PROPOSED ERECTION OF A 7 -STOREY SINGLE USER LIGHT INDUSTRIAL CAR SERVIING WORKSHOP WITH BASEMENT CARPARK

AND ANCILLARY OFFICE AT 2 KUNG CHONG ROAD ( BUKIT MERAH)


Ong & Ong

DAILY SITE REPORT


Date 19/3/2014 WEDNESDAY
S/N Location Chainage Nature of works Time (Hrs) Weather
8-12AM Fine Drizzle Rain

1 Condition 1-6PM Fine Drizzle Rain

RE
1
READING INCLINOMETER TAKEN TWICE
RTO
2 ZONE 1 WEEKLY 0800-1800 2

Total
3

STRUCTURAL STEEL BRACKET


INSTALLATION FOR WALER SUPPORT 0800-1800
INSTALLATION TO SHEET PILES
3 ZONE 3

VISITOR AT SITE:

4 ZONE 4 SOIL DISPOSAL AT SOUTHWEST SIDE OF 0800-1800


THE BUILDING

SOIL DISPOSAL AT NORTHEAST SIDE OF


5 ZONE 1 THE BUILDING, INSTALLATION OF 0800-1800
WALERS AT NORTHSIDE AND SOUTH
SITE MEETING (IF
SIDE OF THE BUILDING
ANY)

HTC MANPOWER MACHINERY

Project Manager 1 WSHO 2 EXCAVATOR 9

Project Coordinator 1 ECO 1 GENERATOR 3

Site Manager 1 Safety Supervisor 1 ROLLER (10 TONS) 2

Project Engineer 2 Quantity Surveyor 1 SOIL DRILL MACHINE

Planning Engineer SPRO 1 VOLVO TRUCK 2

Architect Surveyor 1 TIPPER TRUCK 2

Consultant Tipper Truck Operator 2 AUTO GRADER 1

QECP Excavator Operator 8 TOTAL 19

Site Supervisor 2 Volvo Truck Operator 2

General Worker 14

TOTAL 40

Prepared by RTO Representative: ALFREDO JR. ARIOS CLARO Checked by RE Representative: KEN
(Name & signature) (Name & signature)
Remark: Photo attached (1 page)

17 AUGUST 2017
Photos taken on THURSDAY

2KCR 2KCR

STRUCTURAL STEEL BRACKET INSTALLATION FOR WALER


READING INCLINOMETER TAKEN TWICE WEEKLY
SUPPORT INSTALLATION TO SHEET PILES

2KCR 2KCR
SOIL DISPOSAL ATR NOTRHEAST SIDE OF THE BUILDING,
SOIL DISPOSAL AT SOUTHWEST SIDE OF THE BUILDING INSTALLATION OF WALERS AT NORTHSIDE AND SOUTH SIDE OF
THE BUILDING