You are on page 1of 25

HELMET

Environment Health Safety


EHS journal of L&T Construction

Volume - 5, Issue - 3 July - September 2015

Safety can be top priority ...


... only if driven from the top
Contents From the EDITOR
You can beat gravity 3 The Walk, that has been regaling audiences recently,
You can beat gravity
just by being prepared and careful! is an English film that tells the true life story of a
high-wire artist, Phillippe Petit and his dream of
just by being prepared and careful!
walking between the twin towers of the World Trade
Making it count where 8 Centre. Petit fulfilled his childhood dream but he
it really matters faced death every step of his walk on the tightrope. The constant threat of falling!
Of course, our workmen are not high-wire artists
Workers, at construction sites, face the constant risk of falling
14
but they too constantly face the threat of falling and
Elevating the standards therefore our cover story in this issue of Hemet is and with time and experience they start to believe, foolishly,
about how to be safely harnessed when working at one might add, that they will have sufficient time to regain
Going the distance 20 heights. their balance if they do fall. Studies disprove this notion for it
takes a mere 4 seconds to fall a distance of 256 feet! However,
Normally, safety is compromised at sites either
a worker can still save himself with a properly maintained
A dam good safety strategy 28 due to poor planning or improper equipment or
sheer negligence. However, at hydroelectric power
and worn safety belt or full body harness attached to a secure
anchor.
projects, while all these factors could queer the pitch,
Re-engineering the processes of 38 there is one more reason that gets added to this mix The origins of fall protection equipment date back to the early
water management which is natural disaster. Unfortunately, neither 20th century when linesmen wore body belts to scale utility
do natural disasters come with prior warning nor poles. It took several decades and disasters to understand the
can they be sensed and therefore the project team dangers of using a not-so-properly designed form of body
Building a dam? Can it be safe! 44 just has to be prepared to face if, God forbid, such belt. As these belts were loosely worn around the waist, there
Yes! But its a tall order! disasters occur. was always the danger of these belts getting pulled up to the
armpits or the forces getting directly transferred to the spine
Hydroelectric power projects are fraught with
and midsection of the falling person or, worse still, letting the
dangers because they involve taming the forces
person slip through to a fatal fall.
of nature and nature hardly ever gives in easily.
The huge calamity that befell our team at the By 1917, manufacturers began looking for a body belt that
Editor : Vinod Jacob Chacko Punatsangchhu Project in the Kingdom of Bhutan would distribute the fall arrest forces throughout the body
Associate Editor : Gopi Kannan. S when a whole mountainside decided to slip down while holding the person securely in it. With the First World
on their structures is without precedent and requires War looming large, safety professionals turned to the military
Process Owners : M. Kamarajan tremendous fortitude and innovative thinking to for inspiration and a full body harness was designed after the
Malay Kumar Mahanta evolve remedial measures so that the project can parachute. Designed to keep the falling person suspended in
Stephen Philip Storey proceed. That the calamity did not claim even a an upright position in the event of a fall, the harness was also
Ramachandran N single precious life speak volumes of the quick expected to support them while they waited to be rescued. The
K. S. Sudheesh Kumar thinking and immediate action taken by the team. most striking improvement in the full body harness was that it
The only mantra they follow, as across our several
distributed the fall arrest forces throughout the body unlike a
Technical Associates : P. Nagarajan | Gabrial Fernandez of our other projects, is to be ever prepared for the
concentration of forces at the abdomen region as in the case of
Sudarsan Rajendran most unexpected and deal with it to the best of their
conventional body belts.
Md Quaisar Imam ability.
Sathyanarayana Seelamanthula A full body harness consists of straps that pass over the
Such projects also depict high levels of human
Murali Krishnan shoulders, across the chest, and around the legs (in the pelvic
courage on a daily basis. Just imagine the pressure of
Mathivanan Palaniappan region) along with metallic buckles used to tighten the grip.
digging an underground tunnel palpably feeling the
S. Anantha Prasanna Venkatesh These straps, made of different types of fabric webbing, are sewn
enormous weight of the mighty Himalayas above
together into various configurations and made from synthetic
Editorial team : V. Ramesh Kumar you. Or, contending with the force of a swift-running
fibres with material characteristics consistent with those of
Ashwin Chand | Mayura. K river cascading forcefully down a mountainside.
polyamide and polyester. Manufacturers maintain a uniform
The challenges are huge but we are able to soldier
Photography : V. S. Natanavelu | R. Vijay Kumar thickness of 3 mm and a width of 40 mm in compliance to IS
on following all the safety best practices; even then
3521. The threads used for sewing are physically compatible
Design & layout : Global Print Design, Chennai one cannot ignore the underlying safety principle
that one can never be too careful!

2 HELMET, July - September 2015 HELMET, July - September 2015 3


with that of the webbing, but are usually
of a different colour for ready visual
Anchoring the harness Holding firmly
inspection to easily identify wear and An anchor, what you connect your lanyard or lifeline to, is a key Most full body harnesses are built to support the combined
tear. element of any personal fall protection system. The selection of weight of a person and his tools of less than 140 kg. If this limit
the anchor point depends on whether you want to restrain or is exceeded, it becomes the responsibility of the employer
For sensitive and hazardous applications
arrest a fall. To prevent or restrain a fall, the anchor should be to provide proper protection for the heavier persons with
such as in the oil and gas sector, explosive
capable of supporting 350 kg (3.5 kN) while to arrest one, it appropriate systems.
environment or for applications like
should be able to support 2250 kg (22 kN).
welding and arc flash, specialty fabrics
such as Kevlar are used which are anti- The structure to which the personal fall arrest system is
A class apart
static and flame retardant. Some versions attached to must sustain static loads applied in the directions A detailed fall protection plan should be prepared by a
also feature di-electric hardware for use permitted by the fall arrest system of at least 1630 kg (16 kN) competent safety professional for selecting the right personal
in electrical applications. with certification of a qualified person or 2250 kg (22 kN) fall protection system especially when working at heights
without such certifications. When more than one personnel with a potential fall hazard of 6.75 m (24 feet) or more. This
A fall can be dangerous! are attached to an anchorage, the strengths stated above must plan should ideally enumerate the potential fall hazards, the
be multiplied by the number of systems attached. workmans knowledge of using the system, the environment
Startlingly, studies reveal that a fall from
in which it will be used and the reaction time for rescue until
a height of 11feet has only 15 % chance A full body harness should be rigged so that the user can
which time the equipment should keep the workmen in an
of survival which also means that there neither fall freely to not more than 6 feet (1.8 m), nor make
upright and suspended condition.
is a very high chance of fatality. Medical contact to a level below. The connecting lanyards should be
researches show that the human body anchored above the users head within reach and the length of Harnesses are classified based on the purpose and it is pertinent
cannot survive impacts above 1100 kg lanyard should not exceed a maximum of 2 m. to use the right type following a thorough understanding of
(12 kN) and OSHA (Occupational Safety
and Health Administration) mandates
that the maximum impact force that a
worker can be exposed to is 6 kN as per
European standards. These significant
facts must be borne in mind while
deciding on using the right type of fall
protection equipment when working at
heights.

Safe moorings
The attachment points of the full body
harness are normally sewn into the
webbing and are made of stamped/
forged metal or even sturdy plastic.
To arrest falls, the lanyard is usually
connected to the Dorsal D-ring that
is positioned between the shoulder
straps on the back. Lateral D-rings, if
present, are mostly for positioning or for
restraint applications. Shoulder retrieval
D-rings are meant for rescue or limited
access applications, Sternal D-rings for
suspension or when climbing ladders
and Ventral D-rings for rope access and
rescue applications.

4 HELMET, July - September 2015 HELMET, July - September 2015 5


the task. Class 1 full body harnesses are designed to restrain
a person in a hazardous work position to prevent fall or
Service life Safety
arrest a fall within 3 foot of movement. However, adequate because lives depend on it R o ll
of Honour
adjustments have to be made to keep the line rigid at all times.
While regulatory authorities do not indicate a maximum
Class 2 types are deployed at locations where there are only
service life for synthetic fiber products, they mandate that
limited fall hazards and no possibility of vertical free falls. It is
also used for retrieving victims from a tank or a tall bin. Class
the equipment must be discarded immediately if they have
been subjected to the forces of arresting a fall even once. It is
Helmet congratulates the following sites for achieving
3 full body harnesses are designed to arrest the most severe of
free falls while Class 4 full body harnesses (suspension belts)
advisable to subject the system to periodic inspections which ten million and more LTI free safe man-hours
may reveal defects, damage or inadequate maintenance
are independent work supports designed on the lines of a
based on which it can undergo corrective maintenance or be
Boatswain's chair.
permanently dispensed with. Most harnesses and lanyards 34 NISER Project, Bhubaneswar
September 2011 to September 2015
12 Mall of India Project, Noida
September 2013 to September 2015
come with specific instructions on use, inspection and
Tested on toughness maintenance which must be adhered to.
32 Prestige Bella Vista Project, Chennai
April 2012 to September 2015
11 UP Awas Vikas Basement Project, Ghaziabad
August 2012 to September 2015
Once manufactured, harnesses are subjected to a wide range
of tests to ascertain their quality. Both the harnesses and the To make it last long 31 The Address Wadhwa Project, Mumbai
11 ATC Tower Project, Gurgaon
April 2010 to September 2015 January 2012 to September 2015
lanyards are required to meet the dynamic (free fall) and
To ensure a lasting performance, the full body harness must be
static load tests as per the relevant IS standards. Testing of
raw material on flammability, UV stabilization, corrosion,
maintained as per the manufacturers guidelines. The polyester 25 Cognizant Elcot IT Park Project, Sholinganallur
October 2012 to September 2015
11 TCS Customer Care Centre, Siruseri
April 2012 to September 2015
material can be washed using a soapy solution to remove
chemical analysis and tensile strength is also carried out by the
manufacturers. Such performance tests ensure that the waist
dust, corrosives or contaminants and hung freely to dry in a 26 Delhi One Project
December 2011 to September 2015
11 Wonder Cement Line II Project, Rajasthan
June 2014 to September 2015
shady area away from direct sunlight. When not in use, the
belts, shoulder straps, hoisting straps and sole straps do not
break under a maximum tensile load of 2000 kg (19.6 kN).
equipment should preferably be stored in a clean and dry area 22 ITC Sonar Hotel Project, Kolkata
August 2009 to September 2015
11 Seawoods Ph II Project, Mumbai
December 2013 to June 2015
free from exposure to fumes and corrosive elements.
17 ESIC Hospital Project, Kollam
April 2010 to September 2015
11 Experion Windchants Project, Gurgaon
April 2014 to September 2015
The right attitude
Vertigo or fear of heights is the first aspect to check in a
16 TCS Project, Kochi
October 2011 to September 2015
11 TCS Adibatla Project, Hyderabad
September 2012 to September 2015
workman who is involved in working at heights. The solution
is that they either overcome the fear or simply dont go up the
15 Shell NTCB Project, Bengaluru
February 2014 to September 2015
11 Omkar Bhoiwada Rehab Building
Project, Mumbai
ladder. However there are also other behavioral traits that need June 2011 to September 2015
15 Godrej Garden City Ph-III Project, Ahmedabad
to be monitored to sustain a safe work environment.
yy Complacency is one of the leading causes of falls because
July 2011 to September 2015
11 Omkar Worli Sales Project, Mumbai
December 2012 to September 2015
14 Riverview Phase 2 Project, Lucknow
workmen become careless either due to experience, lack
of training, or just being unconcerned about the hazards
March 2012 to September 2015
11 L&T Realty, Sanofi Tower Project, Powai
February 2013 to September 2015
14 Experion Windchants Project, Gurgaon
yy Horseplay or pushing and shoving others when at heights
must not be tolerated at ay costs. The consequences can
April 2014 to September 2015
10 DLF Maiden Heights Ph I Project, Bengaluru
November 2012 to September 2015
14 Emami City Project, Kolkata
be fatal. January 2013 to September 2015
10 DLF Capital Green Project, Moti Nagar
June 2014 to September 2015
yy Housekeeping is extremely crucial. Hazards increase
13 ESIC Hospital Project, Coimbatore
manifold if unwanted equipment, tools and scrap material
are not cleared resulting in slips, trips and falls.
March 2011 to September 2015
10 IIT Phase-I A Project, Hyderabad
August 2014 to September 2015
13 HCL Ph III Project, Noida
The key to preventing falls from heights is by creating awareness,
January 2013 to September 2015
10 Lodha Fiorenza Project, Goregaon, Mumbai
August 2011 to September 2015
training and skill proficiency. A thorough knowledge of the 12 C-17 IAF Hindan Project, Ghaziabad
hazards, the available equipment, the application and the August 2012 to September 2015
10 DLF Crest Project, Gurgaon
September 2013 to September 2015
limitations of the protection systems will reduce and minimize
12 ESIC Hospital Project, Joka
workplace injuries and fatalities due to falls. November 2009 to September 2015
10 SNU Project, Dadri
October 2011 to September 2015
With inputs from Viraj Syntex Pvt. Ltd 12 CMRL Depot Project, Koyambedu
December 2010 to September 2015

6 HELMET, July - September 2015 HELMET, July - September 2015 7


BUILDINGS & FACTORIES

it was in this testing safety scenario


that L&T won a prestigious mandate
Following instructions
to construct a 2276-room, 250-bed to the T
super specialty facility the NMC Royal
An understandably proud EHS Manager,
Hospital.
Ramesh, begins by sharing that a
Today, the edifice stands tall, completed detailed safety induction programme
at breathtaking speed with quality was conducted for all who were
conforming to international standards, as involved in the project and daily safety
the second largest private hospital in Abu toolbox meetings were held before the
Dhabi and the fourth and largest integrated start of work by the respective foremen
specialty hospital in the UAE. Safety and site engineers. Every specific high-
was of prime focus all along the course risk activity had a consultant approved
of the project as the EHS management method statement and risk assessment
system had to be aligned with the Abu and that was followed to the T, avers
Dhabi Environmental, Health and Safety Ramesh adding that these instructions
Management Systems Regulatory Frame were conveyed to the workforce prior
Work version 2.0 Feb 2012 and had to to the start of each activity. High-risk
comply with the UAE Federal Law 1980. activities were also controlled by strictly
At the end of the day, the EHS team can following a permit-to-work system and
hold their heads high for a job very well there were a plethora of such permits,
done because the project clocked 4.8 informs Ramesh like the hot work permit
million safe man-hours without any time and the confined space work permit, the
lost due to injury. excavation permit, the work at height

T
he Middle East is in the grip of rapid
trade liberalization, globalization
and internationalism which are

Making it count driving construction at an amazing


speed. Rough estimates peg the
construction industry to deliver projects

where it really matters


to the tune of USD 500 billion by the
end of this year. With so much activity
in this space, it is not surprising that the
attention of all stakeholders has turned
to the importance of EHS. Along with
attention, expectations are higher and

8 HELMET, July - September 2015 HELMET, July - September 2015 9


BUILDINGS & FACTORIES BUILDINGS & FACTORIES

avoided time lost due to injuries. We


also conducted a Safety while working
on the Scaff-tag system that was
religiously implemented throughout
Electrical safety and heat stroke. Therefore, enough
precautions were taken to ensure that
at heights awareness programme the project. A green tag indicated An all-weather proof electrical workmen stayed health by providing
among all the supervisors and workers safe to use while a red tag signified distribution system with spider air-conditioned rest areas and well-
which also helped greatly. Plant and unsafe to use. Every scaffold was boxes 30 mA tripping Earth Leakage maintained toilets along with continuous
equipment is another area that can erected, altered and dismantled only Circuit breakers were provided for supply of cold drinking water and oral
easily compromise safety and hence by a third party trained and certified temporary electrical supply with proper rehydration supplements twice a day.
every aspect was inspected and certified scaffold inspector and inspected by cable routing to avoid electrical hazards. The site engineers ensured frequent job
by a 3rd party and then re-checked on them at regular intervals. We ensured rotation and self-paced work patterns to
a daily, weekly and periodical basis to that any scaffold over 10 meter height Staying healthy keep the workmen fit. Working hours
identify any inherent defects. was fixed only after a design were restricted between 12.30 pm and
drawing was made, inspected and The Middle East is known for its searing 3.00 pm from 15th June to 15th September
Often safety is all about doing simple certified by a third party, emphasizes heat and working directly under the to avoid the extreme temperatures as per
things right, smiles Ramesh elaborating Ramesh. sun can easily result in heat exhaustion a local ministerial order.

permit, the energy isolation permit for type to decide on the excavation and a
both electrical and pressure. In fact, dewatering station was installed prior
there were also permits for removing a to excavation to avoid water seepage
hand rail or opening a manhole that had into the excavated areas. Step cutting,
to be strictly followed, affirms Ramesh. shoring and shuttering were provided
for excavation depth of more than 1.2
Building a safe work culture is not a meter to prevent soil collapse as per the
one-man job but it has to be a concerted ADEHSMS requirements. During deep
effort with every stakeholder involved excavation, safety of the workmen was
in it and Ramesh says how, apart from addressed by hard barricading, hazard
the employees, the safety message flashing lights, danger warning signage
was shared loud and clear with the and having safe entries and exits.
subcontractors, visitors and suppliers.
For safety overhead
Ensuring safety under
We strictly followed a No work on
foot ladder rule and instead used light
Before putting any machine to the weight mobile scaffolds with adequate
ground, the soil was first tested to training which worked wonders,
ascertain the water table level and soil remarks Ramesh for it significantly

10 HELMET, July - September 2015 HELMET, July - September 2015 11


BUILDINGS & FACTORIES

Safety
of Honour
R o ll

Helmet congratulates the following sites for achieving


two million and more LTI free safe man-hours
19 Kandla Mundra Road Project
April 2011 to September 2015
4 Hyderabad Metro Track & OETS Project
January 2013 to September 2015

14 Samakhiali Gandhidham Road Project


October 2012 to September 2015
3 Mumbai Monorail
June 2013 to September 2015

13 Delhi Agra Road Project


October 2012 to September 2015
3 Vriddhachalam-Ariyalur Railway
Construction Project
December 2011 to September 2015

Keeping your house safe work area; they also ensured waste
Focus on PPEs 10 Sangareddy Road Project

and clean
segregation and disposal every day
by the local environmental authority
April 2014 to September 2015 3 Hospet-Harlapur Railway Construction
Project
Needless to say, safety helmets, safety
(WMC-Centre of Waste management). January 2013 to September 2015
Housekeeping is key to keeping the Wood, plastic, construction debris,
shoes and hi-vests were mandatory for
all site personnel while other PPEs like
7 Ganjbasoda-Sanchi Railway Construction
Project
project site safe and all workers as a rule food waste and sewage water
devoted the last 30 minutes of every were disposed of in the approved
hand gloves, goggles, ear-plugs, ear-
defenders and full body harnesses were
March 2010 to September 2015 2 Sindhudurg Airport Project
February 2013 to September 2015
shift to it. A dedicated housekeeping municipality area with a duly stamped
distributed whenever work demanded,
team was formed to maintain the delivery note.
confirms Ramesh. We even insisted 6 Kannur International Airport Project
visitors entering the site premise to don
November 2013 to September 2015 2 Maithon Railway Siding Project
March 2010 to September 2015
a helmet, shoes and hi-vest.
5 10MTPA Tata steel Electrified Rail corridor
While safety management is all
about being prepared for the worst
Project
July 2009 to September 2015
2 Rahuri-Daund Railway Electrification
Project
and making every effort to ensure September 2010 to September 2015
that the worst is avoided at all cost,
each project has its own unique set of 5 Chennai Metro Track works Project

safety challenges and we, as a team,


February 2011 to September 2015 2 Rajpura Railway Siding Project
April 2011 to September 2015
were able to face and crack them all,-
states Ramesh with a broad smile. 5 KMDA Flyover Project
We take pride in having safely built a November 2012 to September 2015 2 Bina-Ganjbasoda Railway Construction
Project
health infrastructure for UAEs ever
December 2012 to September 2015
growing needs.
4 Hosur Krishnagiri Road Project
January 2014 to September 2015
2 Wadi-Raichur Railway Electrification
Project
4 Sambalpur Rourkela Road Project
January 2012 to September 2015
July 2014 to September 2015

12 HELMET, July - September 2015 HELMET, July - September 2015 13


TRANSPORTATION INFRASTRUCTURE

Kolkata, The City of Joy, is perhaps one Being a cluster of projects located
of the fastest growing cities with a high around a radius of 70 km, monitoring
migration rate from the neighboring and ensuring safety of the workforce
states and even from Bangladesh. and the public was a herculean task. It
Since most of the roads have been was the young and dynamic Abhishek
planned and constructed during the Chakraborty and Jethin who managed
British Raj, they are no longer able to the EHS portfolio taking into confidence
manage the congestion and the citys the entire team, shares Subhendu Gosh,
residents are paying a heavy price. Alive Project Manager, singing praises of the
to this growing problem, the Kolkata duo. Despite the high rate of workmen
Metropolitan Development Authority attrition, the young safety engineers
(KMDA) proposed the construction of were able to effectively manage and
several elevated corridors to fly over implement EHS systems and policies

A
s the Indian economy makes dense parts of the city and to ease the across all the project sites.
its presence felt in the traffic on the existing carriage ways.
Identification of issue is
Elevating the
global arena, infrastructure L&T was entrusted with the task of
completing a cluster of five elevated
development is very evident across the
country, especially in the metros and sections and Rail Over Bridges, all critical
problem half solved
so also is rampant urbanization. This parts of the larger elevated corridors. We have taken the Integrated

standards
sudden and heavy influx of population Read on to know how team L&T fought Management System (IMS) approach on
is putting enormous pressure on a tough battle crossing hurdles and EHS at our projects and top priority was
the transportation infrastructure of meeting incredible targets to connect accorded to planning and preparation
cities and civic authorities are at their the dots of the ambitious infrastructural of risk assessments. A simple but
wits end to evolve strategies to overcome plan which has brought some joy to the effective document called HIRA (Hazard
this menace. people of Kolkata. Identification and Risk Assessment)

14 HELMET, July - September 2015 HELMET, July - September 2015 15


TRANSPORTATION INFRASTRUCTURE TRANSPORTATION INFRASTRUCTURE

to prevent the fall of even cementicious


liquid, remarks Jethin adding that
height barriers with chain lights were
installed apart from barricades with
retro reflective signage to alert drivers.

Increasing awareness
Every single workman was put through
a complete and comprehensive induction
programme apart from periodic work-
based training programmes. Through
work permits and lift cards, we ensured
that only trained and authorized personnel
were engaged in critical activities, shares
Abhishek adding that adequate safety
stewards were posted at the sites for the
last mile connect. These safety stewards
also interacted closely with the site
engineers to identify and mitigate minor
risks not covered under HIRA.

Providing a safe access


Being a flyover and ROB project,
access to the deck slab was crucial for
the workforce. A conscious decision
was made to erect and use formwork
based safe access systems only with
proper safety net cladding to ensure
safety.

No shocks with proper


planning
With welding, cutting and grinding
happening simultaneously at all
was followed for all critical activities. the workforce on a task-to-task basis. safety of our workforce, we also had to sections of the project site, electrical
Created with contributions from all the We also had in place site specific and consider the safety of the general public. cables crisscrossed the expanse posing
stakeholders of the site, this document on-site emergency plans which laid the This put a lot of pressure on us as the imminent danger. This hazard was
helped identify, assess and mitigate foundation for the excellent EHS track media would get involved even for a controlled through the use of ELCB
risks well in advance obviating the need record of the KMDA projects, adds minor incident, and blow things out of and proper routing of cables apart from
for knee-jerk reactions, shares Jethin Abhishek. proportion. We therefore ensured that ensuring double earthing of electrical
as Abhishek joins the conversation every aspect was addressed to ensure installations. All joints had cable
The safety duo recall that the KMDA that nothing untoward occurred. Edges
by saying that this method statement jointers for added safety.
project was a nightmare from an EHS had proper protection apart from safety
was reviewed thoroughly and finalized
point of view as the construction was nets at appropriate locations to arrest While working on the ROB portions, we
along with the preparation of Safe Work
happening over existing roads which fall of material. At critical zones like Park had to be extremely cautious because of
Methods (SWM) which were effectively
were busy 24x7. Apart from the Circus, we used very closely netted cloth the 25 kVA electrical live line just below
communicated down the line to reach

16 HELMET, July - September 2015 HELMET, July - September 2015 17


TRANSPORTATION INFRASTRUCTURE

the structure. The induction range of these high power lines


are well over 2 m. We introduced catenary tubes to reduce
Safety
of Honour
the induction and instead of safety nets, we used plywood, a R o ll
non-conducting material, to the reduce risk of electrocution,
says Abhishek talking about the precautions taken to build
structures above the main railway line.
Helmet congratulates the following sites for achieving
The fitness check
one million and more LTI free safe man-hours
To ensure proper maintenance of plant, machinery, tools
and tackles, a system was implemented through which the
site engineer had several check points which he verified and
ticked-off to authorize compliance. Right from the radius and 10 TSL Project, Kalinganagar, Odisha 1 220 kV & 132 kV TL- WBSETCL PKG-I
condition of the crane to the wear and tear of lifting tools and September 2012 to September 2015 March 2013 to July 2015
tackles, all equipment were checked for fitness. The system
also included checks on ambient aspects including visibility 3 TFL-IE-BSNL-MOD NFS OFC PKG- E-BSNL
October 2014 to October 2015
1 400/220 kV Switchyard extention NPCIL
RAPP 7&8
and illumination for conducting night work. Once the check
February 2011 to June 2015
was completed by the site engineer, the document was
2 400 KV D/C Bihar Sharif-Sasaram to Varanasi
reviewed by the EHS personnel and submitted to the project
EHS management.
TL Project
September 2012 to December 2015
1 33 kV & 11 kV Network Upgradation
Work for Nabakalebara in Puri
Mock drill June 2014 to June 2015
2 HMRP Power Supply & Scada Package E&I

The litmus test


April 2012 to May 2015 1 TFL-IE-BSNL-MOD NFS OFC PKG- D-BSNL
October 2014 to August 2015
Mock drills were conducted as a litmus test to check the 1 ODSSP Phase-1 Package-7
system. Such drills provided insights into the time it took for an
April 2014 to September 2015
1 765 kV Srikakulam to Vemagiri
TL Project -ER 03
ambulance to reach the site and to gauge the reaction of workmen
in the event of any untoward incident. Kept in secrecy, the mock
1 R-APDRP Project Ludhiana East
February2015toSeptember 2015
June 2014 to August 2015
drills involved a workman acting unconscious or injured and
the EHS personnel keeping a tab on how fellow workmen and 1 BRGF-Murshidabad 1 400 kV Jammalamadugu to Uravakonda
TL Project
the site execution team reacted during such crisis situations. January 2014 to September 2015 July 2014 to April 2015
The results along with critical review were later shared with the
entire team to further sharpen their reaction time.

A systematic approach Ministry of Interior, Qatar conducts three day intensive


Retro reflective signage
safety workshops at L&T
The KMDA project involved several critical activities such
as erection and launching of bow string girders, steel warren The Public Relations department of the Ministry of Interior (MoI) conducted
a three day safety workshop at L&T's Training Hall, Mesaimeer, between 27
truss, and RCC and steel girders over live railway lines. Instead
to 29 July 2015. The first day session on Pedestrian accidents & remedies
of a task-based approach, we adopted a system-based approach
were conducted by the Traffic Department and the Civil Defense General
including the HIRA, SWM and Behaviour Based Safety training,
Directorate while the second day had workshops on drug & alcohol addiction
which paved the way for excellence in safety, claims Abhishek. apart from do's and donts on Qatar's Customs and Traditions handled by
Jethin adds that apart from prominent display of awareness Drugs Prevention and the Public Relations Departments.
and motivational posters, the EHS team also ensured active
On the third day, the Traffic & the Public Relations Departments jointly held
participation of workmen in events such as Safety Month,
an interesting session on Common Traffic Mistakes Among Drivers which
Road Safety Week and other important days observed to focus
was well received by the over 150 workmen who attended these workshops.
on safety. Outstanding and safety conscious workmen were
This safety workshop being a first-of-its-kind, was covered in leading dailies
appreciated and presented with awards on a monthly basis to such as Gulf Times and Qatar Tribune.
Cable jointers recognize and reward compliance, he concludes.

18 HELMET, July - September 2015 HELMET, July - September 2015 19


POWER TRANSMISSION & DISTRIBUTION

Height work training to workmen

across 281 km. Passing through the of days! Anoop acknowledges with
heart of rural India, the project involved a smile, Securing the right of way to
raising and stringing close to 800 towers commence work needed deft handling
across a composite power network as the villagers were familiar with
Tower erection using gin pole technique comprising 3 different voltages over the compensation pattern due to the
25 incident-free months. How did they presence of other transmission lines

T
achieve it? Heres what the safety in- along this section. In some stretches,
he Power Transmission charge had to offer. doing the preparatory arrangements
& Distribution IC of L&T itself took a lot of time as we had to
Construction is engaged in
executing a slew of long-distance high
Establishing a safe join hands with the police and the
local administration to ensure the
voltage transmission line projects ground

Going the distance


safety of our workmen and employees.
across the country among which the Reclining on one of tower basements,
We drive past strategic sections of
Varanasi-Kanpur power corridor is a Anoop quips, Over here close to 100
the alignment that spans landscapes,
vital link which when commissioned policemen were deputed for three days
hamlets, towns and large stretches of
will add 6000 MW of power to the state to facilitate the tower erection works
agricultural lands reflecting the vastness
of Uttar Pradesh. Partnering Power Grid and, for the team, it was all about going
of the project. Glancing at the safety in-
Corporation of India (PGCIL), L&T has the extra mile to ensure that the ground
charge, I remark, To just have a look at
completed a major section of this line was secured.
the entire stretch might take a couple

20 HELMET, July - September 2015 HELMET, July - September 2015 21


POWER TRANSMISSION & DISTRIBUTION POWER TRANSMISSION & DISTRIBUTION

Passing on the steel


batons seamlessly
The projects success lay in tagging
the steel components which made
assembling facile, highlights Anoop,
With a huge volume of 781 towers,
the challenge for the team was in Raising the steely
implementing a secure logistics system
for material handling. To make the
members
process foolproof the project team Looking at one of the towers
deputed a team of ITI fitters who were being erected in the last leg of
well versed with the tower materials the alignment, Anoop relates,
across the 3 stores. Pointing at one These are the largest ones and
Physical verification of tower receipt of the towers, Anoop elaborates on are raised with the support of gin-
the dynamics, On an average a tower poles, section wise. For medium
weighed between 70 to 120 t and and smaller towers, the team
comprised more than 4000 elements deployed the derrick and pulley
and the onus was on the safety team method of lifting. The safety
to lay a safe track for facilitating team innovated on the process by
work which ranged over a week to developing a SOP that specified
a fortnight depending on the tower the safe load weight lift for each
dimensions. We opted for an easy way section along with the requisite
to maneuver new generation pick and tools and tackles and workmen
carry crane to load the tower members to be engaged. Anoop elaborates,
on 11 t tractor trailers which did quick To make the scheme even more
sorties to the work spots. The objective secure, the safety team oriented
was to be quick and also safe during the tower gangs through a series
the lifting and moving process, of training programmes on the
emphasizes Anoop. operating procedures. I ask him
PEP talk at site if this is a standard norm across
all such projects, to which he
clarifies, The system has always
been there but it has undergone
considerable customization at
UNSCRAMBLE site to suit the type of works. He
cites an example of how the team
THE WORDS TO REVEAL THE SAFETY SLOGANS made pictorials of the cage wise
and section wise tower erection
1. SSOHE TRFSI, TESP EXTN procedures and briefed workmen
2. ROU TOMTO, TAFSEY IN OTTO in detail before each phase of
lifting.
3. KAME YTAESF A AYW FO EILF
4. FASTEY YAPS TWIH PAPHY YADS
5. AYTFES SI VOYDEERSBY UBSSSINE
Answers on page 43 Stringing activity in progress

22 HELMET, July - September 2015 HELMET, July - September 2015 23


POWER TRANSMISSION & DISTRIBUTION POWER TRANSMISSION & DISTRIBUTION

Keeping a safe tab of safety stewards across locations over a


period of 7 to 25 days for a single stretch
One of the foremost tasks that the based on the tower orientations. It was a
project team took up was to identify demanding work phase reveals Anoop.
the challenging alignments across We had to start as early as 6 am during
the Double Circuit 765 kV and 400 kV summer when temperatures soared to
lines between Varanasi-Kanpur and 50 and take appropriate breaks to protect
Sarnath and also across the loop-in ourselves from the heat and in winter
loop-out Double Circuit 400 kV line accordingly adjust the work timings to
from Sasaram to Allahabad. As all the escape the biting chill weather.
lines passed through thickly populated
settlements, there was the need to re- Hooked to the life lines
route the lines frequently. Pausing
beneath one of the towers whose base We spot a gang of workmen equipped
area seems big enough to accommodate with the requisite safety PPEs ascending
a tennis court, Anoop mentions, When a tower of about 50 m high in less than
you have a straight line it is more or 15 minutes. It takes a lot of guts to
less easy to raise the towers but in this climb these towers and the men from
project towers had to be joint in a large Bihar and Jharkhand take the honours
scale and hence posed a big challenge in doing such critical works says Anoop.
because the alignment followed a zig- It is important to have a foolproof
zag pattern. The entire alignment was safety system that protects the crew
divided into 20 km stretches and the while working at heights. The project
monitoring of works was done by a team team in addition to the individual safety

Stringing across Railway crossing under progress

Crossing over with Putting it all


caution together
The good thing in this project was that Knitting the strings together was
we didnt have many cross over works either done manually or by deploying
says Anoop, However negotiating the the tensioner and puller machines
railway crossing was a tough task as it depending on the type of tower and
was a single line linking Varanasi with its reach. Similar to the tower works,
the adjacent villages and was always load was calculated for stringing based
busy. Our team took up the crossing on the span between towers. While
works during the initial phases and stringing, it was important to cordon
evolved a detailed pre-task sequence off the entire stretch as the wires
after getting a comprehensive clearance can cut through any infringement
from the concerned authorities. The during the lifting and sagging
whole processes were split into various process. Communicating with locals
activities and close to 100 workmen was taken up through mega phones
were engaged in the stringing works. and a team was deployed till the
Major road crossings were executed by completion of the activity to ensure
blocking the traffic for a limited period the safety of people and the cattle in
of time and scaffoldings were arranged the vicinity.
for smaller cross-overs. Operation of TSE for stringing activity Workmen engaged in conductor make-off

24 HELMET, July - September 2015 HELMET, July - September 2015 25


POWER TRANSMISSION & DISTRIBUTION

equipment, provided fall arrestors at


strategic legs where movement was
Safety
of Honour
likely to be more and equipped the R o ll
crew with vertical and horizontal life
lines. The workmen could access the leg
members of a tower by either walking
across the slender steel joints or position Helmet congratulates the following sites for achieving
themselves in a secure manner by sitting
on them and move. As the crew was five million and more LTI free safe man-hours
experienced, they walked over the tower
members by hooking to the life lines
which made the task doubly secure.
11 Vizag Vessel Project 6 Mumbai Monorail Project
Partnering a conscious
client 10 DMRC CC 28 Project 6 DMRC CC 05 Project
The onus of safe execution is a
collective initiative which rests with
both the contractor and the client and 10 DMRC CMC 1 Project 6 Narmada Project
PGCIL, being one of the prime power
infrastructure developers, ensured that
the way forward was secured. One of 10 Swalkote Project 5 DMRC CC17 Project
the first issues addressed at site from
the clients side was on safe working
at heights through an orientation
programme for workmen. Team L&T
6 Kolkata RVNL Project
added might to the cause by roping in
the services of a professional agency that
demonstrated and trained workmen on
how to safely conduct and manage crisis
while working at heights. This session
also included a special training on Correct answers
how to bring down a person in need of yy Incomplete working platforms in
medical care. scaffold
yy No evidence of toe guards
Reaping the merits of yy Workmen using ledger pipes as
working platforms
good practices Spot the yy Numerous workmen at three different
levels on a single scaffold

HAZARDS
While systems played an important role
in the safe execution of works, L&T also yy Some workmen have not anchored
the safety harness
implemented a best safety performance
yy Workmen working on H-Beam
reward scheme for subcontractors and
workmen. The multi-pronged thrust on
WINNERS yy Working platforms not tied properly
yy No ladder access to the working
safe initiatives enabled the team to clock
Mr. Sunthararajan.C platform
more than 3 million safe man-hours and Engineer EHS, HCI IC yy No evidence of handrails
add one more illustrious benchmark to yy Work area close to live road
the long list of high voltage transmission Mr. Vigneshkumar without barricading - possibility of
Engineer B&F IC unauthorized entry
lines executed by L&T.

26 HELMET, July - September 2015 HELMET, July - September 2015 27


HEAVY CIVIL INFRASTRUCTURE

infrastructure that, once completed, will Royal Government of Bhutan, the safety
produce 1200 MW of clean, green energy team has worked towards achieving a
to feed the energy-starved northern Zero Harm Vision, shares K.K Gupta,
states of India, thanks to a buy back Segment Head. It was N Ramesh Kumar
agreement between India and Bhutan. (NRK) who first landed here and later
Spilt into three packages, L&T won the Bruno Francisco Brotas was brought on
mandate to design and commission the board to bring in global expertise. Bruno
scope under Package 1 of Phase 1 that has introduced a slew of EHS measures
includes the upstream and downstream based on his rich global experience
coffer dams, diversion tunnels, a dam, of working on various construction
an intake and desilting arrangement projects and the two of them are now
including hydro mechanical works. admirably holding fort.
The project command area is around a
rapidly flowing river and steep valleys Before starting any work, we prepare
that keeps posing tough questions to the a work method statement along with
team to create and sustain a safe work a risk assessment to identify and
culture. Since there was no dedicated mitigate all adverse conditions that
EHS department on the client side can potentially impact the workforce
(Punatsangchhu Hydroelectric Project and the environment. This data that is
Authority), the onus of establishing reviewed by the EHS team, approved
norms and implementing them was by the Project EHS head and finally by
entirely on L&T. the Project Director becomes the basis
on which safe work method is prepared
Towards Zero Harm and communicated to the line function
and subsequently to the workforce. We
Vision hold this entire process sacrosanct for
To ensure compliance to L&Ts EHS each and every process, says Bruno
policies and procedures as well as to keenly observing the excavation taking
those of the statutory bodies of the place deep down in the dam pit.

P
unatsangchhu Hydro Electric
Project (PHEP), part of an

A dam good
ambitious vision of producing
20,000 MW by 2020, is being constructed
by L&T in the Himalayan Kingdom of

safety strategy
Bhutan and has already witnessed a host
of new benchmarks that have made the
world sit up and take notice. Deploying
sophisticated equipment and innovative
construction methodologies, team
L&T has been redefining the landscape
to create a world-class hydro power

28 HELMET, July - September 2015 HELMET, July - September 2015 29


HEAVY CIVIL INFRASTRUCTURE HEAVY CIVIL INFRASTRUCTURE

Inducting safely on AV equipment, informative signage and


an array of PPEs that line the walls with
board detailed descriptions.

We deployed a lot of machinery and


equipment at the initial stage of the
Safety at work
project as we were working towards To drill down the message deeper and
excavation figures that were running to instill a stronger sense of safe work
into several lakhs. In a new country, culture, a typical day at the site begins
where pressure on hiring local workforce with a safety pledge and a pre-start
is high, we have to be very cautious verification of work. The EHS in-charge
about appointing operators and drivers. briefs the workmen on the activities for
Ten excavators, 45 dumpers, two dozers, the shift which involves details on class-1
ten ROC with compressors and two risks along with all the control measures.
drill jumbos were operating in an area This meeting is also an opportunity
measuring just about 300 m x 150 m. to create increased awareness on risks
With exposure to such high risks, we by sharing short case studies and near
could not compromise on the safety of the misses from other projects.
team and hence it was made mandatory
for all workmen to undergo an intensive
induction process that would give them
The right ambience for
a quick but strong exposure to the EHS the drill
practices adhered to at L&T, says NRK
Construction of diversion and intake
giving us a walkthrough of the fully
tunnels, adits and desilting chambers
equipped induction facility replete with

involve huge amounts of underground usual scenario of a slushy tunnel floor with shotcreting ensured that there was
excavation which was risky in this case due to leaks through fissures from the no settlement of the roof following the
because of the geological condition of walls. Over to the sides of the tunnel, excavation.
the young fold mountains that changed a temporary cable tray neatly carries
from hard to soft rock within just a all the wires and from the roof hangs Banking on the right
few meters. The tunneling team had to the large ventilator duct that ensures
proceed with utmost caution using the clean breathable air for the workforce to
solution
innovative methods. From an EHS point operate comfortably inside the gigantic The excavation target for the dam
of view, we kept tabs on the ambient structure. structure stood at a staggering 64 lakh
quality by monitoring and improving cu.m. Through the open pit method,
The first view of the underground
illumination, air quality and gas levels. the team meticulously excavated most
desilting chamber is truly breathtaking.
A system of random checks has been of the targeted quantity before disaster
We walk further to see a flight of stairs
created apart from periodic ones before struck suddenly. The right bank of the
with handrails on the wall end leading
each and every shift, NRK explains as dam started settling downwards on
down to the bottom of the chamber
we walk into the mouth of the large three axes due to a shear zone failure.
that we gingerly descend without once
tunnel that leads into the belly of the For the EHS team, it meant sleepless
taking our hands off the rails. Once at the
mountain. nights. Sophisticated instruments
bottom, NRK explains that controlled
were immediately installed and the
At the entrance of the adit, the excellent blasting was carried out along with
movements of the landmass were
quality of work is clearly evident as road heading to excavate this incredibly
monitored day and night.
the floor is dry and clean unlike the large structure and rock bolts along

30 HELMET, July - September 2015 HELMET, July - September 2015 31


HEAVY CIVIL INFRASTRUCTURE HEAVY CIVIL INFRASTRUCTURE

It was on a night shift on July 17, pushed against each other, standing high like a pyramid disaster has delayed the project by almost two years which
2013 that I first noticed a small crack and, at the same time, the crack on the bench had become the client plans to make up by replacing conventional
on the shotcreted section of the right a gaping hole. Experts were consulted from across the globe concrete with Roller Compacted Concrete (RCC) for the dam
bank bench. Initially, we all thought it for mitigation strategies. By the afternoon of 25th July 2015, structure.
must be a surface crack and left it at we noticed that the batching plant and the cable car bench
that. Three days later we noticed that were settling down and that was the final alarm bell for The siren call
the structural steel elements at the us. It was decided to stop traffic during nights and by this
grouting tunnel below were getting time micro piling works had already begun which stabilized Being glacier-fed, Bhutanese rivers are always fraught
twisted out of shape. This was when the movement to a certain extent. This was followed by with the danger of GLOF (Glacier Lake Outburst Flood)
we realized that we were up against heavy grouting and rock anchors which were driven into along the valleys they flow. PHEP being located on the
something really big and dangerous. the rock to stabilize it, recalls NRK with a shudder. As banks of River Punatsangchhu is also at high risk. The
The tunnel and the bench areas were a safety precaution, the ropeway and the cable car were Bhutanese Government has prepared a scheme wherein a
immediately marked out of bounds also carefully dismantled. Survey point instruments are satellite operated GLOF siren has been fixed every 2 km to
and inspections were conducted only monitoring the movements which have now reduced to a alert people of an impending crisis and to move to higher
with explicit permission from the top few mm per day following these mitigation methods, NRK levels to escape from the path of the raging floods. Bruno
management accompanied by the says with visible relief. To be doubly sure of the stability, recalls the mock drills that were conducted to monitor
safety team. Two days later, to our the team now awaits the driving of 2 m concrete piles deep the effective implementation of evacuation and team
horror, we found that the crack on the into the rocks before the execution team can reach the L&T proved its adherence to safety standards by
floor portion of the tunnel was being toe portion of the dam through excavation. This natural scoring high during such drills.
View of adit under pressure from shear zone failure

View of the road that has settled a couple of meters GLOF siren

32 HELMET, July - September 2015 HELMET, July - September 2015 33


HEAVY CIVIL INFRASTRUCTURE HEAVY CIVIL INFRASTRUCTURE

The accolades say it all

yy Merit certificate for achieving 6 million safe man


hours during April 2009 to Oct 2010

yy Winner of the Annual EHS Trophy 2009-2010


(Category Minor)

yy Winner of the Annual EHS trophy 2010-2011


(Category 3 Million Man Hours during the year)

yy ROSPA award Silver category in 2011 and 2012

yy Merit certificate for achieving 2.5 million safe


man hours work in 2013

yy Safety Recognition award 2014, from the Ministry


of Labour and Human Resources (Royal Govt. of
Bhutan)

yy International safety award from British Safety


Council 2015

A matter that needed so that nobody can even accidentally


switch it on while maintenance work
allowed anti-venom medicines to
be stocked at the projects first aid
suppression is in progress. The LOTO system is centre much to the relief of the project
Dust emission is inevitable at a meticulously followed for maintenance management.
construction site. Especially with heavy work on plant, machineries and all
duty dumper trucks plying day and power driven equipment. At PHEP, The green cover
night carrying boulders and muck. What electrical hazards are also considered as
The Bhutanese love nature and their
with 800 trips in 24 hours, it is only a Class 1 risk and to mitigate untoward
Government has drawn stringent statutes
natural that dust, if left unchecked, will incidents, all the connections are routed
to fiercely protect their environment. But
pose a severe threat to the users of the through ELCB which are inspected
development comes at a cost and any
national highway. To settle this issue, two periodically by a qualified tester.
hydel project of such massive scale will
dedicated sprinkler tankers were engaged impact the ecology to some extent. L&T
to continuously sprinkle water along the
A venomous affair ensured that none of the laws governing
highway around the project area. Being a mountainous region, the project the protection of the environment were
site and the quarry area is always under flouted and implemented afforestation
Lock Out, Tag Out the threat of snakes and other venomous programmes by planting saplings in the
Another danger that lurks is of reptiles and with the nearest medical centre backfill areas of the valley, converting
equipment or machinery getting 50 km away, it is dangerous not to stock them into new tracts of virgin forests.
switched on while maintenance anti-venom medicines at the site. But Both noise and air quality levels are
personnel are engaged with it. To prevent Government norms did not allow for continuously monitored and the project
such incidents, a work permit system stocking of such medicines and it was team has vowed to keep the river as
has been implemented wherein the only after a prolonged and persistent clean as possible in its course along
workmen locks and tags the equipment representation, that the authorities the project area.

34 HELMET, July - September 2015 HELMET, July - September 2015 35


HEAVY CIVIL INFRASTRUCTURE

Driven from the top Safety


of Honour
Safety at PHEP is a function driven from the top. Right R o ll
from the Segment Head, the Project Director to the Line
Managers, everybody plays an active role in the planning and
implementation of safety systems. A culture has been developed
to carefully review near misses and first-aid cases to prevent Helmet congratulates the following sites for achieving
reoccurrence of such incidents. With the project firing on all
cylinders and excavation being carried out 24x7, possibilities four million and more LTI free safe man-hours
of such incidents, especially during night shifts, are high. The
top management has volunteered to conduct night vigilance
project tours on a rotational basis to keep the morale high and to
mitigate any noticeable and dangerous inaccuracies on the spot.
15 Storm Water Drainage Works, Jabalpur 4 Kamal Vihar Project, Raipur

In the comforts of their cabin, Bruno and NRK unanimously 6 Hoshiarpur & Jalandhar Sewerage Scheme 4 GDWSS, Hyderabad
agree that the support from the top management has been
extremely encouraging and it is only with this support that the
EHS team has been able to function so efficiently. There was 5 Hogenikal Waater Suply Project-PKG 5 4 Rehabilitation and O&M of 110 MGD
Bhagirathi WTP
a recent initiative called the e-TICS (Tracking of Inspections
Compliance Status) where risks noticed in a site is updated 4 GIDC-DAHEJ Water Supply Project,
online and, if not mitigated within the specified time limits,
execution team. With the frenzied rate of project progress, it
25 & 50 MGD 4 Trans Varuna Sewerage Work, Varanasi
get escalated up to the IC Head level. It is only natural that any
site would want a lesser log of e-TICS. But at PHEP the project is only natural that our colleagues might get annoyed when
management encouraged us to lodge as many e-TICS as were we stop work owing to non-compliance or on identifying a 4 Nalgonda UGD & WSS 4 Dhanbad Water Supply Project, KKCO
noticed since it brought to light the lapses and corrections that threat. But every single stop work notification has been taken
can prove lifesaving. Reason why we were really high on our in the right spirit as the entire project team acknowledges and
appreciates the impact such initiatives have on saving limbs
4 UGDS & WSIS, Nizamabad 3 UFW-D2B, Bangalore
e-TICS, shares NRK.
and lives, adds Bruno saying that it has been truly gratifying to
We have been conferred the authority to judiciously use work in such a positive work atmosphere that holds the safety
stop work and notify the gravity of an unsafe situation to the of its employees and stakeholders as primary.

As part of L&Ts Safety Day events on July 04,


an initiative on car safety was introduced for the
safety of guests traveling in the companys cars.
The instructions include an audio clipping
containing safety instructions for the driver
and the passengers along with an hazard
Spot the

HAZARDS
observation card which the passengers can
A DRIVE fill out if they find anything amiss.

TOWARDS One more step along the way


to live safely! If you have spotted the hazards, rush it to
SAFETY IN CARS ngfernandez@lntecc.com.

36 HELMET, July - September 2015 HELMET, July - September 2015 37


WATER SMART WORLD & COMMUNICATION

Poly Aluminum Chloride (PAC) discharged from tankers at the new chemical house

was opened up for the first time after after formulating a secure strategy and
three decades and there were myriad involved trained workmen to manually
challenges for the team to mitigate. move the chemicals. This is the only
Stepping in after commissioning of the multi storey setup in the plant which is
enhanced system, the editorial gets up newly constructed. As we move forward,
close and personal with the safety in- Vaibhav elaborates, We deployed
charge. a PC 200 breaker to bring down the
Clarifier bridge erection through a customized derrick and wire rope method old structure in a secure manner and
Ensuring a safe chemistry facilitated the works by providing a
2.5 m ramp to reach up to the top of the

L
&T Constructions Water Smart As we are taken through the various building. All through the demolition, the
World & Communications IC facets of the project, Vaibhav, the safety chemicals were transferred in a phased
pioneered a first-of-its-kind in-charge meets us while overseeing the manner. Presently, around 1000 t of

Re-engineering the processes of


refurbishment of a 32 year old water discharge of Poly Aluminum Chloride alum and PAC are stored with provisions
treatment plant for Delhi Jal Board at (PAC) from a tanker at the newly for saturation, dozing and the chlorine
Bhagirathi without hampering the daily constructed chemical house. Armed tonner capacity has been enhanced

water management distribution of water to close to 40 lakh with protection masks, he leads us from 4 to 16 cylinders. Opening one of
people of East Delhi. Putting together the into the facility. Demolishing the old the ducts for an overview of the piping
new system, one of the largest WTPs in chemical house was one of the most layout, Vaibhav points out, The team
the country, in a phased manner called critical tasks of this project highlights devised a safe strategy while revamping
for some robust safety measures backed Vaibhav, As there were huge piles of the chlorine storage rooms which
by innovative engineering as the plant alum, the process commenced only were at 3 locations across the WTP.

38 HELMET, July - September 2015 HELMET, July - September 2015 39


WATER SMART WORLD & COMMUNICATION WATER SMART WORLD & COMMUNICATION

Demolition of the old chemical house Moving a part of the 2800 mm dia RCC duct from the new bifurcation chamber

A secure lifting tackle with an I beam to 64 t was a precision task as we had to


was provided to lift and move the do it without affecting the existing inlet
1500 kg cylinders. Each chlorine main during the last leg of the project.
point is provided with a self-contained The team deployed the diamond rope
breathing apparatus and various cutting method for cutting it fine and
manual leak arresting mechanisms to in about 20 days the interconnection
handle any chlorine leak emergency. was achieved with the new bifurcation
chamber.
Jointing the inlet mains
with precision Installing a foolproof
work process
Adjacent to the chemical house is the
inlet main through which water flows Drawing close to one of the clarifiers,
from the upper Ganga canal to the WTP. Vaibhav briefs, There are 8 such tanks in
Vaibhav points to a huge concrete pipe this plant and the scope of work involved
that lies nearby, Cutting and removing dismantling the existing bridge weighing
a segment of the 2800 mm diameter around 12 t and installing the new one
RCC gravity inlet main weighing close that weighed close to 15 t. To secure the
Precision cutting of the RCC duct through diamond rope cutting method. Carving cut outs in civil structures for new equipment installation

40 HELMET, July - September 2015 HELMET, July - September 2015 41


WATER SMART WORLD & COMMUNICATION WATER SMART WORLD & COMMUNICATION

entire process, the project team designed


and fabricated a customized lifting
arrangement with special tower/derrick
and rope arrangement which won a
PRAISE award from the management.
Through another innovation we
managed to work over the filter beds
by staging a scaffold on rails while
doing the roof revamping. For replacing
the pumps below the filter house, we
erected a gantry crane so that the
civil flanges remained intact while
replacement.

Revamping a dark
chamber
The making over of the WTP is very
much evident as one gets to see the
Customized gantry crane installed at filter house to facilitate mechanical works
state-of-the-art systems installed across
all the facilities except for one place
where it is camouflaged by a vast stretch
core team as the chamber had 1024
pillars which prevented the use of any
the operators. This was very essential as
operators shifts changed every 8 hours
Keeping a vigilant eye
of green. Providing details on the dark kind of support machinery. and the new person taking charge had to Unauthorized movement of men
chamber, Vaibhav says, This is the be aware of the live line and 17 pumps or material never occurred in this
biggest open space in the plant under Insulating the power were installed across five phases. project exclaims Vaibhav, The plant
was continuously monitored by the
which are the 5 reservoirs that store
water coming from the filter houses banks Shielded with a range client and the site security and access
to sensitive work spots was permitted
1024 pillared underground clear water reservoir
and supply to the clear water sump.
With access available only through four
Taking us to the heart of the control
center, Vaibhav indicates, At the touch
of PPEs only after thorough screening. CCTV
cameras were installed at strategic
openings and having been closed for of a button, the entire operations of A project of such intensity had a vast
locations and workmen were allowed
over three decades, it called for some the plant can be accessed but to make range of PPEs to protect the team
to process areas after passing through
very secure strategies to be implemented it happen power is essential on a 24/7 working on different platforms. For the
door frames and hand-held metal
before any kind of work could happen. basis. During execution, the team had above ground works, standard harnesses
detectors. The site was equipped with
to install numerous power banks to and tools were provided along with
Summoning the operator to open a dispensary where the workmen were
sustain and manage water distribution customized scaffolds. Excavation works
one of the vents, we get a peek inside periodically screened for health issues.
in a phased manner. Putting together were taken up only after identification of
which only seems to be outer surface Frequent mock drills were conducted
the networking was tough as the cables the below ground utilities and erection
of the chamber. Vaibhav mentions, for workmen, employees and clients
had to be laid without puncturing the of various electrical and mechanical
On the safety front we installed an on safety and disaster management
main lines and the pump operators were equipment by trained riggers. The
axial flow exhaust fan to remove the which enabled us to achieve more
kept informed about the availability safety team played a pivotal role in
chorine fumes, provided lighting and than 4 million safe man-hours, smiles
of temporary power lines. The safety synchronizing the different shutdowns
Vaibhav.
installed a blower system to reduce team devised a lock out tag out system and ensured secure buffer arrangements
the moisture level before taking up the which indicated the status of work to for work to be carried out across fronts.
works. A team of over 250 workmen
were deployed to manually wipe the
silt after the deposits were sucked out UNSCRAMBLE CORRECT ANSWERS
through negative suction head pump 1. SHOES FIRST, STEP NEXT 2. OUR MOTTO, SAFETY IN TOTO 3. MAKE SAFETY A WAY OF LIFE
sets. Vaibhav emphasizes, The whole
4. SAFETY PAYS WITH HAPPY DAYS 5. SAFETY IS EVERYBODYS BUSINESS
A diver with complete PPEs entering the underground reservoir process was closely monitored by the

42 HELMET, July - September 2015 HELMET, July - September 2015 43


BUILDING
A DAM?
Can it be safe! Yes!
But its a tall order!

D
ams are truly awe-inspiring amounts of water have to continuously some vital safety steps that have to be The safety of a dam covers all stages in its engineering standards for safety, if it is with the enormous amount of piping
manmade structures that contend with a most unpredictable taken while building a dam. life cycle commencing with the inception being operated safely, if its condition is or even due to natural forces like
astound one with their aspect nature! Over the years, dam stage through to the planning and assessed periodically and the operators earthquakes or flash floods that may
immensity, strength and sheer construction has improved with Surprisingly, dams are a bit like people: design stages followed by construction of the dam are well prepared for exceed the anticipated flow.
presence. There is always an uncanny better technology, greater knowledge one is never quite like another, they and commissioning, ongoing operation, all conceivable emergencies. Sadly,
are temperamental, unpredictable, Since each dam is unique, it is very
calm around dams; as if they are of design principles and superior maintenance and surveillance and, in however, one can never be too sure
liable to react completely differently difficult to find a useful reference
waiting in animated suspense for understanding of the characteristics certain cases, decommissioning. One because trouble could be lurking round
in two identical situations all of which to either diagnose symptoms or
something dramatic to occur and that of foundations and dam materials can only breathe easy of having ticked the corner due to a variety of reasons:
makes dam construction extremely take corrective action. Dams have a
is quite possible because these colossal yet, dam disasters are not uncommon all the relevant boxes if a dam has been overtopping, inadequate spillway
challenging. foundation below and the manmade
structures that store mind-boggling and this article attempts to enumerate built in compliance with the prevailing capacity, spillway gate failure, issues

44 HELMET, July - September 2015 HELMET, July - September 2015 45


structure that towers above and to eliminate or minimize the risks managerial approaches to identify The procedure demands some key Designing a dam is not just about flooding or any occurrence of such events.
there is an intricate interaction that of injury throughout the life of the any foreseeable hazards that have requirements: eliminating risks but it is to evolve a The frequency of these inspections is
is constantly played out between the product being designed. It begins at the potential to harm those involved yy All relevant parties including design, systematic safety based approach to dictated by the overall performance of
two very much like in a marriage. The the conceptual and planning stages in the construction process must be construction & safety teams must be determine the right solution. Synergy the dam and the existing conditions like
slightest unpleasant ripple in this finely involving and balancing the objectives identified at the earliest opportunity involved in risk assessments and the of design intent during implementation they could be more frequent for a dam in
balanced relationship can spell disaster of practicality, aesthetics, cost and and necessary mitigation measures risk management process; is crucial to the safety of the dam and a seismic prone zone. Technology does
much again like human relationships! functionality, which at times can be implemented. yy Risk assessments & safe work since design is not just about drawings, not, however, replace visual surveillance
competing. method statements must be specs and reports, the designers role and electronic data has to be regularly
Risks associated with dams broadly At L&T, for example, Heavy Civil developed and approved prior to is absolutely critical. Once the design compared, where possible, with manual
include situations relating to operation, Safety Risk Management is an Infrastructure ICs risk management the commencement of any work is approved, it is time to start with the readings to check and corroborate quality
maintenance, testing, retrofitting old integral part of the construction process is applied through the five steps activity g; construction of the dam but throughout and veracity of data.
dams, safety of people, environment and planning of a dam and combines to risk management and is the key yy All identified risks and risk this process, continuous evaluation or
re-engineering ensures that the finalized The safety plan is supplemented by an
the like. technical, consultative, systematic and driver for risk control within the IC. mitigation plans must be
design is compatible with the prevailing Emergency Response Plan that identifies
documented, approved and simply
A safe design of a dam can be loosely communicated to all parties conditions. emergency conditions which could
defined as The integration of hazard 1. Identify 2. Evaluate endanger the integrity of the dam and
3. Determine 4. Implement 5. Review & yy Regular reviews undertaken should
Hazards / the Risk / A veritable army is required to build a require immediate action, prescribes
identification and risk assessment controls controls update be updated and communicated
Aspects Impact dam: architects, engineers, hydrologists, procedures to be followed in the event
methods early in the design process when change has occurred.
geologists, environmentalists, of an emergency and provides timely
seismologists, social scientists, industrial warning to appropriate emergency
designers, clients, developers, builders, management agencies to implement
owners, job managers, health and safety protection measures for downstream
professionals, ergonomics practitioners, communities.
suppliers (including manufacturers,
importers, plant-hire), constructors, While the safety of dams are regularly
installers, traders, maintenance personnel, monitored during operation and
Government regulators, inspectors maintenance, extensive safety reviews
the list is never-ending. All that is then are conducted based on their type, height,
required is for all these stake holders to be age and record of any past incidents of
in perfect sync with one another to create distress; and frequency of such reviews
a masterpiece much like a symphony could vary from 5 to 10 years. Such safety
orchestra playing in complete sync to reviews could possibly include detailed
create wonderful harmony. study of the structural, hydraulic,
hydrologic and geotechnical design
Once constructed, a well-articulated aspects and of the records and reports
Dam Safety Programme is imperative to from surveillance activities as well as a
oversee design construction, operation review of the dam safety management
and maintenance, surveillance, safety documentation. The frequency of Safety
review, remedial action, education, Reviews can be altered due to the
training and emergency preparedness in identification of a deficiency or weakness,
addition to constant vigilance, frequent changes in standards, acceptance criteria
sampling and testing and ceaseless or technology, changes in arrangements
inspections and quality control. Again, at the dam or a requirement by a higher
like people, dams also age due to the authority or dam regulator.
constant pressure from water, seismicity,
temperature and winds therefore Despite all precautions, dam
surveillance is crucial. These could be construction and maintenance is a lot
routine inspections, periodic dam safety about skill, capability, management,
inspections, comprehensive inspections never letting your eyes off the ball and
or special emergency inspections the associated uncertainties! Yes, it
especially after an earthquake or heavy definitely is a tall order!!

46 HELMET, July - September 2015 HELMET, July - September 2015 47


SAFETY IS AS SIMPLE AS
ABC

ALWAYS BE CAREFUL

Edited by Mr. Vinod Jacob Chacko for L&T Construction from L&T Construction Headquarters, Manapakkam, Chennai - 600 089. The views
expressed in this magazine are not necessarily those of the Management. The contents of this magazine may not be reproduced without
the written permission of the Editor. Not for sale. Only for circulation among employees of L&T Construction. Printed at NPT Offset Press
Pvt. Ltd., Chennai.

You might also like