You are on page 1of 12

BUILDING RESEARCH & INFORMATION (2005) 33(6), 512 522

Innovation in construction: a sociology of


technology approach

Chris Harty

Department of Sociology, County South, Lancaster University, Lancaster LA1 4YD, UK


E-mail: c.harty@lancaster.ac.uk

An alternative approach to understanding innovation is made using two intersecting ideas. The first is that successful
innovation requires consideration of the social and organizational contexts in which it is located. The complex context
of construction work is characterized by inter-organizational collaboration, a project-based approach and power
distributed amongst collaborating organizations. The second is that innovations can be divided into two modes:
bounded, where the implications of innovation are restricted within a single, coherent sphere of influence, and
unbounded, where the effects of implementation spill over beyond this. Bounded innovations are adequately
explained within the construction literature. However, less discussed are unbounded innovations, where many firms
collaboration is required for successful implementation, even though many innovations can be considered
unbounded within constructions inter-organizational context. It is argued that unbounded innovations require an
approach to understand and facilitate the interactions both within a range of actors and between the actors and
technological artefacts. The insights from a sociology of technology approach can be applied to the multiplicity of
negotiations and alignments that constitute the implementation of unbounded innovation. The utility of concepts
from the sociology of technology, including system building and heterogeneous engineering, is demonstrated by
applying them to an empirical study of an unbounded innovation on a major construction project (the new
terminal at Heathrow Airport, London, UK). This study suggests that system building contains outcomes that are
not only transformations of practices, processes and systems, but also the potential transformation of technologies
themselves.

Keywords: collaboration, innovation management, innovation, interaction, project management, project organization,
system building, three-dimensional (3D) computer-aided design (CAD)

Comment comprendre linnovation ? Lauteur propose une autre methode basee sur deux idees se recoupant. Selon la
premiere idee, linnovation necessite que lon prenne en compte les contextes sociaux et organisationnels dans
lesquels elle se situe. La complexite du contexte des travaux de construction tient a la collaboration
interorganisationnelle, a une approche basee sur les projets et la repartition du pouvoir entre ces organisations.
Dapres la seconde idee, on peut distinguer deux modes dinnovation: linnovation limitee, ou les implications de
linnovation sont limitees a une seule sphere dinfluence coherente, et linnovation illimitee, ou les effets de sa
mise en oeuvre vont au-dela de cette sphere. Linnovation limitee est bien expliquee dans la litterature relative au
secteur de la construction. En revanche, linnovation illimitee ne beneficie pas du meme traitement, lorsque
plusieurs entreprises doivent collaborer pour une application reussie de linnovation, meme si de nombreuses
innovations peuvent etre considerees comme illimitees dans le contexte interorganisationnel de la construction. On
pretend que les innovations illimitees necessitent une approche permettant de comprendre et de faciliter les
interactions dune part, au sein dun groupe dacteurs et, dautre part, entre les acteurs et les artefacts
technologiques. Les idees issues dune approche sociologique de la technologie peuvent etre appliquees a la
multiplicite des negociations et des alignements qui contribuent a la mise en oeuvre dinnovations illimitees. On
demontre lutilite de concepts appartenant a la sociologie de la technologie, y compris la construction
industrialisee et lingenierie heterogene, lorsquon les applique a letude empirique dune innovation illimitee
dans le cadre dun grand projet de construction (par exemple, le nouveau terminal de laeroport de Heathrow a
Londres). Cette etude suggere que la construction industrialisee apporte des resultats qui sont non seulement des

Building Research & Information ISSN 0961-3218 print ISSN 1466-4321 online # 2005 Taylor & Francis
http: www.tandf.co.uk journals
DOI: 10.1080/09613210500288605
Innovation in construction: a sociology of technology approach

transformations des pratiques, des processus et des systemes mais qui ont egalement le potentiel de transformer les
technologies elles-memes.

Mots cles: collaboration, gestion de linnovation, innovation, interaction, gestion de projets, organisation de projet,
construction industrialisee, conception assistee par ordinateur (CAO) en trois dimensions (3D)

Introduction from the sociology of technology to unpack the multi-


Construction, like football, is a funny old game. It gen- plicity of negotiations and alignments that constitute
erates a large amount of academic research, much of the implementation of innovative technologies such
which is directed towards developing new models for as 3D CAD and the new practices that use it.
managing aspects of the construction process (e.g.
Love et al., 1998; Practice, 1998; Nicolini et al.,
2001). Other research concerns the transfer of organiz-
ational and management techniques developed in other Contexts of construction work
sectors, such as partnering or supply chain management Innovation, whether product or process based, cannot be
(e.g. Akintola et al., 2000; Dubois and Gadde, 2000). understood outside the contexts of its creation and
Government spokespersons also call for innovative tech- implementation. Construction has some particular
nologies and processes from elsewhere to be adopted in characteristics based on long-standing ways of working,
construction work (Egan, 1998). But often research and which together make it unique from other areas of
finds that attempts to implement innovative techniques industry. Five features are central to understanding the
suggest potential benefits, but also throw up problems construction contexts into which innovations such as
regarding the existing and entrenched ways of 3D CAD are introduced: the collaboration upon which
working and collaborating within construction. In prac- construction work is based, its organization around par-
tice, real-life contingencies and multiple interdependen- ticular projects, the centrality of communication to its
cies complicate the adoption of new tools and processes performance, the importance of inter-organizational
and there is little to guide the practitioner through the relations, and the way power is distributed.
messy and contingent process of adoption and diffusion.

This paper has three main aims. First, to set out the key Construction work as collaborative
characteristics of construction work, based on its colla- Extensive collaboration is required to build more or less
borative and inter-organizational nature, and the dis- anything, from the simplest house to the most high-tech-
tribution of power within it. Second, to distinguish nology corporate headquarters. Construction work is
between two different types, or modes, of innovation, constituted from the efforts of manifold organizations,
which are given here the terms bounded and each with their own resources, practices and aims. At
unbounded. This distinction is used here to differen- an organizational level they carry out activities recogniz-
tiate between innovations that are relatively contained able in a traditional sense as a single firm acting in its own
in their effects and consequences within a single organiz- interests at the expense of others. For instance, competing
ation or coherent sphere of influence, and those which for work through tendering, or developing competitive
have widely felt inter-organizational repercussions and edge through using new practices and new tools to
affect a number of such spheres of influence. Third, to improve upon existing methods in terms of speed or
outline an alternative way to understand unbounded cost. However, actually to undertake work requires the
innovations within construction using concepts from collaboration of a number of different firms and a wide
the sociology of technology, and to use these to frame range of skills and specialisms: architectural and design
a discussion of empirical material detailing the practices, general contractors, specialized subcontrac-
implementation of three-dimensional (3D) computer- tors, fabricators, manufacturers, and suppliers.
aided design (CAD) technologies and processes on the
construction of a new, fifth terminal (T5) at Heathrow
Airport, London, UK. Construction work as project-based
In order to satisfy the requirement for collaboration and
The argument made here is that understanding the geographical centring of activity around a particular
unbounded innovations such as 3D CAD within the site, construction work is organized as project based,
particular embedded characteristics of construction where a diverse range of firms, with different parts to
work requires an approach that accounts for inter- play, all have to be coordinated. It is within project and
actions between a range of actors and technological inter-organizational contexts that innovations such as
artefacts. Although existing construction research 3D CAD have to function. Project organization and
addresses a range of innovative activity within the project management have become of great interest
sector, a good case can be made for applying insights across many different areas of industry, generating
513
Harty

research into alternative forms of organization that move relations within construction have become a subject
away from traditional firm-based models of activity. of scrutiny from a number of perspectives, but often
Much of this work concentrates on aligning older, less the specificities of construction contexts complicate
flexible hierarchical models with long-term mass pro- matters. The benefits of supply chain management
duction; and associating new, project-oriented organiz- (SCM) as a way to improve inter-firm coordination in
ation with contemporary consumer demand for construction have been delineated by Vrijhoef and
innovation, newness and change, with corresponding Koskela (2000), but they point out that practical
low volume production, and with the expansion of new ways to implement SCM need to be developed to
markets such as mobile telecommunications and software account for constructions specific situation and
development. Although the maturity of construction as a characteristics. Partnering has also generated interest,
project-based industry questions this tradition versus but much research has overly focused on strategic
novelty opposition, it is certainly the case that traditional and best-practice approaches at the expense of the
models of the firm as a discrete entity fighting within a detail on how actually to implement and sustain
particular environment do not easily map onto the activi- inter-organizational relations within construction
ties of construction firms. contexts (Bresnen and Marshall, 2000; Bresnen et al.,
2005). These cases point to a need to ground any inno-
In light of this recognition, project organization has vation within the specific contexts of construction
received considerable attention. A growing literature work. The benefits of modular architectures have
on complex products and systems (Davies and Brady, been shown to be useful in some areas such as elevator
2000; Gann and Salter, 2000; Hobday, 2000; Hobday design (Mikkola, 2000), and manufacturing techniques
et al., 2000; Prencipe et al., 2003) initially looks interest- have been used to provide insights into managing an
ing for those interested in construction organization, and industrialized construction process as a holistic
it reveals a mismatch between a high amount of inno- system (Gann, 1996), but neither of these offers a
vation and learning at the project level, where many way of conceptualizing the fabric of existing construc-
novel problems are encountered and solved, and the tion practices and interactions.
capture and translation of this into a reusable organiz-
ational resource. It is a problem that has been high-
lighted within construction activity (Dubois and
Gadde, 2000). However, quite how to bridge this Power and control in construction
projectfirm gap is a more difficult challenge. Also The final and possibly most important feature in giving
from a construction point of view, most complex pro- construction its particular character is the distribution
ducts and systems cases are confined within a single of power. Construction work may be coordinated by
organization, and do not engage with the extra require- one main contractor, but each organization involved
ment of inter-firm collaboration where ownership and has its own influence on a project and brings its own
control of activities are not necessarily clearly delineated. expectations and working methods. Even contractual
obligations, which are the mainstay of the formal
coordination of construction work, are in reality hard
Construction work as communication based to enforce, especially once work is underway (Earl,
The challenges of managing the inter-organizational 1996). In construction, the implementation of inno-
collaboration and project basis of construction work vations located at this inter-organizational or project-
bring this paper to the third key feature: the role of wide level is placed beyond the control of a single
communication and information transfer within sphere of influence. But surprisingly, there has been
construction projects. Efficient collaboration (whether little attention paid to the distributed nature of power
intra- or inter-organizational) relies on effective within construction. Walker and Newcombe (2000)
diffusion of information throughout a project, an area discuss the mismatch between the autonomy of
which has been considered problematic in construction construction organizations and the interdependencies
for some time (e.g. Higgin and Jessop, 1965). Design inherent in construction work, and they outline a
details, work schedules, materials purchasing, and typology of power as expertise-, reward- (i.e. exercised
supply and resource allocation need to be coordinated through the allocation of work) prestige or reputation-
across the project and, therefore, and crucially, across based, and coercive, but they stop short of unpacking
multiple firms. It is vital to ensure effective collaboration the mechanisms through which these are accepted or
and the minimum of delays. In construction work, com- resisted, central to Foucaults (1991) conception of
munication must hold together complex sequences of power as reciprocal, where power can only be exer-
activity extending across organizational boundaries. cised if others accept it.

The context into which innovations such as 3D CAD


Construction work as inter-organizational are introduced is one with multiple inter-
A common theme across these features is the central organizational relations, complex interdependencies
importance of inter-organizational relations. These between firms and the lack of a single authoritative
514
Innovation in construction: a sociology of technology approach

driving force that can see through implementation relies on high levels of shared commitment among
across a whole project. parties, and to directing resources to a collective end,
as well as on long-term relations that are difficult to
sustain within the contexts of construction projects
ephemeral, shifting coalitions (Love et al., 1999).
Bounded and unbounded modes of
innovation What does this mean for the study of innovations in
Given the inter-organizational contexts of construction construction? Within the construction literature,
work and the distribution of power across multiple although it has been argued by some that innovation
organizations within construction projects, a distinc- in construction is low (Winch, 1998; Koskela and
tion needs to be made between innovations that can Vrijhoef, 2001), good cases have been made for a large
be contained within a single sphere of influence and amount of innovative activity, such as that made by
those that extend beyond this into the wider inter- Gann (2000), most notably within the research and
organizational landscape of construction work. These development activities of product suppliers and manu-
are termed here bounded and unbounded modes of facturers. Often, these innovations take the form of
innovation, respectively. The key to this differentiation bounded substitutions of one product for something
is not the inherent nature of the innovation itself, or the else, what Bowley (1960) calls ersatz innovations,
particular strategy of implementation, but the context but others can have wide-ranging or systemic effects,
into which it is introduced. The distinction between such as the move from steam to electric power in indus-
bounded and unbounded rests on the (potentially try driving demand for new types of factory building,
unforeseen) consequences of an innovation repercus- or the development of the elevator as a response to
sions beyond the control of its implementer. requirements of generating high rental incomes from
buildings within confined urban spaces (Gann, 2000).
There are several alternative ways of differentiating In these cases, although the consequences of adoption
between modes of innovation. For instance, as auton- resonated across organizational boundaries, the
omous versus systemic (Teece, 1986); as linear versus external pressures of client demand and expectation
interactive (Rothwell, 1994); or as networked versus acted as a single driving force, which led to the accom-
firm-based (e.g. Powell, 1991; Powell et al., 1996). modation of innovations across the spectrum of
However, although useful, none of these specifically construction work.
considers the scope or reach of an innovation alongside
the implementers ability to influence or direct its adop- Another example of a bounded innovation in construc-
tion and use. The concept of bounded or unbounded tion is two-dimensional (2D) CAD. Although its
innovation does just this. It distinguishes between inno- introduction instigated considerable changes in the
vations that can be contained within an implementers activities of drafters, it had little significance for the
control and those that spill beyond this into potentially rest of the actors and organizations in the overall
more contested domains. It adds a further way of dif- construction process. In terms of inputs, the design
ferentiating innovations in addition to those above. information required to produce the drawings
For instance, a bounded innovation could be con- remained the same, as did its output as paper-
sidered either systemic or autonomous in Teeces based plans for use by contractors on site, irrespective
terms. The introduction of electronic procurement of their production on computer or drawing
and leaner supply chains by Ford in the late 1980s board. Both the decision to adopt and the conse-
had considerable implications for component suppliers quences of adoption were contained within single
(Hammer, 1990), but their dependence on Ford meant organizations.
they had to adapt to the new processes. In this way, a
systemic innovation was also a bounded one, as With the present case of 3D CAD, things are somewhat
Fords sphere of influence extended throughout the different. 3D CAD has been in use for some time in
system of component suppliers. Rothwell discusses construction as a visualization tool to produce
how interactive modes of product development use representations of designs to communicate ideas to
inter-organizational collaboration and shared technol- clients and other collaborators on a project.
ogies, but does so in the context of novel research and However, it can also be put to a more ambitious use
development and new ventures, with shared goals as a coordination tool to combine all design infor-
based on mutual benefits, rather than innovation mation from architects, designers and engineers,
emerging from existing contexts with multiple effectively creating a virtual building through software
engrained and potentially contesting positions. In this before on-site work commences. The model allows any
sense, an interactive mode of innovation can also be dimensional problems between disciplines such as
described as bounded, for although there are a structural steel and building services to be discovered
number of spheres of influence, they are all in accord. at the design stage, a process known as clash detec-
In a similar way, the network organization as tion, where problems can be rectified much more
opposed to hierarchical modes of operation also cheaply and quickly than after fabrication of materials
515
Harty

and on-site work begins. An internal study conducted electricity networks (Hughes, 1983), railways and
by Laing in 2001 found that this method could the Internet (Summerton, 1994).
produce savings of more than 10% of the total project
cost. Also, the 3D model can be used as the source for Hughes (1983, 1998) is concerned with the production
materials scheduling and time planning for the project, of a functioning system through the interconnection of
and for facility management after construction. its constituent parts from a heterogeneous network of
technologies, people and organizations. But this
Implementing 3D CAD in this way requires system building is not just about selecting and connect-
adaptations far beyond its location within drafting ing the right components. More than just a jigsaw
departments, creating repercussions throughout the puzzle, Hughes describes system building as born
inter-organizational fabric of construction work. Full from processes of alignment involving the selection,
specification of designs is needed in order to construct adaptation, and even creation of necessary components
the virtual building, rather than providing partial 2D and their coordination to form a holistic system.
schematics which are fleshed out as on-site construc- Although once up and running such large technical
tion progresses, reconfiguring the sequences in which systems gradually build up their own momentum, in
construction work is undertaken. The physical build- Hughess case of electrification, alignment activities
ing has to match the virtual model exactly, constrain- centred around a single figure. Thomas Edison stood
ing the activities of on-site workers and leaving no at the centre of the emerging electricity network in
margins for alteration. 3D CAD is an unbounded the US, inventing artefacts and companies to manu-
innovation, and to succeed it must gain support from facture and sell them, and cajoling institutions and
organizations located throughout the construction firms into supporting the new power source.
process. It extends from its actual location within
CAD departments potentially to affect the coordi- The idea of system building is appealing, but it does not
nation of the whole construction process. map onto the distribution of power and diversity of
existing practices and expectations within cons-
truction. However, Law (1986, 1994) provides the
concept of heterogeneous engineering to describe
Useful concepts from the sociology of the process of producing relatively stable socio-
technology technical entities through the interconnection and
Existing models of innovation in construction rely on a aligning of diverse objects and actors. Suchman
single, central driving force, whether a single organiz- (2000, p. 313) uses the concept to describe the
ation, external driver or a coordinated coalition, to painstaking arrangement of myriad human and non-
introduce innovation and manage them into good human elements in a study of the design of a new
currency (e.g. Winch 1998; also Van de Ven, 1986). bridge, and discusses the interactions between multiple
However, where there are conflicting interests, as is and conflicting constituencies of interested actors,
the case within many construction projects, there is including public agencies, local government depart-
little in the way of attempts actually to investigate ments, land owners, citizens groups and politicians.
how they might be resolved, and the mechanisms by Suchman goes on to describe alignment activities as
which such negotiations might play out. persuasive story telling where the different concerns
and views of involved parties intersect and are dis-
This is where a turn to the sociology of technology cussed and negotiated, although some voices are
can help in providing some concepts that account more persuasive than others.
for both multiple interactions and influences as inno-
vations are developed and implemented. Much of this MacKenzie (1990), in a discussion of missile testing
work is oriented around examining how a diverse and accuracy, also accounts for a plethora of different
range of actors and material objects interact and perspectives, and argues that the technological charac-
combine to produce new or reconfigure existing teristics of an artefact are affected by a combination of
socio-technical practices, processes and systems. existing and emerging interests and stakes in possible
Although differences in approach exist, there are outcomes. Taking this further, Bijker (1992) shows
common features, notably the grounding of concepts how the negotiations between different relevant
within specific contexts, and a commitment to social groups can transform technological artefacts,
detailed, qualitative and often ethnographic research. a process of invention through diffusion that serves
Empirical settings and cases include laboratories and to highlight both the malleability of technologies and
the production of scientific knowledge (Latour and the importance of their contexts of use in shaping
Woolgar, 1979; Law, 1994), new technological inno- their characteristics and potential uses. It is not only
vations including the bicycle (Bijker, 1995), the elec- the outcomes of the implementation of innovation
tric vehicle (Callon, 1986) and road-guidance that are affected by negotiations between different
technologies (Mangematin and Callon, 1995), and actors and groups, but also the very technologies
complex inter-organizational systems such as around which negotiations are located.
516
Innovation in construction: a sociology of technology approach

Together, these ideas provide a framework with which informal discussions, and attending team and project
to approach the study of complex, unbounded inno- meetings. Towards the end of the period, the author
vations such as 3D CAD. Successful system building conducted 23 semi-structured, one-hour-long inter-
involves activities of the alignment of multiple actors views with interviewees ranging from the head of
and artefacts towards a specific goal or vision. In the delivery for the whole project to agency-based CAD
context of construction, this alignment must account drafters. The interviews were informed by what the
for multiple constituencies and overlapping spheres author had seen and participated in over the previous
of influence. Heterogeneous engineering is the process months.
of producing and holding together specific orderings
and configurations of different actors and objects. The commitment to project-wide implementation of
The outcomes of these orderings are not only just 3D CAD as a way of coordinating construction
new or transformed practices, processes or systems, work, the scale of the T5 project, and the wide range
but also, potentially, a transformation of technologies. of organizations and individuals involved in it make
Positioned in this way, a distributed system building it an excellent case for thinking about innovation as
approach, looking at how attempts are made to put distributed system building. In this section, the
together stable assemblies of people, technologies and approach is used to frame and analyse some particular
practices within specific contexts, has much to offer cases from the authors research.
in thinking about the dynamics of unbounded inno-
vation in construction.

Visions of 3D CAD at T5
The official vision of 3D CAD at T5 rests on collabor-
System building in action: theTerminal 5 ation and information sharing across the whole
Project at Heathrow Airport, London project. This collaboration is enabled by shared and
This paper will now use these concepts to discuss intercompatible design and drafting software, and
empirical material taken from research on the design mediated by a document management database. All
of BAAs new fifth terminal (hereafter T5) at Heathrow information created for the project is captured, and
Airport, London, UK. T5 is one of the biggest construc- all elements of the design of the terminal are integrated
tion projects currently underway in the world, creating into a single model environment (SME). This vision is
over 6000 construction jobs over its five-to-six-year also informed by assumptions about the nature of 3D
duration. BAA is a consistent purchaser of construction CAD technologies. The T5 project managers spoken
work and as such has considerable financial leverage to smooth out the transition of using 3D CAD as
and some understanding of the problems associated part of an on-going process that started with the
with the sector. Using this leverage, for T5s design introduction of 2D CAD systems in the early 1980s,
and construction, BAA has implemented rolling frame- drawing a continuum from designing everything
work agreements with upwards of 50 construction using CAD (for the Terminal 4 project, which started
firms, rather than allocate work based on competitive in 1980) to using compatible CAD systems that
tendering. A condition of the agreements is that allowed a limited combination of different design
firms staff working on T5 are co-located to offices at elements on one 2D drawing, to T5 making the step
Heathrow Airport, rather than work from their par- up to 3D modelling and virtual building, allowing all
ticular firms offices. BAA is also committed to imple- design and construction information to be coordinated
menting 3D CAD as a method of coordinating both and shared.
the process of designing and building the terminal,
and the variety of information produced for it. This vision of integrated 3D modelling held by BAA
However, rather than force through implementation and the projects management is one of a technology-
as a condition of work allocation, they pursued an led construction process, with the potential of 3D
integrated team approach to the project (BAA, CAD as the avant-garde, inspiring a vision of new
2003) involving all partners in consultations over the ways of working, driving reconfigurations of practice.
introduction and use of the new technologies. On bringing the vision to fruition, one project
manager commented that:
The analysis of the T5 project and the implementation
of 3D CAD there is based on research conducted by the Im not saying that were 100% there but we
author at the co-located project offices at Heathrow know the technology will be there to enable us
between October 2001 and April 2002. At the time to do it.
the project was moving from concept to detailed (interview, 13 February 2002)
design, and the coordinative issues of using 3D CAD
across the whole project were beginning to be appreci- and another stated that if I had a conclusion . . . its
ated. The author spent several weeks in blocks of three that we need to train (interview, 14 February 2002).
or four days observing staff at work, engaging in This assumes that all project staff can be united
517
Harty

within this vision, but this does not account for the sharing and coordination with the rest of the project
different expectations and existing practices that are within the SME.
brought into the project. Contrast the opinion of one
project manager with one of the drafters: One group with which the author was involved con-
cerned building services, a complex discipline including
I had this far-out vision that a construction electrical, plumbing, heating and air-conditioning
worker doesnt need a drawing hed have a elements. Some of the group had already experienced
little camera, a little chip in it and boom 3D CAD software, using it as a solution to coordinate
he can call up the document and use it . . .. complex services and several different 3D modelling
packages were available, all with their own merits and
its only going to get worse as more construction
drawbacks. At a series of meetings between project man-
[rather than design] based people get on board
agement, building services engineers and CAD drafters,
. . . when you come to it its some hairy arsed
the relative advantages of each available package was
steel fitter on site who wants a sheet of paper to
discussed. The chosen software would have to align
see where this re-bar goes.
with engineers and drafters expectations and with the
(interviews)
requirements of working in 3D and within a coordinated
SME. However, no available products could fulfil all
The durability of existing ways of working, and expec-
these requirements. The intended outcome of these dis-
tations about how project activities should be under-
cussions was the selection of a technology, but the
taken, are not considered within the official vision,
actual outcome was a list, to be distributed to developers,
but present a very real challenge to implementation.
outlining necessary changes to transform existing soft-
On reflecting on the success of implementing 3D
ware products into something that would align the offi-
CAD, one manager said that project staff from
cial visions commitment to coordination through 3D
different organizations:
CAD with the working needs of engineers and drafters.
all brought their own practices in. Weve had a
The focus group was a site of attempts at alignment.
real struggle trying to set up standard processes
Efforts were being made to engineer or build heteroge-
not set them up thats the easy part but to
neously a system of 3D CAD software and practices,
get people to use them thats been out greatest
but, crucially, with more than one system builder,
challenge and continues to be.
and with a number of ideas and visions informing its
(interview)
assembly, none of which had the ability to overrule
Although particular technologies might inspire visions others or persuade them to change. The negotiations
and suggest new ways of working, actually realizing between them positioned the software packages as
them is another issue. At T5, 3D CAD was being intro- the thread with which to stitch together the official
duced into a project context of existing practices, vision and the visions of services engineers and draf-
alternative visions and expectations that challenged ters. But the software packages in their existing forms
the official vision. Technological possibility was not could not do this, and so new requirements were fed
enough to drive implementation and there was much back to developers to transform the software into
work to do in heterogeneously engineering a coherent something capable of enabling this alignment.
and inclusive system of technologies and practices
from the diverse range of expectations and visions
present within the project.
Transforming and aligning technologies
These new considerations, which included the require-
ment that fabrication, as well as modelling, could be
Aligning visions and practice undertaken with the same software, hence integrating
Another implication of this grand vision was the inte- the two processes in line with BAAs vision, extended
gration of all the practices of design and drafting (as the project network beyond the staff located at the
well as construction and fabrication later on in the shared offices to include software developers. Although
project). In order to achieve this, and to consider the the idea of combining users insights in the develop-
different practices and expectations of project staff, ment of new products is not new (e.g. Von Hippel,
focus groups were initiated based on functional distinc- 1986, 1988, 1989), in terms of system building this
tions and the division of activities across the project. introduced another set of negotiations. The developers
These were intended to involve project staff fully in themselves had to become aligned in order to produce
the implementing of 3D CAD technologies and prac- new versions of their products that were compatible
tice. The aim was for different groups to outline their not only with the requirements of users, but also with
specific requirements from the technology, and to BAAs vision. This in fact led to more difficulties,
select software components that could fulfil those especially as none of the developers had previously
requirements in a way that would also allow capture, considered adding functions such as fabrication to
518
Innovation in construction: a sociology of technology approach

their software, or thought about intercompatibility a temporary stop-gap was rejected. However, rather
with products that were seen as competitors: than wait while the negotiations continued, they took
alternative action:
weve had software Xs developers in, then weve
asked software X and software Y to write a link we wanted to get on everyone was talking
[for file compatibility] between them. . . . Soft- about 3D, but the only way we could see 3D
ware X come back with a 41 page document going was to start it . . . through the back door
saying we cant do this based on blah blah [we brought] in a stand alone machine thats
blah . . .. not connected to the network and that has got
(interview) CADduct [a 3D ductwork CAD package] on it
. . . weve pushed it, otherwise . . . we still
Accommodating the projects requirements also meant wouldnt have CADduct in here.
that some software had to transform from something (interview, 12 February 2002)
intended as a design tool into something that was not
only about spatial representation, but also about a Here the system-building efforts of project manage-
manufacturing tool (i.e. it could control the fabrication ment could satisfy neither the official vision nor the
of components). This represented a substantial trans- desires of the staff actually to do some work. These
formation of a piece of softwares functions, showing engineers smuggled in their own computer complete
how fluid such technologies can be within contexts of with modelling software, and unofficially did some
use, and the extent to which system-building activities design work. In fact, they built their own competing
can impact on technological artefacts. In this case, the system, albeit one of limited size compared with
innovative software does not drive the implementation BAAs vision, based on existing individuals, skills and
of new practices to support it, but is itself being defined software. They even aligned the developers of
and redefined within the network of visions and nego- CADduct to their system, convincing them to spend
tiations surrounding it. Even though BAAs vision is some time at the T5 office and make changes to the
understood to derive from technological possibility, software specifically for them. Within the negotiations
here the technology did not exist in a form that was between project managers and staff there is more than
capable of enabling the vision within the context of one system builder, and here there is more than one
the project and the needs of the building services system being built. Links between bits of technology,
teams. Eventually, although various developers users and visions of what they are aiming to achieve
accommodated several changes, the plan to link are dynamic, with alignment being undertaken
drafting and fabrication had to be dropped. potentially by many different builders, including, in
this case, our engineers above.

Competing and parallel systems The problems encountered in attempts to set up one
These events are difficult to explain within a frame- all-inclusive, unified system at T5 stem from the
work of bounded innovation, as offered by much of diversity of different skills, practices and conventions
the organizing and innovation literature. But when across construction work as a whole, which have to
viewed as a competitive system-building endeavour, be made in some way commensurable. This was
the interplay between different (and heterogeneous) attempted by using shared technologies and impos-
components in the network shows how potential out- ing standards for their use, including specific ways
comes can be altered, both for the innovation itself of layering and formatting CAD drawings. The
and for the system into which it is placed. There is com- strategy was supported through a CAD test to
petition over the shaping of both the innovation and ensure that all users, including engineers and archi-
the system. However, this does not necessarily lead to tects as well as drafters, could use the software in
a single, unified system. the specified way:

The negotiations within the building services group every user that walks through this door has to be
went on for several weeks, during which the project, trained up dedicated to this particular functional-
in terms of designing the services, was at a standstill. ity before he can get onto the [IT] system.
Because of the commitment to integrating all design (interview)
work into the 3D model, there was little point in
doing design work as it would have to be repeated The means by which diverse activities are made com-
using whatever set of software tools were eventually mensurable and coordinated is through standard,
implemented. In addition, and partly due to the size shared ways of using compatible CAD software and
of the project, the process of installing and licensing with collaboration and information sharing mediated
software on the projects network was complicated through electronic document management. However,
and very rigorous. One team of building service engin- not all activities that are important for the project
eers suggestion to use a particular piece of software as revolve around the actual use of CAD. One individual,
519
Harty

a temporary works engineer, had 30 years of experi- opposite effect of actually barring some individuals
ence of construction and especially of heavy lifting and technologies from being aligned at all.
work. He possessed a vast knowledge of complex
construction techniques and of suppliers and fabrica-
tors of lifting machinery, and these qualities were the Making 3D CAD work
reason for his secondment to the T5 project. The above examples show some of the failures experi-
However, he failed the CAD test, and so could not enced as the technologies and practices that should
access any of the CAD software or document make up an integrated 3D CAD system were negotiated
management tools on the project network. But he and argued over. It can also be suggested that the misdir-
also needed to be producing designs for temporary ected alignment efforts can in fact inhibit the building of
works structures quickly to be sent out to fabricators some systems and exclude people and artefacts from
and manufacturers. Delays in temporary works could being aligned. However, in other areas, negotiations
potentially set back the whole project. This resulted were more successful. For the structural steel work in
in a rather circuitous workaround. He had to draw the project, the project managers were able gradually
the design using his own CAD software on his own to persuade engineers of the usefulness of 3D CAD.
old laptop, which sat on the desk next to his idling Initial scepticism based on engineers own understand-
and much newer networked computer with a 21-inch ings of what 3D CAD means and what it should do:
screen. He then e-mailed the files to himself at his T5
computer through a consumer dial-up account on the I used to argue with him [one of the project man-
laptop plugged into a telephone line. He then opened agers] at the beginning I say no you just cant
the drawings on a read-only version of AutoCAD and do it it wont work wed have real argument
could then print them out. If there were any changes sessions.
or errors to rectify, he had to go back to the original (interview)
on his laptop and repeat the process.
turned to acceptance as they were won over by the
This case, like that of the services engineers, is another benefits of adjusting their practices to accommodate
of assembling an alternative, if again rather ad hoc 3D CAD coordination:
system to enable work to get done. In both cases the
alignment of existing skills and practices within an at the beginning I was shying away from 3D stuff
integrated, project-wide system failed, and in both I couldnt see it working, but more and more
cases this triggered alternative assemblies to be put you get into it theres a certain logic there
together, which avoided the official system, and and it does make sense for everybody to be
which relied on different visions about how project working in 3D . . ..
work could be carried out. (structural drafter 1, interview)

So what was wrong with the methods of alignment when I first joined . . . I wasnt sure what they
employed to build the official T5 system? In order to mean [by 3D model]. . . . Now Ive been here
support the official vision, the conditions of entry two years and Ive changed my thinking and
onto the projects system for both technologies and the way I worked previously . . ..
people were extremely strict. Only totally intercompa- (CAD drafter 2, interview)
tible software was approved, and once installed, it was As the project has progressed you can see why we
subject to finely specified and detailed rules governing did it . . . the system is working . . . if you can
ways of use the document outlining these standard understand the actual system it becomes a lot
practices runs to nearly two hundred pages. But this easier . . ..
only acted on one specific part of the practices of (structural engineer 1, interview)
design CAD and did not consider other areas of
expertise. As one engineer said: The benefits of the coordination of the steel work with
other disciplines, and the integration of its design and
I can only assume I am not required here, a fabrication, was enough to convince these engineers
draughtsman is whats needed? My engineering and drafters to change their practices. There was no
skills are obviously of no use to the project. coercion, but the story of coordinated 3D CAD was
(e-mail) powerful enough to align them within the T5 system.

From the project managements point of view, the


methods they hoped would integrate a wide range of
skills and practices within one system had the unex- Contribution of a system building approach
pected effect of actually excluding useful and necessary The above cases demonstrate how attempts to build
skills from it. Aligning all of the projects staff through systems of practices, people and technologies revolve
the imposition of rigorous CAD standards had the around the interactions between a wide range of
520
Innovation in construction: a sociology of technology approach

actors and technologies, and, like Suchmans case of culture and the unique features of the organis-
bridge-building, reveals their practical, political, tech- ational structure.
nical, contested, negotiated and situationally specific
character (Suchman, 2000, p. 322). They also rep- Each of these suggests that the particular configur-
resent an extension of Hughess work into a domain ations of construction work, with long-standing div-
where multiple interests and visions intersect, and it isions between disciplines and organizations and
shows how the process of implementing 3D CAD accepted ways of working, obstructs attempts to intro-
challenged and transformed these positions, and even duce new innovations and initiatives. The approach
the technologies themselves. To use Bijkers term, 3D used in the current study provides an alternative to
CAD was being invented through diffusion. the view that innovating across projects and between
firms is about system integration through a single
But the presented empirical material is based on a driving force, an alternative that focuses on the mech-
specific case, where many conflicting interests intersect anisms through which established roles, distinct
and where power can be resisted as well as exerted. disciplines, and traditional cultures contest and nego-
Also, the specific nature of 3D CAD as an innovation tiate with and over new technologies or new ways of
to coordinate disparate parts of the construction working. The notion of unbounded innovations offers
process means its implementation cuts across these a way to conceptualize innovation in construction
multiple spheres of influence. At T5, 3D CAD can be which is grounded in its particular existing character-
described as a systemic innovation, as its consequences istics and practices. Power is considered not only as
spread right across the fragmented landscape of distributed, but also as reciprocal, and something
construction work. It also shows many of the charac- which can be accepted or resisted. Technologies are
teristics of Rothwells fifth generation innovation. not finalized, fixed objects that can be imposed and
However, neither definition gives much of an indi- to which people must adapt, but are malleable and
cation of the contests and negotiations that character- can be transformed through contests over the building
ized 3D CADs on-going development at T5. By also of systems. Unforeseen consequences are also con-
positioning 3D CAD as an unbounded innovation, it sidered, where attempts at alignment can result in the
is differentiated from other forms of systemic or inter- exclusion of necessary actors from the system, and
active innovation, which have more consistent and trigger the assembly of alternate, parallel systems.
unified distributions of influence and expectation.
This multi-centred system building approach enables
In construction work, a context with multiple interests the researcher to recognize the complexity of the con-
and influences is by no means unusual, and the pro- texts of construction and is oriented towards inclu-
blems this situation can generate when implementing siveness rather than simplification. It accounts for
inter-organizational and project-wide strategies are the visions and expectations that mobilize system
often acknowledged in construction research. Return- building activity, but also their malleability and trans-
ing to the studies cited above, the same challenges formability as these activities occur. But perhaps
and potential problems are revealed. Nicolini et al. more importantly it goes beyond the identification
(2001, pp. 44 45) found that their advocated of barriers to innovation by focusing on the actual
approach of clustering: processes by which existing positions and expec-
tations interact with novel technologies and new
necessarily produces a certain breaking away ways of working.
from the established practices of the UK
construction industry . . . and posed major chal-
lenges to established roles, not only for the
main contractor and the designers, but also for
the suppliers and specialist contractors. References
Akintola, A., McIntosh, G. and Fitzgerald, E. (2000) A survey of
supply chain collaboration and management in the UK
Similarly, Love et al. (1998, p. 381) comment that: construction industry. European Journal of Purchasing and
Supply Management, 6, 159168.
each discipline has become dedicated to the BAA (2003) Terminal 5 Website (available at: http://www.baa.
optimisation of its own function, with little co.uk).
regard, or understanding of, its effect on the . . . Bijker, W. (1992) The social construction of fluorescent lighting,
or how an artefact was invented in its diffusion stage, in
construction process. W. Bijker and J. Law (eds): Shaping Technology/Building
Society Studies in Sociotechnical Change, MIT Press,
And Akintola et al. (2000, p. 167), when discussing Cambridge, MA, pp. 75102.
SCM, comment that: Bijker, W. (1995) Of Bicycles, Bakelites and Bulbs: Towards a
Theory of Sociotechnical Change, MIT Press, Cambridge,
MA.
the problems of implementing. . . are at present Bowley, M. (1960) Innovation in Building Materials, Gerald
associated with an inappropriate traditional Duckworth, London.

521
Harty

Bresnen, M., Goussevskaia, A. and Swan, J. (2005) Implementing Love, P., Gunasekaran, A. and Li, H. (1998) Concurrent engin-
change in construction project organizations: exploring the eering: a strategy for procuring construction projects. Inter-
interplay between structure and agency. Building Research national Journal of Project Management, 16(6), 375383.
& Information, 33(6), 547 560. Love, P., Li, H. and Mandal, P. (1999) Rework: a symptom of a
Bresnen, M. and Marshall, N. (2000) Partnering in construction: dysfunctional supply chain. European Journal of Purchasing
a critical review of issues, problems and dilemmas. and Supply Management, 5(1), 111.
Construction Management and Economics, 18, 229 237. MacKenzie, D. (1990) Inventing Accuracy: A Historical Soci-
Callon, M. (1986) The sociology of an actor-network: the case of ology of Nuclear Missile Guidance, MIT Press, Cambridge,
the electric vehicle, in M. Callon, J. Law and A. Rip (eds): MA.
Mapping the Dynamics of Science and Technology, Mangematin, V. and Callon, M. (1995) Technological compe-
Macmillan, London, pp. 1934. tition strategies of the firms and choice of the first users:
Davies, A. and Brady, T. (2000) Organisational capabilities and the case of road guidance technologies. Research Policy,
learning in complex product systems: towards repeatable 24, 441 458.
solutions. Research Policy, 29, 931953. Mikkola, J.H. (2000) Modularity and Interface Management:
Dubois, A. and Gadde, L. (2000) Supply strategy and network The Case of Schindler Elevators, LINK. Copenhagen.
effects purchasing behaviour in the construction industry. Nicolini, N., Holti, R. and Smalley, M. (2001) Integrating project
European Journal of Purchasing and Supply Management, 6, activities: the theory and practice of managing the supply
207 215. chain through clusters. Construction Management and
Earl, P. (1996) Contracts, coordination and the construction Economics, 19, 37 47.
industry, in P. Earl (ed.): Management, Marketing and the Powell, W.W. (1991) Neither market nor hierarchy: network
Competitive Process, Edward Elgar, Cheltenham. forms of organisation, in G. Thompson, J. Frances,
Egan, J. (1998) Rethinking Construction: Report of the Construc- R. Levacic and J. Mitchell (eds): Markets, Hierarchies and
tion Task Force, HMSO, London. Networks the Coordination of Social Life, Sage,
Foucault, M. (1991) Discipline and Punish: The Birth of the London, pp. 265 276.
Prison, Penguin, London. Powell, W.W., Koput, K.W. and Smith-Doerr, L. (1996) Inter-
Gann, D. (1996) Construction as a manufacturing process? organizational collaboration and the locus of innovation:
Similarities and differences between industrialized housing networks of learning in biotechnology. Administrative
and car production in Japan. Construction Management Science Quarterly, 41(March), 116145.
and Economics, 14(5), 437 450. Practice, C.B. (1998) A New Initiative to Benchamark UK
Gann, D. (2000) Building Innovation Complex Constructs in a Construction, CBP, Watford.
Changing World, Thomas Telford, London. Prencipe, A., Davies, A. and Hobday, M. (eds): (2003) The Business
Gann, D. and Salter, A.J. (2000) Innovation in project-based of Systems Integration, Oxford University Press, Oxford.
service-enhanced firms: the construction of complex pro- Rothwell, R. (1994) Towards the fifth-generation innovation
ducts and systems. Research Policy, 29, 955972. process. International Marketing Review, 11(1), 7 31.
Hammer, M. (1990) Reengineering work: dont automate, Suchman, L. (2000) Organizing alignment: a case of bridge-
obliterate. Harvard Business Review, 68(4), pp. 104112. building. Organization, 7(2), 311327.
Higgin, G. and Jessop, N. (1965) Communication in the Building Summerton, J. (ed.): (1994) Changing Large Technical Systems,
Industry, Tavistock, London. Westview, Boulder, CO.
Hobday, M. (2000) The project-based organisation: an ideal Teece, D.J. (1986) Profiting from technological innovation
form for managing complex products and systems? Research implications for integration, collaboration, licensing and
Policy, 29, 871 893. public policy. Research Policy, 15(6), 285305.
Hobday, M., Rush, H. and Tidd, J. (2000) Innovation in complex Van de Ven, A. (1986) Central problems in the management of
products and systems. Research Policy, 29, 793804. innovation. Management Science, 32(5), 570607.
Hughes, T. (1983) Networks of Power Electrification in Western Von Hippel, E. (1986) Lead users: a source of novel product
Society 18801930, John Hopkins University Press, concepts. Management Science, 32(7), 791805.
Baltimore, MD. Von Hippel, E. (1988) The Sources of Innovation, Oxford
Hughes, T.P. (1998) Rescuing Prometheus, Pantheon, New York, University Press, London.
NY. Von Hippel, E. (1989) New product ideas from lead users.
Koskela, L. and Vrijhoef, R. (2001) Is the current theory of con- Research Management, 32(3), 2427.
struction a hindrance to innovation? Building Research & Vrijhoef, R. and Koskela, L. (2000) The four roles of supply
Information, 29(3), 197 207. chain management in construction. European Journal of
Latour, B. and Woolgar, S. (1979) Laboratory Life: The Con- Purchasing and Supply Management, 6, 169178.
struction of Scientific Facts, Sage, London. Walker, A. and Newcombe, R. (2000) The positive uses of power
Law, J. (1986) On methods of long distance control: vessels, navi- on a major construction project. Construction Management
gation and the Portuguese route to India, in J. Law (ed.): and Economics, 18, 37 44.
Power, Action and Belief: A New Sociology of Knowledge, Winch, G. (1998) Zephyrs of creative destruction: understanding
Routledge & Kegan Paul, London, pp. 234 263. the management of innovation in construction. Building
Law, J. (1994) Organising Modernity, Blackwell, Oxford. Research & Information, 26(4), 268 279.

522

You might also like