Professional Documents
Culture Documents
ON
PRESTRESS GIRDER
18.30M SPAN
UNDER THE GUIDANCE OF
Sh. RAJESH KUMAR
PROF. T/I
BY
R.C.MANDAL, AXEN/C/SILAPATHAR
K.K.KUTTY, AXEN/C/PANVEL
H.K.DAS, ADEN/HQ/LUMDING
INTREGRATED COURSE NO-813
FROM-14.07.08 TO 26.09.08
! "" "
" # $
%&'
( ") * $
+
, $-$*$, " # ,
$
.
!
" " ! " # $
+
/
0 " +
" " # $
!
! "#
$%&'()*%+'$
*$ $
2'
* ( * 3*
Site snap
TMS-48.25MPA
Water cement ratio -0.38
Cement-473.68kg/cum
Water-180 kg/cum
Sand- 410.18kg/cum
Coarse Agg. -1311.55kg/cum
28 days cube strength 52.15 N/ sq mm
48.31 N/ sq mm
51.24 N/ sq mm
Reinforcement
Pile boring
Pile cape casting
Abutment and pier casting
Pedestal casting
Placing of bearing
Casting of PSC girder
Casting of girder
Bed for Erecting Staging
1. Bed for erecting pipe and jack for prop
concreting was done earlier.
2. Care was taken no settlement took place.
3. Horizontal bracing was provided.
4. Bottom girder shuttering was done.
Placing of Bearings
1. Bearing was placed truly horizontal
2. Bearing was fixed on specified surface with
adhesive material.
Placing reinforcement
! "
# $ % &
' (% & ) %
*
+ +, - % -& &
Placing of cable duct
. After completion of reinforcement cable duct
was fixed as per design profile.
2. 75mm dia hole have been kept for cable.
3. Care should be taken during concreting no
leakage took place.
4. PVC pipe of 60 mm dia was inserted in to the
ducts and moved to and fro to prevent
setting of slurry leaked in to the duct if any
during casting of girder.
5. Side shuttering was done.
Cable profile
Distance of cable from bottom of girder
Center 2m 4m 6m 8m End
1. 120 128.7 154.80 198.20 259.20 330
2. 120 141.10 204.50 310.30 458.10 630
3. 280 306.90 3876.70 522.40 711.10 930
4. 440 472.70 570.90 734.60 963.80 1230
5. 630 638.5 754.10 946.80 121.60 1530
6. 760 804.30 937.30 1159.00 1469.40 1830
Cable position
Cable position
Concreting of girder
Mixing
View of stressing
Grouting of cable
After one day of stressing the slip in cable was
measured and if found ok cable duct was
grouted with net cement slurry (1:1) with
grouting pump . Non shrinkage compound
(conbex 100) was mixed with cement slurry.
Cement used was fresh and sieve through 75
micron. Grouting carried out under pressure of 5
kg /sqcm maintained for 1minute. While injecting
the slurry from one end the density of slurry
coming out from other end should be same. In
similar way others cables were grouted.
- Elongation required =135.56mm
-Jack used multiple fressinet cable stretching
jack
Observation of Cable No 1 Girder No 1
( A1P1)
4 3* 2
% * /
#" #"/ 01 ',,
# ", .
. ' " "
' ,, .
. '#" #"
+ ", .
. ''" '"
" #,, .
. '+ +
#", .
. ' , ,
Contd
# ' + "
',,/ 01 ' , ,
'", .. ' # #
! +,, .
. '!" !"
, +", .
. +," ,"
",, .
. + ' '
# "", .
. +#" #"
' +, " , .
. +' '
3 + " 0'44+ 5 6
# + 07'8
, "07
Quality control was ensured as:
Sieve Analysis
5
% / ,,,,3
4 62 70
82 4 50
7 9 50
7 82 4 9$ 43
82 4
#, '' '' '' 9 '9
# , ' " ,# ,#9 '# ! 9
' + " ' ! , ! ,9 #, 9
'$ 8$
'211 % 8? ?=$
?4<
'%'0
7$ &%11 87 >' ?7$
=4< &?=4
(
>$ 2441 8%% '7& 2>$?4< @ 0
2$ '44 >2% ?4? ?$
&4<
=$ &>4 2= ?=2 '$
84<
%$ 87 0
Field Testing of Cement
(Quick assessing the quality of cement )
Date of manufacture
Because aging reduces the strength
Open the bags No lumps should be
present (Mean no setting)
Thrust your hand into the cement
There should be cool feeling (means no
heat of hydration no setting)
Pinch of cement between fingers-It
should give smooth feeling (means no
setting).
Contd.
Handful of cement thrown on water It
should float initially before finally
settling
Take 100 gm of cement, make stiff
paste, prepare cake with sharp edges,
put on glass plate and Immerse in water
Shape shouldnt be disturbed
It should set and attain strength.
Period of storage %age of strength
Fresh 100%
3 months 80%
6 months 70%
12 months 60%
24 months 50%
Site snap
Measurement of
elongation and
gauge pressure