CRONOGRAMA VALORIZADO

PROYECTO: MEJORAMIENTO, AMPLIACION DE LOS SERVICIOS DE AGUA POTABLE Y ALCANTARILLADO EN EL SECTOR DE LA CALLE BOLIVAR, DISTRITO DE SANTIAGO - ICA - ICA

CLIENTE: MUNICIPALIDAD DISTRITAL DE SANTIAGO FECHA: JULIO DEL 2017

LUGAR: ICA - ICA - SANTIAGO


MES 1
ITEM DESCRIPCIN UND. METRADO PRECIO S/. PARCIAL S/. COSTO TOTAL
SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4

01 AGUA POTABLE 59,026.14

01.01 OBRAS PROVISIONALES 4,050.00


01.01.01 CARTEL DE IDENTIFICACION DE OBRA GLB 1.00 1,200.00 1,200.00 S/.1,200.00 S/.1,200.00

01.01.02 ABASTECIMIENTO DE AGUA POTABLE CON CISTERNA GLB 1.00 1,850.00 1,850.00 S/.462.50 S/.462.50 S/.462.50 S/.462.50 S/.1,850.00
MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y HERRAMIENTAS EN OBRA DE
01.01.03 AGUA POTABLE GLB 1.00 1,000.00 1,000.00 S/.500.00 S/.500.00 S/.1,000.00

01.02 OBRAS PRELIMINARES 2,709.84

01.02.01 LIMPIEZA DE TERRENO MANUAL m 633.14 1.03 652.13 S/.652.13 S/.652.13

01.02.02 CINTA PLASTICA PARA SEALIZACION DE PELIGRO. m 1,266.28 0.71 899.06 S/.899.06 S/.899.06

01.02.03 TRAZO NIVELES Y REPLANTEO DE OBRA m 633.14 1.83 1,158.65 S/.1,158.65 S/.1,158.65

01.03 MOVIMIENTO DE TIERRAS 21,902.77

01.03.01 EXCAVACION MANUAL DE ZANJA EN TERRENO NORMAL m 633.14 12.59 7,971.23 S/.2,657.08 S/.2,657.08 S/.2,657.08 S/.7,971.23

01.03.02 REFINE Y NIVELACION DE FONDO PARA TUBERIAS DE AGUA POTABLE m 633.14 2.18 1,380.25 S/.460.08 S/.460.08 S/.460.08 S/.1,380.25

01.03.03 CAMA DE APOYO PARA TUBERIAS, INCLUIDO ARENA E=0.10M m 633.14 3.68 2,329.96 S/.776.65 S/.776.65 S/.776.65 S/.2,329.96

01.03.04 PROTECCION SOBRE TUBERIA E=0.20 M m 633.14 5.61 3,551.92 S/.1,183.97 S/.1,183.97 S/.1,183.97 S/.3,551.92

01.03.05 RELLENO Y COMPACTACION DE ZANJA PARA TUBERIA DE AGUA POTABLE m 633.14 9.27 5,869.21 S/.1,956.40 S/.1,956.40 S/.1,956.40 S/.5,869.21

01.03.06 ELIMINACION DE MATERIAL EXCEDENTE DE EXCAVACIONES m3 3.17 252.43 800.20 S/.800.20 S/.800.20
SUMINISTRO E INSTALACION DE TUBERIA PVC UF. PARA RED DE AGUA
01.04 POTABLE 14,793.35 S/.0.00

01.04.01 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP UF CLASE 10 63MM. m 275.85 22.18 6,118.35 S/.2,039.45 S/.2,039.45 S/.2,039.45 S/.6,118.35

01.04.02 SUMINISTRO E INSTALACION DE TUBERIA PVC SAP UF CLASE 10 90MM. m 357.29 24.28 8,675.00 S/.2,891.67 S/.2,891.67 S/.2,891.67 S/.8,675.00

01.05 PRUEBA HIDRAULICA PARA RED DE AGUA POTABLE 1,376.36 S/.0.00

01.05.01 DOBLE PRUEBA HIDRAULICA TUBERIA 63MM m 275.85 2.14 590.32 S/.295.16 S/.295.16 S/.590.32

01.05.02 DOBLE PRUEBA HUDRAULICA TUBERIA 90MM m 357.29 2.20 786.04 S/.393.02 S/.393.02 S/.786.04

01.06 SUMINISTRO E INSTALACION DE ACCESORIOS DE RED DE AGUA POTABLE 2,339.62 S/.0.00

01.06.01 REDUCCION PVC UF 90MM x 63MM und 4.00 36.69 146.76 S/.48.92 S/.48.92 S/.48.92 S/.146.76

01.06.02 CODO PVC UF 90MM X 90 und 2.00 34.67 69.34 S/.23.11 S/.23.11 S/.23.11 S/.69.34

01.06.03 CODO PVC UF 90MM X 22.5 und 1.00 44.86 44.86 S/.14.95 S/.14.95 S/.14.95 S/.44.86

01.06.04 TAPON PVC UF 63MM und 4.00 38.86 155.44 S/.51.81 S/.51.81 S/.51.81 S/.155.44

01.06.05 TAPON PVC UF 90MM und 1.00 20.86 20.86 S/.6.95 S/.6.95 S/.6.95 S/.20.86

01.06.06 VALVULA COMPUERTA BRIDADA 63MM. und 4.00 211.88 847.52 S/.282.51 S/.282.51 S/.282.51 S/.847.52

01.06.07 VALVULA COMPUERTA BRIDADA 90MM. und 3.00 235.88 707.64 S/.235.88 S/.235.88 S/.235.88 S/.707.64

01.06.08 CAJA DE CONCRETO PARA VALVULAS DE CONTROL und 7.00 49.60 347.20 S/.115.73 S/.115.73 S/.115.73 S/.347.20

01.07 CONEXIONES DOMICILIARIAS DE AGUA POTABLE 11,854.20 S/.0.00

01.07.01 CONEXION DOMICILIARIA DE AGUA 1/2" - CORTA und 60.00 147.97 8,878.20 S/.2,959.40 S/.2,959.40 S/.2,959.40 S/.8,878.20

01.07.02 CAJA DE CONCRETO PARA CONEXIONES DOMICILIARIAS DE AGUA POTABLE und 60.00 49.60 2,976.00 S/.992.00 S/.992.00 S/.992.00 S/.2,976.00

COSTO DIRECTO 59,026.14 17,617.52 17,159.08 17,847.26 6,402.28 59,026.14


GASTOS GENERALES 10% 5,902.61 S/.1,761.75 S/.1,715.91 S/.1,784.73 S/.640.23 S/.5,902.61
UTILIDAD 5% 2,951.31 880.88 857.95 892.36 320.11 2,951.31

SUB TOTAL 67,880.06 S/.20,260.15 S/.19,732.94 S/.20,524.35 S/.7,362.62 S/.67,880.06


IGV 18% 12,218.41 3,646.83 3,551.93 3,694.38 1,325.27 12,218.41

TOTAL 80,098.47 S/.23,906.97 S/.23,284.87 S/.24,218.73 S/.8,687.89 S/.80,098.47