You are on page 1of 1

MUROS DE LADRILLO KING KONG DE ARCILLA

MURO LADRILLO KK C.A. 1:5, TIPO IV, P. TARRAJEO DE CABEZA

Rendimiento M2/DIA 6.45 P.U. (S/) 87.57

DESCRIPCION UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL TOTAL


MANO DE OBRA
CAPATAZ HH 0.10 0.124 23.06 2.86
OPERARIO HH 1.00 1.240 20.07 24.89
PEON HH 0.50 0.620 14.81 9.18 36.94

MATERIALES
ARENA GRUESA M3 0.064 42.29 2.72
AGUA M3 0.014 5.68 0.08
CEMENTO PORTLAND TIPO I - SOL BLS 0.454 17.97 8.15
CLAVOS C/C PROMEDIO P/CONSTRUCCION KG 0.022 2.89 0.06
LADRILLO ARCILLA KING KONG 18 HUECOS (TIPO IV) 9X12X24CM MLL 0.069 526.21 36.31
MADERA TORNILLO (LARGA) P2 0.403 5.46 2.20 49.53

EQUIPOS
HERRAMIENTAS MANUALES %MO 3.00 36.94 1.11 1.11

MURO LADRILLO KK C.A. 1:5, TIPO IV, P. TARRAJEO DE SOGA

Rendimiento M2/DIA 9.46 P.U. (S/) 53.69

DESCRIPCION UNIDAD CUADRILLA CANTIDAD PRECIO PARCIAL TOTAL


MANO DE OBRA
CAPATAZ HH 0.10 0.085 23.06 1.95
OPERARIO HH 1.00 0.846 20.07 16.97
PEON HH 0.50 0.423 14.81 6.26 25.18

MATERIALES
ARENA GRUESA M3 0.029 42.29 1.22
AGUA M3 0.014 5.68 0.08
CEMENTO PORTLAND TIPO I - SOL BLS 0.204 17.97 3.66
CLAVOS C/C PROMEDIO P/CONSTRUCCION KG 0.022 2.89 0.06
LADRILLO ARCILLA KING KONG 18 HUECOS (TIPO IV) 9X12X24CM MLL 0.039 526.21 20.52
MADERA TORNILLO (LARGA) P2 0.403 5.46 2.20 27.75

EQUIPOS
HERRAMIENTAS MANUALES %MO 3.00 25.18 0.76 0.76