07-May-17 29-May-17
A7880 Shutdown 10 30-May-17 10-Jun-17
ASBUILT 13 27-May-17 10-Jun-17
A7830 Prepare and Submission of AS Built drawings 13 27-May-17 10-Jun-17
REPLACEME
REPLACEMENT OF DETERIORATED 9" & 15" AC PIPELINE ABUSAMRAH 757 25-Jan-15 A 25-Jun-17
PIPELINE (D.I - 450 Meter) 455 25-Jan-15 A 10-Feb-16 A
A7420 Survey and Trial Pit Works 10 25-Jan-15 A 04-Feb-15 A
A7450 Settingout Handvoer to TPD 3 31-Jan-15 A 02-Feb-15 A
A7430 Prepare and Submission of Shop drawings 5 22-Feb-15 A 24-Feb-15 A
A7440 Approval of Shop drawings 12 25-Feb-15 A 20-Apr-15 A
A7360 Trench Excavation 15 01-Aug-15 A 06-Feb-16 A
A7390 Sand Bedding 15 02-Aug-15 A 07-Feb-16 A
A7370 Pipe Laying, Jointing and Thrust Block Works 15 03-Aug-15 A 07-Feb-16 A
A7400 Post Bedding 15 04-Aug-15 A 08-Feb-16 A
A7410 Installation of Warning Tape 15 05-Aug-15 A 09-Feb-16 A
A7380 Full Backfilling and Reinstatement 15 06-Aug-15 A 10-Feb-16 A
HOUSE CONNECTIONS
CO 4 01-May-17 04-May-17
A8350 Excavation for MDPE Pipe (61 M) 2 01-May-17 02-May-17

Actual Work 6 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A8360 Laying and Warning Tape and Backfilling for MDPE 2 01-May-17 02-May-17
A8370 Stop Valves Box installed 1 03-May-17 03-May-17
A8380 Tapping Saddles (02 Nos) 1 04-May-17 04-May-17
ASPHALT WORKS (01 No) 5 16-Aug-15 A 23-Mar-16 A
A7710 ASPHALT Works 5 16-Aug-15 A 23-Mar-16 A
TESTING & PRE-COMMISIONING 314 24-Mar-16 A 25-Mar-17
A7530 Preparation Works 5 24-Mar-16 A 29-Mar-16 A
A7540 Hydrotesting 3 30-Mar-16 A 02-Apr-16 A
A7460 Flushing and Disinfection 2 23-Mar-17 25-Mar-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (02 No's)
SHUTDOW 12 11-Jun-17 24-Jun-17
A7500 Preparation Works 5 11-Jun-17 15-Jun-17
A7510 Submission of Documents and Request for Shutdown 0 11-Jun-17
A7600 Obtain Approval 6 11-Jun-17 17-Jun-17
A7520 Shutdown 6 18-Jun-17 24-Jun-17
ASBUILT 1 25-Jun-17 25-Jun-17
A7470 Prepare and Submission of AS Built drawings 1 25-Jun-17 25-Jun-17
REPLACEME
REPLACEMENT OF EXISTING WATER NETWORK AT SHK.KHALIFA SHABIYA 988 19-Jan-15 A 07-Oct-17
PIPELINE (HDPE - 2350 Meter) 319 19-Jan-15 A 18-Jun-17
A5980 Survey and Trial Pit Works 30 19-Jan-15 A 23-Feb-15 A
A6040 Settingout Handover to TPD 4 15-Feb-15 A 17-May-15 A
A5990 Prepare and Submission of Shop drawings 3 25-Feb-15 A 17-May-15 A
A6000 Approval of Shop drawings 21 10-Mar-15 A 17-May-15 A
A5920 Trench Excavation 30 17-May-15 A 05-Jun-17
A5950 Sand Bedding 30 18-May-15 A 06-Jun-17
A5970 Installation of Warning Tape 30 18-May-15 A 17-Jun-17
A5930 Pipe Laying, Jointing and Fittings Installation 25 19-May-15 A 12-Jun-17
A5960 Post Bedding 30 20-May-15 A 15-Jun-17
A5940 Full Backfilling and Reinstatement 25 21-May-15 A 18-Jun-17
HOUSE CONNECTIONS
CO 100 23-Mar-17 17-Jul-17
A8390 Excavation for MDPE Pipe (2800 M) 78 23-Mar-17 21-Jun-17
A8400 Laying and Warning Tape and Backfilling for MDPE 80 23-Mar-17 24-Jun-17
A8410 Stop Valves Box installed 10 25-Jun-17 05-Jul-17
A8420 Tapping Saddles (104 Nos) 10 06-Jul-17 17-Jul-17
VALVE CH
CHAMBER(07 No's) 120 23-Mar-17 09-Aug-17
A6110 Excavation 102 23-Mar-17 19-Jul-17
A6120 Blinding Concrete 100 27-Mar-17 20-Jul-17
A6130 Shuttering and Steel Fixing Works 99 30-Mar-17 23-Jul-17
A6140 Concrete Works 98 04-Apr-17 26-Jul-17
A6150 Installation of Valves and Fittings 100 06-Apr-17 31-Jul-17
A6160 Wall Concrete 98 09-Apr-17 31-Jul-17
A6170 Painting / Coating / Waterproofing 97 11-Apr-17 01-Aug-17
A6200 Backfilling 98 12-Apr-17 03-Aug-17
A6180 Installation of Ladder 97 15-Apr-17 05-Aug-17
A6190 Installation of Pre-Cast Cover Slab 100 15-Apr-17 08-Aug-17
A6210 Installation of Manhole Cover 101 15-Apr-17 09-Aug-17
NDRC WORKS
WO (06 No's) 120 23-Mar-17 09-Aug-17
A6240 NDRC Work 120 23-Mar-17 09-Aug-17
ASPHALT WORKS (02 No's) 14 27-Aug-15 A 09-Aug-17
A6270 ASPHALT Works 14 27-Aug-15 A 09-Aug-17
TESTING & PRE-COMMISIONING 120 23-Mar-17 09-Aug-17
A6010 Pillar Fire Hydrant and underground services 109 23-Mar-17 27-Jul-17
A6100 Hydrotesting 54 08-Jun-17 09-Aug-17
A6090 Preparation Works 50 13-Jun-17 09-Aug-17
A6020 Flushing and Disinfection 4 29-Jul-17 01-Aug-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (04 No's)
SHUTDOW 25 09-Sep-17 07-Oct-17
A6060 Preparation Works 14 09-Sep-17 24-Sep-17
A6070 Submission of Documents and Request for Shutdown 0 09-Sep-17
A7560 Obtain Approval 15 09-Sep-17 25-Sep-17
A6080 Shutdown 10 26-Sep-17 07-Oct-17
ASBUILT 10 26-Sep-17 07-Oct-17
A6030 Prepare and Submission of AS Built drawings 10 26-Sep-17 07-Oct-17
WATER NETW
NETWORK FOR 98 COMMERCIAL PLOTS AT NAGLAH - SANAYYAH 887 25-Jan-15 A 23-Nov-17
PIPELINE (HDPE - 6400 Meter) 255 25-Jan-15 A 13-Jun-17
A5620 Survey and Trial Pit Works 20 25-Jan-15 A 03-Mar-15 A
A5680 Settingout Handover to TPD 5 09-Feb-15 A 06-Apr-15 A
A5630 Prepare and Submission of Shop drawings 10 25-Feb-15 A 06-Apr-15 A
A5640 Approval of Shop drawings 12 25-Mar-15 A 06-Apr-15 A
A5560 Trench Excavation 110 10-May-15 A 06-Jun-17
A5590 Sand Bedding 110 12-May-15 A 07-Jun-17
A5570 Pipe Laying, Jointing and Fittings Installation 90 14-May-15 A 08-Jun-17
A5600 Post Bedding 110 16-May-15 A 10-Jun-17
A5610 Installation of Warning Tape 110 18-May-15 A 12-Jun-17
A5580 Full Backfilling and Reinstatement 90 20-May-15 A 13-Jun-17
VALVE CH
CHAMBER (21 No's) 409 25-May-16 A 03-Aug-17
A5750 Excavation 10 25-May-16 A 15-Jun-17
A5760 Blinding Concrete 5 26-May-16 A 17-Jun-17
A5810 Painting / Coating / Waterproofing 3 28-May-16 A 31-Jul-17
A5780 Concrete Works 7 01-Jun-16 A 09-Jul-17
A5840 Backfilling 8 03-Jun-16 A 02-Aug-17
A5790 Installation of Valves and Fittings 5 05-Jun-16 A 23-Jul-17
A5820 Installation of Ladder 4 08-Jun-16 A 03-Aug-17
A5830 Installation of Pre-Cast Cover Slab 5 11-Jun-16 A 03-Aug-17
A5770 Shuttering and Steel Fixing Works 8 15-Jun-16 A 27-Jun-17

Actual Work 7 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A5850 Installation of Manhole Cover 3 20-Jun-16 A 03-Aug-17
A5800 Wall Concrete 6 24-Jul-17 30-Jul-17
NDRC WORKS
WO (13 No's) 10 01-Aug-17 12-Aug-17
A5880 NDRC Work 10 01-Aug-17 12-Aug-17
ASPHALT WORKS (10 No's) 15 04-Oct-15 A 10-Aug-17
A5910 ASPHALT Works 15 04-Oct-15 A 10-Aug-17
TESTING & PRE-COMMISIONING 8 10-Aug-17 19-Aug-17
A5730 Preparation Works 2 10-Aug-17 12-Aug-17
A5650 Pillar Fire Hydrant and underground services 3 13-Aug-17 15-Aug-17
A5740 Hydrotesting 4 13-Aug-17 16-Aug-17
A5660 Flushing and Disinfection 3 16-Aug-17 19-Aug-17
SHUTDOWN AND CONNECTION TO EXISTING LINE (03 No's)
SHUTDOW 28 23-Oct-17 23-Nov-17
A5700 Preparation Works 16 23-Oct-17 09-Nov-17
A5710 Submission of Documents and Request for Shutdown 0 23-Oct-17
A7580 Obtain Approval 18 23-Oct-17 12-Nov-17
A5720 Shutdown 10 13-Nov-17 23-Nov-17
ASBUILT 15 07-Nov-17 23-Nov-17
A5670 Prepare and Submission of AS Built drawings 15 07-Nov-17 23-Nov-17
KHATM AL S
SHAKLA 35 23-Mar-17 03-May-17
STAGE 01 0 23-Mar-17 23-Mar-17
A8460 Submission and Approval of Chamber co-ordinates from TP 0 23-Mar-17 23-Mar-17
A8470 Permits/ NOC issuance to start Excavation 0 23-Mar-17
A8480 Civil Construction of DN 400 BFV Chamber 0 23-Mar-17 23-Mar-17
A8490 Pipeline Testing works and request for Flushing 0 23-Mar-17 23-Mar-17
A8500 Pipeline Flushing and Request for Shutdown to AADC 0 23-Mar-17 23-Mar-17
A8510 Preparation for Shutdown 0 23-Mar-17 23-Mar-17
A8520 Shutdown / Interconnection works 0 23-Mar-17 23-Mar-17
A8430 Notice of commencement from AADC 0 23-Mar-17
A8440 Free Issued Material from AADC 0 23-Mar-17
A8450 Surveying works for TPD Approval 0 23-Mar-17 23-Mar-17
STAGE 02 0 02-May-17 03-May-17
A8530 Notice of commencement from AADC 0 02-May-17
A8540 Surveying works for TPD Approval 0 03-May-17 03-May-17
A8550 Submission and Approval of Chamber co-ordinates from TP 0 03-May-17 03-May-17
A8560 Permits/ NOC issuance to start Excavation 0 03-May-17
A8570 Civil Construction works of FM and FCV Chamber 0 03-May-17 03-May-17
A8580 Preparation and Request of Shutdown to AADC 0 03-May-17 03-May-17
A8590 Shutdown Works (Installation of Pipes and Fittings, Valves 0 03-May-17 03-May-17
A8600 Steel and Casting works for U-Cut on Chamber wall 0 03-May-17 03-May-17
ADDITIONAL W
WORKS AT NATLAH P/S 677 04-Jan-15 A 22-Aug-17
SURGE PROTECTION
PROT SYSTEM 648 04-Jan-15 A 19-Jul-17
A1820 Surge Analysis required information for Survey works 32 04-Jan-15 A 27-Jan-16 A
A1770 Investigate Existing Surge Protection System 7 02-Jul-15 A 25-Aug-15 A
A1780 Prepare and Submission of Investigation Report 30 26-Aug-15 A 26-Mar-16 A
A1790 Prepare and Submission of Surge Analysis Report 30 26-Aug-15 A 15-Sep-16 A
A1800 Client Approval (Whether to Repair the Existing Surge Sys 21 27-Mar-16 A 25-Apr-17
A1810 New Surge Protection System (Optional and To be decided 62 26-Apr-17 06-Jul-17
A2030 Repair Existing Surge Protection System (Optional & To be 67 26-Apr-17 12-Jul-17
A2050 Commissioning 68 02-May-17 19-Jul-17
INSTRUMENTATION & CONTROL WORKS
INSTRUMENT 0 23-Mar-17 23-Mar-17
A1720 Investigation of Existing PLC System 0 23-Mar-17 23-Mar-17
A2040 Survey Works & Collect information 0 23-Mar-17 23-Mar-17
A1730 Preparation & Submission of Investigation report 0 23-Mar-17 23-Mar-17
A1750 Submission of FDS approval 0 23-Mar-17 23-Mar-17
A1760 Approval of FDS approval 0 23-Mar-17 23-Mar-17
HYPOCHLORINATION SYSTEM
HYPOCHLOR 0 23-Mar-17 23-Mar-17
A8150 Investigate existing Hypochlorination system 0 23-Mar-17 23-Mar-17
A8160 Preparation & Submission of Investigation report 0 23-Mar-17 23-Mar-17
A8180 Client approval 0 23-Mar-17 23-Mar-17
A1830 Submission & Approval of Drawings 0 23-Mar-17 23-Mar-17
A1840 Material Procurement 0 23-Mar-17 23-Mar-17
A1850 Construction of Hypo Chlorination system 0 23-Mar-17 23-Mar-17
A1860 Testing & Precommissioning of Hypochlorination system 0 23-Mar-17 23-Mar-17
A1870 Commissioning of Hypochlorination system 0 23-Mar-17 23-Mar-17
A1880 Provide training to AADC Personnel 0 23-Mar-17 23-Mar-17
VENTILATION ROOM 538 19-Sep-15 A 09-Aug-17
A1920 Submission and Approval of Drawings 30 19-Sep-15 A 24-Jul-17
A1930 Material Procurement 110 23-Mar-17 29-Jul-17
A1940 Construction of Ventilation Room 25 06-Jul-17 03-Aug-17
A1960 Re-Alignment of Boundry Wall 25 12-Jul-17 09-Aug-17
FRESH AIR S
SUPPLY UNIT 604 19-Sep-15 A 22-Aug-17
A1890 Submission and Approval of Drawings 30 19-Sep-15 A 24-Jul-17
A1900 Material Procurement 120 23-Mar-17 09-Aug-17
A1910 Installation of Fresh Air Supply Unit 30 09-Jul-17 12-Aug-17
A1970 Pre-Commisioning and Commisioning 33 16-Jul-17 22-Aug-17
MISCELLANEOUS WORKS
MISCELLANEO 879 03-Aug-14 A 25-May-17
A2160 Undertake GRP Repair works for the existing GRP Pipeline 430 03-Aug-14 A 30-Jun-15 A
A2070 Reinstatement of Interlocking Tiles 234 15-Jul-15 A 29-Sep-16 A
A2080 Replacement of Suction line 1200/1000 at Natlah P/S 55 23-Mar-17 25-May-17
A2350 Checking & Rectifying and Settlement or Craks / Minor lea 20 03-May-17 25-May-17
HANDING OVE
OVER 192 13-Apr-17 23-Nov-17
A4530 New Network for Jaffer Jadeed - Zakher 0 13-Apr-17
A4550 Replacement of Deteriorated 9" & 15" AC Pipeline - Al Saad 0 10-Jun-17

Actual Work 8 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary
Replacement of Deteriorated GRP and AC pipelines for Rehabilitation of the Existing Pipelines at Different areas of Al Ain

Activity ID Activity Name Original Start Finish 2015 2016 2017 2018
Duration
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
A4600 Replacement of Deteriorated 9" & 15" AC Pipeline - Abusa 0 25-Jun-17
A4610 Replacement of Deteriorated 9" & 15" AC Pipeline - Remah 0 26-Aug-17
A4540 Replacement of Deteriorated 1000 mm GRP Pipe line from 0 26-Sep-17
A4580 Replacement of Existing Water Network at Shk.Khalifa Sh 0 07-Oct-17
A4560 Udgat Almuwaiji Water Network 0 22-Oct-17
A4570 Adgat Almuwaiji Area Water Network 0 28-Oct-17
A4590 Water Network for 98 Commercial Plots at Naglah 0 23-Nov-17
CLOSEOUT DO
DOCUMENTS 68 27-Sep-17 14-Dec-17
A2130 Submission of Operating Manual 18 27-Sep-17 17-Oct-17
A2140 Submission of QA/QC Dossier 18 27-Sep-17 17-Oct-17
A2360 Submission of Water Network Project Data 18 27-Sep-17 17-Oct-17
A2110 Submission of Project Closeout Report 18 25-Nov-17 14-Dec-17
PROJECT FINISH
FIN 0 14-Dec-17 14-Dec-17
A1010 Project Finish (PAC) 0 14-Dec-17

Actual Work 9 Date Revision Checked Approved


23-Mar-17 A6003.1 Updated 23-Mar-2017 R.K M.R
Remaining Work
Critical Remaining Work
Milestone
Summary