You are on page 1of 3

RUBRO:

UNIDAD: M3
DETALLE: HORMIGN ARMADO FC 210 KG/CM2 FY 4200 KG/CM2 ( 0.23 m x 0.10 m)

EQUIPOS
COSTO
DESCRIPCION CANTIDAD TARIFA RENDIMIENTO COSTO
HORA
A B C=A*B R D=C*R
Herramienta menor 5% 0 0 0 0 2.053
Concretera 1 5 5 0.80 4.000
Vibrador 1 3.5 3.5 0.80 2.800

SUBTOTAL M 8.853
MANO DE OBRA
COSTO
DESCRIPCION CANTIDAD JORNAL/HR RENDIMIENTO COSTO
HORA
A B C=A*B R D=C*R
Albail 4 3.75 15.00 0.80 12.000
Pen 8 3.15 25.20 0.80 20.160
Fierrero 1 3.75 3.75 0.80 3.000
Carpintero 1 3.75 3.75 0.80 3.000
Maestro 0.5 5.24 2.62 0.80 2.096
Residente 0.1 10.00 1.00 0.80 0.800

SUBTOTAL N 41.056
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNIT. COSTO
A B C=A*B
Cemento Portland Saco 8 6.70 53.60
Arena M3 0.6 8.00 4.80
Piedra 3/4 M3 0.9 26.00 23.40
Agua potable M3 0.4 4.00 1.60
Acero de refuerzo en varillas Kg. 108.2 1.26 136.33
Tabla de encofrado 2.2 x 0.3 m U 12 4.50 54.00
Tira 6x6cm x 2.4m Unidad 6 4.00 24.00
Alambre recocido # 18 Kg. 2.85 3.50 9.98

SUBTOTAL O 307.71
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD TARIFA. COSTO
A B C=A*B

SUBTOTAL P 0

TOTAL COSTO DIRECTO (M+N+O+P) 357.62

INDIRECTOS Y UTILIDADES 25% 89.40


OTROS INDIRECTOS 0% 0.00
COSTO TOTAL DEL RUBRO 447.02
VALOR OFERTADO
MATRIZ - ANALISIS DE PRECIOS UNITARIOS
RUBRO:
UNIDAD: M

DETALLE: ANCLAJE A PISO CON SIKADUR PREMIER Y VARILLA CORRUGADA DE 12mm C/ 0.20 m DE SEPARACION

EQUIPOS
DESCRIPCION CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO
A B C=A*B R D=C*R
Herramienta menor 5% 5 0 0 0 0.07

SUBTOTAL M 0.07
MANO DE OBRA
DESCRIPCION CANTIDAD JORNAL/HR COSTO HORA RENDIMIENTO COSTO
A B C=A*B R D=C*R
Maestro 0.05 5.24 0.26 0.4 0.1048
Pen 1 3.13 3.13 0.4 1.25

SUBTOTAL N 1.35
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNIT. COSTO
A B C=A*B
SIKA DUR 32 PRIMER KG 0.12 19.75 2.39
VARILLA CORRUGADA DE 12MM KG 1.44 1.2 1.73

SUBTOTAL O 4.12
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD TARIFA. COSTO
A B C=A*B

SUBTOTAL P 0

TOTAL COSTO DIRECTO (M+N+O+P) 5.54

INDIRECTOS Y UTILIDADES 25% 1.39

OTROS INDIRECTOS 0%

COSTO TOTAL DEL RUBRO 6.93


VALOR OFERTADO
MATRIZ - ANALISIS DE PRECIOS UNITARIOS
RUBRO:
UNIDAD: M2
DETALLE: ENLUCIDO INTERIOR DE RIOSTRA

EQUIPOS
COSTO
DESCRIPCION CANTIDAD TARIFA RENDIMIENTO COSTO
HORA
A B C=A*B R D=C*R
Herramienta menor 5% 0 0 0 0 0.461

SUBTOTAL M 0.461
MANO DE OBRA
COSTO
DESCRIPCION CANTIDAD JORNAL/HR RENDIMIENTO COSTO
HORA
A B C=A*B R D=C*R
Maestro 0.5 5.24 2.62 0.8 2.10
Albail 1 3.75 3.75 0.8 3.00
Pen 1 3.15 3.15 0.8 2.52
Residente 0.2 10.00 2.00 0.8 1.60

SUBTOTAL N 9.22
MATERIALES
DESCRIPCION UNIDAD CANTIDAD PRECIO UNIT. COSTO
A B C=A*B
Cemento Portland Saco 0.2 6.79 1.36
Arena fina M3 0.04 8.00 0.32
Agua M3 0.02 4.00 0.08

SUBTOTAL O 2.6
TRANSPORTE
DESCRIPCION UNIDAD CANTIDAD TARIFA. COSTO
A B C=A*B

SUBTOTAL P 0

TOTAL COSTO DIRECTO (M+N+O+P)


12.28
INDIRECTOS Y UTILIDADES 25%
3.07
OTROS INDIRECTOS 0%
0

COSTO TOTAL DEL RUBRO


15.35
VALOR OFERTADO

You might also like