Activity ID Activity Name Original Start Finish Total Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018

Total Qtr 4, 2017 Qtr 1, 2018 Qtr 2, 2018 Qtr 3, 2018 Qtr 4, 2018 Qtr 1, 2019
Duration Float Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan

CN:A301233 US 550 Bridge Over Rio Grande - Update 416d Oct-18-2017 ADec-02-2018 -7d CN:A301233 US 550 Bridge Over Rio Grande - Upd
A1030 SUBSTANTIAL COMPLETION 0d Nov-11-2018 -7d SUBSTANTIAL COMPLETION
A1020 PUNCHLIST 20d Nov-12-2018 Dec-02-2018 -7d PUNCHLIST
A1040 FINAL COMPLETION 0d Dec-02-2018 -7d FINAL COMPLETION
GENERAL CONDITIONS 130d Oct-18-2017 AFeb-11-2018 -11d GENERAL CONDITIONS, Feb-11-2018
LONG LEAD SUBMITTALS 130d Oct-18-2017 AFeb-11-2018 -11d LONG LEAD SUBMITTALS, Feb-11-2018
SD1010 NMDOT REVIEW OF STEEL SHOP DRAWINGS 20d Oct-18-2017 ANov-13-2017 -11d NMDOT REVIEW OF STEEL SHO P DRAWINGS
SD1020 FABRICATION OF STEEL COMPONENTS 87d Nov-14-2017 Feb-11-2018 -11d FABRICATION OF STEEL COMPONENTS
PHASE 2 72d Feb-12-2018 Apr-24-2018 -11d PHASE 2, Apr-24-2018
PH2050 ERECT STEEL GIRDERS SPANS 1 2d Feb-12-2018 Feb-13-2018 -11d ERECT STEEL GIRDERS SPANS 1
PH2060 ERECT STEEL GIRDERS SPANS 2 2d Feb-14-2018 Feb-15-2018 -11d ERECT STEEL GIRDERS SPANS 2
PH2080 ERECT STEEL GIRDERS SPANS 4 2d Feb-16-2018 Feb-17-2018 -11d ERECT STEEL GIRDERS SPANS 4
PH2090 ERECT STEEL GIRDERS SPANS 5 2d Feb-18-2018 Feb-19-2018 -11d ERECT STEEL GIRDERS SPANS 5
PH2100 PROFILE GIRDERS 3d Feb-20-2018 Feb-22-2018 -11d PROFILE GIRDERS
PH2110 INSTALL SIP 10d Feb-23-2018 Mar-04-2018 -11d INSTALL SIP
PH2120 FORM AND REBAR BRIDGE DECK TO STA 105+62.82 10d Mar-05-2018 Mar-14-2018 -11d FORM AND REBAR BRIDGE DECK TO STA 105+62.82
PH2150 FORM AND REBAR BRIDGE TO STA 109+08.15 10d Mar-15-2018 Mar-24-2018 -11d FORM AND REBAR BRIDGE TO STA 109+08.15
PH2180 DRY RUN FOR DECK PLACEMENT 2 1d Mar-25-2018 Mar-25-2018 -11d DRY RUN FOR DECK PLACEMENT 2
PH2160 PLACE DECK PLACEMENT 2 1d Mar-26-2018 Mar-26-2018 -11d PLACE DECK PLACEMENT 2
PH2240 CURE DECK 2 7d Mar-27-2018 Apr-02-2018 -11d CURE DECK 2
PH2260 INSTALL PED RAIL 7d Apr-03-2018 Apr-09-2018 -11d INSTALL PED RAIL
PH2220 FRP CWB 9d Apr-10-2018 Apr-18-2018 -11d FRP CWB
PH2250 WEATHER DAYS 6d Apr-19-2018 Apr-24-2018 -11d WEATHER DAYS
PH2330 COMPLETE PHASE 2 0d Apr-24-2018 -11d COMPLETE PHASE 2
PHASE 3A 20d Apr-25-2018 May-14-2018 -11d PHASE 3A, May-14-2018
PHA3050 START PHASE 3A 0d Apr-25-2018 -11d START PHASE 3A
PHA3060 PERFORM REMOVAL FOR DETOURS 5d Apr-25-2018 Apr-29-2018 -11d PERFORM REMOVAL FOR DETOURS
PHA3080 INSTALL DS 10A 2d Apr-30-2018 May-01-2018 -11d INSTALL DS 10A
PHA3090 BUILD CBC CONNECTION FROM EXISTING TO 30" PIPE 9d May-02-2018 May-10-2018 -11d BUILD CBC CONNECTION FROM EXISTING TO 30" PIPE
PHA3100 REGRADE DITCH LINE 130+50 TO 134+50 LT 4d May-11-2018 May-14-2018 -11d REGRADE DITCH LINE 130+50 TO 134+50 LT
PHA3110 COMPLETE PHASE 3A 0d May-14-2018 -11d COMPLETE PHASE 3A
PHASE 3B 14d May-15-2018 May-29-2018 -11d PHASE 3B, May-29-2018
PHB3050 START PHASE 3B 0d May-15-2018 -11d START PHASE 3B
PHB3070 DEMO EXISTING MEDIAN 5d May-15-2018 May-19-2018 -11d DEMO EXISTING MEDIAN
PHB3080 GRADE AND PREP FOR DETOURS 5d May-20-2018 May-24-2018 -11d GRADE AND PREP FOR DETOURS
PHB3090 PAVE PHASE 3B DETOURS 4d May-25-2018 May-29-2018 -11d PAVE PHASE 3B DETOURS
PHB3060 COMPLETE PHASE 3B 0d May-29-2018 -11d COMPLETE PHASE 3B
PHASE 4A 51d May-30-2018 Jul-22-2018 -11d PHASE 4A, Jul-22-2018
PHB4010 SET TCWB SOUTH SIDE 3d May-30-2018 Jun-01-2018 -11d SET TCWB SOUTH SIDE
PHA4120 START PHASE 4A 0d May-30-2018 -11d START PHASE 4A
PHA4140 EARTHWORK FOR NORTH EAST WIDENING 7d Jun-02-2018 Jun-08-2018 -11d EARTHWORK FOR NORTH EAST WIDENING
PHA4200 INSTALL DS1-B 3d Jun-09-2018 Jun-11-2018 -11d INSTALL DS1-B
PHA4280 INSTALL DS-2 7d Jun-12-2018 Jun-18-2018 -11d INSTALL DS-2
PHA4190 INSTALL DS3 3d Jun-19-2018 Jun-21-2018 -11d INSTALL DS3
PHA4290 INSTALL DS 4 NORTH 3d Jun-22-2018 Jun-24-2018 -11d INSTALL DS 4 NORTH
PHA4300 INSTALL DS 5 NORTH 2d Jun-25-2018 Jun-26-2018 -11d INSTALL DS 5 NORTH
PHA4310 INSTALL DS -6 2d Jun-27-2018 Jun-28-2018 -11d INSTALL DS -6
PHA4320 INSTALL DS 7 NORTH 2d Jun-29-2018 Jun-30-2018 -11d INSTALL DS 7 NORTH
PHA4330 INSTALL DS 8 2d Jul-01-2018 Jul-02-2018 -11d INSTALL DS 8
PHA4210 INSTALL DS-9 3d Jul-06-2018 Jul-08-2018 -11d INSTALL DS-9
PHA4230 INSTALL DS-10B NORTH 2d Jul-09-2018 Jul-10-2018 -11d INSTALL DS-10B NORTH
PHA4250 INSTALL DS-12D 3d Jul-11-2018 Jul-13-2018 -11d INSTALL DS-12D
PHA4220 INSTALL DS-15 NORTH AND CAP 2d Jul-14-2018 Jul-15-2018 -11d INSTALL DS-15 NORTH AND CAP
PHA4240 INSTALL DS-16 NORTH AND CAP 2d Jul-16-2018 Jul-17-2018 -11d INSTALL DS-16 NORTH AND CAP
PHA4260 INSTALL DS-17 NORTH AND CAP 2d Jul-18-2018 Jul-19-2018 -11d INSTALL DS-17 NORTH AND CAP
PHA4270 INSTALL DS-18 NORTH AND CAP 3d Jul-20-2018 Jul-22-2018 -11d INSTALL DS-18 NORTH AND CAP
PHA4130 COMPLETE PHASE 4A 0d Jul-22-2018 -11d COMPLETE PHASE 4A
PHASE 4C 22d Jul-23-2018 Aug-15-2018 -7d PHASE 4C, Aug-15-2018
PHC4000 ERECT STEEL GIRDERS SPANS 3 5d Jul-23-2018 Jul-26-2018 -9d ERECT STEEL GIRDERS SPANS 3
PHC4010 START PHASE 4C 0d Jul-23-2018 -9d START PHASE 4C
PHC4020 FORM AND REBAR PLACEMENT 3 10d Jul-27-2018 Aug-05-2018 -7d FORM AND REBAR PLACEMENT 3
PHC4030 DRY RUN DECK PLACEMENT 3 1d Aug-06-2018 Aug-06-2018 -7d DRY RUN DECK PLACEMENT 3
PHC4040 PLACE DECK 3 1d Aug-07-2018 Aug-07-2018 -7d PLACE DECK 3
PHC4050 CURE DECK 3 7d Aug-08-2018 Aug-14-2018 -7d CURE DECK 3
PHC4070 COMPLETE BRIDGE BARRIER 1d Aug-15-2018 Aug-15-2018 -7d COMPLETE BRIDGE BARRIER
PHC4060 COMPLETE PHASE 4C 0d Aug-15-2018 -7d COMPLETE PHASE 4C
PHASE 5 51d Aug-16-2018 Oct-06-2018 -7d PHASE 5, Oct-06-2018
PH5520 START PHASE 5 0d Aug-16-2018 -7d START PHASE 5
PH5540 SHIFT TRAFFIC 1d Aug-16-2018 Aug-16-2018 -7d SHIFT TRAFFIC
PH5560 INSTALL LEVELING PAD 3d Aug-17-2018 Aug-19-2018 -7d INSTALL LEVELING PAD
PH5550 INSTALL MSE WALL 10d Aug-20-2018 Aug-29-2018 -7d INSTALL MSE WALL
PH5570 FRP SLEEPER ABUTMENT 2 2d Aug-30-2018 Aug-31-2018 -7d FRP SLEEPER ABUTMENT 2
PH5580 FRP APPROACH SLAB ABUTMENT 2 5d Sep-01-2018 Sep-06-2018 -7d FRP APPROACH SLAB ABUTMENT 2
PH5590 FRP BRIDGE BARRIER DEPARTURE 3d Sep-07-2018 Sep-09-2018 -7d FRP BRIDGE BARRIER DEPARTURE
PH5600 FRP RETAINING WALL 8d Sep-10-2018 Sep-17-2018 -7d FRP RETAINING WALL
PH5610 FLATWORK COMPLETE 9d Sep-18-2018 Sep-26-2018 -7d FLATWORK COMPLETE
PH5620 INSTALL CWB 250 LF RT 5d Sep-27-2018 Oct-01-2018 -7d INSTALL CWB 250 LF RT
PH5630 INSTALL METAL RAILING 5d Oct-02-2018 Oct-06-2018 -7d INSTALL METAL RAILING
PH5530 COMPLETE PHASE 5 0d Oct-06-2018 -7d COMPLETE PHASE 5
PHASE 6A 26d Oct-07-2018 Nov-01-2018 -7d PHASE 6A, Nov-01-2018
PHA6110 SHFIT TRAFFIC 1d Oct-07-2018 Oct-07-2018 -7d SHFIT TRAFFIC
PHA6150 START PHASE 6A 0d Oct-07-2018 -7d START PHASE 6A
PHA6120 COMPLETE MEDIAN WORK 10d Oct-08-2018 Oct-17-2018 -7d COMPLETE MEDIAN WORK
PHA6140 INSTALL ASPHALT CURB 10d Oct-18-2018 Oct-27-2018 -7d INSTALL ASPHALT CURB
PHA6130 RESET TCWB ON NORTH SIDE OF US 550 5d Oct-28-2018 Nov-01-2018 -7d RESET TCWB ON NORTH SIDE OF US 550
PHA6160 COMPLETE PHASE 6A 0d Nov-01-2018 -7d COMPLETE PHASE 6A
PHASE 6B 10d Nov-02-2018 Nov-11-2018 -7d PHASE 6B, Nov-11-2018
PHB6110 START PHASE 6B 0d Nov-02-2018 -7d START PHASE 6B
PHB6160 INSTALL PROJECT SIGNING 10d Nov-02-2018 Nov-11-2018 -7d INSTALL PROJECT SIGNING
PHB6170 SEED PROJECT AND INSTALL FINAL BMP'S 10d Nov-02-2018 Nov-11-2018 -7d SEED PROJECT AND INSTALL FINAL BMP'S
PHB6120 COMPLETE PHASE 6B 0d Nov-11-2018 -7d COMPLETE PHASE 6B