DAILY ACTIVITY REPORT - SITE WORK

WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 22.MAY.16


: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : MONDAY

PERMIT NO : MANPOWER : 4

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Safety induction occurred together with 4 BV staff Induction delayed due to the late arrival of msian BV staff
2 Arrangements of helium leak equipments on steam turbine C3. Location sticker didnt arrived Stick on each spots will take atleast half a day, thus this
3 Work permit has been arranged with Mr Hamizi process has postponed to the next day.
4 Alternative sticker has arranged at night.
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 23.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : TUESDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Temporary location stiker has be stick on every location Took half day to finish it.
2 helium leak detector has been calibrated
3 Inspection has been started.
4 The location sticker not arrived yet
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 24.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : THUESDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Inspection for 3C has been continued Took almost half day


2 Location sticker has been replaced with new sticker
3
4
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 25.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : WEDNESDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Inspection for 3C has been continued Took almost half day


2
3
4
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 26.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : THURSDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Inspection for 3C finished in the half day Took almost half day
2 all the inspection equipments has been shifted to 2C the exhaust has water ejection due to the drainage stuckage.
3 permit to work has been arranged
4 the location stickers are been sticked on the 2c locaitons
5 preparation of location sticker for 1C. the inspection for 2C has been changed to 1C due to the weekly outage for 2C
eekly outage for 2C.
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 27.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : FRIDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 Location sticker for 1C has been fninshed.


2 The Helium leak detector has been calibrated.
3 The inspection started for 1C
4
5
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 28.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : SATURDAY

PERMIT NO : MANPOWER : 6

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 The inspection for 1C has been continued.


2 Instructed BV inspectors to start doing the report and slides for 3C so that can be done the presentation asap
3
4
5
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 29.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : SUNDAY

PERMIT NO : MANPOWER : 2

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS : 0800am - 2200pm

S/N TIME TODAY ACTIVITIES FINDING/OBSERVATION ACTION TAKEN REMARKS

1 The inspection for 1C succesfully done


2 All the machineries and equipments has been released from TNB Include BV's leak test detectors has been brought to Kapar.
3 Preparing the reports and slides for the next day presentation.
4
5
DAILY ACTIVITY REPORT - SITE WORK
WORK TITLE HELIUM LEAK TEST BLOCK 2&3 DATE 30.MAY.16
: :

LOCATION : TNB STESEN JANAELECTRIK SULTAN ISMAIL DAY : MONDAY

PERMIT NO : MANPOWER :

PREPARED BY : MOHAMED MAHBOOB KHAN BIN ABU HANIFA WORKING HOURS :

S/N TIME TODAY ACTIVITIES

Presentation day:
The inspection for 1C and 3C has been done succesfully according to the
client's QAQC requirements.
The inspections and the presentation were satisfied the clients exept there
are few matters that were suggested for further improvements such as
listed below:
1. The describtion for every place should be described in detail as in tag In reports.
2.For every particular places after inspection must call the forman if found any leaks.
3. There will be add on locations for the next units. Will be supervised by turbine forman.
4. The pictures in reports should be more clear iin the report.

CONCLUSION:
Over all I found the leak inspectors were really hard working and has
finished the jobs on time.

From my own point of view I suggest that the presentation should be


done by TSB engineers and if there is any questions should be forward to
the leak inspectors so that can be reduce the communication problems
during the presentations.