Brief information on CDM in Mongolia

Current state of CDM in Mongolia

Legal framework Dates

Ratification of UNFCCC (non-annex I party) 1993 .09.30

Ratification of Kyoto protocol 1999.12.15

National committee on Climate Change was established 2000

Establishment of CDM DNA under Ministry of Nature, Environment and Tourism 2004.11.14

CDM projects in Mongolia Number

The structure of Approval Committee, approval


Registered projects in UNFCCC 3 procedure and sustainable development criteria of
Number of projects approved by CDM DNA 4 CDM project were adopted on August 7, 2009 by the
decision of Minister for Nature, Environment and
Number of project idea notes (PIN) endorsed 14 Toursim.
by CDM DNA
Approval procedures of CDM DNA CDM project approval procedure/ CDM project cycle
№ Submitting PDDs and PINs to CDM DNA, MNET
CDM DNA
Project Idea
5.1-When a PIN is submitted to the CDM DNA together with letter of request for Project Appraisal
1 Endorsement , CDM DNA will send the PIN to it’s each approval committee Committee
members within 3 working days .

2 5.3-CDM DNA will gather the evaluation of PINs from Appraisal committee members -Ministry of Nature, Voluntary
within 5 working days after sending it to their review. Environment and Tourism basis
Project Idea
5.4 –CDM DNA will respond to project developers within 10 working days by issuing -Ministry of mineral Endorsement/
Note/ PIN
objection
3 endorsement letter or objecting the PINs if it doesn’t meet the sustainable resources and energy
development criteria. -Ministry of Finance 10 working days

4 6.3 –CDM DNA will designate a technical committee to review and comment on PDD
- Ministry of Food, Obligatory
Agriculture and Soft Project
after 3 working days since it is submitted.
Approval/ Objection design
Industries document/
5 6.5 –CDM DNA will put PDDs for public consultation on it’s website for 2 weeks after
- Íèéñëýëèéí çàñàã 30 working days PDD
it’s submitted .
äàðãûí òàìãûí ãàçàð
6.8 -ÒÁÁ-òýé õîëáîîòîé ñàíàëàà èëýðõèéëýõýýð õºíäëºíãèéí ýòãýýä 3-ààñ äîîøã¿é -Mongolian National
6 õîíîãèéí ºìíº óðüä÷èëàí òîâ÷îîíä ìýäýãäñýí áîë хурлын хэлэлц¿¿лэгт тºсºлд chamber of Commerce
оролцогчдыг áàéëöóóëàí оролцуулж болно.
and Industry
6.10 -Õîðîîíû ãèø¿¿í á¿ðèéí òóõàéí òºñºëä ºãñºí ¿íýëãýýíèé íèéëáýð ä¿í ñºðºã áóþó -Mongolian association of
7 òàòãàëçñàí ýñâýë 0-ýýñ äýýø ýåðýã áóþó äýìæñýí áàéæ áîëîõ áºãººä òóñ á¿ð íýã Energy
ñàíàëä òîîöîãäîíî. Õорооны гиш¿¿äèéí ýíãèéí îëîíõûí ñàíàëààð òóõàéí òºñºëä
- National University of
òàòãàëçñàí ýñâýë áàòëàìæ áè÷èã îëãîõûã äýìæñýí øèéäâýðèéã ãàðãàíà. Ñàíàë
òýíöñýí òîõèîëäîëä òîâ÷îîíû ñàíàëûã õàðãàëçàí ¿çíý. Mongolia
- University of Science
8 6.11 -Хорооны даргûí гарын ¿сэг зурж áàòàëãààæóóëñàí ¿íýëãýýíèé øèéäâýðò and Technology
¿íäýñëýí òовчооны дарга òóõàéí тºсºлд оролцогчдод татгалзсан эсвэл
áàòëàìæèëñàí àëáàí áè÷èã олгоно.

9 6.12- ЦХМ-ын тºслийн баримт бичгийн багцыг х¿лээж авснаас хойш àæëûí 30
õîíîãò áàãòààí áàòëàìæ áè÷èã îëãîõ ýñýõ òàëààðõ àëáàí ¸ñíû øèéäâýð ãàðãàíà. Validation by
10 7.1 -Сонирхлын зºрчилòýé ãýæ тухайн õîðîîíû гиш¿¿н ¿çâýë àëèâàà тºслийг DOE
¿нэлэхээс татгалзаíà. Ýíý òóõàéãàà хорооíä болон товчоонд мэдэгдэх ¿¿рэгтэй.

11 7.2 -ЦХМ-ын ¿ндэсний товчооны гаргасан шийдвэр òºсºлд оролцогчäûí àøèã


сонирхлûã зºрчñºн ãýæ ¿çâýë õîëáîãäîõ õóóëü, òîãòîîìæèéí äàãóó ãîìäîë ãàðãàí
øèéä¿¿ëýõ ýðõòýé.

12 Хэрэв дээрх øàëãóóð ¿ç¿¿ëýëò тус б¿рä ºãñºí îíîîíóóäûí íèéëáýð 0 болон ò¿¿íýýñ
Implementat Verification/
дээш байвал òóõàéí тºслèéã óëñ îðíû òогтвортой хºгжлийн шалгуурт нийцэж Registration CER issuance
ion DOE
байна гэж ¿знэ.
Sustainable development criteria for CDM
projects evaluation in Mongolia

№ Criterias Point Impact


Impact on Environment
1 +2 High (positive)
Impact on Climate Change of the world
Contribution to sustainable management of local natural resources
Contribution to reduction of other pollutants in the air +1 Moderate (positive)
Impact on Society
2
Impact on health and displacement of local people
0 Neutral (no impact)
Contribution to poverty reduction by creating jobs
Impact on Economy and Technology
3 -1
Efficiency and productivity of resource use Moderate (negative)
Know how and technology transfer to Mongolia
Creation of Infrastructure -2 High(negative)
Feasibility and Profitability of the project
International needs and demand
4
Attractiveness for the investors
Central and local government support
Projects will be evaluated on the basis
Sufficient infrastructure and human resources
of this sustainable development
criteria. And all the projects must
comply Mongolian law. Projects that
receive positive points will be issued
Endorsement/ Approval letter.
CDM projects reported to the CDM DNA, Mongolia
№ Project Name Project Participants Annual СО2 reduction Total Current status
Investment
1 Energy conservation and Ch. Bat 75.0 – 90.0 thousand ton CO2- 10.3 million US$ PDD drafted
emission reductions from poor Tel/Fax:315347 eq
households E-mail: Choimpogbat@yahoo.com
Improvement of heating systems in T.Ganbold, G.Purevdorj 30,0 thousand ton CO2- eq 47.7 million US$ PIN
2 urban centers of Mongolia ganucs@fea.energy.mn,
prurevdorj@mobinet.mn

3 Energy efficiency rehabilitation for G.Myagmar 100.0 –110.0 thousand tonCO2 80.0 million US$ PDD stage
pre-cast panel buildings in myagmar_arch@yahoo.com eq
Ulaanbaatar city

Reconstruction boilers in Power T.Ganbold 32,0 – 33,0 thousand ton CO2- 15.0 million US$ PIN
Plants of Darkhan and Erdenet tel:99163103, 341371 Ext: 225, eq
4 fax:343479
ganucs@fea.energy.mn

5 Salkhit wind park (50 MW) N.Ganhyag 180.0 – 190.0 thousand ton 85.0 million US$ Validation stage
gankhuyagd@newcom.mn CO2- eq

6 Replacement of coal and wood Ts.Puntsag 15.445 thousand ton CO2-eq PIN
fired heating by renewable info@steppesolar.com
heating system tel:317177/331356

Community based heating supply T.Ganbold 17,0-23,0 thousand tonCO2- eq 2,0 million US$ PDD stage (financed by ADB
in rural remote areas of Mongolia G.Purevdorj carbon fund)
7 Tel:99163103, 341371 Ext: 225,
Fax:343479
ganucs@fea.energy.mn,
prurevdorj@mobinet.mn

Program of Energy Efficiency, T.Ganbold 30,0 thousand tonCO2- eq 9.0 million US$ PIN
Power Plant Darkhan tel:99163103, 341371 Ext: 225,
8 fax:343479
ganucs@fea.energy.mn

9 Energy conservation with Tsoodol- general manager 30,0 thousand ton CO2- eq 0.6 - 0.8 million US$ PIN
utilisation of active mineral Tel: +976-99096149
additives (pozzolans) in Cement khutul_cement@rail.com
production

Energy conservation with Sh.Munhjargal-general manager 30,0 thousand ton CO2- eq 6.5 million US$ PIN
introduction of variable speed Tel: +976-91111558
10 drive pumps for heating engineer@dhc.mn
distribution in Ulaanbaatar
CDM projects reported to the CDM DNA (continued)

11 Waste gas to green energy B.Jigjidsuren 28,5 thousand 5,43 million PDD stage
Tel: 70110181 ton CO2 US$
info@newenergy.mn maqsood@newenergy.mn
zagdochir@newenergy.mn

12 Geothermal heating supply in ger Г.Мягмар, Deputy Director, 3 æèë= 99,6 ìÿí 175,0 million PIN
district Утас: 327252 Факс:322904 òí CO2- US$
E-mail: myagmar_arch@yahoo.com дүйцүүлэн

13 Maikhan Hydro Power Plant (12 Б. Давгадорж 47.3 ìÿí òí CO2- 9.8 million US$. PDD stage
MW ) Óòàñ:354257, 350268 дүйцүүлэн
usnyerchim@mongol.net, bdagvadorj@yahoo.com

14 Geothermal Project in Khangai Т. Ганболд, ЦХМ-ын зөвлөх, 50.0 ìÿí òí CO2 14.0 million US$ PIN
region of Mongolia Г. Пүрэвдорж
Утас:99163103, 341371 Ext: 225, Факс:343479
ganucs@fea.energy.mn, prurevdorj@mobinet.mn

15 Reduction of CO2 while introducing Äýä захирал Б. Цэрэннадмид 30,0 thousand 3.2 - 3.5 million PIN
the Ladle Refining furnace in утас: 1372-24203 tonCO2- US$
Darkhan metallurgical plant of факс: 1372-23946 дүйцүүлэн
Mongolia info@dmplant.mn HTTP:/www.dmplant.mn/

16 250 MW Khanbogd High power ÿéöýòãýõ захирал С. Мөнхжаргал 1.412 ìÿí òí CO2- 438 сая US$ PDD stage
wind farm óòàñ:70110546 дүйцүүлэн
qleantech@yahoo.com , www.qleantech.net

17 Biogas plant in Mongolia Äэд захирал Н. Ганбаатар 2.312 ìÿí òí 980.0 million PIN
óòàñ: 976-329192 факс:311612 CO2- дүйцүүлэн US$
гар утас: 976-99116315
info@monbiogas.com,
batsaikhan_baldandorj@yahoo.com www.ntic.mn

18 Shainshand wind farm Р. Давааням 174.0 ìÿí òí CO2- 75.0 million US$ PIN
Óòàñ:11-327626 дүйцүүлэн
sainshandwp@yahoo.com , www.monwea.mn

19 Thaishir hydro power plant ЦХМ-ын зөвлөх Т. Ганболд 29.640 ton CO2- НҮБ-ын уур амьсгалын өөрчлөлтийн
утас:99163103, 341371 Ext: 225, факс:343479 eq суурь конвенцийн газарт
ganucs@fea.energy.mn бүртгэгдсэн.48 ßÁÁ –ã 2010 îíû 1-ð
ñàðä àâñàí.

20 Durgun Hydro power plant ЦХМ-ын зөвлөх Т. Ганболд, 30.4 thousand НҮБ-ын уур амьсгалын өөрчлөлтийн
утас:99163103, 341371 Ext: 225, факс:343479 tonCO2- суурь конвенцийн газарт бүртгэгдсэн.
ganucs@fea.energy.mn дүйцүүлэн Õÿíàëò øèíæèëãýý õèéñýí òàéëàí
áýëòãýãäýæ áàéãàà.

21 Retrofit program for decentralised Dipl. Ing. Walter Paulsen: Andreas Glas M.A. 12 ìÿí òí CO2- НҮБ-ын уур амьсгалын өөрчлөлтийн
heating stations in Ulaanbaatar Tel.: +49 97 99 01-25 Tel.: +49 97 99 01-28 дүйцүүлэн суурь конвенцийн газарт бүртгэгдсэн.
Fax: +49 97 99 01-50 Îðîëöîã÷ òàëóóäûí çºð÷èëäººíººñ ¿¿äýí
õýðýãæèõã¿é áàéãàà.
CDM National bureau (DNA) Ministry of Nature, Environment
and Tourism

Potential sector for CDM projects in Mongolia

№ Projects Ангилал
1 Renewable Energy - Solar, wind, hydro and geothermal power stations
- Biomass, biogas
- Energy efficiency in electricity and heat stations
Energy efficiency - energy efficiency in supply and demand side
2 - Retrofit for small HOBs
- Improving coal quality

Electricity and heat - Energy efficiency rehabilitation for Pre-cast Panel buildings
3 supply efficiency in - Energy efficiency in lightning (PV lamp )
construction
- Energy conservation and emisision reductions from poor households

- Introducing of new technology in brick factory


- Introducing new technology in cement production
4 Industry
- Technology change in metallurgical plant

5 Waste -Composting
management -Utilization of landfill gas
6 Fuel switch - Gas
- Afforestation and Reforestation
7 Other - Land use management
- Coal mine methane utilization
- Improving the stoves of ger district and quality of coal

Address: Ministry of Nature, Environment and Toursim, CDM National Bureau (DNA)
UN street 5/2, Government building 3,
Tel: 976-51-266314
Fax: 976-11-321401 Email: info@cdm-mongolia.com Website: www.cdm-mongolia.com

You might also like