Professional Documents
Culture Documents
http : //www.cigre.org
Design Challenges for 800kV, 3000MW HVDC Champa Kurukshetra Transmission link with
Dedicated Metallic Return (DMR) Users Perspective
SUMMARY:
Power Grid Corporation of India Ltd. (POWERGRID) is constructing 800kV, 3000MW HVDC Champa
Kurukshetra Transmission link with Dedicated Metallic Return (DMR) instead of Conventional Ground
Return. The HVDC Transmission line is app. 1305 kms long and both the pole and ground return conductors
are running on the same tower. This will be the first 800KV HVDC Project having DMR conductor running
on the same tower carrying the pole Conductor. Provision is kept to upgrade above HVDC Bipole to 6000 MW
at a later date with increased power transfer requirement. The proposed scheme shall facilitate strengthening of
North-West transmission corridor for dispersal of power with reliability and security. The paper elaborates the
various challenges in the conception and design pertaining to the above said project from users perspective.
The major issues discussed in the paper includes-
*puneet@powergridindia.com
1
Introduction
Presently, in the Indian Power System, the North-West inter-regional transmission corridors are mainly based
on alternating current technology. However, considering the long distance and the amount of power transfer
requirements to Northern Region from Independant Power Producers (IPP) generation projects in Chhattisgarh,
HVDC System has been planned to transmit the power generated by these IPPs. Power Grid Corporation of
India Ltd. (POWERGRID), is constructing 800kV, 3000MW HVDC Champa Kurukshetra Transmission
link with Dedicated Metallic Return (DMR) instead of Conventional Ground Return.Provision of addition of
another 3000MW Bipole to the above said link thereby increasing the capacity to 6000 MW at a later date has
been kept with increased power transfer requirement to NR. This 800 kV link will provide the transmission
scheme associated with IPPs in Chhattisgarh through a Pooling substation in Champa, scheduled for
commissioning during the period of 2015 -2016.
The HVDC system shall have the capability of operating for two hours at transmitted power levels at least
10% (ten percent) higher than the maximum continuous ratings for AC Voltages (380kV-420kV), ambient
temperatures (Dry Bulb temp. In the range of 0 to 50 Deg) and redundant cooling (Converter Transformer and
Thyristor Valve) in service. The HVDC system shall be capable of operating for half an hour at transmitted
power levels of at least 20% (twenty percent) higher than the maximum continuous ratings. Further, the HVDC
2
has dynamic rating to operate at least for five seconds at 1.46 pu power level. This capability
apability can be utilised in
dynamic conditions for AC system stablisation.
tablisation. Also,The HVDC system shall be capable of operating
continuously at Reduced DC Voltages to neutral of upto 640 kV at rectifier DC bus in bipolar as well as in
monopole modes thereby ensuring supply of power under inlcement
inl ement weather conditions.
The main scheme parameters for the HVDC project are finalised as per below :
Rectifier Inverter
Fig 1
Various Operating Modes with respect to conductor/DMR configuration
The HVDC Line is designed with a Dedicated Metallic Return Conductor (DMR) which is split into 2 x Twin
Lapwing Conductors, namely, DMR 1and DMR 2 for reliability and maintainability
maintainability. Necessary switching
arrangement is provided with Isolators to isolate each DMR Conductor offline and operate the system with one
twin lapwing DMR conductor.
The various modes of operation envisaged are as per following:-
following:
a) Bi-polar
polar with both DMR in operation (Fig 2)
b) Bi-polar
polar with one DMR in operation. (Fig 3)
c) Mono-Polar
Polar with both DMR parallel to Pole Metallic Return Conductor(PMR) (Fig 4)
d) Mono-Polar
Polar with one DMR parallel to PMR (Fig 5)
e) Mono-polar
polar with both DMR (Fig 6)
f) Mono-polar with one DMR (Fig 7)
g) Mono-polar with PMR (Fig 8)
3
Fig 2 Fig 3
Fig 4 Fig 5
Fig 6 Fig 7
4
Fig 8
DC Switches
The DC Switches namely, Dedicated Metallic Return Transfer Breaker (GRTS), Pole Metallic Return
Transfer Breaker (MRTB) are critical equipment in the scheme as they are utilised in realising the
flexibility offered by various operating modes of the Scheme. In a conventional HVDC scheme with
Ground Return, the duty of the MRTB is higher than the GRTS as the same has to commutate larger
current from ground to metallic
metallic path, the resistance of Ground being considerably lower than that of
the Metallic path. However, in the present scheme, the Pole Conductor is having lower resistance as
compared to the Dedicated
ated Metallic Return Conductor. Therefore, the duty of the GRTS is higher than
the MRTB Breaker. Further, these switches being in the return path, these have to be designed taking
into consideration the future Bipole operation with 6000 MW
5
Switching to Pole Metallic Return Mode both in automatic and manual mode with an operating
telecommunication.
Blocking of converters.
In Monopolar DMR operation, DMR fault is to be detected and cleared with automatic restart.
Open Circuit
In case of open circuit in one conductor only, the protection shall limit the current in the
dedicated metallic return conductor to limit overloading of the remaining conductor.
In case of open circuit in both conductors the system shall be grounded at the converter station
and the DMR Line shall be isolated.
Operation shall continue in balanced Bipolar Mode or Monopolar Pole Metallic Return as
applicable.
There is a requirement of providing necessary equipment to detect faults on the DMR conductor at the
rectifier and Inverter station under all conditions, which could restrict the power carrying capabilities
of the HVDC transmission system depending on the nature of fault on the DMR.
Fig 11 Fig 12
Preliminary studies of the impact of parallel AC Lines have been carried out by POWERGRID on
PSCAD to assess the induced current on the HVDC Line due to the parallel AC Lines and the results
indicate the presence of Induced AC Current on the HVDC Line. Max value of induced current by 765
kV &400 kV line obtained in bipolar Mode and Monopolar
Monopolar Mode with DMR 1 and DMR 2 are
obtained as 14 Amp Refer (Fig 13) and 6.93 Amp Refer (Fig 14) respectively
respectively.
Fig 13 Fig 14
Extensive
xtensive assessment study using PSCAD to verify the impact of the location of these circuits on the
levels of AC current induced on the DC circuits considering all operating modes, relative position of
the AC circuit locations in relation to the DC transmission,
transmission, different frequency deviations, DC filter
outages and variations on the DC transmission line lengths are to be carried out in the project. Also the
resonance study of the DC Line as well as DMR line is being carried out in Champa Kurukshetra
Project.
Selection of Pole & DMR Conductor Configuration for HVDC Transmission Line
Construction of Indias first +/- 800 kV HVDC transmission line between Biswanath Chariyali & Agra
(line length approx. 1750 km) by POWERGRID is in advance stage. Extensive studies were carried
out for design and optimization of this line including studies for conductor-bundle
bundle selection ; tower
design optimization ; insulator design & optimization ; electrical clearances & earthwire selection etc.
Hexagonal ACSR Lapwing conductor-bundle
cond bundle and Y type insulator strings were adopted for the HVDC
line [10]. The basic transmission line parameters and Pole Conductor Configuration for +/- 800 kV
HVDC Champa-Kurukshetra
Kurukshetra line has been adopted from the design of the 800 kV Biswanath
Chariyali - Agra line. The +/- 800 kV HVDC Champa-Kurukshetra
Kurukshetra line has been designed to carry
6000 MW considering the addition of future Bipole (3000MW) at Champa and Kurukshetra. The
Dedicated metallic return conductor has to be rated to carry the current of two poles (present and
future) connected in parellel to one HV conductor.. Additionally, the DMR must be able to carry the
7
current corresponding to reduced voltage operation of Monopolar HVDC line and half an hour 20%
over load rating. For the +/- 800 kV HVDC Champa-Kurukshetra line, six ACSR Lapwing conductors
per pole and four ACSR Lapwing conductors for the DMR are being used.
Fig 15 Fig 16
Fig 17 Fig 18
8
Alternative-1 (2 X Twin Lapwing DMR above the conductors and below each earthwire) has been
adopted for the +/-800 kV HVDC Champa-Kurukshetra line with DMR conductor keeping in view the
advantages offered by the alternative viz. higher reliability of DMR, ease of line maintenance under
one pole shutdown with the other pole in operation & more flexibility of operation.
9
Acknowledgement
Authors wish to thank POWERGRID for granting them permission to present the paper. Views
expressed in the paper are of the authors only and need not necessarily be of the management of
POWERGRID.
BIBLIOGRAPHY
[1] Voiplav Jankov and Mark Stobart, "HVDC system performance with a neutral conductor".
ICHVE International conference, 2010
[2] R.R.Welling, M Sublich and others, Simultaneous Pole and Neutral Faults on an HVDC Line
with Dedicated Metallic Return Power Delivery, IEEE Transactions on (Volume:5, Issue: 2),
Pages 1129-1136, 1990
[3] R.N. Nayak, R.P. Sasmal and others "Experience with blocking devices during monopolar
operation of 500 KV 2000MW Talcher - Kolar HVDC", Cigre B4-204:2006
[4] J. Arrillaga,Y.H.Liu, N R Watson, Flexible Power Transmission The HVDC Option
[5] Edward Wilson Kimbark, Direct Current Transmission, Volume I
[6] Hingorani and Gyugyi, Understanding Facts
[7] E.V. Larsen R.A. Walling C.J. Bridenbaugh , Parellel AC/DC Transmission Lines steady state
Induction Issues,IEEE Transactions on Power Delivery, Vol. 4, No. 1, January 1989
[8] P. Sarma Maruvada, Electric Field and Ion Current Environment of HVdc Transmission Lines:
Comparison of Calculations and Measurements, IEEE Transactions on Power Delivery, Vol. 27,
No. 1, January 2012, pp. 401-410.
[9] P. Sarma Maruvada, Corona in Transmission Systems: Theory, Design and Performance,
Johannesburg, South Africa, Eskom Holdings, 2011
[10] Rajesh Gupta, Anish Anand,Gopal Ji, Gopal Gupta, B.S. Pandey, , Design and Optimization of
Indias First +/- 800 kV HVDC Transmission Line, Cigre, New Delhi, 2013
[11] Puneet Tyagi, Rakesh Kumar, M M Goswami, I S Jha 800kV, 3000MW HVDC Champa-
Kurukshetra Transmission Link with dedicated Metallic Return (DMR)- Key Design
Consideration,GRIDTECH 2013, New Delhi
10