You are on page 1of 1

Pq.

per: Bol~on

q=10kPa
A

h =3.5m
F

Stiff glacial clay Activ/


' d
:"J.
P=1149
Centre of
rotation
___3
D
Fig 1 (a). Design cross-section of cantilever Fig 1 (b). Active andpassive pressure Fig 1 (c). Approximate equilibrium free- body

to be placed on the retained fill to simulate traffic, and an over-dig of at least TABLE 2 - Earth pressures calculated at salien( points in Fig 1
0.5m is to be assumed in excavations. No further safety factors are then
Stresses O"v cr'
v crh' O"h
appropriate. The wall must simply be shown to have an equilibrium free- u
body diagram.
kPa =q+ p =O"v- U = K crv' =crh'+u
A 0 10 10 3 3
Example: cantilever wall in stiff glacial clay B 81 224 143 47 128
Design situation
Consider a simple cantilever wall to retain a 3m cutting in glacial clay of F '0 0 0 0 0
soil type C, described above. The cutting might be for a ro(:!d, and the wall
E 78 141 63 265 343
might be of steel sheet-piles or bored cast-in-place concrete, for example.
To conform to the design situation imposed in BS8002, section 3.2.2.2, the Overturning moments are: 34 x 5.5 + 637 x 3.8 = 2608kNrnlm
retained height will be increased to 3.5m and the retained surcharge will be Restoring moments are: 1149 x 2.6 = 2987kNrnlm
10kPa. It will be assumed that the preexisting water table was high, so the
phreatic surfaces in the long term will be taken at the levels of the ground Satisfying global equilibrium
surface . each side of the wall, conforming to 3.2.2.3. There would be a dis- Whereas in previous styles of safety audit the restoring moments should
tinct advantage in permitting drainage through the wall, but this might be have exceeded the overturning moments by some. safety factor, BS8002 has
regarded as requiring specialist geotechnical attention, and the objective already dealt with safety by this juncture. We are now in the middle of a rou-
here is to set out some simple calculations for the non-specialist. tine piece of structural analysis for a wall. It should be in equilibrium, so
Fig l(a) shows the design cross-section. Information given above for soil the overturning moments should exactly balance the restoring moments.
type C can be used to establish the following values: designY = 21kNim3, It is evident that, if 379kNrnlm of extra overturning moment were applied,
design$= 25.7, and so designO = 19.8. Earth pressure coefficients Ka = 0.33 the 11m wall would be in equilibrium. It is marginally too deep for its cur-
and Kp = 4.2 can then be found from the tables of Kerisel & Absi. It remains rent requirements, if the full design soil strengths are to be mobilised. One
to guess the wall depth necessary to support a 3.5m face under these cir- way of controlling the subsequent iteration which the designer may wish to
cumstances, so that this may be iterated until equilibrium is achieved. pursue is to calculate the actual surcharge which would bring the wall into
equilibrium at its current depth. This is easily computed; the force AI should
Global equilibrium: initial trial be increased by 37915.5 =69kNim, so the active pressure should be increased
The approach of Bolton, Powrie & Symons 11 offers a starting point. Their by 69110.2 = 6.8kPa, so an additional surcharge could be carried equal to
Fig 2 shows that a cantilever wall in soil with ylyw = 2, with full height 6.810.33 = 21kPa. The 11m wall can carry a surcharge on the retained soil of
phreatic surfaces, and mobilising the required <1> = 25.7, 81$ = 0.77, needs 31kPa. If desired, the depth could speculatively be .reduced by lm and the
an embedment ratio d/h == 2.2. For h = 3.5m, we getd= 7.7m, so a total wall calculation repeated. Interpolation between equilibrium values of applied sur-
height of 11.2m is indicated. Our soil is heavier, which adds stability, but it charge would then indicate a wall depth of 10.5m which almost exactly
is also surcharged on the active side, which reduces stability; a wall height mobilises the permissible soil strength under an active surcharge of lOkPa.
of ll.Om will therefore be our starting point. Their figure also shows that Once the wall is in moment equilibrium, other forces and stress~resultants
such a wall would pivot about a point 7% ,up from the toe of the wall, can be calculated. Suppose that we accept the current situation of the 11m
which is about 0.8 m. Earth pressures flip over at the pivot from active to wall. Above BE, the new active forces are 740kNim, the passive forces are
passive: see Fig l(b) where the pivot is represented by point B on the 1149kNim, so the toe resistance R = 1149 -740 = 409kNim. This is sup-
retained side and E on the excavated side. Equilibrium will be considered posed to be developed over the bottom 0.8m, if the original assumption
all
to have been sufficiently well proven if the earth pressures above BE are about the pivot point is valid. The net resisting pressure below the pivot BE
shown to be in moment equilibrium about point C, which is at the midpoint is therefore required to be 40910.8 = 511kP.a. To check whether this is
of the 'fixed-earth' zone BO between the pivot and the toe. mobilisable, a simplified approach can be used for this small section near
It is now necessary to calculate earth pre~sures at A, B, E and F. The first the toe. The vertical effective stress at B and at E can be used to find con-
step is to find the pore pressure at D assuming a linear rate of piezometric servative estimates of the mobilisable passive pressure on BD and active
pressure reduction around the wall (BS8002, section 3.3.5.2). In this case, pressure on ED, as shown in Table 3.
The net resisting pressure is therefore at least 770-99 = 671kPa, which
u0 = 9.8 x 11 [1- 3.5118.5] = 87kPa
exceeds .the requirement of 511kPa. The 'fixed-earth' region is well fixed.
Since it is assumed that pore pressures change linearly. we can deduce As with the over-provision of restoring moment, it is. not essential to
mobilise all the available soil strength. In this case, the designer should prob-
u8 = 87 x 10.2 I 11 = 81kPa
.ably be satisfi~d to have a design for a wall in equilibrium in which every
uB =87 x 6.7 I 7.5 =78kPa soil zone is approaching its perruitted degree of mobilisation under a slight-
The earth pressures calculated in Table 2 lead to the pressure diagram in ly more onerous design situation than that set by the Code.
Fig l(b). This leads to the calculation of active forces AI= 34kNim andA2
= 637kNim and passive force P = 1149kNim, with magnitudes derived Calculating bending moments
from areas on the pressure diagram, and lines of action passing through the Once a free-body diagram has been.produced, bending moments can be cal-
centroids of those areas, as shown in Fig l(c). They are to be considered to culated, The 11m-deep wall, carrying 31kPa of surcharge on its retained soil,
be held in equilibrium by a fixing forceR acting at C. Fig l(c) is a trial equi- has a mobilised total active pressure of lOkPa at the retained surface, ris-
librium free-body diagram constructed on the assumption that the wall ing at 12.25kPalm, and a mobilised total passive pressure rising at
should be 11m deep to resist design earth pressures. The first step in check- 51.2kPa/m below the excavation. Net pressure, shear force and bending
ing global equilibrium is to take moments for all forces about C. moment diagrams are easily drawn. Shear force is found to pass through

368 The Structural Engineer/Volume 74/No 21/5 November 1996

You might also like