You are on page 1of 47

Acquisition of

Working Interest in
Kakap Production
Sharing Contract
(PSC)
INVESTMENT PROPOSAL

Ang Shi Mei A0105999L


Kenng Ong Shao Yang A0101968B
Lim Yong Khoon Ben A0101911J
Quay Jun Rong Terance A0111911X
Shawn Tiang Song En A0103536N
Tan Mew Leng A0101408X

GLENVILLE PETROLEUM
INVESTMENT COMMITTEE
1
Table of Contents
1. Overview of the Kakap Production Sharing Contract (PSC) ............................................................................ 4
Key Oil & Gas Reserves Metrics ...................................................................................................................... 5
2. Regional Business Opportunity: Indonesian Oil & Gas Sector ........................................................................ 7
Fiscal and Tax Reforms .................................................................................................................................... 7
3. Investment Summary ........................................................................................................................................ 9
Acquisition Bid ............................................................................................................................................... 11
Ownership of SPV and Equity Contribution................................................................................................... 12
4. Major Risks and Mitigation Measures ............................................................................................................ 13
Risk: Increase in 6-month USD LIBOR ......................................................................................................... 13
Mitigation Measures ....................................................................................................................................... 15
Interest Rate Swap ...................................................................................................................................... 15
Risk: Cost Escalation ...................................................................................................................................... 16
Mitigation Measures ....................................................................................................................................... 17
Fixed price (Lump sum) O&M contract w/ Cap and Floor on inflation-indexation ................................... 17
Service Level Agreement ............................................................................................................................ 18
Risk: Brent Oil Price ....................................................................................................................................... 18
Mitigation Measures ....................................................................................................................................... 20
Hedging with Derivatives ........................................................................................................................... 20
Costless collars and Swaps ......................................................................................................................... 22
Risk: Offtake Quantity / Demand Risk ........................................................................................................... 22
Mitigation Measures ....................................................................................................................................... 22
Take-or-Pay Contract .................................................................................................................................. 22
Risk: Political Risk ......................................................................................................................................... 23
Mitigation Measures ....................................................................................................................................... 23
Political Risk Insurance .............................................................................................................................. 23
ECA Loans Counter Guarantee ............................................................................................................... 24
Offshore Account ........................................................................................................................................ 24
Implementation Agreement ........................................................................................................................ 24
Strategic Consortium Structure ................................................................................................................... 24
Risk: Force Majuere........................................................................................................................................ 25
Mitigation Measures ....................................................................................................................................... 25
Concessions in Offtake Agreement and Loan Agreement .......................................................................... 25
Implementation Agreement ........................................................................................................................ 25

2
Insurance (financed using Catastrophe Bonds) ........................................................................................... 25
Re-Financing................................................................................................................................................... 26
5. Financing Structure ......................................................................................................................................... 28
Project Financing Structure and Contractual Parties ...................................................................................... 28
Special Purpose Vehicle (SPV) .................................................................................................................. 29
Government ................................................................................................................................................ 31
Lenders ....................................................................................................................................................... 31
Sponsors ...................................................................................................................................................... 33
Operators..................................................................................................................................................... 33
Offtakers ..................................................................................................................................................... 33
Key Contractual Agreements .......................................................................................................................... 34
Shareholders Agreement............................................................................................................................ 34
Production Sharing Contract ....................................................................................................................... 35
Loan Agreement ......................................................................................................................................... 35
Operations & Maintenance Agreement....................................................................................................... 37
Crude Oil Sales Agreement ........................................................................................................................ 37
Gas Sales Agreement .................................................................................................................................. 38
References ........................................................................................................................................................... 39

List of Appendices
A1 Risk Register with Mitigation Measures
A2 Oil and 6-Month LIBOR Model/ Illustrative Model
A3 Financial model inputs (Key Assumptions)
A4 Income statement
A5 Cashflow waterfall
A6 DCF and Financial Analysis
A7 Debt Structure
A8 Amortization Schedule
A9 Aggregated Loan Repayment
A10 Depreciation Schedule
A11 Capital Structure
A12 Sensitivity Analysis
A13 Valuation Range

3
1. Overview of the Kakap Production Sharing Contract (PSC)
The Kakap Production Sharing Contract (PSC) is an existing oil and gas field located in the
Natuna Sea between Malaysia and Indonesia. It is located approximately 480km northeast of
Singapore in Indonesian waters. The field is approximately 3000 km2 and has 8 producing oil
and gas fields.

Operations started in year 2000, with a remaining 20 years of production from 2016 onwards.
Currently, the produced gas is sold to Singapore through the West Natuna Transportation
(WNTS) to markets in Singapore. The WNTS collects and delivers dry, sales-quality gas direct
to Jurong Island, Singapore. The main trunk line of the WNTS runs towards Pulau Batam until it
reaches the territorial waters of Singapore (Figure 1).

Figure 1 Transportation Pipeline from Kakap to Singapore (Source: Premier Oil, 2016)

The major partners of the existing PSC are the Government of Indonesia, owner of the oil and
gas reserves, as well as contractors whom are tasked to explore, develop and produce oil and gas.
The contractors are entitled rights to operate the assets and receive production and revenue from
the sales of oil and gas.

4
Key Oil & Gas Reserves Metrics
Kakap PSC has four major oil and gas producing fields concentrated in the South of Kakap KF
Field, KRA Field, KH Field and KG Field. They are situated in water depths of approximately
90 metres and host all oil and gas production equipment (Figures 2-6).

Figure 2 KH Platform Figure 3 KF Platform

9 platform wells 14 platform wells


Average production rate: 5,000 bbl/day Average production rate: 3,500 bbl/day
and 12 mmcfd of gas

Figure 4 KG Platform Figure 5 KRA Platform

6 platform wells 13 platform wells


Average production rate: 3,000 bbl/day Average production rate 4,500 bbl/day
and 10 mmcfd of gas and 25 mmcfd of gas

5
Figure 6 Kakap Natuna FPSO

Maximum oil processing capacity: 25,000 bbl/day


Storage capacity: 650,000 bbl
Maximum offload rate: 19,000 bbl/day

The following table shows the remaining reserves breakdown for each field (Figure 7).
Recoverable reserves are classified into undiscovered and discovered.

Figure 7 Remaining reserves breakdown for each field

6
2. Regional Business Opportunity: Indonesian Oil & Gas Sector

Fiscal and Tax Reforms


Indonesia is an OPEC member but has been a net oil importer for years. Oil production has
declined steadily from a peak of 1.7 million bpd in 1991 to an average of 786,000 bpd in 2015.
Moreover the Oil and Gas sector in Indonesia is just a shadow of its former glory as collectively,
the sector is only expected to contribute 3.4% to state revenue in 2016, down from 25% in 2006.

In view of the despondent industry data as reflected above, the Indonesia government is adamant
to revive its flagging upstream oil and gas sector. The first of many steps planned for to give the
sector a boost includes a reversal of the changes introduced in the GR79- by removing taxes on
oil and gas exploration (VAT, import and land taxes) Furthermore, fiscal reforms in production
sharing contracts are also expected to follow in the near future as investors/sponsors can look
forward to receiving larger portions of exploration outputs, elevating the actual return on their
investments (Reuters, 2016).

Additionally, non-fiscal incentives to ramp up spending and investments in the oil and gas
industry are also proposed. They are as follows:

Non-Fiscal Incentives Proposed to Revise Government Regulation No. 79/2010


Costs for exploration in an area that is part of one working area can be reimbursed
through the cost recovery scheme
Investment credit; investment made by the oil and gas contractor will be reimbursed
by the Indonesian government (including interest payment)
Domestic market obligation; contractors will not have to comply with mandatory
sales to the domestic market for a specific period
A faster depreciation calculation to reduce contractor's' costs

Tax Amnesty
Indonesia has launched a Tax Amnesty programme to encourage funds worth US$42.7
billion in assets stashed offshore to be reinvested into the country. These funds are to be
used to boost the economy of Indonesia through:

1. Government bonds
2. State-owned enterprise bonds
3. Financial investments in appointed banks
4. Corporate bonds supervised by OJK (Indonesian government agency)

7
5. Government-related infrastructure projects
6. Sectors to be determined by the Ministry of Finance
7. Other investments based on prevailing law

The Tax Amnesty programme will ensure economic stability and growth in the future. As
such, in the face of a stable domestic economic climate, it will be less probable for the
government of Indonesia to heighten overall exploration and production costs through
taxes and fees.

8
3. Investment Summary

Key Financial Indicators


Debt-Equity ratio 78% / 22%
Present value of future cash flows USD$ 398.5million
NPV USD$ 0,51million
IRR 12.53%
EIRR 17.68%
Payback period 5.42Years
ROI 216.71%

Key Project Parameters


Expiry date of PSC 2035
Years left till Expiry 19.25 Years
Discount rate 12.5%
Hurdle rate 12.5%
Minimum DSCR 1.10
Target DSCR 1.20
Minimum LLDSCR 1.40
Target LLDSCR 1.50

Key Project Assumptions


Average Brent Oil Price/bbl USD$45.94 (Refer to Appendix_A1)
Average 6-Month LIBOR 2%
Average Cost Escalation rate 4%

Financing Structure
Debt-Equity ratio 78% / 22%
Risk-free rate (Rf) 1.99%
Taxes 30%
Equity 100million USD
Consortium Strength 5
Ownership of Glenville 24.5%
Paid up capital 24.5million USD
Shareholder type -Operator
-Major Shareholder
Debt 298million USD
Pre-tax net Cost of Debt 6.16%
After Tax Cost of Debt 4.312%

9
Acquisition bid
USD$398 million

10
In 2015, the minimum expected hurdle rate of an investment (in stocks) is approximately 10%
with a risk premium of 4% (Rf= 6%) based on the analysis of Berkshire. The returns on
investments in US stocks averages at 9.03% (arithmetic average) for the past 10 years, and
11.01% extending to 40 years.

Annual Returns on Investments in


S&P 500 3-month T.Bill 10-year T. Bond
Arithmetic Average
1928-2015 11.41% 3.49% 5.23%
1966-2015 11.01% 4.97% 7.12%
2006-2015 9.03% 1.16% 5.16%
Geometric Average
1928-2015 9.50% 3.45% 4.96%
1966-2015 9.61% 4.92% 6.71%
2006-2015 7.25% 1.14% 4.71%

Risk Premium
Stocks T Bills Stocks T Bonds
1928-2015 6.05% 4.548%
1966-2015 4.69% 2.90%
2006-2015 6.11% 2.53%

Compared against the historic market risk premium of 6% (highest), the investment in Kakap
PSC in year 2016 is highly profitable with rate of return at 12.53%, considering the current
Rf=2% The outlook of the investment market in Indonesia has been recognised to be positive
with potential growth attributing to the Governments efforts which includes approving of Tax
Amnesty programme.

Acquisition Bid
The recommended bid price for Kakap PSC will be at US$398 million. The proposed business
model of this project will generate returns at the rate of 12.53% and equity returns at 17.68%.
The payback period of the invested sum is 5.42 years, with a return of investment of 216.71%.
Over the project lifespan of 19.25 years from Q4 2016 - 2035, Glenville Petroleum will reap a
total profit of US$70.12million in nominal future value and US$4.33 million in present value.

11
Ownership of SPV and Equity Contribution
A Special Purpose Vehicle (SPV) will be formed with Glenville Petroleum being the major
shareholder and also the operator of the project. Glenville Petroleum will own 24.50% of the
SPV, following that with Samudera Indonesia owning 20.30%, Royal Dutch Shell with 19.40%,
British Petroleum with 18.50%, and Sembcorp Gas Pte Ltd with 17.30%. The respective parties
will contribute equity of US$1 million per 1% equity owned.

12
4. Major Risks and Mitigation Measures

Risk: Increase in 6-month USD LIBOR

Figure 8 LIBOR Predictions

The 6-Month USD LIBOR serves as the base benchmark interest rates for both tranches of
commercial loan undertaken by the SPV. As such, any movements in the LIBOR would have a
consequential impact on the amount of interest payable throughout the entire loan tenure. LIBOR
movements may not seem to have a significant impact on un-levered key financial indicators
such as the NPV and IRR, however, from the perspective of the investors, EIRR and Annual Net
income would be severely shaken due to the rising interest expense.

If Federal Reserve of the U.S. begins to raise the Federal Funds Rate, LIBOR is expected to
follow with this upward movement. The current indications are that Yellen and Co. are looking
to increase interest rates towards the end of 2016 to stimulate economic growth within the US
(Reuters, 2016). With the 2016 US Presidential Election casting a deep uncertainty on the
economic policies that are to come in the near future, it would be prudent to take up certain
measures to hedge against the uncertain future of LIBOR.

13
14
Mitigation Measures
Interest Rate Swap
An interest rate swap results in a fixed interest rate being agreed with the Lenders. This allows
the SPV to retain a firm grip on their future interest repayment cost. As PT Suribian expects
LIBOR to increase in the coming years, it would be wise to fix it when it is currently low. This
would ensure that interest repayments can be fixed at least for the next 3 years instead of letting
it float with LIBOR rates. This protects our downsides as rising interest rates for the period of of
the swap would have minimal effect on PT Suribians interest expense. Not to mention, the swap
will also reduce potential upsides in the event of a plunge in interest rates. However, the
probability of a further reduction of LIBOR is low as current rates are deemed to be around the
lowest in history.

Renewal periods of 3 years will mitigate LIBOR risks away for the period, allowing them to be
certain of their interest expenses and refine budget forecast during the same period. Although the
fixed rate will be higher than that of the floating rate at that point of time, it is important that the
agreed rate has to protect PT Suribian from the expected rising LIBOR within the 3 year periods.
As such, the SPV is able to do away with rising Interest Rate risk from the list of uncertainties.

15
Risk: Cost Escalation

Figure 9 Interest Rate Prediction

It is industry practice to engage the O&M services provider with a fixed price lump sum contract
containing a built-in inflation indexation fee adjustment clause. However, this arrangement
exposes the SPV operating profit to the risk of inflation-driven OPEX escalation. As captured in
the chart above, the variability range of Indonesias domestic inflation rate can span over a large
quantum of basis points. Historical records have shown that inflation rates have attained a high
of approximately 9% and an approximate average of 5% over the past 5 years. The repercussions
can be detrimental and dire on SPVs bottom line and resultant IRR due to the sensitive nature of
IRR to movements in the Cost escalation rate. With a cost escalation factor of 1.05 (5%), the
consequential IRR would plunge to an undesirable level of 11.19%, falling well below the hurdle
rate of 12.5%. Essentially, based on the sensitivity analysis, if the average cost escalation growth
rate> 4.03%, IRR< Hurdle

Cost escalation could also be due to repair cost for equipment breakdowns. If the equipment is
critical to the operation, it may halt the extraction and thus affecting the sales. In this case, the
SPV is importing machineries for oil and gas extraction from Germany.

16
Mitigation Measures
In view of the precarious nature of this risk factor, as any slight upward movements from the
base case would result the project IRR to be less than the hurdle rate, it is imperative to devise
risk mitigation measures to cement the foothold of our acquisition proposal at an investment
grade level. Listed below are the mitigation strategies that will be employed.

Fixed price (Lump sum) O&M contract w/ Cap and Floor on inflation-indexation
The O&M agreement for upstream oil and gas exploration usually functions on a fixed fee/lump
sum basis which is indexed for domestic inflation and renewable every 5 years. The lump sum
feature of the industrys O&M contracts does indeed grant certain degree of price (expenses)
certainty to the SPV, however, its effectiveness is often undermined by the built-in inflation-
indexation component which transfers the risk of inflation over to the SPV.

17
In order to mitigate our downside exposure, this inflation-driven cost escalation risk should be
shared between both the SPV and the O&M service provider. This could be achieved by
imposing both a resistance and support (ceiling and floor) to the amount of adjustment the
operating fees are allowed to fluctuate because of inflation. Based on the sensitivity analysis, an
adjustment limit of 6% should be imposed on the OPEX so as to maintain our DSCR levels
above our target level of 1.2. However this still has an inherent detrimental impact on the IRR, as
IRR levels will fall to approximately 10%, which lies outside our hurdle rate.

Service Level Agreement


The SPV could have a Service Level Agreement with the German equipment manufacturer. The
agreement would have clauses that ensure that the equipment is functional for a certain period of
time before the next scheduled maintenance. If the equipment failed before the next scheduled
date, the manufacturer would need to make good the defects and pay a fine to make up for the
loss incurred by the SPV due to this incident. This will transfer the risk of equipment
breakdown, which leads to cost escalation, to the equipment manufacturer. Furthermore, in view
of the hefty penalties in the event of a non-compliance to performance specifications, the
supplier would be more inclined to supply equipment above a pre-defined quality standard.

Risk: Brent Oil Price

Figure 10 Oil Price Prediction

The asset class of energy commodities is infamous for their high beta/volatility due to their
inherent elastic inter-dependency with a myriad of macroeconomic and systematic risk factors.
The iconic peak and trough prices recorded before and after the 2008 financial crisis stands
testament to its unpredictability and reflects a jarring concern Brent oil price movements have on
the top line of our business P/L statement.

18
For reference, long term average nominal Brent Oil Spot Prices is US$41.65/bbl for 1980 to
2015 (35 years), US$54.10/bbl for 1995 to 2015 (20 years), US$82.55/bbl for period 2005 to
2015 (10 years), US$93.17/bbl for 2010 to 2015 (5 years) and US$42.28/bbl for 2016 YTD.
Though it is possible that Brent oil prices may drop towards the 30-year average, however the
Oil and gas industry structure has changed over this period. Upstream exploration and production
costs have increased over the years and Brent Oil demand is now not only driven by
industrialisation of emerging markets as a conventional energy source but has also been
propelled by significant growth in oil-based investment fund (e.g. Oil ETFs). In present times, oil
price trends tend to be predisposed around the resistance-support band of US$40-50/bbl, which
mirrors more closely to the 35-year and 20-year average price, however, fuelled by upbeat
information on OPECs commitment to curtail overall output to 32.5million bbl/d, and with
optimistic economic growth forecasts of emerging markets from China and India bolstering
confidence in oil demand, the route to recovery seems less uncertain.

The recovery of oil prices may paint a comforting picture of revenue streams for PT Suribian,
especially since the formers high correlation with the latter. However, if Brent prices were to
skyrocket back to 2015 levels or beyond, off takers might cut back on their demand as their cost
prices go up as well. This will cause unstable revenue streams due to the elastic nature of oil.

A downside scenario which simulates a -10% reduction in average prices to USD$41 per barrel
of Brent Oil, would drive DSCR and IRR down to dangerous levels of 1.23 and 8.83%
respectively. If average oil prices were to plummet further to 10-year historical low levels of
USD$33.70 as in Q1 2016 (EIA, 2016), it will expose the project to even greater risks than the
aforementioned. The low revenue streams will make continuing operations unsustainable as the
DCSR will fall to levels of 0.7, deeming obligatory debt repayments impossible and resulting in
a potential cessation/termination of the project in its entirety due to the breach of contractual
covenants. As such, our comprehensive mitigation measures strives to reduce and eliminate the
potential risks that arises from volatile Brent oil prices.

19
Mitigation Measures
Hedging with Derivatives
SPV will ensure that there will be a rigorous system of market research and Brent oil price
modelling in place such that timely hedging could be planned for and executed to perfection.

Derivative strategy 1: Put options


Many oil and gas producers hedge with put options as doing so allows them to mitigate
their exposure to declining crude oil, natural gas and/or NGL prices while retaining the
ability to benefit from potentially higher prices. A put option provides the buyer of the
option with a hedge against potentially declining prices; it provides the buyer of the
contract the right, but not the obligation to purchase or sell a specific volume of the

20
underlying commodity or the financial equivalent of said commodity, on or before a
specific date or period of time.

In the event that forward looking market research reports revealed that Brent Oil Spot
prices would fall below the base level of USD$46/bbl for the upcoming month of
delivery, SPV would proceed to attain approval from the hedging committee to purchase
a USD$46 Brent Oil Put Option at a premium.

Figure 11 Crude Oil Hedging Put Option

If Brent Oil Spot prices were indeed to fall to levels below the strike price of $46/bbl, say
$36/bbl, our hedge would be in the money and the SPV would incur a net hedging gain
of $10 less premium paid. However, conversely, if spot prices were to exceed strike
levels, not only will the option not be exercised, but the net revenue received by SPV will
suffer a hit equivalent to the premium paid. Evident from the chart above, as much as
hedging with options will diminish (slightly) the potential gains of a bullish oil market, it
provides a reliable cushion in bearish times, by securing stable streams of revenue at the
strike price, ensuring that our debt could be service in a timely fashion.

21
Derivatives Strategy 2: Futures
Futures contract traded on the Intercontinental Exchange (ICE) serves as another viable strategy
to hedge the SPVs exposure to volatile Brent oil prices. When oil projections reveals a steep
downturn in prices, we will short the Brent oil Futures contract only to buy back the futures
contract at its trough point. The hedging gain on the futures contract, which equals to the
difference in both transaction prices, would be used to offset the actual loss in revenue from
Brent oil production due to the season of bearish times (low spot prices). In order to perform a
perfect hedge, one important complexity to grasp when dabbling in the futures market is the
calendar basis risk. To counteract the calendar basis risk, it entails the hedger to short a
combination of December and November 2017 contracts to properly hedge October 2017 Brent
oil production as the November futures contract will expire somewhere during the middle of the
October production month.

Costless collars and Swaps


Other measures involve the utilisation of costless collars and swaps to hedge against the price
volatility of Brent oil prices so as to ascertain the steadiness of our revenue streams and resultant
obligatory debt repayments. However, the residual risk/secondary risks generated in the form of
potential margin calls or increased collateral demands are to be monitored with prudence for
effective risk management.

Risk: Offtake Quantity / Demand Risk


In the event of an extreme economy slowdown or contraction in major oil consumers such as
China or India, there will be a sharp reduction in international demand for oil producers such as
PT Suribian. Any reduction in offtake quantity due to a global financial contraction will have
adversarial impacts on PT Suribians revenue streams, debt service and eventual returns.

Mitigation Measures
Take-or-Pay Contract
A take-or-pay contract is an agreement whereby the offtaker (BP) has to either take, and pay the
contract price for, a minimum contract quantity of commodity each year; or pay the applicable
contract price for such quantity if it is not taken during the applicable year. This places the risk
of deteriorating global demand on the offtaker-BP by requiring them to always be responsible for
the payment for a minimum purchase commitment, leaving PT Suribian with only the market
price risks to manage, which as mentioned above, will be hedged.

22
The take quantity for healthy cash flow generation based on our projection is fixated at
484,000bbl/quarter, however, to capitalise on periods when oil prices stampede into bull-market
territory, production output and resultant take quantity can be ramped up (to a maximum
capacity of 16,000bbl/day or 1.44million bbl/ quarter) so as to generate more cash flows, albeit
in a hastened reserve-depleting manner.

Risk: Political Risk


Political risk is the risk the project's returns could suffer as a result of political changes or
instability in a country. Instability affecting project returns could stem from a change in
government, legislative bodies, other foreign policy makers or military control. Also known as
"geopolitical risk," it becomes more of a factor as the time horizon gets longer. Political risk was
determined to be of a high concern to the team because of the political landscape in Indonesia.
According the Berne Union, the international organization of the worlds export credit and
political risk insurers, Indonesia ranked eighth in 2014 among the countries for which political
risk claims have been paid. It also continues to be a country for which investors have demanded
political risk mitigation, ranking fifth in the same year (Insurance Times, 2015). Some potential
political risk in Indonesia could be expropriation of project by the government, rising duties and
taxes, restrictions on repatriation of profits or use of project reserves and etc. In a recent move by
the Indonesian government that grant Amnesty to tax invaders (Chan and Soeriaatmadja, 2016),
analysts and speculator see it as the government is having a cash crunch and is relying on the
returning tax to ease the situation. As such, there are chances that the Indonesian government
will increase the tax payable and at the same time block the outflow of funds overseas.

Mitigation Measures
Political Risk Insurance
To mitigate such risk, PT Suribian will procure Political Risk Insurance (PRI) from Barclays. In
the scenario that the Indonesian government expropriate the working assets of the project, the
replacement cost or book value of the equipment or inventory that is lost will be insured under
the PRI. If the project experiences loss of realizable value of exported products, the PRI would
cover the book value of the crude oil or the replacement costs. Agencies also provide dispute
resolution services which prevents disputes from escalating and keeps important investments on
track. However, it should be noted that the PRI coverage is limited and does not holistically
cover the entire loss suffered by the project (IE Singapore, 2016).

23
ECA Loans Counter Guarantee
Loans obtained from ECA agencies would come with a counter guarantee from the host
government which incentivise them to abide by their promised commitments. As such, GOI
would be less probable to perform acts of expropriation, pre-mature termination or any other
unprecedented manoeuvres to undermine the success of the project.

Offshore Account
To avoid the government stopping the repatriation of profits overseas, the SPV may consider
setting up an offshore account. By having accounts set up overseas, the Indonesian government
would not be able to interfere in any transactions conducting by the SPV. However, in view of
the prevailing tax amnesty, Indonesian government may not give approval after knowing the
existence of such arrangement. This could be resolved through having an Implementation
Agreement with the Indonesian government, which will be mentioned in the next section.

Implementation Agreement
Implementation agreements provide for direct contractual obligations and undertakings between
the Indonesian government and the SPV. An example of a clause, extracted from World Bank
(2016), for preventing expropriation could be,

the Indonesian Government shall ensure that no Relevant Authority expropriates,


compulsorily acquires, nationalises, or confiscates all or any part of the Project (Kakap
PSC), any assets, rights or other interest of the Company, or the interest of any
Investors.

For repatriation of profits, the SPV could include the following clause,

PT Suribian shall have the right to open any type of foreign or local bank accounts and
shall have the right to freely convert an amount in [ ] or any type of foreign currency
into any other currency and transfer any such amount abroad.

More clauses could be added to obtain assurance from the Indonesian government to prevent or
minimise effects coming from Political risks.

Strategic Consortium Structure


By incorporating local business entities into our consortium structure, it is less likely that the
project will be affected by Political risks as compared to Indonesian projects fully owned by
foreigners. It is less likely that the government would undermine the business activities that

24
involves local companies. In PT Suribian, we have Samudera Indonesia as one of our partner
within the consortium and Bank Mandiri within the syndicate of commercial banks (lenders).
Risk: Force Majuere
Some of the Force Majeure risk identified for the Kakap PSC are listed as follows,
Natural disasters, e.g. earthquakes, tsunami, leading to the destruction of oil platforms
War, e.g. recent China and Indonesia confrontation around Natuna islands that may result
in future skirmishes on territorial disputes, leading to stoppage of operations
Civil disturbance, e.g. strike and riots that leads to stoppage of works

Mitigation Measures
Concessions in Offtake Agreement and Loan Agreement
One way the risk of Force Majeure may impact the success of the project is the extraction and
production rate/capacity of the oil and gas resources from the PSC. PT Suribian would be
penalised if we are not able to keep up with the production and delivery, i.e. Liquidated Damages
as stated in the Offtake Agreement. To mitigate this risk, the SPV would negotiate for
concessions, written into the Agreement that states that in the event of Force Majeure, the SPV
will not be penalised for the duration of operations that was affected by the incident.

With Force Majeure taking place, more resources would definitely be needed to recover the
facilities back to state for safe operations. As such, PT Suribian may not have the ability to
service the debt for certain period. To mitigate this risk, the SPV would negotiate with the
lenders that refinancing of loans will be guaranteed, in the event of Force Majeure.

Implementation Agreement
Within an Implementation Agreement, a clause should be added that in the event of Force
Majeure, the Indonesian government will come in to support. The contract shall allow for an
extension of concessionary rights to the land and resources in the event of a force majeure. The
duration of extension shall be the period from the event of force majeure which results in the
cease of operations to the restart of operations. The host government shall also be obliged
provide for concessionary loans of US$200 million in contingency to relieve the financial burden
of the SPV to restart the operations.

Insurance (financed using Catastrophe Bonds)


Given the high risk of a natural catastrophe occurring in the region, it is highly recommended for
PT Suribian to take up a force majeure insurance to cover their losses. Types of losses covered
by the policy include continued debt servicing, loss of income, ongoing fixed costs, spoilage, and
related contingencies. As the insured amount could be substantial, the insurance company may

25
resort to selling Catastrophe Bonds (known as Cat Bonds) to raise funds; diversifying their risk
by selling it as a bond to investors.
Re-Financing
In the instance that LIBOR rates, which function as the base benchmark rate for both tranches of
commercial loan, were to skyrocket to 20-year high levels of 7%, the nominal interest expense
borne by the SPV would catapult to unreasonable heights, after factoring in the interest margin
payable. As such, even if our base projections on future cash flow (CFADS) were to hold true,
the exorbitant interest repayment would drive the projects DSCR into dangerous territories of
less than 1.

In this scenario, PT Suribian has the options to either renegotiate new contract terms with
existing lenders for a longer loan tenure to further spread out loan repayments, or apply for a
rate-and-term refinancing to procure additional funds from other commercial banks to service
outstanding debt and interest repayment.

The option to refinance will be kept as a last resort given that the other measures would have
already helped mitigate LIBOR fluctuations. However, additional risk stemming from
refinancing will arise in a climate of high LIBOR which put PT Suribian in an unfavourable
position; refinancing in such a situation will only cause the project to take on more debt at a
higher cost.

26
The graph above summarizes the effective valuation range of KAKAP PSC in present value
after sensitizing the three principal variables, namely Brent oil prices, 6-Month LIBOR and Cost
escalation rate to a fluctuation range of +/- 10%, +/- 50% and +/- 25% respectively. Evidently,
Oil prices prove to be the most impactful and sensitive risk factor with its wider valuation range
and highly elastic change in valuation with every unit change in Oil price. However, in light of
the sufficiency of mitigation measures established earlier to protect the downside of this
investment, the action to acquire is still recommended. The acquisition bid of USD$ 398 million
proves to be a conservative yet competitive one as any previously identified downside exposure,
as shown on the left side of the maroon divider, has been substantially mitigated while any
probable upside gains (in addition to the 12.53% IRR) as indicated on the right side of the
maroon line are still very well preserved.

27
5. Financing Structure

Project Financing Structure and Contractual Parties


Figure 12 shows the proposed financing structure for the Kakap Production and Sharing
Contract. The key players in project finance are:
the government (Government of Indonesia);
the lenders (Syndicate of Banks and ECA);
the project sponsors (Samudera Indonesia, Royal Dutch Shell, Glenville Petroleum,
British Petroleum and Sembcorp Gas Pte Ltd) who invest in the SPV;
the operators in charge of the operations and maintenance of the oil and gas production
fields and platforms (Glenville Petroleum);
the offtakers for crude oil sales (British Petroleum) and gas sales (Sembcorp Gas Pte Ltd)

Figure 12 Project Financing Structure for Kakap PSC

28
Special Purpose Vehicle (SPV)

Figure 13 Project Structure for Kakap PSC SPV

SPV is an arrangement used to protect a subsidiary of a company from being affected by


financial pressure such as bankruptcy. The SPV is a structured finance tool whose purpose is to
preserve funding, assets, or operations from being affected by the rest of Glenvilles businesses.

The SPV would allow Glenville to isolate the needed funds to assure investors that the
companys assets are duly protected, as are the designated funds for the SPV. Once an SPV is
created, it must be managed and owned separately from the company, because otherwise it
would act like a subsidiary. As an independent entity, an SPV is now responsible for managing
its funds, decisions, and risk capital. However, many SPVs run on auto-mode, which means they
have a pre-punched program, which requires minimal, or no management decisions. They may
even have no actual office; just documents that contain a shareholder agreement, joint venture
contract, or Deed of Trust.

29
Purposes of the SPV
To be used for synthesizing a lease, which is considered an expense in the income
statement rather than a liability on the balance sheet. This is also known as On-
Balance versus Off-Balance SPV, which are the 2 types of SPVs.
To secure a project from possible financial or operational failures of the company
To gain independence from the company in terms of funding, ownership, and
management

Financial Accounting Standards Board (FASB) Guidelines for SPV:


1. At least 3% of the total debt, assets, and equity of a SPV must be owned by an
independent third party.
2. The third party owner of the SPV is independent of the company and has enough
equity investment in the project.
3. The third party owner must have controlling financial interest in the SPV. This means
at least enough to have a vote.
4. The third party owner is not guaranteed by another party.

Pros and Cons of the SPV


The SPVs are a safeguard against bankruptcy and creditors since assets can be transferred
to the SPV and remain virtually untouchable. At the same time, any high-risk project can
use the SPV to protect the mother company from great losses should the project fail.
Thus, the most important advantage of the SPV is protection of funds and assets.

SPVs also make it easier to manage funds. Instead of expanding a business, one can just
create special projects even if only to test the market for new business opportunities. One
can also sidestep certain regulatory requirements that block investment opportunities such
as the case of the Foreign Institutional Investors. Finance management is improved
because Glenville could be more tax efficient through manipulation of financial
statements and the windows of opportunity for companies to choose a more favourable
tax resident for their SPV where assets can be better secured. Finally, SPVs provide the
added advantages of creative accounting and an effective way of cloaking any secret
project that competitors would do anything to know about.

The disadvantages of the SPVs include the cost of setting up the SPV, loss in tax benefits
for the mother company (Glenville), compliance with the rigid FASB rules, lack of
funding options, and the legal obligations of a limited company.

30
Government
The Government of Indonesia is the owner of the four major oil and gas production fields (KF
field, KRA field, KH field and KG field). The government provides the concession for the SPV
to explore, develop and market oil and gas resources in Indonesia.

Lenders
The loans for the project are obtained from two sources:

1. Syndicate of Commercial Banks

Commercial Bank Loan Amount (Percentage)

Development Bank of Singapore (DBS) USD 74.5 million (25%)

Sumitomo Mitsui Banking Corporation (SMBC) USD 59.6 million (20%)

Australia and New Zealand Banking Group (ANZ) USD 59.6 million (20%)

Standard Chartered USD 53.6 million (18%)

Bank Mandiri USD 50.7 million (17%)

Total USD 298 million (100%)

The syndicate of banks comprise of secured creditors, headed by the lead arranger
Development Bank of Singapore (DBS). DBS is approached to be our lead arranger
because, like Glenville, it is incorporated in Singapore and this would streamline the loan
structuring and agreement process due to commonalities in their geographical locale.

Sumitomo Mitsui Banking Corporation (SMBC) is a multinational banking and financial


services company and also one of Japans leading bank. SMBC has been selected because
of its good track record in the Asia Pacific region and also have been involved in several
projects in Indonesia. Australia and New Zealand Banking Group (ANZ) is a New
Zealand owned bank while Standard Chartered is a British owned multinational banking
and financial services company. These two banks have a relatively long standing stable
reputation in Singapore and likewise, have maintained a good track record in the Asia
Pacific region.

31
Bank Mandiri is the largest bank in Indonesia in terms of assets, loans and deposits. Bank
Mandiri has been approached largely due to its knowledge in the Indonesian markets.
Since it is also an Indonesian owned bank, their involvement in the syndicate could
facilitate the concession agreement with the Government of Indonesia.

Lastly, all the above-mentioned chosen banks command respectable rankings in the
International financing review PFI league table.

2. KfW with Hermes as the Export Credit Agency (ECA)

An Export Credit Agency (ECA) is a financial institution that offers financing to


domestic companies for international export operations and other activities. ECAs offer
loans and insurance to such companies to help remove the risk of uncertainty of exporting
to other countries and underwrite political risks and commercial risks of oversea
investments, thus encouraging exportation and international trade. ECA acts as an
intermediary between a nations government and an exporter in order to provide some
type of financing.

The German Development Bank (KfW Entwicklungsbank) will provide the CAPEX loan
that we require for replacement of capital expenditure. The equipment and plants used in
the project will be purchased from Bechtel, a leading oil, gas and chemical company in
Germany. KfW will cover loans and insurance that Bechtel requires for export of
equipment to Indonesia. Bechtels vested interest in the project will ensure the
performance, as well as the operations & maintenance of the equipment be carried out to
its best effect.

A HERMES cover (usually 85% of the loan amount) is an Export Credit Guarantee by
the German Federal Government, and forms an important part of the German foreign
trade policy and protect German companies in the event of non-payment by foreign
debtors. HERMES guarantees enable exporters to cover themselves against economic
risks and political risks and the purpose is for the promotion of exports and helping to
provide for jobs in Germany. Risks covered by the HERMES cover includes political
risks such as bad debt losses due to legislative measures, war and civil commotion, losses
due to inability to convert or transfer sums paid in local currency by the debtor due to
restrictions in the international payment system, inability to fulfil the contract, and loss of
goods due to political circumstances. Also covered is the commercial risks such as
protracted default and bankruptcy of buyer.

32
Indonesia-German Double Taxation Avoidance Agreement
The bilateral economic agreement between Indonesia and Germany eliminates double
taxation of the same income in the two countries. Exporters under the HERMES Cover
will enjoy the benefits of the Double Taxation Avoidance. Exporters of German
companies will be safeguarded against the risks as mentioned, and at the same time be
able to expand their business overseas.

Sponsors
The Sponsors of the project are Samudera Indonesia, Royal Dutch Shell, Glenville Petroleum,
British Petroleum and Sembcorp Gas Pte Ltd.

Samudera and Royal Dutch Shell are companies with vested interest in the oil and gas industry
and this Kakap PSC project of a huge scale and lucrative returns would be of interest to them.
These equity investors will provide capital infusions to the project. The success of this project
can potentially lead to expansion and growth of their respective core businesses.

Glenville Petroleum is a Singapore-based petroleum company investing in this project to


increase it acreage of oil and gas producing fields in the region. Glenville is the largest
shareholder and would double up as the operator of this oil and gas exploration project.

British Petroleum and Sembcorp holds dual roles as offtakers and sponsors as well. As offtakers,
they chose to double up as sponsors because they have a vested interest to keep the project going.

Operators
The Operator for this project is Glenville Petroleum, a Singapore-based petroleum company
investing in this project to increase its acreage of oil and gas producing fields in the region.
Glenville is also the largest shareholder of the SPV for this project.

Offtakers
There are 2 offtakers in this project structure - for crude oil sales (British Petroleum) and gas
sales (Sembcorp Gas Pte Ltd). They are the existing offtakers for the Kakap PSC project and
have been approached to continue their offtaking roles because of their experience and
knowledge in the project.

33
Key Contractual Agreements
The participating contractors in Kakap PSC are:
Contractor Equity Contribution Percentage Ownership

Glenville Petroleum (Glenville) USD 24.5 million 24.50%

Samudera Indonesia USD 20.3 million 20.30%

Royal Dutch Shell (Shell) USD 19.4 million 19.40%

British Petroleum (BP) USD 18.5 million 18.50%

Sembcorp Gas Pte Ltd (SembGas) USD 17.3 million 17.30%

Total USD 100 million 100%

Glenville will spearhead the formation of the SPV before submitting a collective bid for the
Kakap PSC. Glenville, alongside the identified partnering contractors in the table above, has
worked out the ownership distribution structure as such. The percentage ownership shall dictate
the amount of capital each partner has to provide as equity to finance the bid submission as well.

Even though Glenville has the largest ownership in the consortium, it was decided that Glenville
should have less than 25% ownership of the consortium so that the accounts and debts of
Glenvilles involvement in this project will be kept independent from the parent company. The
parent companys balance sheet is thus insulated from any profits or loss arising from the project.

The major contracts and agreements between the partnering contractors of the SPV are further
elaborated on in the following sections.

Shareholders Agreement
As means of financing the project, shares from the project will be sold to all parties in the SPV.
In return, the SPV will pay out dividends based on the parties stake in the project company from
the profit made from the oil and gas sales.

Cash sweep
Cash sweeping gives PT Suribian the option to use excess free cash flows to pay down
outstanding debt rather than distribute it to shareholders. The shareholders will be paid
their dividends in the order as below.

34
Order Items

1 Disburse cash for OPEX and CAPEX based on approved budget

2 Pay royalties and taxes

3 Payment to agents

4 Pay principal repayment + interests

5 Meet any shortfall under the DSRA

6 Disbursement for approved additional CAPEX

7 85% of excess cashflows for Mandatory Prepayment

8 Remaining for permitted Disbursement

Equity Sponsor Support


Establish a contingency fund with pooled capital from all sponsors according to their
ownership proportion. This fund will only be tapped as a last resort in the event of
symptoms such as:
1. Breach of restrictive covenants (DSCR <1.1)
2. DSRA has been depleted

Production Sharing Contract


A production sharing contract is entered into between the Government of Indonesia and the SPV.
This agreement describes the project takeover and provides the grant and terms of the
governmental license for project ownership, operations and exploitation of natural resources.

The contract shall allow for an extension of concessionary rights to the land and resources in the
event of a force majeure. The duration of extension shall be the period from the event of force
majeure which results in the cease of operations to the restart of operations. The host government
shall also be obliged provide for concessionary loans of US$200 million in contingency to
relieve the financial burden of the SPV to restart the operations.

Loan Agreement
The loan agreement between the syndicate of banks and the Kakap PSC consortium is an
underwritten deal, whereby the syndicate of banks will guarantee the entire loan commitment
of 10 years (from 2017 to 2026). Traditionally banks would not prefer such an arrangement
because of the high risk on the loan arrangers to ensure full subscription of the loan amount of
USD 298 million. However, the consortium believes that this is the most optimal loan

35
arrangement to handle the loan amount of such a scale, and to better manage borrowing risks as
well.

This loan agreement with the syndicate of banks is further split into two tranches - Commercial
Loan A and Commercial Loan B. Loan A, with a facility amount of USD 115 million, will be
fully drawn down in year 2016, prior to the acquisition. The interest margin is stipulated at a
variable floating rate of 6 month LIBOR + 3.50% (premium), amortized over the entire loan
tenure of 5 years from 2017 to 2021. Loan B with a facility amount of USD 183 million, will be
fully drawn down in year 2016 as well. The interest margin is stipulated at a variable floating
rate of 6 month LIBOR + 4.75% (premium), amortized over the entire loan tenure of 10 years
from 2017 to 2026. The repayment of loan will commence in year 2017, taking into
considerations the operation period in year 2016 is only three months.

The ECA loan of USD 50 million will be fully drawn down in year 2016 on the date of
Operational Commencement. The interest margin is stipulated at a fixed rate of 6.50%, to be
repaid over the loan tenure of 15 years from 2017 to 2031.

Assets of the Kakap PSC project are to be used as collaterals in return for the loan agreement.
Both agreements are non-recourse loans. Both loans require a minimum Debt Service Coverage
Ratio of 1.1.

Clauses within the loan agreement will provide for mitigation against force majeure risks. In the
event of a force majeure, the SPV has the right to refinance with the syndication of banks at
amicable terms to tide over the crisis when no revenue is generated during the period which is
affected by the event of a force majeure.

In the event the SPV has excess cash, the terms of the debt allows for early repayment at the
borrowers option. This option to use excess cash to periodically repay debt ahead of schedule is
called cash sweep. Essentially, cash sweep enables front loading of as much of the debt
repayment (pre-payment) early in the project so as to reduce or eliminate the risks of loan default
in the future, with respective to detrimental scenarios such as higher LIBOR jacking up interest
repayments. This option makes the disbursement of dividends more stringent. For example,
dividends will be disbursed only if the DSCR exceed 1.2. The excess cash for the first 3 years
will be used for pre-payment of loans to reduce leverage and lower the gearing ratio

When DSCR is below 1, i.e. CFADS< debt service, the DSRA will be tapped to bridge the
shortfall. The debt service reserve account (DSRA) works as an additional security measure for
lenders. It comprises of a deposit equivalent to 12 months of projected debt service obligations,
funded by excess cashflow after all preceding payments have been made.

36
Operations & Maintenance Agreement
The Operations & Maintenance (O&M) Agreement between the SPV and Glennville specifies
the responsibilities of Glenville as the O&M Contractor, the period of operation, the maintenance
and repairs required, and any other fees. Glenville is required to secure the necessary permits to
operate and maintain the fields and platforms. Transportation of crude oil and gas from the fields
to the offtakers will be managed by Glenville as well.

Under this agreement, a performance guarantee is provided by Glenville to sustain extraction and
production of crude oil and gas above a predefined stipulated value of 700,000 barrels/year and
11,770,000,000 cubic feet/year respectively, to ensure the minimum projected revenue stream is
met.

Glenville will be contracted at a fixed price to mitigate the risk of cost escalation in the event of
unexpected increase in cost for operations to maintain its production. However, provisions will
be made for the increase in cost due to inflation and will be capped at 6%.

Service Level Agreements will also be included to bind the service providers such as the
operators and equipment supplier. Under the agreement, the Operator shall be obliged to perform
optimally to produce the quantity of oil as scheduled. The equipment supplier shall also be
responsible to provide a guarantee that the equipment supplied shall function at the agreed
availability rate and shall provide technical support to ensure the functionality.

Crude Oil Sales Agreement


Crude oil produced from Kakap PSC is sold to BP under a long-term Crude Oil Sales
Agreement. The quantity of crude oil, 700,000 barrels/year, will be stipulated in the contract as
the minimum quantity that BP has to purchase.

A take-or-pay clause is to be included to ensure a guarantee on the revenue stream from the
proceeds of oil sales. Under this provision, BP has to unconditionally pay for the quantity of
crude oil as stipulated in the contract whether or not the actual sale of crude oil has taken place.
However, the take-or-pay clause comes with a concession, allowing BP to receive a make-up
quantity for the amount that BP failed to consume which corresponds to the quantity for which a
take-or-pay payment was made.

Crude oil prices will be in accordance to the prices as indicated by Brent Crude. The crude oil
prices will be committed on the day in which the sale and purchase of crude oil is to be made.

37
In the agreement, provisions shall be made to exclude the liability of the Operator and SPV as an
entity to supply to minimum amount of oil required to be sold to BP in the event of a force
majeure that disrupted the operations. No liquidated damages or any losses can be claimed
against the Operator and SPV.

Gas Sales Agreement


The SPV enters into a long-term Gas Sales Agreement with SembGas to purchase gas produced
from Kakap PSC. The quantity of gas, 11,770,000,000 cubic feet/year, will be stipulated in the
contract as the minimum quantity that Sembgas has to purchase.

A take-or-pay clause shall be included to ensure a guarantee on the revenue stream from the
proceeds of gas sales. From this clause, SembGas has to unconditionally pay for the quantity of
gas as stipulated in the contract whether or not the actual sale of gas has taken place. However,
the take-or-pay clause comes with a concession, allowing SembGas to receive a make-up
quantity for the amount that SembGas failed to consume which corresponds to the quantity for
which a take-or-pay payment was made.

The measurement of gas will be converted from per cubic feet into oil per barrel for the purpose
of determining the price of gas using the oil prices. The conversion rate of gas per cubic feet to
per barrel will be 1:6,000. In other words, 6,000 cubic feet of gas is equivalent to 1 barrel oil.
Crude oil prices will be in accordance to the prices as indicated by Brent Crude. The crude oil
prices will be committed on the day in which the sale and purchase of crude oil is to be made.

In the agreement, provisions shall be made to exclude the liability of the Operator and SPV as an
entity to supply to minimum amount of gas required to be sold to SembGas in the event of a
force majeure that disrupted the operations. No liquidated damages or any losses can be claimed
against the Operator and SPV.

Historically, all domestic gas had to be sold to Pertamina under a gas supply agreement.
Pertamina then in turn sold the gas to the end-user (e.g. State Electricity Company (PLN) and
PGN). Prices were fixed for a designated supply for the duration of the contract.

Today, Indonesias principal oil and gas law is Law No. 22/2001 (Oentoeng Suria & Partners,
2011). Under this law, the government now has the power to grant rights to mine which such
power used to be held by Pertamina. Now, individual producers can sell directly to end users
with contract terms and conditions negotiated directly between the producer and the buyer (with
assistance from SKK Migas). There continues however to be government involvement in
steering contracts towards certain domestic buyers rather than the producers preference to
export due to favourable pricing and terms (PWC, 2016).

38
References

Chan, F and Soeriaatmajda, W. (2016). Indonesia passes tax amnesty Bill. The Straits Times.
Retrieved 18 October 2016 from http://www.straitstimes.com/asia/se-asia/indonesia-
passes-tax-amnesty-bill

Deloitte. (2016). Price forecast March 31, 2016 from


https://www2.deloitte.com/content/dam/Deloitte/ca/Documents/resource-evaluation-and-advisory/ca-
en-rea-price-forecast-march-2016.PDF

IE Singapore. (2016). Political Risk Insurance Scheme. Retrieved 11 October 2016 from
http://www.iesingapore.gov.sg/Assistance/Global-Company-Partnership/Access-to-
Financing/Political-Risk-Insurance-Scheme

Insurance Times. (2015). The political risks of doing business in Indonesia. Retrieved 15
October 2016 from http://www.insurancetimes.co.uk/the-political-risks-of-doing-
business-in-indonesia/1415241.article

Knoema (2016). World Bank Commodity Forecast Price Data. Retrieved 16 October 2016 from
https://knoema.com/WBCFPD2015Oct/world-bank-commodity-forecast-price-data-july-2016

Oentoeng Suria & Partners. (2011). Indonesias Oil and Gas Laws A legal introduction.
Attorneys at Law.

Premier Oil. (2016). Indonesia. Retrieved 19 October 2016 from http://www.premier-


oil.com/premieroil/operations/indonesia

PWC. (2016). Oil and gas in Indonesia. Investment and Taxation Guide. 7th edition. Retrieved 21
October 2016 from https://www.pwc.com/id/en/energy-utilities-
mining/assets/May%202016/PwC%20Indonesia-oil-and-gas-guide-2016.pdf

Reuters. (2016). Oil industry welcomes Indonesia's tax reform, but says it's not enough from
http://www.reuters.com/article/us-indonesia-oil-gas-idUSKCN11T0E9

US Energy Information Administration (2016). SHORT-TERM ENERGY AND WINTER


FUELS OUTLOOK from http://www.eia.gov/forecasts/steo/

World Bank. (2016). Implementation Agreement (Example 1). World Bank Group. Retrieved 20
October 2016 from https://ppp.worldbank.org/public-private-
partnership/library/implementation-agreement-example-1

39
Appendix
Appendix A1_ Risk Register with Mitigation Measures
Type of Risks Descriptions Mitigation Descriptions Risk Allocation

Construction & In this case, more of


Completion Risk the asset
enhancement works
(or A&A works)

Suppliers not able to


deliver the equipment
for the A&A works.
Competitive Competitive Tendering will show all Consortium/
Tendering the available suppliers for the A&A Contractors
works. If the winner is not able to
supply, the Consortium or Contractor
can look for the runner up. To
preserve the tendered price by all
suppliers, there must be a clause in
the tender to say how long must the
price stay valid till. The
specifications stated in the contract
must also be generic so that more
suppliers can tender for the CAPEX
works.

To have a clause in the Capital


Improvement Contract to state the
Liquidated Damages suffered due to
Delay in A&A works the delay by the contractor/supplier.

Run Risk Analysis to calculate the


contingency needed for the A&A.
Liquidated Contractors
Damages
(Referring to Deepwater Horizon
Insufficient case)
Contingency
Mismanagement in certain processes
especially the external contractors in
during the O&M phase. Getting
external auditor to audit and check on
Looking at not being works done by these external
able to complete the Risk Analysis contractors. Analysis the entire
extraction of oil and production process to see if there can

40
gas due to exploding be any loopholes. Signing Service Consortium
of PSC - Energy Level Agreement.
Digital
Pre-explosion
risk analysis
and precaution
measures Consortium/
External
Contractors

Technology Risk Equipments not able Service Level Claiming from Suppliers or O&M Suppliers or O&M
to perform up to Agreement / Contractor when equipments are not Contractor
specifications (e.g. Equipment performing up to
pumps) Performance standard/specification.
Agreement or
Product
Warranty

Market (Price and Higher than expected Fixed-Price Contract the Operator at a fixed price Operator
Quantity) & operating cost Contract for to transfer the risk of having higher
Operating Risk escalation rate due to Operator OPEX .
macroeconomic
factors such as
surging inflation rates
- Investopedia

Demand and Price


Risk: Supply glut in
the market- due to the
lack of consensus
within OPEC to Long term Certainty of Cash Flow to cover Debt
curtail overall output Offtake service, OPEX and ROI.
and the surge in shale Agencies/
Agreements
oil extraction will (take-and-pay) Offtakers
hamper any form of with agencies
price recovery, or organisation
resulting in lower with huge
sales generated - facility/infrastru
Energy Digital cture/compound
.

Hedging the
risk of price
fluctuations
with futures
contracts in the
derivatives

41
market.
Take short position in brent oil
futures, to mitigate any form of
1. Long Term downside exposure. Consortium
Contracts
Inability to retain key
personnel in running 2. Establish
the PSC - equates to Proper
higher OPEX - Succession
Energy Digital Plans
3. Penalties and
LD

Provide incentives with long term


contracts to bind key personnel to
projects.
Consortium
Establish succession and handover
plans to ensure smooth handover for
operations.
Failure to ensure smooth operations
will incur penalties and LD.

Output Risk Reduction in Maintenance Formulate a robust maintenance Consortium


production rate contract and schedule to maintain efficiency rate
towards the end of CAPEX at an acceptable operative level.
project (decrease in assessment &
pressure) - Kabupaten forecast
Muara Enim Conduct yearly assessment on rig
performance and construct a CAPEX
forecast for efficiency preservation.
Consortium

Consortium can sue the


Inaccurate estimates Engineer/Analyst for negligence.
by independent
reserve Professional
engineers/analyst - Service
Energy Digital Contract
Independent
Reserve Engineers/
Analyst

42
Financial Risk Forex Risk Defining the Clauses in the long term sales Consortium/
currency agreement of oil and gas should
denomination specify the transaction currency to be Offtakers
of revenue in USD.
streams in
USD.

Interest rate
swap Fixing the interest rate payable to
lenders, albeit at a higher nominal
Interest Risk- rising rate. Consortium /
LIBOR due to global Lenders
economic recovery

Performance of
Insolvency risk of Undertaking / Signing Letters of Performance of
Sponsors and Corporate Undertaking or Guarantees by the
offtakers - Energy Guarantees Parent Companies.
Members of the
Digital Consortium /
Parent Companies
Set up a contingency fund for senior
debt service - DSRA (Debt service
reserve account).

Political Risk Expropriation, or Political Risk (From IES) - PRI is able to cover Consortium/
blocking expatriation Insurance / risks such as expropriation, currency
of profits overseas by Memorandum inconvertibility, political violence, Agencies providing
Indonesian Govt; lack of breach of contract by host the PRI (KFW)
of electricity in Understanding / government and non honouring of
Indonesia - Guarantees and sovereign financial obligation.
Kabupaten Muara assurances from However, up to a certain amount
Enim . May take over host country ($500,000SGD in the case of IES).
the PSC or demand
part of the supply to
Indonesia; reduces ECA loan
the profit forecast counter
because prices is guarantee ECA Loans come with a counter
fixed by PLN. guarantee from the host government
which incentivise them to abide by
Rising Taxes (e.g. their promised commitments; less
Labour, Property and probable to perform acts of
etc) - Energy Digital. expropriation, pre-mature termination
Rising Tax is or any other unprecedented ECA/ Government
probable due to the manoeuvres to undermine the success
environment damages of the project.
during the BP Oil
Spill
Signing a bilateral agreement with
the Government to garner support

43
during the years of operations.
Implementation
Agreement
Having accounts and transactions
taking place overseas so that
Indonesian government have no
control.
Offshore
Account Consortium/
Having local Indonesian company Government
within the Consortium. Less likely
government will undermine business
with local entities

Strategic
Consortium Consortium
Structure

Consortium

Legal Risk Changes in World- Loan SPV can only accept the risk. SPV Consortium
wide Energy Policy - Refinancing, can source for additional funds
Clover Cash Sweep, through loan refinancing, Cash
DSRA Sweep, or from the DSRA when
more money are needed to pay the
policy changes e.g. tax, or machinery
that are more environmental friendly.

Applicable only to personnels


employed or hired by the SPV.
Having stringent checks or external
auditors to ensure compliance.
Anti-corruption
Corruptions management
system Consortium

Environmental Methane and black Service Level Vapor recovery units that reduce Service Provider
Risk carbon, two potent Agreement emissions from the well or tighter
greenhouses gases, (SLA) with valves that prevent fugitive
will likely be emitted Vapour emissions. Fine the Service Provider
in significant amounts Recovery Unit if they are not able to limit emissions
during drilling to a level according to the SLA.

44
Oil spill - BP Case
Establish A well trained, properly resourced
Oversight and adequately funded team should
Committee / be set up to carry out effective and
Independent Oil efficient supervision of oil
Rig Inspectors drilling.This will provide necessary
checks and balances and avoid Consortium
oversights as well as offer
recommendations where necessary.

The scope of work includes:

Develop a risk mapping and identification


framework of risks, of critical barriers,
and of requirements for
barrier performance.
Address communication
barriers and review
technology
Use risk models to evaluate
alternative design and
operational methods
Management of change in
operations (interface
handling, technology,
personnel & process)
Address shortcomings and
gaps in present drilling
operation risk assessment

45
Force Majeure Having Hurricane/ Insurance Purchasing Insurance SPV will get Consortium/
Risk Typhoon/ Storms. payout in the event of Force Majeure.
May affect extraction However, such insurance might not Insurer
operations. be available, or payout will be
limited.

Signing a bilateral agreement that the


Indonesian will step in to help in the
event of Force Majeure e.g. extension
of concessions, concessionary loans
Implementation and etc. Government
Agreement

SPV will not be penalised in the


event of Force Majeure e.g.
Liquidated Damages to the Offtakers
for late delivery, and penalty for late
debt service to the banks. Loan
Agreement to provide for guaranteed
Offtake & Loan loan refinancing in the event of Force
Agreement Majeure.
Offtakers &
Lenders

46
Appendix A2_ Oil and 6-Month LIBOR Model

Oil price model basis

2016 2017 2018 2019 2020 2021 2022-2035

42.28 51.58 55.87 59.12 62.03 64.79 41.65

EIA 2016 EIA Average Average Average Average BP 35 year


average forecast forecasted forecasted forecasted forecasted historical
price price price price average
provided provided provided provided
by by by by
worldbank worldbank worldbank worldbank
and and and and
deloitte deloitte deloitte deloitte
consulting consulting consulting consulting

47

You might also like