LAST WEEK CURRENT WEEK Week 01 Week 02 Comments


Weekly Cutoff: 05-May-17 PLAN DATES FORECAST DATES QUANTITY / HOURS
SAT SU MO TU WE TH FR SA SU MO TU WE TH FR SA SU MO TU WE TH FR SA SU MO TU WE TH FR

Matl (Y/N)
Confirm
Plan

U.O.M.
P6 ACTIVITY ID / Work Duration
K011 - Steam Boiler System Start Finish ManPower & Start Finish ACTUAL FORECAST 29-Apr 30-Apr 1-May 2-May 3-May 4-May 5-May 6-May 7-May 8-May 9-May 10-May 11-May 12-May 13-May 14-May 15-May 16-May 17-May 18-May 19-May 20-May 21-May 22-May 23-May 24-May 25-May 26-May
FluorCodes Days
Qty
WBS - Level 01

WBS - Level 02

WBS Label 03

C32510 Control Room Building Sat, 22Apr Thu, 18May Plan Sat, 06May Sun, 04Jun 26 600 hrs 940 hrs
ManPower 0 hrs 300 hrs 6 6 6 6 6
C32510 Rendering of Internal and External Walls M2 Y Sat, 22Apr Sat, 29Apr
Qty
Sat, 06May Wed, 10May 5
Cum: 31.0 Cum: 1.4
ManPower 0 hrs 60 hrs 3 3
C35300 Install Doors and Window EA N Thu, 04May Thu, 11May
Qty
Thu, 25May Sun, 04Jun 10
Cum: 4.0
ManPower 0 hrs 180 hrs 3 3 3 3 3 3
C21200 Fabricate Ceiling Steel Structures MT N Sat, 22Apr Sat, 29Apr
Qty
Mon, 15May Sat, 20May 6
Cum: 0.2
ManPower 0 hrs 200 hrs 4 4 4 4 4
C33400 Install Ceiling M2 N Thu, 04May Thu, 11May
Qty
Mon, 22May Sat, 27May 6
Cum: 18.0
ManPower 600 hrs 0 hrs
C36100 Floor Finish M2 N Thu, 11May Mon, 15May
Qty
Mon, 29May Tue, 30May 2
Cum: 18.1
ManPower 0 hrs 0 hrs
C36500 Painting and Finishing M2 N Mon, 15May Thu, 18May
Qty
Tue, 30May Wed, 31May 2
Cum: 126.5
ManPower 0 hrs 0 hrs
Qty
ManPower 0 hrs 0 hrs
Qty
ManPower 0 hrs 0 hrs
Qty
ManPower 0 hrs 200 hrs 20
Qty
C13000 Steam Boiler Hanger / Equipment Fri, 07Apr Sat, 06May Plan Fri, 28Apr Thu, 25May 24 240 hrs 610 hrs
Foundations ManPower 240 hrs 160 hrs 4 4 4 4 4 4 4 4 4 4
C01120 Break Existing Concrete Slab & Cart away Debris M3 Y Fri, 07Apr Fri, 21Apr
Qty
Fri, 28Apr Wed, 10May 10
Cum: 12.0 Cum: 0.0
ManPower 0 hrs 40 hrs 2 2
C03200 Excavation to Foundation Depth M3 Y Fri, 21Apr Fri, 21Apr
Qty
Thu, 11May Fri, 12May 2
Cum: 1.0
ManPower 0 hrs 60 hrs 6
C13001 Blinding (PCC) of Foundation M3 Y Sat, 22Apr Sat, 22Apr
Qty
Fri, 12May Fri, 12May 1
Cum: 50,000.0
ManPower 0 hrs 30 hrs 3
C12001 Delivery to Site of Reinforcement Bars MT N Sat, 22Apr Sat, 22Apr
Qty
Sat, 13May Sat, 13May 1
ManPower 0 hrs 150 hrs 3 3 3 3 3
C12001 Fabrication of Reinforcement Bars MT N Mon, 24Apr Wed, 26Apr
Qty
Mon, 15May Fri, 19May 4
ManPower 0 hrs 60 hrs 6
C13001 Casting of Foundation Base M3 N Wed, 26Apr Wed, 26Apr
Qty
Sat, 20May Sat, 20May 1
ManPower 0 hrs 40 hrs 2 2
C11200 Fixing of Formwork for Foundation Pedestal/Plinth M2 N Thu, 27Apr Fri, 05May
Qty
Mon, 22May Tue, 23May 2
ManPower 0 hrs 70 hrs 6 1
C13001 Casting of Foundation Plinth M3 N Sat, 06May Sat, 06May
Qty
Wed, 24May Thu, 25May 2
ManPower 0 hrs 0 hrs
Qty
ManPower 0 hrs 0 hrs
Qty

29Apr 30Apr 01May 02May 03May 04May 05May 06May 07May 08May 09May 10May 11May 12May 13May 14May 15May 16May 17May 18May 19May 20May 21May 22May 23May 24May 25May 26May

CODE ACTIVITY TOTAL SA SU MO TU WE TH FR SA SU MO TU WE TH FR SA SU MO TU WE TH FR SA SU MO TU WE TH FR


Manpower 0 0 0 0 0 0 6 6 6 6 6 0 0 0 0 0 0 0 0 0 0 0 0 0
C32510 CONTROL BUILDINGS M2
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty
Manpower 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
C13000 CONCRETE M3
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Manpower 0 0 0 0 0 0 0 0 0 20 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Qty 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

PLAN MANPOWER TOTAL Manpower 0 0 0 0 0 0 6 6 6 126 6 0 0 0 0 0 0 0 0 0 0 0 0 0

A5MI-4-K011-PMRE-003 Three (3) Week Look Ahead TEMPLATE Rev1 PROJECT CONTROLSCBG 18.5 MTPA EXPANSION PROJECT Date: 5/11/2017 at 8:18 AM Page: 1 of 1