Professional Documents
Culture Documents
FOR
1.0 DEFINITIONS
In the contract the following expression shall, unless the context otherwise requires,
have the meanings thereby respectively assigned to them.
APPROVAL shall mean the written approval of the OWNER and of the statutory
authorities, wherever such authorities are specified by any codes or otherwise.
BIS means The Bureau of Indian Standards, the National Standards Body of India,
resolves to be the leader in all matters concerning Standardization, Certification and
Quality.
BoM Bill of Materials
CAPACITY UTILIZATION FACTOR or CUF shall mean the ratio of the annual output of
the PLANT versus installed annual PLANT capacity.
COMMISSIONING shall mean the satisfactory, continuous and uninterrupted
operation of the equipment/system as specified after all necessary initial tests,
checks and adjustments required at site for a period of at least 5 consecutive days to
the satisfaction of the OWNER.
CONTRACT shall mean Supply Work Order No. ______ dated ____________ , Service Work
Order No. _____ dated _______alongwith the agreement signed between OWNER and the
CONTRACTOR incorporating Terms & Conditions, specification & Schedule of work
after issuance of Letter of Award and other necessary documents.
CONTRACT PERIOD shall mean time from the date of issue of Letter of Award (LOA) up
to FINAL ACCEPTANCE and thereafter five year (05)period of Operation and
Maintenance Contract for the project after completion of FINAL ACCEPTANCE.
CONTRACT PRICE shall mean the price payable to the CONTRACTOR for Supply
Work Order No. ______ dated ____________ and Service Work Order No. _____ dated
_______under the contract for full and successful performance of its contractual
obligations.
DELIVERY OF EQUIPMENT means delivery in accordance with the terms of the
contract complete in all respect, after approval by the Project Manager/Site-in-Charge.
DETAILED DRAWINGS means the execution drawings, which will be furnished by
the Contractor for execution of the work that will form part of the contract.
FINAL ACCEPTANCE TEST means on commissioning of the Solar PV Grid
interactive System, the plant performance shall be observed on real live condition for a
This contract shall be applicable to both Supply Work Order No. ______ dated ____________
and Service Work Order No. _____ dated _______. Material to be sold by CONTRACTOR to
OWNER under Supply Work Order No. _____ dated _______ shall be provide by OWNER to
CONTRACTOR as free supply to execute services as covered under Service Work Order
No. _____ dated _______. Sales Tax Declaration forms E/C as the case may be for
interstate sales (transaction) or within the state of Maharashtra respectively shall be
issued for the supply portion.
3.1 The CONTRACTOR shall not, without the OWNERs prior written consent, disclose the
contract or any provision thereof or any specification, plan, drawing, pattern
therewith to any person other than person employed by the CONTRACTOR in
performance of the contract. Disclosure to any such employed person shall be made in
confidence and shall extend strictly for purpose of performance only.
3.2 The CONTRACTOR shall not, without OWNERs prior written consent, make use of
any document or information enumerated under this clause except for purpose of
performing the contract.
3.3 Any document other than the Contract itself, enumerated under this clause shall remain
the property of the OWNER.
5.1 All materials shall be of the best quality and workmanship capable of satisfactory
operation under the operating and climatic conditions as may be specified. Unless
otherwise specified, they shall conform in all respect to the latest edition of the relevant
Bureau of Indian Standard (BIS) specification wherever Indian specifications apply or
British Standard (BS) or internationally accepted standard.
5.2 The CONTRACTOR shall supply & deliver all equipment and materials for installation at
site. The CONTRACTOR shall arrange for transportation, loading & unloading and safe
storage of materials at project site at his own cost & risk.
5.3 If the CONTRACTOR shall offer equipment manufactured in accordance with
other international well recognized standards, he shall, in that case, supply a copy in
English of the Standard Specification adopted and shall clearly mention in what
respect such standard specification differs from Indian Standard Specifications. The
Plant, equipment, and materials offered by the CONTRACTOR should comply with
one consistent set of Standards only as far as possible.
6.0 INTER-CHANGEABILITY
All the parts shall be made accurately to Standard gauges so as to facilitate replacement
and repairs. All corresponding parts of similar apparatus shall be inter-changeable.
7.1 The CONTRACTOR shall be responsible for securely protecting and packing the plant
&equipment as per prescribed standards in force to withstand the journey and ensuring
safety of materials and also arrival of materials at destination in original condition and
good for contemplated use. Packing case size & weight shall take into consideration the
remoteness of the goods final destination and absence of heavy material handling
facilities at all points in transit.
7.2 Packing lists of materials shall be provided in each package to facilitate checking up of
the contents at the destination.
7.3 In order to import any items, associated with the Solar PV Power Project, from abroad or
from any other state in India, CONTRACTOR shall have to arrange any clearance,
permission, if required at his own risk, from any Government controlled organization
for transportation of materials from manufacturing shop to delivery at site.
Necessary certificates if so required shall be issued by the OWNER within reasonable
time after getting written request from the CONTRACTORalong with the necessary
documents substantiating necessity of such approvals.
7.4 All packing material is the property of CME and shall be immediately deposited by the
CONTRACTOR to CMEs Store at project site.
8.5 In any case if the contractor deviates from the design or specification as defined in the
tender document, the contractor has to submit the deviation sheet along with the offer.
Formats for the technical and commercial deviations are provided respectively.
9.0 NEGLIGENCE
9.1 If the CONTRACTOR shall neglect to manufacture or supply the plant and equipment
with due diligence and expeditiousness or shall refuse or neglect to comply with
any reasonable order given to him in writing by the Project Manager / Site-in-Charge or
shall contravene any provisions of the contract, the OWNER may give seven days
notice in writing to the CONTRACTOR, to make good the failure, neglect or
contravention complained of and, If the CONTRACTOR shall fail to comply with the
notice within reasonable time from the date of serving thereof, in the event of failure,
neglect or contravention capable of being made good within that time, then in such
case, if the OWNER shall think fit, it shall be lawful for him to take the manufacture or
supply of plant wholly or in part, out of the CONTRACTORs hand and give it to another
person on contract at a reasonable price and the OWNER shall be entitled to retain any
balance which may be otherwise due on the contract by him to the CONTRACTOR or
10.1 The CONTRACTOR shall comply with all applicable laws or ordinances, codes,
approved standards, rules, and regulations and shall procure all necessary Municipal,
Panchayat and Government permits & licenses etc. at his own cost.
10.2 The CONTRACTOR shall leave the OWNER and the PROJECT MANAGER/SITE-IN-
CHARGE harmless as a result of any infractions thereof. If required, the CONTRACTOR
shall renew the above permits & licenses in case such situation warrants at his own cost.
11.2 If the CONTRACTOR being an individual or if a firm, any partner thereof shall at any
time, be adjudged insolvent or shall have a receiving order or order from
administration of his estate made against him or shall take any proceeding for
composition under any Insolvency Act for the time being in force or make any
conveyance or assignment with his creditors or suspend payment or if the firm be
dissolved under Partnership Act, or
12.2 If the CONTRACTOR fails to deliver or execute any or all of the goods within the
time period(s) under the contract or any extension thereof granted by the OWNER
pursuant to the clause for Delay in Execution or Failure to Supply or If the CONTRACTOR
fails to perform any other obligations(s) under the contract.
13.1 In case of non-performance in any form or change of the covenant and conditions of the
Contract by the CONTRACTOR, CME shall have the power to annul, rescind, cancel or
terminate the order and upon its notifying in writing to the CONTRACTOR that it has so
done, this contract shall absolutely determine. The decision of CME in this regard shall
be final and binding.
13.2 The OWNER may cancel the order or a portion thereof and if so purchase or authorize
purchase of the plant/equipment not so delivered or order plant/equipment of
similar description (opinion of the OWNER shall be final) at the risk and cost of the
CONTRACTOR.
14.2 The term Force Majeure shall have herein mean riots (other than among the
CONTRACTORs employee), Civil commotion, War (whether declared or not), invasion, act
of foreign enemies hostilities, civil war, rebellion, revolution, insurrection, military
coup, damage from aircraft, nuclear fission, embargoes, quarantines, acts of god such
as earthquake (above 7.0 magnitude on Richter scales), lightning, unprecedented floods,
fires not caused by CONTRACTORs negligence and other causes which the
CONTRACTOR has no control and accepted as such by the Project Manager/Site-in-
Charge whose decision shall be final and binding. Normal rainy season and monsoons are
not Force Majeure.
14.3 Upon occurrence of such causes and upon its termination, the party alleging that it has
been rendered unable as aforesaid thereby shall notify the other party in writing by
registered notice within 24 (twenty four) hours of the alleged beginning and ending
thereof giving full particulars and satisfactory evidence in support of its claim.
14.4 Time for performance of the relative obligation suspended by the force majeure shall
stand extended by the period for which such clause lasts.
14.5 If works are suspended by Force Majeure conditions lasting for more than two months,
the OWNER shall have the option of cancelling this contract in whole or part thereof, at
its discretion.
14.6 The CONTRACTOR shall not claim any compensation for ,Force Majeure conditions and
shall take appropriate steps to insure men and materials utilized by him under the
contract well in advance
The CONTRACTOR shall provide guarantee and be entirely responsible for the execution
of the contract in accordance with the specification, schedules, and annexure. He shall
further provide guarantee and be responsible for the quality and workmanship of all
materials and completed works, correct designs and drawings, correct delivery of
material, erection, testing and commissioning including operation & maintenance.
CME shall have the right to make any change in the design, which may be necessary in
23.0 MANUALS
The CONTRACTOR shall supply all necessary erection and commissioning manuals,
O&M manuals etc. as and when required. Six sets of test results, manuals etc. shall
be submitted by the CONTRACTOR on completion of the work.
26.0 ASSIGNMENTS
The CONTRACTOR shall not assign in whole or in part, its obligations to perform under
the contract except with the OWNERs prior written consent.
The CONTRACTOR shall notify the OWNER in writing of all sub contracts awarded
under the contract if not already specified in his offer. Such notification in his original
offer or later shall not relieve the CONTRACTOR from any liability or obligation under
the contract
In case, the CONTRACTOR engages any Sub-CONTRACTOR to carry out a part of the
work, the Sub-CONTRACTOR should have requisite Government License for carrying
out such part of the work.
29.0 INSPECTION & TESTING
29.4 For all tests to be carried out, whether in the premises of the CONTRACTOR or any Sub-
CONTRACTOR, the CONTRACTOR, shall provide labour, materials, electricity, fuel, water,
stores, apparatus and instruments etc. free of charge as may reasonably be demanded to
carry out such tests of the plant in accordance with the contract. The CONTRACTOR shall
provide all facilities to the PROJECT MANAGER/SITE-IN-CHARGE or his authorized
representative to accomplish such testing.
29.5 The project manager / Site-in-charge or his authorized representative shall have the
right to carry out inward inspection of the items on delivery at site and if the items have
been found to be not in line with the approved specifications, shall have the liberty to
reject the same.
29.6 If CME desires, testing of any component(s) of the plant be carried out by an
independent agency. The inspection fee, if any, shall be paid by the OWNER. However,
the CONTRACTOR shall render all necessary help to CME whenever required free of
charge.
29.7 The CONTRACTOR has to provide the necessary testing reports to the owner as and
when required.
29.8 Neither the waiving of inspection nor acceptance after inspection by the OWNER shall,
in any way, absolve the CONTRACTOR of the responsibility of supplying the plant
and equipment strictly in accordance with specification and drawings etc.
The CONTRACTOR shall deliver the equipment of the plant and machineries in
In respect of all matters, which are left to the decision of the PROJECT
MANAGER/SITE-IN-CHARGE, including the granting or withholding certificates, the
PROJECT MANAGER/SITE-IN-CHARGE shall, if required to do so by the
CONTRACTOR, give in writing a final decision thereon. If the final decision is not
accepted by the CONTRACTOR the matter will, at the request of the CONTRACTOR
be referred to arbitration under the provision for arbitration hereinafter contained
but, subject to the right of reference to arbitration; such decision shall be final and
binding on the CONTRACTOR
35.0 ARBITRATION
Except where otherwise provided, if at any time, any question, dispute or difference,
whatever shall arise between the CONTRACTOR and the OWNER upon or in relation to
or in connection with this contract either of the parties may give to the other notice in
writing of the existence of such a question, on rejection of the matter, the dispute or
difference shall be referred to the sole arbitrator jointly appointed by CME and the
CONTRACTOR at the time of dispute after ascertaining the terms of reference mutually.
The Arbitrator will preferably be a member of Arbitration Council and arbitration
proceedings will take place as per provisions of Arbitration and Conciliation Act, 1996 or
any statutory modifications or re-enactment thereof, and the rules made there under and
for the time being in force shall apply.
The CONTRACTOR will ensure that the work under this contract shall continue
during arbitration proceedings and dispute and no payments due from or payment
by the OWNER shall be withheld on account of such proceedings except to the extent
which may be in dispute.
The CONTRACT shall be deemed to have been entered into at Mumbai, INDIA and all
causes of action in relation to the CONTRACT will thus be deemed to have been arisen
only within the jurisdiction of the Mumbai Courts.
38.0 NOTICES
For all purpose of the contract, including arbitration there under, the address of the
CONTRACTOR mentioned in the tender shall be the address to which all
communications addressed to the CONTRACTOR shall be sent, unless the
CONTRACTOR has notified a change by a separate letter containing no other
communication and sent by registered post with acknowledgement due to the Project
Manager. The CONTRACTOR shall be solely responsible for the consequence of an
omission to notify change of address in the manner aforesaid.
Any communication or notice on behalf of the OWNER in relation to the contract
agreement may be issued to the CONTRACTOR by Project Manager and all such
communication and notice may be served on the CONTRACTOR either by registered post
or under certificate of posting or by ordinary post or by hand delivery at the option of
the officer.
Instructions or notices to the CONTRACTOR and notices from the CONTRACTOR to the
OWNER recorded in a minute signed by the authorized representatives of both
OWNER & CONTRACTOR. Such notice or instruction shall be valid notice of instruction
for the purpose of contract.
If the CONTRACTOR fails, on receipt of the order, to take up the work within a
reasonable period or leave the work site after partial execution of the work CME shall
have the liberty to get the work done through other agency at his own risk and additional
cost if any. If the situation, so warrants, to compel CME to cancel the order placed on the
CONTRACTOR, he shall be liable to compensate the loss or damage, which CME
may sustain due to reasons of failure on his part to execute the work in time.
The rate(s) quoted against the work shall remain firm during the entire contract period.
42.0 SAMPLES
The CONTRACTOR shall not carry out important operation without the consent in
writing of the PROJECT MANAGER or his representative. For carrying out such important
activity, the CONTRACTOR shall intimate to CME at least 72 hours before starting of
the job.
The CONTRACTOR shall be responsible to provide all wages and allied benefits to
his labours engaged for execution of the project work and also to carry out
Operation &Maintenance service. The CONTRACTOR shall remain liable to the
authorities concerned for compliance of the respective existing rules and regulations of
the government for this purpose and shall remain liable for any contravention thereof.
The General and Special Conditions of Contract are complementary to each other and
where they are in conflict, the special condition shall prevail.
46.0 INSURANCE
46.1 HASPL shall bear the responsibility to arrange for project insurance encompassing all the
probable risks associated with the proposed Solar Power Project including warranty of
solar PV modules.
46.2 Erection all Risks Policy should be taken by the CONTRACTOR till the time the entire
erection and completion of WORK including issue of FINAL ACCEPTANCE CERTIFICATE
by the OWNER.
46.3 The goods supplied under the contract shall be fully insured as long as the
plantcontinues to remain under the custody of the CONTRACTOR against the loss or
damageincidental to manufacture or acquisition, transportation, storage and delivery in
such a manner that CME shall not incur any financial loss. The CONTRACTOR may ensure
adequate insurance of Solar PV systems against robbery, theft and acts of God such as
natural calamities, flood etc. till Final ACCEPTANCE CERTIFICATE by OWNER.
46.4 In case of any loss or damage or pilferage or theft or fire accident or combination of the
said incidents etc. under the coverage of insurance, the CONTRACTOR shall lodge the
claim as per rules of insurance. Any FIR required to be lodged to local Police Station
shall be the responsibility of CONTRACTOR.
46.5 The CONTRACTOR shall arrange to supply/rectify/recover the materials even if the
claim is unsettled for timely completion of the project. The final financial settlement
with the insurance company shall be rested upon the CONTRACTOR.
46.6 In case of any delay of the project attributable to the CONTRACTOR, the CONTRACTOR
himself in consultation with CME should take the extension of insurance. Any financial
implications shall, however, be borne by the CONTRACTOR.
46.7 The CONTRACTOR should arrange for providing insurance coverage to his workmen
under Workmens Compensation Act or similar Rules and Acts as applicable during
execution of work for covering risk against any mishap to his workmen.
CONTRACTOR shall also undertake a Third Party Insurance. CME will not be
responsible for any such loss or mishap.
46.8 Fire insurance is to be arranged by the CONTRACTOR up to issue of Final Acceptance
Certificate.
46.9 Arranging insurance shall be in the scope of the HASPL upto Final acceptance. After final
acceptance the insurance of the plant shall be in CME's scope.
47.3 CONTRACTOR should ensure the continuous running of Power Plant without any
interruption within the contractual period of operation & maintenance of the power plant.
All repairing & replacement works are to be completed by the CONTRACTOR within
24 hours from the time of occurrence of fault or defect. If it is not possible to set right
the equipment within this time, the CONTRACTOR shall notify the OWNER indicating
nature of fault & cause of damage etc. within 12 hours from the time of occurrence of the
fault and expected time for rectification of the same.
Sr. Reference
Stage
No. From D (Days)
3. Completion Time period (Final Acceptance) 250 Days from Zero date
4. Water consumption per annum 125 M3p.a for all 5 years of O&M
period
5. Auxiliary Power consumption per Annum 20,500 kWh p.a. for all 5 years of
O&M period
50.0 WARRANTY
50.1 The CONTRACTOR must ensure that the goods supplied under the contract are new,
unused and of most recent or current models and incorporate all recent improvements in
design and materials unless provided otherwise in the contract.
50.2 THE WARRANTYs SHALL BE AS FOLLOWS:
50.3 During the period of Warranty / Guarantee the CONTRACTOR shall remain liable to
replace any defective parts that become defective in the plant, under the conditions
provided for by the contract and arising solely from faulty design, materials or
workmanship, provided such defective parts are not repairable at site. After
replacement the defective parts shall be returned to the CONTRACTORs works at the
expense of the CONTRACTOR unless otherwise arranged.
50.4 If any defects not remedied within a reasonable time, the OWNER may proceed to do
work at the CONTRACTORs risk and cost, but without prejudice to other rights, which
the OWNER may have against the CONTRACTOR in respect of such defects.
50.5 At the end of guarantee period, the CONTRACTORs liability shall cease. In respect of
goods not covered by the clause No 40.0, the OWNER shall be entitled to the benefit
of such guarantee given to the CONTRACTOR by the original CONTRACTOR or
manufacturer of such goods.
50.6 During the operation & maintenance and guarantee period, the CONTRACTOR shall
be responsible for any defects in the work due to faulty workmanship/ improper
preventive maintenance or due to use of substandard materials in the work. Any defects
in the work during the guarantee period shall therefore, be rectified by the CONTRACTOR
without any extra cost to CME within a reasonable time as may be considered from the
date of receipt of such intimation from CME failing which CME shall take up
rectification work at the risk and cost of the CONTRACTOR.
The test to prove the Performance Guarantee shall be conducted at site by the
contractor in presence of Owners representative. This test shall be binding on both
the parties of the Contract to determine compliance of the equipment with functional
guarantee. Any special equipment, instrumentation tools and tackles required for
successful completion of the Performance Guarantee Test shall be provided by the
Contractor free of cost. The accuracy class of the instrumentation shall be as per the
relevant clause of the documents.
Generation loss due to grid outage (or power evacuation system which is not in the
scope of the CONTRACTOR): the measured global solar radiation of the period of the
outage of the power evacuation system shall be excluded to calculate average global
solar radiation for the period of the PG test.
51.2 Actual Performance ratio
The ACTUAL PERFORMANCE RATIO (APR) shall be equal to or more than the
Minimum Guaranteed Performance ratio of 75%. The Performance Ratio Test should be
conducted within 15 days of successful commissioning of the plant. PLANT having
performance ratio below 75 % shall not be accepted by CME. In such case, the
CONTRACTOR at its own cost should Make Good the PLANT so as to be capable to
meet the Minimum Guaranteed Performance ratio. This shall be verified by again
carrying out the PR test, within a reasonable period of time. In case, the CONTRACTOR
fails to achieve the minimum 75% PR ratio even in the repeated PR test, then without
prejudice to any other right or remedy available CME shall be entitled to forfeit the
Security Deposit and Performance Guarantee and terminate the CONTRACT and the
a) If the Contractor is not able to demonstrate Guaranteed Performance Ratio during the
three months he will be given one or more chance to demonstrate the PG test. In that
case the steps for PG test shall be repeated again as above.
b) Performance Ratio will be considered while taking over the plant from the contractor
which should be minimum of 75%.
c) During the O&M period, at the end of every year starting from first year Value of C.U.F
(Co-efficient of utilization factor) shall be demonstrated by CONTRACTOR, which shall
be not less than value as specified in Annexure-A every year throughout O&M period.
d) Thecapacity factor of a PV power plant (usually expressed as a percentage) is the ratio
of the actual output over a period of one year and its output if it had operated at
nominal power the entire year, as described by the formula:
If the CONTRACTOR is found responsible for any delay in completion of the work, formal
time extension shall be granted by CME but reserving its right to recover a sum
towards Mutually Agreed damages, for late completion as per Mutually Agreed Damages
as mentioned below in Mutually Agreed Damages.
If the CONTRACTOR fails to deliver the plant or fails to start the work within specified
time frame after signing of contract agreement or leave the work site after partial
execution of the work, CME shall have the right to get the work done through any
other agency at the risk and cost of the CONTRACTOR. Further to this, CME may,
without prejudice to the right of the OWNER to recover damages for breach of trust of
the contract, may impose penalties.
In case the CONTRACTOR fails to achieve FINAL ACCEPTANCE of the plant by the
due date indicated in Time of Completion, then the OWNER shall levy the Mutually
For Auxiliary power consumption more than the value as per Guaranteed Parameters
of this document, the CONTRACTOR shall pay Mutually Agreed damages (MAD)
equivalent to the additional consumption of units @ Power Penalty rate per Kwh.
The auxiliary power consumption shall be verified at the end of each year of O&M.
d) Annual Water consumption more than guaranteed.
For water consumption more than the value as per the Guaranteed Parameters of this
document, the CONTRACTOR shall pay Mutually Agreed damages (MAD) equivalent to
the additional consumption of units @ 70 Rs per unit(M3).
The water consumption shall be verified at the end of each year of O&M.
The Mutually Agreed Damages shall be recovered from any amount payable to the
CONTRACTOR including the balance payments and / or Security Deposit cum
Performance Bank Guarantee. In case of deduction from the Performance Bank
Guarantee, the CONTRACTOR shall immediately replenish the Bank Guarantee to the
value equivalent to 10% of the Total Contract Value.
b) All payment shall be made on the basis of actual measurement for the quantified items
as per schedule of works.
c) The CONTRACTOR shall submit the bill / invoice for the work executed showing
separately CST, VAT, Service Taxes and any other statutory levies in the bill / invoice.
54.2 The payment will be made to the CONTRACTOR on award of the contract as follows:
The O&M charges for the respective year shall be paid at the end of every year after
evaluating the CUF.
56.0 MANUALS
The CONTRACTOR shall supply all necessary erection and commissioning manuals,
O&M manuals etc. as and when required. Three sets of test results, manuals etc.
shall be submitted by the CONTRACTOR on completion of the work.
57.0 PROGRAMME OF WORK
The contractor shall submit the programme of work including a Bar Chart indicating
there in the starting position and completion date of each of the major items of work.
The work shall be taken over by CME upon successful completion of all tasks to be
performed at site(s) on equipment supplied, installed, erected & commissioned by the
CONTRACTOR in accordance with provision of Tender. During handing over complete
project work, i.e. after FINAL ACCEPTANCE, the CONTRACTOR shall submit the following
for considering final payment.
(a) All as- Built Drawings
Immediately after taking over of complete project(s), the same will be handed over to the
CONTRACTOR for operation & maintenance period.
A 22kV breaker to be installed by contractor with necessary metering & protections &
shall be coupled with the receiving station indoor breaker panel. Extension of existing
22 kV switchgear at CME receiving station & related activities is in scope of contractor.
The distance between solar plant & the 22kV CME receiving station is approximately
One (1) kilo meter. In addition to that one breaker panel is proposed on the transformer
22kV side.
All equipment and instruments, indoor and outdoor, shall be marked with No. and
provided with danger boards before commissioning.The contractor shall touch up the
surface with paint of same shade for equipments, which are scratched and / or damaged
during transportation and erection before commissioning.
The contractor shall employ skilled and semi-skilled labourers for erection, testing
and commissioning as required. All the electricians, cable jointers, wiremen, welders
and others employed shall possess valid certificates / license recognised by competent
authorities. The contractor shall set up his own facilities at site at allocated place to
undertake fabrication jobs threading etc.
The Contractor shall carry out major civil engineering works as called for in scope of
work pertaining to electrical equipment's like foundation, plate inserts etc. as per the
latest relevant drawings as well as carry out minor civil works such as, but no limited to,
the grouting of base plates, channels, supports and foundation bolts, cutting holes in
walls and ceiling, chipping of floor and ceiling and making good the same after
installation of the equipment and any other minor civil works advised by CME for
completion of the work has to be carried out without any extra charges.
Power transformers, 22kV Switchgears, LT panel etc. shall be handled and erected as
per the relevant codes of practice and manufacturer's drawings and instruction manuals.
For power transformer, drying out and oil filling as required, after checking and
testing the contractor shall carry out the dielectric strength. If required, the contractor
shall carry out oil filtration before commissioning at no extra cost.
During erection, care is to be taken to see that painting does not peel off at any place and
if so, it has to be given a 'Touch-up' after erection by the contract.
*****************
CONTENTS
2.0 DEFINITONS
2.1 Scope of Supply & Work includes all, design, engineering, manufacture, procurement &
supply ofequipment, and materials, testing at manufacturers works, inspection,
packing and forwarding, supply, unloading at site, associated civil works, services,
permits, installation and incidentals, insurance at all stages, erection, testing and
commissioning of 2.0 MWp Grid Connected Solar PV Power Plant with associated
equipments and materials on turnkey basis at CME, Khirkee, Pune and operation &
Maintenance for 5 years.
2.2 The offered Grid Connected Solar Power Plant should be able to generate power
through solar energyand supply clean and green electricity to the grid. CME may avail
carbon credits under clean development mechanism as per Regulations in force.
2.3 The equipment and materials for 2 MWp Grid Interactive Solar PV Power Plant with
associatedsystem (Typical) shall include but not be limited to the Supply, Erection,
Testing &Commissioning of the following:
(a) Solar PV modules, of suitable rating in each array.
(b) Solar PV modules in array totalling 2.0 MWp give details mentioned in the bid
including mounting frames, structures, array foundation and module inter
connection.
(c) Array Junction boxes, distribution boxes and Fuse boxes. MCBs, Surge Arrestors
(d) Power Conditioning Units (PCU) with SCADA.
(e) LT Interfacing Panel with bus bars, CT, PT, SFU and circuit breakers, Plant
Monitoring Desk.
(f) 415V bus duct between Transformer and Interface Panel with necessary
supporting arrangements.
(g) HT & LT Power and Control Cables including end terminations and other required
accessories for both AC & DC power. DC string cable shall be stranded copper
where as AC cable shall be stranded aluminium.
(h) 22kV Switchgear with CT, VCB, PT, Relays, Cable termination kits etc.
(i) One (1) Nos. 2500 kVA, 22/0.433 kV, Oil type, Off Circuit Tap Changer having 5
equal steps with voltage range 5% in steps of 2.5 %, Dyn11, percentage
(w) 22kV CME Receiving Station: Connection of 22kV output of breaker (near
Transformer) to 22kV switchgear at about 1Km distance in CME receiving station.
2.8 Obtaining statutory approvals / clearances from all relevant Government &non
government agencies for the plant.
2.9 The Contractor shall arrange deployment of manpower and required consumable
during commissioning.
2.10 Submission of following documents drawings data design and engineering information
to CME or its authorized representative for review and approval in three copies as per
clause(C) of COMPLETION TIME mentioned in contract document.
2.11 List of Drawings shall be submitted as below but not limited to the following.
ARRAY YARD
11* Model mounting structure GA, part drawings and BOM with fasteners
12* Drawing for AC, DC cable, communication cable trenches and wiring
13 Drawing for Array Junction Box
14* Drawing for Array Yard lighting
15 Array yard lightning protection
16 Drawing for Earthing system for Array yard Other drawing as may be required by
CME for clear understanding.
25 Drawing for lighting fixture Other drawing as may be required by CME for clear
understanding.
Miscellaneous drawings
26* Structural details of construction works includes foundation, tie beam, column,
lintel, chajja, roof beam with roof, and water storage tank with supporting
structure details, parapet, plinth protection.
27* Control Room internal illumination & concealed wiring layout
28 Line diagram, Block diagram & CKT diagram for Surveillance Camera Desk
29 Other drawing as may be required by CME for clear understanding
* These drawings are major drawings and should get approved as per clause( C ) of
COMPLETION TIME mentioned in contract document s.
i. These drawings shall show sufficient overall dimensions, clearances and space
requirements of all apparatus to be furnished, to enable the Owner to determine the
design and layout of the installation.
ii. Within 07 days of receipt of such drawings, the Owner shall convey his approval or
otherwise of the same, and in the event of disapproving the drawing, the Contractor shall
re-submit the revised drawings with proper revision number for approval after
making necessary modification / correction.
iii. No extension of time shall be allowed on account of the time consumed in submission
and examination of defective drawings and resubmission of the corrected drawings.
iv. Within a reasonable period from the date of receipt of approval, the Contractor shall
submit six sets of drawings to CME and these drawings (as mentioned above), thereafter
be deemed to be the Contract Drawings.
v. These drawings, when so signed, shall become the property of CME. No exclusion
from the drawings in any way will be allowed in execution except with written
permission of Site-in -charge of CME.
vi. The Contractor, if required by the Project Manager/Site-in-Charge shall supply additional
copies of any drawing without charging any extra cost, which may reasonably be
required for the purpose of the contract.
(k) 22kV Indoor feeder panels with CT, VCB, PT, : As per SLD & cl 3.31
Relays
(w) LED system Lighting arrangement for the plant : System to satisfy lux
safety level
xxiii. Identification and Traceability: Each PV module used in must use a RF identification
tag. The following information must be mentioned in the RFID used on each module.
This must be laminated inside the panel and it must be able to withstand harsh
environmental conditions.
(a) Name of the manufacturer of PV module
(b) Name of the manufacturer of Solar cells
(c) Month and year of the manufacturer (Separately for Solar cell and module) Country of
origin (Separately for Solar cell and module)
(d) I-V curve for the module
(e) Wattage, Im, Vm and FF for the module
(f) Unique Serial No and Model No of the module
(g) Date and year of obtaining IEC PV module qualification certificate
(h) Name of the test lab issuing IEC certificate
d. Metering
Following metering instrument shall be provided on the UPS :
a. HV side : Delta
b. LV side : Star
(ix) Off load tap changer : Having 5 equal steps (in step
of 2.5% of each to have
voltage variation of 5% on
HV side Also match the range
of requirement of HV voltage
viz-a-viz Inverter output
voltage.
e. Efficiency:
The percentage loading for the maximum efficiency shall be clearly stated at unity
power factor as well as 0.8 and 0.9. Pf.
f. Insulation:
(a) The dielectric strength of the winding, given insulation and the bushings shall conform to
the values given in IS: 2026 (Part. III)/1981 (or its latest amendment) for highest system
voltage of 22 kV, 1.1 kV and shall be suitable for the following impulse test\power
frequency test voltages.
i. 22kV 12 kV 75 kVp 35 kV
g. Temperature Rise:
Each transformer shall be capable of operating continuously at their normal rating
without exceeding temperature rise limits as specified below:
Type of Temp.rise External
cooling. cooling
medium (Air)
Winding( Temp. rise ONAN 50 degree C. When the oil
measured by resistance circulation is
method) natural non directed
Oil (Temp. rise As above. 45 degree C. -
measured by
thermometer
method)
The reference temperature conditions for which the transformers shall be
designed are as per the climatic conditions of the site as specified. The hottest spot
temperature shall not exceed 98degree C when calculated over an annual weighted
average ambient temperature of 35 degree C when transformer is loaded to its rated
MVA. The transformer shall be capable of being over loaded in accordance of IS: 6600/
1972. Bushing and its terminal connectors shall have minimum continuous current
rating corresponding to 120% rated current of transformer at lowest tap.
h. Impedances:
The percentage impedance at 75 deg. C shall be 7.15% for the sub- station
transformers subject to tolerance as per IS: 2026. The duration of short circuit with
reference to the impedance voltage shall also be in accordance with the latest IS: 2026.
i. Guarantees:
The Contractors are required to offer the transformers having no load losses and load
losses not exceeding the following values as per CBIP manual.
(a) No load loss at rated voltage, : 2600Watts
Rated current, rated frequency
(b) Load loss at rated current, rated : 25000 Watts
Voltage, rated freq. and 75 Deg.C.
j. Cooling :
(a) Transformer shall be provided with ONAN type cooling.
(b) The ONAN cooling of the transformers shall be by natural circulation of air while
the circulation of oil shall be effected by natural convection, the maximum oil flow being
assured by a method whereby the return flow of cooled oil is made to enter the
tank at alevel coinciding with the bottom of the hot columns of oil thus avoiding centre
heads of cold oil at the bottom of the tank. Out flow shall be arranged to coincide as
nearly as possible with the hot oil level at the top of the tank so that the total available
Radiator valves shall have clear & distinct OPEN/CLOSE indication embossed/ casted
as well as painted on the both sides of main body of valve.
x. Factory Assembly And Tests:
The transformer shall be completely assembled and tested at the Factory.
Routine and Acceptance tests as per specification are to be conducted and no deviation in
respect of conducting these tests will be acceptable. No extra charges for these tests will
be paid. Test charges shall be part of cost of the equipment. If purchaser selects to send
a representative, all tests shall be carried out in his presence. Type test certificate shall be
furnished before start of supply
y. Routine Tests:
Each completed transformer shall be subjected to following routine tests as per IS: 2026
Part. I & III (latest amendment). No extra charges for any of the tests shall be paid.
No deviation shall be acceptable. If the CONTRACTOR desires, he may not fix
radiators on transformers (other than the one which is to be type tested) during
routine testing. However in that case, radiator manufacturer's test certificate shall be
furnished for reference of inspecting officer with undertaking that CONTRACTORshall be
responsible for proper alignment/fixing of radiator on transformer at site.
1. Measurement of resistance of each winding.
2. Measurement of turns ratio between HV-LV windings at each tap.
3. Checking of polarity and phase relation-ships for each winding.
4. Measurement of no load loss and no load current.
5. Positive phase sequence impedance/short circuit impedance between HV-LV
windings on minimum, maximum and normal taps.
6. Separate source voltage withstand test.
7. BDV test on transformer oil.
8. Induced over voltage withstand test.
9. Measurement of neutral unbalance current.
10. Regulation at rated load at unity, 0.90 and 0.80 lagging power factor.
11. Load losses measured at rated frequency by applying voltage sufficient to
produce the ratedrelevant current in one winding with the other winding short
circuited.
12. Measurement of insulation resistance.
13. The total losses shall comprise of the No Load Losses, load losses at rated output
dulyconverted at 75 degree C average winding temperature and shall also be
indicated in thetest report. Load losses shall be that corresponding to rated load
(a) IEC-298 : A.C. Metal - enclosed and control gear for rated
voltages above 1KV and including 72.5KV
(b) IS-3427 : A.C. Metal - enclosed and control gear for rated
voltages above 1KV and including 52KV
(f) IS-5578 & 11353 : Making and arrangement for switchgear bus bar main
connections and auxiliary wiring.
a. Symmetrical : 40KA
VTs shall be provided with HRC type fuses on the secondary side. The VT fuses on
primary side shall also be provided with all safety precautions. One of the secondary
terminals of the VTs shall be solidly earthed. One number three phase voltage
transformer of this rated output will be required for each incoming indoor panel.
Voltage transformers should be mounted in the top part of the cubicle for ease of
replacement of fuses.
(f) Current Transformers :
(iii) Frequency : 50 Hz
a. Rated output : 10 VA 10 VA
However VA burden should not be less than
suitable for A.C. series trip requirement with
shunt trip arrangement
The core shall be of high grade non ageing laminated silicon steel of low hysterics loss
and high permeability to ensure high accuracy for both normal and fault current.
(g) The rating of secondary winding shall be 1 Amps. However, the current transformers
will have to satisfy the requirement of rated VA burden, class of accuracy, accuracy limit
factor and short time thermal rating as specified. Magnetization curves corresponding
to all secondary taps must be submitted with the tender.
The ratings of current transformers of all classes regarding ratio error, knee point
voltage, resistance of secondary winding etc. shall have to be co-ordinated with the
requirements of protective relays and protection scheme, without any extra cost.
(h) All the type test certificates are also needed to be furnished with tender.
(i) The tenderer shall also furnish along with the tender, complete general arrangement,
schematic and outline diagrams indicating the mounting arrangement and position of
current transformers, voltage transformer terminal blocks etc. Type of
currenttransformer and voltage transformer employed shall also be clearly stated.
3.32 Indicating and Integrating Meters/Instruments :
All indicating instruments shall be of switchboard type, back connected, suitable for
flush mounting and provided with dust and vermin proof cases for tropical use and
finished in suitable colour. All instruments shall have practical laboratory means for
adjustment of accuracy. The limits of errors for ammeters/voltmeters shall be those
permissible for class 0.5 instruments as per IS: 1248. The ammeters and voltmeters
shall be suitably scaled to indicate the current/voltage for all the rating of
current/voltage transformers. A phase selector switch with four/six position shall be
used to measure the current/voltage of each phase/line. The meters shall be located at
eye level to facilitate observation of readings correctly.
(b) For22kV Switchgear located in Existing CME 22kV Receiving Station for evacuation shall
have following as a minimum protection :
(i) IDMT + High set and Instantaneous O/C, S/C (50/51)
(ii) IDMT + High set and Instantaneous E/F protection (50N/51N)
(iii) Breaker failure protection (50BF)
(iv) Trip circuit supervision (74TC)
(v) Lockout (86)
The circuit breaker shall be fitted with shunt trip coil for operation on Numerical
relay with communication facility with standard open protocol / SCADA compatibility.
The coils should be rated for 110VAC operation on station battery.
Three phase protection relays shall be Numerical Over-current & Earth Fault
protection having 2 elements for over current and one for earth fault protection. The
setting for over-current shall be 50-200% (in step of 1%) for earth fault element from
5 to 80% (in step of 1%).
These relays shall be numerical / non directional with selectable curve from all standard
5 IDMT curves. The relay should be able to store a minimum of two previous fault
values including fault level and phase. The relay should be fully compatible to
(c) Numerical relay with necessary protections along with communication facility and
standard open protocol.
(d) Single phase 22kV current transformers of suitable ratio for metering and
protection. The class of accuracy shall be 0.5 S for metering and 5P15 for protection.
Rated burden (output) shall be 10 VA for each secondary winding. Instrument
security factor for metering core shall not exceed 5.
(e) 22000/110 Volts three phase voltage transformers of suitable burden and class of
accuracy 0.5. The transformer shall be star-star connected.
(f) Arrangement for reception of incoming and outgoing cable connection along with
cable termination and sealing kits of requisite size XLPE power cables.
(g) Set of three phase air insulated main electrolytic copper bus bars of 800 A
continuous current rating with PVC insulation or sleeves. STC rating 40 KA for 3
seconds
(h) Mechanical ON/OFF indicator.
(j) Auxiliary switch having minimum of 8 contacts 4 normally open and 4 normally
closed.
(k) 11000/110 Volts three phase voltage transformers of suitable burden and class of
accuracy 0.5. The transformer shall be star-star connected.
(m) Voltmeter phaseselector switch to indicate phase to phase and phase to neutral
voltage of all the three phases.
(n) KW/KWH meter, Power factor(PF) meter
(p) 240V, 80W AC single phase anti condensation heaters with thermostat (0-60 Deg.
C) and switch.
(q) Anti pumping contactor.
(s) Adaptor Box for Matching existing panel bus bar(if necessary)
(t) Loose Set of 3 phase Air insulated inter connection electrolytic copper bus bars, 800
Amps. Rating with PVC insulation with nuts and bolts supports etc. STC rating 40 KA
for 3 seconds.
(u) Test terminal blocks for metering and relays, 3 phase 4 wire.
3.40 Allequipments shall be complete in all respect. All fittings, accessories or apparatus
which may not have been mentioned above but which are usual/ necessary for the
equipments shall be included for each circuit breaker panel.
3.41 Temperature Rise :
The maximum temperature rise of various parts of the circuit breakers when tested
under rated conditions shall not exceed the specified values at a peak ambient
temperature of 50 deg. c. The breakers may be provided with silver plated contacts if
necessary to meet the requirement of IS: 13118 where higher temperature rise is
permitted with silver plating contacts. The quantity of silver facing shall be such that
after carrying out one tenth of the total number of operations specified for the
mechanical endurance test, there is still continuous layer of silver on the contacts.
The temperature rise of CTs and PTs shall also not exceed the permissible values as per
relevant Indian Standards when corrected for max. ambient temperature at site.
3.42 Inspection And Testing
Each equipment shall comply with and shall be subjected to all routine and
acceptance tests prescribed in the relevant Indian Standard Specification/IEC.
i. Test of 22kV Indoor Circuit Breaker :
a. Routine/Acceptance Tests:
The following acceptance and routine tests shall be got conducted in presence of
(f) IEC 60920 & 60921 : Ballast for Tubular Fluorescent Lamps
Equipment and material conforming to any other standard, which ensures equal or
better quality, may be accepted subject to approval of the Owner. In such case, copies of
the English version of the standards adopted shall have to be submitted along with the
bid.
The electrical installation shall meet the requirements of Indian Electricity Rules as
amended upto date and relevant IS Codes of Practice. In addition, other rules and
regulations applicable to the work shall be followed
3.44 Design Criteria
a. General
The illumination system shall provide lighting supply to all plant areas. In addition, it
shall also provide emergency lighting to selected areas during plant emergency
conditions, as described below.
The entire illumination system shall be installed in an adverse industrial environment.
Fixtures / Accessories in some areas shall be subject to vibration, dust, oil / water
vapours.
The design shall be such so to ensure the minimum lighting levels as specified for
different areas.
Led Fixtures and lamps shall be used
The lighting system shall comprise the following two (2) categories:
(a) Normal 230V AC Lighting System
(b) Emergency Lighting
The illumination system shall comprise of following sub-systems:
b. Normal A.C. Lighting
This shall be provided by A.C. lighting fixtures distributed throughout the plant.
These lights shall be ON as long as the station A.C. supply is available. A.C. lighting
fixtures shall be fed from respective area A.C. Lighting Panels, which in turn shall be
connected to Lighting Distribution Boards (LDB).
c. Emergency Lighting
This shall be provided by A.C. lighting fixtures in Switchgear and control room. These
lights fixtures shall be normally fed from respective Emergency Lighting Panels, which
in turn shall be connected to UPS ACDB.
d. General Technical Requirements:
The lighting system for outdoor and indoor areas of Solar Power Plant shall be designed
in such a way that uniform illumination is achieved. In outdoor yard only equipment are
to be illuminated and luminaries shall be aimed as far as possible towards
transformers.
e. Illumination Calculation
Standard Lumen method shall be adopted for interior and exterior lighting in order to
The lighting level shall take into account appropriate light output ratio of luminaires
coefficient of utilization maintenance factor (of 0.7 or less) to take into account
deterioration with time and dust deposition.
ii. Receptacles
a. Heavy duty metal clad, welding receptacles shall be provided at array yard. Welding
receptacles shall have IP 55 degree of protection.
b. The welding receptacle used in control room /switchgear room shall be wall mounted
type. It shall be interlocked such that
(a) Switch can be put ON only when the plug is fully engaged
(b) Plug can be taken out only when the switch is in OFF position.
(c) Cover can be opened only when the switch is in OFF position.
c. Two nos. 20A, 240V, AC 3 pin industrial type power receptacles with controlling
switches and loose matching plugs mounted in a weather proof and dust tight boxes
shall be supplied and installed at each of the platforms near access doors. The box shall
be fabricated of galvanized sheet steel having suitable hinged door properly gasketted
to make it dust proof.
d. The lighting fixtures and receptacles shall be fed such that loading of all the three
phases is balanced. The lamps on the same vertical line shall be fed from different
phases, so that failure of any one phase shall not cause total blackout on one side.
iii. Wiring Arrangement And Installation For Illumination Work
Wiring installation covers supply and wiring of all the conduits, junction boxes, wires,
accessories, cable identification tags/ferrules, hardware and consumables required to
complete the installation.All the cables and conduits shall be clamped in steel supports
fixed to the wall. Necessary dash fasteners shall be provided by the Contractor for this
purpose. The conduits shall be supported at 750 mm intervals. The wiring shall be
continuous without any loose joints. Whenever looping or connection is to be made on
wires, it shall be done within the junction box through suitable fixed terminal strips. For
longer run of conduits, pullout boxes shall be provided at an interval of 4 m. Separate
conduit shall be used for individual phases. All conduits shall be electrically continuous
and thoroughly grounded by drawing 12 SWG GI wire along the conduit.The maximum
conduit fill shall not exceed 60%. Suitable pull boxes shall be provided at convenient
locations. All aviation light fixture, conduits and junction boxes etc. shall be properly
earthed. Earth wire shall run inside along the entire length of conduit between the
(m) Output Luminous flux : > 24 lux and > 40% uniformity
(s) Energy Consumption Watt/ : < 1.2 W Per LED (Preference shall be given
Lamp to minimum Watts per LED)
(a) Main distribution board/ Lighting panels shall be wall/Column mounted. However, the
above provisions may be changed as per design requirement.
(b) The Lighting Distribution board shall be fed from UPS DB. The lighting distribution
boards shall consist of four pole MCB as incomer and required number of outgoing
feeders.The board shall be designed for the required short circuit level of 9 kA. All the
distribution boards shall be sheet steel metal clad, dust and vermin proof, cubicle type
with degree of protection conforming to IP-52. Outdoor panels shall be weather proof
type with IP-54 protection. The thickness of sheet steel enclosures shall be 2 mm
minimum for load bearing, 1.6 mm for other members and 3mm for gland plate.
(c) The equipment shall be housed inside a sheet steel cubicle with hinged front access
door and the board shall be complete with Aluminium busbar, of size not less than 25x6
(d) At least one 5/15A flush type receptacle shall be provided in each switchboard and so
located that only the plug projects outside.
(e) Switches shall have quick-make and quick-break mechanism operated by a suitable
external handle complete with position indicator
xi. Lighting Poles/Towers
(a) Street / roads light poles shall be swaged steel tubular pole complete with single /
double arm luminaire mounting type fixing brackets, weather-proof junction box and all
other accessories made from steel confirming to 18:2713 (Part III) 1980. The steel for
3.45 Tests
a. Shop Tests
All equipment shall be completely assembled, wired, adjusted and routine tested as per
relevant IEC Standards at manufacturer's works.
Tests on Lighting Distribution Boards / Panels shall include:
(b) IS:1554(Part II) : PVC insulated(heavy duty) electric cables for working
voltage from 3.3kv up to and including 22kV
(c) IS: 3961 : Recommended current ratings for cables.
(d) IS: 8130 : Conductors for insulated electric cables and flexible
cords
(g) IS: 3975 : Mild steel wires, strips and tapes for armouring cables
(h) IS: 5609 : Specification for low frequency wires and cables with
PVC insulation and PVC sheath
(k) IEC: 540 : The methods for insulations and sheath of electric
cables and cords(elastomeric and thermoplastic
compounds)
(p) IEC: 502 : Extruded solid dielectric insulated power cables for
rated voltages from 1kV upto 30kV.
(r) IEEE: 383 : Standard for type test for class IE electric cables, filled
splices and connection for nuclear power generation
station.
(i) BICC Hand Book For cables in fire regarding temperature index-chapter-6
(ii) Indian Electricity Rule.
Equipment and material conforming to any other standard, which ensures equal or
better quality, may be accepted subject to approval of the Owner.
The electrical installation shall meet the requirements of Indian Electricity Rules as
amended up to date and relevant IS Codes of Practice. In addition, other rules and
regulations applicable to the work shall be followed.
ii. Design Criteria
a. For L.V. Cable:
(a) The cable shall be used for connection of power and control circuits of the auxiliary
electrical systems.
Multi-pair twisted instrumentation cables shall be same as single pair shielded cable,
except that the area of cross section of the conductor shall be 1.0 Sq.mm.
Following additional features shall be applicable:
(i) Shielding: In addition to individual shielding of pair, overall shielding shall be provided.
Overall shield shall be Aluminium backed mylar tape helically applied with metallic side
down either side 25% overlap and 100% coverage. Shield thickness shall be 0.075mm. Drain
wire shall be similar to individual pair drain wire and shall be in continuous contact with the
Aluminium side of the overall shield.
(ii) Twist: Overall twist of all pair shall be as per manufacturer standard.
(iii) Pair-Identification: Pairs shall be identified by numbered melinex tape applied over
individual pair shield at interval not more than 250 mm. Conductor insulation shall be
black and white for each pair.
d. 650/1100v Grade Two Core Control Cable
(A) Construction
(i) Conductor: Each core shall be seven stranded annealed tinned copper conductor of
cross section 1.5mm2 generally complying to IS 8130.
(ii) Insulation: Each core shall be provided with extruded HR PVC insulation conforming
to IS 5831 Type 'C'. Insulation thickness shall be as per IS-1554 (I) Color of core
insulation shall be red and black.
A 2.5 meter straight section of each type of cable trays shall be simply supported
at the two ends. A uniformly distributed load of 100 Kg per meter will be applied along
the length of the tray. The maximum deflection at mid span shall not exceed 7 mm.
All the tests shall be carried out as per relevant standards
3.56 ERECTION, TESTING & COMMISSIONING
i. The installation shall be carried out by an electrical contractor holding a valid license
as required by the State Government Authorities.
ii. The contractor shall provide necessary drawings and documents required by
i. CME shall have free access to Contractors manufacturers works to inspect, expedite
and witness shop tests. Any materials or work found to be defective or which does not
meet the requirements of the specification will be rejected and shall be replaced at
Contractors cost. Owner reserves the right to carry out stage wise inspection of
fabrication and components. The Contractor shall furnish a detailed quality assurance
plan for CME review.
ii. The test & inspection shall be carried out at manufacturers work and at Sion site with
the Contractors obligation. The test and Inspection shall be done in accordance with
the relevant standards and the Manufacturer's standard before the delivery to site as
well as after the erection and commission at site. The Contractors shall give the list of
tests that they will carry out at site to show the performance of plant.
iii. A detailed 'QAP' for Manufacturing and Inspection shall be submitted by the Contractor
for Owner's approval. The data of each test and inspection shall be recorded and
2.1.2 Frequency 50 Hz
3.3 COLOUR FINISH SHADE AS PER IS: 5 Painting with epoxy based
3.4 BUSBAR MATERIAL Al alloy of E 91 E grade. for Main & aux bus bars
-
3.4.1 Bus bar insulation Fully Insulated
3.5.1 Material GS
3.8 CABLE ENTRY / BUS DUCT ENTRY (a) Interface panel: Top Bus duct Entry
: Bottom cable entry
4.9 Minimum no. of auxiliary contacts 4 NO, 4 NC spare for purchasers use
5.8 Minimum no. of auxiliary contacts 4 NO, 4 NC spare for purchasers use
6.8 Relays / series releases Overload / Earth fault /Short circuit with settable
settings
6.9 Under voltage release Yes/No No
6.10 Minimum no. of auxiliary contacts 2 NO, 2 NC spare for purchasers use
7.9 Minimum no. of auxiliary contacts 1 NO, 1 NC spare for purchasers use
1.0 GENERAL
1.1 Type, No ,length of each busduct Non-segregated Phase Bus duct. Length
as per site requirement (maximum
approx.. 10Mtr)
SR.NO. ITEM
1.0 TECHNICAL PARAMETERS
1.1 GENERAL
1.1.16 Efficiency at (100%) full load 96% minimum for Inverter and 96% minimum for
rectifier/charger for 0.7 lag to unity PF operation.
1.1.17 Sheet material type and thickness CRCA sheet steel & min.25 mm thick
3.0 BATTERIES
3.1 Type SMF Lead Acid
4.0 INVERTER
4.14 Accuracy 1%
7.3 Transfer time (m sec.) Zero in sync. Mode else 5msec. (max.)
9.4 Frequency 50 Hz
10.8 Main ups DB / UPS sub-DB Free standing, floor mounted / Wall mounted
11.3 Capacity Make & carry full load current of inverters at 0.8
PF lag.
11.4 Short time rating 150% of full load current for 2min.
(iii) Inner Sheath : Extruded FRLS PVC compound conforming to type ST2 of IS: 5831
for multicore cable.
(iv) Armour : Galvanised single round/ strip steel wire armour for twin and
multicore cables. Non-magnetic hard drawn aluminium single round
wire conforming to H4 grade for single core cables.
(v) Overall Sheath : Extruded FRLS PVC compound conforming to type ST2 of IS: 5831.
1.0 AC SIDE
1.3 Frequency
2.0 DC SIDE
2.1 PV power
2.7 Others
2.14 Weight
1.0 Service
2.0 Type
(a) HV side
(b) LV side
(a) HV winding kV
(b) LV winding kV
11.0 Duty
(a) Range %
(b) In steps of
(a) HV side
(b) LV side
(a) Height m
(b) Breadth m
(c) Length m
22.0 Painting
1.4 Class
(c) One minute power frequency withstand voltage for auxiliary circuits.
1.16 Total break time measured from the instant of trip circuit energisation :
(b) Whether the circuit breaker is trip free or fixed trip and whether it is
with lockout preventing closing.
(d) Current required at rated supply voltage to close the circuit breaker.
(i) Type
(ii) Material
(d) Life :
(i) Derating factor for specified 50 Deg.C ambient temp. & site condition
if any.
1.23 The manufacture should give the necessary information as regards the
overall dimensions of the circuit breakers and details necessary for the
design of the foundation. General information regarding maintenance should
also be given.
2.7 Frequency.
2.12 TYPE :
(i) Primary.
(ii) Secondary.
(iii) Make.
2.13 Whether Voltage Transformer is mounted on the top part of the Cubical.
3.6 Frequency.
4.0 RELAYS :
4.6 VA BURDEN.
4.8 Whether relay is able to store a minimum of two previous fault values
including fault level and phase.
4.11 Whether numerical relay is with communication facility and standard open
protocol / SCADA compatibility along with IED for purpose of SCADA.
4.16 Range of setting for over current and earth fault protection.
5.1.6 Size.
(a) CT circuits.
(b) PT circuits.
(a) AC circuits.
(iv) Neutral.
(v) Earth.
(b) DC circuits.
6.1 BUSHINGS :
(i) Total
(ii) Protected.
(i) Dry.
(ii) Wet.
(a) Make
(b) Wattage
(a) Make/Material
(a) Size.
(a) Size.
(a) Primary :
(iii) Material.
(b) Secondary :
(iii) Material.
(a) Make
(b) Type
(c) Size
(ii) to earth.
(a) Size
(b) Material
(a) Size
(b) Material
SR.NO. ITEM
1.6.1 Frames
1.6.2 Covers
1.6.3 Doors
1.12.1 Material
1.12.2 Size
2.1 Make
3.0 FUSES
3.1 Make
3.2 Type
4.1 Make
5.1 Make
5.2 Ratio
6.1 Make
7.0 VOLTMETER
7.1 Make
7.2 Type
8.0 AMMETER
8.1 Make
8.2 Type
9.1 Make
10.1 Make
SR.NO. ITEM
1.0 GENERAL
1.1 Manufacture
(a) Rectifier
(b) Inverter
6.3 No of Positions
8.0 PANELS
(a) Material
(b) Size