PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+00 GALIAN 64.00

x y x.y y.x
62.00

0.000 54.369 - 864.467 60.00

15.9000 53.4850 852.285 1,188.116


58.00
22.2140 53.6028 1,165.902 1,139.151
21.2517 52.4850 1,115.395 98.882 56.00

1.884 52.485 102.431 - Galian Galian

54.00
0.000 54.369 - -
0+000
0.000 0.000 Bidang persamaan
52.00 20.00 14.00

26.1049 53.6754 1,403.869 1,696.143 Reference level


50.00

31.6000 53.7780 1,781.134 1,936.008 ELEVASI RENCANA

36.0000 56.3650 2,039.929 2,305.092

56.356

54.369

53.485

53.778

56.365
ELEVASI TANAH ASLI

40.8958 56.6647 2,146.416 2,317.348 JARAK (m) 4.60 15.90 15.70 4.40
40.8958 52.4850 2,146.416 1,411.626
26.8958 52.4850 1,443.643 1,370.116
26.1049 53.6754 - -
64.00 64.00

JUMLAH62.0014,197.420 14,326.948 62.00

LUAS= x . y- 60.00
y.x 64.764 M2 60.00

2
58.00 58.00 2.25 2.00 3.75 2.00 4.00

BATU Uk > 1000 Kg 56.4850


Batu Uk. < 250 Kg
x y 56.00 x . y y.x 56.00
Batu Uk.> 1.000 Kg
1
1.5 1
1.50 1

53.9850
0.000 52.485 54.00 - 118.091 54.00
1.5
1.50
2.250 0+00053.985 121.466 229.436 0+000 52.4850
1
52

4.250 53.985 52.00


Bidang persamaan 240.061 431.880 Bidang persamaan
52.00 4.70 7.22 2.08

8.000 56.485 50.00


Reference level
451.880 564.850 Reference level
50.00
10.0000 56.4850 524.850 790.790
ELEVASI RENCANA ELEVASI RENCANA
14.0000 52.4850 734.790 625.616
56.356

54.369

53.485

53.778

56.365
56.356

54.369

53.485
11.9199 52.4850
ELEVASI TANAH ASLI 655.416 494.356 ELEVASI TANAH ASLI
9.419 54.985 517.904 464.843
J ARAK (m) 4.60 15.90J ARAK (m) 4.60 15.70 15.90 4.40 12.40 15.70
56.356

54.369

53.485

53.778

56.365
56.356

54.369

53.485
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.60 15.90J ARAK (m) 4.60 15.70 15.90 4.40 12.40 15.70
8.454 54.985 443.708 258.649
4.704 52.485 246.889 -
0.000 52.485 - -
Diperiksa :
JUMLAH 3,936.965 3,978.512 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 20.774 M2
2 Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00 64.00
0+00 BATU UK 250 - 1000 Kg
x y x.y y.x
62.00 62.00

0.000 52.485 - 196.819


3.750 54.985 206.194
60.00 259.254 60.00
4.715 54.985 247.467 396.717
7.215 52.485 378.679 -
58.00 58.00 2.25 2.00 3.75 2.00 4.00
0.000 52.485 - -
56.4850
56.00 56.00 1.5 1
1 1.50 1
Geotextile Ba
53.9850
JUMLAH 832.340
54.00 852.790 54.00
1.5
1.50
1
52.4850
LUAS= Bidang
x persamaan
. y- y . x 52.00 10.225 M2 Bidang persamaan
52.00 4.70 7.22 2.0
2
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


56.356

54.369

53.485

53.778

56.365
56.356

54.369

53.485
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.60 15.90


JARAK (m) 4.60 15.70 15.90 4.40
GEOTEXTILE 64.00 64.00
( 4.70 + 7.22 + 2.08 )
62.00 14.00 M' 62.00

60.00 60.00

Perapian
Permukaan Tanggul Timbunan
58.00 58.00 Hasil Galian
4.00

56.00 56.00

Galian Galian Galian

MERAPIKAN PERMUKAAN TANGGUL


54.00 54.00

4.00 0+000 0+000


52.00 20.00 52.00 20.00
Bidang persamaan 4.00 M' Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


56.356

54.369

53.485
54.369

53.485
56.356

53.778

56.365

57.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.60 15.90 J ARAK (m) 15.70 4.60 4.40 15.90 12.40
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.356

54.369

53.485
54.369

53.485
56.356

53.778

56.365

57.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.60 15.90 J ARAK (m) 15.70 4.60 4.40 15.90 12.40

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+025 GALIAN
x y x.y y.x 62.00

0.000 54.563 - 627.475 60.00

11.5000 54.1230 620.292 1,186.825 58.00

21.9283 53.9384 1,160.511 1,135.630


21.0542 52.9230 1,114.251 55.781 56.00
Galian

1.054 52.923 57.509 - 54.00


0.000 54.563 - -
0+025 20.00

0.000 0.000 Bidang persamaan


52.00 14.00

Reference level
27.5169 53.9390 1,485.032 1,947.198 50.00

36.1000 53.9680 1,959.808 2,298.740

54.563

52.923

53.938

53.939
ELEVASI RENCANA

42.5945 54.2883 2,254.229 2,289.338

56.365

54.563

53.923

53.968
54.123
ELEVASI TANAH ASLI

42.1700 52.9230 2,231.763 1,490.841 J ARAK (m) 2.90 11.50 11.30 13.30
28.1700 52.9230 1,519.462 1,456.277
27.5169 53.9390 - -
- -

64.00 64.00
JUMLAH 12,402.857 12,488.104
62.00 62.00
LUAS= x . y- y . x 42.624 M2
60.00 2 60.00

BATU Uk >58.00
1000 Kg 58.00
2.25 2.00 3.75 2.00 4.00

+ 56.923
x y x.y y.x Batu Uk. < 250 Kg
1.5 1
56.00 56.00 Batu Uk.> 1.000 Kg
1 1.50 1

0.000 52.923 - 119.077 + 54.423

2.250 54.423
54.00
122.452 231.298 54.00 1.5
1.50
1.00 + 52.9231 1.00
4.250
0+025 54.423 241.923 435.384 0+025 4.70 7.22 2.08
52.00 52.00
8.000
Bidang persamaan 56.923 455.384 569.230 Bidang persamaan
Reference level Reference level
10.0000 56.9230
50.00 529.230 796.922 50.00
14.0000 52.9230 740.922 630.837
ELEVASI RENCANA ELEVASI RENCANA
11.9199 52.9230 660.637 498.482
56.365

54.563

53.968
53.923

54.402

57.264
56.365

54.563

53.923
54.123

54.123
9.419 ASLI 55.423
ELEVASI TANAH 522.029 468.546 ELEVASI TANAH ASLI

J ARAK (m) 2.90 11.50 11.30


JARAK (m) 2.90 13.30 11.50 8.80 11.30 7.30 13.
ELEVASI RENCANA ELEVASI RENCANA

56.365

54.563

53.968

54.402
53.923

57.264
54.123

56.365

54.563

53.923
54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454
J ARAK (m) 55.423 447.411
2.90 260.710 11.50 11.30
JARAK (m) 2.90 13.30 11.50 8.80 11.30 7.30 13.
4.704 52.923 248.950 -
0.000 52.923 - -
Diperiksa :
JUMLAH 3,968.937 4,010.485 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 20.774 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00 64.00
0+025 BATU UK 250 - 1000 Kg
x 62.00
y x.y y.x 62.00

0.000 52.923 - 198.461


60.00 60.00
3.750 55.423 207.836 261.319
4.715 55.423 249.532 399.877
2.25 2.00 3.75 2.00
7.215 52.923
58.00 381.839 - 58.00
+ 56.923
0.000 52.923 - -
1.5
56.00 56.00 1 1.50
Geotextile
+ 54.423
54.00 54.00 1.5
JUMLAH 839.208 859.658 1.00 + 52.9231
1.50

0+025 0+025 4.70 7.22


52.00 52.00
LUAS=
Bidang persamaan x . y- y . x 10.225 M2 Bidang persamaan
Reference level 2 Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


56.365

56.365
53.923

54.563

53.968

54.402
54.563

54.123

54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

64.00 64.00
J ARAK (m) 2.90 11.50 JARAK (m) 11.30 2.90 13.30 11.50 8.80 11.30
GEOTEXTILE
( 4.7 + 7.22 + 2.08 ) 62.00 62.00

14 M'
60.00 60.00
Perapian
Permukaan Tanggul

58.00 58.00
13.16

56.00 56.00
Galian Galian Galian

54.00 54.00

MERAPIKAN PERMUKAAN TANGGUL


0+025 20.00 0+025 20.00
( 13.16 ) Bidang persamaan
52.00
Bidang persamaan
52.00 14.00

Reference level 13.16 M' Reference level


50.00 50.00

54.563

52.923
54.563

52.923

53.938

53.939

52.923
ELEVASI RENCANA ELEVASI RENCANA

54.563
56.365
53.923

53.968

54.402
56.365

54.563

54.123
54.123

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.90 11.50 11.30


J ARAK (m) 2.90 13.30 11.50 8.80 11.30 7.30
54.56

52.92
53.93
54.56

52.92

53.93

52.92
ELEVASI RENCANA ELEVASI RENCANA

54.563
56.365
53.923

53.968

54.402
56.365

54.563

54.123
54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.90 11.50 11.30


J ARAK (m) 2.90 13.30 11.50 8.80 11.30 7.30

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+050 GALIAN
x y x.y y.x 64.00

0.000 54.623 - 606.315 62.00

11.1000 54.2350 600.958 1,226.177 60.00

22.6086 54.1404 1,193.011 1,160.077


21.4272 52.7680 1,130.670 75.300 58.00

1.427 52.768 77.947 - 56.00

0.000 54.623 - - Galian

54.00

33.5667 53.8512 1,805.419 1,954.799 0+050 20.00


52.00
Bidang persamaan
36.3000 53.7860 1,968.280 2,603.242 Reference level
50.00
48.4000 54.2226 2,553.971 2,624.374
ELEVASI RENCANA
48.4000 52.7680 2,553.971 1,815.219

54.235

53.768
56.235

54.623

54.124
ELEVASI TANAH ASLI
34.4000 52.7680 1,852.481 1,771.248
JARAK (m) 2.50 11.10 13.50 11.70
33.5667 53.8512 - -

64.00 64.00

JUMLAH 13,736.709 13,836.751


62.00 62.00

LUAS= x . y- y . x 50.021 M2
60.00 60.00
2
58.00 58.00 2.25 2.00 3.75 2.00 4.00
BATU Uk > 1000 Kg + 56.768
x56.00 y x.y y.x 56.00 Batu Uk.> 1.000 Kg
1.5 1
Batu Uk. < 250 Kg

1 1.50 1

0.00054.00
52.768 - 118.728 54.00
+ 54.268
1.5
2.250 54.268 122.103 230.639 + 52.768
1 1.00
1.50

0+0504.250 54.268 241.264 434.144 0+050 4.70 7.22 2.08


52.00 52.00
Bidang persamaan Bidang persamaan
Reference level8.000 56.768 454.144 567.680 Reference level
10.000050.00 56.7680 527.680 794.752 50.00

ELEVASI RENCANA14.0000 52.7680 738.752 628.989 ELEVASI RENCANA

11.9199 52.7680 658.789 497.022


56.235

54.623

54.235

53.768

54.324
56.235
54.124

54.623

54.235

57.172
54.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
9.419 55.268 520.569 467.236
J ARAK (m) 2.50 11.10 13.50
JARAK (m) 2.50 11.70 11.10 14.80
13.50 2.50
ELEVASI RENCANA ELEVASI RENCANA

56.235

54.623

54.235

53.768

54.324
56.235
54.124

54.623

54.235

57.172
54.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 8.454 55.268 2.50 446.101 259.981


11.10 13.50
JARAK (m) 2.50 11.70 11.10 14.80
13.50 2.50

4.704 52.768 248.221 -


0.000 52.768 - -
Diperiksa :
JUMLAH 3,957.623 3,999.170 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 20.774 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00 64.00
BATU UK 250 - 1000 Kg
x y x.y
62.00
y.x 62.00

0.000 52.768 - 197.880


60.00 60.00
3.750 55.268 207.255 260.589
4.715 55.268 248.801 398.759
58.00 58.00 2.25 2.00 3.75 2.00
7.215 52.768 380.721 -
+ 56.768
0.000 52.768 - -
56.00 56.00 1.5 1
1 1.50
Geotextile
+ 54.268
54.00 54.00 1.5
1.50
1
JUMLAH 836.777 857.227 + 52.768
1.00
0+050 0+050 4.70 7.22
52.00 52.00
Bidang persamaan Bidang persamaan
LUAS= x level
Reference . y- y . x 10.225 M2 Reference level
2 50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


64.00 64.00

54.623

54.235
56.235
56.235

54.623

54.235

53.768
54.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m)
62.00 2.50 11.10 13.50
J ARAK (m) 2.50
62.00 11.70 11.10 14.80
13.50

GEOTEXTILE
60.00 60.00
( 4.7 + 7.22 + 2.08 )
Perapian
14 M' Permukaan Tanggul
58.00 58.00
8.85

56.00 56.00
Galian Galian

54.00 54.00

0+050 MERAPIKAN PERMUKAAN TANGGUL 20.00 0+050 20.00


52.00 52.00
Bidang persamaan Bidang persamaan
Reference level ( 8.85 ) Reference level
50.00 8.85 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.235

54.235
56.235

54.623

54.235

54.623

53.768
54.124

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 11.10 13.50 J ARAK (m) 11.70 2.50 11.10 14.80
ELEVASI RENCANA ELEVASI RENCANA

56.235

54.235
56.235

54.623

54.235

54.623

53.768
54.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 11.10 13.50 J ARAK (m) 11.70 2.50 11.10 14.80

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+075 GALIAN 64.00

x y x.y y.x
62.00

0.000 54.886 - 702.541 60.00

12.8000 54.0980 701.850 1,190.156


58.00
22.0000 54.8320 1,205.439 1,252.171
22.8365 54.7927 1,212.572 1,171.336 56.00
Galian
21.3776 53.0980 1,135.108 94.939
54.00
1.788 53.098 98.136 - 1.00

0+075 20.00
0.000 54.886 Bidang persamaan
52.00

Reference level
50.00

34.3612 54.2516 1,859.731 2,012.734 ELEVASI RENCANA

37.1000 54.1230 2,020.640 2,665.558

56.352

54.098
54.886

54.832

54.123
ELEVASI TANAH ASLI
49.2500 54.4647 2,615.077 2,682.386 J ARAK (m) 2.40 12.80 9.20 15.10
49.2500 53.0980 2,664.327 1,871.705
35.2500 54.0980 1,912.369 1,858.872
34.3612 64.00
54.2516 - - 64.00

62.00 62.00
JUMLAH 15,425.249 15,502.399
60.00 60.00
LUAS= x . y- y . x 38.575 M2
2 2.25 2.00 3.75 2.00 4.00
58.00 58.00
+ 57.098
Batu Uk. <
BATU Uk > 1000 Kg Batu Uk.> 1.000 Kg
1.5 1
56.00 56.00 1 1.50 1
x y x.y y.x
+ 54.598

54.00 54.00 1.5


0.000 53.098 - 119.471 + 53.098
1
1.50

0+075 2.250 54.598 122.846 232.042 0+075 4.70 7.22 2.08


4.250 52.00
Bidang persamaan 54.598 242.667 436.784 Bidang persamaan
52.00

8.000
Reference level 57.098 456.784 570.980 Reference level
50.00 50.00
10.0000 57.0980 530.980 799.372
ELEVASI RENCANA ELEVASI RENCANA
14.0000 53.0980 743.372 632.923
11.9199 53.0980 662.723 500.130
56.352

54.098

54.832
54.886

54.886

54.098

54.832
56.352

54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
9.419 55.598 523.678 470.025
J ARAK (m) 2.40 12.80 J ARAK (m)9.20 2.40 15.1
10
2.80 9.20 14.90
56.352

54.098

54.832
54.886

54.886

54.098

54.832
56.352

54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 8.454 55.598 2.40 448.890 261.533 12.80 J ARAK (m)9.20 2.40 15.1
10
2.80 9.20 14.90
4.704 53.098 249.773 -
0.000 53.098 - -
Diperiksa :
JUMLAH 3,981.712 4,023.259 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 20.774 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

BATU UK 25062.00
- 1000 Kg 62.00

x y x.y y.x
60.00 60.00
0.000 53.098 - 199.118
3.750 55.598
58.00
208.493 262.145 58.00
2.25 2.00 3.75 2.00

4.715 55.598 250.357 401.140 + 57.098

7.215 53.098 383.102 - 1.5 1


56.00 56.00 1 1.50
0.000 53.098 - - Geotextile
+ 54.598

54.00 54.00 1.5


1.50
1
+ 53.098

0+075 0+075 4.70 7.22


JUMLAH
52.00 841.952 862.402 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
LUAS= x50.00
. y- y . x 10.225 M2 50.00

ELEVASI RENCANA
2 ELEVASI RENCANA
56.352

54.886

54.098

54.832

54.886

54.098

54.123
56.352

54.832
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

64.00 64.00
JARAK (m) 2.40 12.80 J ARAK (m) 9.20 2.40 15.1
12.80
0 9.20 14.90

62.00 62.00
GEOTEXTILE
( 4.7 + 7.22 +60.00
2.08 ) 60.00
14 M' Perapian
Permukaan Tanggul
58.00 58.00
7.35

56.00 56.00
Galian Galian

54.00 54.00
1.00 1.00

0+075
MERAPIKAN PERMUKAAN TANGGUL
20.00 0+075 20.00
52.00 52.00
Bidang persamaan Bidang persamaan
( 7.36 + 0.42 )
Reference level Reference level
50.00 7.78 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.801
56.352

54.886

54.098
56.352

54.098

54.832

54.542
54.886

54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.40 12.80 9.20 J ARAK (m) 15.10 2.40 12.80 14.90 0.90
9.2
ELEVASI RENCANA ELEVASI RENCANA

56.801
56.352

54.886

54.098
56.352

54.098

54.832

54.542
54.886

54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.40 12.80 9.20 J ARAK (m) 15.10 2.40 12.80 14.90 0.90
9.2

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+100 GALIAN
x y x.y y.x
64.00

0.000 55.412 - 620.614 62.00

11.2000 55.3260 619.824 1,254.987


22.6835 55.3414 1,218.422 1,177.803 60.00

21.2825 53.7140 1,143.168 91.206 58.00

1.698 53.714 94.105 -


Galian
0.000 55.421 - - 56.00

54.00

34.0092 55.0781 1,862.262 2,711.495 20.00


0+100
49.2300 54.7576 2,644.340 2,695.717 Bidang persamaan
52.00

Reference level
49.2300 53.7140 2,644.340 1,892.344 50.00

35.2300 53.7140 1,940.401 1,826.770 ELEVASI RENCANA

34.0092 55.0781 - -

55.342
57.236

55.326
55.412

55.192
ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11.90 5.50 22.70

64.00 64.00

JUMLAH 12,166.862 12,270.937


62.00 62.00

LUAS= x . y- y . x 52.038 M2
60.00 60.00
2
2.25 2.00 3.75 2.00 4.00

58.00 58.00 + 57.714


BATU Uk > 1000 Kg 1.5
Batu Uk. < 250 Kg
Batu Uk.> 1.000 Kg 1
x y x.y y.x 1 1.50 1
56.00 56.00
+ 55.214
1.5
0.000 53.714 - 120.857 1
1.50
54.00 54.00 + 53.714
2.250 55.214 124.232 234.660 4.70 7.22 2.08
0+100
4.250 52.0055.214 245.285 441.712 0+100
52.00
Bidang persamaan Bidang persamaan
8.000 57.714 461.712 577.140
Reference level Reference level
10.0000 50.00
57.7140 537.140 807.996 50.00

14.0000 53.7140
ELEVASI RENCANA 751.996 640.266 ELEVASI RENCANA
11.9199 53.7140 670.065 505.932
57.236

55.326

55.342

57.386
55.326
55.412

57.236

55.192

55.342

54.714
55.412

55.192
9.419
ELEVASI TANAH ASLI
56.214 529.480 475.233 ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11(m)


J ARAK .90 2.70 5.50 11.20 22.70 11.90 5.50 2.20
ELEVASI RENCANA ELEVASI RENCANA

57.236

55.326

55.342

57.386
55.326
57.236

55.342
55.412

55.192

54.714
55.412

55.192
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 8.454 56.214 2.70 454.098 264.431


11.20 11(m)
J ARAK .90 2.70 5.50 11.20 22.70 11.90 5.50 2.20
4.704 53.714 252.671 -
0.000 53.714 - -
Diperiksa :
JUMLAH 4,026.678 4,068.225 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 20.774 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

BATU UK 250 - 1000 Kg


62.00 62.00
x y x.y y.x

60.00
0.000 53.714 - 201.428 60.00

3.750 56.214 210.803 265.049 2.25 2.00 3.75 2.00

4.715
58.00 56.214 253.262 405.584 58.00 + 57.714
7.215 53.714 387.547 - 1.5
1
0.000 53.714 - - 1.50
56.00 56.00 Geotextile
+ 55.214
1.5
1.50
1
54.00 54.00 + 53.714

JUMLAH 851.611 872.061 4.70 7.22


0+100 0+100
52.00 52.00
Bidang persamaan Bidang persamaan
LUAS= x . y- y . x 10.225 M2
Reference level Reference level
50.00 2 50.00

ELEVASI RENCANA ELEVASI RENCANA


55.326

55.342
57.236

55.326
55.412

57.236

55.192
55.412
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00

J ARAK (m) 2.70 11.20 JARAK11.90


(m) 2.70 5.50 11.20 22.70 11.90
GEOTEXTILE 62.00 62.00
( 4.7 + 7.22 + 2.08 )
60.00 14 M' 60.00 Perapian
Permukaan Tanggul

8.12
58.00 58.00

Galian Galian
56.00 56.00

54.00 54.00

MERAPIKAN PERMUKAAN TANGGUL 20.00 20.00


0+100 0+100
( 8.12 + 0.36 Bidang
) persamaan
52.00
Bidang persamaan
52.00

Reference level 8.48 M' Reference level


50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


57.236

55.326
55.326

55.342
57.236

55.412
55.192
55.412

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11.90 JARAK (m) 5.50 2.70 11.20 22.70 11.90
ELEVASI RENCANA ELEVASI RENCANA

57.236

55.326
55.326

55.342
57.236

55.412
55.192
55.412
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11.90 JARAK (m) 5.50 2.70 11.20 22.70 11.90

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+125 GALIAN
x y x.y y.x 64.00

62.00
0.000 55.552 - 883.277
15.9000 55.4420 877.863 1,255.257 60.00

22.6409 55.2115 1,219.348 1,185.612


21.4740 53.8560 1,156.504 91.340 58.00

1.696 53.856 94.216 - Galian


Galian
56.00
0.000 55.552 - -
54.00
20.00 11.54
27.7278 55.0556 1,521.036 1,932.452 0+125
35.1000 54.8560 1,936.888 2,243.610 Bidang persamaan
52.00

Reference level
40.9000 55.1820 2,202.710 2,220.491 50.00

40.2394 53.8560 2,167.133 1,545.667 ELEVASI RENCANA

28.7000 53.8560 1,580.096 1,493.308

57.665

55.552

55.442

55.124
ELEVASI TANAH ASLI
27.7278 55.0556 - -
J ARAK (m) 4.50 15.90 9.30 9.90

64.00 64.00

JUMLAH 12,755.795 12,851.013


62.00 62.00

LUAS= x . y- y . x 47.609 M2
2 60.00 60.00
2.25 2.00 3.75 2.00

58.00 58.00 + 57.856 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 1.5
Batu Uk.> 1.000 Kg 1
x y x.y y.x 1 1.50 1
56.00 56.00
+ 55.356 + 55.498 +
1.5 1
0.000 53.856 - 121.176 + 53.856 1 1.83 + 53.856 1
54.00 54.00
2.250 55.356 124.551 235.263 11.54

4.250 55.356 0+125245.88852.00 442.848 0+125


52.00
Bidang persamaan Bidang persamaan
8.000 57.856 Reference 462.848
level
578.560 Reference level
10.0000 57.8560 554.984 50.00 714.961 50.00

12.3576 55.4984 667.419


ELEVASI RENCANA 647.439 ELEVASI RENCANA

11.6659 54.0088 657.443 508.709


57.665

55.552

55.442

57.992

58.034
54.856
57.665

55.552

55.124

55.442

55.182

55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
9.419 56.356 530.817 476.434
J ARAK (m) 4.50 15.90
J ARAK (m) 4.50 9.30 15.90 9.90 5.80 9.30 1.40 3.90
ELEVASI RENCANA ELEVASI RENCANA

57.665

55.552

55.442

57.992
54.856

58.034
57.665

55.552

55.442
55.124

55.182

55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.356J ARAK (m) 455.299 4.50


265.099 15.90
J ARAK (m) 4.50 9.30 15.90 9.90 5.80 9.30 1.40 3.90

4.704 53.856 253.339 -


0.000 53.856 - -
Diperiksa :
JUMLAH 3,952.588 3,990.488 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 18.950 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

BATU UK 250 - 100062.00


Kg 62.00
x y x.y y.x

60.00 60.00
0.000 53.856 - 201.960 2.25 2.00 3.75 2.00
3.750 56.356 211.335 265.719
58.00 58.00 + 57.856
4.715 56.356 255.129 392.294
1.5
6.961 54.110 374.892 369.842 1 1.50
6.835 53.856 368.106
56.00 - 56.00 Geotextile
+ 55.356
0.000 53.856 - -
1.5
+ 53.856 1
54.00 54.00
11.54
JUMLAH
0+125 1,209.461 1,229.815 0+125
52.00 52.00
Bidang persamaan Bidang persamaan
LUAS= x level
Reference . y- y . x 10.177 M2 Reference level
2 50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


57.665

55.552

55.442

54.856
57.665

55.552

55.442
55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 64.00 15.90


J ARAK (m) 4.50 9.30 64.00 15.90 9.90 5.80 9
GEOTEXTILE
( 11.54 + 1.83 ) 62.00 62.00

13.37 M'
60.00 60.00 Perapian
Permukaan Tanggul
Timb
Hasil G
3.53
58.00 58.00

Galian Galian
Galian
56.00 56.00

1.00
54.00 54.00
MERAPIKAN PERMUKAAN TANGGUL 20.00 20.00

0+125 0+125
( 3.53 ) Bidang persamaan
52.00
Bidang persamaan
52.00

Reference level 3.53 M' Reference level


50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

54.856

57.992
57.665

55.552

55.442

55.442
57.665
55.124

55.552

55.182
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 15.90 J ARAK (m) 9.30 4.50 9.90 15.905.80 1.40 3.90
ELEVASI RENCANA ELEVASI RENCANA

54.856

57.992
57.665

55.552

55.442

55.442
57.665
55.124

55.552

55.182
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 15.90 J ARAK (m) 9.30 4.50 9.90 15.905.80 1.40 3.90

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+150 GALIAN 64.00

x y x.y y.x
62.00

0.000 55.332 - 663.984


60.00
12.0000 55.5630 668.076 1,016.803
18.3000 55.6730 1,017.271 1,221.154
58.00
21.9344 55.5886 1,191.213 1,158.022
20.8320 54.3080 1,131.344 55.611
Galian
56.00
1.024 54.308 56.660 -
0.000 55.332 - - 54.00 20.00

0+150
27.3909 55.4618 1,518.442 1,580.661 Bidang persamaan
52.00

28.5000 55.4360 1,576.278 2,222.984 Reference level


50.00
40.1000 55.3080 2,177.751 2,154.927
ELEVASI RENCANA
38.9623 54.3080 2,115.965 1,543.433

57.965

55.332

55.673

55.436
55.563
28.4200 54.3080 1,576.224 1,487.545 ELEVASI TANAH ASLI

27.3909 55.4618 - - J ARAK (m) 2.50 12.00 6.30 10.20

64.00 64.00
JUMLAH 13,029.225 13,105.124
62.00 62.00
LUAS= x . y- y . x 37.950 M2
2 60.00 60.00
2.25 2.00 3.75 2.00 2.25 2

+ 58.308 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 58.00 58.00
1.5
Batu Uk.> 1.000 Kg 1 Batu Uk.> 1
x y x.y y.x 1 1.50 1

56.00 56.00 + 55.808 + 55.925


+ 55.808
1.5 1.5
0.000 54.308 - 122.193 + 54.308
1 2.45
+ 54.308
1

2.250 55.808 125.568 237.184 54.00 54.00


10.54

4.250 55.808 247.809 446.464


0+150 0+150
52.00 52.00
8.000 58.308 466.464 583.080
Bidang persamaan Bidang persamaan
Reference level Reference level
10.0000 58.3080 559.255 721.999 50.00 50.00
12.3825 55.9255 680.448 630.588
ELEVASI RENCANA ELEVASI RENCANA
11.2755 54.9524 640.539 517.597

55.308
55.332

56.978
57.965

55.563

55.673

55.436
57.965

55.332

55.436
55.563

55.673
9.419 56.808 535.075 ELEVAS480.255
I TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00


J ARAK (m) 2.50 6.30 12.00 10.20 6.30 11.60 10.20 1.90 5
ELEVASI RENCANA ELEVASI RENCANA

55.332

55.308

56.978
57.965

55.563

55.673

55.436
57.965

55.332

55.436
55.563

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.808 459.120 J ARAK 267.225


(m) 2.50 12.00
J ARAK (m) 2.50 6.30 12.00 10.20 6.30 11.60 10.20 1.90 5
4.704 54.308 255.465 -
0.000 54.308 - -
Diperiksa :
JUMLAH 3,969.742 4,006.584 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 18.421 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00
BATU UK 250 - 1000 Kg
x y x.y y.x
60.00 60.00
2.25 2.00 3.75 2.00

0.000 54.308 - 203.655 + 58.308


B
3.750 56.808 213.030
58.00 267.850 58.00
1.5 1
1
4.715 56.808 259.099 373.285 1.50 1
Geotextile
6.571 54.952 356.858
56.00 320.810 56.00 + 55.808
5.838 54.308 317.050 - 1.5
1
0.000 54.308 - - + 54.308 2.4
54.00 54.00
10.54

0+150 0+150
JUMLAH 1,146.037
52.00 1,165.600 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
LUAS= x . y- y . x50.00 9.782 M2 50.00
2
ELEVASI RENCANA ELEVASI RENCANA

55.673

55.308
57.965

55.332

55.563

55.436
55.332
57.965

55.563

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 2.50 64.00 12.00 J ARAK (m) 6.30 2.50 64.00 10.20 12.00 11.60
6.30

GEOTEXTILE 62.00 62.00

( 10.54 + 2.45 )
Perapian
60.00 12.99 M' 60.00 Permukaan Tanggul

8.26

58.00 58.00

Galian Galian Galian


56.00 56.00

1.00

54.00 20.00 54.00 20.00

MERAPIKAN PERMUKAAN TANGGUL


0+150 0+150
52.00 52.00
( 8.26 + 1.59 ) Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 9.85 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

57.965

55.332

55.563
55.308
57.965

55.563

55.436

56.978
55.332

55.673

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00 6.30 J ARAK (m) 10.20 2.50 12.00
11.60 1.90 6.30 5.60
ELEVASI RENCANA ELEVASI RENCANA

57.965

55.332

55.563
55.308
57.965

55.563

55.436

56.978
55.332

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00 6.30 J ARAK (m) 10.20 2.50 12.00
11.60 1.90 6.30 5.60

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+175 GALIAN
x y x.y y.x
62.00

0.000 56.862 - 477.641


60.00
8.400 55.986 469.190 985.354
17.6000 55.8560 982.076 1,284.548 58.00
22.9975 55.7998 1,246.648 1,209.818 Galian

21.6814 54.2080 1,175.305 143.868 56.00

2.654 54.208 150.912 -


0.000 56.862 54.00 20.00

0+175
25.1057 55.7778 1,399.793 1,517.156 Bidang persamaan
52.00

27.2000 55.7560 1,501.658 2,035.094 Reference level


50.00
36.5000 55.2080 1,978.592 1,955.009
ELEVASI RENCANA
35.4117 54.2080 1,919.597 1,436.512

58.698

56.862

55.986

55.856

55.756
26.5000 54.2080 1,478.112 1,360.930 ELEVASI TANAH ASLI

25.1057 55.7778 - - JARAK (m) 6.00 8.40 9.20 9.60

64.00 64.00
JUMLAH 12,301.885 12,405.930
62.00 62.00
LUAS= x . y- y . x 52.023 M2
2 60.00 60.00
2.25 2.00 3.75 2.00 2.25

+ 58.208 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 58.00 58.00 1
1.5 1
Batu Uk.> 1.000 Kg Batu
x y x.y y.x 1 1.50 + 56.645

56.00 56.00 + 55.708 + 55.70

0.000 54.208 - 121.968


1.5 1.5
1 3.60 1
+ 54.208 + 54.208
2.250 55.708 125.343 236.759 54.00 54.00
8.91

4.250 55.708 247.384 445.664


0+175 0+175
52.00 52.00
8.000 58.208 465.664 582.080
Bidang persamaan Bidang persamaan
Reference level Reference level
10.0000 58.2080 566.446 673.082 50.00 50.00
11.5634 56.6446 643.486 593.601
ELEVASI RENCANA ELEVASI RENCANA
10.4794 55.6485 594.266 524.153

55.208
58.698

56.862

55.986

55.856

55.756

57.689
58.698

55.756
56.862

55.986

55.856
9.419 56.708 534.133 ELEVASI479.409
TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30 9.60 2.70 3.50
ELEVASI RENCANA ELEVASI RENCANA

55.208
58.698

56.862

55.986

55.856

55.756

57.689
58.698

55.756
56.862

55.986

55.856
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.708 458.274 266.754


J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30 9.60 2.70 3.50
4.704 54.208 254.994 -
0.000 54.208 - -
Diperiksa :
JUMLAH 3,889.990 3,923.472 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 16.741 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00
NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 - 1000 Kg


60.00 60.00
x y x.y y.x 2.25 2.00 3.75

+ 58.20
58.00 58.00
0.000 54.208 - 203.280 1.5
1 1.
3.750 56.708 212.655 267.378
Geotextile
4.715 56.708 262.380 327.489
56.00 56.00 + 55.708

5.775 55.648 313.051 234.111 1.5


1
+ 54.208
4.207 54.208 228.053 -
54.00 54.00
8.91
0.000 54.208 - -
0+175 0+175
52.00 52.00
Bidang persamaan Bidang persamaan

JUMLAH Reference level


1,016.140 1,032.258 Reference level
50.00 50.00

LUAS= x . y- y . x ELEVASI RENCANA 8.059 M2 ELEVASI RENCANA

2
58.698

56.862

55.986

55.856

55.756
56.862

55.986

55.856
58.698
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30
64.00 64.00

62.00 62.00

GEOTEXTILE
Perapian
( 8.91 + 3.60 ) 60.00 60.00 Permukaan Tanggul
Timbunan
12.51 M' 5.55
Hasil Galia

58.00 58.00 0.73

Galian
Galian
56.00 56.00

1.00
54.00 20.00
54.00 20.00

MERAPIKAN0+175 PERMUKAAN 0+175


52.00 TANGGUL 52.00
Bidang persamaan Bidang persamaan
( 5.55 + 0.73 ) level
Reference Reference level
50.00 6.28 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

58.698

56.862

55.986
58.698

56.862

55.986

55.856

55.756

55.208

57.689

57.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20
ELEVASI RENCANA ELEVASI RENCANA

58.698

56.862

55.986
55.208
58.698

56.862

55.986

55.856

55.756

57.689

57.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+200 GALIAN
x y x.y y.x 62.00

0.000 56.485 - 508.365 60.00

9.000 56.124 502.704 948.496


58.00
16.9000 55.8560 941.513 1,232.809
Galian
22.0712 55.7108 1,203.675 1,180.478
56.00
21.1894 54.5360 1,155.585 64.843 1.00

1.189 54.536 67.161 - 54.00 20.00

0.000 56.485
0+200
- - Bidang persamaan
52.00

25.4067 55.6172 1,410.986 1,573.967


Reference level
50.00

28.3000 55.5360 1,577.782 2,054.832 ELEVASI RENCANA


37.0000 55.7520 2,017.832 1,939.785

56.485

55.856

55.536
58.865

56.124
ELEVASI TANAH ASLI
34.7931 54.5360 1,897.477 1,427.752
26.1800 54.5360 1,456.058 1,385.580 J ARAK (m) 8.50 9.00 7.90 11.40

25.4067 55.6172 - -
64.00 64.00

JUMLAH 12,230.772 12,316.907


62.00 62.00

LUAS= x . y- y . x 43.068
60.00 M2 60.00 2.25 2.00 3.75 2.00
2 Batu
+ 58.536
1
58.00 58.00 1.5 1
Batu Uk.> 1.000 Kg
BATU Uk > 1000 Kg 1 1.50
+
x y x.y 56.00
y.x 56.00
+ 56.036
1.5
1 3.97
+ 54.536
0.000 54.536 - 122.706
54.00 54.00 4.70 3.91
2.250 56.036 126.081 238.153
4.250 56.036 0+200
248.778 448.288 0+200
52.00 52.00
Bidang persamaan Bidang persamaan
8.000 58.536 468.288 585.360
Reference level Reference level
10.0000 58.5360 564.497 707.484
50.00 50.00

12.0863 56.4497 673.336


ELEVASI RENCANA
606.558 ELEVASI RENCANA
10.7451 55.7107 612.858 524.739
58.865

56.485

55.856

55.536

55.752
58.865

56.485

55.856
56.124

56.124
9.419 57.036 537.222
ELEVAS I TANAH ASLI 482.182 ELEVASI TANAH ASLI

J ARAK (m) 8.50 J ARAK (m) 9.00 8.50


7.90 9.00 11.40 7.90 8.70 14
ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485

55.856

55.536

55.752
58.865

56.485

55.856
56.124

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 57.036 J ARAK461.047


(m) 268.297 8.50 J ARAK (m) 9.00 8.50
7.90 9.00 11.40 7.90 8.70 14
4.704 54.536 256.537 -
0.000 54.536 - -
Diperiksa :
JUMLAH 3,948.645 3,983.767 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 17.561 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 -60.00


1000 Kg 60.00 2.25 2.00 3.75 2.00
x y x.y y.x
+ 58.536
1
58.00 58.00 1.5
0.000 54.536 - 204.510 1 1.50
1

3.750 57.036 213.885 268.925 Geotextile


+ 56.036
4.715 57.036
56.00 262.673 344.554 56.00
1.5
6.041 55.710 329.452 217.715 1 3.97
+ 54.536
3.908 54.536 213.127 -
54.00 54.00 4.70 3.91
0.000 54.536 - -
0+200 0+200
52.00 52.00
Bidang persamaan Bidang persamaan
Reference levelJUMLAH 1,019.136 1,035.704 Reference level
50.00 50.00

LUAS=
ELEVAS x . y- y . x
I RENCANA 8.284 M2 ELEVASI RENCANA
2

55.856

55.752
58.865

56.485

58.865

56.485

55.536
56.124

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 64.00 8.50 9.00 JARAK (m) 7.90 64.00 8.50 11.40 9.00 8.70 7.90

62.00 62.00

GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 60.00
+ 3.91 + 3.97 ) 60.00 Timbunan
Hasil Galian
12.58 M' 4.54

58.00 58.00 0.64

Galian Galian

56.00 56.00
1.00

54.00 20.00 54.00 20.0

0+200
MERAPIKAN PERMUKAAN TANGGUL 0+200
52.00 52.00
( 4.54
Bidang persamaan + 0.64 ) Bidang persamaan
Reference level Reference level
50.00
5.18 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485
55.856

55.536
58.865

56.485

55.752

57.956
56.124
56.124

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.50 9.00 7.90 J ARAK (m) 11.40 8.50 8.70 9.00 4.00 3.20
ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485
55.856

55.536
58.865

56.485

55.752

57.956
56.124
56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.50 9.00 7.90 J ARAK (m) 11.40 8.50 8.70 9.00 4.00 3.20

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+225 GALIAN
x y x.y y.x 64.00

0.000 56.342 - 653.567 62.00

11.6000 56.1240 648.150 1,178.604


60.00
21.0000 55.8750 1,173.547 1,214.527
21.7365 55.8832 1,192.790 1,173.547 58.00

21.0000 54.8750 1,152.375 80.502 Galian

1.467 54.875 82.654 - 56.00


1.00

0.000 56.342 - - 20.00


54.00

27.9629 55.9523 1,565.531 1,734.521 0+225


52.00
Bidang persamaan
31.0000 55.9860 1,741.084 2,037.890 Reference level
50.00
36.4000 56.1640 2,058.973 2,309.452
ELEVASI RENCANA
41.1198 56.5652 2,256.449 2,303.895

59.685

56.342

55.875

55.986
56.124
40.7299 54.8750 2,235.053 1,580.949 ELEVASI TANAH ASLI

28.8100 54.8750 1,611.986 1,534.464 J ARAK (m) 5.80 11.60 9.40 10.00

27.9629 55.9523 - -

64.00 64.00
JUMLAH 15,718.593 15,801.919

62.00 62.00
LUAS= x . y- y . x 41.663 M2
2 2.25 2.00 3.75 2.00 2.31
60.00 60.00
+ 58.875 Batu Uk. < 250 Kg

BATU Uk > 1000 Kg


1
1.5 1
58.00 58.00 Batu Uk.> 1.000 Kg
1 1.50
x y x.y y.x + 56.565
+ 56.375
56.00 56.00 1.5
1.50 1.73
0.000 54.875 - 123.469 + 54.875 1 + 54.875

2.250 56.375 126.844 239.594


54.00 54.00
4.70 7.22

4.250 56.375 250.219 451.000


0+225 0+225
8.000 58.875 471.000
Bidang persamaan588.750
52.00
Bidang persamaan
52.00

10.0000 58.8750 565.652


Reference level 724.739 Reference level
50.00 50.00
12.3098 56.5652 675.500 674.252
ELEVASI RENCANA ELEVASI RENCANA
11.9199 54.8750 683.904 516.868
59.685

56.342

55.875

55.986

56.865
56.623
59.685

56.342

56.164
56.124

55.875
56.124
9.419 57.375 540.415
ELEVAS I TANAH ASLI485.048 ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60


JARAK (m) 5.80 9.40 11.60 10.00 9.40
5.40 5.40 10.00
2.50
ELEVASI RENCANA ELEVASI RENCANA

59.685

56.342

55.875

55.986

56.865
56.623
59.685

56.342

56.164
56.124

55.875
56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 57.375 J463.913


ARAK (m) 269.892 5.80 11.60
JARAK (m) 5.80 9.40 11.60 10.00 9.40
5.40 5.40 10.00
2.50
4.704 54.875 258.132 -
0.000 54.875 - -
Diperiksa :
JUMLAH 4,035.579 4,073.611 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 19.016 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00
BATU UK 250 - 1000 Kg
x y x.y y.x 2.25 2.00 3.75 2.00
60.00 60.00
+ 58.875
0.000 54.875 - 205.781
1.5
3.750 57.375 58.00 215.156 270.523 58.00 1 1.50
Geotextile
4.715 57.375 258.736 413.961 + 56.375
7.215 54.875 56.00 395.923 - 56.00 1.5
1.50
0.000 54.875 - - + 54.875 1

4.70 7.22
54.00 54.00

0+225 0+225
JUMLAH
Bidang persamaan
52.00 869.815 890.265 Bidang persamaan
52.00

Reference level Reference level


LUAS= x . y- y50.00
.x 10.225 M2 50.00

ELEVASI RENCANA 2 ELEVASI RENCANA

59.685

56.342
56.342

55.986
59.685

55.875

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00
JARAK (m) 5.80 11.60 J ARAK (m) 9.40 5.80 10.00 11.60 5.40 5.40

62.00 62.00
GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 + 7.22
60.00+ 1.73 ) 60.00 Timbunan
13.65 M' 4.84 Hasil Galian

58.00 58.00 2.11

Galian Galian

56.00 56.00
1.00

20.00 20.00
54.00 54.00

0+225
MERAPIKAN PERMUKAAN TANGGUL 0+225
52.00 52.00
( 4.84 +
Bidang persamaan 2.11 ) Bidang persamaan
Reference level Reference level
50.00 6.95 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA


59.685

56.342
59.685

56.865
56.342

55.875

55.986

56.623

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60 9.40 J ARAK (m) 10.00 5.80 5.40 15.40
1.60 2.50
ELEVASI RENCANA ELEVASI RENCANA

59.685

56.342
59.685

56.865
56.342

55.875

55.986

56.623

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60 9.40 J ARAK (m) 10.00 5.80 5.40 15.40
1.60 2.50

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+250 GALIAN
x y x.y y.x
62.00

0.000 55.715 - 473.578


8.500 55.802 475.346 987.695 60.00

17.7000 55.9230 981.555 1,548.748


27.6943 55.4551 1,515.294 1,391.047 58.00

25.0842 54.7150 1,372.482 54.715 Galian

1.000 54.715 55.715 - 56.00


1.00
0.000 55.715
24.19
54.00

0+250
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

59.689

55.923
55.802
55.715
ELEVASI TANAH ASLI

J ARAK (m) 8.30 8.50 9.20 7.70

JUMLAH 4,400.391 4,455.783


64.00 64.00

LUAS= x . y- y . x 27.696 M2
62.00 62.00

2
60.00 60.00 2.25 2.00 3.75 2.00 1.54 2.25 2.00 3.75

BATU Uk > 1000 Kg + 58.715


1
Batu Uk. < 250 Kg +

1.5 1.5
x y x.y y.x 58.00 58.00 Batu Uk.> 1.000 Kg
1
1
+ 57.171
Batu Uk.> 1.000 Kg
1
1.50 1.5
+ 56.215 2.89 + 56.215
56.00 56.00
0.000 54.715 - 123.109
1.41
1.5 1.5
1 1.50 1 1.50
+ 54.715 3.14 + 54.715 3.14
2.250 56.215 126.484 238.914 4.70 6.84 4.70
54.00 54.00
4.250 56.215 249.539 449.720
8.000 58.715 469.720 0+250 587.15052.00
0+250
52.00
Bidang persamaan Bidang persamaan
10.0000 58.7150 571.713Reference level
677.788 Reference level
11.5437 57.1713 653.073 498.534
50.00 50.00

8.720 56.574 492.288


ELEVAS I 413.782
RENCANA ELEVASI RENCANA

7.314 56.455 400.186 265.564

56.261

56.574
59.689

55.802

55.923

56.261
59.689

55.802

55.923
55.715

57.124
55.715

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70 9.20 2.60 7.70 3
ELEVASI RENCANA ELEVASI RENCANA

56.261

56.574
59.689

55.802

55.923

56.261
59.689

55.802

55.923
55.715

57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
4.704 54.715 257.379 -
JARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70 9.20 2.60 7.70 3
0.000 54.715 - -
- -
Diperiksa :
JUMLAH 3,220.381 3,254.561 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 17.090 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
64.00 64.00
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58.

58.00 58.00 1.5


1
Geotextile 1.50
+ 56.215
56.00 56.00
1.5
1 1.50
+ 54.715 3.14

54.00 54.00 4.70

0+250 0+250
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.261
59.689

55.802
59.689

55.923
55.802

55.715
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

64.00 64.00
J ARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70

62.00 62.00

GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 + 3.14 + 1.41 + 2.89 ) 60.00 60.00 Timbunan
Hasil Galian
6.26
12.14 M'
0.97
58.00 58.00

Galian Galian

56.00 56.00
1.00 1.00

24.19 24.19
54.00 54.00

0+250
MERAPIKAN PERMUKAAN TANGGUL
0+250
52.00 52.00
Bidang persamaan Bidang persamaan
( 6.26 + 0.97 ) Reference level Reference level
50.00 7.23 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.261
55.802

55.923
59.689

56.574
55.715

59.689

55.802

55.923
57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 8.50


J ARAK (m) 9.20 8.30 7.70 8.50 3.70 2.60 9.20 7
ELEVASI RENCANA ELEVASI RENCANA

56.261
55.802

55.923
59.689

56.574
55.715

59.689

55.802

55.923
57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 8.50


J ARAK (m) 9.20 8.30 7.70 8.50 3.70 2.60 9.20 7

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+275 GALIAN
x y x.y y.x 62.00

0.000 55.896 - 391.272 60.00


7.000 55.465 391.902 920.719
16.6000 55.9860 936.124 1,198.100 58.00

21.4000 56.3930 1,216.911 1,415.464 Galian


25.1000 56.8650 1,430.564 1,529.589 56.00

26.8986 56.9946 1,465.032 1,316.815 1.00

23.1042 54.4650 1,258.370 77.939 54.00 22.11

1.431 54.465 79.987 -


0+275
0.000 55.896 - - Bidang persamaan
52.00

Reference level
50.00

ELEVASI RENCANA

56.393
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70

64.00
JUMLAH 6,778.891 6,849.899
62.00
LUAS= x . y- y . x 35.504 M2
2 60.00 2.25 2.00 3.75

+ 58.46
BATU Uk > 1000 Kg 58.00
Batu Uk.> 1.000 Kg
x y x.y y.x 1.

+ 55.965
56.00
0.000 54.465 - 122.546 + 54.465
4.56

2.250 55.965 125.921 237.851 54.00 4.70

4.250 55.965 248.476 447.720


0+275
8.000 58.465 467.720 584.650 Bidang persamaan
52.00

10.0000 58.4650 571.944 658.936 Reference level


50.00
11.2706 57.1944 642.357 486.038
8.498 56.994 462.844 268.100 ELEVASI RENCANA

4.704 54.465 256.203 -


59.685

55.465
55.896

55.986

56.393

56.865
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70


ELEVASI RENCANA

59.685

55.465
55.896

55.986

56.393

56.865
ELEVASI TANAH ASLI
0.000 54.465 - -
J ARAK (m) 5.00 7.00 9.60 4.80 3.70

Diperiksa :
JUMLAH 2,775.465 2,805.841 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.188 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58.465
58.00 58.00
1.5
Geotextile
+ 55.965
56.00 56.00
4.56
+ 54.465
54.00 54.00 4.70

0+275 0+275
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

59.685

55.896

55.986

56.865
55.465

56.393
55.465
59.685

55.896
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.00 64.00J ARAK (m) 7.00 5.00 9.60 7.00 4.80 3.70
9.60

62.00
GEOTEXTILE
( 4.70 + 4.56 + 2.78 ) Perapi
Permukaan
60.00
12.04 M'

58.00

Galian
56.00

1.00

54.00 22.11

MERAPIKAN PERMUKAAN TANGGUL 0+275


52.00
Bidang persamaan
( 2.50 ) Reference level
2.50 M' 50.00

ELEVASI RENCANA

56.393

56.865
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70


ELEVASI RENCANA

56.393

56.865
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+300 GALIAN
x y x.y y.x
62.00

0.000 56.143 - 454.758


8.100 55.703 455.973 941.381 60.00

16.9000 56.2930 961.368 1,280.677


22.7502 56.8857 1,290.005 1,108.941 58.00

19.4942 56.7030 1,066.391 81.652 Galian

1.440 54.703 80.846 - 56.00


1.00
0.000 56.143 - -
18.56
54.00

0+300
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.703
59.865

56.293
56.143
ELEVASI TANAH ASLI

J ARAK (m) 4.70 8.10 8.80

JUMLAH 3,854.583 3,867.410 64.00

LUAS= x . y- y . x 6.413 M2 62.00

2
60.00 2.25 2.00 3.75 2.00

+ 58.715
BATU Uk > 1000 Kg 1

58.00 Batu Uk.> 1.000 Kg


x y x.y y.x 1.50
1.
+ 56.215 1.76
56.00
0.000 54.715 - 123.109 + 54.715
3.91

2.250 56.215 126.484 238.914 54.00 4.70

4.250 56.215 249.539 449.720


0+300
8.000 58.715 469.720 587.150 Bidang persamaan
52.00

10.0000 58.7150 580.000 629.131 Reference level


50.00
10.7150 58.0000 611.430 563.180
ELEVASI RENCANA
9.710 57.063 552.353 454.221

55.703

56.293

57.063
59.865

56.143

7.960 56.885 435.531 267.587 ELEVASI TANAH ASLI

J ARAK (m) 4.70 8.10 8.80 7.60


ELEVASI RENCANA

56.293
59.865

55.703

57.063
56.143
ELEVASI TANAH ASLI

4.704 54.715 257.379 - J ARAK (m) 4.70 8.10 8.80 7.60


0.000 54.715 - -

Diperiksa :
JUMLAH 3,282.437 3,313.012 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.288 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00

60.00 2.25 2.00

58.00

Geotextile
+ 56.215
56.00

+ 54.715

54.00 4.70

0+300
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.703
59.865

56.293
56.143
ELEVASI TANAH ASLI
64.00
J ARAK (m) 4.70 8.10 8.80
62.00
GEOTEXTILE
Perapian
( 4.70 + 3.91 + 1.76 + 1.37 ) Permukaan Ta
60.00
11.74 M'

58.00
Galian

56.00
1.00

18.56
54.00

MERAPIKAN PERMUKAAN TANGGUL 0+300


52.00
( 0.72 ) Bidang persamaan
Reference level
0.72 M' 50.00

ELEVASI RENCANA

55.703

56.293
59.865

56.143

ELEVASI TANAH ASLI

JARAK (m) 4.70 8.10 8.80 7.60


ELEVASI RENCANA

55.703

56.293
59.865

56.143
ELEVASI TANAH ASLI

JARAK (m) 4.70 8.10 8.80 7.60

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00

0+325 GALIAN
x y x.y y.x 62.00

60.00
0.000 55.521 - 188.771
3.400 55.814 191.491 753.489 58.00
13.5000 56.3210 766.093 999.365
Galian
17.7441 56.7476 967.426 817.404 56.00

14.4042 54.5210 785.331 54.521 1.00

1.000 54.521 55.521 - 54.00 13.87

0.000 55.521 0+325


52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.521

56.321
59.965

55.814
ELEVASI TANAH ASLI

JARAK (m) 5.60 3.40 10.10 5.70

64.00

JUMLAH 2,765.862 2,813.551


62.00

LUAS= x . y- y . x 23.844 M2
60.00
2 2.25 2.00

58.00
BATU Uk > 1000 Kg Batu Uk.> 1.000 Kg

x y x.y y.x + 56.021


56.00
1.50
0.000 54.521 - 122.672 + 54.521

54.00 4.70
2.250 56.021 126.047 238.089
4.250 56.021 248.714 448.168 0+325
52.00
8.000 58.521 468.168 585.210 Bidang persamaan
Reference level
10.0000 58.5210 570.102 673.624 50.00
11.5108 57.0102 654.895 541.597
ELEVASI RENCANA
9.500 56.894 539.097 457.655

55.521

56.321
59.965

55.814
8.044 56.747 438.567 266.938 ELEVASI TANAH ASLI

J ARAK (m) 5.60 3.40 10.10


ELEVASI RENCANA

55.521

56.321
59.965

55.814
ELEVASI TANAH ASLI

4.704 54.521 256.467 - J ARAK (m) 5.60 3.40 10.10


0.000 54.521 - -

Diperiksa :
JUMLAH 3,302.057 3,333.953 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.948 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58
58.00 58.00

Geotextile
+ 56.021
56.00 56.00
1.50
+ 54.521 4.01

54.00 54.00 4.70

0+325 0+325
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
55.521
59.965

59.965
55.814

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) J ARAK (m) 5.60 3.40 5.6010.10 3.40 5.70

62.00 62.00

GEOTEXTILE Perapian
( 4.70 + 4.01 + 3.43 ) 60.00 60.00 Permukaan Tanggul

12.14 M'
58.00 58.00

Galian Galian

56.00 56.00

1.00 1.00

54.00 54.00 13.87 13.87

MERAPIKAN PERMUKAAN TANGGUL 0+325 0+325


52.00 52.00
( 5.04 + 1.33 ) Bidang persamaan Bidang persamaan
Reference level Reference level
6.37 M'
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
59.965

56.894
55.521
55.814
59.965

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 5.60 10.10 3.40 5.70
10.10
ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
59.965

56.894
55.521
55.814
59.965

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 5.60 10.10 3.40 5.70
10.10

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+350 GALIAN
x y x.y y.x 62.00

0.000 56.135 - 488.375 60.00


8.700 55.278 489.384 856.809
15.5000 56.2510 885.422 1,265.648 58.00

22.5000 57.1240 1,277.505 1,184.420 Galian

20.7342 56.7780 1,125.411 964.329 56.00

16.9842 54.2780 921.868 100.794 1.00

1.857 54.278 104.243 - 54.00


15.99

0.000 56.135 - - 0+350


52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

56.251
60.235

55.278
56.135
ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) 5.60 8.70 6.80 7.00

62.00 62.00

JUMLAH 4,803.833 4,860.375


60.00 60.00
2.25 2.00 3.75 2.00 1.00
LUAS= x . y- y . x 28.271 M2
+ 58.278 1
2 58.00 58.00 1
Batu Uk.> 1.000 Kg
1.50

BATU Uk > 1000 Kg 56.00 56.00 + 55.778


2.60

x y x.y y.x 4.51


1.50
+ 54.278 + 54.2
54.00 54.00
0.000 54.278 - 122.126 4.70 6.30

2.250 55.778 125.501 237.057 0+350 0+350


4.250 55.778 247.682 446.224 Bidang persamaan 52.00 52.00
Bidang persamaan
8.000 58.278 466.224 582.780 Reference level Reference level
50.00 50.00
10.0000 58.2780 572.767 641.134
11.0013 57.2767 628.438 585.368 ELEVASI RENCANA ELEVASI RENCANA

10.2200 57.1240 580.271 482.926

56.251
60.235

55.278
60.235

55.278
56.135

56.135

57.124
8.454 56.778 458.866 267.084 ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) JARAK (m) 5.60 8.70 5.60 6.80 8.70 7.00 6
56.251
60.235

55.278
60.235

55.278
56.135

56.135

57.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

4.704 54.278 255.324 - JARAK (m) JARAK (m) 5.60 8.70 5.60 6.80 8.70 7.00 6
0.000 54.278 - -
- -
Diperiksa :
JUMLAH 3,335.072 3,364.698 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 14.813 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 - 1000 Kg 60.00 60.00


2.25 2.00 3.75 2.00
x y x.y y.x
+ 58.278
58.00 58.00
0.000 0.000 - -
1.50
0.000 0.000 - - Geotextile
0.000 0.000 - - 56.00 56.00 + 55.778

0.000 0.000 - - 1.50 4.51


+ 54.278
0.000 0.000 - -
54.00 54.00
4.70 6.30

0+350 0+350
52.00 52.00
Bidang persamaan Bidang persamaan
JUMLAH - - level
Reference Reference level
50.00 50.00

LUAS= x . y- y . x - M2
ELEVASI RENCANA ELEVASI RENCANA
2

56.251
60.235

55.278
60.235

55.278

56.135
56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 64.00 J ARAK (m) 64.00 5.60 8.70 5.60 6.80 8.70 7.00

62.00 62.00
GEOTEXTILE
Perapi
( 4.70 + 4.51 + 2.60 ) 60.00 60.00 Permukaan

11.81 M'
58.00 58.00

Galian Galian

56.00 56.00

1.00 1.00
54.00 54.00
15.99 15.99

MERAPIKAN PERMUKAAN TANGGUL 0+350 0+350


52.00 52.00
Bidang persamaan Bidang persamaan
( 6.13 )
Reference level Reference level
6.13 M' 50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.251
60.235

55.278

56.251
60.235

55.278
56.135

56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 5.60 8.70 8.70 6.80 6.80 7.00
ELEVASI RENCANA ELEVASI RENCANA

56.251
60.235

55.278

56.251
60.235

55.278
56.135

56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 5.60 8.70 8.70 6.80 6.80 7.00

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME 64.00 64.00 SKET GAMBAR

62.00 62.00
0+375 GALIAN
x y x.y y.x
60.00 60.00

0.000 56.042 - 330.648


58.00 58.00
5.900 55.678 334.860 812.899 Galian Galian
14.6000 56.7560 833.441 1,191.876
56.00 56.00
21.0000 57.0850 1,203.766 1,415.160
1.00 1.00
24.7904 57.3222 1,355.489 1,193.689
54.00 54.00 20.03 20.03
20.8242 54.6780 1,138.626 74.581
1.364 54.678 76.441 - 0+375 0+375
52.00 52.00
0.000 56.042 - - Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANAELEVASI RENCANA

60.325

56.042

55.678

56.756
56.042
60.325

55.678

56.756
ELEVASI TANAH AS
ELEVAS
LI I TANAH ASLI

J ARAK (m)
64.00
J ARAK (m)
64.00
4.70 4.70 5.90 5.90 8.70 8.70 6.40

62.00 62.00
JUMLAH 4,942.624 5,018.852
60.00 60.00 2.25 2.00 3
LUAS= x . y- y . x 38.114 M2
2
58.00 58.00 Batu Uk.> 1.000 Kg

BATU Uk > 1000 Kg + 56.178


56.00 56.00
x y x.y y.x 1.50
+ 54.678 + 54.678

0.000 54.678 - 123.026 54.00 54.00 4.70

2.250 56.178 126.401 238.757


0+375 0+375
4.250 56.178 249.382 449.424 Bidang persamaan
52.00
Bidang persamaan
52.00

8.000 58.678 469.424 586.780 Reference level Reference level


50.00 50.00
10.0000 58.6780 574.803 657.059
11.1977 57.4803 641.875 498.354 ELEVASI RENCANA ELEVASI RENCANA
8.670 57.322 474.058 269.643
60.325

56.042

55.678

57.085
56.756
60.325

56.042

55.678

56.756
4.704 54.678 257.205 - ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 4.70 5.904.70 5.908.70 8.70 6.40


ELEVASI RENCANA ELEVASI RENCANA

60.325

56.042

55.678

57.085
56.756
60.325

56.042

55.678

56.756
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

0.000 54.678 - - J ARAK (m) J ARAK (m) 4.70 5.904.70 5.908.70 8.70 6.40

Diperiksa :
JUMLAH 2,793.147 2,823.042 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 14.947 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00

62.00
BATU UK 250 - 1000 Kg
x y x.y y.x
60.00 2.25 2.0

0.000 0.000 - -
58.00
0.000 0.000 - -
Geotextile
0.000 0.000 - - + 56.178
56.00
0.000 0.000 - - 1.50
+ 54.678
0.000 0.000 - - 4.70
54.00

0+375
52.00
Bidang persamaan
Reference level
JUMLAH - - 50.00

ELEVASI RENCANA

LUAS= x . y- y . x - M2

55.678
60.325

56.042

56.756
ELEVASI TANAH ASLI
2
64.00 J ARAK (m) 64.00 4.70 5.90 8.70 6.40

62.00 62.00

Perapian
Permukaan Tanggul
60.00 60.00
GEOTEXTILE 6.21

( 4.70 +4.77 + 2.52 )


58.00 58.00
11.99 M' Galian

56.00 56.00
1.00 1.00

54.00 20.03
54.00

0+375 0+375
52.00 52.00
Bidang persamaan Bidang persamaan
MERAPIKAN PERMUKAAN
Reference level TANGGUL Reference level
( 6.21 + 0.70 ) 50.00 50.00

ELEVASI RENCANA 6.91 M' ELEVASI RENCANA


60.325

56.042

57.085
55.678

56.756

60.325

56.042

57.523

55.678
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.70 5.90 J ARAK (m) 8.70 6.40 4.70 7.00 5.90
60.325

56.042

55.678

56.756

57.085

57.523
60.325

56.042

55.678
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.70 5.90 J ARAK (m) 8.70 6.40 4.70 7.00 5.90

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

64.00
NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00

0+400 GALIAN 60.00


x y x.y y.x
Galian
58.00
0.000 56.356 - 225.424
4.000 55.806 228.612 569.221 56.00
10.2000 57.1530 587.194 1,400.249 1.00

24.5000 57.5680 1,421.578 1,590.166 54.00 20.76

27.6224 58.0236 1,582.929 1,523.694


0+400
26.2599 57.3060 1,504.850 1,449.509 Bidang persamaan
52.00

25.2942 57.3060 1,386.274 1,234.612 Reference level


50.00
21.5442 54.8060 1,180.751 84.949
1.550 54.806 87.352 - ELEVASI RENCANA

0.000 56.356 - -

59.368

56.356

55.806

57.153
ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) 7.90 4.00 6.20 14.30

62.00 62.00

60.00 60.00 2.25 2.00 3.75 2.00 0.7


Ba
JUMLAH 7,979.540 8,077.825 + 58.806 1 +5
1
58.00 58.00 Batu Uk.> 1.000 Kg
1.50
LUAS= x . y- y . x 49.142 M2 1.54
2 + 56.306 0.97
56.00 56.00
1.50 4.51
BATU Uk > 1000 Kg + 54.806

x y x.y
54.00 y.x 54.00 4.70

0.000 0+400
54.806 - 123.314 0+400
2.250 56.306 52.00
126.689 239.301 52.00
Bidang persamaan Bidang persamaan
4.250 56.306
Reference level 249.926 450.448 Reference level
8.000 58.806 50.00
470.448 588.060 50.00

10.0000ELEVAS
58.8060
I RENCANA
580.236 634.070 ELEVASI RENCANA
10.7824 58.0236 617.896 546.524
55.806
59.368

56.356

57.568

55.806
59.368

56.356
57.153
9.419 ELEVAS
57.306
I TANAH ASLI
539.765 484.465 ELEVASI TANAH ASLI
8.454 57.306 463.330 269.567
J ARAK (m) 7.90 4.00J ARAK (m) 6.20 14.30
7.90 4.00 6.106
55.806
59.368

56.356

57.568

55.806
59.368

56.356
57.153
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

4.704 J ARAK
54.806
(m) 257.807 - 7.90 4.00J ARAK (m) 6.20 14.30
7.90 4.00 6.106
0.000 54.806 - -

Diperiksa :
JUMLAH 3,306.097 3,335.748 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 14.826 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 - 1000 Kg 60.00 60.00 2.25 2.00 3.75

x y x.y y.x + 58.80

58.00 58.00
1.5
0.000 0.000 - - Geotextile
+ 56.306
0.000 0.000 - - 56.00 56.00
0.000 0.000 - - + 54.806
1.50 4.51

0.000 0.000 - - 4.70


54.00 54.00
0.000 0.000 - -
0+400 0+400
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00
JUMLAH - -
ELEVASI RENCANA ELEVASI RENCANA

LUAS= x . y- y . x - M2

55.806
59.368

56.356

55.806
59.368

56.356

57.568
57.153

57.153
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
2
64.00
J ARAK (m) JARAK (m) 7.90 64.00
4.00 6.20
7.90 4.00 14.30 6.20

62.00 62.00

Perapian
Permukaan Tanggul
60.00 60.00
GEOTEXTILE
3.57
( 4.70 + 4.51 + 0.97 + 1.54 )
Galian
58.00 11.72 M' 58.00

56.00 56.00
1.00 1.00

54.00 54.00 20.76

0+400 0+400
MERAPIKAN PERMUKAAN
BidangTANGGUL
persamaan
52.00
Bidang persamaan
52.00

( 3.57 +0.39 ) Reference level Reference level


50.00 50.00
3.96 M'
ELEVASI RENCANA ELEVASI RENCANA
56.356

55.806
59.368

59.368

56.356

55.806

57.568
57.153

57.153
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 7.90 J ARAK4.00


(m) 6.20 7.90 14.30 4.00 6.20 6.10
ELEVASI RENCANA ELEVASI RENCANA

56.356

55.806
59.368

59.368

56.356

55.806

57.568
57.153

57.153
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 7.90 J ARAK4.00


(m) 6.20 7.90 14.30 4.00 6.20 6.10

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
NGAN VOLUME

SKET GAMBAR

Galian Galian

20.00 14.00
54.369

53.485

53.778

56.365

57.124
60 15.90 15.70 4.40 12.40

2.25 2.00 3.75 2.00 4.00

56.4850
Batu Uk. < 250 Kg
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

53.9850

1.5
1.50
1
52.4850

4.70 7.22 2.08


53.778

56.365

57.124

15.70 4.40 12.40


53.778

56.365

57.124
15.70 4.40 12.40

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

56.4850
Batu Uk. < 250 Kg
1.5 1
1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
53.9850

1.5
1.50
1
52.4850

4.70 7.22 2.08


53.485

53.778

56.365

57.124
15.70 4.40 12.40

Perapian
Permukaan Tanggul Timbunan
Hasil Galian
4.00

Galian
53.778

56.365

57.124

15.70 4.40 12.40


53.778

56.365

57.124
15.70 4.40 12.40

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

20.00
14.00
52.923

53.938

53.939

52.923
53.923

53.968

54.402

57.264
54.123

11.50 11.30 13.30 8.80 7.30

2.25 2.00 3.75 2.00 4.00

+ 56.923
Batu Uk. < 250 Kg
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 54.423
1.5
1.50
+ 52.9231

4.70 7.22 2.08


53.968

54.402

57.264

13.30 8.80 7.30


53.968

54.402

57.264
13.30 8.80 7.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

+ 56.923
Batu Uk. < 250 Kg
1.5 1
1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
+ 54.423
1.5
1.50
1.00 + 52.9231

4.70 7.22 2.08


53.923

53.968

54.402

57.264
13.30 8.80 7.30

Perapian
Permukaan Tanggul Timbunan
Hasil Galian

13.16

alian Galian

14.00
53.938

53.939

52.923
53.923

53.968

54.402

57.264

13.30 8.80 7.30


53.93
53.93

52.92
53.923

53.968

54.402

57.264
13.30 8.80 7.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

20.00 14.00
54.235

53.768

54.324
54.124

57.172
11.10 13.50 11.70 14.80 2.50

2.25 2.00 3.75 2.00 4.00

+ 56.768
Batu Uk. < 250 Kg
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 54.268
1.5
1.50
1 1.00
+ 52.768

4.70 7.22 2.08


53.768

54.324

57.172

11.70 14.80 2.50


53.768

54.324

57.172
11.70 14.80 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

+ 56.768
Batu Uk. < 250 Kg
1.5 1
1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
+ 54.268
1.5
1.50
1 1.00
+ 52.768

4.70 7.22 2.08


53.768

54.324

57.172
54.124

11.70 14.80 2.50

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
8.85

Galian
54.324
53.768
54.124

57.172

11.70 14.80 2.50


54.324
53.768
54.124

57.172
11.70 14.80 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 14.00

56.801
54.098

54.832

54.542
54.123
12.80 9.20 15.10 14.90 0.90

2.25 2.00 3.75 2.00 4.00

+ 57.098
Batu Uk. < 250 Kg
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 54.598
1.5
1.50
1
+ 53.098

4.70 7.22 2.08


56.801
54.542
54.123

15.10 14.90 0.90 3.80


56.801
54.542
54.123
15.10 14.90 0.90 3.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

+ 57.098
Batu Uk. < 250 Kg
1.5 1
1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
+ 54.598
1.5
1.50
1
+ 53.098

4.70 7.22 2.08

56.801
54.832

54.542
54.123

15.10 14.90 0.90 3.80

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
7.35
0.42

Galian
56.801
54.542
54.123

15.10 14.90 0.90 3.80


56.801
54.542
54.123
15.10 14.90 0.90 3.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 14.00
55.342

57.386
55.326

55.192

54.714
11.20 11.90 5.50 22.70 2.20

2.25 2.00 3.75 2.00 4.00

+ 57.714
Batu Uk. < 250 Kg
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 55.214
1.5
1.50
1
+ 53.714

4.70 7.22 2.08


57.386
55.192

54.714

5.50 22.70 2.20


57.386
55.192

54.714
5.50 22.70 2.20

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

+ 57.714

1.5 1 Batu Uk. < 250 Kg


1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
+ 55.214
1.5
1.50
1
+ 53.714

4.70 7.22 2.08


55.342

57.386
54.714
55.192

5.50 22.70 2.20

Timbunan
Perapian Hasil Galian
Permukaan Tanggul

8.12

0.36

an Galian

1.00
55.342

57.386
55.192

54.714

5.50 22.70 2.20 3.50


55.342

57.386
55.192

54.714
5.50 22.70 2.20 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 11.54
55.552

55.442

57.992
54.856

58.034
55.124

55.182
15.90 9.30 9.90 5.80 1.40 3.90
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 57.856
Batu Uk. < 250 Kg
1.5 1
1 1.50 1Batu Uk. 250 - 1.000 Kg
Geotextile
+ 55.356 + 55.498

1.5
+ 53.856 1 1.83

11.54
55.442

54.856

57.992

58.034
55.124

55.182
9.30 9.90 5.80 1.40 3.90

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
3.53

Galian

1.00
58.034
54.856

57.992
55.442

55.124

55.182

9.30 9.90 5.80 1.40 3.90


58.034
54.856

57.992
55.442

55.124

55.182
9.30 9.90 5.80 1.40 3.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 10.54

55.308
55.673

55.436

56.978
55.563

12.00 6.30 10.20 11.60 1.90

2.25 2.00 3.75 2.00

+ 58.308 Batu Uk. < 250 Kg

1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 55.808 + 55.925

1.5
1 2.45
+ 54.308

10.54
55.308

56.978
55.673

55.436

57.012

6.30 10.20 11.60 1.90 5.60


55.308

56.978
55.673

55.436

57.012
6.30 10.20 11.60 1.90 5.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.308
Batu Uk. < 250 Kg
1.5 1
1 1.50 1 Batu Uk. 250 - 1.000 Kg
Geotextile
+ 55.808 + 55.925

1.5
1 2.45
+ 54.308

10.54
55.673

55.308

56.978
55.436

57.012
10.20 11.60 1.90 5.60

Perapian
Permukaan Tanggul
Timbunan
8.26 Hasil Galian

1.59

Galian

1.00
55.308
55.436

56.978
55.673

57.012

10.20 11.60 1.90 5.60


55.308
55.436

56.978
55.673

57.012
10.20 11.60 1.90 5.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 8.91

55.208
56.862

55.986

55.856

55.756

57.689
6.00 8.40 9.20 9.60 9.30 2.70

2.25 2.00 3.75 2.00

+ 58.208 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 + 56.645

+ 55.708
1.5
1 3.60
+ 54.208
8.91
55.208
55.856

55.756

57.689

57.865

9.20 9.60 9.30 2.70 3.50


55.208
55.856

55.756

57.689

57.865
9.20 9.60 9.30 2.70 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.208
1
1.5 1 Batu Uk. 250 - 1.000 Kg
1 1.50 + 56.645
Geotextile
+ 55.708 Batu Uk. < 250 Kg
1.5
1 3.60
+ 54.208
8.91

55.208

57.689

57.865
55.856

55.756

9.20 9.60 9.30 2.70 3.50

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
5.55
0.73

Galian

1.00
55.856

55.756

55.208

57.689

57.865

9.60 9.30 2.70 3.50


55.208
55.856

55.756

57.689

57.865
9.60 9.30 2.70 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 8.61
56.485

55.856

55.536

55.752

57.956
56.124

8.50 9.00 7.90 11.40 8.70 4.00

2.25 2.00 3.75 2.00

+ 58.536 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50
+ 56.450
+ 56.036
1.5
1 3.97
+ 54.536 56.450
4.70 3.91
55.856

55.536

55.752

57.956

57.996

7.90 11.40 8.70 4.00 3.20


55.856

55.536

55.752

57.956

57.996
7.90 11.40 8.70 4.00 3.20

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.536
1 Batu Uk. < 250 Kg
1.5 1 Batu Uk. 250 - 1.000 Kg
1 1.50
Geotextile + 56.450
+ 56.036
1.5
1 3.97
+ 54.536 56.450
4.70 3.91
55.856

55.752

57.956

57.996
55.536

90 11.40 8.70 4.00 3.20

Perapian
Permukaan Tanggul
Timbunan
4.54 Hasil Galian

0.64

lian Galian

1.00
55.536

55.752

57.956

57.996

11.40 8.70 4.00 3.20


55.536

55.752

57.956

57.996
11.40 8.70 4.00 3.20

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 11.92
56.342

55.875

55.986

56.623

56.865
56.164
56.124

11.60 9.40 10.00 5.40 5.40 2.50

2.25 2.00 3.75 2.00 2.31

+ 58.875 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50
+ 56.565
+ 56.375
1.5
1.50 1.73
+ 54.875 1

4.70 7.22
55.875

55.986

56.865
56.623
56.164

9.40 10.00 5.40 5.40 2.50


55.875

55.986

56.865
56.623
56.164
9.40 10.00 5.40 5.40 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 2.31

+ 58.875 Batu Uk. < 250 Kg


1
1.5 1
1 Batu Uk. 250 - 1.000 Kg
1.50
Geotextile + 56.565
+ 56.375
1.5
1.50 1.73
+ 54.875 1

4.70 7.22
55.986

56.865
55.875

56.623
56.164

9.40 10.00 5.40 5.40 2.50

Perapian
Permukaan Tanggul
Timbunan
4.84 Hasil Galian

2.11
Galian

1.00
56.865
55.875

55.986

56.623
56.164

10.00 5.40 5.40 2.50


56.865
55.875

55.986

56.623
56.164
10.00 5.40 5.40 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

24.19

56.261
55.923

56.574
55.802
55.715

57.124
8.30 8.50 9.20 7.70 3.70 2.60
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.54

+ 58.715
1
1.5 1
1
+ 57.171
Geotextile 1.50
+ 56.215 2.89
1.5 1.41
1 1.50
+ 54.715 3.14

4.70 6.84

56.261
55.923

56.574
55.802

57.124
8.50 9.20 7.70 3.70 2.60

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
6.26

0.97

Galian

24.19
56.261
55.923

56.574

57.124

9.20 7.70 3.70 2.60


56.261
55.923

56.574

57.124
9.20 7.70 3.70 2.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

22.11

56.393

57.283
59.685

55.896

55.465

55.986

56.865
5.00 7.00 9.60 4.80 3.70 5.80

2.25 2.00 3.75 2.00 1.27

+ 58.465 Batu Uk. < 250 Kg


1
Batu Uk.> 1.000 Kg 1 + 57.194
1.50
2.78
+ 55.965

4.56
+ 54.465

4.70
55.465
55.896

55.986

56.393

56.865

57.283

5.00 7.00 9.60 4.80 3.70 5.80


55.465
55.896

55.986

56.393

56.865

57.283
5.00 7.00 9.60 4.80 3.70 5.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.27

+ 58.465
1
1 + 57.194
1.50
Geotextile 2.78
+ 55.965

4.56
+ 54.465

4.70
55.986

56.865

57.283
55.465

56.393

7.00 9.60 4.80 3.70 5.80

Perapian
Permukaan Tanggul
Timbunan
2.50 Hasil Galian

Galian

1.00

22.11
56.393

56.865

57.283
55.896

55.465

55.986

5.00 7.00 9.60 4.80 3.70 5.80


56.393

56.865

57.283
55.896

55.465

55.986
5.00 7.00 9.60 4.80 3.70 5.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

64.00

62.00

60.00

58.00
Galian

56.00
1.00

18.56
54.00

0
52.00
maan
l
50.00

A
55.703

58.000
59.865

56.293

57.063
56.143

ASLI

4.70 8.10 8.80 7.60

.00

.00

.00 2.25 2.00 3.75 2.00

+ 58.715 Batu Uk. < 250 Kg


1
1+ 58.000
.00 Batu Uk.> 1.000 Kg
1.50
1.37
+ 56.215 1.76
.00
3.91
+ 54.715

.00 4.70

.00

00
55.703

56.293

57.063

58.000
59.865

56.143

4.70 8.10 8.80 7.60


56.293

58.000
59.865

55.703

57.063
56.143
4.70 8.10 8.80 7.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.715
1
1+ 58.000
1.50
Geotextile 1.37
+ 56.215 1.76

3.91
+ 54.715

4.70
55.703

57.063
59.865

56.293

58.000
56.143

4.70 8.10 8.80 7.60

Perapian
Permukaan Tanggul Timbunan
Hasil Galian
0.72

Galian

1.00

18.56
58.000
55.703

56.293

57.063
59.865

56.143

4.70 8.10 8.80 7.60


55.703

57.063

58.000
56.293
59.865

56.143
4.70 8.10 8.80 7.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

13.87
55.521

56.321
59.965

56.894

57.235
55.814

5.60 3.40 10.10 5.70 5.90

2.25 2.00 3.75 2.00 1.51

+ 58.521 Batu Uk. < 250 Kg


1
Batu Uk.> 1.000 Kg 1 + 57.010
1.50

+ 56.021 3.43

1.50
+ 54.521 4.01

4.70 6.81
55.521

56.321

57.235
59.965

56.894
55.814

5.60 3.40 10.10 5.70 5.90


55.521

56.321

57.235
59.965

56.894
55.814
5.60 3.40 10.10 5.70 5.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.51

+ 58.521
1
1 + 57.010
1.50
Geotextile
+ 56.021 3.43

1.50
+ 54.521 4.01

4.70 6.81
55.521

56.321

57.235
59.965

56.894
55.814

5.60 3.40 10.10 5.70 5.90

Perapian
Permukaan Tanggul
Timbunan
5.04 Hasil Galian

1.33

Galian

1.00

13.87
55.521

56.321
59.965

56.894

57.235
55.814

5.60 3.40 10.10 5.70 5.90


55.521

56.321
59.965

56.894

57.235
55.814
5.60 3.40 10.10 5.70 5.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

15.99

56.251
60.235

55.278

58.355
57.124
56.135

5.60 8.70 6.80 7.00 6.30

2.25 2.00 3.75 2.00 1.00

+ 58.278 Batu Uk. < 250 Kg


1
1 + 57.277
Batu Uk.> 1.000 Kg
1.50
2.60
+ 55.778

1.50 4.51
+ 54.278

4.70 6.30
56.251
55.278

58.355
56.135

57.124

5.60 8.70 6.80 7.00 6.30


56.251
55.278

58.355
56.135

57.124
5.60 8.70 6.80 7.00 6.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.00

+ 58.278 1
1 + 57.277
1.50
Geotextile 2.60
+ 55.778

1.50 4.51
+ 54.278

4.70 6.30
56.251
55.278

58.355
56.135

57.124
8.70 6.80 7.00 6.30

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
6.13

Galian

1.00

15.99
56.251
60.235

55.278

58.355
56.135

57.124

5.60 8.70 6.80 7.00 6.30


56.251
60.235

55.278

58.355
56.135

57.124
5.60 8.70 6.80 7.00 6.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

20.03
60.325

56.042

57.085
55.678

56.756

57.523
4.70 5.90 8.70 6.40 7.00

2.25 2.00 3.75 2.00 1.20

+ 58.678 Batu Uk. < 250 Kg


1
1
Batu Uk.> 1.000 Kg + 57.480
1.50
2.53
+ 56.178

1.50 4.77
+ 54.678

4.70 6.49
56.042

55.678

57.085
56.756

57.523

4.70 5.90 8.70 6.40 7.00


56.042

55.678

57.085
56.756

57.523
4.70 5.90 8.70 6.40 7.00

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.20

+ 58.678 1
1
1.50 + 57.480
Geotextile 2.53
+ 56.178

1.50 4.77
+ 54.678

4.70 6.49
55.678
60.325

56.042

56.756

57.085

57.523
4.70 5.90 8.70 6.40 7.00

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
6.21

0.70

Galian

1.00

20.03
57.085
55.678

56.756

57.523

58.000

8.70 6.40 7.00


55.678

56.756

57.085

57.523

58.000
8.70 6.40 7.00

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

20.76

58.458
59.368

56.356

55.806

57.568
57.153

7.90 4.00 6.20 14.30 6.10

2.25 2.00 3.75 2.00 0.78


Batu Uk. < 250 Kg
+ 58.806 1 + 58.024
1
Batu Uk.> 1.000 Kg
1.50
1.54
+ 56.306 0.97

1.50 4.51
+ 54.806

4.70
57.568

58.458
57.153

6.20 14.30 6.10


57.568

58.458
57.153
6.20 14.30 6.10

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 0.78

+ 58.806 1 + 58.024
1
1.50
Geotextile 1.54
+ 56.306 0.97

1.50 4.51
+ 54.806

4.70
56.356

55.806

57.568

58.458
57.153

4.00 6.20 14.30 6.10

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
3.57
0.39
Galian

00

20.76
58.458
57.568
57.153

6.20 14.30 6.10


58.458
57.568
57.153
6.20 14.30 6.10

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

P.0 20.773
25.00 20.773 519.33
P.1 20.773 - -
25.00 20.773 519.33
P.2 20.773 - -
25.00 20.773 519.33
P.3 20.773 - -
25.00 20.773 519.33
P.4 20.773 - -
25.00 19.787 494.68
P.5 18.801 - -
25.00 18.611 465.27
P.6 18.421
25.00 17.581 439.52
P.7 16.741
25.00 17.151 428.77
P.8 17.561
25.00 18.288 457.20
P.9 19.015
25.00 18.053 451.32
P.10 17.090
25.00 16.139 403.46
P.11 15.187
25.00 15.237 380.92
P.12 15.287
25.00 15.617 390.42
P.13 15.947
25.00 15.380 384.50
P.14 14.814
25.00 14.880 372.01
P.15 14.947
25.00 14.887 372.18
P.16 14.827
SUB TOTAL 400.00 7,117.57

TOTAL 400.00 7,117.57

Diperiksa : Dihitung Oleh :


Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Timbunan Hasil Galian, Diratakan dan dirapikan (AB)


JARAK Timbunan Hasil Galian, Diratakan dan dirapikan (AB)
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

P.0 Err:509
25.00 Err:509 Err:509
P.1 Err:509 - -
25.00 Err:509 Err:509
P.2 Err:509 - -
25.00 Err:509 Err:509
P.3 Err:509 - -
25.00 Err:509 Err:509
P.4 Err:509 - -
25.00 Err:509 Err:509
P.5 Err:509 - -
25.00 Err:509 Err:509
P.6 Err:509 - -
25.00 Err:509 Err:509
P.7 Err:509 - -
25.00 Err:509 Err:509
P.8 Err:509 - -
25.00 Err:509 Err:509
P.9 Err:509 - -
25.00 Err:509 Err:509
P.10 Err:509 - -
25.00 Err:509 Err:509
P.11 Err:509 - -
25.00 Err:509 Err:509
P.12 Err:509 - -
25.00 Err:509 Err:509
P.13 Err:509 - -
25.00 Err:509 Err:509
P.14 Err:509 - -
25.00 Err:509 Err:509
P.15 Err:509 - -
25.00 Err:509 Err:509
P.16 Err:509 - -
SUB TOTAL 400.00 Err:509

TOTAL 400.00 Err:509


Err:509
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
#REF!
#REF!
#REF!

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Galian Tanah Berpasir (AB)


JARAK Galian Tanah Berpasir (AB)
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

P.0 Err:509
25.00 Err:509 Err:509
P.1 Err:509 - -
25.00 Err:509 Err:509
P.2 Err:509 - -
25.00 Err:509 Err:509
P.3 Err:509 - -
25.00 Err:509 Err:509
P.4 0.250 - -
25.00 0.250 6.25
P.5 0.250 - -
25.00 0.250 6.25
P.6 0.250 - -
25.00 0.250 6.25
P.7 0.250 - -
25.00 0.250 6.25
P.8 0.250 - -
25.00 0.250 6.25
P.9 0.250 - -
25.00 0.250 6.25
P.10 0.250 - -
25.00 0.250 6.25
P.11 0.250 - -
25.00 0.250 6.25
P.12 0.250 - -
25.00 0.250 6.25
P.13 0.250 - -
25.00 0.250 6.25
P.14 0.250 - -
25.00 0.250 6.25
P.15 0.250 - -
25.00 0.250 6.25
P.16 0.250 - -
SUB TOTAL 400.00 Err:509

TOTAL 400.00 Err:509


Err:509
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

P.0 Err:509
25.00 Err:509 Err:509
P.1 Err:509 - -
25.00 Err:509 Err:509
P.2 Err:509 - -
25.00 Err:509 Err:509
P.3 Err:509 - -
25.00 Err:509 Err:509
P.4 13.500 - -
25.00 13.500 337.50
P.5 13.500 - -
25.00 13.500 337.50
P.6 13.500 - -
25.00 13.500 337.50
P.7 13.500 - -
25.00 13.500 337.50
P.8 13.500 - -
25.00 13.500 337.50
P.9 13.500 - -
25.00 13.500 337.50
P.10 13.500 - -
25.00 13.500 337.50
P.11 13.500 - -
25.00 13.500 337.50
P.12 13.500 - -
25.00 13.500 337.50
P.13 13.500 - -
25.00 13.500 337.50
P.14 13.500 - -
25.00 13.500 337.50
P.15 13.500 - -
25.00 Err:509 Err:509
P.16 Err:509 - -
SUB TOTAL 400.00 Err:509

TOTAL 400.00 Err:509


2,384.00
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Pemasangan Batu Uk. < 250 Kg


JARAK Pemasangan Batu Uk. < 250 Kg
PROFIL LEBAR LEBAR RATA2 LUAS KET
M' M' M2 M2

P.0 Err:509
25.00 Err:509 Err:509
P.1 Err:509 - -
25.00 Err:509 Err:509
P.2 Err:509 - -
25.00 Err:509 Err:509
P.3 Err:509 - -
25.00 Err:509 Err:509
P.4 Err:509 - -
25.00 Err:509 Err:509
P.5 Err:509 - -
25.00 Err:509 Err:509
P.6 13.000 - -
25.00 13.000 325.00
P.7 13.000 - -
25.00 13.000 325.00
P.8 13.000 - -
25.00 13.000 325.00
P.9 13.000 - -
25.00 13.000 325.00
P.10 13.000 - -
25.00 13.000 325.00
P.11 13.000 - -
25.00 13.000 325.00
P.12 13.000 - -
25.00 13.000 325.00
P.13 13.000 - -
25.00 13.000 325.00
P.14 13.000 - -
25.00 13.000 325.00
P.15 13.000 - -
25.00 13.000 325.00
P.16 13.000 - -
SUB TOTAL 400.00 Err:509

TOTAL 400.00 Err:509


-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL PANJANG PANJANG RATA2 LUAS KET
M' M' M' M2

P.0 1.900
25.00 2.350 58.75
P.1 2.800 - -
25.00 Err:509 Err:509
P.2 Err:509 - -
25.00 Err:509 Err:509
P.3 Err:509 - -
25.00 Err:509 Err:509
P.4 Err:509 - -
25.00 Err:509 Err:509
P.5 Err:509 - -
25.00 Err:509 Err:509
P.6 Err:509 - -
25.00 Err:509 Err:509
P.7 Err:509 - -
25.00 Err:509 Err:509
P.8 Err:509 - -
25.00 Err:509 Err:509
P.9 Err:509 - -
25.00 Err:509 Err:509
P.10 Err:509 - -
25.00 Err:509 Err:509
P.11 Err:509 - -
25.00 Err:509 Err:509
P.12 Err:509 - -
25.00 Err:509 Err:509
P.13 Err:509 - -
25.00 Err:509 Err:509
P.14 Err:509 - -
25.00 Err:509 Err:509
P.15 Err:509 - -
25.00 Err:509 Err:509
P.16 Err:509 - -
SUB TOTAL 400.00 Err:509
TOTAL 400.00 Err:509
DIAMBIL HASIL 1,454.75
-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00 1,454.75
- Err:509

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Galian Tanah Biasa, Diratakan dan dirapikan (AB) Normalisasi


JARAK Galian Tanah Biasa, Diratakan dan dirapikan (AB)
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

Pn.0 #REF! - -
25.00 #REF! #REF!
Pn.1 #REF! - -
16.50 #REF! #REF!
Pn.2 #REF! - -
#REF! #REF!
Pn.3 #REF! - -
#REF! #REF!
Pn.4 #REF! - -
#REF! #REF!
Pn.5 #REF! - -
#REF! #REF!
Pn.6 #REF! - -
#REF! #REF!
Pn.7 #REF! - -
#REF! #REF!
Pn.8 #REF! - -
#REF! #REF!
Pn.9 #REF! - -
#REF! #REF!
Pn.10 #REF! - -
#REF! #REF!
Pn.11 #REF! - -
#REF! #REF!
Pn.12 #REF! - -
#REF! #REF!
Pn.13 #REF! - -
#REF! #REF!
Pn.14 #REF! - -
#REF! #REF!
Pn.15 #REF! - -
#REF! #REF!
Pn.16 #REF! - -
-
SUB TOTAL 41.50 #REF!
TOTAL 41.50 #REF!
-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
PERHITUNGAN VOLUME

PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
BIDANG : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NO SKET GAMBAR PERHITUNGA

TYPIKAL BRONJONG
TIMBUNAN HASIL GALIAN
DIRATAKAN DAN DIRAPIKAN
1.00

0.50 0.50

0.50
1.50
1.50

Batu Kosong

7.00
Geotextile

JALUR
URAIAN PEKERJAAN SAT JALUR KIRI
NORMALISASI
400.00 m 41,50 m
I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 -
2 Pembersihan lapangan m2 1,454.75

II. PEKERJAAN POKOK


1 Galian Tanah Biasa, Diratakan dan dirapikan (AB) m3 7,117.57 #REF!
2 Pasangan Batu Kosong m3 Err:509
3 Pasangan Bronjong Dia. 3 mm, Uk. 2,0 x 1,0 x 0,50 m (Pabrikasi) m3 Err:509
4 Pemasangan Geotextile (Non Wooven) m2 Err:509
5 Pemancangan Kayu Cerucuk Dia.8- 10 Cm m -

Diperiksa :
PENGAWAS PEKERJAAN Kontr
PT. BINA

Yusrin, ST T. A
Team Leader Si
PERHITUNGAN VOLUME

PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
BIDANG : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NO SKET GAMBAR PERHITUNGA

TYPIKAL BRONJONG A. TANGGUL BRONJONG (JALUR KIRI)


L= 400.00 M

I.2 Err:509
Sesuai Tabel perhit. Volume

II.1 Err:509
TIMBUNAN HASIL GALIAN
DIRATAKAN DAN DIRAPIKAN

Sesuai Tabel perhit. Volume


1.00

0.50 0.50

II.2 Galian Tanah Berpasir (AB)


Sesuai Tabel perhit. Volume
0.50

1.50
1.50

Batu Kosong
II.3 Err:509
Geotextile 7.00

Sesuai Tabel perhit. Volume

II.4 Pemasangan Batu Uk. < 250 Kg

Sesuai Tabel perhit. Volume

TYPIKAL NORMALISASI B. NORMALISASI DAN TIMBUNAN HASIL


L= 41.50 M

1 Galian Tanah Biasa, Diratakan dan dirap


GALIAN Sesuai Tabel perhit. Volume

Timbunan hasil galian (dihitung)


1.20 6.37 20.99 3.99 5.00 1.00 6.01
2 Galian Tanah Biasa, Diratakan dan dirap
Sesuai Tabel perhit. Volume
63.381
64.832

64.470

63.805

63.779
65.370

66.269

66.644
64.301

62.266

62.266

63.779

3 Bronjong ujung P.0


Sesuai Tabel perhit. Volume

4 Bronjong ujung P.16


Sesuai Tabel perhit. Volume

5 Pemasangan Geotextile (Non Wooven)

Sesuai Tabel perhit. Volume

Diperiksa :
PENGAWAS PEKERJAAN Kontr
PT. BINA

Yusrin, ST T. A
Team Leader Si
PERHITUNGAN VOLUME

PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
BIDANG : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NO SKET GAMBAR PERHITUNGA

GAMBAR TYPIKAL BRONJONG


A. PENAMPANG TYPIKAL BRONJONG
L= 400.00 M
1.00

LAPIS 1 = 1,00 X 0,50 X 1


LAPIS 2 = 2,00 X 0,50 X 1
0.50

LAPIS 3 = 3,00 X 0,50 X 1


0.50

Bronjong Kawat Dia. 3 mm Uk,

0.50
1x2x0,5 m (Pabrikasi) LAPIS 4 = 4,00 X 0,50 X 1
LAPIS 5 = 5,00 X 0,50 X 1
1.50
LAPIS 6 = 5,00 X 0,50 X 1
Batu Kosong
LAPIS 7 = 7,00 X 0,50 X 1
0.50

0.50

7.00

Geotextile

B. BATU KOSONG PADA BRONJONG TYPE


L= 400.00 M

( 0,5 x 0,5 )

Diperiksa :
PENGAWAS PEKERJAAN Kontr
PT. BINA

Yusrin, ST T. A
Team Leader Si
S ACEH)

HITUNGAN VOLUME

1.50

BRONJONG
VOLUME KET
PENUTUP

1.00
1,454.75

#REF!
Err:509
Err:509 Err:509
Err:509 Err:509
-

Dihitung :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
S ACEH)

HITUNGAN VOLUME

KIRI)

= 1,454.75 m2

= 7,117.57 m3

= Err:509 m3

= Err:509 m3

= Err:509 m2

N HASIL GALIAN

dan dirapikan (AB)


= #REF! m3

dan dirapikan (AB)


= m3

= Err:509 m3

= Err:509 m3

Wooven)

= Err:509 m2

Dihitung :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
S ACEH)

HITUNGAN VOLUME

= 0.50 m2
= 1.00 m2
= 1.50 m2
= 2.00 m2
0X1 = 2.50 m2
0X1 = 2.50 m2
= 3.50 m2
= 13.50 m2

ONG TYPE PYRAMID

= 0.25
= 0.25 m2

Dihitung :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
PER
PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTS
LOKASI : KABUPATEN ACEH BESAR
BIDANG : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

KONTRAK
NO URAIAN KEGIATAN SAT VOLUME HARGA SATUAN
Rp

I. PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 50,000,000.00

II. PEKERJAAN POKOK


1 Galian Tanah Berpasir (AB) m3 5,526.30 18,385.00

2 Pemasangan Batu Uk. < 250 Kg m3 6,566.13 411,270.00

3 Pemasangan Batu Uk. > 1.000 Kg m3 14,544.70 491,026.00

4 Pemasangan Geotekstil ( Non Wooven ) m2 10,349.24 52,946.00

JUMLAH
PPN 10 %
TOTAL
DIBULATKAN

#REF! TIM MUTUAL CHE


NO

Mengetahui / Menyetujui:
Pejabat Pelaksana Teknis Kegiatan
Pembangunan Prasarana Pengaman Pantai
DINAS PENGAIRAN PROV. ACEH CV. FREE
Muhammad Nasir, ST
Nip. 19660323 199211 1 001
PERHITUNGAN MC-0
CEH BESAR (OTSUS ACEH)

KONTRAK MC-0 DEVIASI


JUMLAH HARGA VOLUME HARGA SATUAN JUMLAH HARGA VOLUME HARGA SATUAN
Rp Rp Rp Rp

50,000,000.00 50,000,000.00 400.00

50,000,000.00 1.00 50,000,000.00 50,000,000.00 - 50,000,000.00

10,491,830,033.84 12,432,541,284.51

101,601,025.50 - 18,385.00 - (5,526.30) 18,385.00

2,700,452,285.10 16,680.24 411,270.00 6,860,082,417.90 10,114.11 411,270.00

7,141,825,862.20 11,348.60 491,026.00 5,572,458,866.61 (3,196.10) 491,026.00

547,950,861.04 - 52,946.00 - (10,349.24) 52,946.00

10,541,830,033.84 12,482,541,284.51
1,054,183,003.38 1,248,254,128.45
11,596,013,037.22 13,730,795,412.96
11,596,013,000.00 13,730,795,000.00

MUTUAL CHECK DINAS PENGAIRAN ACEH (2,134,782,000) (114,123) (7,133)


NAMA JABATAN TANDA TANG

Ismail, ST KETUA 1. ....................................

Ir. Badrizal SEKRETARIS/ANGGOTA

Rinal Dianto, ST ANGGOTA


3. ....................................

Marzuki, ST ANGGOTA

Yunita Andriani, ST ANGGOTA 5. ....................................

3,256,225,000.00 Banda Aceh, Juli 2017


Diperiksa : Dihitung Oleh :
Konsutan Supervisi Kontraktor Pelaksana
CV. FREEPORT CONSULTANT PT. BINA YUSTA AZ ZUHRI
Yusrin, ST T. Al Munawar
Team Leader Site Manager
DEVIASI
JUMLAH HARGA KET
Rp

1,940,711,250.67

(101,601,025.50)

4,159,630,132.80

(1,569,366,995.59)

(547,950,861.04)

1,940,711,250.67
194,071,125.07
2,134,782,375.74
2,134,700,000.00

TANDA TANGAN

2. ....................................

4. ....................................

eh, Juli 2017

or Pelaksana
USTA AZ ZUHRI
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

K.0 Err:509
40.00 Err:509 Err:509
K.1 Err:509 - -
43.50 Err:509 Err:509
K.2 Err:509 - -

SUB TOTAL 83.50 Err:509

TOTAL 83.50 Err:509

Diperiksa : Dihitung Oleh :


Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

K.0 Err:509
40.00 Err:509 Err:509
K.1 Err:509 - -
43.50 Err:509 Err:509
K.2 Err:509 - -

SUB TOTAL 83.50 Err:509

TOTAL 83.50 Err:509

Diperiksa : Dihitung Oleh :


Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Galian Tanah Berpasir (AB)


JARAK Galian Tanah Berpasir (AB)
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

K.0 Err:509
40.00 Err:509 Err:509
K.1 Err:509 - -
43.50 Err:509 Err:509
K.2 Err:509 - -

SUB TOTAL 83.50 Err:509

TOTAL 83.50 Err:509


Err:509
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL LUAS LUAS RATA2 VOLUME KET
M' M2 M2 M3

K.0 13.000
40.00 13.000 520.00
K.1 13.000 - -
43.50 13.000 565.50
K.2 13.000 - -

SUB TOTAL 83.50 1,085.50

TOTAL 83.50 1,085.50


2,384.00
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Pemasangan Batu Uk. < 250 Kg


JARAK Pemasangan Batu Uk. < 250 Kg
PROFIL LEBAR LEBAR RATA2 LUAS KET
M' M' M2 M2

K.0 Err:509
40.00 Err:509 Err:509
K.1 Err:509 - -
43.50 Err:509 Err:509
K.2 Err:509 - -

SUB TOTAL 83.50 Err:509

TOTAL 83.50 Err:509


-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL PANJANG PANJANG RATA2 LUAS KET
M' M' M' M2

K.0 Err:509
40.00 Err:509 Err:509
K.1 Err:509 - -
43.50 Err:509 Err:509
K.2 Err:509 - -

SUB TOTAL 83.50 Err:509

TOTAL 83.50 Err:509


-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
LEMBAR PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH
BESAR (OTSUS ACEH)
LOKASI : KABUPATEN ACEH BESAR
KEGIATAN : IRIGASI RAWA DAN PANTAI
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Err:509
JARAK Err:509
PROFIL PANJANG PANJANG RATA2 LUAS KET
M' M' M' M2

K.0 7.000
40.00 7.000 280.00
K.1 7.000 - -
43.50 7.000 304.50
K.2 7.000 - -

SUB TOTAL 83.50 584.50

TOTAL 83.50 584.50


-
Diperiksa : Dihitung Oleh :
Pengawas Lapangan Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
11,596,013,000.00
2,134,700,000.00
-
Yusrin, ST T. AL MUNAWAR
Team Leader Manager lapangan
PEMERINTAH ACEH
DINAS PENGAIRAN
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167

Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)

PERHITUNGAN
MUTUAL CHECK AKHIR (MC-100)
(BESERTA PENAMBAHAN 10%)

PEKERJAAN :
PEMBANGUNAN BANGUNAN PANTAI GP. SANE
KEC. LHOONG KAB. ACEH BESAR
(OTSUS ACEH)

TAHUN ANGGARAN
2017

KONTRAKTOR PELAKSANA :

PT. BINA YUSTA AZ ZUHRI


JL. CUT NYAK DHIEN NO. 53 KM. 6 GP. RIMA KENEURUM KEC. PEUKAN BADA
EH
RAN
2, 22899, 33126, 21167

A - BANDA ACEH (23247)

RI
PEUKAN BADA
DAFTAR REKAPITULASI PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Luas Penampang
Luas Penampang Luas Penampang Luas Penampang Volume (M3) Volume (M3)
Pasangan
No. Patok Jarak Galian Tanah Biasa Pasangan Batu Uk. Pasangan Batu Galian Tanah Pasangan Batu Uk.
Geotextile (Non
(AB) > 1000 Kg Uk. 250-1000 Kg Berpasir (AB) 1000 Kg
Woven)

0+000 - 30.484 10.723 -


25.00 - 0.000 - - -
0+025 - 34.892 15.556 -
25.00 - 0.000 - - -
0+050 - 34.831 13.439 -
25.00 - 0.000 - - -
0+075 - 34.502 11.984 -
25.00 - 0.000 - - -
0+100 - 59.943 58.584 -
25.00 - 0.000 - - -
0+125 - 66.838 87.761 -
25.00 - 0.000 - - -
0+150 - 70.062 98.949 -
25.00 - 0.000 - - -
0+175 - 71.224 101.844 -
25.00 - 0.000 - - -
0+200 - 73.067 108.949 -
25.00 - 0.000 - - -
0+225 - 73.451 113.422 -
25.00 - 0.000 - - -
0+250 - 0.000 - -
25.00 - 0.000 - - -
0+275 - 0.000 - -
25.00 - 0.000 - - -
0+300 - 0.000 - -
25.00 - 0.000 - - -
0+325 - 0.000 - -
25.00 - 0.000 - - -
0+350 - 0.000 - -
- - 0.000 - - -
0+380 - 0.000 - -
-

-
350.00 -

Komposisi Volume Penggunaan Batu


1 Batu Uk > 1000 Kg di Ambil 85 % batu Uk > 1000 Kg = 85% x
2 Batu Uk > 1000 Kg di Ambil 12.5 % Untuk Batu Pengunci (batu Uk < 250 Kg) = 12.5% x
3 Volume Batu Uk < 250 Kg 97.50% x
1,668.912 +
4 Menyediakan/Memasang Geotextile (Non Wooven)
5 Galian Tanah Berpasir (AB)

Diperiksa oleh : Diperiksa oleh :


Pengawas Lapangan Konsultan Pengawas

Nip. 19750222 200701 1 002 Team Leader


UNGAN VOLUME

Volume (M2)
Volume (M3) Volume (M3)
Pasangan
Pasangan Batu Uk. > Pasangan Batu Uk. Keterangan
Geotextile (Non
1000 Kg 250 - 1000 Kg
Woven)

817.200 328.487 -

871.537 362.437 -

866.662 317.787 -

1,180.562 882.100 -

1,584.762 1,829.312 -

1,711.250 2,333.875 -

1,766.075 2,509.912 -

1,803.637 2,634.912 -

1,831.475 2,779.637 -

918.137 1,417.775 -

- - -

- - -

- - -

- - -

- - -

- - -

- - -

- - -
13,351.297 15,396.234 -

13,351.297 = 11,348.60 m3
13,351.297 = 1,668.91 m3
15,396.234 = 15,011.33 m3
15,011.328 = 16,680.24 m3
= - m2
= - m3

Banda Aceh, Juli 2017


` Diajukan Oleh
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. ALMUNAWAR
Site Manager
DAFTAR REKAPITULASI PERHITUNGAN VOLUME

NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

Luas Penampang Merapikan Luas Penampang Volume (M2) Merapikan Volume (M2)
No. Patok Jarak
Permukaan Tanggul (AB) Pembersihan lapangan Permukaan Tanggul (AB) Pembersihan lapangan

0+000 4.000 7.520


25.00 214.500 192.000
0+025 13.160 7.840
25.00 275.125 179.125
0+050 8.850 6.490
25.00 207.875 145.875
0+075 7.780 5.180
25.00 203.250 133.875
0+100 8.480 5.530
25.00 150.125 157.125
0+125 3.530 7.040
25.00 167.250 189.625
0+150 9.850 8.130
25.00 201.625 191.250
0+175 6.280 7.170
25.00 143.250 186.750
0+200 5.180 7.770
25.00 151.625 137.000
0+225 6.950 3.190
25.00 177.250 161.625
0+250 7.230 9.740
25.00 121.625 171.875
0+275 2.500 4.010
25.00 40.250 89.250
0+300 0.720 3.130
25.00 88.625 131.250
0+325 6.370 7.370
25.00 156.250 172.375
0+350 6.130 6.420
25.00 163.000 178.000
0+375 6.910 7.820
- - -
0+400 3.960 3.010
- -
0+425
375.00 2,461.625 2,417.000

Banda Aceh, Juli 2017


Diperiksa oleh : Diperiksa oleh : Diajukan Oleh
Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHR

T. ALMUNAWAR
Nip. 19750222 200701 1 002 Team Leader Site Manager
Keterangan
h, Juli 2017

r Pelaksana
STA AZ ZUHRI
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00 64.00
0+00 PEMBERSIHAN LAPANGAN
( 7.52 )
62.00 62.00
7.52 M'
60.00 60.00
Pembersihan lapangan

58.00 58.00
7.52

56.00 56.00

Galian Galian Galian

54.00 54.00

0+000 0+000
52.00 20.00 52.00 20.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.356

54.369

53.485
56.356

54.369

53.485

53.778

56.365

57.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.60 15.90 J ARAK (m) 15.70 4.60 4.40 15.90
12.40

64.00

62.00

60.00

58.00
0+025 PEMBERSIHAN LAPANGAN
( 7.84 ) 56.00
Galian
7.84 M'
54.00

0+025 20.00
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA
56.365

54.563

54.123
ELEVASI TANAH ASLI

J ARAK (m) 2.90 11.50 11.30


ELEVASI RENCANA

56.365

54.563

54.123
ELEVASI TANAH ASLI

J ARAK (m) 2.90 11.50 11.30

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00 64.00

0+050 PEMBERSIHAN LAPANGAN


( 2.70 + 3.79 ) 62.00 62.00

6.49 M'
60.00 60.00

58.00 58.00 Pembersihan lapangan

3.79
56.00 56.00
Galian Galian Ga
2.70
54.00 54.00

0+050 20.00 0+050 20.00


52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

54.623
56.235

54.235
56.235

54.623

54.235

53.768

54.324
54.124

57.172
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 11.10 13.50 J ARAK (m) 11.70 2.50 11.10 14.80 2.50
13.50

64.00 64.00

62.00 62.00

60.00 60.00

58.00 58.00 Pembersihan la

0+075 PEMBERSIHAN
56.00 LAPANGAN 56.00 2.43
Galian
( 2.75 + 2.43 ) Galian
2.75

54.00 5.18 M' 54.00


1.00 1.00

0+075 20.00 0+075 20.00


52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.801
54.098
56.352

54.886
56.352

54.886

54.098

54.832

54.542
54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.40 12.80 9.20 J ARAK (m) 15.10 2.40 12.80 14.90 0.909.
ELEVASI RENCANA ELEVASI RENCANA

56.801
54.098
56.352

54.886
56.352

54.886

54.098

54.832

54.542
54.123
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.40 12.80 9.20 J ARAK (m) 15.10 2.40 12.80 14.90 0.909.

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
64.00 PERHITUNGAN VOLUME 64.00 SKET GAMBAR

62.00 62.00
0+100 PEMBERSIHAN LAPANGAN
(60.00
2.07 + 3.46 ) 60.00
5.53 M'
58.00 58.00 Pembersihan lapangan

Galian 3.46
Galian
56.00 56.00
2.07

1.00
54.00 54.00
20.00 20.00
0+100 0+100
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

57.236

55.326
57.236

55.342

57.386
55.326
55.412

55.192

55.412

54.714
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 64.00 2.70 11.20 11.90 5.50 (m) 64.00


JARAK 2.70 22.70
11.20 2.20
11.90

62.00 62.00

60.00 60.00
Pembersihan lapangan

3.90
58.00 58.00

3.14
Galian Galian
Galian
56.00 56.00
0+125 PEMBERSIHAN LAPANGAN
( 3.14 + 3.90 ) 1.00
54.00 54.00
7.04 20.00
M' 20.00

0+125 0+125
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

58.034
55.552

57.992

55.442
57.665

55.552

55.442

57.665

54.856

55.182
55.124

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.50 15.90 J ARAK9.30


(m) 4.50 9.90 5.80
15.90 1.40 3.90
55.552

57.992

58.034
55.442
57.665

55.552

55.442

57.665

54.856

55.182
55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 4.50 15.90 J ARAK9.30


(m) 4.50 9.90 5.80
15.90 1.40 3.90

Diperiksa :
PENGAWAS PEKERJAAN

0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

0+150 PEMBERSIHAN LAPANGAN


( 2.53 + 5.60 ) 60.00 60.00
8.13 M' Pembersihan lapangan

58.00 58.00 5.60

Galian Galian 2.53


Galian
56.00 56.00

1.00
54.00 20.00 54.00 20.00

0+150 0+150
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


57.965

55.332

55.563

55.673

57.965

55.332

55.563
55.308

56.978

55.673
55.436

57.012
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) 2.50 12.00 6.30 J ARAK (m) 10.20 2.50 12.00
11.60 1.90 6.30 5.60

62.00 62.00

60.00 60.00
Pembersihan lapangan
3.50
58.00 58.00

Galian 3.67 Galian


Galian
56.00 56.00

0+175 PEMBERSIHAN LAPANGAN 1.00

( 3.67 + 3.5054.00
) 20.00
54.00 20.00

7.17 M'
0+175 0+175
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


58.698

56.862

55.856

55.756

56.862

55.208

57.689

57.865
55.986

58.698

55.986
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20
56.8

55.8

55.2

57.6
58.6

55.9

58.6

55.7

56.8

55.9

57.8
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
64.00
PATOK
PERHITUNGAN VOLUME 64.00 SKET GAMBAR

62.00 62.00
0+200 PEMBERSIHAN LAPANGAN
( 4.57 + 3.20 )
60.00 60.00
7.77 M' Pembersihan lapangan

3.20
58.00 58.00
4.57
Galian Galian

56.00 56.00

1.00

54.00 20.00 54.00 2

00 0+200
52.00 52.00
samaan Bidang persamaan
evel Reference level
50.00 50.00

ANA ELEVASI RENCANA

58.865

56.485
58.865

56.485

55.856

55.536

55.752

57.956

57.996

56.124
56.124

64.00 64.00
H ASLI ELEVASI TANAH ASLI

8.50 9.00 7.90 11.40


JARAK (m) 8.50
8.70 4.00 9.00 3.20
62.00 62.00

60.00 60.00
Pembersihan lapangan

58.00 58.00
Galian Galian 3.19

56.00 56.00
0+225 PEMBERSIHAN LAPANGAN 1.00

( 3.1954.00
) 20.00 20.00
54.00
3.19 M'
0+225 0+225
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


59.685

56.623
56.342

55.875

56.342

55.986

56.865
59.685
56.124

56.164

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 5.80 11.60 9.40


J ARAK (m) 10.00
5.80 5.40 11.60 5.40 2.50 9.40
59.685

56.623
56.342

55.875

56.342

55.986

56.865
59.685
56.124

56.164

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 5.80 11.60 9.40


J ARAK (m) 10.00
5.80 5.40 11.60 5.40 2.50 9.40

Diperiksa :
PENGAWAS PEKERJAAN

0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN
62.00 VOLUME 62.00 SKET GAMBAR

60.00 60.00
0+250 PEMBERSIHAN LAPANGAN Pem

( 1.41 + 2.66 + 5.67 )


5.
58.00 9.74 M' 58.00
2.66
1.41
Galian

56.00 56.00
1.00 1.00

24.19 2
54.00 54.00

0+250 0+250
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.261
55.802
59.689

59.689

55.923

56.574

55.802

57.124
55.715

55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

64.00 64.00
J ARAK (m) 8.30 8.50 JARAK (m) 9.20 8.30 7.70 8.50 3.70 2.60 9

62.00 62.00

60.00 60.00

58.00 58.00

Galian Galian
56.00 56.00

0+275 PEMBERSIHAN LAPANGAN 1.00 1.00

( 4.01 ) 54.00 54.00 22.11 22.11


4.01 M'
0+275 0+275
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


59.685

55.896

55.465
59.685

55.896

55.465

55.986

56.393

56.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.00 J ARAK (m) 7.00 5.00 9.60 7.00 4.80 3.70
9.60 5.80
59.685

55.896

55.465
59.685

55.896

55.465

55.986

56.393

56.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.00 J ARAK (m) 7.00 5.00 9.60 7.00 4.80 3.70
9.60 5.80

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI 64.00

NOMOR 62.00
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

60.00
0+300 PEMBERSIHAN LAPANGAN Pe

( 1.76 + 1.37 )
58.00
3.13 M'
Galian

56.00
1.00

18.56
54.00

0+300
52.00
Bidang persamaan
Reference level
50.00

64.00 ELEVASI RENCANA 64.00

59.865

55.703

56.293
56.143
ELEVASI TANAH ASLI
62.00 62.00
J ARAK (m) 4.70 8.10 8.80

60.00 60.00

58.00 58.00
1.46
Galian Galian

56.00 56.00

1.00 1.00

0+325 PEMBERSIHAN LAPANGAN 54.00 54.00 13.87


( 1.46 + 5.91 )
0+325 7.37 M' 0+325
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.521
55.521

56.321
59.965
59.965

56.894
55.814
55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 10.10 5.60 5.70


3.40
55.521
55.521

56.321
59.965
59.965

56.894
55.814
55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 10.10 5.60 5.70


3.40

Diperiksa :
PENGAWAS PEKERJAAN

0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

0+350 PEMBERSIHAN LAPANGAN 60.00 60.00 Pe


( 6.42 )
6.42 M'
58.00 58.00

Galian Galian

56.00 56.00

1.00 1.00
54.00 54.00
15.99 15.99

0+350 0+350
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.251
60.235

60.235

55.278

55.278
56.135

56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00

JARAK (m) J ARAK (m) 5.60 8.70 5.60 6.80


8.70 7.00 6.80
62.00 62.00

60.00 60.00

58.00 58.00
Galian Galian

56.00 56.00
1.00 1.00
0+375 PEMBERSIHAN LAPANGAN
( 3.22 + 4.60 ) 54.00 54.00 20.03 20.03

7.82 M'
0+375 0+375
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


60.325

56.042

57.085
55.678

56.756
60.325

56.042

55.678

56.756
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) JARAK (m) 4.70 5.90 4.70 8.70 5.90 6.40 8.70 7.
60.325

56.042

57.085
55.678

56.756
60.325

56.042

55.678

56.756
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) JARAK (m) 4.70 5.90 4.70 8.70 5.90 6.40 8.70 7.

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

62.00 62.00
0+400 PEMBERSIHAN LAPANGAN
( 3.01 )
Pem
3.01 60.00
M' 60.00

Galian Galian
58.00 58.00

56.00 56.00
1.00 1.00

20.76 20.76
54.00 54.00

0+400 0+400
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.806

55.806
59.368

56.356

59.368

56.356
57.153

57.153
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 7.90 4.00 7.906.20 4.00 6.20


14.30
Diperiksa :
PENGAWAS PEKERJAAN

0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

BATU UK 250 - 1000 Kg


62.00 62.00
x y x.y y.x

60.00
0.000 53.714 - 201.428 60.00

3.750 56.214 210.803 265.049 2.25 2.00 3.75 2.00

4.715
58.00 56.214 253.262 405.584 58.00 + 57.714
7.215 53.714 387.547 - 1.5
1
0.000 53.714 - - 1.50
56.00 56.00 Geotextile
+ 55.214
1.5
1.50
1
54.00 54.00 + 53.714

JUMLAH 851.611 872.061 4.70 7.22


0+100 0+100
52.00 52.00
Bidang persamaan Bidang persamaan
LUAS= x . y- y . x 10.225 M2
Reference level Reference level
50.00 2 50.00

ELEVASI RENCANA ELEVASI RENCANA


55.326

55.342
57.236

55.326
55.412

57.236

55.192
55.412
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00

J ARAK (m) 2.70 11.20 JARAK11.90


(m) 2.70 5.50 11.20 22.70 11.90
GEOTEXTILE 62.00 62.00
( 4.7 + 7.22 + 2.08 )
60.00 14 M' 60.00 Perapian
Permukaan Tanggul

8.12
58.00 58.00

Galian Galian
56.00 56.00

54.00 54.00

MERAPIKAN PERMUKAAN TANGGUL 20.00 20.00


0+100 0+100
( 8.12 + 0.36 Bidang
) persamaan
52.00
Bidang persamaan
52.00

Reference level 8.48 M' Reference level


50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


57.236

55.326
55.326

55.342
57.236

55.412
55.192
55.412

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11.90 JARAK (m) 5.50 2.70 11.20 22.70 11.90
ELEVASI RENCANA ELEVASI RENCANA

57.236

55.326
55.326

55.342
57.236

55.412
55.192
55.412
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.70 11.20 11.90 JARAK (m) 5.50 2.70 11.20 22.70 11.90

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+125 GALIAN
x y x.y y.x 64.00

62.00
0.000 55.552 - 883.277
15.9000 55.4420 877.863 1,255.257 60.00

22.6409 55.2115 1,219.348 1,185.612


21.4740 53.8560 1,156.504 91.340 58.00

1.696 53.856 94.216 - Galian


Galian
56.00
0.000 55.552 - -
54.00
20.00 11.54
27.7278 55.0556 1,521.036 1,932.452 0+125
35.1000 54.8560 1,936.888 2,243.610 Bidang persamaan
52.00

Reference level
40.9000 55.1820 2,202.710 2,220.491 50.00

40.2394 53.8560 2,167.133 1,545.667 ELEVASI RENCANA

28.7000 53.8560 1,580.096 1,493.308

57.665

55.552

55.442

55.124
ELEVASI TANAH ASLI
27.7278 55.0556 - -
J ARAK (m) 4.50 15.90 9.30 9.90

64.00 64.00

JUMLAH 12,755.795 12,851.013


62.00 62.00

LUAS= x . y- y . x 47.609 M2
2 60.00 60.00
2.25 2.00 3.75 2.00

58.00 58.00 + 57.856 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 1.5
Batu Uk.> 1.000 Kg 1
x y x.y y.x 1 1.50 1
56.00 56.00
+ 55.356 + 55.498 +
1.5 1
0.000 53.856 - 121.176 + 53.856 1 1.83 + 53.856 1
54.00 54.00
2.250 55.356 124.551 235.263 11.54

4.250 55.356 0+125245.88852.00 442.848 0+125


52.00
Bidang persamaan Bidang persamaan
8.000 57.856 Reference 462.848
level
578.560 Reference level
10.0000 57.8560 554.984 50.00 714.961 50.00

12.3576 55.4984 667.419


ELEVASI RENCANA 647.439 ELEVASI RENCANA

11.6659 54.0088 657.443 508.709


57.665

55.552

55.442

57.992

58.034
54.856
57.665

55.552

55.124

55.442

55.182

55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
9.419 56.356 530.817 476.434
J ARAK (m) 4.50 15.90
J ARAK (m) 4.50 9.30 15.90 9.90 5.80 9.30 1.40 3.90
ELEVASI RENCANA ELEVASI RENCANA

57.665

55.552

55.442

57.992
54.856

58.034
57.665

55.552

55.442
55.124

55.182

55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.356J ARAK (m) 455.299 4.50


265.099 15.90
J ARAK (m) 4.50 9.30 15.90 9.90 5.80 9.30 1.40 3.90

4.704 53.856 253.339 -


0.000 53.856 - -
Diperiksa :
JUMLAH 3,952.588 3,990.488 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 18.950 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
64.00 64.00

BATU UK 250 - 100062.00


Kg 62.00
x y x.y y.x

60.00 60.00
0.000 53.856 - 201.960 2.25 2.00 3.75 2.00
3.750 56.356 211.335 265.719
58.00 58.00 + 57.856
4.715 56.356 255.129 392.294
1.5
6.961 54.110 374.892 369.842 1 1.50
6.835 53.856 368.106
56.00 - 56.00 Geotextile
+ 55.356
0.000 53.856 - -
1.5
+ 53.856 1
54.00 54.00
11.54
JUMLAH
0+125 1,209.461 1,229.815 0+125
52.00 52.00
Bidang persamaan Bidang persamaan
LUAS= x level
Reference . y- y . x 10.177 M2 Reference level
2 50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA


57.665

55.552

55.442

54.856
57.665

55.552

55.442
55.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 64.00 15.90


J ARAK (m) 4.50 9.30 64.00 15.90 9.90 5.80 9
GEOTEXTILE
( 11.54 + 1.83 ) 62.00 62.00

13.37 M'
60.00 60.00 Perapian
Permukaan Tanggul
Timb
Hasil G
3.53
58.00 58.00

Galian Galian
Galian
56.00 56.00

1.00
54.00 54.00
MERAPIKAN PERMUKAAN TANGGUL 20.00 20.00

0+125 0+125
( 3.53 ) Bidang persamaan
52.00
Bidang persamaan
52.00

Reference level 3.53 M' Reference level


50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

54.856

57.992
57.665

55.552

55.442

55.442
57.665
55.124

55.552

55.182
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 15.90 J ARAK (m) 9.30 4.50 9.90 15.905.80 1.40 3.90
ELEVASI RENCANA ELEVASI RENCANA

54.856

57.992
57.665

55.552

55.442

55.442
57.665
55.124

55.552

55.182
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 4.50 15.90 J ARAK (m) 9.30 4.50 9.90 15.905.80 1.40 3.90

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+150 GALIAN 64.00

x y x.y y.x
62.00

0.000 55.332 - 663.984


60.00
12.0000 55.5630 668.076 1,016.803
18.3000 55.6730 1,017.271 1,221.154
58.00
21.9344 55.5886 1,191.213 1,158.022
20.8320 54.3080 1,131.344 55.611
Galian
56.00
1.024 54.308 56.660 -
0.000 55.332 - - 54.00 20.00

0+150
27.3909 55.4618 1,518.442 1,580.661 Bidang persamaan
52.00

28.5000 55.4360 1,576.278 2,222.984 Reference level


50.00
40.1000 55.3080 2,177.751 2,154.927
ELEVASI RENCANA
38.9623 54.3080 2,115.965 1,543.433

57.965

55.332

55.673

55.436
55.563
28.4200 54.3080 1,576.224 1,487.545 ELEVASI TANAH ASLI

27.3909 55.4618 - - J ARAK (m) 2.50 12.00 6.30 10.20

64.00 64.00
JUMLAH 13,029.225 13,105.124
62.00 62.00
LUAS= x . y- y . x 37.950 M2
2 60.00 60.00
2.25 2.00 3.75 2.00 2.25 2

+ 58.308 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 58.00 58.00
1.5
Batu Uk.> 1.000 Kg 1 Batu Uk.> 1
x y x.y y.x 1 1.50 1

56.00 56.00 + 55.808 + 55.925


+ 55.808
1.5 1.5
0.000 54.308 - 122.193 + 54.308
1 2.45
+ 54.308
1

2.250 55.808 125.568 237.184 54.00 54.00


10.54

4.250 55.808 247.809 446.464


0+150 0+150
52.00 52.00
8.000 58.308 466.464 583.080
Bidang persamaan Bidang persamaan
Reference level Reference level
10.0000 58.3080 559.255 721.999 50.00 50.00
12.3825 55.9255 680.448 630.588
ELEVASI RENCANA ELEVASI RENCANA
11.2755 54.9524 640.539 517.597

55.308
55.332

56.978
57.965

55.563

55.673

55.436
57.965

55.332

55.436
55.563

55.673
9.419 56.808 535.075 ELEVAS480.255
I TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00


J ARAK (m) 2.50 6.30 12.00 10.20 6.30 11.60 10.20 1.90 5
ELEVASI RENCANA ELEVASI RENCANA

55.332

55.308

56.978
57.965

55.563

55.673

55.436
57.965

55.332

55.436
55.563

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.808 459.120 J ARAK 267.225


(m) 2.50 12.00
J ARAK (m) 2.50 6.30 12.00 10.20 6.30 11.60 10.20 1.90 5
4.704 54.308 255.465 -
0.000 54.308 - -
Diperiksa :
JUMLAH 3,969.742 4,006.584 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 18.421 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00
BATU UK 250 - 1000 Kg
x y x.y y.x
60.00 60.00
2.25 2.00 3.75 2.00

0.000 54.308 - 203.655 + 58.308


B
3.750 56.808 213.030
58.00 267.850 58.00
1.5 1
1
4.715 56.808 259.099 373.285 1.50 1
Geotextile
6.571 54.952 356.858
56.00 320.810 56.00 + 55.808
5.838 54.308 317.050 - 1.5
1
0.000 54.308 - - + 54.308 2.4
54.00 54.00
10.54

0+150 0+150
JUMLAH 1,146.037
52.00 1,165.600 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
LUAS= x . y- y . x50.00 9.782 M2 50.00
2
ELEVASI RENCANA ELEVASI RENCANA

55.673

55.308
57.965

55.332

55.563

55.436
55.332
57.965

55.563

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 2.50 64.00 12.00 J ARAK (m) 6.30 2.50 64.00 10.20 12.00 11.60
6.30

GEOTEXTILE 62.00 62.00

( 10.54 + 2.45 )
Perapian
60.00 12.99 M' 60.00 Permukaan Tanggul

8.26

58.00 58.00

Galian Galian Galian


56.00 56.00

1.00

54.00 20.00 54.00 20.00

MERAPIKAN PERMUKAAN TANGGUL


0+150 0+150
52.00 52.00
( 8.26 + 1.59 ) Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 9.85 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

57.965

55.332

55.563
55.308
57.965

55.563

55.436

56.978
55.332

55.673

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00 6.30 J ARAK (m) 10.20 2.50 12.00
11.60 1.90 6.30 5.60
ELEVASI RENCANA ELEVASI RENCANA

57.965

55.332

55.563
55.308
57.965

55.563

55.436

56.978
55.332

55.673
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 2.50 12.00 6.30 J ARAK (m) 10.20 2.50 12.00
11.60 1.90 6.30 5.60

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+175 GALIAN
x y x.y y.x
62.00

0.000 56.862 - 477.641


60.00
8.400 55.986 469.190 985.354
17.6000 55.8560 982.076 1,284.548 58.00
22.9975 55.7998 1,246.648 1,209.818 Galian

21.6814 54.2080 1,175.305 143.868 56.00

2.654 54.208 150.912 -


0.000 56.862 54.00 20.00

0+175
25.1057 55.7778 1,399.793 1,517.156 Bidang persamaan
52.00

27.2000 55.7560 1,501.658 2,035.094 Reference level


50.00
36.5000 55.2080 1,978.592 1,955.009
ELEVASI RENCANA
35.4117 54.2080 1,919.597 1,436.512

58.698

56.862

55.986

55.856

55.756
26.5000 54.2080 1,478.112 1,360.930 ELEVASI TANAH ASLI

25.1057 55.7778 - - JARAK (m) 6.00 8.40 9.20 9.60

64.00 64.00
JUMLAH 12,301.885 12,405.930
62.00 62.00
LUAS= x . y- y . x 52.023 M2
2 60.00 60.00
2.25 2.00 3.75 2.00 2.25

+ 58.208 Batu Uk. < 250 Kg


BATU Uk > 1000 Kg 58.00 58.00 1
1.5 1
Batu Uk.> 1.000 Kg Batu
x y x.y y.x 1 1.50 + 56.645

56.00 56.00 + 55.708 + 55.70

0.000 54.208 - 121.968


1.5 1.5
1 3.60 1
+ 54.208 + 54.208
2.250 55.708 125.343 236.759 54.00 54.00
8.91

4.250 55.708 247.384 445.664


0+175 0+175
52.00 52.00
8.000 58.208 465.664 582.080
Bidang persamaan Bidang persamaan
Reference level Reference level
10.0000 58.2080 566.446 673.082 50.00 50.00
11.5634 56.6446 643.486 593.601
ELEVASI RENCANA ELEVASI RENCANA
10.4794 55.6485 594.266 524.153

55.208
58.698

56.862

55.986

55.856

55.756

57.689
58.698

55.756
56.862

55.986

55.856
9.419 56.708 534.133 ELEVASI479.409
TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30 9.60 2.70 3.50
ELEVASI RENCANA ELEVASI RENCANA

55.208
58.698

56.862

55.986

55.856

55.756

57.689
58.698

55.756
56.862

55.986

55.856
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 56.708 458.274 266.754


J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30 9.60 2.70 3.50
4.704 54.208 254.994 -
0.000 54.208 - -
Diperiksa :
JUMLAH 3,889.990 3,923.472 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 16.741 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00
NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 - 1000 Kg


60.00 60.00
x y x.y y.x 2.25 2.00 3.75

+ 58.20
58.00 58.00
0.000 54.208 - 203.280 1.5
1 1.
3.750 56.708 212.655 267.378
Geotextile
4.715 56.708 262.380 327.489
56.00 56.00 + 55.708

5.775 55.648 313.051 234.111 1.5


1
+ 54.208
4.207 54.208 228.053 -
54.00 54.00
8.91
0.000 54.208 - -
0+175 0+175
52.00 52.00
Bidang persamaan Bidang persamaan

JUMLAH Reference level


1,016.140 1,032.258 Reference level
50.00 50.00

LUAS= x . y- y . x ELEVASI RENCANA 8.059 M2 ELEVASI RENCANA

2
58.698

56.862

55.986

55.856

55.756
56.862

55.986

55.856
58.698
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 6.00 J ARAK (m) 8.40 6.00 9.20 8.40 9.60 9.20 9.30
64.00 64.00

62.00 62.00

GEOTEXTILE
Perapian
( 8.91 + 3.60 ) 60.00 60.00 Permukaan Tanggul
Timbunan
12.51 M' 5.55
Hasil Galia

58.00 58.00 0.73

Galian
Galian
56.00 56.00

1.00
54.00 20.00
54.00 20.00

MERAPIKAN0+175 PERMUKAAN 0+175


52.00 TANGGUL 52.00
Bidang persamaan Bidang persamaan
( 5.55 + 0.73 ) level
Reference Reference level
50.00 6.28 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

58.698

56.862

55.986
58.698

56.862

55.986

55.856

55.756

55.208

57.689

57.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20
ELEVASI RENCANA ELEVASI RENCANA

58.698

56.862

55.986
55.208
58.698

56.862

55.986

55.856

55.756

57.689

57.865
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.00 8.40 9.20 J ARAK (m) 9.60 6.00 9.30 8.40 2.70 3.50 9.20

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+200 GALIAN
x y x.y y.x 62.00

0.000 56.485 - 508.365 60.00

9.000 56.124 502.704 948.496


58.00
16.9000 55.8560 941.513 1,232.809
Galian
22.0712 55.7108 1,203.675 1,180.478
56.00
21.1894 54.5360 1,155.585 64.843 1.00

1.189 54.536 67.161 - 54.00 20.00

0.000 56.485
0+200
- - Bidang persamaan
52.00

25.4067 55.6172 1,410.986 1,573.967


Reference level
50.00

28.3000 55.5360 1,577.782 2,054.832 ELEVASI RENCANA


37.0000 55.7520 2,017.832 1,939.785

56.485

55.856

55.536
58.865

56.124
ELEVASI TANAH ASLI
34.7931 54.5360 1,897.477 1,427.752
26.1800 54.5360 1,456.058 1,385.580 J ARAK (m) 8.50 9.00 7.90 11.40

25.4067 55.6172 - -
64.00 64.00

JUMLAH 12,230.772 12,316.907


62.00 62.00

LUAS= x . y- y . x 43.068
60.00 M2 60.00 2.25 2.00 3.75 2.00
2 Batu
+ 58.536
1
58.00 58.00 1.5 1
Batu Uk.> 1.000 Kg
BATU Uk > 1000 Kg 1 1.50
+
x y x.y 56.00
y.x 56.00
+ 56.036
1.5
1 3.97
+ 54.536
0.000 54.536 - 122.706
54.00 54.00 4.70 3.91
2.250 56.036 126.081 238.153
4.250 56.036 0+200
248.778 448.288 0+200
52.00 52.00
Bidang persamaan Bidang persamaan
8.000 58.536 468.288 585.360
Reference level Reference level
10.0000 58.5360 564.497 707.484
50.00 50.00

12.0863 56.4497 673.336


ELEVASI RENCANA
606.558 ELEVASI RENCANA
10.7451 55.7107 612.858 524.739
58.865

56.485

55.856

55.536

55.752
58.865

56.485

55.856
56.124

56.124
9.419 57.036 537.222
ELEVAS I TANAH ASLI 482.182 ELEVASI TANAH ASLI

J ARAK (m) 8.50 J ARAK (m) 9.00 8.50


7.90 9.00 11.40 7.90 8.70 14
ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485

55.856

55.536

55.752
58.865

56.485

55.856
56.124

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 57.036 J ARAK461.047


(m) 268.297 8.50 J ARAK (m) 9.00 8.50
7.90 9.00 11.40 7.90 8.70 14
4.704 54.536 256.537 -
0.000 54.536 - -
Diperiksa :
JUMLAH 3,948.645 3,983.767 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 17.561 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 -60.00


1000 Kg 60.00 2.25 2.00 3.75 2.00
x y x.y y.x
+ 58.536
1
58.00 58.00 1.5
0.000 54.536 - 204.510 1 1.50
1

3.750 57.036 213.885 268.925 Geotextile


+ 56.036
4.715 57.036
56.00 262.673 344.554 56.00
1.5
6.041 55.710 329.452 217.715 1 3.97
+ 54.536
3.908 54.536 213.127 -
54.00 54.00 4.70 3.91
0.000 54.536 - -
0+200 0+200
52.00 52.00
Bidang persamaan Bidang persamaan
Reference levelJUMLAH 1,019.136 1,035.704 Reference level
50.00 50.00

LUAS=
ELEVAS x . y- y . x
I RENCANA 8.284 M2 ELEVASI RENCANA
2

55.856

55.752
58.865

56.485

58.865

56.485

55.536
56.124

56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 64.00 8.50 9.00 JARAK (m) 7.90 64.00 8.50 11.40 9.00 8.70 7.90

62.00 62.00

GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 60.00
+ 3.91 + 3.97 ) 60.00 Timbunan
Hasil Galian
12.58 M' 4.54

58.00 58.00 0.64

Galian Galian

56.00 56.00
1.00

54.00 20.00 54.00 20.0

0+200
MERAPIKAN PERMUKAAN TANGGUL 0+200
52.00 52.00
( 4.54
Bidang persamaan + 0.64 ) Bidang persamaan
Reference level Reference level
50.00
5.18 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485
55.856

55.536
58.865

56.485

55.752

57.956
56.124
56.124

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.50 9.00 7.90 J ARAK (m) 11.40 8.50 8.70 9.00 4.00 3.20
ELEVASI RENCANA ELEVASI RENCANA

58.865

56.485
55.856

55.536
58.865

56.485

55.752

57.956
56.124
56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.50 9.00 7.90 J ARAK (m) 11.40 8.50 8.70 9.00 4.00 3.20

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+225 GALIAN
x y x.y y.x 64.00

0.000 56.342 - 653.567 62.00

11.6000 56.1240 648.150 1,178.604


60.00
21.0000 55.8750 1,173.547 1,214.527
21.7365 55.8832 1,192.790 1,173.547 58.00

21.0000 54.8750 1,152.375 80.502 Galian

1.467 54.875 82.654 - 56.00


1.00

0.000 56.342 - - 20.00


54.00

27.9629 55.9523 1,565.531 1,734.521 0+225


52.00
Bidang persamaan
31.0000 55.9860 1,741.084 2,037.890 Reference level
50.00
36.4000 56.1640 2,058.973 2,309.452
ELEVASI RENCANA
41.1198 56.5652 2,256.449 2,303.895

59.685

56.342

55.875

55.986
56.124
40.7299 54.8750 2,235.053 1,580.949 ELEVASI TANAH ASLI

28.8100 54.8750 1,611.986 1,534.464 J ARAK (m) 5.80 11.60 9.40 10.00

27.9629 55.9523 - -

64.00 64.00
JUMLAH 15,718.593 15,801.919

62.00 62.00
LUAS= x . y- y . x 41.663 M2
2 2.25 2.00 3.75 2.00 2.31
60.00 60.00
+ 58.875 Batu Uk. < 250 Kg

BATU Uk > 1000 Kg


1
1.5 1
58.00 58.00 Batu Uk.> 1.000 Kg
1 1.50
x y x.y y.x + 56.565
+ 56.375
56.00 56.00 1.5
1.50 1.73
0.000 54.875 - 123.469 + 54.875 1 + 54.875

2.250 56.375 126.844 239.594


54.00 54.00
4.70 7.22

4.250 56.375 250.219 451.000


0+225 0+225
8.000 58.875 471.000
Bidang persamaan588.750
52.00
Bidang persamaan
52.00

10.0000 58.8750 565.652


Reference level 724.739 Reference level
50.00 50.00
12.3098 56.5652 675.500 674.252
ELEVASI RENCANA ELEVASI RENCANA
11.9199 54.8750 683.904 516.868
59.685

56.342

55.875

55.986

56.865
56.623
59.685

56.342

56.164
56.124

55.875
56.124
9.419 57.375 540.415
ELEVAS I TANAH ASLI485.048 ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60


JARAK (m) 5.80 9.40 11.60 10.00 9.40
5.40 5.40 10.00
2.50
ELEVASI RENCANA ELEVASI RENCANA

59.685

56.342

55.875

55.986

56.865
56.623
59.685

56.342

56.164
56.124

55.875
56.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

8.454 57.375 J463.913


ARAK (m) 269.892 5.80 11.60
JARAK (m) 5.80 9.40 11.60 10.00 9.40
5.40 5.40 10.00
2.50
4.704 54.875 258.132 -
0.000 54.875 - -
Diperiksa :
JUMLAH 4,035.579 4,073.611 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 19.016 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00
BATU UK 250 - 1000 Kg
x y x.y y.x 2.25 2.00 3.75 2.00
60.00 60.00
+ 58.875
0.000 54.875 - 205.781
1.5
3.750 57.375 58.00 215.156 270.523 58.00 1 1.50
Geotextile
4.715 57.375 258.736 413.961 + 56.375
7.215 54.875 56.00 395.923 - 56.00 1.5
1.50
0.000 54.875 - - + 54.875 1

4.70 7.22
54.00 54.00

0+225 0+225
JUMLAH
Bidang persamaan
52.00 869.815 890.265 Bidang persamaan
52.00

Reference level Reference level


LUAS= x . y- y50.00
.x 10.225 M2 50.00

ELEVASI RENCANA 2 ELEVASI RENCANA

59.685

56.342
56.342

55.986
59.685

55.875

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00
JARAK (m) 5.80 11.60 J ARAK (m) 9.40 5.80 10.00 11.60 5.40 5.40

62.00 62.00
GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 + 7.22
60.00+ 1.73 ) 60.00 Timbunan
13.65 M' 4.84 Hasil Galian

58.00 58.00 2.11

Galian Galian

56.00 56.00
1.00

20.00 20.00
54.00 54.00

0+225
MERAPIKAN PERMUKAAN TANGGUL 0+225
52.00 52.00
( 4.84 +
Bidang persamaan 2.11 ) Bidang persamaan
Reference level Reference level
50.00 6.95 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA


59.685

56.342
59.685

56.865
56.342

55.875

55.986

56.623

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60 9.40 J ARAK (m) 10.00 5.80 5.40 15.40
1.60 2.50
ELEVASI RENCANA ELEVASI RENCANA

59.685

56.342
59.685

56.865
56.342

55.875

55.986

56.623

56.124
56.124

56.164
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.80 11.60 9.40 J ARAK (m) 10.00 5.80 5.40 15.40
1.60 2.50

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+250 GALIAN
x y x.y y.x
62.00

0.000 55.715 - 473.578


8.500 55.802 475.346 987.695 60.00

17.7000 55.9230 981.555 1,548.748


27.6943 55.4551 1,515.294 1,391.047 58.00

25.0842 54.7150 1,372.482 54.715 Galian

1.000 54.715 55.715 - 56.00


1.00
0.000 55.715
24.19
54.00

0+250
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

59.689

55.923
55.802
55.715
ELEVASI TANAH ASLI

J ARAK (m) 8.30 8.50 9.20 7.70

JUMLAH 4,400.391 4,455.783


64.00 64.00

LUAS= x . y- y . x 27.696 M2
62.00 62.00

2
60.00 60.00 2.25 2.00 3.75 2.00 1.54 2.25 2.00 3.75

BATU Uk > 1000 Kg + 58.715


1
Batu Uk. < 250 Kg +

1.5 1.5
x y x.y y.x 58.00 58.00 Batu Uk.> 1.000 Kg
1
1
+ 57.171
Batu Uk.> 1.000 Kg
1
1.50 1.5
+ 56.215 2.89 + 56.215
56.00 56.00
0.000 54.715 - 123.109
1.41
1.5 1.5
1 1.50 1 1.50
+ 54.715 3.14 + 54.715 3.14
2.250 56.215 126.484 238.914 4.70 6.84 4.70
54.00 54.00
4.250 56.215 249.539 449.720
8.000 58.715 469.720 0+250 587.15052.00
0+250
52.00
Bidang persamaan Bidang persamaan
10.0000 58.7150 571.713Reference level
677.788 Reference level
11.5437 57.1713 653.073 498.534
50.00 50.00

8.720 56.574 492.288


ELEVAS I 413.782
RENCANA ELEVASI RENCANA

7.314 56.455 400.186 265.564

56.261

56.574
59.689

55.802

55.923

56.261
59.689

55.802

55.923
55.715

57.124
55.715

ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70 9.20 2.60 7.70 3
ELEVASI RENCANA ELEVASI RENCANA

56.261

56.574
59.689

55.802

55.923

56.261
59.689

55.802

55.923
55.715

57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
4.704 54.715 257.379 -
JARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70 9.20 2.60 7.70 3
0.000 54.715 - -
- -
Diperiksa :
JUMLAH 3,220.381 3,254.561 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 17.090 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
64.00 64.00
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58.

58.00 58.00 1.5


1
Geotextile 1.50
+ 56.215
56.00 56.00
1.5
1 1.50
+ 54.715 3.14

54.00 54.00 4.70

0+250 0+250
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.261
59.689

55.802
59.689

55.923
55.802

55.715
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

64.00 64.00
J ARAK (m) 8.30 J ARAK (m) 8.50 8.30 9.20 8.50 7.70 3.70

62.00 62.00

GEOTEXTILE Perapian
Permukaan Tanggul
( 4.70 + 3.14 + 1.41 + 2.89 ) 60.00 60.00 Timbunan
Hasil Galian
6.26
12.14 M'
0.97
58.00 58.00

Galian Galian

56.00 56.00
1.00 1.00

24.19 24.19
54.00 54.00

0+250
MERAPIKAN PERMUKAAN TANGGUL
0+250
52.00 52.00
Bidang persamaan Bidang persamaan
( 6.26 + 0.97 ) Reference level Reference level
50.00 7.23 M' 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.261
55.802

55.923
59.689

56.574
55.715

59.689

55.802

55.923
57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 8.50


J ARAK (m) 9.20 8.30 7.70 8.50 3.70 2.60 9.20 7
ELEVASI RENCANA ELEVASI RENCANA

56.261
55.802

55.923
59.689

56.574
55.715

59.689

55.802

55.923
57.124
55.715
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.30 8.50


J ARAK (m) 9.20 8.30 7.70 8.50 3.70 2.60 9.20 7

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+275 GALIAN
x y x.y y.x 62.00

0.000 55.896 - 391.272 60.00


7.000 55.465 391.902 920.719
16.6000 55.9860 936.124 1,198.100 58.00

21.4000 56.3930 1,216.911 1,415.464 Galian


25.1000 56.8650 1,430.564 1,529.589 56.00

26.8986 56.9946 1,465.032 1,316.815 1.00

23.1042 54.4650 1,258.370 77.939 54.00 22.11

1.431 54.465 79.987 -


0+275
0.000 55.896 - - Bidang persamaan
52.00

Reference level
50.00

ELEVASI RENCANA

56.393
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70

64.00
JUMLAH 6,778.891 6,849.899
62.00
LUAS= x . y- y . x 35.504 M2
2 60.00 2.25 2.00 3.75

+ 58.46
BATU Uk > 1000 Kg 58.00
Batu Uk.> 1.000 Kg
x y x.y y.x 1.

+ 55.965
56.00
0.000 54.465 - 122.546 + 54.465
4.56

2.250 55.965 125.921 237.851 54.00 4.70

4.250 55.965 248.476 447.720


0+275
8.000 58.465 467.720 584.650 Bidang persamaan
52.00

10.0000 58.4650 571.944 658.936 Reference level


50.00
11.2706 57.1944 642.357 486.038
8.498 56.994 462.844 268.100 ELEVASI RENCANA

4.704 54.465 256.203 -


59.685

55.465
55.896

55.986

56.393

56.865
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70


ELEVASI RENCANA

59.685

55.465
55.896

55.986

56.393

56.865
ELEVASI TANAH ASLI
0.000 54.465 - -
J ARAK (m) 5.00 7.00 9.60 4.80 3.70

Diperiksa :
JUMLAH 2,775.465 2,805.841 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.188 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58.465
58.00 58.00
1.5
Geotextile
+ 55.965
56.00 56.00
4.56
+ 54.465
54.00 54.00 4.70

0+275 0+275
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

59.685

55.896

55.986

56.865
55.465

56.393
55.465
59.685

55.896
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 5.00 64.00J ARAK (m) 7.00 5.00 9.60 7.00 4.80 3.70
9.60

62.00
GEOTEXTILE
( 4.70 + 4.56 + 2.78 ) Perapi
Permukaan
60.00
12.04 M'

58.00

Galian
56.00

1.00

54.00 22.11

MERAPIKAN PERMUKAAN TANGGUL 0+275


52.00
Bidang persamaan
( 2.50 ) Reference level
2.50 M' 50.00

ELEVASI RENCANA

56.393

56.865
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70


ELEVASI RENCANA

56.393

56.865
59.685

55.896

55.465

55.986
ELEVASI TANAH ASLI

J ARAK (m) 5.00 7.00 9.60 4.80 3.70

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+300 GALIAN
x y x.y y.x
62.00

0.000 56.143 - 454.758


8.100 55.703 455.973 941.381 60.00

16.9000 56.2930 961.368 1,280.677


22.7502 56.8857 1,290.005 1,108.941 58.00

19.4942 56.7030 1,066.391 81.652 Galian

1.440 54.703 80.846 - 56.00


1.00
0.000 56.143 - -
18.56
54.00

0+300
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.703
59.865

56.293
56.143
ELEVASI TANAH ASLI

J ARAK (m) 4.70 8.10 8.80

JUMLAH 3,854.583 3,867.410 64.00

LUAS= x . y- y . x 6.413 M2 62.00

2
60.00 2.25 2.00 3.75 2.00

+ 58.715
BATU Uk > 1000 Kg 1

58.00 Batu Uk.> 1.000 Kg


x y x.y y.x 1.50
1.
+ 56.215 1.76
56.00
0.000 54.715 - 123.109 + 54.715
3.91

2.250 56.215 126.484 238.914 54.00 4.70

4.250 56.215 249.539 449.720


0+300
8.000 58.715 469.720 587.150 Bidang persamaan
52.00

10.0000 58.7150 580.000 629.131 Reference level


50.00
10.7150 58.0000 611.430 563.180
ELEVASI RENCANA
9.710 57.063 552.353 454.221

55.703

56.293

57.063
59.865

56.143

7.960 56.885 435.531 267.587 ELEVASI TANAH ASLI

J ARAK (m) 4.70 8.10 8.80 7.60


ELEVASI RENCANA

56.293
59.865

55.703

57.063
56.143
ELEVASI TANAH ASLI

4.704 54.715 257.379 - J ARAK (m) 4.70 8.10 8.80 7.60


0.000 54.715 - -

Diperiksa :
JUMLAH 3,282.437 3,313.012 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.288 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00

60.00 2.25 2.00

58.00

Geotextile
+ 56.215
56.00

+ 54.715

54.00 4.70

0+300
52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.703
59.865

56.293
56.143
ELEVASI TANAH ASLI
64.00
J ARAK (m) 4.70 8.10 8.80
62.00
GEOTEXTILE
Perapian
( 4.70 + 3.91 + 1.76 + 1.37 ) Permukaan Ta
60.00
11.74 M'

58.00
Galian

56.00
1.00

18.56
54.00

MERAPIKAN PERMUKAAN TANGGUL 0+300


52.00
( 0.72 ) Bidang persamaan
Reference level
0.72 M' 50.00

ELEVASI RENCANA

55.703

56.293
59.865

56.143

ELEVASI TANAH ASLI

JARAK (m) 4.70 8.10 8.80 7.60


ELEVASI RENCANA

55.703

56.293
59.865

56.143
ELEVASI TANAH ASLI

JARAK (m) 4.70 8.10 8.80 7.60

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00

0+325 GALIAN
x y x.y y.x 62.00

60.00
0.000 55.521 - 188.771
3.400 55.814 191.491 753.489 58.00
13.5000 56.3210 766.093 999.365
Galian
17.7441 56.7476 967.426 817.404 56.00

14.4042 54.5210 785.331 54.521 1.00

1.000 54.521 55.521 - 54.00 13.87

0.000 55.521 0+325


52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

55.521

56.321
59.965

55.814
ELEVASI TANAH ASLI

JARAK (m) 5.60 3.40 10.10 5.70

64.00

JUMLAH 2,765.862 2,813.551


62.00

LUAS= x . y- y . x 23.844 M2
60.00
2 2.25 2.00

58.00
BATU Uk > 1000 Kg Batu Uk.> 1.000 Kg

x y x.y y.x + 56.021


56.00
1.50
0.000 54.521 - 122.672 + 54.521

54.00 4.70
2.250 56.021 126.047 238.089
4.250 56.021 248.714 448.168 0+325
52.00
8.000 58.521 468.168 585.210 Bidang persamaan
Reference level
10.0000 58.5210 570.102 673.624 50.00
11.5108 57.0102 654.895 541.597
ELEVASI RENCANA
9.500 56.894 539.097 457.655

55.521

56.321
59.965

55.814
8.044 56.747 438.567 266.938 ELEVASI TANAH ASLI

J ARAK (m) 5.60 3.40 10.10


ELEVASI RENCANA

55.521

56.321
59.965

55.814
ELEVASI TANAH ASLI

4.704 54.521 256.467 - J ARAK (m) 5.60 3.40 10.10


0.000 54.521 - -

Diperiksa :
JUMLAH 3,302.057 3,333.953 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 15.948 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR 64.00 64.00


PATOK
PERHITUNGAN VOLUME SKET GAMBAR

62.00 62.00

60.00 60.00 2.25 2.00 3.75

+ 58
58.00 58.00

Geotextile
+ 56.021
56.00 56.00
1.50
+ 54.521 4.01

54.00 54.00 4.70

0+325 0+325
52.00 52.00
Bidang persamaan Bidang persamaan
Reference level Reference level
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
55.521
59.965

59.965
55.814

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) J ARAK (m) 5.60 3.40 5.6010.10 3.40 5.70

62.00 62.00

GEOTEXTILE Perapian
( 4.70 + 4.01 + 3.43 ) 60.00 60.00 Permukaan Tanggul

12.14 M'
58.00 58.00

Galian Galian

56.00 56.00

1.00 1.00

54.00 54.00 13.87 13.87

MERAPIKAN PERMUKAAN TANGGUL 0+325 0+325


52.00 52.00
( 5.04 + 1.33 ) Bidang persamaan Bidang persamaan
Reference level Reference level
6.37 M'
50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
59.965

56.894
55.521
55.814
59.965

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 5.60 10.10 3.40 5.70
10.10
ELEVASI RENCANA ELEVASI RENCANA

55.521

56.321
59.965

56.894
55.521
55.814
59.965

55.814
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 3.40 5.60 10.10 3.40 5.70
10.10

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

64.00
0+350 GALIAN
x y x.y y.x 62.00

0.000 56.135 - 488.375 60.00


8.700 55.278 489.384 856.809
15.5000 56.2510 885.422 1,265.648 58.00

22.5000 57.1240 1,277.505 1,184.420 Galian

20.7342 56.7780 1,125.411 964.329 56.00

16.9842 54.2780 921.868 100.794 1.00

1.857 54.278 104.243 - 54.00


15.99

0.000 56.135 - - 0+350


52.00
Bidang persamaan
Reference level
50.00

ELEVASI RENCANA

56.251
60.235

55.278
56.135
ELEVASI TANAH ASLI
64.00 64.00
J ARAK (m) 5.60 8.70 6.80 7.00

62.00 62.00

JUMLAH 4,803.833 4,860.375


60.00 60.00
2.25 2.00 3.75 2.00 1.00
LUAS= x . y- y . x 28.271 M2
+ 58.278 1
2 58.00 58.00 1
Batu Uk.> 1.000 Kg
1.50

BATU Uk > 1000 Kg 56.00 56.00 + 55.778


2.60

x y x.y y.x 4.51


1.50
+ 54.278 + 54.2
54.00 54.00
0.000 54.278 - 122.126 4.70 6.30

2.250 55.778 125.501 237.057 0+350 0+350


4.250 55.778 247.682 446.224 Bidang persamaan 52.00 52.00
Bidang persamaan
8.000 58.278 466.224 582.780 Reference level Reference level
50.00 50.00
10.0000 58.2780 572.767 641.134
11.0013 57.2767 628.438 585.368 ELEVASI RENCANA ELEVASI RENCANA

10.2200 57.1240 580.271 482.926

56.251
60.235

55.278
60.235

55.278
56.135

56.135

57.124
8.454 56.778 458.866 267.084 ELEVASI TANAH ASLI ELEVASI TANAH ASLI

JARAK (m) JARAK (m) 5.60 8.70 5.60 6.80 8.70 7.00 6
56.251
60.235

55.278
60.235

55.278
56.135

56.135

57.124
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

4.704 54.278 255.324 - JARAK (m) JARAK (m) 5.60 8.70 5.60 6.80 8.70 7.00 6
0.000 54.278 - -
- -
Diperiksa :
JUMLAH 3,335.072 3,364.698 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 14.813 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI
64.00 64.00

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR
62.00 62.00

BATU UK 250 - 1000 Kg 60.00 60.00


2.25 2.00 3.75 2.00
x y x.y y.x
+ 58.278
58.00 58.00
0.000 0.000 - -
1.50
0.000 0.000 - - Geotextile
0.000 0.000 - - 56.00 56.00 + 55.778

0.000 0.000 - - 1.50 4.51


+ 54.278
0.000 0.000 - -
54.00 54.00
4.70 6.30

0+350 0+350
52.00 52.00
Bidang persamaan Bidang persamaan
JUMLAH - - level
Reference Reference level
50.00 50.00

LUAS= x . y- y . x - M2
ELEVASI RENCANA ELEVASI RENCANA
2

56.251
60.235

55.278
60.235

55.278

56.135
56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) 64.00 J ARAK (m) 64.00 5.60 8.70 5.60 6.80 8.70 7.00

62.00 62.00
GEOTEXTILE
Perapi
( 4.70 + 4.51 + 2.60 ) 60.00 60.00 Permukaan

11.81 M'
58.00 58.00

Galian Galian

56.00 56.00

1.00 1.00
54.00 54.00
15.99 15.99

MERAPIKAN PERMUKAAN TANGGUL 0+350 0+350


52.00 52.00
Bidang persamaan Bidang persamaan
( 6.13 )
Reference level Reference level
6.13 M' 50.00 50.00

ELEVASI RENCANA ELEVASI RENCANA

56.251
60.235

55.278

56.251
60.235

55.278
56.135

56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 5.60 8.70 8.70 6.80 6.80 7.00
ELEVASI RENCANA ELEVASI RENCANA

56.251
60.235

55.278

56.251
60.235

55.278
56.135

56.135
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

J ARAK (m) J ARAK (m) 5.60 5.60 8.70 8.70 6.80 6.80 7.00

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+375 GALIAN
x y x.y y.x

0.000 56.042 - 330.648


5.900 55.678 334.860 812.899
14.6000 56.7560 833.441 1,191.876
21.0000 57.0850 1,203.766 1,415.160
24.7904 57.3222 1,355.489 1,193.689
20.8242 54.6780 1,138.626 74.581
1.364 54.678 76.441 -
0.000 56.042 - -

JUMLAH 4,942.624 5,018.852

LUAS= x . y- y . x 38.114 M2
2

BATU Uk > 1000 Kg


x y x.y y.x

0.000 54.678 - 123.026


2.250 56.178 126.401 238.757
4.250 56.178 249.382 449.424
8.000 58.678 469.424 586.780
10.0000 58.6780 574.803 657.059
11.1977 57.4803 641.875 498.354
8.670 57.322 474.058 269.643
4.704 54.678 257.205 -
0.000 54.678 - -

Diperiksa :
JUMLAH 2,793.147 2,823.042 PENGAWAS PEKERJAAN

LUAS= x . y- y . x 14.947 M2
2 0
0
PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

BATU UK 250 - 1000 Kg


x y x.y y.x

0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -

JUMLAH - -

LUAS= x . y- y . x - M2
2

GEOTEXTILE

M'

MERAPIKAN PERMUKAAN TANGGUL

M'
Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader

PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+025 GALIAN
x y x.y y.x

0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -

JUMLAH - -

LUAS= x . y- y . x - M2
2

BATU Uk > 1000 Kg


x y x.y y.x
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
Diperiksa :
JUMLAH - - PENGAWAS PEKERJAAN

LUAS= x . y- y . x - M2
2 0
0

PERHITUNGAN VOLUME
NAMA PEKERJAAN : PEMBANGUNAN BANGUNAN PANTAI GP. SANE KEC. LHOONG KAB. ACEH BESAR (OTSUS ACEH)
LOKASI/PROPINSI : KABUPATEN ACEH BESAR
PELAKSANA : PT. BINA YUSTA AZ ZUHRI

NOMOR
PATOK
PERHITUNGAN VOLUME SKET GAMBAR

0+025 BATU UK 250 - 1000 Kg


x y x.y y.x

0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -
0.000 0.000 - -

JUMLAH - -

LUAS= x . y- y . x - M2
2
GEOTEXTILE

M'

MERAPIKAN PERMUKAAN TANGGUL

M'

Diperiksa :
PENGAWAS PEKERJAAN

Yusrin, ST
Team Leader
NGAN VOLUME

SKET GAMBAR
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

3.79

Galian
2.70
53.768

54.324
54.124

57.172

11.70 14.80 2.50

Pembersihan lapangan

2.43
Galian
2.75
56.801
54.542
54.123

15.10 14.90 0.90 3.80


56.801
54.542
54.123
15.10 14.90 0.90 3.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

3.46
Galian
2.07

1.00

57.386
55.192

54.714

50 22.70 2.20 3.50

Pembersihan lapangan

3.90

3.14
Galian

1.00
58.034
57.992
54.856

55.182
55.124

9.90 5.80 1.40 3.90


57.992

58.034
54.856

55.182
55.124
9.90 5.80 1.40 3.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

5.60

Galian 2.53

1.00
55.308

56.978
55.436

57.012
10.20 11.60 1.90 5.60

Pembersihan lapangan
3.50

3.67
Galian

1.00
55.756

55.208

57.689

57.865

9.60 9.30 2.70 3.50


55.2

57.6
55.7

57.8
9.60 9.30 2.70 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

3.20

4.57
Galian

1.00
55.536

55.752

57.956

57.996

11.40 8.70 4.00 3.20

Pembersihan lapangan

Galian 3.19

1.00
56.623
55.875

55.986

56.865
56.164

10.00 5.40 5.40 2.50


56.623
55.875

55.986

56.865
56.164
10.00 5.40 5.40 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

5.67

2.66
1.41
Galian

24.19
56.261
55.923

56.574

57.124

9.20 7.70 3.70 2.60

Pembersihan lapangan

4.01

Galian

1.00

22.11
55.465

55.986

56.393

56.865

57.283

7.00 9.60 4.80 3.70 5.80


55.465

55.986

56.393

56.865

57.283
7.00 9.60 4.80 3.70 5.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

1.37
1.76
Galian

1.00

18.56

57.063
59.865

55.703

56.293

58.000
56.143

4.70 8.10 8.80 7.60

Pembersihan lapangan

5.91
1.46
Galian

1.00

13.87
55.521

56.321

56.894

57.235
55.814

60 3.40 10.10 5.70 5.90


55.521

56.321

56.894

57.235
55.814
60 3.40 10.10 5.70 5.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

6.42

Galian

1.00

15.99

56.251
55.278

58.355
56.135

57.124
5.60 8.70 6.80 7.00 6.30

Pembersihan lapangan

4.60
3.22

Galian

1.00

20.03 58.000
56.042

57.085
55.678

56.756

57.523

5.90 8.70 6.40 7.00


58.000
56.042

57.085
55.678

56.756

57.523
5.90 8.70 6.40 7.00

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Pembersihan lapangan

3.01

Galian

1.00

20.76
55.806
56.356

57.568

58.458
57.153

4.00 6.20 14.30 6.10


Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 4.00

+ 57.714

1.5 1 Batu Uk. < 250 Kg


1 1.50 1
Geotextile Batu Uk. 250 - 1.000 Kg
+ 55.214
1.5
1.50
1
+ 53.714

4.70 7.22 2.08


55.342

57.386
54.714
55.192

5.50 22.70 2.20

Timbunan
Perapian Hasil Galian
Permukaan Tanggul

8.12

0.36

an Galian

1.00
55.342

57.386
55.192

54.714

5.50 22.70 2.20 3.50


55.342

57.386
55.192

54.714
5.50 22.70 2.20 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 11.54
55.552

55.442

57.992
54.856

58.034
55.124

55.182
15.90 9.30 9.90 5.80 1.40 3.90
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 57.856
Batu Uk. < 250 Kg
1.5 1
1 1.50 1Batu Uk. 250 - 1.000 Kg
Geotextile
+ 55.356 + 55.498

1.5
+ 53.856 1 1.83

11.54
55.442

54.856

57.992

58.034
55.124

55.182
9.30 9.90 5.80 1.40 3.90

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
3.53

Galian

1.00
58.034
54.856

57.992
55.442

55.124

55.182

9.30 9.90 5.80 1.40 3.90


58.034
54.856

57.992
55.442

55.124

55.182
9.30 9.90 5.80 1.40 3.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 10.54

55.308
55.673

55.436

56.978
55.563

12.00 6.30 10.20 11.60 1.90

2.25 2.00 3.75 2.00

+ 58.308 Batu Uk. < 250 Kg

1.5 1
Batu Uk.> 1.000 Kg
1 1.50 1

+ 55.808 + 55.925

1.5
1 2.45
+ 54.308

10.54
55.308

56.978
55.673

55.436

57.012

6.30 10.20 11.60 1.90 5.60


55.308

56.978
55.673

55.436

57.012
6.30 10.20 11.60 1.90 5.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.308
Batu Uk. < 250 Kg
1.5 1
1 1.50 1 Batu Uk. 250 - 1.000 Kg
Geotextile
+ 55.808 + 55.925

1.5
1 2.45
+ 54.308

10.54
55.673

55.308

56.978
55.436

57.012
10.20 11.60 1.90 5.60

Perapian
Permukaan Tanggul
Timbunan
8.26 Hasil Galian

1.59

Galian

1.00
55.308
55.436

56.978
55.673

57.012

10.20 11.60 1.90 5.60


55.308
55.436

56.978
55.673

57.012
10.20 11.60 1.90 5.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 8.91

55.208
56.862

55.986

55.856

55.756

57.689
6.00 8.40 9.20 9.60 9.30 2.70

2.25 2.00 3.75 2.00

+ 58.208 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50 + 56.645

+ 55.708
1.5
1 3.60
+ 54.208
8.91
55.208
55.856

55.756

57.689

57.865

9.20 9.60 9.30 2.70 3.50


55.208
55.856

55.756

57.689

57.865
9.20 9.60 9.30 2.70 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.208
1
1.5 1 Batu Uk. 250 - 1.000 Kg
1 1.50 + 56.645
Geotextile
+ 55.708 Batu Uk. < 250 Kg
1.5
1 3.60
+ 54.208
8.91

55.208

57.689

57.865
55.856

55.756

9.20 9.60 9.30 2.70 3.50

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
5.55
0.73

Galian

1.00
55.856

55.756

55.208

57.689

57.865

9.60 9.30 2.70 3.50


55.208
55.856

55.756

57.689

57.865
9.60 9.30 2.70 3.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian
Galian

1.00

20.00 8.61
56.485

55.856

55.536

55.752

57.956
56.124

8.50 9.00 7.90 11.40 8.70 4.00

2.25 2.00 3.75 2.00

+ 58.536 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50
+ 56.450
+ 56.036
1.5
1 3.97
+ 54.536 56.450
4.70 3.91
55.856

55.536

55.752

57.956

57.996

7.90 11.40 8.70 4.00 3.20


55.856

55.536

55.752

57.956

57.996
7.90 11.40 8.70 4.00 3.20

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.536
1 Batu Uk. < 250 Kg
1.5 1 Batu Uk. 250 - 1.000 Kg
1 1.50
Geotextile + 56.450
+ 56.036
1.5
1 3.97
+ 54.536 56.450
4.70 3.91
55.856

55.752

57.956

57.996
55.536

90 11.40 8.70 4.00 3.20

Perapian
Permukaan Tanggul
Timbunan
4.54 Hasil Galian

0.64

lian Galian

1.00
55.536

55.752

57.956

57.996

11.40 8.70 4.00 3.20


55.536

55.752

57.956

57.996
11.40 8.70 4.00 3.20

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian Galian

1.00

20.00 11.92
56.342

55.875

55.986

56.623

56.865
56.164
56.124

11.60 9.40 10.00 5.40 5.40 2.50

2.25 2.00 3.75 2.00 2.31

+ 58.875 Batu Uk. < 250 Kg


1
1.5 1
Batu Uk.> 1.000 Kg
1 1.50
+ 56.565
+ 56.375
1.5
1.50 1.73
+ 54.875 1

4.70 7.22
55.875

55.986

56.865
56.623
56.164

9.40 10.00 5.40 5.40 2.50


55.875

55.986

56.865
56.623
56.164
9.40 10.00 5.40 5.40 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 2.31

+ 58.875 Batu Uk. < 250 Kg


1
1.5 1
1 Batu Uk. 250 - 1.000 Kg
1.50
Geotextile + 56.565
+ 56.375
1.5
1.50 1.73
+ 54.875 1

4.70 7.22
55.986

56.865
55.875

56.623
56.164

9.40 10.00 5.40 5.40 2.50

Perapian
Permukaan Tanggul
Timbunan
4.84 Hasil Galian

2.11
Galian

1.00
56.865
55.875

55.986

56.623
56.164

10.00 5.40 5.40 2.50


56.865
55.875

55.986

56.623
56.164
10.00 5.40 5.40 2.50

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

24.19

56.261
55.923

56.574
55.802
55.715

57.124
8.30 8.50 9.20 7.70 3.70 2.60
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.54

+ 58.715
1
1.5 1
1
+ 57.171
Geotextile 1.50
+ 56.215 2.89
1.5 1.41
1 1.50
+ 54.715 3.14

4.70 6.84

56.261
55.923

56.574
55.802

57.124
8.50 9.20 7.70 3.70 2.60

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
6.26

0.97

Galian

24.19
56.261
55.923

56.574

57.124

9.20 7.70 3.70 2.60


56.261
55.923

56.574

57.124
9.20 7.70 3.70 2.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

22.11

56.393

57.283
59.685

55.896

55.465

55.986

56.865
5.00 7.00 9.60 4.80 3.70 5.80

2.25 2.00 3.75 2.00 1.27

+ 58.465 Batu Uk. < 250 Kg


1
Batu Uk.> 1.000 Kg 1 + 57.194
1.50
2.78
+ 55.965

4.56
+ 54.465

4.70
55.465
55.896

55.986

56.393

56.865

57.283

5.00 7.00 9.60 4.80 3.70 5.80


55.465
55.896

55.986

56.393

56.865

57.283
5.00 7.00 9.60 4.80 3.70 5.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.27

+ 58.465
1
1 + 57.194
1.50
Geotextile 2.78
+ 55.965

4.56
+ 54.465

4.70
55.986

56.865

57.283
55.465

56.393

7.00 9.60 4.80 3.70 5.80

Perapian
Permukaan Tanggul
Timbunan
2.50 Hasil Galian

Galian

1.00

22.11
56.393

56.865

57.283
55.896

55.465

55.986

5.00 7.00 9.60 4.80 3.70 5.80


56.393

56.865

57.283
55.896

55.465

55.986
5.00 7.00 9.60 4.80 3.70 5.80

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

64.00

62.00

60.00

58.00
Galian

56.00
1.00

18.56
54.00

0
52.00
maan
l
50.00

A
55.703

58.000
59.865

56.293

57.063
56.143

ASLI

4.70 8.10 8.80 7.60

.00

.00

.00 2.25 2.00 3.75 2.00

+ 58.715 Batu Uk. < 250 Kg


1
1+ 58.000
.00 Batu Uk.> 1.000 Kg
1.50
1.37
+ 56.215 1.76
.00
3.91
+ 54.715

.00 4.70

.00

00
55.703

56.293

57.063

58.000
59.865

56.143

4.70 8.10 8.80 7.60


56.293

58.000
59.865

55.703

57.063
56.143
4.70 8.10 8.80 7.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00

+ 58.715
1
1+ 58.000
1.50
Geotextile 1.37
+ 56.215 1.76

3.91
+ 54.715

4.70
55.703

57.063
59.865

56.293

58.000
56.143

4.70 8.10 8.80 7.60

Perapian
Permukaan Tanggul Timbunan
Hasil Galian
0.72

Galian

1.00

18.56
58.000
55.703

56.293

57.063
59.865

56.143

4.70 8.10 8.80 7.60


55.703

57.063

58.000
56.293
59.865

56.143
4.70 8.10 8.80 7.60

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

13.87
55.521

56.321
59.965

56.894

57.235
55.814

5.60 3.40 10.10 5.70 5.90

2.25 2.00 3.75 2.00 1.51

+ 58.521 Batu Uk. < 250 Kg


1
Batu Uk.> 1.000 Kg 1 + 57.010
1.50

+ 56.021 3.43

1.50
+ 54.521 4.01

4.70 6.81
55.521

56.321

57.235
59.965

56.894
55.814

5.60 3.40 10.10 5.70 5.90


55.521

56.321

57.235
59.965

56.894
55.814
5.60 3.40 10.10 5.70 5.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.51

+ 58.521
1
1 + 57.010
1.50
Geotextile
+ 56.021 3.43

1.50
+ 54.521 4.01

4.70 6.81
55.521

56.321

57.235
59.965

56.894
55.814

5.60 3.40 10.10 5.70 5.90

Perapian
Permukaan Tanggul
Timbunan
5.04 Hasil Galian

1.33

Galian

1.00

13.87
55.521

56.321
59.965

56.894

57.235
55.814

5.60 3.40 10.10 5.70 5.90


55.521

56.321
59.965

56.894

57.235
55.814
5.60 3.40 10.10 5.70 5.90

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

Galian

1.00

15.99

56.251
60.235

55.278

58.355
57.124
56.135

5.60 8.70 6.80 7.00 6.30

2.25 2.00 3.75 2.00 1.00

+ 58.278 Batu Uk. < 250 Kg


1
1 + 57.277
Batu Uk.> 1.000 Kg
1.50
2.60
+ 55.778

1.50 4.51
+ 54.278

4.70 6.30
56.251
55.278

58.355
56.135

57.124

5.60 8.70 6.80 7.00 6.30


56.251
55.278

58.355
56.135

57.124
5.60 8.70 6.80 7.00 6.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR

2.25 2.00 3.75 2.00 1.00

+ 58.278 1
1 + 57.277
1.50
Geotextile 2.60
+ 55.778

1.50 4.51
+ 54.278

4.70 6.30
56.251
55.278

58.355
56.135

57.124
8.70 6.80 7.00 6.30

Perapian
Permukaan Tanggul
Timbunan
Hasil Galian
6.13

Galian

1.00

15.99
56.251
60.235

55.278

58.355
56.135

57.124

5.60 8.70 6.80 7.00 6.30


56.251
60.235

55.278

58.355
56.135

57.124
5.60 8.70 6.80 7.00 6.30

Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
NGAN VOLUME

SKET GAMBAR
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan

NGAN VOLUME

SKET GAMBAR
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan

NGAN VOLUME

SKET GAMBAR
Dihitung :
KONTRAKTOR PELAKSANA

T. AL MUNAWAR
Manager Lapangan
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 area 29.5 Potongan JT - 0 (STA 0+0


8.00 le Galian Tanah Berpasir (A
7.00 POINT X Y
6.00 at 1 0.000 0.342
5.00
4.00 4.05
3.43 4.00 4.05 2.00 at 2 0.300 0.124
4.00
? ? at 3 6.300 -0.153
3.00 + 2.700 BATU >1000
+ 2.700
1.5 1.5 at 4 11.900 -0.243
2.00 1 1
at 5 2.70 12.220 -0.250
0.79 1.00 GALIAN TANAH BERPASIR HWL + 0.79
2.00 at 6 10.050 LWL - 0.20
-2.000
0.20 0.00 5.43 1 5.43 1

-1.00
1.34 1
2.00
1.34
at
1 7 2.00 5.440 -2.000
3.94
-2.00
3.94
1.80 1.80 at 8 3.940 -1.000
J T-0 4.61 - GEOTEXTILE
2.000 4.61
at
- 2.000
9 0.000 -1.000
-3.00
Bidang persamaan
Reference level -4.00 at 10 0.000 0.342
-5.00

- 2.000
- 1.000
ELEVASI RENCANA

-0.452
-0.243

-0.243

-0.452
-0.153
0.986

0.342
0.423

-0.153
0.423
0.124

0.986

0.342
1.235

1.235

0.124
ELEVASI TANAH ASLI

JARAK (m) 8.90 4.90 6.00 0.30 8.90 6.00 5.60


4.90 6.00 10.10
0.30 6.00 5.60 10.10
F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 9.00
area 28.1 Potongan JT - 0 (STA 0+0
8.00 8.00

7.00 7.00
le Batu UK 1.000 Kg
6.00 6.00 POINT X Y
5.00 5.00 at 1 0.000 0.415
4.00 4.05 3.43 4.00 4.05 2.00
4.00 4.00 at 2 3.430 2.700
? ?
3.00 3.00 + 2.700
1.5
BATU >1+ 2.700
000
1.5
atBATU >1000
3 7.430 2.700
2.00 2.00 1 1 at 4 11.480 0.000
2.70
1.00 HWL + 0.79 1.00
2.00
at 5 13.480HWL + 0.790.000
1
at 1 1 6
LWL - 0.20
0.00
15.480 -2.000
0.00 LWL - 0.20 5.43 5.43
1.34 1 1.34
-1.00 -1.00 2.00 2.00
3.94 3.94 at 7 10.870 -2.000
-2.00 -2.00 1.80 1.80
J T-0 GEOTEXTILE
4.61 - 2.000 at4.61 8 - 2.000 6.820 0.700
-3.00 -3.00
Bidang persamaan
Reference level -4.00
at 9 4.030 0.700
-4.00
-5.00 -5.00 at 10 3.530 0.368

- 2.000
- 1.000
ELEVASI RENCANA at 11 0.000 0.415

-0.243
-0.243

-0.452
-0.153
0.423
-0.153
0.986

0.342
0.423

0.342
0.986

0.124
1.235

0.124
1.235

ELEVASI TANAH ASLI

8.90 6.00 4.90 5.606.00 0.30 6.00 5.60 10.10


J ARAK (m) 8.90 4.90 6.00 0.30 10.10
F=
9.00 9.00

8.00 8.00

7.00 7.00 area 23.6 Potongan JT - 0 (STA 0+0


6.00 6.00 le Pemasangan Batu Uk. < 25
5.00 5.00
4.00 4.05 3.43 4.00 4.05 2.00 POINT X Y
4.00 4.00
? ? at 1 0.000 0.368
3.00 3.00 + 2.700 + 2.700 BATU >1000
2.00 2.00
1.5
1
1.5
1 at 2 0.500 0.700
1.00 HWL + 0.79 1.00 at 3
2.70
3.290
HWL + 0.79 0.700
2.00
0.00 LWL - 0.20 0.00 5.43 15.43 1 at 4 5.840 LWL - 0.20 -1.000
1.34 1 1.34 1
-1.00 -1.00
3.94
2.00
3.94 at 5
2.00
1.890 -1.000
-2.00 -2.00 1.80 1.80
+050 JT-0 GEOTEXTILE
4.61
GEOTEXTILE - 2.000 4.61 - 2.000
-3.00 -3.00
persamaan Bidang persamaan
9.00 9.00

8.00 8.00

7.00 7.00

6.00 6.00

5.00 5.00
4.00 4.05 3.43 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 BATU >1000
1.5 1.5
2.00 2.00 1 1
2.70
1.00 HWL + 0.79 1.00 HWL + 0.79
2.00
0.00 LWL - 0.20 0.00 5.43 15.43 1 LWL - 0.20
1.34 1 1.34 1
-1.00 -1.00 2.00 2.00
3.94 3.94
1.80 1.80
+050
-2.00
JT-0
-2.00
4.61
GEOTEXTILE - 2.000 4.61 at - 2.000 6 1.890 0.342
-3.00 -3.00 GEOTEXTILE
persamaan Bidang persamaan at 7 0.000 0.368
ce level -4.00 Reference level -4.00
-5.00 -5.00

- 2.000
- 1.000
NCANA ELEVASI RENCANA

F=

-0.243

-0.452
-0.153
0.986

0.423

0.342

-0.243

-0.452
1.235

0.124

-0.153
0.342
0.986

0.423
1.235

0.124
NAH ASLI ELEVASI TANAH ASLI

JARAK (m) 8.90 4.90 6.00


8.90 0.30 6.00
4.90 5.60
6.00 0.30 6.00 10.10 5.60 10.10
Pasangan Geotextile (Non Woven)
( 5.43 + 1.34 + 3.94 + 1.80 + 4.61 )
DATA PENDUKUNG

PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167 Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

area 18.7 Potongan STA JT - 1 (STA0+


9.00
le Galian Tanah Berpasir (A
8.00
POINT X Y
7.00

6.00
at 1 0.000 1.859
5.00
at 2 3.900 1.653
4.00 4.05 3.00 4.00 4.05 2.00
4.00 at 3 5.700 1.563
? ?
3.00 + 2.700 + 2.700 BATU >1000 4
at 8.100 1.346
1.5 1.5
2.00 1 1 at 5 8.500 0.865
GALIAN TANAH BERPASIR 2.70
HWL + 0.79 1.00 at 6 12.600HWL + 0.79 0.236
2.00
LWL - 0.20 0.00
6.39
1
1
6.39
at 1 1 7 17.100 -0.268
LWL - 0.20

GEOTEXTILE
-1.00 4.87 2.00 4.87 at 8 2.00 17.870 -0.291
JT-1
-2.00
4.61 - 2.000 at
4.61
9 - 2.000 15.750 -2.000
-3.00
Bidang persamaan at 10 11.140 -2.000
Reference level -4.00
-5.00 at 11 7.090 0.700
at 12 1.160 0.700

- 2.000
0.700
ELEVASI RENCANA
at 13 0.000 1.859

-0.268

-0.458

-0.268

-0.458
0.865

0.236

0.865

0.236
1.756

1.689

1.859

1.653

1.563

1.346

1.689

1.859

1.653

1.563

1.346
1.756

ELEVASI TANAH ASLI

JARAK (m) 8.10 6.20 3.90 1.80


8.10 2.40 0.40 4.10 6.20 4.50 3.90 6.20
1.80 2.40 0.40 4.10 4.50 6.20

F=
DATA PENDUKUNG

PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167 Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00
area 27.6 Potongan STA JT - 1 (STA0+
8.00
le Batu UK 1.000 Kg
7.00
POINT X Y
6.00
at 1 0.000 0.700
5.00
4.00 4.05 3.00 4.00 4.05 at 2.002 3.000 2.700
4.00
? ? at 3 7.000 2.700
3.00 + 2.700 BATU >1000 + 2.700 BATU >1000
1.5 1.5 at 4 11.050 0.000
2.00 1 1
at 5 13.0502.70 0.000
+ 0.79 1.00 HWL + 0.79
6.39
2.00
6.39
at 6 15.050 -2.000
- 0.20 0.00 1 1 LWL -

GEOTEXTILE
1 at 7 1 10.440 -2.000
-1.00 4.87 2.00 4.87 2.00
at 8 6.390 0.700
-2.00
JT-1 4.61 - 2.000 at 9
4.61 0.000
- 2.000 0.700
-3.00
Bidang persamaan
Reference level -4.00
-5.00

- 2.000
0.700
ELEVASI RENCANA

-0.268
-0.268

-0.458

-0.458
0.236
0.865
0.865

0.236
1.756

1.859
1.689

1.653

1.563

1.346
1.756

1.653

1.563
1.689

1.859

1.346

ELEVASI TANAH ASLI

J ARAK (m) 8.10 6.20 3.90 8.10 2.40 0.40


1.80 4.10 6.20 4.50 3.90 1.80
6.20 2.40 0.40 4.10 4.50 F6.20
=

9.00 9.00

8.00 8.00 area 20.4 Potongan STA JT - 1 (STA0+


7.00 7.00 le Pemasangan Batu Uk. < 25
6.00 6.00 POINT X Y
5.00 5.00
4.00 4.05 3.00 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 BATU >1000
1.5 1.5
2.00 2.00 1 1
2.70
1.00 HWL + 0.79 1.00 HWL + 0.79
2.00
6.39 6.39
0.00 LWL - 0.20 0.00 1 1 LWL -
9.00 9.00

8.00 8.00

7.00 7.00

6.00 6.00

5.00 5.00
4.00 4.05 3.00 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 BATU >1000
1.5 1.5
2.00 2.00 1 1
2.70
1.00 HWL + 0.79 1.00 HWL + 0.79
2.00
6.39 6.39
0.00 LWL - 0.20 0.00 1 1 LWL -
1 1
1.00 -1.00 GEOTEXTILE GEOTEXTILE
4.87 2.00 4.87 2.00

2.00 -2.00
J T-1 4.61 - 2.000 4.61 - 2.000
3.00 -3.00
Bidang persamaan
4.00 Reference level -4.00
5.00 -5.00 F=

- 2.000
0.700
ELEVASI RENCANA
Pasangan Geotextile (Non Woven)

-0.268

-0.458

-0.268

-0.458
0.865

0.236
0.865

0.236
1.689

1.859

1.653

1.563

1.346
1.756
1.859

1.653

1.563
1.756

1.689

1.346
ELEVASI TANAH ASLI ( 6.39+ 4.87 + 4.61 )
JARAK (m) 8.10 6.20 3.90 8.10 1.80 2.40 0.40 6.20
4.10 3.90
4.50 1.80 2.40 0.40
6.20 4.10 4.50 6.20
DATA PENDUKUNG

PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167 Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 area 24.1 Potongan JT - 2 (STA 0+0


8.00 le Galian Tanah Berpasir (A
7.00 POINT X Y
6.00 at 1 0.000 1.512
5.00
4.00 4.05 2.22 4.00 4.05
at 2.00
2 0.600 0.914
4.00
? ?
at 3 1.600 0.785
3.00 + 2.700
1.5
+ 2.700
1.5 at 4 >1000 5.900
BATU 0.235
1
2.00 1
at
4.87 5 10.500 -0.235
2.70
GALIAN TANAH BERPASIR
L + 0.79 1.00 3.71
2.00
3.71 at 6 12.690 -0.349
HWL + 0.79
2.51 2.51
1
7 11
- 0.20 0.00
1 at 10.650 -2.000 LWL - 0.2
-1.00 2.00 2.00
4.54 4.54
at 8 6.040 -2.000
-2.00
JT-2
1.80
4.61 - 2.000
GEOTEXTILE at
1.80
9
4.61 4.540
- 2.000 -1.000
-3.00
Bidang persamaan at 10 0.000 -1.000
Reference level -4.00
-5.00 at 11 0.000 1.512

- 2.000
- 1.000
ELEVASI RENCANA

-0.235

-0.568
-0.235

-0.568

0.785

0.235
0.785

0.235

0.914
1.326
1.785

1.785
1.326

0.914

1.215

1.512
1.215

1.512

ELEVASI TANAH ASLI

J ARAK (m) 10.70 3.70 3.70 0.60


1.00 4.30 10.70 4.60 6.40
3.70 3.70 0.60
1.00 4.30 4.60 6.40 F=
DATA PENDUKUNG

PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167 Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN


9.00

8.00 area 28.0 Potongan JT - 2 (STA 0+0


7.00 le Batu UK > 1.000 Kg
6.00 POINT X Y
5.00
4.00 4.05 2.22 4.00 4.05
at 2.00
1 0.000 1.222
4.00
? at 2 2.220 2.700
?
3.00 + 2.700
1.5
BATU >1000 + 2.700
1.5 at 3
BATU >1000 6.220 2.700
1
2.00 1 at
4.87 4 10.270 2.70
0.000
1.00 HWL + 0.79
HWL + 0.79 3.71
2.00
3.71
at 5 12.270 0.000
2.51 2.51
0.00 1 1 LWL - 0.2
LWL - 0.20
1 at 6 1 14.270 -2.000
-1.00 2.00 2.00
4.54 4.54 at 7 9.660 -2.000
-2.00 1.80
JT-2 1.80
4.61 - 2.000
GEOTEXTILE at 8
4.61 5.610
- 2.000 0.700
-3.00
Bidang persamaan at 9 3.620 0.700
Reference level -4.00
-5.00 at 10 3.620 1.512
at 11 0.000 1.222

- 2.000
- 1.000
ELEVASI RENCANA

-0.568

-0.568
-0.235

-0.235
0.785

0.235
0.785

0.235
1.785

1.326

0.914
1.785

1.326

0.914
1.512
1.215

1.215

1.512
ELEVASI TANAH ASLI

J ARAK (m) 10.70 3.70 3.70 0.60


1.00 10.704.30 4.60 3.70 6.40
3.70 0.60
1.00 4.30 4.60 6.40
F=
00 9.00
00 8.00
00 7.00 area 23.5 Potongan JT - 2 (STA 0+0
00 6.00 le Pemasangan Batu Uk. < 25
00 5.00 4.00 4.05 2.22 4.00 4.05 2.00
POINT X Y
00 4.00
? ?
at 1 0.000 0.700
00 3.00 + 2.700
1.5
+ 2.700
1.5 at
BATU >1000 2 1.990 0.700
00 1 1
2.00
4.87 at 3 2.70
4.540 -1.000
00 HWL + 0.79 1.00 HWL + 0.79
3.71
2.51
2.00
3.71
2.51
at 4 0.000 -1.000
00 LWL - 0.20 0.00 1 1 LWL - 0.20
1 1
00 -1.00 2.00 2.00
4.54 4.54
00 9.00
00 8.00
00 7.00
00 6.00
00 5.00
4.00 4.05 2.22 4.00 4.05 2.00
00 4.00
? ?
00 3.00 + 2.700 + 2.700 BATU >1000
1.5 1.5
00 2.00 1 1
4.87
2.70
00 HWL + 0.79 1.00 3.71 HWL + 0.79
3.71
2.00
2.51 2.51
00 LWL - 0.20 0.00 1 1 LWL - 0.20
1 1
00 -1.00 2.00 2.00
4.54 4.54
00 -2.00 1.80 1.80

00
J T-2 GEOTEXTILE 4.61
GEOTEXTILE - 2.000 4.61 - 2.000
-3.00
Bidang persamaan
00 Reference level -4.00
00 -5.00

- 2.000
- 1.000
ELEVASI RENCANA F=

-0.568
-0.235

-0.235

-0.568
0.785

0.235

0.785

0.235
1.785

1.326

0.914
1.785

1.326

0.914
1.215

1.512

1.215

1.512
ELEVASI TANAH ASLI
Pasangan Geotextile (Non Woven)
10.70 3.70 3.70 10.70
0.60
1.00 4.30 3.70 4.60 3.70 0.60 6.40
1.00 4.30 4.60
J ARAK (m)
( 3.71 + 2.51 + 4.54 +6.40
1.80 + 4.61)
DATA PENDUKUNG
PEMERINTAH ACEH
DINAS PENGAIRAN Kegiatan
Pekerjaan
: Pembangunan Prasarana Penga
: Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Lokasi : Kab. Aceh Besar
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 9.00
area 27.6 Potongan JT-3 (STA 0+0
8.00 8.00
le Batu UK > 1.000 Kg
7.00 7.00
POINT X Y
6.00 6.00
at 1 0.000 -0.665
5.00 5.00 4.05 2.00
2.00 4.05 4.00 2.00 4.05 4.00 4.05
at
2.00
2 0.670 0.000
4.00 4.00
? ? at 3 2.670 0.000
3.00 3.00 + 2.700 + 2.700
BATU >1000 BATU >1000
1.5
1.5
1
at 4 6.720 2.700
2.00 2.00 BATU < 1250
1.00 1.00 HWL + 0.79
2.70 4.87
HWL + 0.79
2.70 4.87 2.70 at
HWL + 0.79
5 2.70 10.720 HWL +2.700
0.79

0.00 0.00 LWL - 0.20 - 0.665 LWL - 0.20 - 0.665 1


at 1 6
LWL - 0.20
14.770 0.000
LWL - 0.20
0.66 0.66 1 - 1.321 1.32 1 - 1.321 1.32
-1.00 -1.00
at 7 16.770 0.000
-2.00 -2.00 18.09 18.09
at 8 18.090 -1.300
JT-3 at 9 16.520 -1.360
-3.00 -3.00
Bidang persamaan
-4.00 Reference level -4.00 at 10 13.030 -1.240
-5.00 -5.00 at 11 10.110 0.700
ELEVASI RENCANA at 12 7.320 0.700
at 13 4.800 -0.999
-0.568

-0.986
-0.568

-0.450

-0.986
-0.450

-1.325

-1.365

-1.246

-1.425
-1.235
-1.325

-1.235

-1.365

-1.425
-1.246
-1.215
-1.215
ELEVASI TANAH ASLI
at 14 4.620 -0.986
JARAK (m) 8.50 6.00 8.50 4.10 1.40 6.00
2.60 3.80 4.10 4.301.40 2.60 4.60 3.80 at 15
4.30 0.000
4.60 -0.665

9.00 9.00
8.00 8.00
7.00 7.00 F=
6.00 6.00
5.00 5.00
2.00 4.05 4.00 4.05 4.05 2.00
2.00 4.00 4.05 2.00
4.00 4.00
? ?
area 21.7 Potongan JT-3 (STA 0+0
3.00 3.00 + 2.700
1.5
+ 2.700
1.5 le >1000
BATU Pemasangan Batu Uk. < 25
2.00 2.00 BATU < 250 BATU < 2501 1 POINT X Y
2.70 4.87 2.70 4.87 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 - 0.665 LWL - 0.20 - 0.665 1 LWL1 - 0.20 LWL - 0.20
9.00 9.00
8.00 8.00
7.00 7.00
6.00 6.00
5.00 5.00
2.00 4.05 4.00 4.05 4.05 2.00
2.00 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 BATU >1000
1.5 1.5
2.00 2.00 BATU < 250 BATU < 2501 1
2.70 4.87 2.70 4.87 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79
at 1 0.000HWL + 0.79
-0.999
LWL - 0.20 - 0.665 LWL - 0.20 - 0.665 1 LWL1 - 0.20
0.00 0.00
0.66 0.66 1 - 1.321 1.32 at 2
1 - 1.321 2.550 0.700
LWL - 0.20
1.32
1.00 -1.00
at 3 5.340 0.700
2.00 -2.00
JT-3
18.09 18.09
at 4 8.260 -1.246
3.00 -3.00
Bidang persamaan at 5 5.340 -1.215
4.00 Reference level -4.00
5.00 -5.00
at 6 3.940 -1.325
at 7 0.000 -0.999
ELEVASI RENCANA

-0.568

-0.986
-0.450

-1.235

-1.425
-1.325

-1.365

-1.246
6

-1.215
-0.568

-0.986
-0.450

-1.325

-1.235

-1.246
-1.365

-1.425
-1.215
ELEVASI TANAH ASLI

J ARAK (m) 8.50 6.00 8.50 4.10 1.40 6.00


2.60 3.80 4.10 1.40
4.30 2.60 3.80
4.60 4.30 4.60
F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga
DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Lokasi : Kab. Aceh Besar
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 9.00 area 22.8 Potongan JT-4 (STA 0+1


8.00 8.00 le Batu UK > 1.000 Kg
7.00 7.00 POINT X Y
6.00 6.00 at 1 0.000 -1.543
5.00 5.00
2.00 4.05 2.00
4.00 4.05 4.05 4.00
2.00 4.05 2.00 at 2 1.540 0.000
4.00
4.00
? ? at 3 3.540 0.000
3.00 3.00 + 2.700 + 2.700
1.5 1.5 at 4 7.590 2.700
2.00 2.00 BATU < 250 4.87 1
1
BATU >1000
2.70 2.70
4.87 BATU >1000
2.70 at
2.70 5 11.590 2.700
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 LWL - 0.20 LWL - 0.20 1 1 LWL - 0.20


at 6 LWL
15.640
- 0.20
0.000
0.00
1 1 1 - 1.253
-1.00 -1.00 1.54 - 1.543 1 1.54 - 1.543 1
1 - 1.253 1.25 at
1.25 7 17.640 0.000
-2.00 -2.00 at 8 18.890 -1.200
JT-4 18.90 18.90
at 9 14.620 -1.720
-3.00 -3.00
aan Bidang persamaan
-4.00 Reference level -4.00 at 10 10.990 0.700
-5.00 -5.00
at 11 8.200 0.700
ELEVASI RENCANA
A
at 12 4.790 -1.576
at 13 0.000 -1.543

-1.890

-1.369
-1.458

-1.536

-1.587

-1.734

-1.253
-1.536
-1.458

-1.587

-1.734

-1.890

-1.253

-1.369

-1.412
SLI ELEVASI TANAH ASLI

JARAK (m) 9.40 9.40 7.60 3.10 7.60 3.50 3.105.80 3.50 5.80 5.80 5.80 11.00 11.00

9.00 9.00 F=
8.00 8.00

7.00 7.00

6.00 6.00 area 4.19 Potongan JT-4 (STA 0+1


5.00 5.00
2.00 4.05 4.00 2.00 4.05
4.05 2.00 4.00 4.05 2.00 le Pemasangan Batu Uk. < 25
4.00 4.00
? ? POINT X Y
3.00 3.00 + 2.700 + 2.700
1.5 1.5 at 1 0.000 -1.576
2.00 2.00 BATU < 250 BATU < 250 14.87 1
BATU >1000
1.00
2.70
HWL + 0.79
4.87
2.70 2.70 at
2.70 2
HWL + 0.79
3.410 0.700
1.00 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 1LWL - 0.20 at 3 LWL 6.200
- 0.20 0.700
1 1 1 - 1.253 1 - 1.253 1.25
1.54 - 1.543 1 1.54 - 1.543 1 1.25
-1.00 -1.00

-2.00
9.00 9.00

8.00 8.00

7.00 7.00

6.00 6.00

5.00 5.00
2.00 4.05 4.00 2.00 4.05
4.05 2.00 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
2.00 2.00 BATU < 250 BATU < 250 14.87 1
4.87 BATU >1000
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 1LWL - 0.20 LWL - 0.20
1 1 1 - 1.253 1 - 1.253
-1.00 -1.00 1.54 - 1.543 1 1.54 - 1.543 1 1.25
at
1.25
4 9.840 -1.722
-2.00 -2.00 at 5 8.310 -1.890
J T-4 18.90 18.90

maan
-3.00
Bidang persamaan
-3.00 at 6 4.810 -1.734
el -4.00
-5.00
Reference level -4.00
-5.00
at 7 1.710 -1.587
at 8 0.000 -1.576
NA ELEVASI RENCANA

-1.734
-1.458

-1.536

-1.587

-1.253

-1.369
-1.458

-1.536

-1.587

-1.890

-1.253

-1.369
-1.734

-1.890

-1.412
ASLI ELEVASI TANAH ASLI

JARAK (m) 9.40 7.60


9.40 3.10 3.50
7.60 5.80
3.10 3.50 5.80 5.80 15.80
1.00 11.00 F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga
DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 area 28.1 Potongan JT-5 ( STA 0+1


8.00 le Batu UK 1.000 Kg
7.00
POINT X Y
6.00
at 1 0.000 -1.382
5.00
2.00 4.05 4.00 4.05
2.00 2.00
4.05 4.00 4.05 2.00 at 2 1.380 0.000
4.00

3.00 + 2.700
? ? at 3 3.380 0.000
+ 2.700
1.5 1.5
2.00 BATU 1< 250 1 at 4 7.430 2.700
4.87 4.87 BATU >1000 BATU >1000
1.00 HWL + 0.79
2.70
HWL + 0.79
2.70 2.70
HWL + 0.79 at
2.70
5 HWL + 0.79 11.430 2.700
0.00LWL - 0.20
1
LWL - 0.20 1 LWL - 0.201 at 6 LWL15.480
- 0.20 0.000
1 1 1
1.38 - 1.382 1 - 1.382 1
at 7 17.480 0.000
1.38
-1.00 - 1.638 1.64 - 1.638 1.64

J T-5
-2.00
19.12 19.12
at 8 19.120 -1.638
Bidang persamaan
-3.00
at 9 15.930 -1.563
Reference level -4.00
-5.00 at 10 14.140 -1.506
ELEVASI RENCANA
at 11 10.830 0.700
at 12 8.040 0.700
-1.386

-1.356

-1.582

-1.486

-1.563

-1.582

-1.486

-1.689

-1.972
-1.356

-1.386
-1.442

-1.689

-1.442

-1.563
-1.972
ELEVASI TANAH ASLI
at 13 4.690 -1.532
J ARAK (m) 8.90 4.90 8.90
3.50 2.70 3.80
4.90 3.50
5.30 2.70 6.30
3.80 5.30 at 14
6.30 1.030 -1.386
9.00
at 15 0.000 -1.382
9.00

8.00 8.00

7.00 7.00 F=
6.00 6.00

5.00 5.00
2.00 4.05 4.00 4.05 2.00
area 23.7 Potongan JT-5 ( STA 0+1
2.00 4.05 4.00 4.05 2.00
4.00 4.00
?
le Pemasangan Batu Uk. < 25
?
3.00 3.00 + 2.700
1.5
+ 2.700
1.5 POINT X Y
2.00 2.00 BATU < 250 4.87
BATU < 2501 4.87
1
at 2.70 1
BATU >1000 0.000 -1.532
2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79
at 2 3.350
HWL + 0.79
0.700
0.00 LWL - 0.20 1 LWL 1- 0.20 LWL - 0.20
0.00 LWL - 0.20
1.38 - 1.382 1
1 1.38 - 1.382 1
1 1 1 at 3 6.140 0.700
-1.00 -1.00 - 1.638 1.64 - 1.638 1.64

2.00 -2.00
J T-5 19.12 19.12
9.00 9.00

8.00 8.00

7.00 7.00

6.00 6.00

5.00 5.00
2.00 4.05 4.00 2.00 4.05 4.05 2.00 4.00 4.05 2.00
4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
2.00 2.00 BATU < 250 BATU < 2501 1
4.87 4.87 BATU >1000
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 LWL 1- 0.20 LWL - 0.20
1 1 1 1
1.38 - 1.382 1 1.38 - 1.382 1 - 1.638 1.64
-1.00 -1.00 - 1.638 1.64
at 4 9.450 -1.506
2.00 -2.00
J T-5 19.12 19.12 at 5 7.440 -1.442
3.00 -3.00
Bidang persamaan
-4.00
at 6 4.740 -1.486
4.00 Reference level
5.00 -5.00 at 7 1.240 -1.582
ELEVASI RENCANA at 8 0.000 -1.532
-1.356

-1.386

-1.582

-1.486

-1.442

-1.563

-1.689

-1.972
-1.386

-1.486

-1.442

-1.689
-1.356

-1.582

-1.563

-1.972
ELEVASI TANAH ASLI

J ARAK (m) 8.90 4.90 8.90 3.50 2.70 4.903.80 3.50 5.30 2.70 3.80
6.30 5.30 6.30 F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga
DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

9.00 9.00
area 24.9 Potongan JT-6 (STA 0+1
8.00 8.00
le Pemasangan Batu Uk. > 1.0
7.00 7.00

6.00
POINT X Y
6.00

5.00 5.00
at 1 0.000 -1.615
4.002.00 4.05 2.00 4.00 4.05 2.00
4.00 4.00
2.00 4.05 4.05
at 2 1.620 0.000
? ?
3.00 3.00 + 2.700 + 2.700 at 3 3.620 0.000
1.5 1.5
2.00 2.00 4.87 BATU < 250 1
4.87 BATU >1000
1
BATU >1 at
000 4 7.670 2.700
2.70 2.70
HWL + 0.79 at 5 11.670 2.700
2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 1 LWLat - 0.20 6 15.720LWL - 0.20 0.000
1 1 1 1
1.61 - 1.615 1 1.61 - 1.615 1 - 1.554 1.55 - 1.554 1.55
-1.00 -1.00 at 7 17.720 0.000
-3
-2.00
JT-6
-2.00
at 8 19.270 -1.554
-3.00 -3.00 19.27 19.27
ersamaan Bidang persamaan at 9 14.320 -1.474
e level -4.00 Reference level -4.00
-5.00 -5.00 at 10 11.060 0.700
NCANA ELEVASI RENCANA
at 11 8.270 0.700
at 12 5.200 -1.345
-1.893

-1.356

-1.756

-1.325

-1.253

-1.356

-1.468

-1.325

-1.253

-1.568

-1.468

-1.568
-1.893

-1.756

-1.689

-1.689
NAH ASLI ELEVASI TANAH ASLI
at 13 3.370 -1.356
J ARAK (m) 8.60 5.20
8.60 5.20 1.10
5.20 4.30 5.20 6.20
1.10 4.30 10.20
6.20 at 14 10.200.000 -1.615

9.00 9.00

8.00 8.00 F=
7.00 7.00

6.00 6.00 area 9.23 Potongan JT-6 (STA 0+1


5.00 5.00
2.00 4.05 4.00 2.00 4.05
4.05 2.00 4.00 4.05 2.00 le Pemasangan Batu Uk. < 25
4.00 4.00 ? ? POINT X Y
3.00 3.00 + 2.700 + 2.700
1.5 1.5 at 1 0.000 -1.345
2.00 2.00 BATU < 250 BATU < 250 1 1
BATU >1000
at 2 3.070 0.700
4.87 4.87
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 1 LWL - 0.20 at 3 LWL 5.860
- 0.20
0.700
1 1 1 1
-1.00 -1.00 1.61 - 1.615 1 1.61 - 1.615 1 - 1.554 1.55 - 1.554 1.55

-2.00 -2.00
9.00 9.00

8.00 8.00

7.00 7.00

6.00 6.00

5.00 5.00
2.00 4.05 4.00 2.00 4.05
4.05 2.00 4.00 4.05 2.00
4.00 4.00 ? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
2.00 2.00 BATU < 250 BATU < 250 1 1
4.87 4.87 BATU >1000
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 1 1 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 -1.00 1.61 - 1.615 1 1.61 - 1.615 1 - 1.554 1.55 - 1.554 1.55 at 4 9.120 -1.474
-2.00 -2.00 at 5 8.760 -1.468
J T-6
maan
-3.00
Bidang persamaan
-3.00 19.27 19.27
at 6 4.460 -1.253
el -4.00
-5.00
Reference level -4.00
-5.00
at 7 3.360 -1.325
at 8 0.000 -1.345
NA ELEVASI RENCANA
6
-1.756

-1.325

-1.253

-1.468

-1.568

-1.689
-1.893

-1.893

-1.356

-1.356

-1.468

-1.568

-1.689
-1.756

-1.325

-1.253
ASLI ELEVASI TANAH ASLI

JARAK (m) 8.60 5.208.60 5.20 1.10


5.20 4.30 5.20 6.20
1.10 4.30 10.20
6.20 10.20 F=
DATA PENDUKUNG

PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga

DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai


Aceh)

Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167 Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Jenis Pekerjaan Revetment

5.10 SKET GAMBAR


2.00 4.05 5.10 4.002.00 4.05
4.05 2.00
4.00 4.11 4.05 2.00 4.11 PERHITUNGAN

4.00 4.00
? ? area 28.1 Potongan JT-7 (STA 0+1
3.00 3.00 + 2.700 + 2.700
le Pemasangan Batu Uk. > 1.0
1.5 1.5 1.5 1.5
2.00 2.00
2.70 2.70
1 11 4.87 BATU >1000 1 4.87
2.70
BATU >1000 POINT
2.70
X Y
1.00 1.00 HWL + 0.79 HWL + 0.79 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79
at 1 0.000 -5.098
0.00 0.00LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20

1
1
1
1 1
1
1
1 at 2 5.100 0.000
-1.00 -1.00

-2.00 -2.00 4.11


at 4.11 3 7.100 0.000
-3.00 -3.00
5.10 5.10
at 4 11.150 2.700
- 4.114 - 4.114
-4.00 -4.00 at 5 15.150 2.700
- 5.098 - 5.098
-5.00 -5.00 - 4.267 - 4.267 at 6 19.200 0.000
- 4.933 - 4.933
-6.00 -6.00 at 7 21.200 0.000
-7.00
JT-7
-7.00
at 8 25.310 -4.114
-8.00
maan
-8.00
Bidang persamaan at 9 22.050 -4.263
el -9.00 Reference level -9.00
-10.00 -10.00 at 10 21.990 -4.267
A ELEVASI RENCANA
at 11 14.540 0.700
at 12 11.750 0.700
-5.625

-5.236

-4.856

-4.859

-4.736

-4.652

-4.263

-3.985

-3.759
-5.625

-4.856

-4.859

-4.263
-5.236

-4.736

-4.652

-3.985

-3.759
ELEVASI TANAH ASLI
ASLI
at 13 3.300 -4.930
JARAK (m) 4.20 7.60 4.20 5.70 7.60 2.60 2.705.70 2.60
6.20 2.70 6.10 6.20 5.00 6.10at 14 5.00 0.000 -5.098
5.10 2.00 4.05 5.10 4.002.00 4.05
4.05 2.004.00 4.11 4.05 2.00 4.11

4.00 4.00
? ?
3.00 3.00 + 2.700
F=
+ 2.700

2.00 1.5 1.5 1.5 1.5


2.00 1 11 1 4.87 BATU >1000
2.70 4.87 2.70
1.00
2.70
BATU < 250
HWL + 0.79 BATU < 250 + 0.700
2.70
HWL + 0.79
1.00 HWL + 0.79 + 0.700 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20


1 1
LWL - 0.20 area 23.6 LWL - 0.20 Potongan JT-7 (STA 0+1
1 1
-1.00 -1.00 1 1 1 1
le Pemasangan Batu Uk. < 25
-2.00 -2.00
5.10 5.10
4.11 4.11
POINT X Y
-3.00
-3.00
- 4.114 - 4.114 at 1 0.000 -4.933
-4.00 -4.00

-5.00
- 5.098 - 5.098
- 4.267 - 4.267
at 2 8.450 0.700
-5.00
- 4.933 - 4.933
-6.00 -6.00
5.10 2.00 4.05 5.10 4.002.00 4.05
4.05 2.004.00 4.11 4.05 2.00 4.11

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700

2.00 1.5 1.5 1.5 1.5


2.00 1 11 1 4.87 BATU >1000
2.70 4.87 2.70
1.00
2.70 BATU < 250
HWL + 0.79 BATU < 250 + 0.700
2.70
HWL + 0.79
1.00 HWL + 0.79 + 0.700 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 1 1 1 1
-1.00

-2.00 -2.00 4.11 4.11


5.10 5.10
-3.00 -3.00
- 4.114 - 4.114
-4.00 -4.00
- 5.098 - 5.098
-5.00 - 4.267 - 4.267
-5.00

-6.00 -6.00
- 4.933 - 4.933
at 3 11.240 0.700
-7.00 -7.00 at 4 18.690 -4.260
4 J T-7
rsamaan
-8.00
Bidang persamaan
-8.00 at 5 12.540 -4.652
level -9.00
-10.00
Reference level -9.00
-10.00
at 6 9.840 -4.736
ELEVASI RENCANA
at 7 7.240 -4.859
CANA
at 8 1.540 -4.856
-5.625

-5.236

-4.856

-4.859

-4.736

-4.652

-4.263

-3.985

-3.759
-5.625

-5.236

-4.859

-4.736

-4.263

-3.985
-4.856

-4.652

-3.759
AH ASLI ELEVASI TANAH ASLI
at 9 0.000 -4.933
JARAK (m) 4.20 7.60 4.20 5.707.60 2.60 2.705.70 2.60
6.20 2.70 6.10 6.20 5.00 6.10 5.00

F=
DATA PENDUKUNG
PEMERINTAH ACEH
DINAS PENGAIRAN
Kegiatan : Pembangunan Prasarana Penga
Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Lokasi : Kab. Aceh Besar
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN


6.43 2.00 6.43
4.05 2.00
4.00 4.05 4.05 4.00
2.00 5.02
4.05 2.00 5.02

area 28.1 Potongan JT-8 (STA 0+2


4.00 4.00 le Pemasangan Batu Uk. > 1.0
? ?
3.00 3.00 + 2.700 + 2.700 POINT X Y
1.5 1.5
1.5 1.5
2.00 2.00 1 1 1 4.87 BATU >10001 4.87 BATU >1000 at 1 0.000 -6.431
2.70 2.70 2.70 2.70
BATU < 250
1.00 1.00 HWL + 0.79 HWL + 0.79 + 0.700 + 0.700 HWL + 0.79
at 2
HWL + 0.79
6.430 0.000
0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1
1
1
1 1
1
1
1
at 3 8.430 0.000
-1.00 -1.00
at 4 12.480 2.700
-2.00 -2.00

-3.00 -3.00
5.02
at
5.02
5 16.480 2.700
6.43 6.43

-4.00 -4.00
- 5.020
at
- 5.020
6 20.530 0.000
-5.00 -5.00 at 7 22.530 0.000
- 6.431 - 6.431
-6.00 -6.00 - 5.253 - 5.253
at 8 27.550 -5.020
T-5
-7.00
J T-8
-7.00 - 6.409 - 6.409
at 9 24.880 -5.245
-8.00 -8.00
persamaan Bidang persamaan
at 10 24.810 -5.250
ce level -9.00 Reference level -9.00
-10.00 -10.00 at 11 15.880 0.700
NCANA ELEVASI RENCANA at 12 13.090 0.700
at 13 2.420 -6.400
-6.457

-5.245
-6.457
-6.425

-6.425

-6.325

-6.357

-6.325

-5.845

-5.845

-4.756

-5.245

-4.756
-6.357
NAH ASLI ELEVASI TANAH ASLI
at 14 1.180 -6.425
JARAK (m) 6.70 7.90
6.70 5.40
7.90 4.80 5.40 5.60 4.80 5.80 5.60 5.80
at 15 0.000 -6.430
6.43 2.00 6.43
4.05 2.00
4.00 4.05 4.05 4.00
2.00 4.05
5.02 2.00 5.02

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 F=
1.5 1.5
1.5 1.5
2.00 2.00 1 1 1 BATU >1000
1 4.87 4.87
2.70 2.70 BATU < 250 2.70 2.70
1.00 HWL + 0.79BATU < 250 HWL + 0.79
area 23.6 Potongan JT-8 (STA 0+2
1.00 HWL + 0.79 + 0.700 + 0.700 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20

-1.00 -1.00 1
1
1
1 1
1
1
1 le Pemasangan Batu Uk. < 25
-2.00 -2.00 POINT X Y
5.02 5.02
-3.00 -3.00 6.43 6.43 at 1 0.000 -6.409
-4.00 -4.00
- 5.020 - 5.020 at 2 10.660 0.700
-5.00 -5.00
- 6.431 - 6.431
-6.00 -6.00 - 5.253 - 5.253
6.43 2.00 6.43
4.05 2.00
4.00 4.05 4.05 4.00
2.00 4.05
5.02 2.00 5.02

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
1.5 1.5
2.00 2.00 1 1 1 BATU >1000
1 4.87 4.87
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79BATU < 250 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 -1.00 1 1 1 1

-2.00 -2.00
5.02 5.02
-3.00 -3.00 6.43 6.43

-4.00 -4.00
- 5.020 - 5.020
-5.00 -5.00

-6.00 -6.00
- 6.431 - 6.431
- 5.253 - 5.253
at 3 13.450 0.700
-7.00 -7.00 - 6.409 - 6.409 at 4 22.380 -5.250
T-5 J T-8
persamaan
-8.00
Bidang persamaan
-8.00 at 5 16.860 -5.845
ce level -9.00
-10.00
Reference level -9.00
-10.00
at 6 12.060 -6.357
ENCANA ELEVASI RENCANA
at 7 6.660 -6.325
at 8 0.000 -6.409
-6.457

-6.325

-6.357
-6.425

-5.845

-5.245

-4.756
-6.457

-6.425

-6.325

-6.357

-5.845

-5.245

-4.756
ANAH ASLI ELEVASI TANAH ASLI

JARAK (m) 6.70 6.70


7.90 5.40
7.90 4.80 5.40 5.60 4.80 5.805.60 5.80

F=
DATA PENDUKUNG
PEMERINTAH ACEH
DINAS PENGAIRAN
Kegiatan : Pembangunan Prasarana Penga
Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Lokasi : Kab. Aceh Besar
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

area 28.4 Potongan JT-9 (STA 0+2


6.76 4.05 2.004.00 4.05 4.002.00 4.05 2.00 5.85
6.76 2.00 4.05 5.85
le Pemasangan Batu Uk. > 1.0
4.00
POINT X Y
4.00 ?
3.00 3.00 + 2.700
?
+ 2.700 at 1 0.000 -6.760
2.00 2.00
1
1.5
1
1.5
1.5
1
1.5
1 4.87
BATU >1000 BATU >1000 at 2 6.760 0.000
2.70 4.87 2.70
2.70 BATU < 250 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 + 0.700 + 0.700 HWL + 0.79 at
HWL + 0.79
3 8.760 0.000
0.00 LWL - 0.20 LWL - 0.20
at 4 12.810 2.700
0.00 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 1 1 1 1
-1.00

-2.00 -2.00
at 5 16.810 2.700
-3.00 -3.00
6.76
5.85 5.85 at 6 20.860 0.000
6.76
-4.00 -4.00 at 7 22.860 0.000
-5.00 -5.00 - 5.848 - 5.848
at 8 28.710 -5.848
-6.00 -6.00 - 6.760 - 6.760

-7.00
- 6.024 - 6.024 at 9 26.290 -6.024
-7.00
T-6 J T-9 - 6.838 - 6.838
at 10 16.200 0.700
-8.00 -8.00
g persamaan Bidang persamaan
ence level -9.00 Reference level -9.00 at 11 13.420 0.700
-10.00 -10.00
at 12 2.110 -6.830
RENCANA ELEVASI RENCANA
at 13 0.000 -6.760
-6.321
-6.568

-6.875

-6.754

-6.886

-6.475

-5.432
-6.321
-6.568

-6.875

-6.475

-6.125

-5.432
-6.754

-6.886

-6.125
ANAH ASLI ELEVASI TANAH ASLI

m) J ARAK (m) 8.30 8.30


4.60 5.10 4.60 2.00 5.10 6.10 2.00 4.00 6.10 4.00
9.50 9.50

F=

6.76 2.00 6.76 4.05 2.004.00 4.05 4.05 4.002.00 4.055.85 2.00 5.85 area 23.8 Potongan JT-9 (STA 0+2
le Pemasangan Batu Uk. < 25
4.00 4.00
? ? POINT X Y
3.00 3.00
at 1 0.000 -6.838
+ 2.700 + 2.700
1.5 1.5
1.5 1.5
2.00 2.00 1 1 1 4.87 1 BATU >1000
1.00 1.00 HWL + 0.79
2.70
HWL + 0.79
2.70
BATU < 250 BATU < 250 + 0.700 + 0.700
4.87
2.70
HWL + 0.79
2.70
HWL + 0.79
at 2 11.310 0.700
0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWLat
- 0.20 3 14.100 0.700
1 1 1 1
-1.00 -1.00 1 1 1 1

-2.00 -2.00
6.76 2.00 6.76 4.05 2.004.00 4.05 4.05 4.002.00 4.055.85 2.00 5.85

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
1.5 1.5
2.00 2.00 1 1 1 4.87 1 BATU >1000
4.87
2.70 2.70 BATU < 250 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 -1.00 1 1 1 1
at 4 24.180 -6.020
-2.00
at 5 22.800 -6.125
-2.00

-3.00 -3.00 5.85 5.85

-4.00 -4.00
6.76 6.76
at 6 18.800 -6.475
-5.00 -5.00 - 5.848 - 5.848 at 7 12.700 -6.886
-6.00 -6.00 - 6.760 - 6.760
- 6.024 - 6.024
at 8 10.700 -6.754
-7.00 -7.00
T-6 J T-9 - 6.838 - 6.838 at 9 5.600 -6.321
-8.00 -8.00
persamaan
nce level -9.00
Bidang persamaan
Reference level -9.00
at 10 1.000 -6.875
-10.00 -10.00
at 11 0.000 -6.838
ENCANA ELEVASI RENCANA
-6.321

-6.321
-6.568

-6.875

-6.886

-6.475
-6.754

-5.432
-6.568

-6.875

-6.754

-6.886

-6.475

-5.432
-6.125

-6.125
ANAH ASLI ELEVASI TANAH ASLI

) JARAK (m) 8.30 4.60


8.30 5.10 4.60 2.00 5.10 6.10 2.00 4.00 6.10 4.00
9.50 9.50 F=
DATA PENDUKUNG
PEMERINTAH ACEH
DINAS PENGAIRAN
Kegiatan : Pembangunan Prasarana Penga
Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247) Lokasi : Kab. Aceh Besar
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

7.01 2.00 4.05


7.01
4.00
2.00 4.05
4.05 2.00
4.00
6.20
4.05 2.00 6.20 area 28.1 Potongan JT-10 (STA 0+2
le Pemasangan Batu Uk. > 1.0
4.00 4.00 ? ? POINT X Y
3.00 + 2.700
+ 2.700
at 1 0.000 -7.014
3.00
1.5 1
1.5
.5 1.5
2.00 2.00 1 1 BATU >1000
1 4.87 1 4.87 BATU >1000
1.00 1.00 HWL + 0.79
2.70
HWL + 0.79
2.70 BATU < 250 + 0.700 + 0.700
2.70
HWL + 0.79 2.70
HWL + 0.79
at 2 7.010 0.000
0.00 0.00 LWL - 0.20 LWL - 0.20
1 1 1 1
LWL - 0.20 at - 0.20
LWL 3 9.010 0.000
1 1 1 1
-1.00 -1.00 at 4 13.060 2.700
-2.00 -2.00
-3.00
at 5 17.060 2.700
-3.00 6.20 6.20

-4.00 -4.00
7.01 7.01
at 6 21.110 0.000
-5.00 -5.00 at 7 23.110 0.000
- 6.200 - 6.200
-6.00 -6.00 - 7.014 - 7.014 at 8 29.310 -6.200
-7.00 -7.00
at 9 27.010 -6.337
- 6.337 - 6.337
-7 JT-10 - 6.904 - 6.904
-8.00 -8.00
ersamaan
at 10 16.460 0.700
Bidang persamaan
e level -9.00 Reference level -9.00
-10.00 -10.00
at 11 13.670 0.700
CANA ELEVASI RENCANA
at 12 2.260 -6.900
at 13 0.000 -7.014
-7.253

-6.423
-6.875

-6.759

-6.665

-6.423

-5.863
-6.875

-6.759

-6.665

-6.578

-5.863
-7.253

-6.578
NAH ASLI ELEVASI TANAH ASLI

JARAK (m) 7.80 7.80


7.40 7.40
4.80 5.00 4.80 5.50 5.00 5.509.40 9.40

F=
7.01 2.00 7.01 4.05 2.00 4.00 4.05 4.05 4.00 2.00 4.05 6.20 2.00 6.20

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700 area 23.6 Potongan JT-10 (STA 0+2
1.5 1.51.5
2.00 2.00 1 1 1 4.87
1.5
1 4.87 BATU >1000 le Pemasangan Batu Uk. < 25
2.70 BATU
2.70 < 250 2.70 2.70
BATU < 250
1.00 1.00 HWL + 0.79 HWL + 0.79 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79
POINT X Y
0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20

-1.00 1
1
1
1 1
1
1
1 at 1 0.000 -6.904
-1.00
-2.00 -2.00 at 2 11.410 0.700
-3.00 -3.00
7.01 7.01
6.20 6.20 at 3 14.200 0.700
-4.00 -4.00
at 4 24.750 -6.330
-5.00 -5.00
- 6.200 - 6.200
-6.00 -6.00
- 7.014 - 7.014
7.01 2.00 7.01 4.05 2.00 4.00 4.05 4.05 4.00 2.00 4.05 6.20 2.00 6.20

4.00 4.00
? ?
3.00 + 2.700 + 2.700
3.00
1.5 1.51.5 1.5
2.00 2.00 1 1
1 4.87 1 4.87 BATU >1000
2.70 BATU
2.70 < 250 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 1 1 1 1
-1.00
-2.00 -2.00
-3.00 -3.00 6.20 6.20
7.01 7.01
-4.00 -4.00

-5.00 -5.00

-6.00 -6.00
- 6.200 - 6.200 at 5 23.300 -6.423
- 7.014
at 6 18.460 -6.578
- 7.014
-7.00 -7.00 - 6.337 - 6.337
JT-7 JT-10 - 6.904 - 6.904
ng persamaan
-8.00
Bidang persamaan
-8.00 at 7 12.800 -6.665
rence level -9.00
-10.00
Reference level -9.00
-10.00
at 8 8.000 -6.759
RENCANA ELEVASI RENCANA
at 9 0.600 -6.875
at 10 0.000 -6.904
-7.253

-6.665

-6.578

-5.863
-6.875

-6.759

-6.423
-7.253

-6.875

-6.578
-6.759

-6.665

-6.423

-5.863
TANAH ASLI ELEVASI TANAH ASLI

m) JARAK (m) 7.80 7.80 7.40 7.40


4.80 5.004.80 5.00
5.50 5.50 9.40 9.40
F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga
DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

area 28.1 Potongan JT-11 (STA 0+2


le Pemasangan Batu Uk. > 1.0
POINT X Y
7.37 2.00 7.37 4.05 2.004.00 4.05 4.05 4.00 2.00 4.05 6.66 2.00 6.66
at 1 0.000 -7.368
4.00 4.00
? ?
at 2 7.370 0.000
3.00 3.00 + 2.700
1.5
+ 2.700
1.5
1.5 1.5
at 3 9.370 0.000
2.00 2.00

1.00 1.00 HWL + 0.79


2.70
HWL + 0.79
2.70
1
BATU < 250
1
+ 0.700
1 4.87 BATU >11000
+ 0.700
4.87 BATU >1000
2.70
HWL + 0.79
2.70
HWL + 0.79
at 4 13.420 2.700
0.00 0.00 LWL - 0.20 LWL - 0.20
1 1 1 1
LWL - 0.20 LWL at
- 0.20 5 17.420 2.700
-1.00 -1.00 1 1 1 1
at 6 21.470 0.000
-2.00 -2.00

-3.00 -3.00
at 7 23.470 0.000
6.66 6.66
-4.00 -4.00
7.37 7.37 19.480 19.480
at 8 30.130 -6.600
-5.00 -5.00
at 9 27.930 -6.700
-6.00 -6.00 - 6.660 - 6.660

-7.00 -7.00
- 7.368 - 7.368 at 10 16.810 0.700
JT-8 J T-11 - 7.290
- 6.712 - 6.712
at 11 14.020 0.700
-8.00 -8.00 - 7.290
Bidang persamaan Bidang persamaan
Reference level -9.00
-10.00
Reference level -9.00
-10.00
at 12 2.040 -7.290
VASI RENCANA ELEVASI RENCANA
at 13 0.000 -7.368
-6.851

-6.641

-6.641
-7.542

-6.997

-6.924

-6.759

-6.851
-7.268
-7.542

-7.268

-6.997

-6.924

-6.759
VASI TANAH ASLI ELEVASI TANAH ASLI

AK (m) J ARAK (m) 7.20 6.50


7.20 6.30
6.50 6.10
6.30 4.406.10 5.00 4.40 5.00
F=
7.37 2.00 7.37 4.05 2.00 4.00 4.05 4.05 4.00 2.00 4.05 6.66 2.00 6.66
area 23.6 Potongan JT-11 (STA 0+2
4.00 4.00
? ?
le Pemasangan Batu Uk. < 25
3.00 3.00 + 2.700
1.5
+ 2.700
1.51.5 1.5
POINT X Y
2.00 2.00 1 1
1.00 1.00 HWL + 0.79
2.70
HWL + 0.79
2.70
BATU < 250 BATU < 250
1
+ 0.700
4.87
+ 0.700
1 4.87 BATU >1000
2.70
HWL + 0.79
2.70
HWL + 0.79
at 1 0.000 -7.290
0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20at 2 11.990 0.700
1 1 1 1
1 1 1 1
-1.00 -1.00
at 3 14.770 0.700
-2.00 -2.00

-3.00 -3.00
at 4 25.890 -6.710
6.66 6.66
7.37 7.37 19.480 19.480
-4.00 -4.00

-5.00 -5.00
7.37 2.00 7.37 4.05 2.00 4.00 4.05 4.05 4.00 2.00 4.05 6.66 2.00 6.66

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.51.5 1.5
2.00 2.00 1 1
1 4.87 1 4.87 BATU >1000
2.70 2.70 < 250
BATU 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 1 1 1 1
-1.00

-2.00 -2.00

-3.00 -3.00
6.66 6.66

at 5 23.880 -6.759
7.37 7.37 19.480 19.480
-4.00 -4.00

at 6 19.480 -6.851
-5.00 -5.00

-6.00 -6.00 - 6.660 - 6.660

-7.00 -7.00
- 7.368 - 7.368
at 7 13.380 -6.924
JT-8 J T-11 - 6.712 - 6.712

Bidang persamaan
-8.00
Bidang persamaan
-8.00 - 7.290 - 7.290
at 8 7.080 -6.997
Reference level -9.00 Reference level -9.00
-10.00 -10.00 at 9 0.580 -7.268
ELEVASI RENCANA ELEVASI RENCANA at 10 0.000 -7.290

-6.851

-6.641
-6.851

-6.641
-7.268

-6.997

-6.924

-6.759
-7.542
-7.542

-7.268

-6.759
-6.997

-6.924
ELEVASI TANAH ASLI ELEVASI TANAH ASLI

ARAK (m) JARAK (m) 7.20 7.20


6.50 6.50
6.30 6.30
6.10 6.10
4.40 5.004.40 5.00 F=
DATA PENDUKUNG
PEMERINTAH ACEH Kegiatan : Pembangunan Prasarana Penga
DINAS PENGAIRAN Pekerjaan : Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN


7.40 2.00 4.05 4.00 4.05 2.00 6.71
7.40 2.00 4.05 4.00 4.05 2.00 6.71

area 28.1 Potongan JT-12 (STA 0+3


4.00
4.00
3.00
?
+ 2.700
? le Pemasangan Batu Uk. > 1.0
3.00 + 2.700

2.00 2.00
1
1.5
1
1
1.5
.5
1
1.5
1 4.87
BATU >1000 BATU >1000
POINT X Y
2.70 4.87 2.70
BATU < 250
at 1 0.000 -7.402
1.00 2.70 HWL + 0.79 + 0.700 2.70 HWL + 0.79
1.00 HWL + 0.79 + 0.700 HWL + 0.79

0.00 LWL - 0.20 LWL - 0.20


at 2 7.400 0.000
0.00 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 1 1 1 1
-1.00

-2.00 -2.00 at 3 9.400 0.000


-3.00 -3.00
7.40 7.40
6.71 6.71 at 4 13.450 2.700
-4.00 -4.00

-5.00 -5.00
at 5 17.450 2.700
-6.00 -6.00 - 6.712 - 6.712 at 6 21.500 0.000
- 7.402
at 7 23.500 0.000
- 7.402
-7.00 -7.00
JT-9 J T-12 - 6.815 - 6.815
-8.00 -8.00 - 7.361 - 7.361
dang persamaan
eference level -9.00
Bidang persamaan
Reference level -9.00
at 8 30.210 -6.710
-10.00 -10.00
at 9 28.120 -6.810
ELEVASI RENCANA
at 10 16.850 0.700
ASI RENCANA
- 7.274
- 7.274

-- 7.238
- 7.238
-7.564

-7.283

- 7.104

-6.999

-6.492
-7.564

-7.283

7.104

-6.492
-6.999
-7.412

-7.412

ASI TANAH ASLI ELEVASI TANAH ASLI


at 11 14.060 0.700
K (m) JARAK (m) 4.40 6.00 4.40 7.00
6.00 2.70 7.00 4.00 2.70 5.50 4.00 5.509.70 9.70
at 12 2.020 -7.361
at 13 0.000 -7.402
7.40 2.00 7.40 4.05 2.00
4.00 4.05 4.05 4.00
2.00 4.05
6.71 2.00 6.71

4.00 4.00 F=
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
1.5 1.5
2.00 2.00
2.70 2.70
1 1 1 4.87 1 4.87
2.70
BATU >1000 area
2.70
23.6 Potongan JT-12 (STA 0+3
1.00 HWL + 0.79 BATU < 250 BATU < 250 HWL + 0.79
le Pemasangan Batu Uk. < 25
1.00 HWL + 0.79 + 0.700 + 0.700 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20

-1.00 -1.00 1
1
1
1 1
1
1
1 POINT X Y
-2.00 -2.00 at 1 0.000 -7.322
-3.00 -3.00
6.71 6.71
at 2 12.030 0.700
7.40 7.40
-4.00 -4.00
at 3 14.820 0.700
-5.00 -5.00
- 6.712
at 4 26.100 -6.810
-6.00 -6.00 - 6.712
- 7.402 - 7.402
-7.00 -7.00
T-9 J T-12 - 6.815 - 6.815
-8.00 -8.00 - 7.361 - 7.361
7.40 2.00 7.40 4.05 2.00
4.00 4.05 4.05 4.00
2.00 4.05
6.71 2.00 6.71

4.00 4.00
? ?
3.00 3.00 + 2.700 + 2.700
1.5 1.5
1.5 1.5
2.00 2.00 1 1 4.87 1 BATU >1000
1 4.87
2.70 2.70 2.70 2.70
1.00 1.00 HWL + 0.79 HWL + 0.79 BATU < 250 BATU < 250 + 0.700 + 0.700 HWL + 0.79 HWL + 0.79

0.00 0.00 LWL - 0.20 LWL - 0.20 LWL - 0.20 LWL - 0.20
1 1 1 1
-1.00 -1.00 1 1 1 1

-2.00 -2.00

-3.00 -3.00
6.71 6.71
7.40 7.40
-4.00 -4.00

-5.00 -5.00

-6.00 -6.00 - 6.712 - 6.712

-7.00 -7.00
- 7.402 - 7.402 at 5 22.930 -6.699
T-9 J T-12 - 6.815 - 6.815

g persamaan
-8.00
Bidang persamaan
-8.00 - 7.361 - 7.361 at 6 17.430 -7.104
ence level -9.00
-10.00
Reference level -9.00
-10.00
at 7 13.430 -7.283
RENCANA ELEVASI RENCANA
at 8 10.730 -7.238
at 9 3.730 -7.274

- 7.274
- 7.274

- 7.238

-- 7.238

- 7.104
7.104

-7.283

-6.999

-6.492
-7.564

-7.564

-7.283

-6.999

-6.492
-7.412
-7.412

TANAH ASLI ELEVASI TANAH ASLI


at 10 0.000 -7.322
m) J ARAK (m) 4.40 6.00 4.40 7.00
6.00 2.70 7.00 4.00 2.70 5.50 4.00 9.70
5.50 9.70

F=
DATA PENDUKUNG
PEMERINTAH ACEH
DINAS PENGAIRAN Kegiatan
Pekerjaan
: Pembangunan Prasarana Penga
: Pembangunan Bangunan Pantai
Aceh)
Jln. Ir. Mohd. Thaher No. 18 Telp. (0651) 21982, 21919, 24212, 22899, 33126, 21167
Lokasi : Kab. Aceh Besar
Fax. 236862 - Email sda-aceh@yahoo.com PO Box 130 LUENG BATA - BANDA ACEH (23247)
Jenis Pekerjaan Revetment

SKET GAMBAR PERHITUNGAN

B Perhitungan Penutup Ujung JT


PENAMPANG ATAS

PENAMPANG BAWAH

LUAS PENAMPANG ATAS

A A r = 8.05 M'
= 3.14
15.46

= 101.740
8.05

8.05
15.46

LUAS PENAMPANG BAWAH


BATU > 1000

B
r = 15.46 M'
= 3.14
TAMPAK ATAS = 375.248

2.00 4.05 2.00 7.40

4.00

3.00 + 2.700
PENAMPANG ATAS
2.00
2.70
TINGGI PASANGAN
1.00 HWL + 0.79
+ 0.00
0.00 LWL - 0.20
1
-1.00
8.05 1
BATU > 1000
t = 7.40 M'
-2.00
= 7.400
-3.00
7.40
-4.00

-5.00

PENUTUP -6.00
2.00 4.05 2.00 7.40

4.00

3.00 + 2.700
PENAMPANG ATAS
2.00
2.70
1.00 HWL + 0.79
+ 0.00
0.00 LWL - 0.20
1
-1.00
8.05 1
BATU > 1000
-2.00

-3.00
7.40
-4.00

-5.00

PENUTUP -6.00

JT-12 -7.00
- 7.402

-8.00 15.46
Bidang persamaan
Reference level -9.00
-10.00
PENAMPANG BAWAH

ELEVASI RENCANA

- 7.274
- 7.238
-7.283

-7.564
-7.412
ELEVASI TANAH ASLI

J ARAK (m) 2.70 7.00 6.00 4.40

POTONGAN B-B
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT - 0 (STA 0+000) 16.646 M2


Galian Tanah Berpasir (AB )
XY YX
0.000 0.102
-0.045 0.781
-1.530 -1.820
-2.975 -2.969
-24.440 -2.512
-20.100 -10.880
-5.440 -7.880
-3.940 0.000
0.000 0.000
0.000 0.000

-58.470 -25.178
16.646
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT - 0 (STA 0+000) 27.860 M2


Batu UK 1.000 Kg
XY YX
0.000 1.423
9.261 20.061
0.000 30.996
0.000 0.000
-26.960 0.000
-30.960 -21.740
7.609 -13.640
4.774 2.821
1.483 2.471
1.464 0.000
0.000 0.000

-33.329 22.392
27.860

Potongan JT - 0 (STA 0+000) 5.117 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 0.184
0.350 2.303
-3.290 4.088
-5.840 -1.890
0.646 -1.890
0.695 0.000
0.000 0.000

-7.439 2.795
5.117

17.120 M'
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan STA JT - 1 (STA0+025) 24.291 M2


Galian Tanah Berpasir (AB )
XY YX
0.000 7.250
6.095 9.422
7.672 12.660
7.006 11.441
2.006 10.899
-3.376 4.035
-4.976 -4.789
-35.740 -4.583
-31.500 -22.280
7.798 -14.180
4.963 0.812
2.156 0.000
0.000 0.000

-37.896 10.687
24.291
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan STA JT - 1 (STA0+025) 26.747 M2


Batu UK 1.000 Kg
XY YX
0.000 2.100
8.100 18.900
0.000 29.835
0.000 0.000
-26.100 0.000
-30.100 -20.880
7.308 -12.780
4.473 0.000
0.000 0.000

-36.319 17.175
26.747

Potongan STA JT - 1 (STA0+025) - M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 0.000
0.000

15.870 M'
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT - 2 (STA 0+050) 21.536 M2


Galian Tanah Berpasir (AB )
XY YX
0.000 0.907
0.471 1.462
0.376 4.631
-1.386 2.467
-3.664 -2.982
-25.380 -3.716
-21.300 -12.080
-6.040 -9.080
-4.540 0.000
0.000 0.000
0.000 0.000

-61.463 -18.391
21.536
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT - 2 (STA 0+050) 24.133 M2


Batu UK > 1.000 Kg
XY YX
0.000 2.712
5.994 16.794
0.000 27.729
0.000 0.000
-24.540 0.000
-28.540 -19.320
6.762 -11.220
3.927 2.534
5.473 2.534
4.423 0.000
0.000 0.000

-26.501 21.763
24.133

Potongan JT - 2 (STA 0+050) 5.550 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 1.393
-1.990 3.178
-4.540 0.000
0.000 0.000
-6.530 4.571
5.550

17.170 M'
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-3 (STA 0+075) 30.484 M2


Batu UK > 1.000 Kg
XY YX
0.000 -0.445
0.000 0.000
7.209 0.000
18.144 28.944
0.000 39.879
0.000 0.000
-21.801 0.000
-24.602 -21.476
-20.484 -17.720
9.121 -12.536
7.077 5.124
-7.312 3.360
-4.732 -4.615
-3.072 0.000
0.000 0.000

-40.452 20.515
30.484

Potongan JT-3 (STA 0+075) 10.723 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -2.547
1.785 3.738
-6.653 5.782
-10.035 -6.653
-7.075 -4.787
-3.936 0.000
0.000 0.000

-25.914 -4.467
10.723
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-4 (STA 0+100) 34.892 M2


Batu UK > 1.000 Kg
XY YX
0.000 -2.376
0.000 0.000
9.558 0.000
20.493 31.293
0.000 42.228
0.000 0.000
-21.168 0.000
-32.490 -17.544
10.234 -18.902
7.693 5.740
-12.923 3.353
-7.390 0.000
0.000 0.000

-25.993 43.792
34.892

Potongan JT-4 (STA 0+100) 15.556 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -5.374
2.387 4.340
-10.676 6.888
-18.597 -14.309
-14.409 -9.090
-7.633 -2.965
-2.694 0.000
0.000 0.000

-51.622 -20.510
15.556
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-5 ( STA 0+125) 34.831 M2


Batu UK 1.000 Kg
XY YX
0.000 -1.907
0.000 0.000
9.126 0.000
20.061 30.861
0.000 41.796
0.000 0.000
-28.632 0.000
-29.884 -26.093
-23.990 -22.100
9.898 -16.309
7.581 5.628
-12.317 3.283
-6.500 -1.577
-1.423 0.000
0.000 0.000
-56.080 13.582
34.831

Potongan JT-5 ( STA 0+125) 13.439 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -5.132
2.345 4.298
-9.246 6.615
-13.626 -11.204
-11.055 -6.835
-7.498 -1.842
-1.899 0.000
0.000 0.000

-40.979 -14.100
13.439
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-6 (STA 0+150) 34.502 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -2.616
0.000 0.000
9.774 0.000
20.709 31.509
0.000 42.444
0.000 0.000
-27.536 0.000
-28.403 -22.253
10.024 -16.302
7.742 5.789
-11.123 3.640
-7.051 -4.532
-5.442 0.000
0.000 0.000

-31.306 37.679
34.502

Potongan JT-6 (STA 0+150) 11.984 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -4.129
2.149 4.102
-8.637 6.384
-13.388 -12.912
-10.976 -6.547
-5.909 -4.210
-4.519 0.000
0.000 0.000

-41.280 -17.312
11.984
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-7 (STA 0+175) 59.943 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -25.999
0.000 0.000
19.170 0.000
30.105 40.905
0.000 51.840
0.000 0.000
-87.216 0.000
-107.896 -90.713
-94.087 -93.743
15.393 -62.042
10.178 8.225
-57.927 2.310
-16.823 0.000
0.000 0.000

-289.103 -169.217
59.943

Potongan JT-7 (STA 0+175) 58.584 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -41.683
5.915 7.868
-47.882 13.083
-86.945 -53.420
-59.389 -45.775
-47.812 -34.288
-35.157 -7.482
-7.596 0.000
0.000 0.000
-278.866 -161.697
58.584
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-8 (STA 0+200) 66.838 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -41.351
0.000 0.000
22.761 0.000
33.696 44.496
0.000 55.431
0.000 0.000
-113.100 0.000
-144.499 -124.897
-130.620 -130.128
17.367 -83.370
11.116 9.163
-83.776 1.694
-15.548 -7.552
-7.587 0.000
0.000 0.000

-410.190 -276.514
66.838

Potongan JT-8 (STA 0+200) 87.761 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -68.319
7.462 9.415
-70.612 15.666
-130.811 -88.515
-107.179 -70.490
-76.279 -42.337
-42.683 0.000
0.000 0.000

-420.102 -244.580
87.761
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-9 (STA 0+225) 70.062 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -45.697
0.000 0.000
23.652 0.000
34.587 45.387
0.000 56.322
0.000 0.000
-133.685 0.000
-172.949 -153.743
18.403 -97.588
11.340 9.394
-91.658 1.477
-14.263 0.000
0.000 0.000

-324.573 -184.448
70.062

Potongan JT-9 (STA 0+225) 98.949 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -77.337
7.917 9.870
-84.882 16.926
-148.102 -137.256
-147.630 -115.150
-129.456 -82.232
-85.775 -73.680
-67.634 -37.822
-38.500 -6.321
-6.838 0.000
0.000 0.000

-700.900 -503.002
98.949
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-10 (STA 0+250) 71.224 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -49.168
0.000 0.000
24.327 0.000
35.262 46.062
0.000 56.997
0.000 0.000
-143.282 0.000
-185.737 -167.462
18.907 -104.307
11.522 9.569
-94.323 1.582
-15.851 0.000
0.000 0.000

-349.175 -206.727
71.224

Potongan JT-10 (STA 0+250) 101.844 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -78.774
7.987 9.940
-89.886 17.325
-158.969 -147.489
-153.267 -118.568
-123.035 -84.198
-86.515 -53.320
-55.000 -4.055
-4.142 0.000
0.000 0.000
-662.827 -459.139
101.844
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-11 (STA 0+275) 73.067 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -54.302
0.000 0.000
25.299 0.000
36.234 47.034
0.000 57.969
0.000 0.000
-154.902 0.000
-201.871 -184.338
19.551 -112.627
11.767 9.814
-102.205 1.428
-15.030 0.000
0.000 0.000

-381.157 -235.022
73.067

Potongan JT-11 (STA 0+275) 108.949 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -87.407
8.393 10.339
-99.106 18.123
-174.990 -160.234
-163.601 -131.665
-134.879 -91.666
-93.619 -49.021
-51.457 -4.058
-4.228 0.000
0.000 0.000
-713.487 -495.589
108.949
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Potongan JT-12 (STA 0+300) 73.451 M2


Pemasangan Batu Uk. > 1.000 Kg
XY YX
0.000 -54.774
0.000 0.000
25.380 0.000
36.315 47.115
0.000 58.050
0.000 0.000
-157.685 0.000
-205.730 -188.685
19.684 -114.748
11.795 9.842
-103.495 1.414
-14.952 0.000
0.000 0.000

-388.688 -241.786
73.451

Potongan JT-12 (STA 0+300) 113.422 M2


Pemasangan Batu Uk. < 250 Kg
XY YX
0.000 -88.083
8.421 10.374
-100.924 18.270
-174.843 -156.153
-162.894 -116.763
-126.942 -95.406
-97.206 -78.146
-78.050 -26.997
-27.311 0.000
0.000 0.000
-759.749 -532.904
113.422
DATA PENDUKUNG ( BACK UP DATA )

Pembangunan Prasarana Pengaman Pantai


Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus
Aceh)

PERHITUNGAN VOLUME SATUAN

Perhitungan Penutup Ujung JT - 12

/
=^ 101.740 M2

/
= ^ 375.248 M2

7.400 M'
-
BACK UP DATA
Pemasangan Batu Uk > 1000 kg (Tutup Ujung JT-12)

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017

LUAS RATA 2 TINGGI VOLUME


NO NO PATOK
(M2) (M2) (M) ( M3 )
1 Penampang Atas 101.740
238.494 7.400 1,764.856
2 Penampang Bawah 375.248
-

TOTAL 1,764.856

Komposisi Volume Penggunaan Batu :


Batu Uk > 1000 Kg di Ambil 85 % Batu Uk > 1000 Kg = 85% x 1,764.856 =
Batu Uk > 1000 Kg di Ambil 12.5 % Untuk Batu Pengunci = 12.5% x 1,764.856 =

Total Volume Batu Uk > 1000 Kg =


KET.
1,500.128
220.607

1,500.128
REKAPITULASI
Pemasangan Batu Uk > 1000 kg (Tutup Ujung JT-12)
Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
PANJANG VOLUME
No ITEM PEKERJAAN (M) M3

1 Pemasangan Batu Uk. > 1.000 Kg 1,500.128


Diperiksa oleh : Di

Konsultan Pengawas Kontra


CV. FREEPORT CONSULTANT PT. BINA

IR. EDWARD ZEIN T. A


Chief Inspector S
REKAPITULASI
Batu Uk > 1000 kg (Tutup Ujung JT-12)
p. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)

KETERANGAN
Diajukan Oleh

Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
DAFTAR REKAPITULASI PERHITUNGAN
Kegiatan : Pembangunan Prasarana Pengaman Pantai
Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi : Kab. Aceh Besar

Luas Luas
Luas Luas
Penampang Penampang Volume (M3) Volume
No. Penampang Penampang
Jarak Pasangan Pasangan Galian Tanah Pasangan
Patok Galian Tanah Pasangan Batu
Batu Uk. < Geotextile Berpasir (AB) Uk. > 10
Berpasir (AB) Uk. > 1000 Kg
250 Kg (Non Woven)

0+000 30.484 10.723 -


25.00 - -
0+025 34.892 15.556 -
25.00 - -
0+050 34.831 13.439 -
25.00 - -
0+075 34.502 11.984 -
25.00 - -
0+100 59.943 58.584 -
25.00 - -
0+125 - 66.838 87.761 -
25.00 - -
0+150 - 70.062 98.949 -
25.00 - -
0+175 - 71.224 101.844 -
25.00 - -
0+200 - 73.067 108.949 -
13.10 - -
0+225 - 73.451 113.422 -
- -
-
- -
-
-
-
-
-
-

### -

Komposisi Volume Penggunaan Batu


1 Batu Uk > 1000 Kg di Ambil 85 % Batu Uk > 1000 Kg = 85% x
2 Batu Uk > 1000 Kg di Ambil 12.5 % Untuk Batu Pengunci = 12.5% x
3 Volume Batu Uk < 250 Kg = 97.5% x
= ### +
4 Volume Batu Uk > 1000 Kg
5 Menyediakan/Memasang Geotextile (Non Wooven)
6 Galian Tanah Berpasir (AB)

Diperiksa oleh : Diperiksa oleh :


Pengawas Lapangan Konsultan Pengawas
CV. FREEPORT CONSULTANT

TAUFIK HIDAYAT, ST. MT IR. EDWARD ZEIN


Nip. 19820808 201212 1 003 Chief Inspector
PITULASI PERHITUNGAN VOLUME

ec. Lhoong Kab. Aceh Besar (Otsus Aceh)

Volume (M2)
Volume (M3) Volume (M3)
Pasangan
Pasangan Batu Pasangan Batu Keterangan
Geotextile
Uk. > 1000 Kg Uk. < 250 Kg
(Non Woven)

817.200 328.487 -

871.537 362.437 -

866.662 317.787 -

1,180.562 882.100 -

1,584.762 1,829.312 -

1,711.250 2,333.875 -

1,766.075 2,509.912 -

1,803.637 2,634.912 -

959.692 1,456.530 -

- - -

- - -

- - -

- - -

- - -

- - -

### ### -

11,561.377 = 9,827.17 m3
11,561.377 = 1,445.17 m3
12,655.352 = 12,338.96 m3
1,445.170 = ### m3 9,899.69
= 9,827.17 m3 12,793.41
= - m2 1,800.25
= - m3 2,348.24

Err:509
` Diajukan Oleh
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
REKAPITULASI
Galian Tanah

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
PANJANG VOLUME
No ITEM PEKERJAAN
(M) M3

1 Galian Tanah Berpasir (AB) 75.00 1,353.725


Diperiksa oleh : D
Konsultan Pengawas Kontr
CV. FREEPORT CONSULTANT PT. BINA

IR. EDWARD ZEIN T. A


Chief Inspector S
I

b. Aceh Besar (Otsus Aceh)

KETERANGAN
Diajukan Oleh

Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
BACK UP DATA
Galian Tanah

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017

LUAS RATA 2 JARAK VOLUME


NO NO PATOK
(M2) (M2) (M) ( M3 )
1 JT - 0 16.646
20.468 25.00 511.700
2 JT - 1 24.291
22.913 25.00 572.825
3 JT - 2 21.536
10.768 25.00 269.200
4 JT - 3 0.000
- -

TOTAL 75.00 1,353.725


eh Besar (Otsus Aceh)

KET.
REKAPITULASI
Pemasangan Batu Uk > 1000 kg

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
PANJANG VOLUME
No ITEM PEKERJAAN (M) M3

1 Pemasangan Batu Uk. > 1.000 Kg 276.000 10,774.778


Diperiksa oleh : Diaj
Konsultan Pengawas Kontrak
CV. FREEPORT CONSULTANT PT. BINA Y

IR. EDWARD ZEIN T. AL


Chief Inspector Site
000 kg

ceh Besar (Otsus Aceh)

KETERANGAN
Diajukan Oleh

Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
BACK UP DATA
Pemasangan Batu Uk > 1000 kg

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017

LUAS RATA 2 JARAK VOLUME


NO NO PATOK
(M2) (M2) (M) ( M3 )
1 JT - 0 27.860
27.305 25.000 682.625
2 JT - 1 26.747
25.440 25.000 636.000
3 JT - 2 24.133
27.308 25.000 682.700
4 JT - 3 30.484
32.688 25.000 817.200
5 JT - 4 34.892
34.861 25.000 871.525
6 JT - 5 34.831
34.666 25.000 866.650
7 JT - 6 34.502
47.222 25.000 1,180.550
8 JT - 7 59.943
63.390 25.000 1,584.750
9 JT - 8 66.838 -
68.450 25.000 1,711.250
10 JT - 9 70.062 -
70.643 25.000 1,766.075
11 JT - 10 71.224 -
72.145 25.000 1,803.625
12 JT - 11 73.067 - -
73.259 1.000 73.259
13 JT - 12 73.451 - -

TOTAL 276.000 12,676.209

Komposisi Volume Penggunaan Batu :


Batu Uk > 1000 Kg di Ambil 85 % Batu Uk > 1000 Kg = 85% x 12,676.209 =
Batu Uk > 1000 Kg di Ambil 12.5 % Untuk Batu Pengunci = 12.5% x 12,676.209 =

Total Volume Batu Uk > 1000 Kg =


KET.
10,774.777
1,584.526

10,774.778
REKAPITULASI
Pemasangan Batu Uk > 250 kg

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
PANJANG VOLUME
No ITEM PEKERJAAN (M) M3

1 Pemasangan Batu Uk. < 250 Kg 276.000 13,160.626


Diperiksa oleh : Dia
Konsultan Pengawas Kontra
CV. FREEPORT CONSULTANT PT. BINA

IR. EDWARD ZEIN T. AL


Chief Inspector Si
250 kg

Aceh Besar (Otsus Aceh)

KETERANGAN
Diajukan Oleh

Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
BACK UP DATA
Pemasangan Batu Uk > 250 kg

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017

LUAS RATA 2 JARAK VOLUME


NO NO PATOK
(M2) (M2) (M) ( M3 )
1 JT - 0 5.117
2.558 25.000 63.950
2 JT - 1 0.000 - -
2.775 25.000 69.375
3 JT - 2 5.550 - -
8.136 25.000 203.400
4 JT - 3 10.723 - -
13.139 25.000 328.475
5 JT - 4 15.556 - -
14.497 25.000 362.425
6 JT - 5 13.439 - -
12.711 25.000 317.775
7 JT - 6 11.984 - -
35.284 25.000 882.100
8 JT - 7 58.584 - -
73.172 25.000 1,829.300
9 JT - 8 87.761 - - -
93.355 25.000 2,333.875
10 JT - 9 98.949 - - -
100.396 25.000 2,509.900
11 JT - 10 101.844 - - -
105.396 25.000 2,634.900
12 JT - 11 108.949 - - -
111.185 1.000 111.185
13 JT - 12 113.422 - - -
-

TOTAL 276.000 11,646.660

Komposisi Volume Penggunaan Batu :


Volume Batu Uk < 250 Kg 11,646.66 x 97.5% =
Volume Batu Pengunci (pada Batu Uk > 1000 Kg) =
Volume Batu Pengunci (pada Tutup Ujung JT-12) =
Total Volume Batu Uk < 250 Kg : Volume Batu Uk < 250 Kg + Volume Batu Pengunci =
KET.
11,355.493
1,584.526
220.607
13,160.626
REKAPITULASI
Pemasangan Geotextile (Non Woven)

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
PANJANG VOLUME
No ITEM PEKERJAAN (M) M3

1 Pemasangan Geotekstil ( Non Wooven ) 75.00 1,040.000


Diperiksa oleh : Dia
Konsultan Pengawas Kontra
CV. FREEPORT CONSULTANT PT. BINA

IR. EDWARD ZEIN T. AL


Chief Inspector Sit
n Woven)

Aceh Besar (Otsus Aceh)

KETERANGAN
Diajukan Oleh

Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
Site Manager
BACK UP DATA
Pemasangan Geotextile (Non Woven)

Nama Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi / Propinsi : Gp. Sane Kec. Lhoong Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017

LUAS RATA 2 JARAK VOLUME


NO NO PATOK
(M2) (M2) (M) ( M3 )
1 JT - 0 17.120
16.495 25.00 412.375
2 JT - 1 15.870
16.520 25.00 413.000
3 JT - 2 17.170
8.585 25.00 214.625
4 JT - 3 0.000
- -

TOTAL 75.00 1,040.000


n)

Aceh Besar (Otsus Aceh)

KET.

12,726,802,000.00
12,730,000,000.00
3,198,000.00
REKAP PERHITUNGAN VOLUME PEKERJAAN POKOK
REKAPITULASI VOLUME MC 100
KEGIATAN : Pembangunan Prasarana Pengaman Pantai
PEKERJAAN : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
LOKASI : Kab. Aceh Besar
TAHUN : 2017

No Uraian Pekerjaan Satuan Volume


1 2 3 4

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.000

II. PEKERJAAN POKOK


1 Galian Tanah Berpasir (AB) M3 1,353.725
2 Pemasangan Batu Uk. < 250 Kg M3 13,160.626
3 Pemasangan Batu Uk. > 1.000 Kg M3 12,274.905
4 Pemasangan Geotekstil ( Non Wooven ) M2 1,040.000

Diperiksa oleh : Diperiksa oleh : Diajukan Oleh :


Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
- CV. FREEPORT CONSULTANT PT. BINA YUSTA AZ ZUHRI
-

-
-
TAUFIK HIDAYAT, ST. MT IR. EDWARD ZEIN T. AL MUNAWAR
Nip. 19820808 201212 1 003 Chief Inspector Site Manager
TUNGAN VOLUME PEKERJAAN POKOK
APITULASI VOLUME MC 100

Keterangan
5

Diajukan Oleh :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
REKAP PERHITUNGAN VOLUME
KEGIATAN : Pembangunan Prasarana Pengaman Pantai
PEKERJAAN : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
LOKASI : Kab. Aceh Besar
TAHUN : 2017

Volume Volume
No Uraian Pekerjaan Satuan Volume ( + ) Volume ( - )
MC - 0 MC -100

1 2 3 4 5 6 7

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.00 - - 1.000

II. PEKERJAAN POKOK


1 Galian Tanah Berpasir (AB) M3 - 1,353.725 - 1,353.725
2 Pemasangan Batu Uk. < 250 Kg M3 14,900.91 1,740.283 13,160.626
3 Pemasangan Batu Uk. > 1.000 Kg M3 8,886.56 3,388.342 - 12,274.905
4 Pemasangan Geotekstil ( Non Wooven ) M2 - 1,040.000 - 1,040.000

Diperiksa oleh : Diperiksa oleh : Diajukan Oleh


Pengawas Lapangan Konsultan Pengawas Kontraktor Pelaksana
CV. FREEPORT CONSULTANT PT. BINA YUSTA AZ ZUHRI

TAUFIK HIDAYAT, ST. MT IR. EDWARD ZEIN T. AL MUNAWAR


Nip. 19820808 201212 1 003 Chief Inspector Site Manager

Disetujui Oleh :
Pejabat Pelaksana Teknis Kegiatan ( PPTK )
Pembangunan Prasarana Pengaman Pantai
Dinas Pengairan Aceh

MUHAMMAD NASIR, ST
Nip. 19660323 199211 1 001
PERHITUNGAN VOLUME

Keterangan

Diajukan Oleh
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI

T. AL MUNAWAR
REKAPITULASI KUANTITAS DAN HARGA PEKERJAAN
MUTUAL CHECK AKHIR (MC-100)

Kegiatan : Pembangunan Prasarana Pengaman Pantai


Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Lokasi : Kab. Aceh Besar
Tahun Anggaran : 2017

Volume Jumlah Harga (Rp )


Harga Satuan
No Uraian Pekerjaan Satuan
MC-0 MC - 10O ( Rp ) MC - 0

1 2 3 4 5 7 8

I PEKERJAAN PERSIAPAN 50,000,000.00


1 Mobilisasi dan Demobilisasi Ls 1.000 1.000 50,000,000.00 50,000,000.00

II. PEKERJAAN POKOK 10,491,830,328.07


1 Galian Tanah Berpasir (AB) M 3
- 1,353.725 18,385.00 -
2 Pemasangan Batu Uk. < 250 Kg M3 14,900.909 13,160.626 411,270.00 6,128,296,844.43
3 Pemasangan Batu Uk. > 1.000 Kg M3 8,886.563 12,274.905 491,026.00 4,363,533,483.64
4 Pemasangan Geotekstil ( Non Wooven ) M2 - 1,040.000 52,946.00 -

A Jumlah Harga Termasuk Biaya Umum dan Keuntungan Rp 10,541,830,328.07


B Pajak Pertambahan Nilai (PPN) = 10 % (A) Rp 1,054,183,032.81
C Jumlah (A + B ) Rp 11,596,013,360.87
D Dibulatkan Rp 11,596,013,000.00

Terbilang : Sebelas Milyar Lima Ratus Sembilan Puluh Enam Juta Tiga Belas Ribu Rupiah,-

Disetujui Oleh : Diperiksa oleh :


Pejabat Pelaksana Teknis Kegiatan ( PPTK ) Konsultan Pengawas
Pembangunan Prasarana Pengaman Pantai CV. FREEPORT CONSULTANT
Dinas Pengairan Aceh
MUHAMMAD NASIR, ST YUSRIN, ST
Nip. 19660323 199211 1 001 Team Leader
I KUANTITAS DAN HARGA PEKERJAAN
TUAL CHECK AKHIR (MC-100)

Jumlah Harga (Rp )


Keterangan
MC - 100

9 10

50,000,000.00
50,000,000.00

11,519,820,405.84
24,888,234.13
5,412,570,706.43
6,027,297,625.29
55,063,840.00

Rp 11,569,820,405.84
Rp 1,156,982,040.58
Rp 12,726,802,446.42
Rp 12,726,802,000.00

as Ribu Rupiah,-

Diajukan Oleh :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
YUSRI, MJ
Direktur Utama
LAMPIRAN BERITA ACARA MUTUAL CHECK AKHIR ( 100% )
Pekerjaan : Pembangunan Bangunan Pantai Gp. Sane Kec. Lhoong Kab. Aceh Besar (Otsus Aceh)
Lokasi : Kab. Aceh Besar
No. Kontrak / Tgl : KU.602-A/KPA-IRP/721/2017 Tanggal 7 Juni 2017
No. AMD-I / Tgl : KU.602-A/KPA-IRP/ADD 1/1341/2017, Tanggal 26 Juli 2017
Tahun Anggaran : 2017
Kegiatan : Pembangunan Prasarana Pengaman Pantai
Pelaksana : PT. BINA YUSTA AZ ZUHRI

Volume Jumlah Harga ( Rp )


Harga Satuan
No Uraian Pekerjaan Satuan
MC - 0 MC - 100 ( Rp ) MC - 0 MC - 10O

1 2 3 4 5 6 7 8

I PEKERJAAN PERSIAPAN
1 Mobilisasi dan Demobilisasi Ls 1.000 1.000 50,000,000.000 50,000,000.00 50,000,000.00

II. PEKERJAAN POKOK


1 Galian Tanah Berpasir (AB) M3 - 1,353.725 18,385.000 - 24,888,234.13
2 Pemasangan Batu Uk. < 250 Kg M3 14,900.909 13,160.626 411,270.000 6,128,296,844.43 5,412,570,706.43
3 Pemasangan Batu Uk. > 1.000 Kg M3 8,886.563 12,274.905 491,026.000 4,363,533,483.64 6,027,297,625.29
4 Pemasangan Geotekstil ( Non Wooven ) M2 - 1,040.000 52,946.000 - 55,063,840.00

A Jumlah Harga Termasuk Biaya Umum dan Keuntungan Rp 10,541,830,328.07 Rp 11,569,820,405.84


B Pajak Pertambahan Nilai (PPN) = 10 % (A) Rp 1,054,183,032.81 Rp 1,156,982,040.58
C Jumlah (A + B ) Rp 11,596,013,360.87 Rp 12,726,802,446.42
D Dibulatkan Rp 11,596,013,000.00 Rp 12,726,802,000.00
Terbilang : Dua Belas Milyar Tujuh Ratus Dua Puluh Enam Juta Delapan Ratus Dua Ribu Rupiah,-

Disetujui Oleh : Diperiksa oleh :


Pejabat Pelaksana Teknis Kegiatan ( PPTK ) Konsultan Pengawas
Pembangunan Prasarana Pengaman Pantai CV. FREEPORT CONSULTANT
Dinas Pengairan Aceh
MUHAMMAD NASIR, ST YUSRIN, ST
Nip. 19660323 199211 1 001 Team Leader
CARA MUTUAL CHECK AKHIR ( 100% )

VOLUME
Ket.
Tambah (+) Kurang (-)

9 10 11

- -

24,888,234.13 -
- 715,726,138.00
1,663,764,141.65 -
55,063,840.00 -

Rp 1,743,716,215.77 Rp 715,726,138.00

s Dua Ribu Rupiah,-

1,159,601,300.00
12,755,614,300.00 Diajukan Oleh :
Kontraktor Pelaksana
PT. BINA YUSTA AZ ZUHRI
YUSRI, MJ
Direktur Utama