DATE: 21 FEB 2017

STEEL=FE 500 CONC M15(1:2:3)


1 MATERIAL

S.N Items of
TOTAL Rate Unit Amount Remarks
Work
1 Cement 1769 945 Bags 1671705
2 Sand 4439 110 Cu.ft 488290
3 Steel 42147.82 81 KG 3413973
4 Agg. 6956 135 Cu.ft 939060
TOTAL 6513028
A.LABOUR COST= 1888778
B.WASTAGE= 195390.9
C . CONTINGENCIES= 300000
D .BACKFILL COST 200000

TOTAL AMOUNT NRS= 9097198


(NINETY LAKH NINETY SEVEN THOUSAND ONE HUNDRED AND NINETY EIGHT ONLY )
CONCRETE WORK
WALL

BASE AREA=14.11SQFT BASE VOLUME=2700 CUFT

UPPER WALL AREA=26.58SQFT UPPER WALL VOLUME=4784.4CUFT

TOTAL AREA=40.69 SQFT


TOTAL VOLUME =7484.4cuft
COLUMN

NO OF COLUMN REQUIRED =13(SIZE 14"X14")


VOLUMN OF ONE COLUMN=22.96 SQFT
VOLUMN OF 13 COLUMN=298.48 CUFT

TOTAL VOLUMN OF CONC REQD FOR STR= 7782.88CU FT


Cement Sand
Cu.Feet Cu. Yard Cu. Meter Cu.Feet Cu. Yard Cu. Meter
M15= 1:2:3 1414.982 52.40695 40.06664 4439.2 164.4 126.82
Aggregate No. Of Cement Bag (50kg)
6956 257.62 198.74 1768.728003
REINFORCEMENT WORK

WORK Description Dia NO Length Length Wt/m Qty REMARKS


Ft metre kg
Reinforcement Work
Foundation -
Y-DIRECTION Bottom bar 12 f 432 9.5 2.9 0.89 1114.992
Top bar 16 f 432 9.5 2.9 1.58 1979.424

X-DIRECTION Bottom bar 12 f 15 192 58.53 0.89 781.3755


Top bar 16 f 15 192 58.53 1.58 1387.161 lap length 12'
(4 times 3')
wall
MAIN BAR Front Face 12 f 432 41 12.5 0.89 4806
Back Face 20 f 432 41 12.5 2.47 13338 lap length 10'-6''

STARTER BAR Front Face 12 f 432 9 2.75 0.89 1057.32


Back Face 20 f 432 9 2.75 2.47 2934.36

DISTRIBUTION Front Face 12 f 80 192 58.53 0.89 4167.336


BAR Back Face 12 f 80 192 58.53 0.89 4167.336 lap length 12'
(4 times 3')

U BAR TOP 12 f 432 3 0.92 0.89 353.7216

Column
TOTAL NO
23 16 f 138 41 12.5 1.58 2725.5
20 f 138 41 12.5 2.47 4260.75 lap length 10'-6''
Ring 8 f 2280 6 1.83 0.4 1668.96

Binding wire 500


TOTAL 42147.82