MANPOWER ALLOCATION ( SHINBO )

Date: 6-Dec-14
Foreman

WORK
BLDG Floor ZONE Work Description % Assesment
Incharge Engineer Supervisor Foreman Leadman Elect. Helper Sub Total
SHINBO HDEC KEO
A & B TERM Sammy Termination of EML module 1 1 2
Grd
A & B EUDR EUDR works @ PG-3001 and 3018 finished 1 4 1 6
Marvin
1 A&B C Pipe conduit installation works for EML and cable looping 4 2 6
2 A & B EUDR Sammy EUDR works @P2- 0005, 2003 & 5004 4 3 7
3 A&B CT Mone GI conduit, rod channel and trunking installation works 1 6 2 9
3M 0
A & B EUDR EUDR works @ P4- 2047 finished 1 2 1 4
4 Sammy
A&B L Continuation of support for FL6 lighting Al 1 1 2 48
PMR
5 0
A&B CA Sammy Cable pulling for normal and essential lighting and LCP rmeote 4 2 6
6
A & B EUDR Marvin EUDR works @P6- 2042 1 1 2
7 A&B C Sammy Dismantling of existing conduit pipe flor lights and ceiling rose 1 1 2
8 0
9 A&B CA Mone Installation of cable tray and rod channel 1 1 2
Rooftop 0
PMR Sub Total 1 0 3 0 29 16 48
4 0
5 0
A & B EUDR Benjamin EUDR works @ A6- corridor 1 6 4 11
6 A & B EUDR Sonny EUDR works @6th floor 1 6 4 11
A&B T Trunking covering, sealant and circualr covering works 4 2 6
7 A & B CA Edgar Cable pulling, pipe clip fixing and support works GERALD JOEMARI 4 4 8 53
AH TOWER
8 A&B C Reroute pipe with plenum box location 1 1 1 3
9 0
10 A&B CA Edgar Cable pulling, rod support fixing, ceiling rose and light fixture fixing 10 4 14
EPS 0
Mechanical 0
AH Tower Sub Total 1 1 3 0 31 19 53
A & B EUDR Arnel EUDR works @ AG- 3015 and 3016 1 1 14 1 17
Grd A&B L Randulph Lighting fixing fixture works @GF 2 2 4
A & B CT Conduit and trunking installation works @3F and 3M 2 1 4
Mario 1
A&B C Conduit pipe installation woks 2 1 3
1
A&B C Abdul Conduit and power box installation works @A1- 1000 1 4 1 6
2 A&B C Randulph Conduit installation works and wire pulling works WASEEM ALVIN 1 3 2 6 63
AH PODIUM 3 A&B L Joynal Small power and cable looping works @A3- 2008 2 1 3
3M 0
A&B CA Joynal Cable pulling and looping and dressing @ 3F 1 1 1 3
EPS
A&B CA Vertical trunking for LTG and small cable dressing @GF, 2F and 3F 1 1 5 4 11
Toto
Mechanical A&B T Fabricate and assembly of tray fittings @3F 4 2 6
AH Podium Sub Total 1 6 2 39 16 63
A&B T Shamshad Trunking covering works @W4- 3029 3030 and 3032 3 2 5
A & B EUDR Jonas EUDR works @ W4 finished 5 6 11
4
A & B TERM Abu Sattar Termination works on-going 3 0 3
A&B T Ronaldo Aluminum trunking works finshed @nurse station 1 1 2
5 0
6 0
A&B C Shamshad Conduit rectification and spur box installation works 1 2 1 4
7
A&B L Ronaldo Fixing ofjunction box, riod channel and rectifying cables done 2 1 3
A&B L Jonas CDIB light support making and balance ceiling rose fixing finished 1 2 0 3
SHANIJ RAMESH 88
WH TOWER 8 A&B C Shamshad Light fixing fixture works @W7- 3017, 3018, 3019, 3020 and 3021 2 2 4
A&B L Abu Sattar Junction box fixing and lighting fixtures 2 2 4
9 0
A & B EUDR Jonas EUDR works @ W10-3000, 3001 and 1022 6 4 10
10 A&B L Rolando Lighting fixing fixture of flia lights, frames and gypsum board done 1 5 4 10
A&B L Lighting fixture fixing works@ W10 3 3 6
Abu Sattar
11 A&B L Lighting fixture fixing works@ W11 2 1 3
EPS A&B CT Conduit and trunking installation works @GF, 3M and 11F 6 2 9
Tuhin 1
Mechanical A&B T Trunking installation works @3F 8 3 11
WH Tower Sub Total 1 1 4 0 52 32 88
GRD A&B T Cable tray installation works for isolator panel 1 8 4 13
Padrique
A & B EUDR EUDR works @W1 9 8 17
1
A&B C Raihan GI conduit and support installation works 1 6 1 8
2 A & B EUDR Napoleon EUDR works @W2- 1035, 1034, 103 and, 1033 1 5 5 11
3 A&B C Habibur Small power conduit and support installation works WASEEM ALVIN 7 5 12 73
WH PODIUM
3M 0
A & B CA Habibur Cable pulling and cable dressing works @3F 1 2 2 5
EPS
A & B TERM Aner Wire termination of power panel and cable arranging works @2F 1 4 2 7
Mechanical 0
WH Podium Sub Total 1 5 0 41 27 73
PMR Energised Panel Look out 1 1
PMR EMDB Imran Energised Panel Look out 1 1
AH MDB Energised Panel Look out 1 1
AH EMDB Energised Panel Look out 0
SHAFEEK 5
SUBSTATION WH MDB Albin Energised Panel Look out 1 1
WH EMDB Energised Panel Look out 1 1
GEN RM. PMR 0
GEN RM. HOSP. 0
Substation Sub Total 1 0 0 2 0 3 5
W Fabrication Wire Arranging for used wires 2 1 3
Fabrication 23
Mr.Moon T Rakib Cable trunking installation works 1 10 9 20
Mr. Moon Group Sub Total 0 0 1 0 12 10 23
Zone-A T Hashem Main Trunking and Support Installation and Rectification works 7 4 12
Zone-B T Hashem Trunking Installation works @ LL Zone D 7 3 10
Zone-C T Hashem Main Trunking and Support Installation and Rectification works 1 7 4 11
Zone-D T Hashem Main Trunking and Support Installation and Rectification works 6 3 9
T Hashem Main Trunking and Support Installation and Rectification works JAMSHED 6 2 8 135
Zone-E
LL L Morshed Lighting fixture and threaded installation, wall chipping 1 19 4 24
C Shahin Conduit circular box cover installation & ceiling rose 1 20 3 24
Zone-F
C Tohidul Conduit installation of power box and add'l wire pulling for earthing 1 11 2 14
CA Biazon Cable glanding and termination 1 9 1 11
Zone-H
CT Ansari Cable tray and trunking insstallation works 1 4 7 12
MELCHOR &
Lower Level Sub Total 1 AJEER 6 0 96 33 135
Zone-5 C Excavation, wire pulling & piping @ Oval Park area 6 3 10
Jakir 1 18
LANDSCAPE Zone-3 C Chipping, piping and cable pulling 6 2 8
LANDSCAPE Sub Total 1 0 12 5 18
Main Route / T Mandal Cable tray and support installation 1 17 2 20
Gen. Rm. ROMMEL
Boiler Room 0
20
CEP AMCC Room 0
Basement 0
MEZZ / Floor 0
CEP Sub Total 1 2 1 0 17 2 20
Warehouse 3 2 5
Housekeeping(HDEC) 1 5 6
Office Material Assistant 1 0 1 18
Others
Safety Assistant 3 0 3
Ofiice Design Assistant 3 0 3
Sub-Contractor Sub Total 0 0 0 0 11 7 18
WH CD Anwar-Q.pec Cable Dressing, Wire Pulling and glanding works @1F and 3th floor 1 5 5 11
35
Subcontractor AH CA Anwar-Q.pec Wire Pulling works @1F, 9F and L.L UPS 1 12 11 24
Sub-Contractor Sub Total 0 0 2 0 17 16 35
Korean Managers 15 0
Office Staf 24 0
Office
Workers Late By Bus 0
Sub Total 39 0 0 0 0 0 0
ETC New Workers Today 0
EUDR 96 46 5 32 4 357 186 584
Total
630

Note: C= Conduiting, W= Wiring, T= Trunking, CT= Conduiting and Trunking, LPS= Lightning Protection System L = Lighting Fixture, Term = Termination T/C = Test & Commisioning CA= Cabling CD=Cable Dressing WD= Wiring Device