You are on page 1of 1

S10 Pgina: 1

Hoja resumen

Obra 1101004 AMPLIACION Y MEJORAMIENTO DEL SERVICIO DE SANEAMIENTO BASICO EN LA CAPITAL DE


VILLA KINTIARINA Y LA COMUNIDAD DE KINTIARINA ALTA , DISTRITO DE VILLA KINTIARINA - LA
CONVENCION - CUSCO
Localizacin 080910 CUSCO - LA CONVENCION - VILLA KINTIARINA
Fecha Al 04/09/2017

Presupuesto base

001 OBRAS DE CAPTACION, CONDUCCION, TRATAMIENTO Y ALMACENAMIENTO 1,857,193.30


002 SECTOR N 1 VILLA KINTIARINA 4,267,729.86
003 SECTOR N 2 KINTIARINA ALTA 2,226,237.54
004 PLAN DE MONITOREO ARQUEOLOGICO 30,957.97

(CD) S/. 8,382,118.67

COSTO DIRECTO 8,382,118.67


GASTOS GENERALES (9.66%) 809,712.66
UTILIDAD (7%) 586,748.31
===============
SUBTOTAL 9,778,579.64
IGV (18%) 1,760,144.34
===============
SUPERVISION DE OBRA (5.38%) 450,957.98
================
PRESUPUESTO DE OBRA 11,989,681.96
================
EDUCACION SANITARIA 60,000.00
GESTION TECNICA Y ADMINISTRATIVA DE LOS SERVICIOS DE AGUA Y SANE 38,000.00
COSTO DE ELABORACION DE EXPEDIENTE TECNICO (6%) 502,927.12
=================
PRESUPUESTO TOTAL DEL PIP 12,590,609.08

Descompuesto del costo directo

MANO DE OBRA S/. 3,455,097.03


MATERIALES S/. 4,225,215.06
EQUIPOS S/. 597,005.67

SUBCONTRATOS S/. 104,801.80

Total descompuesto costo directo S/. 8,382,119.56

Nota : Los precios de los recursos no incluyen I.G.V. son vigentes al : 04/09/2017