You are on page 1of 1

Batching Plant Setting Up Schedule

To make schedule at Site with following key point Start Concrete production shall
be after production test . It
1 Schedule for Foudation of BUMA meens that Production will
2 Schedule of USI to confirming with Project Manager Hendry (He will stay at site 2 weeks from Sep 12) start Dec.4 in eariest case
3 Check Material Availability supplied by USI and setting target receiving schedule(If not yet received)
4 Minimum Requirement for Production concrete:
(F)1Unit of Batching Plant, (G)Loading Ramp, (N)Labolatory, (C)Chiller, (J)Concrete Wash Pond
(H)Sediment Pond 1,(Q)Toilet, (R )Sewage, (T)Genset Shelter 1, Water Supply Line, Electrical Supply Line, Drainage
5 To dedicate water supply tie in point
6 Drainege must be planned at site and incorporating to This Schedule

Work Description Sep Oct Nov Dec


4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25
S/C Milestone 1st Concrete Casting
A WORK SHOP
Foundation USI
Container Installation USI
Roof Installation USI
B DAIRY SAND & AGGREGATE SHED
Foundation BUMA
Roof Colomn Materal Fab BUMA
Elecrion of Shed BUMA
C CHILLER & INSULATED TANK (3 ea)
Foundation USI to be confirmed BUMA on
Chiller Installation USI
25th Sep
Water Supply Line (Inside Area) USI
D CONCRETE WATER TANK
Foundation USI
Chiller Installation USI
Water Supply Line (Inside Area) USI
E West HOPPER, Mixer, Conveyor, Operation Room & 3Silos
Foudation with Anchor Bolt BUMA
Installation Hopper USI
Installation Conveyer USI
Installation Silo USI
installation Operation Room USI
Electrical Line from Generator USI
F East HOPPER, Mixer, Conveyer, Operation Room & 4 Silos
Foudation with Anchor Bolt BUMA
Installation Hopper USI Hopper Roof to be considered
Installation Conveyer USI
where necessary
Installation Silo USI
installation Operation Room USI
Electrical Line from Generator USI
G LOADING RAMP 1) Plan to Subcontract between USI & Baharu
ConcreteBund Wall BUMA will be 26th September.
Back Fill BUMA 2) Plan to start Erection work of 1st Batcing
Crushed Stone BUMA Palnt Unit from 28th September
H SEDIMENT POND 1
Size Information USI
Excavation USI
Concrete Lining w/WireMesh BUMA
I SEDIMENT POND 2 considering SIMOPS.
Size Information USI Buma will install scaffolding only one side.
Excavation USI (other than Hoppoer side).
Concrete Lining w/WireMesh BUMA to carry out Retaining Wall work.
J CONCRETE WASH POND
Size Information USI
Concrete Paving w/WireMesh BUMA
K CRUSHER MACHINE
Gravel Paving BUMA
L CONCRETE WASTE AREA
Gravel Paving BUMA
M CURING PONDSteel Pond)
Excavation USI
Installation USI
Back Fill USI
N LABORATORY DELIVERY CHECK
Foundation USI
Laboratory (Container) Installation USI
Air Conditioner USI
Water Supply Line (Inside Area) or Small Tank USI
Electrical Line from Generator (P)Office Area
O REST AREA
Installation w/o Fdn USI
P OFFICE AREA
Foundation USI
Office Installation USI
Generator Installation w/Steel Pan etc. USI
Q TOILET
Foundation USI
Toilet Installation USI
R SEWAGE (Septic Tank) 4nos of site toilet is under
Excavation USI operation in batching Plant Area. it
Septic Tank Installation USI can be utilized in initial stage.
Back Fill USI
S STOCK CEMENT SHELTER
Foundation BUMA
Roof Colomn Materal Fab BUMA
Elecrion of Shed BUMA
T GENSET SHELTER 1 Strat Concrete production shall be
Size Information USI after production test . It meens
Concrete Pave w/Dike BUMA that Production will start Dec.4
Generator/Panel Installtion USI in eariest case
U GENSET SHELTER 2
Size Information USI
Concrete Pave w/Dike BUMA
Generator/Panel Installtion USI

CARIBLATION USI

PRODUCTION TEST USI


USI will arrange Government Authorities and PT DDT
to get certificate & calibartion for Batching Plant

You might also like