Presupuesto
Presupuesto 0301003 CONTRUCCION MURO CONTENCION EN CAMINERIA A LOS BAOS THERMALES CUCHUMBAYA
Cliente MUNICIPALIDAD DISTRITAL DE CUCHUMBAYA
Lugar MOQUEGUA - MARISCAL NIETO - CUCHUMBAYA
400,178.04
Item Descripcin Und. Metrado Precio S/. Parcial S/.
01 OBRAS PRELIMINARES 19,069.71
01.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 234.60 3.51 823.45
01.02 TRANSPORTE DE MATERIALES MANUAL kg 79,331.57 0.23 18,246.26
02 MOVIMIENTO DE TIERRAS 82,575.66
02.01 EXCAVACION DE ZANJAS - MATERIAL SUELTO m3 889.60 31.44 27,969.02
02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 271.64 51.69 14,041.07
02.03 ELIMINACION DE MATERIAL EXCEDENTE TRASLADO CON BUGUE A UNA m3 772.45 38.94 30,079.20
DISTANCIA DE 180M Y CON VOLQUETE, ESPONJAMIENTO 1.25
02.04 MATERIAL DE FILTRO SELECCIONADO m3 60.78 172.53 10,486.37
03 CONCRETO SIMPLE
04 MUROS DE CONTENCION 5,694.63
04.01 SOLADO DE CONCRETO F'C= 100 KG/CM2 e=4" m2 13.63 36.47 497.09
04.02 CIMIENTO CICLOPEO DE 1:8+30% P.G. (F'c=140KG/CM2) m3 5.95 307.58 1,830.10
04.03 MUROS CONCRETO CICLOPEO FC=140 KG/CM2 + 30% P.M. m3 10.80 311.80 3,367.44
05 CONCRETO ARMADO
06 ZAPATAS 53,880.05
06.01 CONCRETO EN ZAPATAS FC=210KG/CM2 m3 60.78 454.55 27,627.55
06.02 ENCOFRADO Y DESENCOFRADO NORMAL PARA ZAPATAS m2 69.41 52.72 3,659.30
06.03 ACERO ESTRUCTURAL EN ZAPATAS GRADO 60 kg 3,342.19 6.76 22,593.20
07 PANTALLA 113,187.04
07.01 CONCRETO EN PANTALLA FC= 210 KG/CM2 m3 99.72 449.12 44,786.25
07.02 ENCOFRADO PARA ELEVACIONES RENDIMIENTO=12 M2/DIA m2 493.48 61.95 30,571.09
07.03 ACERO ESTRUCTURAL EN PANTALLA GRADO 60 kg 5,596.11 6.76 37,829.70
08 REVOQUES ENLUCIDOS Y MOLDURAS 37,509.66
08.01 TARRAJEO RSTICO EN EXTERIORES m2 326.90 56.63 18,512.35
08.02 TARRAJEO CON PIEDRA LAJA MOQUEGUANA m2 170.41 111.48 18,997.31
09 DRENAJE 13,045.06
09.01 DRENAJE DE TUB. CRIBADA DE PVC SAP DE 4" m 58.00 212.88 12,347.04
09.02 DRENAJE LLORADORES DE PVC SAL DE 2" m 34.00 20.53 698.02
10 PINTURA 2,314.45
10.01 PINTADO DE MUROS RUSTICOS C/LATEX ACRILICO (SUPERLATEX O SIM) m2 326.90 7.08 2,314.45
11 VARIOS 11,512.28
11.01 JUNTAS DE TECKNOPORT m2 25.92 12.61 326.85
11.02 FLETE GLB 1.00 11,185.43 11,185.43
COSTO DIRECTO 338,788.54
GASTOS GENERALES (13.0505%) 44,213.50
GASTOS DE SUPERVISION (4.2070%) 14,253.00
GASTOS DE LIQUIDACION (0.8628%) 2,923.00
-------------------------------
COSTO TOTAL