Project :

Location :
Owner :

MASTER
FORMAT DESCRIPTION OF ITEM U/I U/P QTY SUB T/P
NO
DIV-010 SECONDARY WALL
2X3X8' C STUDS PCS. 185.00 16.00 2,960.00
12MMX4'X8' GYPSUM BOARD PCS. 330.00 6.00 1,980.00
GYPSUM BLACK SCREW PCS. 0.65 200.00 130.00
LATEX SEMI GLOSS GALS. 550.00 2.00 1,100.00
6,170.00

DIV-020 PLATFORM & FLOORING


1.2MM THK. X 2X3X20' C FLOOR JOISTS PCS. 1,030.00 8.00 8,240.00
20MM THK. X4'X8' PLYWOOD PCS. 800.00 4.00 3,200.00
BLACK SCREW PCS. 0.65 150.00 97.50
WOOD LAMINATE FLOORING SQM 850.00 9.00 7,650.00
19,187.50

DIV-030 REFLECTED CEILING


2X2X20' TUBULAR PCS. 1,030.00 5.00 5,150.00
1X2X20' TUBULAR JOISTS PCS. 500.00 4.00 2,000.00
12MM THK.. X4'X8' FICEM BOARD STO. FLRG. PCS. 565.00 4.00 2,260.00
BLACK SCREW PCS. 0.65 150.00 97.50
3MM TH. X4'X8'FICEM CEILING PCS. 250.00 4.00 1,000.00
BLIND RIVETS PCS. 0.65 300.00 195.00
10,702.50
DIV-050 METALS
Steel Roof Framing System Sq.m 600.00 93.00 55,800.00
Cee Floor joists pcs 650.00 24.00 15,600.00
Stair & Balcony Railing lin.m. 1,200.00 13.00 15,600.00
87,000.00
DIV-060 WOOD & PLASTICS
lumber, tangile, 1" x 10 x 4' ceiling vent PC 400.00 6.00 2,400.00
lumber, 2" x 2" BF 25.00 320.00 8,000.00
nail, finishing, 1" KG 45.00 2.00 90.00
nails, C.W., finishing 2" KG 45.00 5.00 225.00
plyboard, 3/4" x 4' x 8' SHT 865.00 12.00 10,380.00
hardiflex, 1/8" x 4' x 8' PC 160.00 22.00 3,520.00
wood glue, stikwell 1 kg can CN 95.00 1.00 95.00
Lentrek soil treatment LT 1,000.00 1.00 1,000.00
Solignum wood preservative (4-liter) CN 633.00 1.00 633.00

wire mesh screen, '1/8" x 1/8" x W4' (circulation vents) MT 60.00 3.00 180.00
26,523.00

DIV-070 THERMAL & MOISTURE PROTECTION


fascia board, Hardisenepa, 1" x 12" x 12' PC 529.00 6.00 3,174.00
insulation, polyethylene with aluminum backing 2 sides,
6mm x 1m x 50m roll RO 2,300.00 1.00 2,300.00

Plain g.i. sheet, # 26 x 4' x 8' (fascia & firewall flashing) PC 288.00 4.00 1,152.00
plain stainless stl sht. gutter, rectangular shape, # 26 x
L2.4m PC 380.00 10.00 3,800.00
steel tile, Tilespan 0.4mm x 1220mm x L.S. PC 260.00 94.00 24,440.00

375351581.xls Page 1 of 106


Project :
Location :
Owner :

MASTER
FORMAT DESCRIPTION OF ITEM U/I U/P QTY SUB T/P
NO
steel tile Spanish type ridge cap, Tilespan 0.8mm x 1220mm
x 1.21m PC 136.00 12.00 1,632.00
aluminum rivets PC 0.60 200.00 120.00
g.i. wire ball strainer, # 16 PC 11.15 6.00 66.90
S- type screw PC 1.15 250.00 287.50
36,972.40
DIV-080 DOORS & WINDOWS
Wood Panel Type Doors Std. size SE 3,000.00 2.00 6,000.00
Wood Flush Type Doors Std. size SE 1,800.00 3.00 5,400.00
D-7 PVC flush door SE 1,500.00 2.00 3,000.00
hinges, loose pin, (Taiwan) brass, 3" x 3" PCS 27.00 15.00 405.00
lockset, Yale door knob , keyed on one side, US5 brass
#5237 SE 500.00 7.00 3,500.00
W-1 Steel casement window, French type SF 125.00 114.00 14,250.00
32,555.00
DIV-090 FINISHES
ceramic tiles, Mariwasa vitrified, 12.5mm x 200mm x 200mm PC 16.00 240.00 3,840.00
Painting lot 20,000.00 1.00 20,000.00
23,840.00
DIV-100 SPECIALTIES
kitchen sink, double basin, stainless steel SE 3,500.00 1.00 3,500.00
3,500.00

DIV-150 MECHANICAL/SANITARY
A. HOUSE DRAIN
75mm cleanout pcs. 22.00 1.00 22.00
75mm long sweep elbow pcs. 22.00 3.00 66.00
75mm x 50mm Tee pcs. 22.00 2.00 44.00
75mm x 75mm Tee-Wye pcs. 22.00 2.00 44.00
75mm P-trap pcs. 22.00 1.00 22.00
75mm x 3000mm Pvc soil pipe pcs. 300.00 1.00 300.00
75mm floor drain pcs. 50.00 1.00 50.00
B. SOIL STACK
75MM X 3000MM Pvc soil pipe pcs. 300.00 2.00 600.00
75mm x 1/8bend elbow pcs. 22.00 2.00 44.00
75mm x 75mm Tee pcs. 22.00 2.00 44.00
75mm cleanout pcs. 22.00 1.00 22.00
75mm x 50mm Tee-Wye pcs. 22.00 2.00 44.00
75mm x 50mm cross-tee pcs. 22.00 1.00 22.00
75mm floor drain pcs. 22.00 1.00 22.00
C. WASTE & VENT PIPE
50mm x 3000mm Pvc pipe pcs. 200.00 4.00 800.00
50mm x 50mm elbpw pcs. 22.00 2.00 44.00

375351581.xls Page 2 of 106


Project :
Location :
Owner :

MASTER
FORMAT DESCRIPTION OF ITEM U/I U/P QTY SUB T/P
NO
50mm x 50mm Tee pcs. 22.00 3.00 66.00
D. WATER SUPPLY
20mm x 3000mm Pvc pipe pcs. 45.00 2.00 90.00
20mm tee pcs. 8.00 1.00 8.00
20mm elbow pcs. 8.00 1.00 8.00
20mm x 12mm reducer bushing pcs. 8.00 2.00 16.00
12mm tee pcs. 8.00 4.00 32.00
12mm plain elbow pcs. 8.00 2.00 16.00
12mm elbow one face threaded pcs. 8.00 6.00 48.00
12mm shower control valve pcs. 120.00 2.00 240.00
12mm shower heads pcs. 150.00 2.00 300.00
12mm faucet pcs. 45.00 2.00 90.00
Teflon tape rolls 10.00 4.00 40.00
Solvent cement 220gms/can can 45.00 1.00 45.00
E. FIXTURES & ACCESSORIES
Water closet with tank and accessories sets 2,200.00 2.00 4,400.00
10mm water supply control valve pcs. 35.00 2.00 70.00
12mm x 10mm reducer bushing pcs. 8.00 2.00 16.00
10mm x 50mm nipple pcs. 8.00 2.00 16.00
plastic water supply hose pcs. 25.00 2.00 50.00
lavatory with P-trap, faucet and accessories sets 1,500.00 2.00 3,000.00
10mm water supply control valve pcs. 35.00 2.00 70.00
10mm water supply hose pcs. 25.00 2.00 50.00
soap holder pcs. 100.00 2.00 200.00
paper holder pcs. 100.00 2.00 200.00
towel bar pcs. 200.00 4.00 800.00
100mm x 100mm floor drain pcs. 45.00 2.00 90.00
g.i. ball valve, 12mm dia PC 250.00 4.00 1,000.00
g.i. hose bibb, 12mm dia PC 70.00 2.00 140.00
13,291.00
DIV-160 ELECTRICAL
circuit breaker, Class CTL branch, Westinghouse/ GE, 40A
220V PR 115.00 1.00 115.00
circuit breaker, Class CTL main, Westinghouse/ GE, 20A
220V PR 220.00 5.00 1,100.00
circuit breaker, Class CTL main, Westinghouse/ GE, 15A
220V PR 2.00 2.00 4.00
conductor, 'copper AWG, Phelp Dodge (#12) Thhn
stranded (power) MT 5.33 112.00 596.96
conductor, copper AWG, Phelp Dodge (#14) Thhn solid
(lighting) MT 5.33 90.00 479.70

conductor, copper AWG, Phelp Dodge (#10) Thhn stranded MT 8.95 10.00 89.50

375351581.xls Page 3 of 106


Project :
Location :
Owner :

MASTER
FORMAT DESCRIPTION OF ITEM U/I U/P QTY SUB T/P
NO

conductor, copper AWG, Phelp Dodge (#8) Thhn stranded MT 12.57 10.00 125.70

conductor, copper AWG, Phelps Dodge (#6) Thhn stranded MT 40.00 30.00 1,200.00
electrical tape, 20-m RO 20.00 5.00 100.00
fixture: bulb receptacle, porcelain, 4" x 4" PC 35.00 18.00 630.00
panel box, 'Lighting/power main lug, Ever/NEMA 8 - 1"
spaces (8max) EA 350.00 1.00 350.00
pipe, PVC moldplex, 20mm dia x 50m- roll MT 10.75 100.00 1,075.00
pipe, RSC conduit, 1" dia (25mm) x 3m PC 340.00 5.00 1,700.00
pipe, RSC entrance cap, 1" dia (25mm) PC 75.00 1.00 75.00
pipe, RSC long sweep elbow, 1" dia (25mm) PC 125.00 1.00 125.00
plate, 1-device space, telephone, Toshiba PC 65.00 2.00 130.00
plate, 1-device space, Toshiba PC 65.00 2.00 130.00
plate, 2-devices space, Toshiba PC 65.00 7.00 455.00
plate, 3-devices space, Toshiba PC 65.00 1.00 65.00
conveniece outlet, grounding type 10A 250V, Toshiba
DG3951 PC 73.00 14.00 1,022.00
outlet, tandem type (range), 40A 250V, with plate,Toshiba
DC2583 PC 260.00 1.00 260.00
receptacle, weatherproofed, 10A 250V, Eagle PC 65.00 1.00 65.00
telephone modular wall flush jack with plate, TEC SE 66.25 2.00 132.50
telephone wire, Paciflex jacketed 22/3C or AT&T 4C/24 MT 9.33 20.00 186.60
telephone wiring block (entrance bridge) SE 392.00 1.00 392.00
telephone, outdoor wiring box, hinged door, 4-terminal SE 392.00 1.00 392.00
box, junction utility, rectangular flush mounted pvc, Neltex
orange, 2" x 4" *** PC 15.00 35.00 525.00
box, 'junction, octagonal flush mounted pvc, Neltex orange,
4" x 4" PC 15.00 14.00 210.00
11,730.96

SUB-TOTAL
DIVISION SUMMARY
AMOUNT
DIV-020 SITE WORK 6,170.00
DIV-030 CONCRETE 19,187.50
DIV-040 MASONRY 10,702.50
DIV-050 METALS 87,000.00
DIV-060 WOOD & PLASTICS 26,523.00
DIV-070 THERMAL & MOISTURE PROTECTION 36,972.40
DIV-080 DOORS & WINDOWS 32,555.00
DIV-090 FINISHES 23,840.00
DIV-100 SPECIALTIES 3,500.00
DIV-150 MECHANICAL/SANITARY 13,291.00
DIV-160 ELECTRICAL 11,730.96
TOTAL DIRECT COST OF MATERIALS 271,472.36
TOTAL DIRECT COST OF LABOR 25% OF MATERIALS 67,868.09
TOTAL DIRECT COST OF LABOR & MATERIALS 339,340.45

375351581.xls Page 4 of 106


Project :
Location :
Owner :

MASTER
FORMAT DESCRIPTION OF ITEM U/I U/P QTY SUB T/P
NO

Prepared by: Conforme:

FEDERICO "BOB" D. DAVID EDGARDO M. BONDOC


A R C H I T E C T O W N E R

375351581.xls Page 5 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR EQUIPMENT
OUTPUT HOURS COST COST COST
DIV-010 GENERAL REQUIREMENTS 0 0.00 0.00 0.00
010 Overhead & Miscellaneous Data 0 0.00 0.00 0.00
010-000 Overhead 0 0.00 0.00 0.00
0200 INSURANCE, All risk type 0 Job 1.00 0.00 0.00 0.00
0600 Public Liability 0 Job 1.00 0.00 0.00 0.00
0010 PERMITS 0 Job 1.00 0.00 0.00 0.00
013 Submittals 0 0.00 0.00 0.00
013-300 Survey Data 0 0.00 0.00 0.00
1200 Crew for building layout, 3 man crew A-7 1 3 Day 1.00 0.00 2,887.50 0.00
014 Quality Control 0 0.00 0.00 0.00
014-100 Testing Services 0 0.00 0.00 0.00
1800 TESTING, Compressive strength, cylinders, delivered to lab 0 Ea. 5.00 0.00 770.00 0.00
015 Construction Facilities & Temporary Controls 0 0.00 0.00 0.00
015-100 Temporary Utilities 0 0.00 0.00 0.00
0350 Lighting, incl. service lamps, wiring & outlets 1-Elec 34 0.05875 CSF Flr 2.00 9.39 24.26 0.00
0400 Power for temporary lighting only, per month, minimum per month 0 CSF Flr 2.00 0.00 0.00 0.00
015-250 Construction Aids 0 0.00 0.00 0.00
0014 STEEL SCAFFOLDING, Rent, 1 use per mo., no plank 0 0.00 0.00 0.00
0090 Building exterior 3 Carp 16.8 15.897625 CSF 89.00 2,227.23 5,739.39 0.00
0460 Building interior walls, (area) up to 16' high 3 Carp 22.7 2.774625 CSF 21.00 505.31 990.41 0.00
0800 Building interior floor area, up to 30' high 3 Carp 90 0.9345 CCF 28.00 210.21 336.88 0.00
015-400 Security 0 0.00 0.00 0.00
0010 WATCHMAN Service, monthly basis, uniformed man 0 Hr. 1.00 0.00 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 6 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
016 Material & Equipment 0 0.00 0.00 0.00
016-400 Equipment Rental 0 0.00 0.00 0.00
0010 CONCRETE EQUIPMENT RENTAL without operators 0 0.00 0.00 0.00
1300 Finisher, concrete floor, gas, manual, 3 blade, 36" trowel 4.75 Ea. 1.00 1.44 102.99 308.00
1800 Mixer, powered, mortar & concrete, gas 4.825 Ea. 1.00 1.83 99.14 298.38
2120 Pump, concrete, truck mounted, 4" line, 80' boom 67.825 Ea. 1.00 17.71 1,501.50 4,514.13
2700 Vibrators, concrete, Gas engine, 5H.P. 1.40625 Ea. 1.00 0.54 28.88 86.63
0010 EARTHWORK EQUIPMENT RENTAL without operators 0 0.00 0.00 0.00
1300 Vibratory plate compactor, gas, 24" plate, 5000 lb. blow 5.65 Ea. 1.00 3.18 102.99 308.00
0010 GENERAL EQUIPMENT RENTAL 0 0.00 0.00 0.00
7800 Welding Machine, electric, 300 amp 17.175 Ea. 3.00 10.68 297.41 895.13
8100 Wheelbarrow, any size 2.05 Ea. 4.00 0.00 52.75 157.85

PREPARED BY: ARCH. FEDERICO D. DAVID Page 7 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
017 Contract Closeout 0 0.00 0.00 0.00
017-100 Final Cleaning 0 0.00 0.00 0.00
0011 CLEANING UP After job completion 0 Project 1.00 0.00 0.00 0.00
0100 Cleanup of floor area, Final A-5 11.5 2.80135 MSF 14.32 47.41 799.41 91.79

PREPARED BY: ARCH. FEDERICO D. DAVID Page 8 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
022 Earthwork 0 0.00 0.00 0.00
022-200 Excavation/Backfill/Compact 0 0.00 0.00 0.00
0010 BACKFILL by hand, no compaction, light soil 1 Clab 14 23.55375 C.Y. 330.00 0.00 6,733.65 0.00
0300 COMPACTION in 6" layers, hand tamp 1 Clab 20.6 5.723 C.Y. 118.00 0.00 1,635.48 0.00
0600 COMPACTION in 6" layers, Vibrating plate A-1 60 1.96175 C.Y. 118.00 0.00 561.06 222.61
0010 EXCAVATING, STRUCTURAL Hand, pits to 6' deep, sandy soil 1 Clab 8 25.25 C.Y. 202.00 0.00 7,213.17 0.00
1400 EXCAVATING, TRENCH or continuous footing, common earth 0 0.00 0.00 0.00
By hand with pick & shovel to 6' deep, light soil 1 Clab 8 16 C.Y. 128.00 0.00 4,570.72 0.00
022-800 Soil Treatment 0 0.00 0.00 0.00
0020 TERMITE PRETREATMENT, Slab & Walls, residential 1 Skwk 1508 4.030625 SF Flr. 6,449.00 1,489.72 1,613.86 3,103.58
0400 Insecticides for termite control 1 Skwk 14.2 0.14075 Gal. 2.00 36.58 52.36 0.00
025 Paving & Surfacing 0 0.00 0.00 0.00
025-100 Walk/Road/Parking Paving 0 0.00 0.00 0.00
0310 SIDEWALKS, DRIVEWAYS & PARKING, concrete 3,000psi, 0 0.00 0.00 0.00
cast in place with 6 x 6 - W1.4 x W1.4 mesh, broomed finish, 0 0.00 0.00 0.00
no base, 4" thick B-24 600 8.02 S.F. 1,604.00 2,840.68 2,686.30 0.00
025-150 Unit Pavers 0 0.00 0.00 0.00
1500 PAVING BLOCKS on 4" thick sand bed laid flat, 4.5 per S.F. D-1 110 37.645625 S.F. 2,077.00 10,275.44 12,474.46 0.00
025-800 Pavement Marking 0 0.00 0.00 0.00
0010 PAINTING LINES On pavement, reflectorized white, 4" wide B-78 20000 0.033 L.F. 132.00 12.71 12.71 5.08
026 Piped Utilities 0 0.00 0.00 0.00
026-010 Piped Utilities 0 0.00 0.00 0.00
0200 BEDDING For pipe and conduits, not incl. compaction, sand B-6 150 0.14 C.Y. 7.00 46.49 43.25 18.06
0500 Compacting bedding in trench A-1 90 0.02225 C.Y. 2.00 0.00 6.35 2.50
0200 EXCAVATION & BACKFILL hand excavate & trim for pipe 8" dia. 1 Clab 155 2.08 L.F. 320.00 0.00 591.36 0.00
027 Sewerage & Drainage 0 0.00 0.00 0.00
027-100 Subdrainage System 0 0.00 0.00 0.00
1020 PIPING, DRAINAGE & SEWAGE, CONCRETE, non- reinforced pipe, 0 0.00 0.00 0.00
Extra strength, T&G joints, 8" diameter B-21 200 1.8725 L.F. 107.00 669.42 624.10 115.35
027-400 Septic Systems 0 0.00 0.00 0.00
0100 SEPTIC TANKS Not incl. excav. Or piping, precast, 2,000 gallon B-21 5 1.4 Ea. 2.00 3,118.50 465.85 86.63
2200 Excavation for septic tank, 3/4 C.Y. backhoe B-12F 145 0.275 C.Y. 20.00 0.00 95.87 120.51
028 Site Improvements 0 0.00 0.00 0.00
028-100 Irrigation Systems 0 0.00 0.00 0.00
0800 SPRINKLER IRRIGATION SYSTEM for lawns, residential system, 0 0.00 0.00 0.00
custom, 1" diameter supply B-20 2619 4.33125 S.F. 3,850.00 1,630.48 1,408.14 0.00
028-300 Fences & Gates 0 0.00 0.00 0.00
1400 Gate for 6' High fence, 1-5/8" frame, 3' wide, galvanized steel B-80 10 0.4 Ea. 1.00 122.24 125.13 81.81
1401 Gate for 6' High fence, 1-5/8" frame, 5' wide, galvanized steel B-81 17 2.7 Ea. 4.00 816.20 831.60 546.70
0600 Fence Grill,Open rail, rustic, 3 rails, 3' high B-1 160 1.425 L.F. 76.00 437.44 421.34 0.00
029 Landscaping 0 0.00 0.00 0.00
(see sub-con details) 0 0.00 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 9 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
DIV-030 CONCRETE 0 0.00 0.00 0.00
031 Concrete Formwork 0 0.00 0.00 0.00
031-100 Struct C.I.P. Formwork 0 0.00 0.00 0.00
0650 FORMS IN PLACE, BEAMS & GIRDERS, 12" wide, 4 use C-2 310 97.61125 SFCA 5,038.00 7,370.59 34,331.45 1,066.80
6150 FORMS IN PLACE, COLUMNS 16" X 16" plywood, 4 use C-1 235 63.665 SFCA 3,745.00 4,109.20 21,771.56 720.91
1150 FORMS IN PLACE, ELEVATED SLABS, flat plate to 15' high, 4 use C-2 560 22.446 S.F. 2,088.00 2,451.83 7,878.02 241.16
0150 FORMS IN PLACE, GRADE BEAM, 4 use C-2 605 31.8765 SFCA 3,228.00 2,982.67 11,309.30 310.70
1050 SHORES, Erect & strip, by hand, Vertical members to 13' high 2 Carp 50 5.76 Ea. 144.00 0.00 2,065.14 0.00
0010 WATERSTOP, PVC 1-1/2" diameter 1 Carp 155 0.6955 L.F. 107.00 273.95 249.23 0.00
032 Concrete Reinforcement 0 0.00 0.00 0.00
032-100 Reinforcing Steel 0 0.00 0.00 0.00
0102 REINFORCING IN PLACE, Beams & Girders, #3 to #7 4 Rodm 3200 13.385 Lb. 10,708.00 5,153.23 5,359.35 0.00
0202 REINFORCING IN PLACE, Columns, #3 to #7 4 Rodm 3000 12.31725 Lb. 8,958.00 4,311.04 4,828.36 0.00
0402 REINFORCING IN PLACE, Elevated Slabs, #4 to #7 4 Rodm 5800 6.24375 Lb. 8,325.00 4,166.66 2,243.59 0.00
0502 REINFORCING IN PLACE, Footings, #4 to #7 4 Rodm 4200 11.004 Lb. 11,004.00 4,872.02 4,236.54 0.00
0602 REINFORCING IN PLACE, Slab on grade, #3 to #7 4 Rodm 4200 0.684 Lb. 684.00 329.18 263.34 0.00
033 Cast-In-Place Concrete 0 0.00 0.00 0.00
033-100 Structural Concrete 0 0.00 0.00 0.00
0150 CONCRETE, READY MIX Regular weight, 3000 psi 0 C.Y. 245.00 22,638.00 0.00 0.00
6800 CONCRETE IN PLACE Incl. forms & reinforcing steel, 0 0.00 0.00 0.00
Stairs, Free standing C-15 120 5.55 LF Nose 74.00 712.25 1,894.59 62.68
7000 CONCRETE IN PLACE Incl. forms & reinforcing steel, 0 0.00 0.00 0.00
Stair landings, free standing C-15 285 3.4155 S.F. 108.00 436.59 1,164.24 39.50
0050 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Beams & girders, Roof beams, elevated, pumped C-20 40 9.8 C.Y. 49.00 0.00 3,018.40 1,433.74
0400 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Columns, square or round, pumped C-20 45 7.4655 C.Y. 42.00 0.00 2,304.23 1,091.48
1400 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Elevated slabs, less than 6" thick, pumped C-20 110 2.7645 C.Y. 38.00 0.00 852.20 402.33
1900 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Footings, continuous, shallow, direct chute C-6 120 0 C.Y. 0.00 0.00 0.00 0.00
2400 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Footings, spread, under 1 C.Y., direct chute C-6 55 5.565375 C.Y. 51.00 0.00 1,683.70 115.85
3200 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Footing Tie Beams & Grade beams, direct chute C-6 150 2.52 C.Y. 63.00 0.00 764.03 52.15
4300 PLACING CONCRETE and vibrating, incl. labor & equipment 0 0.00 0.00 0.00
Slab on grade, 4" direct chute C-6 110 4.3055 C.Y. 79.00 0.00 1,300.24 89.72
033-450 Concrete Finishing 0 0.00 0.00 0.00
0200 Steel trowel finish, for resilient tiles C-9 625 13.882375 S.F. 8,543.00 0.00 4,933.58 986.72
0950 Cement topping, laid after, 1:1:1-1/2 mix, 2" thick C-10 500 51.258 S.F. 8,543.00 8,387.09 16,938.63 2,466.79
034 Precast Concrete 0 0.00 0.00 0.00
034-500 Architectural Precast 0 0.00 0.00 0.00
0010 WALL MOLDINGS, Fiberglass reinforced cement D-1 175 22.659 L.F. 1,992.00 18,022.62 7,515.82 0.00
034-800 Precast Specialties 0 0.00 0.00 0.00
1050 LINTELS, Precast concrete, 6" wide, 8" high, stock units to 12' long D-4 190 56.07 L.F. 2,670.00 45,229.80 18,348.91 3,700.62

PREPARED BY: ARCH. FEDERICO D. DAVID Page 10 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-040 MASONRY 0 0.00 0.00 0.00
041 Mortar & Masonry Accessories 0 0.00 0.00 0.00
041-000 Mortar 0 0.00 0.00 0.00
0010 CEMENT 40 kg. bag 0 Bag 1,070.00 21,730.36 0.00 0.00
042 Unit Masonry 0 0.00 0.00 0.00
042-200 Concrete Unit Masonry 0 0.00 0.00 0.00
4100 CONCRETE HOLLOW BLOCKS, 4" thick, tooled joints D-8 430 53.289 S.F. 4,584.00 7,412.33 18,001.37 0.00
4150 CONCRETE HOLLOW BLOCKS, 6" thick, tooled joints D-8 400 78.4125 S.F. 6,273.00 12,800.06 26,566.16 0.00
044 Stone 0 0.00 0.00 0.00
044-550 Marble 0 0.00 0.00 0.00
2510 Flooring, polished tiles, 12" x 12" x 3/8" thick, Thin set, average D-11 0 9.2115 S.F. 276.00 4,064.45 3,267.50 0.00
3550 Thresholds, 3' long, 7/8" thick, 5" wide, Beveled D-12 24 0.99975 Ea. 6.00 160.55 340.73 0.00
044-650 Granite 0 0.00 0.00 0.00
0220 GRANITE Cut to size, polished face, 3/4" thick, counter top D-10 130 32.3785 S.F. 841.00 27,197.94 10,523.01 5,488.16
044-750 Slate 0 0.00 0.00 0.00
3100 SLATE Stair landings, 1" thick, clear D-1 65 1.0455 S.F. 34.00 647.96 346.89 0.00
3600 SLATE Stair treads, sand finish, 1" thick x 12" wide, 3 L.F. to 6 L.F. D-10 120 3.08025 L.F. 74.00 2,222.22 1,068.38 524.22

PREPARED BY: ARCH. FEDERICO D. DAVID Page 11 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-050 METALS 0 0.00 0.00 0.00
050 Metal Materials, Coatings & Fastenings 0 0.00 0.00 0.00
051-200 Structural Steel 0 0.00 0.00 0.00
1300 STRUCTURAL STEEL ROOF FRAMING, 1 storey, complete system E-5 12.9 7.7525 Ton 10.00 18,768.75 3,080.00 1,694.00
1600 STRUCTURAL STEEL ROOF FRAMING, 2 storey, complete system E-5 10.6 11.3205 Ton 12.00 26,565.00 4,481.40 2,471.70
055 Metal Fabrications 0 0.00 0.00 0.00
055-200 Handrails & Railings 0 0.00 0.00 0.00
0780 RAILING, PIPE Stainless steel, 3 Rail, 1-1/2" diameter, Mirror finish E-4 120 3.13725 L.F. 94.00 12,485.55 1,275.70 110.38
0400 RAILING, ORNAMENTAL, Hand forged wrought iron 1-Sswk 12 7.6705 L.F. 92.00 13,282.50 3,072.69 0.00
055-400 Castings 0 0.00 0.00 0.00
0100 CONSTRUCTION CASTINGS Manhole covers 16" x 16", cast iron E-4 46 2.436 Ea. 28.00 3,234.00 994.46 85.70

PREPARED BY: ARCH. FEDERICO D. DAVID Page 12 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-060 WOOD & PLASTICS 0 0.00 0.00 0.00
060 Fasteners & Adhesives 0 0.00 0.00 0.00
060-500 Fasteners & Adhesives 0 0.00 0.00 0.00
0700 NAILS Common, 3d to 60d, plain, Galvanized, material only 0 Lb. 1,000.00 1,732.50 0.00 0.00
2000 NAILS Finish nails, 4d to 10d, plain, Galvanized, material only 0 Lb. 100.00 173.25 0.00 0.00
2700 NAILS Concrete nails, hardened steel, 3/4" to 3" long, plain, Galvanized 0 Lb. 100.00 221.38 0.00 0.00
061 Rough Carpentry 0 0.00 0.00 0.00
061-100 Wood Framing 0 0.00 0.00 0.00
6002 FRAMING, CEILINGS Suspended, 2" x 3" F-2 1000 0 L.F. 0.00 0.00 0.00 0.00
6082 FRAMING, ROOFS Fascia boards, 2" x 10" F-2 180 6.675 L.F. 600.00 1,051.05 2,402.40 103.95
0602 GROUNDS for casework, 1" x 1-1/2" wood strips, on masonry for plaster 1 Carp 225 2.25 L.F. 500.00 105.88 1,029.88 0.00
061-150 Sheathing 0 0.00 0.00 0.00
0102 SHEATHING Plywood on roof, 1/2" thick F-2 1400 6.070625 S.F. 4,415.00 3,059.60 2,294.70 84.99
061-280 Mineral Fiber Cement Panel 0 0.00 0.00 0.00
2100 MINERAL FIBER CEMENT PANEL Hardiflex, incl.panels, fasteners, 0 0.00 0.00 0.00
accessories, trim & sealants, 1/4" thick, flat sheets G-3 1020 30.938 S.F. 7,984.00 87,604.44 10,912.13 307.38
062 Finish Carpentry 0 0.00 0.00 0.00
062-200 Millworks Moldings 0 0.00 0.00 0.00
0550 MOLDINGS, BASE Baseboard, Wood, 1" x 4" 1 Carp 200 9.96 L.F. 1,992.00 3,067.68 3,566.18 0.00
0110 MOLDINGS, CASINGS Wood, 1" x 3-1/2" 1 Carp 220 5.5035 L.F. 1,223.00 3,201.81 2,001.13 0.00
1300 MOLDINGS, CEILINGS Wood, 1" x 3" 1 Carp 300 6.723 L.F. 1,992.00 2,799.26 2,377.45 0.00
3170 MOLDINGS, WINDOW & DOOR Door trim set, 1 head 2 sides, 4-1/2"wide 1 Carp 5.3 6.224625 Opng. 33.00 2,541.00 2,255.14 0.00
228-5950 MOLDINGS, WINDOW & DOOR Window trim sets,incl. casings, 0 0.00 0.00 0.00
header, stops, stool & apron, 2-1/2" wide, average 1 Carp 10 4.2 Opng. 42.00 1,536.15 1,511.90 0.00
062-300 Shelving 0 0.00 0.00 0.00
0700 SHELVING Plywood, 3/4" thick with lumber edge, 24" wide F-1 70 1.539 L.F. 108.00 426.20 555.09 24.95
064 Architectural Woodwork 0 0.00 0.00 0.00
064-100 Custom Casework 0 0.00 0.00 0.00
0840 CABINETS Kitchen base cabinets, hardwoodn not incl. counter top 0 0.00 0.00 0.00
24" deep, 35" high, prefinished, one top drawer, one door below, 18" wide 2 Carp 23.3 0.687 Ea. 8.00 1,617.00 247.17 0.00
1540 CABINETS Range or sink base, two doors below, 36" wide 2 Carp 20.3 0.0985 Ea. 1.00 259.88 35.42 0.00
4720 CABINETS Kitchen wall cabinets, hardwood, 12" deep with two doors 0 0.00 0.00 0.00
24" high, 36" wide 2 Carp 22.7 0.616875 Ea. 7.00 1,684.38 221.66 0.00
0100 CASEWORK, FRAMES Base cabinets, counter storage, 36" high, one bay 0 0.00 0.00 0.00
18" wide 1 Carp 2.7 2.963 Ea. 8.00 1,232.00 1,062.60 0.00
9800 CASEWORK, FRAMES Wardrobe, 7' high, single, 24" wide 1 Carp 2.7 19.629875 Ea. 53.00 10,712.63 7,039.73 0.00
5600 CABINET DOORS Hardwood raised panel, 18" wide, 30" high 1 Carp 14 0.571 Ea. 8.00 438.90 205.59 0.00
1040 CABINET HARDWARE Catches, maximum 1 Carp 80 1.0625 Ea. 85.00 589.05 382.88 0.00
2340 CABINET HARDWARE Door handles & pulls, projecting, wood, maximum 1 Carp 68 1.25375 Ea. 85.00 523.60 449.97 0.00
3040 CABINET HARDWARE Drawer tracks/glides, maximum 1 Carp 24 0.333 Pr. 8.00 246.40 120.12 0.00
4042 CABINET HARDWARE Cabinet hinges, maximum 1 Carp 68 1.25375 Pr. 85.00 981.75 449.97 0.00
8100 VANITIES Vanity bases, 2 doors, 30" high, 21" deep, 36" wide 2 Carp 13.33 1.65 Ea. 11.00 5,187.88 592.90 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 13 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-070 THERMAL & MOISTURE PROTECTION 0 0.00 0.00 0.00
071 Waterproofing & Dampproofing 0 0.00 0.00 0.00
071-100 Sheet Waterproofing 0 0.00 0.00 0.00
2100 ELASTOMERIC WATERPROOFING Fiberglass reinforced, fluid applied 2 Rofc 500 6.996 S.F. 1,749.00 3,838.18 2,289.44 0.00
0600 MEMBRANE WATERPROOFING On slabs, 3 ply, felt G-1 2100 1.589625 S.F. 471.00 371.74 480.54 63.47
072 Insulation & Fireproofing 0 0.00 0.00 0.00
072-200 Roof & Deck Insulation 0 0.00 0.00 0.00
0460 ROOF INSULATION Fibergalss in 4' x 8' sheets, 1-1/16" thick, R3.8 1 Rofc 1000 7.786 S.F. 7,786.00 7,494.03 2,547.97 0.00
073 Shingles & Roof Tiles 0 0.00 0.00 0.00
073-100 Shingles 0 0.00 0.00 0.00
0150 ASPHALT SHINGLES Standard strip shingles, Inorganic, class A 1 Rofc 5.5 800.61375 Sq. 4,402.00 237,267.80 262,689.35 0.00
0700 ASPHALT SHINGLES Hip & Ridge roll shingles 1 Rofc 400 0.65 L.F. 260.00 225.23 215.22 0.00
074 Preformed Roofing & Siding 0 0.00 0.00 0.00
074-100 Preformed Panels 0 0.00 0.00 0.00
0700 STEEL ROOFING Coloured, ribbed, on steel frame, 26 gauge G-3 1000 13.536 S.F. 3,384.00 5,211.36 4,690.22 130.28
076 Flashing & Sheet Metal 0 0.00 0.00 0.00
076-200 Sheet Metal Flash & Trim 0 0.00 0.00 0.00
0010 FLASHING Gauge 24, colored, wall type, 24" wide 1 Shee 145 3.2175 S.F. 468.00 234.23 1,324.32 0.00
2800 GUTTERS 26 gauge galvanized steel, colored, S-type, 36" wide 1 Shee 120 4.815625 L.F. 575.00 1,051.53 1,970.24 0.00
0010 GUTTER GUARD 6" wide strip, aluminum mesh 1 Carp 500 1.15 L.F. 575.00 431.68 409.54 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 14 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-080 DOORS & WINDOWS 0 0.00 0.00 0.00
081 Metal Doors & Frames 0 0.00 0.00 0.00
081-100 Steel Doors & Frames 0 0.00 0.00 0.00
0600 RESIDENTIAL STEEL DOOR Prehung, insulated, exterior, 0 0.00 0.00 0.00
Embossed, full panel, 3'-0" wide x 7'-0" high F-2 15 0.133375 Ea. 1.00 356.13 48.13 2.12
0100 STEEL FRAMES, KNOCK DOWN 18 gauge, up to 5-3/4" deep 0 0.00 0.00 0.00
7'-0" high, 3'-0" wide, single F-2 16 0.875 Ea. 7.00 882.61 316.66 13.88
082 Wood & Platic Doors 0 0.00 0.00 0.00
082-050 Wood & Plastic Doors 0 0.00 0.00 0.00
0440 WOOD FRAMES Exterior frame, incl. ext. trim, 2" x 6" deep F-2 375 1.187875 L.F. 221.00 1,565.56 425.43 17.02
3040 WOOD FRAMES Interior frame, 2" x 5" deep F-2 375 1.8275 L.F. 340.00 2,238.39 654.50 26.18
0380 WOOD DOOR, ARCHITECTURAL Flush, interior, 7 ply, hollow core 0 0.00 0.00 0.00
Walnut face, 3'-0" wide x 7'-0" high F-2 17 0.23525 Ea. 2.00 431.20 84.70 3.73
1720 WOOD DOOR, ARCHITECTURAL Flush, interior, 7 ply, 0 0.00 0.00 0.00
H.P. plastic laminate, 2'-0" wide x 7'-0" high F-2 16 1.25 Ea. 10.00 1,905.75 452.38 19.83
4020 WOOD DOORS, DECORATOR Hand curved door 0 0.00 0.00 0.00
Mahogany, 3'-0" wide x 7'-0" high F-2 14 0.714375 Ea. 5.00 4,908.75 255.06 11.36
1780 WOOD DOORS, PANELED Interior, six panel, hollow core, 1-3/8" thick 0 0.00 0.00 0.00
Molded hardboard, 3'-0" wide x 7'-0" high F-2 13 1.384875 Ea. 9.00 3,170.48 493.76 22.00
1020 WOOD DOORS Entrance door, 1-3/4" x 3'-0" x 7'-0", six panel F-2 15 0.26675 Ea. 2.00 1,174.25 96.25 4.24
3280 WOOD DOORS Interior closet, bi-fold, with hardware, no frame or trim 0 0.00 0.00 0.00
Louvered, pine, 6'-8" x 6'-0" wide F-2 10 3.6 Ea. 18.00 5,024.25 1,299.38 57.17
083-100 Sliding Doors 0 0.00 0.00 0.00
0100 GLASS, SLIDING Wood, 1/2" tempered insul. Glass, 6'-0" wide 2 Carp 4 0.5 Ea. 1.00 1,309.00 179.99 0.00
0450 GLASS, SLIDING Aluminum, 1/2" tempered insul. Glass, 6'-0" wide 2 Carp 4 0.5 Ea. 1.00 558.25 179.99 0.00
083-800 Sound Retardant Doors 0 0.00 0.00 0.00
0010 ACOUSTICAL Incl. framed seals, 3'-0" x 7'-0", wood, 27 STC rating F-2 1.5 0 Ea. 0.00 0.00 0.00 0.00
085 Metal Windows 0 0.00 0.00 0.00
085-100 Steel Windows 0 0.00 0.00 0.00
0100 STEEL SASH Custom units, glazing & trim not included, 0 0.00 0.00 0.00
Casement, 100% vented, 2 Sswk 200 6.45 S.F. 645.00 33,523.88 2,582.58 0.00
2500 STEEL SASH Picture window, glazing & trim not included, 2 Sswk 200 0.49 S.F. 49.00 1,013.99 196.20 0.00
085-200 Aluminum Windows 0 0.00 0.00 0.00
0300 ALUMINUM SASH Stock, grade C, glazed & trim not incl., Sliding 2 Sswk 200 0 S.F. 0.00 0.00 0.00 0.00
087 Hardware 0 0.00 0.00 0.00
087-100 Finish Hardware 0 0.00 0.00 0.00
0020 DEADLOCKS Mortise, heavy duty, double cylinder 1 Carp 9 0.333375 Ea. 3.00 600.60 121.28 0.00
1200 DEADLOCKS Night latch, outside key 1 Carp 10 0.1 Ea. 1.00 96.25 36.00 0.00
1900 DOORSTOPS Holder & bumper, plunger type, door mounted 1 Carp 24 1.08225 Ea. 26.00 1,101.10 390.39 0.00
0010 ENTRANCE LOCKS Cylinder, grip handle, deadlocking latch 1 Carp 9 0.4445 Ea. 4.00 685.30 161.70 0.00
0400 HINGES Full mortise, avg.freq., brass base, 4-1/2" x 4-1/2" US10 0 Pr. 66.00 3,811.50 0.00 0.00
0010 KICKPLATE 6" high, for 3' door, stainless steel 1 Carp 15 0.13325 Ea. 2.00 64.68 47.93 0.00
1700 LOCKSET Standard duty, cylindrical, with sectional trim, 0 0.00 0.00 0.00
residential, interior door 1 Carp. 16 1 Ea. 16.00 338.80 360.36 0.00
0020 MORTISE LOCKSET Comm., wrought knobs & full escutheon trim 0 0.00 0.00 0.00
Non-keyed, passage 1 Carp 9 1.11125 Ea. 10.00 2,310.00 404.25 0.00
087-200 Operators 0 0.00 0.00 0.00
0010 AUTOMATIC OPENERS Double simultaneous doors, one way 2 Skwk 1.7 9.4445 Pr. 2.00 9,201.50 3,503.50 0.00
2400 DOOR CLOSER Rack & pinion, Top jamb mount, regular arm 1 Carp 6 0.33325 Ea. 2.00 415.80 119.35 0.00
087-500 Door/Window Accessories 0 0.00 0.00 0.00
1000 DOOR ACCESSORIES Knockers, brass, standard 1 Carp 16 0.125 Ea. 2.00 128.98 45.05 0.00
088 Glazing 0 0.00 0.00 0.00
088-100 Glass 0 0.00 0.00 0.00
0010 REFLECTIVE GLASS 1/4" float with fused metallic oxide, tinted 2 Glaz 115 3.09275 S.F. 178.00 2,569.88 1,120.47 0.00
0010 WINDOW GLASS Clear Float, stops, putty bed, 1/8" thick 2 Glaz 480 2.660625 S.F. 645.00 2,483.25 968.47 0.00
089 Glazed Curtain Wallls 0 0.00 0.00 0.00
089-200 Glazed Curtain Walll 0 0.00 0.00 0.00
0010 WINDOW WALLS Aluminum, stock, including glazing H-2 160 3.3375 S.F. 178.00 7,024.33 1,123.89 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 15 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-090 FINISHES 0 0.00 0.00 0.00
01 Metal Support Sytems 0 0.00 0.00 0.00
092-050 Furring & Lathing 0 0.00 0.00 0.00
8720 FURRING Suspended ceilings, including, 2" carriers, 24" O.C., with 0 0.00 0.00 0.00
3/4" channels,24" O.C. 1 Lath 190 30.67575 S.F. 5,843.00 3,936.72 11,022.82 0.00
092 Lath, Plaster & Gypsum Board 0 0.00 0.00 0.00
092-100 Gypsum/Cement Plaster 0 0.00 0.00 0.00
0310 CEMENT PLASTER 3/4" thick, troweled finish, on walls J-1 105 120.9675 S.Y. 2,540.00 15,108.56 39,604.95 1,809.12
092-600 Gypsum/Plywood/Cement Board System 0 0.00 0.00 0.00
0150 DRYWALL Plywood, nailed or screwed to studs, on ceilings, 1/4" thick 2 Carp 2000 5.829 S.F. 5,829.00 1,683.12 2,131.96 0.00
093 Tile 0 0.00 0.00 0.00
093-100 Ceramic Tile 0 0.00 0.00 0.00
5110 CERAMIC TILE Floors, unglazed or glazed, set with tile adhesive D-7 470 11.79 S.F. 655.00 4,350.02 3,833.06 0.00
5800 CERAMIC TILE Walls, unglazed or glazed, set with tile adhesive D-7 490 34.425 S.F. 2,040.00 9,306.99 11,191.95 0.00
093-300 Quarry Tile 0 0.00 0.00 0.00
2800 QUARRY TILE Base, stair tred & riser, 3/4" thick, abrasive D-7 47 12.835 S.F. 302.00 2,046.35 4,185.72 0.00
094 Terrazzo 0 0.00 0.00 0.00
094-200 Precast Terrazzo 0 0.00 0.00 0.00
1600 TERRAZZO, PRECAST Floor tiles, non-slip, 1-1/2" thick, 16" x 16" D-1 21 17.24025 S.F. 181.00 4,790.84 5,696.75 0.00
095 Accoustical Trearment & Wood Flooring 0 0.00 0.00 0.00
095-250 Acoustical Space Units 0 0.00 0.00 0.00
0100 SOUND ABSORBING PANELS Perforated Steel facing, painted, with 0 0.00 0.00 0.00
fiberglass or mineral fiber, no backs, 2-1/4" thick, modular 0 0.00 0.00 0.00
space units, ceiling or wall hung, white or colored 1 Carp 100 0 S.F. 0.00 0.00 0.00 0.00
095-600 Wood Strip Flooring 0 0.00 0.00 0.00
5600 WOOD FLOOR Parquetry, standard, 5/16" thick, not incl. finish, Teak 1 Carp 100 12.93 S.F. 1,293.00 15,307.50 4,654.48 0.00
7800 WOOD FLOOR Sanding & finishing, fill, polyurethane,wax A-1A 295 4.363875 S.F. 1,293.00 1,294.29 1,244.51 273.79
096 Flooring & Carpet 0 0.00 0.00 0.00
096-150 Marble Flooring 0 0.00 0.00 0.00
0200 MARBLE Thin gauge tile, thin set, on floors D-7 60 9.2115 S.F. 276.00 3,108.11 3,001.85 0.00
0300 MARBLE Thin gauge tile, thin set, on walls D-7 52 0 S.F. 0.00 0.00 0.00 0.00
096-350 Brick Flooring 0 0.00 0.00 0.00
0600 FLOORING Sidewalk or Patios, on sand bed, laid flat no mortar, 0 0.00 0.00 0.00
Paving blocks, 4.5 per S.F., herringbone pattern D-1 110 37.645625 S.F. 2,077.00 9,715.69 14,969.35 0.00
096-900 Carpet Tile 0 0.00 0.00 0.00
1100 CARPET TILE Tufted, 24" x 24", 24 oz. nylon 1 Tilf 80 1.175 S.Y. 94.00 3,799.95 425.23 0.00
099 Painting & Wall Covering 0 0.00 0.00 0.00
099-100 Exterior Painting 0 0.00 0.00 0.00
0100 SIDING Exterior, oil base, primer or sealer coat, brushwork 2 Pord 2800 0 S.F. 0.00 0.00 0.00 0.00
0800 SIDING Exterior, oil base paint, two coats, brushwork 2 Pord 1850 0 S.F. 0.00 0.00 0.00 0.00
8100 SIDING Exterior, water base, primer or sealer coat, brushwork 2 Pord 2800 4.70475 S.F. 6,273.00 718.49 1,449.06 0.00
8800 SIDING Exterior, water base paint, two coats, brushwork 2 Pord 1850 7.057125 S.F. 6,273.00 1,328.31 2,294.35 0.00
099-200 Interior Painting 0 0.00 0.00 0.00
1000 CABINETS & CASEWORK Primer coat, oil base, brushwork 1 Pord 680 3.597 S.F. 2,398.00 276.97 1,200.20 0.00
2000 CABINETS & CASEWORK Paint per 1 coat, oil base, brushwork 1 Pord 600 3.89675 S.F. 2,398.00 276.97 1,338.68 0.00
0500 DOORS & WINDOWS Flush door & frame, 3'x7', per side, 0 0.00 0.00 0.00
oil, primer coat, brushwork 1 Pord 17 0.7065 Ea. 12.00 29.57 236.78 0.00
1000 DOORS & WINDOWS Flush door & frame, 3'x7', per side, 0 0.00 0.00 0.00
oil, paint 1 coat, brushwork 1 Pord 16 0.75 Ea. 12.00 28.64 251.79 0.00
2000 DOORS & WINDOWS Panel door & frame, 3'x7', per side, 0 0.00 0.00 0.00
oil, primer coat, brushwork 1 Pord 15 0.599625 Ea. 9.00 19.40 200.97 0.00
2200 DOORS & WINDOWS Panel door & frame, 3'x7', per side, 0 0.00 0.00 0.00
oil, paint 1 coat, brushwork 1 Pord 14 0.642375 Ea. 9.00 18.71 215.70 0.00
6800 DOORS & WINDOWS Windows, incl. frame & trim, 4'x8'opening, 0 0.00 0.00 0.00
per side,oil, primer coat, brushwork 1 Pord 10 4.2 Ea. 42.00 124.51 1,406.79 0.00
7000 DOORS & WINDOWS Windows, incl. frame & trim, 4'x8'opening, 0 0.00 0.00 0.00
per side,oil, paint 1 coat, brushwork 1 Pord 10 4.2 Ea. 42.00 119.66 1,406.79 0.00
3800 MISCELLANEOUS Grilles, per side, oil base, primer coat, brushwork 1 Pord 550 0.465 S.F. 248.00 23.87 152.77 0.00
3920 MISCELLANEOUS Grilles, per side, oil base, paint 2 coats, brushwork 1 Pord 340 0.744 S.F. 248.00 33.42 243.47 0.00
7000 MISCELLANEOUS Trim, wood, incl. puttying under 6" wide 0 0.00 0.00 0.00
Primer coat, oil base, brushwork 1 Pord 900 2.241 L.F. 1,992.00 153.38 728.57 0.00
7450 MISCELLANEOUS Trim, wood, incl. puttying under 6" wide 0 0.00 0.00 0.00
Paint 3 coats, oil base, brushwork 1 Pord 370 5.478 L.F. 1,992.00 383.46 1,802.26 0.00
8000 MISCELLANEOUS Cornice, simple design, wood, 0 0.00 0.00 0.00
Primer coat, oil base, brushwork 1 Pord 550 0.93375 S.F. 498.00 47.93 306.77 0.00
8250 MISCELLANEOUS Cornice, simple design, wood, 0 0.00 0.00 0.00
Paint 1 coat, oil base, brushwork 1 Pord 500 0.996 S.F. 498.00 57.52 335.53 0.00
0240 WALLS & CEILINGS Concrete, drywall or plaster, oil base, primer coat 0 0.00 0.00 0.00
Smooth finish, Roller 1 Pord 2040 2.9145 S.F. 5,829.00 561.04 1,009.87 0.00
0840 WALLS & CEILINGS Concrete, drywall or plaster, oil base, 0 0.00 0.00 0.00
Paint 2 coats, Smooth finish, Roller 1 Pord 1190 5.100375 S.F. 5,829.00 1,122.08 1,683.12 0.00
2000 WALLS & CEILINGS Masonry or concrete block, oil base, primer coat, 0 0.00 0.00 0.00
Smooth finish, brushwork 1 Pord 1224 13.51 S.F. 15,440.00 2,674.98 4,161.08 0.00
2800 WALLS & CEILINGS Masonry or concrete block, oil base, 0 0.00 0.00 0.00
Paint 2 coats, Smooth finish, brushwork 1 Pord 756 21.23 S.F. 15,440.00 3,863.86 6,836.06 0.00
4100 WALLS & CEILINGS Silicone, water repellent, 2 coats, spray 1 Pord 2000 0.8745 S.F. 1,749.00 437.69 0.00 0.00
0010 VARNISH 1 coat + sealer, on wood trim, no sanding included 1 Pord 400 0 S.F. 0.00 0.00 0.00 0.00
0100 VARNISH Harwood floors, 1 coat, no sanding included, brushwork 1 Pord 2380 0 S.F. 0.00 0.00 0.00 0.00
099-700 Wallpaper 0 0.00 0.00 0.00
3600 WALL COVERING Adhesive, 5 gal. lot 0 Gal. 0.00 0.00 0.00 0.00
3700 WALL COVERING Wall paper 1 Pape 640 0 S.F. 0.00 0.00 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 16 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-100 SPECIALTIES 0 0.00 0.00 0.00
105 Lockers, Protective Covers & Postal Specialties 0 0.00 0.00 0.00
105-520 Mail Boxes 0 0.00 0.00 0.00
0100 MAIL BOXES Horiz., key lock, 5"H x 6"W x 15"D, alum., Front loading 1 Carp 34 0.029375 Ea. 1.00 85.66 10.59 0.00
108 Toilet & Bath Accessories & Scales 0 0.00 0.00 0.00
108-200 Bath Accessories 0 0.00 0.00 0.00
0200 BATHROOM ACCESSORIES Curtain rod, stainless steel, 5' long,1"dia. 1 Carp 13 0.076875 Ea. 1.00 44.28 27.62 0.00
0500 BATHROOM ACCESSORIES Dispenser units, combined soap & towel 0 0.00 0.00 0.00
dispensers, mirror & shelf, flush mounted 1 Carp 10 1 Ea. 10.00 4,908.75 359.98 0.00
1100 BATHROOM ACCESSORIES Grab bar, straight, 1-1/4" dia., 36" long 1 Carp 20 0.5 Ea. 10.00 808.50 179.99 0.00
3500 BATHROOM ACCESSORIES Mirror with 5" stainless steel shelf, 0 0.00 0.00 0.00
3/4" sq. frame, 18" x 24" 1 Carp 20 0.5 Ea. 10.00 1,299.38 179.99 0.00
4200 BATHROOM ACCESSORIES Napkin/Tampon dispenser, recessed 1 Carp 15 0.66625 Ea. 10.00 6,930.00 239.66 0.00
4300 BATHROOM ACCESSORIES Robe hook, single, regular 1 Carp 36 0.2775 Ea. 10.00 175.18 100.10 0.00
4600 BATHROOM ACCESSORIES Soap dispenser, chrome, 0 0.00 0.00 0.00
surface mounted, liquid 1 Carp 20 0.5 Ea. 10.00 741.13 179.99 0.00
6100 BATHROOM ACCESSORIES Toilet tissue dispenser, 0 0.00 0.00 0.00
surface mounted, stainless steel, single roll 1 Carp 30 0.33375 Ea. 10.00 184.80 120.31 0.00
6290 BATHROOM ACCESSORIES Toilet seat 1 Plum 40 0.25 Ea. 10.00 281.05 105.88 0.00
6500 BATHROOM ACCESSORIES Towel bar, stailess steel, 30" long 1 Carp 21 0.47625 Ea. 10.00 452.38 171.33 0.00
0400 MEDICINE CABINETS Sliding mirror doors, 24" x 19" x 8-1/2" 0 0.00 0.00 0.00
unlighted 1 Carp 5 2 Ea. 10.00 2,387.00 721.88 0.00
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-110 EQUIPMENT 0 0.00 0.00 0.00
110 Equipment 0 0.00 0.00 0.00
110-500 Library Equipment 0 0.00 0.00 0.00
0300 LIBRARY EQUIPMENT Bookshelf, metal, 90" high, 10" shelf, 0 0.00 0.00 0.00
single face 1 Carp 12 9.0045 L.F. 108.00 12,474.00 3,232.85 0.00
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-150 MECHANICAL/SANITARY 0 0.00 0.00 0.00
920 Plumbing -Two Fixture Bathroom incl. WC, lav., acc., pipe & fittings 0 System 1.00 1,631.65 2,017.50 0.00
931 Plumbing -Three Fixture Bathroom incl. Bathtub, WC, lav., acc., pipe & fittings 0 System 0.00 0.00 0.00 0.00
933 Plumbing -Three Fixture Bathroom incl. Shower, WC, lav., acc., pipe & fittings 0 System 8.00 19,725.71 24,549.14 0.00
940 Plumbing -Four Fixture Bathroom incl. Shower, Bathtub, WC, lav., acc., pipe & fittings 0 System 0.00 0.00 0.00 0.00
950 Plumbing -Five Fixture Bathroom incl. Shower, Bathtub,WC, 2 lav., acc., pipe & fittings 0 System 1.00 4,966.02 4,241.55 0.00
910 Fire Sprinkler Systems, Wet, ordinary hazard, 2,000S.F. on 1 floor 0 System 2.00 12,696.11 18,928.14 0.00
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT QUANTITY MATERIAL LABOR TOTAL L&M
OUTPUT HOURS COST COST COST
0 0.00 0.00 0.00
DIV-160 ELECTRICAL 0 0.00 0.00 0.00
230 Residential Service-Single Phase, 200 amperes 0 System 2.00 3,016.48 4,573.42 0.00
900 Lighting, Flourescent, incl. fixture, lamp, outlet box & wiring 0 System 0.00 0.00 0.00
910 Lighting, Incandescent, incl. fixture, lamp, outlet box, conduit & wiring 0 System 0.00 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 17 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST
DIV-010 GENERAL REQUIREMENTS 0.00 0.00
010 Overhead & Miscellaneous Data 0.00 0.00
010-000 Overhead 0.00 0.00
0200 INSURANCE, All risk type Job 0.00 0.00
0600 Public Liability Job 0.00 0.00
0010 PERMITS Job 0.00 0.00
013 Submittals 0.00 0.00
013-300 Survey Data 0.00 0.00
1200 Crew for building layout, 3 man crew A-7 1 24 Day 0.00 0.00 1,500.00 2,887.50
014 Quality Control 0.00 0.00
014-100 Testing Services 0.00 0.00
1800 TESTING, Compressive strength, cylinders, delivered to lab Ea. 0.00 80.00 154.00
015 Construction Facilities & Temporary Controls 0.00 0.00
015-100 Temporary Utilities 0.00 0.00
0350 Lighting, incl. service lamps, wiring & outlets 1-Elec 34 0.235 CSF Flr 2.44 4.70 6.30 12.13
0400 Power for temporary lighting only, per month, minimum per month CSF Flr 0.00 0.00
015-250 Construction Aids 0.00 0.00
0014 STEEL SCAFFOLDING, Rent, 1 use per mo., no plank 0.00 0.00
0090 Building exterior 3 Carp 16.8 1.429 CSF 13.00 25.03 33.50 64.49
0460 Building interior walls, (area) up to 16' high 3 Carp 22.7 1.057 CSF 12.50 24.06 24.50 47.16
0800 Building interior floor area, up to 30' high 3 Carp 90 0.267 CCF 3.90 7.51 6.25 12.03
015-400 Security 0.00 0.00
0010 WATCHMAN Service, monthly basis, uniformed man Hr. 0.00 0.00
CREW HOURLY RENT
ITEM NO. ITEM DESCRIPTION EQUIP. UNIT OPERATOR PER DAY
FACTOR FACTOR COST FACTOR COST
016 Material & Equipment 0.00 0.00
016-400 Equipment Rental 0.00 0.00
0010 CONCRETE EQUIPMENT RENTAL without operators 0.00 0.00
1300 Finisher, concrete floor, gas, manual, 3 blade, 36" trowel 38.00 Ea. 0.75 1.44 53.50 102.99
1800 Mixer, powered, mortar & concrete, gas 38.60 Ea. 0.95 1.83 51.50 99.14
2120 Pump, concrete, truck mounted, 4" line, 80' boom 542.60 Ea. 9.20 17.71 780.00 1,501.50
2700 Vibrators, concrete, Gas engine, 5H.P. 11.25 Ea. 0.28 0.54 15.00 28.88
0010 EARTHWORK EQUIPMENT RENTAL without operators 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 18 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
1300 Vibratory plate compactor, gas, 24" plate, 5000 lb. blow 45.20 Ea. 1.65 3.18 53.50 102.99
0010 GENERAL EQUIPMENT RENTAL 0.00 0.00
7800 Welding Machine, electric, 300 amp 45.80 Ea. 1.85 3.56 51.50 99.14
8100 Wheelbarrow, any size 4.10 Ea. 0.00 6.85 13.19
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST
017 Contract Closeout 0.00 0.00
017-100 Final Cleaning 0.00 0.00
0011 CLEANING UP After job completion Project 0.00 0.00
0100 Cleanup of floor area, Final A-5 11.5 1.565 MSF 1.72 3.31 29.00 55.83
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST
022 Earthwork 0.00 0.00
022-200 Excavation/Backfill/Compact 0.00 0.00
0010 BACKFILL by hand, no compaction, light soil 1 Clab 14 0.571 C.Y. 0.00 10.60 20.41
0300 COMPACTION in 6" layers, hand tamp 1 Clab 20.6 0.388 C.Y. 0.00 7.20 13.86
0600 COMPACTION in 6" layers, Vibrating plate A-1 60 0.133 C.Y. 0.00 2.47 4.75
0010 EXCAVATING, STRUCTURAL Hand, pits to 6' deep, sandy soil 1 Clab 8 1 C.Y. 0.00 18.55 35.71
1400 EXCAVATING, TRENCH or continuous footing, common earth 0.00 0.00
By hand with pick & shovel to 6' deep, light soil 1 Clab 8 1 C.Y. 0.00 18.55 35.71
022-800 Soil Treatment 0.00 0.00
0020 TERMITE PRETREATMENT, Slab & Walls, residential 1 Skwk 1508 0.005 SF Flr. 0.12 0.23 0.13 0.25
0400 Insecticides for termite control 1 Skwk 14.2 0.563 Gal. 9.50 18.29 13.60 26.18
025 Paving & Surfacing 0.00 0.00
025-100 Walk/Road/Parking Paving 0.00 0.00
0310 SIDEWALKS, DRIVEWAYS & PARKING, concrete 3,000psi, 0.00 0.00
cast in place with 6 x 6 - W1.4 x W1.4 mesh, broomed finish, 0.00 0.00
no base, 4" thick B-24 600 0.04 S.F. 0.92 1.77 0.87 1.67
025-150 Unit Pavers 0.00 0.00
1500 PAVING BLOCKS on 4" thick sand bed laid flat, 4.5 per S.F. D-1 110 0.145 S.F. 2.57 4.95 3.12 6.01
025-800 Pavement Marking 0.00 0.00
0010 PAINTING LINES On pavement, reflectorized white, 4" wide B-78 20000 0.002 L.F. 0.05 0.10 0.05 0.10
026 Piped Utilities 0.00 0.00
026-010 Piped Utilities 0.00 0.00
0200 BEDDING For pipe and conduits, not incl. compaction, sand B-6 150 0.16 C.Y. 3.45 6.64 3.21 6.18

PREPARED BY: ARCH. FEDERICO D. DAVID Page 19 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0500 Compacting bedding in trench A-1 90 0.089 C.Y. 0.00 1.65 3.18
0200 EXCAVATION & BACKFILL hand excavate & trim for pipe 8" dia. 1 Clab 155 0.052 L.F. 0.00 0.96 1.85
027 Sewerage & Drainage 0.00 0.00
027-100 Subdrainage System 0.00 0.00
1020 PIPING, DRAINAGE & SEWAGE, CONCRETE, non- reinforced pipe, 0.00 0.00
Extra strength, T&G joints, 8" diameter B-21 200 0.14 L.F. 3.25 6.26 3.03 5.83
027-400 Septic Systems 0.00 0.00
0100 SEPTIC TANKS Not incl. excav. Or piping, precast, 2,000 gallon B-21 5 5.6 Ea. 810.00 1,559.25 121.00 232.93
2200 Excavation for septic tank, 3/4 C.Y. backhoe B-12F 145 0.11 C.Y. 0.00 2.49 4.79
028 Site Improvements 0.00 0.00
028-100 Irrigation Systems 0.00 0.00
0800 SPRINKLER IRRIGATION SYSTEM for lawns, residential system, 0.00 0.00
custom, 1" diameter supply B-20 2619 0.009 S.F. 0.22 0.42 0.19 0.37
028-300 Fences & Gates 0.00 0.00
1400 Gate for 6' High fence, 1-5/8" frame, 3' wide, galvanized steel B-80 10 3.2 Ea. 63.50 122.24 65.00 125.13
1401 Gate for 6' High fence, 1-5/8" frame, 5' wide, galvanized steel B-81 17 5.4 Ea. 106.00 204.05 108.00 207.90
0600 Fence Grill,Open rail, rustic, 3 rails, 3' high B-1 160 0.15 L.F. 2.99 5.76 2.88 5.54
029 Landscaping 0.00 0.00
(see sub-con details) 0.00 0.00
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST
DIV-030 CONCRETE 0.00 0.00
031 Concrete Formwork 0.00 0.00
031-100 Struct C.I.P. Formwork 0.00 0.00
0650 FORMS IN PLACE, BEAMS & GIRDERS, 12" wide, 4 use C-2 310 0.155 SFCA 0.76 1.46 3.54 6.81
6150 FORMS IN PLACE, COLUMNS 16" X 16" plywood, 4 use C-1 235 0.136 SFCA 0.57 1.10 3.02 5.81
1150 FORMS IN PLACE, ELEVATED SLABS, flat plate to 15' high, 4 use C-2 560 0.086 S.F. 0.61 1.17 1.96 3.77
0150 FORMS IN PLACE, GRADE BEAM, 4 use C-2 605 0.079 SFCA 0.48 0.92 1.82 3.50
1050 SHORES, Erect & strip, by hand, Vertical members to 13' high 2 Carp 50 0.32 Ea. 0.00 7.45 14.34
0010 WATERSTOP, PVC 1-1/2" diameter 1 Carp 155 0.052 L.F. 1.33 2.56 1.21 2.33
032 Concrete Reinforcement 0.00 0.00
032-100 Reinforcing Steel 0.00 0.00
0102 REINFORCING IN PLACE, Beams & Girders, #3 to #7 4 Rodm 3200 0.01 Lb. 0.25 0.48 0.26 0.50
0202 REINFORCING IN PLACE, Columns, #3 to #7 4 Rodm 3000 0.011 Lb. 0.25 0.48 0.28 0.54
0402 REINFORCING IN PLACE, Elevated Slabs, #4 to #7 4 Rodm 5800 0.006 Lb. 0.26 0.50 0.14 0.27
0502 REINFORCING IN PLACE, Footings, #4 to #7 4 Rodm 4200 0.008 Lb. 0.23 0.44 0.20 0.39

PREPARED BY: ARCH. FEDERICO D. DAVID Page 20 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0602 REINFORCING IN PLACE, Slab on grade, #3 to #7 4 Rodm 4200 0.008 Lb. 0.25 0.48 0.20 0.39
033 Cast-In-Place Concrete 0.00 0.00
033-100 Structural Concrete 0.00 0.00
0150 CONCRETE, READY MIX Regular weight, 3000 psi C.Y. 48.00 92.40 0.00
6800 CONCRETE IN PLACE Incl. forms & reinforcing steel, 0.00 0.00
Stairs, Free standing C-15 120 0.6 LF Nose 5.00 9.63 13.30 25.60
7000 CONCRETE IN PLACE Incl. forms & reinforcing steel, 0.00 0.00
Stair landings, free standing C-15 285 0.253 S.F. 2.10 4.04 5.60 10.78
0050 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Beams & girders, Roof beams, elevated, pumped C-20 40 1.6 C.Y. 0.00 32.00 61.60
0400 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Columns, square or round, pumped C-20 45 1.422 C.Y. 0.00 28.50 54.86
1400 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Elevated slabs, less than 6" thick, pumped C-20 110 0.582 C.Y. 0.00 11.65 22.43
1900 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Footings, continuous, shallow, direct chute C-6 120 0.4 C.Y. 0.00 7.85 15.11
2400 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Footings, spread, under 1 C.Y., direct chute C-6 55 0.873 C.Y. 0.00 17.15 33.01
3200 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Footing Tie Beams & Grade beams, direct chute C-6 150 0.32 C.Y. 0.00 6.30 12.13
4300 PLACING CONCRETE and vibrating, incl. labor & equipment 0.00 0.00
Slab on grade, 4"direct chute C-6 110 0.436 C.Y. 0.00 8.55 16.46
033-450 Concrete Finishing 0.00 0.00
0200 Steel trowel finish, for resilient tiles C-9 625 0.013 S.F. 0.00 0.30 0.58
0950 Cement topping, laid after, 1:1:1-1/2 mix, 2" thick C-10 500 0.048 S.F. 0.51 0.98 1.03 1.98
034 Precast Concrete 0.00 0.00
034-500 Architectural Precast 0.00 0.00
0010 WALL MOLDINGS, Fiberglass reinforced cement D-1 175 0.091 L.F. 4.70 9.05 1.96 3.77
034-800 Precast Specialties 0.00 0.00
1050 LINTELS, Precast concrete, 6" wide, 8" high, stock units to 12' long D-4 190 0.168 L.F. 8.80 16.94 3.57 6.87
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-040 MASONRY 0.00 0.00


041 Mortar & Masonry Accessories 0.00 0.00
041-000 Mortar 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 21 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0010 CEMENT 40 kg. bag Bag 10.55 20.31 0.00
042 Unit Masonry 0.00 0.00
042-200 Concrete Unit Masonry 0.00 0.00
4100 CONCRETE HOLLOW BLOCKS, 4" thick, tooled joints D-8 430 0.093 S.F. 0.84 1.62 2.04 3.93
4150 CONCRETE HOLLOW BLOCKS, 6" thick, tooled joints D-8 400 0.1 S.F. 1.06 2.04 2.20 4.24
044 Stone 0.00 0.00
044-550 Marble 0.00 0.00
2510 Flooring, polished tiles, 12" x 12" x 3/8" thick, Thin set, average D-11 0 0.267 S.F. 7.65 14.73 6.15 11.84
3550 Thresholds, 3' long, 7/8" thick, 5" wide, Beveled D-12 24 1.333 Ea. 13.90 26.76 29.50 56.79
044-650 Granite 0.00 0.00
0220 GRANITE Cut to size, polished face, 3/4" thick, counter top D-10 130 0.308 S.F. 16.80 32.34 6.50 12.51
044-750 Slate 0.00 0.00
3100 SLATE Stair landings, 1" thick, clear D-1 65 0.246 S.F. 9.90 19.06 5.30 10.20
3600 SLATE Stair treads, sand finish, 1" thick x 12" wide, 3 L.F. to 6 L.F. D-10 120 0.333 L.F. 15.60 30.03 7.50 14.44
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-050 METALS 0.00 0.00


050 Metal Materials, Coatings & Fastenings 0.00 0.00
051-200 Structural Steel 0.00 0.00
1300 STRUCTURAL STEEL ROOF FRAMING, 1 storey, complete system E-5 12.9 6.202 Ton 975.00 1,876.88 160.00 308.00
1600 STRUCTURAL STEEL ROOF FRAMING, 2 storey, complete system E-5 10.6 7.547 Ton 1,150.00 2,213.75 194.00 373.45
055 Metal Fabrications 0.00 0.00
055-200 Handrails & Railings 0.00 0.00
0780 RAILING, PIPE Stainless steel, 3 Rail, 1-1/2" diameter, Mirror finish E-4 120 0.267 L.F. 69.00 132.83 7.05 13.57
0400 RAILING, ORNAMENTAL, Hand forged wrought iron 1-Sswk 12 0.667 L.F. 75.00 144.38 17.35 33.40
055-400 Castings 0.00 0.00
0100 CONSTRUCTION CASTINGS Manhole covers 16" x 16", cast iron E-4 46 0.696 Ea. 60.00 115.50 18.45 35.52
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-060 WOOD & PLASTICS 0.00 0.00


060 Fasteners & Adhesives 0.00 0.00
060-500 Fasteners & Adhesives 0.00 0.00
0700 NAILS Common, 3d to 60d, plain, Galvanized, material only Lb. 0.90 1.73 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 22 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
2000 NAILS Finish nails, 4d to 10d, plain, Galvanized, material only Lb. 0.90 1.73 0.00
2700 NAILS Concrete nails, hardened steel, 3/4" to 3" long, plain, Galvanized Lb. 1.15 2.21 0.00
061 Rough Carpentry 0.00 0.00
061-100 Wood Framing 0.00 0.00
6002 FRAMING, CEILINGS Suspended, 2" x 3" F-2 1000 0.016 L.F. 0.22 0.42 0.37 0.71
6082 FRAMING, ROOFS Fascia boards, 2" x 10" F-2 180 0.089 L.F. 0.91 1.75 2.08 4.00
0602 GROUNDS for casework, 1" x 1-1/2" wood strips, on masonry for plaster 1 Carp 225 0.036 L.F. 0.11 0.21 1.07 2.06
061-150 Sheathing 0.00 0.00
0102 SHEATHING Plywood on roof, 1/2" thick F-2 1400 0.011 S.F. 0.36 0.69 0.27 0.52
061-280 Mineral Fiber Cement Panel 0.00 0.00
2100 MINERAL FIBER CEMENT PANEL Hardiflex, incl.panels, fasteners, 0.00 0.00
accessories, trim & sealants, 1/4" thick, flat sheets G-3 1020 0.031 S.F. 5.70 10.97 0.71 1.37
062 Finish Carpentry 0.00 0.00
062-200 Millworks Moldings 0.00 0.00
0550 MOLDINGS, BASE Baseboard, Wood, 1" x 4" 1 Carp 200 0.04 L.F. 0.80 1.54 0.93 1.79
0110 MOLDINGS, CASINGS Wood, 1" x 3-1/2" 1 Carp 220 0.036 L.F. 1.36 2.62 0.85 1.64
1300 MOLDINGS, CEILINGS Wood, 1" x 3" 1 Carp 300 0.027 L.F. 0.73 1.41 0.62 1.19
3170 MOLDINGS, WINDOW & DOOR Door trim set, 1 head 2 sides, 4-1/2"wide 1 Carp 5.3 1.509 Opng. 40.00 77.00 35.50 68.34
228-5950 MOLDINGS, WINDOW & DOOR Window trim sets,incl. casings, 0.00 0.00
header, stops, stool & apron, 2-1/2" wide, average 1 Carp 10 0.8 Opng. 19.00 36.58 18.70 36.00
062-300 Shelving 0.00 0.00
0700 SHELVING Plywood, 3/4" thick with lumber edge, 24" wide F-1 70 0.114 L.F. 2.05 3.95 2.67 5.14
064 Architectural Woodwork 0.00 0.00
064-100 Custom Casework 0.00 0.00
0840 CABINETS Kitchen base cabinets, hardwoodn not incl. counter top 0.00 0.00
24" deep, 35" high, prefinished, one top drawer, one door below, 18" wide 2 Carp 23.3 0.687 Ea. 105.00 202.13 16.05 30.90
1540 CABINETS Range or sink base, two doors below, 36" wide 2 Carp 20.3 0.788 Ea. 135.00 259.88 18.40 35.42
4720 CABINETS Kitchen wall cabinets, hardwood, 12" deep with two doors 0.00 0.00
24" high, 36" wide 2 Carp 22.7 0.705 Ea. 125.00 240.63 16.45 31.67
0100 CASEWORK, FRAMES Base cabinets, counter storage, 36" high, one bay 0.00 0.00
18" wide 1 Carp 2.7 2.963 Ea. 80.00 154.00 69.00 132.83
9800 CASEWORK, FRAMES Wardrobe, 7' high, single, 24" wide 1 Carp 2.7 2.963 Ea. 105.00 202.13 69.00 132.83
5600 CABINET DOORS Hardwood raised panel, 18" wide, 30" high 1 Carp 14 0.571 Ea. 28.50 54.86 13.35 25.70
1040 CABINET HARDWARE Catches, maximum 1 Carp 80 0.1 Ea. 3.60 6.93 2.34 4.50
2340 CABINET HARDWARE Door handles & pulls, projecting, wood, maximum 1 Carp 68 0.118 Ea. 3.20 6.16 2.75 5.29
3040 CABINET HARDWARE Drawer tracks/glides, maximum 1 Carp 24 0.333 Pr. 16.00 30.80 7.80 15.02
4042 CABINET HARDWARE Cabinet hinges, maximum 1 Carp 68 0.118 Pr. 6.00 11.55 2.75 5.29

PREPARED BY: ARCH. FEDERICO D. DAVID Page 23 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
8100 VANITIES Vanity bases, 2 doors, 30" high, 21" deep, 36" wide 2 Carp 13.33 1.2 Ea. 245.00 471.63 28.00 53.90
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-070 THERMAL & MOISTURE PROTECTION 0.00 0.00


071 Waterproofing & Dampproofing 0.00 0.00
071-100 Sheet Waterproofing 0.00 0.00
2100 ELASTOMERIC WATERPROOFING Fiberglass reinforced, fluid applied 2 Rofc 500 0.032 S.F. 1.14 2.19 0.68 1.31
0600 MEMBRANE WATERPROOFING On slabs, 3 ply, felt G-1 2100 0.027 S.F. 0.41 0.79 0.53 1.02
072 Insulation & Fireproofing 0.00 0.00
072-200 Roof & Deck Insulation 0.00 0.00
0460 ROOF INSULATION Fibergalss in 4' x 8' sheets, 1-1/16" thick, R3.8 1 Rofc 1000 0.008 S.F. 0.50 0.96 0.17 0.33
073 Shingles & Roof Tiles 0.00 0.00
073-100 Shingles 0.00 0.00
0150 ASPHALT SHINGLES Standard strip shingles, Inorganic, class A 1 Rofc 5.5 1.455 Sq. 28.00 53.90 31.00 59.68
0700 ASPHALT SHINGLES Hip & Ridge roll shingles 1 Rofc 400 0.02 L.F. 0.45 0.87 0.43 0.83
074 Preformed Roofing & Siding 0.00 0.00
074-100 Preformed Panels 0.00 0.00
0700 STEEL ROOFING Coloured, ribbed, on steel frame, 26 gauge G-3 1000 0.032 S.F. 0.80 1.54 0.72 1.39
076 Flashing & Sheet Metal 0.00 0.00
076-200 Sheet Metal Flash & Trim 0.00 0.00
0010 FLASHING Gauge 24, colored, wall type, 24" wide 1 Shee 145 0.055 S.F. 0.26 0.50 1.47 2.83
2800 GUTTERS 26 gauge galvanized steel, colored, S-type, 36" wide 1 Shee 120 0.067 L.F. 0.95 1.83 1.78 3.43
0010 GUTTER GUARD 6" wide strip, aluminum mesh 1 Carp 500 0.016 L.F. 0.39 0.75 0.37 0.71
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-080 DOORS & WINDOWS 0.00 0.00


081 Metal Doors & Frames 0.00 0.00
081-100 Steel Doors & Frames 0.00 0.00
0600 RESIDENTIAL STEEL DOOR Prehung, insulated, exterior, 0.00 0.00
Embossed, full panel, 3'-0" wide x 7'-0" high F-2 15 1.067 Ea. 185.00 356.13 25.00 48.13
0100 STEEL FRAMES, KNOCK DOWN 18 gauge, up to 5-3/4" deep 0.00 0.00
7'-0" high, 3'-0" wide, single F-2 16 1 Ea. 65.50 126.09 23.50 45.24
082 Wood & Platic Doors 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 24 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
082-050 Wood & Plastic Doors 0.00 0.00
0440 WOOD FRAMES Exterior frame, incl. ext. trim, 2" x 6" deep F-2 375 0.043 L.F. 3.68 7.08 1.00 1.93
3040 WOOD FRAMES Interior frame, 2" x 5" deep F-2 375 0.043 L.F. 3.42 6.58 1.00 1.93
0380 WOOD DOOR, ARCHITECTURAL Flush, interior, 7 ply, hollow core 0.00 0.00
Walnut face, 3'-0" wide x 7'-0" high F-2 17 0.941 Ea. 112.00 215.60 22.00 42.35
1720 WOOD DOOR, ARCHITECTURAL Flush, interior, 7 ply, 0.00 0.00
H.P. plastic laminate, 2'-0" wide x 7'-0" high F-2 16 1 Ea. 99.00 190.58 23.50 45.24
4020 WOOD DOORS, DECORATOR Hand curved door 0.00 0.00
Mahogany, 3'-0" wide x 7'-0" high F-2 14 1.143 Ea. 510.00 981.75 26.50 51.01
1780 WOOD DOORS, PANELED Interior, six panel, hollow core, 1-3/8" thick 0.00 0.00
Molded hardboard, 3'-0" wide x 7'-0" high F-2 13 1.231 Ea. 183.00 352.28 28.50 54.86
1020 WOOD DOORS Entrance door, 1-3/4" x 3'-0" x 7'-0", six panel F-2 15 1.067 Ea. 305.00 587.13 25.00 48.13
3280 WOOD DOORS Interior closet, bi-fold, with hardware, no frame or trim 0.00 0.00
Louvered, pine, 6'-8" x 6'-0" wide F-2 10 1.6 Ea. 145.00 279.13 37.50 72.19
083-100 Sliding Doors 0.00 0.00
0100 GLASS, SLIDING Wood, 1/2" tempered insul. Glass, 6'-0" wide 2 Carp 4 4 Ea. 680.00 1,309.00 93.50 179.99
0450 GLASS, SLIDING Aluminum, 1/2" tempered insul. Glass, 6'-0" wide 2 Carp 4 4 Ea. 290.00 558.25 93.50 179.99
083-800 Sound Retardant Doors 0.00 0.00
0010 ACOUSTICAL Incl. framed seals, 3'-0" x 7'-0", wood, 27 STC rating F-2 1.5 10.667 Ea. 485.00 933.63 249.00 479.33
085 Metal Windows 0.00 0.00
085-100 Steel Windows 0.00 0.00
0100 STEEL SASH Custom units, glazing & trim not included, 0.00 0.00
Casement, 100% vented, 2 Sswk 200 0.08 S.F. 27.00 51.98 2.08 4.00
2500 STEEL SASH Picture window, glazing & trim not included, 2 Sswk 200 0.08 S.F. 10.75 20.69 2.08 4.00
085-200 Aluminum Windows 0.00 0.00
0300 ALUMINUM SASH Stock, grade C, glazed & trim not incl., Sliding 2 Sswk 200 0.08 S.F. 11.20 21.56 2.08 4.00
087 Hardware 0.00 0.00
087-100 Finish Hardware 0.00 0.00
0020 DEADLOCKS Mortise, heavy duty, double cylinder 1 Carp 9 0.889 Ea. 104.00 200.20 21.00 40.43
1200 DEADLOCKS Night latch, outside key 1 Carp 10 0.8 Ea. 50.00 96.25 18.70 36.00
1900 DOORSTOPS Holder & bumper, plunger type, door mounted 1 Carp 24 0.333 Ea. 22.00 42.35 7.80 15.02
0010 ENTRANCE LOCKS Cylinder, grip handle, deadlocking latch 1 Carp 9 0.889 Ea. 89.00 171.33 21.00 40.43
0400 HINGES Full mortise, avg.freq., brass base, 4-1/2" x 4-1/2" US10 Pr. 30.00 57.75 0.00
0010 KICKPLATE 6" high, for 3' door, stainless steel 1 Carp 15 0.533 Ea. 16.80 32.34 12.45 23.97
1700 LOCKSET Standard duty, cylindrical, with sectional trim, 0.00 0.00
residential, interior door 1 Carp. 16 0.5 Ea. 11.00 21.18 11.70 22.52
0020 MORTISE LOCKSET Comm., wrought knobs & full escutheon trim 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 25 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
Non-keyed, passage 1 Carp 9 0.889 Ea. 120.00 231.00 21.00 40.43
087-200 Operators 0.00 0.00
0010 AUTOMATIC OPENERS Double simultaneous doors, one way 2 Skwk 1.7 37.778 Pr. 2,390.00 4,600.75 910.00 1,751.75
2400 DOOR CLOSER Rack & pinion, Top jamb mount, regular arm 1 Carp 6 1.333 Ea. 108.00 207.90 31.00 59.68
087-500 Door/Window Accessories 0.00 0.00
1000 DOOR ACCESSORIES Knockers, brass, standard 1 Carp 16 0.5 Ea. 33.50 64.49 11.70 22.52
088 Glazing 0.00 0.00
088-100 Glass 0.00 0.00
0010 REFLECTIVE GLASS 1/4" float with fused metallic oxide, tinted 2 Glaz 115 0.139 S.F. 7.50 14.44 3.27 6.29
0010 WINDOW GLASS Clear Float, stops, putty bed, 1/8" thick 2 Glaz 480 0.033 S.F. 2.00 3.85 0.78 1.50
089 Glazed Curtain Wallls 0.00 0.00
089-200 Glazed Curtain Walll 0.00 0.00
0010 WINDOW WALLS Aluminum, stock, including glazing H-2 160 0.15 S.F. 20.50 39.46 3.28 6.31
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-090 FINISHES 0.00 0.00


01 Metal Support Sytems 0.00 0.00
092-050 Furring & Lathing 0.00 0.00
8720 FURRING Suspended ceilings, including, 2" carriers, 24" O.C., with 0.00 0.00
3/4" channels,24" O.C. 1 Lath 190 0.042 S.F. 0.35 0.67 0.98 1.89
092 Lath, Plaster & Gypsum Board 0.00 0.00
092-100 Gypsum/Cement Plaster 0.00 0.00
0310 CEMENT PLASTER 3/4" thick, troweled finish, on walls J-1 105 0.381 S.Y. 3.09 5.95 8.10 15.59
092-600 Gypsum/Plywood/Cement Board System 0.00 0.00
0150 DRYWALL Plywood, nailed or screwed to studs, on ceilings, 1/4" thick 2 Carp 2000 0.008 S.F. 0.15 0.29 0.19 0.37
093 Tile 0.00 0.00
093-100 Ceramic Tile 0.00 0.00
5110 CERAMIC TILE Floors, unglazed or glazed, set with tile adhesive D-7 470 0.144 S.F. 3.45 6.64 3.04 5.85
5800 CERAMIC TILE Walls, unglazed or glazed, set with tile adhesive D-7 490 0.135 S.F. 2.37 4.56 2.85 5.49
093-300 Quarry Tile 0.00 0.00
2800 QUARRY TILE Base, stair tred & riser, 3/4" thick, abrasive D-7 47 0.34 S.F. 3.52 6.78 7.20 13.86
094 Terrazzo 0.00 0.00
094-200 Precast Terrazzo 0.00 0.00
1600 TERRAZZO, PRECAST Floor tiles, non-slip, 1-1/2" thick, 16" x 16" D-1 21 0.762 S.F. 13.75 26.47 16.35 31.47
095 Accoustical Trearment & Wood Flooring 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 26 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
095-250 Acoustical Space Units 0.00 0.00
0100 SOUND ABSORBING PANELS Perforated Steel facing, painted, with 0.00 0.00
fiberglass or mineral fiber, no backs, 2-1/4" thick, modular 0.00 0.00
space units, ceiling or wall hung, white or colored 1 Carp 100 0.08 S.F. 4.40 8.47 1.87 3.60
095-600 Wood Strip Flooring 0.00 0.00
5600 WOOD FLOOR Parquetry, standard, 5/16" thick, not incl. finish, Teak 1 Carp 100 0.08 S.F. 6.15 11.84 1.87 3.60
7800 WOOD FLOOR Sanding & finishing, fill, polyurethane,wax A-1A 295 0.027 S.F. 0.52 1.00 0.50 0.96
096 Flooring & Carpet 0.00 0.00
096-150 Marble Flooring 0.00 0.00
0200 MARBLE Thin gauge tile, thin set, on floors D-7 60 0.267 S.F. 5.85 11.26 5.65 10.88
0300 MARBLE Thin gauge tile, thin set, on walls D-7 52 0.308 S.F. 5.85 11.26 6.50 12.51
096-350 Brick Flooring 0.00 0.00
0600 FLOORING Sidewalk or Patios, on sand bed, laid flat no mortar, 0.00 0.00
Paving blocks, 4.5 per S.F., herringbone pattern D-1 110 0.145 S.F. 2.43 4.68 3.74 7.21
096-900 Carpet Tile 0.00 0.00
1100 CARPET TILE Tufted, 24" x 24", 24 oz. nylon 1 Tilf 80 0.1 S.Y. 21.00 40.43 2.35 4.52
099 Painting & Wall Covering 0.00 0.00
099-100 Exterior Painting 0.00 0.00
0100 SIDING Exterior, oil base, primer or sealer coat, brushwork 2 Pord 2800 0.006 S.F. 0.07 0.13 0.12 0.23
0800 SIDING Exterior, oil base paint, two coats, brushwork 2 Pord 1850 0.009 S.F. 0.13 0.25 0.19 0.37
8100 SIDING Exterior, water base, primer or sealer coat, brushwork 2 Pord 2800 0.006 S.F. 0.06 0.11 0.12 0.23
8800 SIDING Exterior, water base paint, two coats, brushwork 2 Pord 1850 0.009 S.F. 0.11 0.21 0.19 0.37
099-200 Interior Painting 0.00 0.00
1000 CABINETS & CASEWORK Primer coat, oil base, brushwork 1 Pord 680 0.012 S.F. 0.06 0.12 0.26 0.50
2000 CABINETS & CASEWORK Paint per 1 coat, oil base, brushwork 1 Pord 600 0.013 S.F. 0.06 0.12 0.29 0.56
0500 DOORS & WINDOWS Flush door & frame, 3'x7', per side, 0.00 0.00
oil, primer coat, brushwork 1 Pord 17 0.471 Ea. 1.28 2.46 10.25 19.73
1000 DOORS & WINDOWS Flush door & frame, 3'x7', per side, 0.00 0.00
oil, paint 1 coat, brushwork 1 Pord 16 0.5 Ea. 1.24 2.39 10.90 20.98
2000 DOORS & WINDOWS Panel door & frame, 3'x7', per side, 0.00 0.00
oil, primer coat, brushwork 1 Pord 15 0.533 Ea. 1.12 2.16 11.60 22.33
2200 DOORS & WINDOWS Panel door & frame, 3'x7', per side, 0.00 0.00
oil, paint 1 coat, brushwork 1 Pord 14 0.571 Ea. 1.08 2.08 12.45 23.97
6800 DOORS & WINDOWS Windows, incl. frame & trim, 4'x8'opening, 0.00 0.00
per side,oil, primer coat, brushwork 1 Pord 10 0.8 Ea. 1.54 2.96 17.40 33.50
7000 DOORS & WINDOWS Windows, incl. frame & trim, 4'x8'opening, 0.00 0.00
per side,oil, paint 1 coat, brushwork 1 Pord 10 0.8 Ea. 1.48 2.85 17.40 33.50

PREPARED BY: ARCH. FEDERICO D. DAVID Page 27 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
3800 MISCELLANEOUS Grilles, per side, oil base, primer coat, brushwork 1 Pord 550 0.015 S.F. 0.05 0.10 0.32 0.62
3920 MISCELLANEOUS Grilles, per side, oil base, paint 2 coats, brushwork 1 Pord 340 0.024 S.F. 0.07 0.13 0.51 0.98
7000 MISCELLANEOUS Trim, wood, incl. puttying under 6" wide 0.00 0.00
Primer coat, oil base, brushwork 1 Pord 900 0.009 L.F. 0.04 0.08 0.19 0.37
7450 MISCELLANEOUS Trim, wood, incl. puttying under 6" wide 0.00 0.00
Paint 3 coats, oil base, brushwork 1 Pord 370 0.022 L.F. 0.10 0.19 0.47 0.90
8000 MISCELLANEOUS Cornice, simple design, wood, 0.00 0.00
Primer coat, oil base, brushwork 1 Pord 550 0.015 S.F. 0.05 0.10 0.32 0.62
8250 MISCELLANEOUS Cornice, simple design, wood, 0.00 0.00
Paint 1 coat, oil base, brushwork 1 Pord 500 0.016 S.F. 0.06 0.12 0.35 0.67
0240 WALLS & CEILINGS Concrete, drywall or plaster, oil base, primer coat 0.00 0.00
Smooth finish, Roller 1 Pord 2040 0.004 S.F. 0.05 0.10 0.09 0.17
0840 WALLS & CEILINGS Concrete, drywall or plaster, oil base, 0.00 0.00
Paint 2 coats, Smooth finish, Roller 1 Pord 1190 0.007 S.F. 0.10 0.19 0.15 0.29
2000 WALLS & CEILINGS Masonry or concrete block, oil base, primer coat, 0.00 0.00
Smooth finish, brushwork 1 Pord 1224 0.007 S.F. 0.09 0.17 0.14 0.27
2800 WALLS & CEILINGS Masonry or concrete block, oil base, 0.00 0.00
Paint 2 coats, Smooth finish, brushwork 1 Pord 756 0.011 S.F. 0.13 0.25 0.23 0.44
4100 WALLS & CEILINGS Silicone, water repellent, 2 coats, spray 1 Pord 2000 0.004 S.F. 0.13 0.25 0.00 0.00
0010 VARNISH 1 coat + sealer, on wood trim, no sanding included 1 Pord 400 0.02 S.F. 0.08 0.15 0.43 0.83
0100 VARNISH Harwood floors, 1 coat, no sanding included, brushwork 1 Pord 2380 0.003 S.F. 0.08 0.15 0.07 0.13
099-700 Wallpaper 0.00 0.00
3600 WALL COVERING Adhesive, 5 gal. lot Gal. 6.95 13.38 0.00
3700 WALL COVERING Wall paper 1 Pape 640 0.013 S.F. 0.22 0.42 0.27 0.52
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-100 SPECIALTIES 0.00 0.00


105 Lockers, Protective Covers & Postal Specialties 0.00 0.00
105-520 Mail Boxes 0.00 0.00
0100 MAIL BOXES Horiz., key lock, 5"H x 6"W x 15"D, alum., Front loading 1 Carp 34 0.235 Ea. 44.50 85.66 5.50 10.59
108 Toilet & Bath Accessories & Scales 0.00 0.00
108-200 Bath Accessories 0.00 0.00
0200 BATHROOM ACCESSORIES Curtain rod, stainless steel, 5' long,1"dia. 1 Carp 13 0.615 Ea. 23.00 44.28 14.35 27.62
0500 BATHROOM ACCESSORIES Dispenser units, combined soap & towel 0.00 0.00
dispensers, mirror & shelf, flush mounted 1 Carp 10 0.8 Ea. 255.00 490.88 18.70 36.00
1100 BATHROOM ACCESSORIES Grab bar, straight, 1-1/4" dia., 36" long 1 Carp 20 0.4 Ea. 42.00 80.85 9.35 18.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 28 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
3500 BATHROOM ACCESSORIES Mirror with 5" stainless steel shelf, 0.00 0.00
3/4" sq. frame, 18" x 24" 1 Carp 20 0.4 Ea. 67.50 129.94 9.35 18.00
4200 BATHROOM ACCESSORIES Napkin/Tampon dispenser, recessed 1 Carp 15 0.533 Ea. 360.00 693.00 12.45 23.97
4300 BATHROOM ACCESSORIES Robe hook, single, regular 1 Carp 36 0.222 Ea. 9.10 17.52 5.20 10.01
4600 BATHROOM ACCESSORIES Soap dispenser, chrome, 0.00 0.00
surface mounted, liquid 1 Carp 20 0.4 Ea. 38.50 74.11 9.35 18.00
6100 BATHROOM ACCESSORIES Toilet tissue dispenser, 0.00 0.00
surface mounted, stainless steel, single roll 1 Carp 30 0.267 Ea. 9.60 18.48 6.25 12.03
6290 BATHROOM ACCESSORIES Toilet seat 1 Plum 40 0.2 Ea. 14.60 28.11 5.50 10.59
6500 BATHROOM ACCESSORIES Towel bar, stailess steel, 30" long 1 Carp 21 0.381 Ea. 23.50 45.24 8.90 17.13
0400 MEDICINE CABINETS Sliding mirror doors, 24" x 19" x 8-1/2" 0.00 0.00
unlighted 1 Carp 5 1.6 Ea. 124.00 238.70 37.50 72.19
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-110 EQUIPMENT 0.00 0.00


110 Equipment 0.00 0.00
110-500 Library Equipment 0.00 0.00
0300 LIBRARY EQUIPMENT Bookshelf, metal, 90" high, 10" shelf, 0.00 0.00
single face 1 Carp 12 0.667 L.F. 60.00 115.50 15.55 29.93
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-150 MECHANICAL/SANITARY 0.00 0.00


920 Plumbing -Two Fixture Bathroom incl. WC, lav., acc., pipe & fittings System 847.61 1,631.65 1,048.05 2,017.50
931 Plumbing -Three Fixture Bathroom incl. Bathtub, WC, lav., acc., pipe & fittings System 1,205.00 2,319.63 1,233.96 2,375.37
933 Plumbing -Three Fixture Bathroom incl. Shower, WC, lav., acc., pipe & fittings System 1,280.89 2,465.71 1,594.10 3,068.64
940 Plumbing -Four Fixture Bathroom incl. Shower, Bathtub, WC, lav., acc., pipe & fittings System 1,650.55 3,177.31 1,873.00 3,605.53
950 Plumbing -Five Fixture Bathroom incl. Shower, Bathtub,WC, 2 lav., acc., pipe & fittings System 2,579.75 4,966.02 2,203.40 4,241.55
910 Fire Sprinkler Systems, Wet, ordinary hazard, 2,000S.F. on 1 floor System 3,297.69 6,348.05 4,916.40 9,464.07
DAILY MAN BARE COSTS
ITEM NO. ITEM DESCRIPTION CREW UNIT MATERIAL LABOR
OUTPUT HOURS FACTOR COST FACTOR COST

DIV-160 ELECTRICAL 0.00 0.00


230 Residential Service-Single Phase, 200 amperes System 783.50 1,508.24 1,187.90 2,286.71

PREPARED BY: ARCH. FEDERICO D. DAVID Page 29 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
900 Lighting, Flourescent, incl. fixture, lamp, outlet box & wiring System 90.91 175.00 152.90 294.33
910 Lighting, Incandescent, incl. fixture, lamp, outlet box, conduit & wiring System 21.97 42.29 95.35 183.55

PREPARED BY: ARCH. FEDERICO D. DAVID Page 30 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.25 percent 0.00
0.00 1.55 percent 0.00
0.00 0.50 percent 0.00
0.00 0.00
0.00 0.00
0.00 0.00 4,387.50 2,887.50
0.00 0.00
0.00 0.00
0.00 234.00 154.00
0.00 0.00
0.00 0.00
0.00 0.00 25.56 16.82
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00 136.01 89.51
0.00 0.00 108.23 71.23
0.00 0.00 29.69 19.54
0.00 0.00
0.00 6.90 0.00
RENT CREW
PER WEEK PER MONTH EQUIP.
FACTOR COST FACTOR COST COST
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
160.00 308.00 480.00 924.00 73.15
155.00 298.38 465.00 895.13 74.31
2,345.00 4,514.13 7,025.00 13,523.13 1,044.51
45.00 86.63 135.00 259.88 21.66
0.00 0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 31 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
160.00 308.00 480.00 924.00 87.01
0.00 0.00 0.00
155.00 298.38 465.00 895.13 88.17
20.50 39.46 61.50 118.39 7.89
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST
0.00 0.00
0.00 0.00
0.00 0.30 percent #VALUE!
3.33 6.41 34.05 65.55
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST
0.00 0.00
0.00 0.00
0.00 10.60 20.41
0.00 7.20 13.86
0.98 1.89 3.45 6.64
0.00 18.55 35.71
0.00 0.00
0.00 18.55 35.71
0.00 0.00
0.25 0.48 0.34 0.65
0.00 23.10 44.47
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 1.79 3.45
0.00 0.00
0.00 5.69 10.95
0.00 0.00
0.02 0.04 0.12 0.23
0.00 0.00
0.00 0.00
1.34 2.58 8.00 15.40

PREPARED BY: ARCH. FEDERICO D. DAVID Page 32 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.65 1.25 2.30 4.43
0.00 0.60 1.16
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.56 1.08 6.84 13.17
0.00 0.00
22.50 43.31 953.50 1,835.49
3.13 6.03 5.62 10.82
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.41 0.79
0.00 0.00
42.50 81.81 171.00 329.18
71.00 136.68 285.00 548.63
0.00 5.87 11.30
0.00 0.00
0.00 0.00
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST
0.00 0.00
0.00 0.00
0.00 0.00
0.11 0.21 4.41 8.49
0.10 0.19 3.69 7.10
0.06 0.12 2.63 5.06
0.05 0.10 2.35 4.52
0.00 7.45 14.34
0.00 2.54 4.89
0.00 0.00
0.00 0.00
0.00 0.51 0.98
0.00 0.53 1.02
0.00 0.40 0.77
0.00 0.43 0.83

PREPARED BY: ARCH. FEDERICO D. DAVID Page 33 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.45 0.87
0.00 0.00
0.00 0.00
0.00 48.00 92.40
0.00 0.00
0.44 0.85 18.74 36.07
0.00 0.00
0.19 0.37 7.89 15.19
0.00 0.00
15.20 29.26 47.20 90.86
0.00 0.00
13.50 25.99 42.00 80.85
0.00 0.00
5.50 10.59 17.15 33.01
0.00 0.00
0.54 1.04 8.39 16.15
0.00 0.00
1.18 2.27 18.33 35.29
0.00 0.00
0.43 0.83 6.73 12.96
0.00 0.00
0.59 1.14 9.14 17.59
0.00 0.00
0.06 0.12 0.36 0.69
0.15 0.29 1.69 3.25
0.00 0.00
0.00 0.00
0.00 6.66 12.82
0.00 0.00
0.72 1.39 13.09 25.20
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 34 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 10.55 20.31
0.00 0.00
0.00 0.00
0.00 2.88 5.54
0.00 3.26 6.28
0.00 0.00
0.00 0.00
0.00 13.80 26.57
0.00 43.40 83.55
0.00 0.00
3.39 6.53 27.14 52.24
0.00 0.00
0.00 15.20 29.26
3.68 7.08 26.78 51.55
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
88.00 169.40 1,223.00 2,354.28
107.00 205.98 1,451.00 2,793.18
0.00 0.00
0.00 0.00
0.61 1.17 76.66 147.57
0.00 92.35 177.77
0.00 0.00
1.59 3.06 80.04 154.08
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.90 1.73

PREPARED BY: ARCH. FEDERICO D. DAVID Page 35 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.90 1.73
0.00 1.15 2.21
0.00 0.00
0.00 0.00
0.02 0.04 0.61 1.17
0.09 0.17 3.08 5.93
0.00 1.18 2.27
0.00 0.00 0.00
0.01 0.02 0.64 1.23
0.00 0.00
0.00 0.00
0.02 0.04 6.43 12.38
0.00 0.00
0.00 0.00
0.00 1.91 3.68
0.00 2.21 4.25
0.00 1.35 2.60
0.00 75.50 145.34
0.00 0.00
0.00 37.70 72.57
0.00 0.00
0.12 0.23 4.84 9.32
0.00 0.00
0.00 0.00
0.00 0.00
0.00 121.05 233.02
0.00 153.40 295.30
0.00 0.00
0.00 141.45 272.29
0.00 0.00
0.00 149.00 286.83
0.00 174.00 334.95
0.00 41.85 80.56
0.00 5.94 11.43
0.00 5.50 10.59
0.00 23.80 45.82
0.00 8.75 16.84

PREPARED BY: ARCH. FEDERICO D. DAVID Page 36 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 273.00 525.53
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 1.82 3.50
0.07 0.13 1.01 1.94
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.67 1.29
0.00 0.00
0.00 0.00
0.00 59.00 113.58
0.00 0.88 1.69
0.00 0.00
0.00 0.00
0.02 0.04 1.54 2.96
0.00 0.00
0.00 0.00
0.00 1.73 3.33
0.00 2.73 5.26
0.00 0.76 1.46
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
1.10 2.12 211.10 406.37
0.00 0.00
1.03 1.98 90.03 173.31
0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 37 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.00
0.04 0.08 4.72 9.09
0.04 0.08 4.46 8.59
0.00 0.00
0.97 1.87 134.97 259.82
0.00 0.00
1.03 1.98 123.53 237.80
0.00 0.00
1.18 2.27 537.68 1,035.03
0.00 0.00
1.27 2.44 212.77 409.58
1.10 2.12 331.10 637.37
0.00 0.00
1.65 3.18 184.15 354.49
0.00 0.00
0.00 773.50 1,488.99
0.00 383.50 738.24
0.00 0.00
11.00 21.18 745.00 1,434.13
0.00 0.00
0.00 0.00
0.00 0.00
0.00 29.08 55.98
0.00 12.83 24.70
0.00 0.00
0.00 13.28 25.56
0.00 0.00
0.00 0.00
0.00 125.00 240.63
0.00 68.70 132.25
0.00 29.80 57.37
0.00 110.00 211.75
0.00 30.00 57.75
0.00 29.25 56.31
0.00 0.00
0.00 22.70 43.70
0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 38 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 141.00 271.43
0.00 0.00
0.00 3,300.00 6,352.50
0.00 139.00 267.58
0.00 0.00
0.00 45.20 87.01
0.00 0.00
0.00 0.00
0.00 10.77 20.73
0.00 2.78 5.35
0.00 0.00
0.00 0.00
0.00 23.78 45.78
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 1.33 2.56
0.00 0.00
0.00 0.00
0.37 0.71 11.56 22.25
0.00 0.00
0.00 0.34 0.65
0.00 0.00
0.00 0.00
0.00 6.49 12.49
0.00 5.22 10.05
0.00 0.00
0.00 10.72 20.64
0.00 0.00
0.00 0.00
0.00 30.10 57.94
0.00 0.00

PREPARED BY: ARCH. FEDERICO D. DAVID Page 39 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.00
0.00 0.00
0.00 0.00
0.00 6.27 12.07
0.00 0.00
0.00 8.02 15.44
0.11 0.21 1.13 2.18
0.00 0.00
0.00 0.00
0.00 11.50 22.14
0.00 12.35 23.77
0.00 0.00
0.00 0.00
0.00 6.17 11.88
0.00 0.00
0.00 23.35 44.95
0.00 0.00
0.00 0.00
0.00 0.19 0.37
0.00 0.32 0.62
0.00 0.18 0.35
0.00 0.30 0.58
0.00 0.00
0.00 0.32 0.62
0.00 0.35 0.67
0.00 0.00
0.00 11.53 22.20
0.00 0.00
0.00 12.14 23.37
0.00 0.00
0.00 12.72 24.49
0.00 0.00
0.00 13.53 26.05
0.00 0.00
0.00 18.94 36.46
0.00 0.00
0.00 18.88 36.34

PREPARED BY: ARCH. FEDERICO D. DAVID Page 40 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.37 0.71
0.00 0.58 1.12
0.00 0.00
0.00 0.23 0.44
0.00 0.00
0.00 0.57 1.10
0.00 0.00
0.00 0.37 0.71
0.00 0.00
0.00 0.41 0.79
0.00 0.00
0.00 0.14 0.27
0.00 0.00
0.00 0.25 0.48
0.00 0.00
0.00 0.23 0.44
0.00 0.00
0.00 0.36 0.69
0.00 0.22 0.42
0.00 0.51 0.98
0.00 0.15 0.29
0.00 0.00
0.00 6.95 13.38
0.00 0.49 0.94
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 50.00 96.25
0.00 0.00
0.00 0.00
0.00 37.35 71.90
0.00 0.00
0.00 273.70 526.87
0.00 51.35 98.85

PREPARED BY: ARCH. FEDERICO D. DAVID Page 41 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 0.00
0.00 76.85 147.94
0.00 372.45 716.97
0.00 14.30 27.53
0.00 0.00
0.00 47.85 92.11
0.00 0.00
0.00 15.85 30.51
0.00 20.10 38.69
0.00 32.40 62.37
0.00 0.00
0.00 161.50 310.89
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0.00 75.55 145.43
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 1,895.66 3,649.15
0.00 2,438.96 4,695.00
0.00 2,874.99 5,534.36
0.00 3,523.55 6,782.83
0.00 4,783.15 9,207.56
0.00 8,214.09 15,812.12
BARE COSTS
EQUIPMENT TOTAL REMARKS
FACTOR COST FACTOR COST

0.00 0.00
0.00 1,971.40 3,794.95

PREPARED BY: ARCH. FEDERICO D. DAVID Page 42 of 106


PROJECT: PROPOSED 8-BEDROOMS TWO STOREY RESIDENTIAL
LOCATION: LOTS 7, BLK.26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO, PAMPANGA OWNER: VILMA H. MANALO
SUBJECT: BILL OF MATERIALS
0.00 243.81 469.33
0.00 117.32 225.84

PREPARED BY: ARCH. FEDERICO D. DAVID Page 43 of 106


PROJECT TITLE : PROPOSED 8 BEDROOMS TWO STOREY RESIDENTIAL
LOCATION : LOTS 7&8 BLOCK 26 DIZON ESTATE, SAN AGUSTIN, CITY OF SAN FERNANDO PAMPANGA
OWNER : MS. VILMA H. MANALO
ARCHITECT : FEDERICO "BHOB" D. DAVID
SUBJECT : BILL OF MATERIALS

COST EACH
SYSTEM COMPONENTS QUANTITY UNIT
MAT. INST. TOTAL
Interior column footing, 1.00m square, 0.30m thick, 3,000psi concrete,
Including forms, reinforcing, and dowels.
Concrete 3,000psi-1:2:4 mixture using 88lbs. Portland cement 0.30 m3 504.60
Cement 8.20 130.00 2.46 bags 319.80
Sand 0.44 300.00 0.13 m3 39.60
Gravel 0.88 550.00 0.26 m3 145.20
Placing Concrete 0.30 m3
Forms, Footing, 4 uses 1.20 m2
Reinforcing 5.00 kgs.
G.I.Wire #16 kgs.

TABLE 1 FOUNDATIONS
1.1-124 Spread Footing
1.1-144 Strip Footing
1.1-214 Concrete Wall
1.1-242 Concrete Block Wall
TABLE 2 SUBSTRUCTURES
2.1-104 Interior Slab on Grade
TABLE 3 SUPERSTRUCTURES
3.5-154 Floor-Ceiling Concrete Slab
3.5-212 Floor-Ceiling Concrete Panel
3.5-214 Floor-Ceiling Concrete Plank
3.5-314 Floor-Ceiling Structural Steel
3.5-414 Floor-Ceiling Steel Joists
3.5-714 Floor-Ceiling Wood Joists
3.9-104 Stairs
3.9-900 Selective Price Sheet
TABLE 4 EXTERIOR CLOSURE
4.1-208 Masonry Wall, Concrete Block
4.1-258 Masonry Wall, Brick Stone
4.1-288 Parapet Wall
4.1-289 Masonry Restoration Cleaning
4.1-416 Wood Frame Exterior Wall
4.6-142 Doors, Metal-Commercial
4.6-144 Doors, Residential Exterior
4.6-152 Doors, Sliding-Patio
4.6-702 Doors, Overhead
4.7-142 Windows-Aluminum
4.7-144 Windows-Wood
4.7-145 Windows-Wood
4.7-152 Storm Windows and Doors
4.7-700 Aluminum Frame, Window Wall
4.9-200 Selective Price Sheet
4.9-500 Selective Price Sheet
TABLE 5 ROOFING
5.1-192 Steel Joists Roof & Ceiling
5.1-492 Wood Frame Roof & Ceiling
5.8-104 Roof Hatches, Skylights
5.9-300 Selective Price Sheet
5.9-500 Selective Price Sheet
TABLE 6 INTERIOR CONSTRUCTION
6.1-222 Partitions, Concrete Blocks
6.1-592 Partitions, Wood Studs
6.1-594 Partitions, Metal Stud, NLB
6.1-595 Partitions, Drywall
6.1-596 Partitions, Metal Stud, LB
6.1-692 Partitions, Plaster & Lath
6.1-842 Partitions, Movable Office
6.4-142 Doors, Interior Flush, Wood
6.4-144 Doors, Interior Solid and Louvered
6.4-146 Doors, Interior Flush, Metal
6.4-148 Doors, Closet
6.7-242 Ceiling, Suspended Plaster
6.7-342 Ceiling, Suspended Accoustical
6.7-442 Ceiling, Suspended Gypsum Board
6.9-100 Selective Price Sheet
6.9-300 Selective Price Sheet
6.9-500 Selective Price Sheet
6.9-600 Selective Price Sheet
6.9-700 Selective Price Sheet
6.9-800 Selective Price Sheet
TABLE 7 CONVEYING SYSTEMS
7.1-142 Oil Hydraulic Elevators
TABLE 8 MECHANICAL
8.1-710 Plumbing-Public Restroom
8.1-720 Plumbing-Public Restroom
8.1-920 Plumbing-Two Fixture Bathroom
8.1-931 Plumbing-Three Fixture Bathroom
8.1-932 Plumbing-Three Fixture Bathroom
8.1-933 Plumbing-Three Fixture Bathroom
8.1-940 Plumbing-Four Fixture Bathroom
8.1-950 Plumbing-Five Fixture Bathroom
8.2-910 Fire Sprinkler Systems, Wet
8.2-920 Fire Sprinkler Systems, Dry
8.3-270 Heating-Oil Fired Hot Water
8.3-280 Heating-Gas Fired Hot Water
8.3-310 Heating-Cooling, Oil, Forced Air
8.3-320 Heating-Cooling, Gas, Forced Air
TABLE 9 ELECTRICAL
9.1-220 Commercial Service-3 Phase
9.1-230 Residential Service-1 Phase
9.2-900 Lighting, Flourescent
9.2-910 Lighting, Incandescent
9.2-920 Lighting, High Intensity
9.4-910 Heat, Baseboard
9.9-500 Selective Price Sheet
TABLE 11 SPECIAL
11.1-242 Kitchens
11.1-742 Wood Burning Stoves
11.1-744 Masonry Fireplace
11.9-100 Selective Price Sheet
TABLE 12 SITE WORK
12.1-116 Excavation, Utility Trench
12.1-462 Excavation, Footings or Trench
12.1-464 Excavation, Foundation
12.3-940 Septic Systems
12.5-404 Driveways
12.5-514 Parking Lots, Asphalt
12.5-524 Parking Lots, Concrete
12.7-104 Sidewalks
12.7-604 Landscaping-Lawn Establishment
12.9-300 Selective Price Sheet
12.9-700 Selective Price Sheet
Bare Costs Incl. Subs O&P Cost per Manhour
Crew A-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31 1.671159
1 Gas Eng. Power Tool 58.6 64.45 7.33 8.06
8 M.H. Daily Totals 207 312.45 25.88 39.06

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-1A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Laborer 18.55 148.4 31 248 18.55 31 1.671159
1 Power Equipment 31.2 34.3 3.9 4.29
8 M.H. Daily Totals 179.6 282.3 22.45 35.29

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 18.75 31.07 1.671159
1 Truck Driver (light) 153.2 249.6
8 Light Truck, 1.5 Ton 153.4 168.75 6.39 7.03
24 M.H. Daily Totals 603.4 914.35 25.14 38.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-2A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Laborer 18.55 296.8 31 496 18.75 31.07 1.671159
1 Truck Driver (light) 19.15 153.2 31.2 249.6 1.629243
1 Light Truck, 1.5 Ton 153.4 168.75
1 Concrete Saw 98.8 108.7 10.51 11.56
24 M.H. Daily Totals 702.2 1023.05 29.26 42.63

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (light) 19.45 155.6 31.7 253.6 19.45 31.7 1.62982
1 Dump Truck, 12 Ton 315.6 347.15 39.45 43.4
8 M.H. Daily Totals 471.2 600.75 58.9 75.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 22.82 37.8 1.670236
1 Painter, Ordinary 21.75 174 35.4 283.2 1.627586
24 M.H. Daily Totals 547.6 907.2 22.82 37.8

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 18.62 31.02 1.671159
0.25 Truck Driver (light) 19.15 38.3 31.2 62.4 1.629243
0.25 Light Truck, 1.5 Ton 38.35 42.2 2.13 2.34
18 M.H. Daily Totals 373.45 600.6 20.75 33.36

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Chief of Party 23.1 184.8 36.85 294.8 21.68 34.58 1.595238
1 Instrument Man 20.25 162 32.3 258.4 1.595062
16 M.H. Daily Totals 346.8 553.2 21.68 34.58

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Chief of Party 23.1 184.8 36.85 294.8 20.48 33.1 1.595238
1 Instrument Man 20.25 162 32.3 258.4 1.595062
1 Rodman/Chainmen 18.1 144.8 30.15 241.2 1.665746
24 M.H. Daily Totals 491.6 794.4 20.48 33.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Chief of Party 23.1 184.8 36.85 294.8 19.89 32.36 1.595238
1 Instrument Man 20.25 162 32.3 258.4 1.595062
2 Rodman/Chainmen 18.1 289.6 30.15 482.4 1.665746
32 M.H. Daily Totals 636.4 1035.6 19.89 32.36

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Asbestos Foreman 26.65 213.2 43.85 350.8 26.21 43.11 1.645403
7 Asbestos Workers 26.15 1464.4 43 2408 1.644359
4 Airless Sprayers 109.6 120.55
3 HEPA Vacs., 16 Gal. 93.6 102.95 3.18 3.49
64 M.H. Daily Totals 1880.8 2982.3 29.39 46.6

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Asbestos Foreman 26.65 213.2 43.85 350.8 26.21 43.11 1.645403
7 Asbestos Workers 26.15 1464.4 43 2408 1.644359
2 HEPA Vacs., 16 Gal. 62.4 68.65 0.98 3.29
64 M.H. Daily Totals 1740 2827.45 27.19 46.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Asbestos Foreman 26.65 213.2 43.85 350.8 26.21 43.11 1.645403
7 Asbestos Workers 26.15 1464.4 43 2408 1.644359
4 Airless Sprayers 109.6 120.55
2 HEPA Vacs., 16 Gal. 62.4 68.65
2 Chipping Hammers 19.6 21.55 2.99 3.29
64 M.H. Daily Totals 1869.2 2969.55 29.2 46.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew A-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Asbestos Foreman 26.65 213.2 43.85 350.8 26.21 43.11 1.645403
7 Asbestos Workers 26.15 1464.4 43 2408 1.644359
4 Airless Sprayers 109.6 120.55
2 HEPA Vacs., 16 Gal. 62.4 68.65
1 Large Prod. Vac. Loader 468.2 515 10 11
64 M.H. Daily Totals 2317.8 3463 36.21 54.11
Bare Costs Incl. Subs O&P Cost per Manhour
Crew A-13
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8 23.1 36.85 1.595238
1 Large Prod. Vac. Loader 468.2 515 58.53 64.38
8 M.H. Daily Totals 653 809.8 81.63 101.23
30.9785 31.62775 8
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
31 8
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
31 16
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
31 16
31.2 8
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
31.7 8
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
39 16
35.4 8
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
31 16
31.2 2
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
36.85 8
32.3 8
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
36.85 8
32.3 8
30.15 8
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
36.85 8
32.3 8
30.15 16
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
43.85 8
43 56
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
43.85 8
43 56
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
43.85 8
43 56
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
43.85 8
43 56
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
0 #DIV/0!
#VALUE! #VALUE!
#VALUE! #VALUE!
36.85 8
0 #DIV/0!
0 #DIV/0!
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.22 32.1
2 Building Laborers 18.55 296.8 31 496
24 M.H. Daily Totals 461.2 770.4 19.22 32.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 18.95 31.66
4 Building Laborers 18.55 593.6 31 992
40 M.H., Daily Totals 758 1266.4 18.95 31.66

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.11 33.03
4 Building Laborers 18.55 296.8 31 496
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
1 F.E Loader, T.M., 2.5 C.Y. 764 840.4
2 Dump Trucks, 16 Ton 775.6 853.15 32.08 35.28
48 M.H., Daily Totals 2504.8 3278.75 52.19 68.31

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.03 31.67
4 Building Laborers 18.55 593.6 31 992
1 Truck Drivers (heavy) 19.45 155.6 31.7 253.6
1 Tractor, 4 x 2, 195 H.P. 285.4 313.95
2 Platform Trailer 137.4 151.15 8.81 9.69
48 M.H., Daily Totals 1336.4 1985.1 27.84 41.36

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 21.06 34.49
4 Building Laborers 18.55 593.6 31 992
2 Equip. Oper. (Med.) 24.1 385.6 38.45 615.2
1 Mechanic 25.55 204.4 40.75 326
1 Air Compr., 250 C.F.M. 102.8 113.1
2 Air tools and accessories 29.6 32.55
2 50 ft. Air hoses, 1.5" dia. 12.8 14.1
1 F.E.Loader, T.M., 2.5 C.Y. 764 840.4 14.21 15.63
64 M.H., Daily Totals 2257.2 3207.75 35.27 50.12

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 20.07 32.95
2 Equip. Oper. (Med.) 23.1 184.8 36.85 294.8
1 Backhoe Loader, 48 H.P 200.6 220.65 8.36 9.19
24 M.H., Daily Totals 682.2 1011.45 28.43 42.14
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.81 32.79
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (Med.) 24.1 192.8 38.45 307.6
1 Chipping Machine 188.6 207.45
1 F.E Loader, T.M., 2.5 C.Y. 764 840.4
2 Chain Saws 90 99 21.72 23.89
24 M.H., Daily Totals 1993.4 2720.85 41.53 56.68

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-7A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Laborers 18.55 296.8 31 496 20.07 32.95
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Rake w/ Tractor 197.6 217.35
2 Chain Saws 44.4 48.85 10.08 11.09
24 M.H., Daily Totals 723.6 1057 30.15 44.04

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.63 33.61
2 Building Laborers 18.55 296.8 31 496
2 Equip. Oper. (med.) 24.1 385.6 38.45 615.2
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
1 Hyd. Crane, 25 Ton 508.2 559
1 F.E. Loader, T.M., 2.5 C.Y. 764 840.4
2 Dump Truck, 16 Ton 775.6 853.15 32 35.2
24 M.H., Daily Totals 3367.8 4403.75 20.63 33.61

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 18.95 31.66
4 Building Laborers 18.55 593.6 31 992
1 Air Compr., 250 C.F.M. 102.8 113.1
2 Air Tools & Accessories 29.6 32.55
2 50-Ft. Air Hoses, 1.5" Dia. 12.8 14.1 3.63 3.99
40 M.H., Daily Totals 903.2 1426.15 22.58 35.65

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
12 M.H., Daily Totals 267 431.6 22.25 35.97

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Roll. Compact., 2K Lbs. 79.2 87.1 6.6 7.26
12 M.H., Daily Totals 346.2 518.7 28.85 43.23

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 200 H. P. 832 915.2 69.33 76.27
12 M.H., Daily Totals 1099 1346.8 91.58 112.24

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 200 H. P. 832 915.2
1 Vibratory Roller, Towed 96 105.6 77.33 85.07
12 M.H., Daily Totals 1195 1452.4 99.58 121.04

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 200 H. P. 832 915.2
1 Sheepsft. Roller, Towed 107.4 118.15 78.28 86.11
12 M.H., Daily Totals 1206.4 1464.95 100.53 122.08

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10E
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Tandem Roller, 5 Ton 122.8 135.1 10.23 11.26
12 M.H., Daily Totals 389.8 566.7 32.48 47.23

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10F
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Tandem Roller, 10 Ton 223.8 246.2 18.65 20.52
12 M.H., Daily Totals 490.8 677.8 40.9 56.49

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10G
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Sheepsft Roll., 130 H.P. 512 563.2 42.67 46.93
12 M.H., Daily Totals 779 994.8 64.92 82.9

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10H
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Diaphr. Water Pump. 2" 19 20.9
1 20 ft. Suction Hose, 2" 4.4 4.85
2 50 Ft. Disch. Hoses, 2" 6.8 7.5 2.52 2.77
12 M.H., Daily Totals 297.2 464.85 24.77 38.74

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10I
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Diaphr. Water Pump, 4" 54 59.4
1 20 Ft. Suction Hose, 4" 11.4 12.55
2 50 Ft. Disch. Hoses, 4" 12.8 14.1 6.52 7.17
12 M.H., Daily Totals 345.2 517.65 28.77 43.14

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10J
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Centr. Water Pump, 3" 28.4 31.25
1 20 Ft. Suction Hose, 3" 7.4 8.15
2 50 Ft. Disch. Hoses, 3" 8.8 9.7 3.72 4.09
12 M.H., Daily Totals 311.6 480.7 25.97 40.06

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10K
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Centr. Water Pump, 6" 156.8 172.5
1 20 Ft. Suction Hose, 6" 19.4 21.35
2 50 Ft. Disch. Hoses, 6" 30.8 33.9 17.25 18.98
12 M.H., Daily Totals 474 659.35 39.5 54.95

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10L
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 75 H.P. 291.8 321 24.32 26.75
12 M.H., Daily Totals 558.8 752.6 46.57 62.72

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10M
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 300 H.P. 926.6 1019.25 77.22 84.94
12 M.H., Daily Totals 1193.6 1450.85 99.47 120.91

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10N
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, T.M., 1.5. C.Y 358 393.8 29.83 32.82
12 M.H., Daily Totals 625 825.4 52.08 68.79

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-100
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, T.M., 2.25. C.Y 459.6 505.55 38.3 42.13
12 M.H., Daily Totals 726.6 937.15 60.55 78.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10P
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, T.M., 2.5 C.Y 764 840.4 63.67 70.03
12 M.H., Daily Totals 1031 1272 85.92 106

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10Q
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, T.M., 5 C.Y 1062 1168.2 88.5 97.35
12 M.H., Daily Totals 1329 1599.8 110.75 133.32

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10R
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, W.M., 1 C.Y 235.2 258.7 19.6 21.56
12 M.H., Daily Totals 502.2 690.3 41.85 57.53

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10S
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, W.M., 1.5 C.Y 329 361.9 27.42 30.16
12 M.H., Daily Totals 596 793.5 49.67 66.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10T
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, W.M., 2.5 C.Y 502 552.2 41.83 46.02
12 M.H., Daily Totals 769 983.8 64.08 81.99

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10U
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 F.E. Loader, W.M., 5.5 C.Y 943.6 1037.95 78.63 86.5
12 M.H., Daily Totals 1210.6 1469.55 100.88 122.47

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10V
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 700 H.P. 2689 2957.9 224.08 246.49
12 M.H., Daily Totals 2956 3389.5 246.33 282.46

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10W
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 105 H.P. 414.8 456.3 224.08 246.49
12 M.H., Daily Totals 681.8 887.9 246.33 282.46

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10X
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Dozer, 410 H.P. 1204 1324.4 100.33 110.37
12 M.H., Daily Totals 1471 1756 122.58 146.34

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-10Y
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.25 35.97
0.5 Building Laborer 18.55 74.2 31 124
1 Vibratory Drum Roller 316.2 347.8 26.35 28.99
12 M.H., Daily Totals 583.2 779.4 48.6 64.96

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
16 M.H., Daily Totals 341.2 555.6 21.33 34.73

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Dozer, 200 H.P. 832 915.2 52 57.2
16 M.H., Daily Totals 1173.2 1470.8 73.33 91.93

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Dozer, 200 H.P. 832 915.2
1 Air Powered Tamper 13.8 15.2
1 Air. Compr. 365 C.F.M. 190.4 209.45
2 50 Ft. Air Hoses, 1.5" Dia. 12.8 14.1 65.56 72.12
16 M.H., Daily Totals 1390.2 1709.55 86.89 106.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Backhoe Loader, 48 H.P. 200.6 220.65 12.54 13.79
16 M.H., Daily Totals 541.8 776.25 33.87 48.52

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11K
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Trencher, 8'D., 16"W. 447.8 492.6 27.99 30.79
16 M.H., Daily Totals 789 1048.2 49.32 65.52

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11L
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Grader, 30,000 Lbs. 557.4 613.15 34.84 38.32
16 M.H., Daily Totals 898.6 1168.75 56.17 73.05

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-11M
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 21.33 34.73
1 Building Laborer 18.55 148.4 31 248
1 Backhoe Loader, 80 H.P. 282.4 310.65 17.65 19.42
16 M.H., Daily Totals 623.6 866.25 38.98 54.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
16 M.H., Daily Totals 361.6 576.8 22.6 36.05

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 1 C.Y. 575 632.5 35.94 39.53
16 M.H., Daily Totals 936.6 1209.3 58.54 75.58

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 1.5 C.Y. 724.6 797.05 45.29 49.82
16 M.H., Daily Totals 1086.2 1373.85 67.89 85.87

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 2 C.Y. 968.8 1065.7 60.55 66.61
16 M.H., Daily Totals 1330.4 1642.5 83.15 102.66

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 3.5 C.Y. 2157 2372.7 134.81 148.29
16 M.H., Daily Totals 2518.6 2949.5 157.41 184.34

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12E
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, .5 C.Y. 320.8 352.9 20.05 22.06
16 M.H., Daily Totals 682.4 929.7 42.65 58.11

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12F
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, .75 C.Y. 453.6 498.95 28.35 31.19
16 M.H., Daily Totals 815.2 1075.75 50.95 67.24

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12G
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, .5 C.Y. 398.6 438.45
1 Clamshell Bucket, .5 C.Y 46.2 50.8 27.8 30.58
16 M.H., Daily Totals 806.4 1066.05 50.4 66.63

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12H
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, 1 C.Y. 459.8 505.8
1 Clamshell Bucket, 1 C.Y 62 68.2 32.61 35.87
16 M.H., Daily Totals 883.4 1150.8 55.21 71.92

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12I
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, .75 C.Y. 424.4 466.85
1 Dragline Bucket, .75 C.Y 31 34.1 28.46 31.31
16 M.H., Daily Totals 817 1077.75 51.06 67.36

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12J
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Gradall, 3 Ton, .5 C.Y. 587.6 646.35 36.73 40.4
16 M.H., Daily Totals 949.2 1223.15 59.33 76.45

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12K
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Gradall, 3 Ton, 1 C.Y. 811.2 892.3 50.7 55.77
16 M.H., Daily Totals 1172.8 1469.1 73.3 91.82

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12L
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, .5 C.Y. 398.6 438.45
1 F.E. Attachment, .5 C.Y. 47.8 52.6 27.9 30.69
16 M.H., Daily Totals 808 1067.85 50.5 66.74

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12M
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, .75 C.Y. 424.4 466.85
1 F.E. Attachment, .75 C.Y. 90.6 99.65 32.19 35.41
16 M.H., Daily Totals 876.6 1143.3 54.79 71.46

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12N
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, 1 C.Y. 459.8 505.8
1 F.E. Attachment, 1 C.Y. 127.6 140.35 36.71 40.38
16 M.H., Daily Totals 949 1222.95 59.31 76.43

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12O
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, 1.5 C.Y. 694.2 763.6
1 F.E. Attachment, 1.5 C.Y. 143.4 157.75 52.35 57.59
16 M.H., Daily Totals 1199.2 1498.15 74.95 93.64
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-12P
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crawler Crane, 40 Ton 694.2 763.6
1 Dragline Bucket, 1.5 C.Y. 43.6 47.95 46.11 50.72
16 M.H., Daily Totals 1099.4 1388.35 68.71 86.77

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12Q
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 5/8 C.Y. 372.4 409.65 23.28 25.6
16 M.H., Daily Totals 734 986.45 45.88 61.65

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12R
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 1.5 C.Y. 724.6 797.05 45.29 49.82
16 M.H., Daily Totals 1086.2 1373.85 67.89 85.87

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12S
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Excavator, 2.5 C.Y. 1732 1905.2 108.25 119.08
16 M.H., Daily Totals 2093.6 2482 130.85 155.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12T
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crawler Crane, 75 Ton 817.6 899.35
1 F.E. Attachment, 3 C.Y. 265.4 291.95 67.69 74.46
16 M.H., Daily Totals 1444.6 1768.1 90.29 110.51

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-12V
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 22.6 36.05
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crawler Crane, 75 Ton 817.6 899.35
1 Dragline Bucket, 3 C.Y. 77.8 85.6 55.96 61.56
16 M.H., Daily Totals 1257 1561.75 78.56 97.61

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-13
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.99 32.91
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Crane, 25 ton 508.2 559 9.08 9.98
56 M.H., Daily Totals 1627.8 2402.2 29.07 42.89

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-14
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.64 32.52
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Backhoe Loader, 48 H.P. 200.6 220.65 4.18 4.6
48 M.H., Daily Totals 1143.4 1781.85 23.82 37.12

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-15
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equipment Oper. (med 24.1 192.8 38.45 307.6 20.65 33.53
0.5 Building Laborer 18.55 74.2 31 124
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
2 Dump Trucks, 16 Ton 775.6 853.15
1 Dozer, 200 H.P. 832 915.2 57.41 63.16
28 M.H., Daily Totals 2185.8 2707.15 78.06 96.69

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-16
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.27 32
2 Building Laborers 18.55 296.8 31 496
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6
1 Dump Truck, 16 Ton 387.8 426.6 12.12 13.33
32 M.H., Daily Totals 1004.6 1450.6 31.39 45.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-17
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 19.91 32.64
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6
1 Backhoe Loader, 48 H.P. 200.6 220.65
1 Dump Truck, 12 ton 315.6 347.15 16.13 17.74
32 M.H., Daily Totals 1153.4 1612.2 36.04 50.38

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-18
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.22 32.1
2 Building Laborers 18.55 296.8 31 496
1 Vibrating Compactor 45.2 49.7 1.88 2.07
24 M.H., Daily Totals 506.4 820.1 21.1 34.17

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-19
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Pile Driver Foreman 25.5 204 45.2 361.6 23.71 40.46
4 Pile Drivers 23.5 752 41.65 1332.8
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 40 Ton & Access. 694.2 763.6
60 L.F. Leads, 15K Ft. Lbs. 60 66
1 Hammer, 15K Ft. Lbs 275 302.5
1 Air Compr.,600 C.F.M. 269.6 296.55
2 50 Ft. Air Hoses, 3" Dia. 29.6 32.55 20.76 22.83
64 M.H., Daily Totals 2845.6 4050.8 44.47 63.29

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-20
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (out) 20.55 164.4 34.3 274.4 21.07 35.05
1 Skilled Worker 24.1 192.8 39.85 318.8
1 Building Laborer 18.55 148.4 31 248
24 M.H., Daily Totals 505.6 841.2 21.07 35.05

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-21
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (out) 20.55 164.4 34.3 274.4 21.62 35.73
1 Skilled Worker 24.1 192.8 39.85 318.8
1 Building Laborer 18.55 148.4 31 248
0.5 Equip. Oper. (crane) 24.95 99.8 39.8 159.2
0.5 S.P. Crane, 5 Ton 112.6 123.85 4.02 4.42
28 M.H., Daily Totals 718 1124.25 25.64 40.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-22
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (out) 20.55 164.4 34.3 274.4 21.84 36
1 Skilled Worker 24.1 192.8 39.85 318.8
1 Building Laborer 18.55 148.4 31 248
0.75 Equip. Oper. (crane) 24.95 149.7 39.8 238.8
0.75 S.P. Crane, 5 Ton 168.9 185.8 5.63 6.19
30 M.H., Daily Totals 824.2 1265.8 27.47 42.19

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-23
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 18.95 31.66
4 Building Laborers 18.55 593.6 31 992
1 Drill Rig 417.6 459.35
1 Light truck, 3 Ton 155.8 171.4 14.34 15.77
40 M.H., Daily Totals 1331.4 1897.15 33.29 47.43

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-24
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Cement Finisher 23.05 184.4 36.7 293.6 21.65 35.57
1 Building Laborer 18.55 148.4 31 248
1 Carpenter 23.35 186.8 39 312
24 M.H., Daily Totals 519.6 853.6 21.65 35.57

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-25
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 20.25 33.33
7 Laborers 18.55 1038.8 31 1736
3 Equip. Oper. (med) 24.1 578.4 38.45 922.8
1 Asphalt Paver, 130 H.P 1145 1259.5
1 Tandem Roller, 10 Ton 223.8 246.2
1 Roller, Pneumatic Wheel 231.4 254.55 18.18 20
88 M.H., Daily Totals 3381.8 4693.45 38.43 53.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-25B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 20.57 33.76
7 Laborers 18.55 1038.8 31 1736
4 Equip. Oper. (medium) 24.1 771.2 38.45 1230.4
1 Asphalt Paver, 130 H.P 1145 1259.5
2 Rollers, Steel Wheel 447.6 492.35
1 Roller, Pneumatic Wheel 231.4 254.55 19 20.9
96 M.H., Daily Totals 3798.4 5247.2 39.57 54.66

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-26
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.81 34.64
6 Building Laborers 18.55 890.4 31 1488
2 Equip. Oper. (med.) 24.1 385.6 38.45 615.2
1 Rodman (reinf.) 25.85 206.8 47.1 376.8
1 Cement Finisher 23.05 184.4 36.7 293.6
1 Grader, 30,000 Lbs 557.4 613.15
1 Paving Mach. & Equip. 1238 1361.8 20.4 22.44
88 M.H., Daily Totals 3627 5022.95 41.21 57.08

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-27
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.05 31.83
3 Building Laborers 18.55 445.2 31 744
1 Berm Machine 62 68.2 1.94 2.13
32 M.H., Daily Totals 671.6 1086.6 20.99 33.96

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-28
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 21.75 36.33
1 Building Laborers 18.55 148.4 31 248
24 M.H., Daily Totals 522 872 21.75 36.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-29
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.99 32.91
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Gradall, 3 Ton, 1/2 C.Y 587.6 646.35 10.49 11.54
56 M.H., Daily Totals 1707.2 2489.55 30.48 44.45
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-30
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 21 33.95
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
1 Hyd. Excavator, 1.5 C.Y. 724.6 797.05
2 Dump Truck, 16 Ton 775.6 853.15 62.51 68.76
24 M.H., Daily Totals 2004.2 2465 83.51 102.71

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-31
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.91 33.26
3 Building Laborers 18.55 445.2 31 744
1 Carpenter 23.35 186.8 39 312
102.8 113.1
9.8 10.8
2 50 Ft. Air Hoses, 1.5" Dia. 12.8 14.1 3.14 3.45
40 M.H., Daily Totals 921.8 1468.4 23.05 36.71

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-32
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Highway Laborer 18.55 148.4 31 248 22.71 36.59
3 Equip. Oper. (med.) 24.1 578.4 38.45 922.8
1 Grader, 30,000 Lbs. 557.4 613.15
1 Tandem Roller, 10 Ton 223.8 246.2
1 Dozer, 200 H.P. 832 915.2 50.41 55.45
32 M.H., Daily Totals 2340 2945.35 73.12 92.04

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-32A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Laborer 18.55 148.4 31 248 22.25 35.97
2 Equip. Oper. (medium) 24.1 385.6 38.45 615.2
1 Grader, 30,000 Lbs. 557.4 613.15
1 Roller, Vibratory, 29,000 Lbs 366 402.6 38.48 42.32
24 M.H., Daily Totals 1457.4 1878.95 60.73 78.29

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-32B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Laborer 18.55 148.4 31 248 22.25 35.97
2 Equip. Oper. (medium) 24.1 385.6 38.45 615.2
1 Dozer, 200 H.P. 832 915.2
1 Roller, Vibratory, 29,000 Lbs 366 402.6 49.92 54.91
24 M.H., Daily Totals 1732 2181 72.17 90.88

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-32C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 21.66 35.28
2 Laborers 18.55 296.8 31 496
3 Equip. Oper. (medium) 24.1 578.4 38.45 922.8
1 Grader, 30,000 Lbs. 557.4 613.15
1 Roller, Steel Wheel 223.8 246.2
1 Dozer, 200 H.P. 832 915.2 33.61 36.97
48 M.H., Daily Totals 2652.8 3467.75 55.27 72.25

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
14 M.H., Daily Totals 315.2 508.5 22.51 36.32

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 Scraper, Towed, 7 C.Y. 65.8 72.4
1 Dozer, 300 H.P. 926.6 1019.25
0.25 Dozer, 300 H.P. 231.65 254.8 87.43 96.18
14 M.H., Daily Totals 1539.25 1854.95 109.94 132.5

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 Scraper, Towed, 10 C.Y. 180.4 198.45
1 Dozer, 300 H.P. 926.6 1019.25
0.25 Dozer, 300 H.P. 231.65 254.8 95.62 105.18
14 M.H., Daily Totals 1653.85 1981 118.13 141.5

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 Scraper, Towed, 12 C.Y. 180.4 198.45
1 Dozer, 300 H.P. 926.6 1019.25
0.25 Dozer, 300 H.P. 231.65 254.8 95.62 105.18
14 M.H., Daily Totals 1653.85 1981 118.13 141.5

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 S.P. Scraper, 14 C.Y. 1460 1606
0.25 Dozer, 300 H.P. 231.65 254.8 120.83 132.92
14 M.H., Daily Totals 2006.85 2369.3 143.34 169.24
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-33E
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 S.P. Scraper, 24 C.Y. 1747 1921.7
0.25 Dozer, 300 H.P. 231.65 254.8 141.33 155.47
14 M.H., Daily Totals 2293.85 2685 163.84 191.79

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33F
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 Elev. Scraper, 11 C.Y. 623.2 685.5
0.25 Dozer, 300 H.P. 231.65 254.8 61.06 67.17
14 M.H., Daily Totals 1170.05 1448.8 83.57 103.49

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-33G
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 22.51 36.32
0.5 Building Laborer 18.55 74.2 31 124
0.25 Equip. Oper. (med.) 24.1 48.2 38.45 76.9
1 Elev. Scraper, 20 C.Y. 847.2 931.9
0.25 Dozer, 300 H.P. 231.65 254.8 77.06 84.77
14 M.H., Daily Totals 1394.05 1695.2 99.57 121.09

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
8 M.H., Daily Totals 155.6 253.6 19.45 31.7

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Dump Truck, 12 Ton 315.6 347.15 39.45 43.4
8 M.H., Daily Totals 471.2 600.75 58.9 75.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Dump Truck, 16 Ton 387.8 426.6 48.48 53.32
8 M.H., Daily Totals 543.4 680.2 67.93 85.02

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck Tractor, 40 Ton 365.6 402.15
1 Dump Trailer, 16.5 C.Y. 114.8 126.3 60.05 66.06
8 M.H., Daily Totals 636 782.05 79.5 97.76
Bare Costs Incl. Subs O&P Cost per Manhour
Crew B-34D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck Tractor, 40 Ton 365.6 402.15
1 Dump Trailer, 20 C.Y. 115.8 127.4 60.18 66.19
8 M.H., Daily Totals 637 783.15 79.63 97.89

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34E
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, Off Hwy., 25 Ton 580.6 638.65 72.58 79.83
8 M.H., Daily Totals 736.2 892.25 92.03 111.53

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34F
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, Off Hwy., 22 C.Y. 908 998.8 113.5 124.85
8 M.H., Daily Totals 1063.6 1252.4 132.95 156.55

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34G
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, Off Hwy., 34 C.Y. 1155 1270.5 144.38 158.81
8 M.H., Daily Totals 1310.6 1524.1 163.83 190.51

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34H
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, Off Hwy., 42 C.Y. 1446 1590.6 180.75 198.83
8 M.H., Daily Totals 1601.6 1844.2 200.2 230.53

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34J
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, Off Hwy., 60 C.Y. 1962 2158.2 245.25 269.78
8 M.H., Daily Totals 2117.6 2411.8 264.7 301.48

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-34K
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck Tractor, 240 H.P. 463.4 509.75
1 Low Bed Trailer 274.4 301.85 92.23 101.45
8 M.H., Daily Totals 893.4 1065.2 111.68 133.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-35
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Laborer Foreman (out) 20.55 164.4 34.3 274.4 22.63 36.69
1 Skilled Worker 24.1 192.8 39.85 318.8
1 Welder (plumber) 27.4 219.2 42.9 343.2
1 Laborer 18.55 148.4 31 248
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Electric Welding Mach. 45.8 50.4
1 Hyd. Excavator, .75 C.Y. 453.6 498.95 10.4 11.44
48 M.H., Daily Totals 1585.8 2310.55 33.03 48.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-36
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 21.17 34.64
2 Highway Laborers 18.55 296.8 31 496
2 Equip. Oper. (med.) 24.1 385.6 38.45 615.2
1 Dozer, 200 H.P 832 915.2
1 Aggregate Spreader 62 68.2
1 Tandem Roller, 10 Ton 223.8 246.2 27.95 30.74
40 M.H., Daily Totals 1964.6 2615.2 49.12 65.38

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-36A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 22.01 35.73
2 Laborers 18.55 296.8 31 496
4 Equip. Oper. (medium) 24.1 771.2 38.45 1230.4
1 Dozer, 200 H.P 832 915.2
1 Aggregate Spreader 62 68.2
1 Roller, Steel Wheel 223.8 246.2
1 Roller, Pneumatic Wheel 231.4 254.55 24.09 26.5
56 M.H., Daily Totals 2581.6 3484.95 46.1 62.23

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-37
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.64 32.52
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Tandem Roller, 5 Ton 122.8 135.1 2.56 2.81
48 M.H., Daily Totals 1065.6 1696.3 22.2 35.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-38
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.97 34.32
2 Building Laborers 18.55 296.8 31 496
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Equip. Oper. (medium) 24.1 192.8 38.45 307.6
1 Backhoe Loader, 48 H.P. 200.6 220.65
1 Demol. Hammer, (1000lb) 353.6 388.95
1 F.E. Loader (170 H.P.) 586.4 645.05
1 Pavt. Rem. Bucket 40.2 44.2 29.52 32.47
40 M.H., Daily Totals 2019.6 2671.65 50.49 66.79

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-39
Crew B-39
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.64 32.52
4 Building Laborers 18.55 593.6 31 992
1 Equipment Oper. (light 23.1 184.8 36.85 294.8
1 Air Compr., 250 C.F.M. 102.8 113.1
2 Air Tools & Accessories 29.6 32.55
2 50 Ft. Air Hoses, 1.5" Dia. 12.8 14.1 3.03 3.33
48 M.H., Daily Totals 1088 1720.95 22.67 35.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-40
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Pile Driver Foreman 25.5 204 45.2 361.6 23.71 40.46
4 Pile Drivers 23.5 752 41.65 1332.8
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 40 Ton 694.2 763.6
1 Vibratory Hammer & Gen. 1119 1230.9 28.33 31.16
64 M.H., Daily Totals 3330.4 4584.1 52.04 71.62

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-41
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.28 32.06
4 Building Laborers 18.55 593.6 31 992
0.25 Equip. Oper. (crane) 24.95 49.9 39.8 79.6
0.25 Equip. Oper. Oiler 20.25 40.5 32.3 64.6
0.25 Crawler Crane, 40 Ton 173.55 190.9 3.94 4.34
44 M.H., Daily Totals 1021.95 1601.5 23.22 36.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-42
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.74 34.91
4 Building Laborers 18.55 593.6 31 992
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Welder 26 208 48.85 390.8
1 Hyd. Crane, 25 Ton 508.2 559
1 Gas Welding Machine 73.4 80.75
1 Horz. Boring Csg. Mch. 446.2 490.8 16.06 17.67
64 M.H., Daily Totals 2355.4 3364.55 36.8 52.58

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-43
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.23 33.23
3 Building Laborers 18.55 445.2 31 744
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Drill Rig & Augers 26 1569 1725.9 32.69 35.96
48 M.H., Daily Totals 2540.2 3321.1 52.92 69.19

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-44
Crew B-44
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Pile Driver Foreman 25.5 204 45.2 361.6 23.49 40.3
4 Pile Drivers 23.5 752 41.65 1332.8
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
1 Building Laborer 18.55 148.4 31 248
1 Crane, 40 Ton, & Access. 694.2 763.6
45 L.F. Leads, 15K Ft. Lbs. 45 49.5 11.55 12.71
64 M.H., Daily Totals 2242.8 3392.3 35.04 53.01

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-45
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 21.78 35.08
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6
1 Dist. Tank Truck, 3K Gal. 326 358.6
1 Tractor, 4 x 2, 250 H.P 329.6 362.55 40.98 45.07
16 M.H., Daily Totals 1004 1282.35 62.76 80.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-46
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Pile Driver Foreman 25.5 204 45.2 361.6 21.36 36.92
2 Pile Drivers 23.5 376 41.65 666.4
3 Building Laborers 18.55 445.2 31 744
1 Chain Saw, 36" Long 45 49.5 0.94 1.03
48 M.H., Daily Totals 1070.2 1821.5 22.3 37.95

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-47
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Blast Foreman 20.55 164.4 34.3 274.4 20.73 34.05
1 Driller 18.55 148.4 31 248
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Crawler Type Drill, 4" 229 251.9
1 Air Compr., 600 C.F.M. 269.6 296.55
2 50 Ft. Air Hoses, 3" Dia. 29.6 32.55 22.01 24.21
24 M.H., Daily Totals 1025.8 1398.2 42.74 58.26

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-47A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Drilling Foreman 20.55 164.4 34.3 274.4 21.92 35.47
1 Equip. Oper. (heavy) 24.95 199.6 39.8 318.4
1 Oiler 20.25 162 32.3 258.4
1 Quarry Drill 478.8 526.7 19.95 21.95
24 M.H., Daily Totals 1004.8 1377.9 41.87 57.42

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-48
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor foreman (outsid 20.55 164.4 34.3 274.4 20.64 33.75
3 Building laborers 18.55 445.2 31 744
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Centr. Water Pump, 6" 156.8 172.5
1 20 Ft. Suction Hose, 6" 19.4 21.35
1 50 Ft. Disch. Hose, 6" 15.4 16.95
1 Drill Rig & Augers 1569 1725.9 31.44 34.58
56 M.H., Daily Totals 2916.6 3826.7 52.08 68.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-49
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor foreman (outsid 20.55 164.4 34.3 274.4 21.52 35.6
3 Building laborers 18.55 445.2 31 744
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
2 Equip. Oper. Oilers 20.25 324 32.3 516.8
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
2 Pile Drivers 23.5 376 41.65 666.4
1 Hyd. Crane, 25 Ton 508.2 559
1 Centr. Water Pump, 6" 156.8 172.5
1 20 Ft. Suction Hose, 6" 19.4 21.35
1 50 Ft. Disch. Hose, 6" 15.4 16.95
1 Drill Rig & Augers 1569 1725.9 25.78 28.36
88 M.H., Daily Totals 4162.4 5628.9 47.3 63.96

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-50
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Pile Driver foreman 20.55 408 45.2 723.2 22.7 38.94
6 Pile Drivers 23.5 1128 41.65 1999.2
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
3 Building Laborers 18.55 445.2 31 744
1 Crane, 40 Ton 694.2 763.6
60 L.F. Leads, 15K Ft. Lbs 60 66
1 Hammer, 15K Ft. Lbs. 275 302.5
1 Air Compr., 600 C.F.M. 269.6 296.55
2 50 Ft. Air Hoses, 3" Dia. 29.6 32.55
1 Chain Saw, 36" Long 45 49.5 12.26 13.49
112 M.H., Daily Totals 3915.8 5872.3 34.96 52.43

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-51
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 18.98 31.58
4 Building Laborers 18.55 593.6 31 992
1 Truck Driver (light) 19.15 202.8 31.2 249.6
1 Light Truck, 1.5 Ton 186.8 168.75 3.2 3.52
48 M.H., Daily Totals 445.2 1684.75 22.18 35.1
184.4
103.4 Incl. Subs O&P Cost per Manhour
Crew B-52
Hr. 96.4 Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman 25.35 202.8 42.35 338.8 21.77 36.26
1 Carpenter 23.35 186.8 39 312
3 Building Laborers 18.55 445.2 31 744
1 Cement Finisher 23.05 184.4 36.7 293.6
0.5 Rodman (reinf.) 25.85 103.4 47.1 188.4
0.5 Equip. Oper. (med.) 24.1 96.4 38.45 153.8
0.5 F.E. Ldr. T.M., 2.5 C.Y. 382 420.2 6.82 7.5
56 M.H., Daily Totals 1601 2450.8 28.59 43.76

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-53
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8 23.1 36.85
1 Trencher, Chain, 12 H.P. 79 86.9 9.88 10.86
8 M.H., Daily Totals 263.8 381.7 32.98 47.71

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-54
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8 23.1 36.85
1 Trencher, Chain, 40 H.P. 182.6 200.85 22.83 25.11
8 M.H., Daily Totals 367.4 495.65 45.93 61.96

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-55
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 18.75 36.85
1 Truck Driver (light) 19.15 153.2 31.2 249.6 10.86
1 Flathed Truck w/ Auger 417.6 459.35
1 Truck, 3 Ton 155.8 171.4 23.89 26.28
24 M.H., Daily Totals 1023.4 1376.35 42.64 73.99

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-56
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborers 18.55 148.4 31 248 20.83 33.92
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Crawler Type Drill, 4" 229 251.9
1 Air Compr., 600 C.F.M. 269.6 296.55
1 50 Ft. Air hose. 3" Dia. 14.8 16.3 32.09 35.3
16 M.H., Daily Totals 846.6 1107.55 52.92 69.22

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-57
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.99 34.21
2 Building Laborers 18.55 296.8 31 496
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Power Shovel, 1 C.Y. 459.8 505.8
1 Clamshell Bucket, 1 C.Y 62 68.2
1 Centr. Water Pump. 6" 156.8 172.5
1 20 Ft. Suction Hose, 6" 19.4 21.35
20 50 Ft. Disch. Hoses, 6" 308 338.8 20.96 23.05
48 M.H., Daily Totals 2013.6 2748.65 41.95 57.26

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-58
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Building Laborers 18.55 296.8 31 496 20.07 32.95
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Backhoe Loader, 48 H.P. 200.6 220.65
1 Small Helicopter 3180 3498 140.86 154.94
24 M.H., Daily Totals 3862.2 4509.45 160.93 187.89

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-59
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6 19.45 31.7
1 Truck, 30 Ton 285.4 313.95
1 Water Tank, 5000 Gal. 195 214.5 60.05 66.06
8 M.H., Daily Totals 636 782.05 79.5 97.76

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-60
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 21.29 34.59
2 Building Laborers 18.55 296.8 31 496
1 Equi[. Oper. (crane) 24.95 199.6 39.8 318.4
2 Equip. Oper. (light) 23.1 369.6 36.85 589.6
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crawler Crane, 40 Ton 694.2 763.6
45 L.F. Leads, 15K Ft. Lbs. 45 49.5
1 Backhoe Loader, 48 H.P. 200.6 220.65 16.78 18.46
56 M.H., Daily Totals 2132.2 2970.55 38.07 53.05

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-74
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 21.8 35.31
1 Highway Laborer 18.55 148.4 31 248
4 Equip. Oper. (med.) 24.1 771.2 38.45 1230.4
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
1 Motor Grader, 30,000 20.25 557.4 613.15
1 Grader Attach., Ripper 54 59.4
2 Stabilizers, 310 H.P 1270.8 1397.9
1 Flatbed Truck, 3 Ton 155.8 171.4
1 Chem. Spreader, Towed 94.8 104.3
1 Vibr. Roller, 29,000 Lb. 366 402.6
1 Water Tank 5000 Gal. 195 214.5
1 Truck, 30 Ton 285.4 313.95 46.55 51.21
64 M.H., Daily Totals 4374.4 5537.2 68.35 86.52

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-75
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 22.14 35.83
1 Highway Laborer 18.55 148.4 31 248
4 Equip. Oper. (med.) 24.1 771.2 38.45 1230.4
1 Truck Drivers (heavy) 19.45 155.6 31.7 253.6
1 Motor Grader, 30,000 Lb. 557.4 613.15
1 Grader Attach., Ripper 54 59.4
2 Stabilizers, 310 H.P 1270.8 1397.9
1 Dist. Truck, 3000 Gal. 326 358.6
1 Vibr. Roller, 29,000 Lb. 366 402.6 45.97 50.56
56 M.H., Daily Totals 3813.8 4838.05 68.11 86.39

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-76
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Dock Builder Foreman 25.5 204 45.2 361.6 23.68 40.59
5 Dock builders 23.5 940 41.65 1666
2 Equip. Oper. (crane) 24.95 399.2 39.8 636.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crawler Crane, 50 Ton 802.2 882.4
1 Barge, 400 Ton 405.6 446.15
1 Hammer, 15K. Ft. Lbs. 275 302.5
60 L.F. Leads, 15K. Ft. Lbs. 60 66
1 Air Compr., 600 C.F.M 269.6 296.55
2 50 Ft. Air Hoses, 3" Dia. 29.6 32.55 25.58 28.14
72 M.H., Daily Totals 3547.2 4948.95 49.26 68.73

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-77
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 19.07 31.7
3 Laborers 18.55 445.2 31 744
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 Crack Cleaner, 25 H.P. 75 82.5
1 Crack Filler, Trailer Mtd. 133.6 146.95
1 Flatbed Truck, 3 Ton 155.8 171.4 9.11 10.02
40 M.H., Daily Totals 1127.2 1668.85 28.18 41.72

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-78
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 18.98 31.58
4 Laborers 18.55 593.6 31 992
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 Paint Striper, S.P. 190 209
1 Flatbed Truck, 3 Ton 155.8 171.4
1 Pickup Truck, 3/4 Ton 113.4 124.75 9.57 10.52
48 M.H., Daily Totals 1370.4 2021.15 28.55 42.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-79
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 19.07 31.7
3 Laborers 18.55 445.2 31 744
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 218.6 240.45
1 Flatbed Truck, 3 Ton 155.8 171.4
2 Pickup Truck, 3/4 Ton 226.8 249.5 15.03 16.53
40 M.H., Daily Totals 1364 1929.35 34.1 48.23

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-80
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 20.34 33.34
1 Laborers 18.55 148.4 31 248
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Flatbed Truck, 3 Ton 155.8 171.4
1 Post Driver, T.M. 271 298.1 13.34 14.67
32 M.H., Daily Totals 1077.6 1536.3 33.68 48.01

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-81
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Laborers 18.55 148.4 31 248 20.7 33.72
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6
1 Hydromulcher, T.M. 253.6 278.95
1 Tractor Truck, 4x2 285.4 313.95 22.46 24.7
24 M.H., Daily Totals 1035.8 1402.1 43.16 58.42

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-82
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Highway Laborer 18.55 148.4 31 248 20.83 33.92
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Horiz. Borer, 6 H.P. 39.8 43.8 2.49 2.74
16 M.H., Daily Totals 373 586.6 23.32 36.66

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-83
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Tugboat Captain 24.1 192.8 38.45 307.6 21.33 34.73
1 Tugboat Hand 189.55 148.4 31 248
1 Tugboat, 250 H.P 482.2 530.4 30.14 33.15
16 M.H., Daily Totals 823.4 1086 51.47 67.88

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-84
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 24.1 38.45
1 Rotary Mower/Tractor 232.6 255.85 29.08 31.98
8 M.H., Daily Totals 425.4 563.45 53.18 70.43

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-85
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Highway Laborers 18.55 445.2 31 744 19.84 32.63
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
1 Truck Driver (heavy) 19.45 155.6 31.7 253.6
1 Aerial Lift Truck 544 598.4
1 Brush Chipper, 130 H.P. 188.6 207.45
1 Pruning Saw, Rotary 18 19.8 18.77 20.64
40 M.H., Daily Totals 1544.2 2130.85 38.61 53.27

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-86
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 24.1 38.45
1 Stump Chipper, S.P 155.4 170.95 19.43 21.37
8 M.H., Daily Totals 348.2 478.55 43.53 59.82

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-86A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (medium) 24.1 192.8 38.45 307.6 24.1 38.45
1 Grader, 30,000 Lbs. 557.4 613.15 69.68 76.64
8 M.H., Daily Totals 750.2 920.75 93.78 115.09

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-86B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (medium) 24.1 192.8 38.45 307.6 24.1 38.45
1 Dozer, 200 H.P 832 915.2 104 114.4
8 M.H., Daily Totals 1024.8 1222.8 128.1 152.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-87
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Common Laborer 18.55 148.4 31 248 22.99 36.96
4 Equip. Oper. (med.) 24.1 771.2 38.45 1230.4
2 Feller Bunchers, 50 H.P 664.8 731.3
1 Long Chipper, 22" Tree 1921 2113.1
1 Dozer, 105 H.P 291.8 321
1 Chainsaw, Gas, 36" Long 45 49.5 73.07 80.37
40 M.H., Daily Totals 3842.2 4693.3 96.06 117.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-88
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Common Laborer 18.55 148.4 31 248 23.31 37.39
6 Equip. Oper. (med.) 24.1 1156.8 38.45 1845.6
2 Feller Bunchers, 50 H.P 664.8 731.3
1 Long Chipper, 22" Tree 1921 2113.1
2 Long Skidders, 50 H.P. 679.2 747.1
1 Dozer, 105 H.P 291.8 321
1 Chainsaw, Gas, 36" Long 45 49.5 64.32 70.75
56 M.H., Daily Totals 4907 6055.6 87.63 108.14

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-89
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8 21.13 34.03
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 Truck, Stake Body, 3 Ton 155.8 171.4
1 Concrete Saw 98.8 108.7
1 Water Tank, 65 Gal. 7 7.7 16.35 17.99
16 M.H., Daily Totals 599.6 832.2 37.48 52.02

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-89A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Skilled Worker 24.1 192.8 39.85 318.8 21.33 35.42
1 Laborer 18.55 148.4 31 248
1 Core Drill (large) 52.2 57.4 3.26 3.59
16 M.H., Daily Totals 393.4 624.2 24.59 39.01

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-90
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.16 33.05
3 Highway Laborers 18.55 445.2 31 744
2 Equip. Oper. (light) 23.1 369.6 36.85 589.6
2 Truck Drivers (heavy) 19.45 311.2 31.7 507.2
1 Road Mixer, 310 H.P. 923.4 1015.75
1 Dist. Truck, 2000 Gal. 297.8 327.6 19.08 20.99
64 M.H., Daily Totals 2511.6 3458.55 39.24 54.04

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-90A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 22.01 35.73
2 Laborers 18.55 296.8 31 496
4 Equip. Oper. (medium) 24.1 771.2 38.45 1230.4
2 Graders, 30,000 Lbs. 1114.8 1226.3
1 Roller, Steel Wheel 223.8 246.2
1 Roller, Pnuematic Wheel 231.4 254.55 28.04 30.84
56 M.H., Daily Totals 2802.4 3727.85 50.05 66.57

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-90B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman 20.55 164.4 34.3 274.4 21.66 35.28
2 Laborers 18.55 296.8 31 496
3 Equip. Oper. (medium) 24.1 578.4 38.45 922.8
1 Roller, Steel Wheel 223.8 246.2
1 Roller, Pneumatic Wheel 231.4 254.55
1 Road Mixer, 310 H.P. 923.4 1015.75 28.72 31.59
48 M.H., Daily Totals 2418.2 3209.7 50.38 66.87

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-91
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 21.69 35.23
2 Highway Laborers 18.55 296.8 31 496
4 Equip. Oper. (med.) 24.1 771.2 31.7 1230.4
1 Truck Driver (heavy) 19.45 155.6 253.6
1 Dist. Truck, 3000 Gal. 326 358.6
1 Aggreg. Spreader, S.P. 593.2 652.5
1 Roller, Pneu. Tire, 12 Ton 231.4 254.55
1 Roller, Steel, 10 Ton 223.8 246.2 21.48 23.62
64 M.H., Daily Totals 2762.4 3766.25 43.17 58.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-92
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.05 31.83
3 Highway Laborers 18.55 445.2 31 744
1 Crack Cleaner, 25 H.P. 75 82.5
1 Air Compressor 68.4 75.25
1 Tar Kettle, T.M. 18.2 20
1 Flatbed Truck, 3 Ton 155.8 171.4 9.92 10.91
32 M.H., Daily Totals 927 1367.55 28.97 42.74

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-93
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6 24.1 38.45
1 Feller Buncher, 50 H.P. 332.4 365.65 41.55 45.71
8 M.H., Daily Totals 525.2 673.25 65.65 84.16

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-94
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31
8 M.H., Daily Totals 148.4 248 18.55 31

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-94A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31
1 Diaph. Water Pump, 2" 19 20.9
1 20 Ft. Suction Hose, 2" 4.4 4.85
2 50 Ft. Disch. Hoses, 2" 6.8 7.5 3.78 4.15
8 M.H., Daily Totals 178.6 281.25 22.33 35.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-94B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31
1 Diaph. Water Pump, 4" 54 59.4
1 20 Ft. Suction Hose, 4" 11.4 12.55
2 50 Ft. Disch. Hoses, 4" 12.8 14.1 9.78 10.75
8 M.H., Daily Totals 226.6 334.05 28.33 41.75

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-94C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31
1 Centr. Water Pump, 3" 28.4 31.25
1 20 Ft. Suction Hose, 3" 7.4 8.15
2 50 Ft. Disch. Hoses, 3" 8.8 9.7 5.58 6.13
8 M.H., Daily Totals 193 297.1 24.13 37.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-94D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 18.55 31
1 Centr. Water Pump, 6" 156.8 172.5
1 20 Ft. Suction Hose, 6" 19.4 21.35
2 50 Ft. Disch. Hoses, 6" 30.8 33.9 25.88 28.46
8 M.H., Daily Totals 355.4 475.75 44.43 59.46

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-95
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 21.75 35.4
1 Building Laborer 18.55 148.4 31 248
16 M.H., Daily Totals 348 566.4 21.75 35.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-95A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 21.75 35.4
1 Building Laborer 18.55 148.4 31 248
1 Hyd. Excavator, 5/8 C.Y. 372.4 409.65 23.28 25.6
16 M.H., Daily Totals 720.4 976.05 45.03 61

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-95B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 21.75 35.4
1 Building Laborer 18.55 148.4 31 248
1 Hyd. Excavator, 1.5 C.Y. 724.6 797.05 45.29 49.82
16 M.H., Daily Totals 1072.6 1363.45 67.04 85.22

Bare Costs Incl. Subs O&P Cost per Manhour


Crew B-95C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4 21.75 35.4
1 Building Laborer 18.55 148.4 31 248
1 Hyd. Excavator, 2.5 C.Y. 1732 1905.2 108.25 119.08
16 M.H., Daily Totals 2080 2471.6 130 154.48
Bare Costs Incl. Subs O&P Cost per Manhour
Crew C-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Carpenters 23.35 560.4 39 936 22.15 37
1 Building Laborer 18.55 148.4 31 248
3 Power Tools 24.6 27.05 0.77 0.85
32 M.H., Daily Totals 733.4 1211.05 22.92 37.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-1A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenters 23.35 186.8 39 312 23.35 39
1 Circular Saw, 7" 8.2 9 1.03 1.13
8 M.H., Daily Totals 195 321 24.38 40.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman (ou 25.35 202.8 42.35 338.8 22.88 38.23
4 Carpenters 23.35 747.2 39 1248
1 Building Laborers 18.55 148.4 31 248
4 Power Tools 32.8 36.1 0.68 0.75
48 M.H., Daily Totals 1131.2 1870.9 23.56 38.98

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Rodman Foreman 27.85 222.8 50.75 406 23.93 42.25
4 Rodmen (reinf.) 25.85 827.2 47.1 1507.2
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
2 Building Laborers 18.55 296.8 31 496
3 Stressing Equipment 36.6 40.25
0.5 Grouting Equipment 121.4 133.55 2.47 2.72
64 M.H., Daily Totals 1689.6 2877.8 26.4 44.97

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Rodman Foreman 27.85 222.8 50.75 406 26.35 48.01
3 Rodmen (reinf.) 25.85 620.4 47.1 1130.4
3 Stressing Equipment 36.6 40.25 1.14 1.26
32 M.H., Daily Totals 879.8 1576.65 27.49 49.27

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Rodman Foreman 27.85 222.8 50.75 406 25.21 44.46
4 Rodmen (reinf.) 25.85 827.2 47.1 1507.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Crane, 25 Ton 508.2 559 9.08 9.98
56 M.H., Daily Totals 1919.8 3049 34.29 54.44

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.63 32.5
4 Building Laborers 18.55 593.6 31 992
1 Cement Finisher 23.05 184.4 36.7 293.6
2 Gas Engine Vibrators 64.8 71.3 1.35 1.49
48 M.H., Daily Totals 1007.2 1631.3 20.98 33.99

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.06 33.06
5 Building Laborers 18.55 742 31 1240
1 Cement Finisher 23.05 184.4 36.7 293.6
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
2 Gas Engine Vibrators 64.8 71.3
1 Concrete Bucket, 1 C.Y. 19.2 21.1
1 Hyd. Crane, 55 Ton 710 781 12.41 13.65
64 M.H., Daily Totals 2077.6 2989 32.47 46.71

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.91 34.16
3 Building Laborers 18.55 445.2 31 744
2 Cement Finisher 23.05 368.8 36.7 587.2
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
1 Concrete Pump (small) 542.6 596.85 9.69 10.66
56 M.H., Daily Totals 1713.8 2510.05 30.6 44.82

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-8A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.38 33.45
3 Building Laborers 18.55 445.2 31 744
2 Cement Finisher 23.05 368.8 36.7 587.2
48 M.H., Daily Totals 978.4 1605.6 20.38 33.45

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Cement Finisher 23.05 184.4 36.7 293.6 23.05 36.7
1 Gas Finishing Mach. 37.2 40.9 4.65 5.12
8 M.H., Daily Totals 221.6 334.5 27.7 41.82

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Building Laborer 18.55 148.4 31 248 21.55 34.8
2 Cement Finishers 23.05 368.8 36.7 587.2
2 Gas Finishing Mach. 74.4 81.85 3.1 3.41
24 M.H., Daily Totals 591.6 917.05 24.65 38.21

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 25.47 46.42
6 Struc. Steel Workers 26 1248 48.85 2344.8
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Truck Crane, 150 Ton 1441 1585.1 20.01 22.02
72 M.H., Daily Totals 3274.6 4927.5 45.48 68.44

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman (ou 25.35 202.8 42.35 338.8 23.15 38.36
3 Carpenters 23.35 560.4 39 936
1 Building Laborer 18.55 148.4 31 248
1 Equip. Oper. Oiler 24.95 199.6 39.8 318.4
1 Hyd. Crane, 12 Ton 375.4 412.95 7.82 8.6
48 M.H., Daily Totals 1486.6 2254.15 30.97 46.96

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-13
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Worker 26 208 48.85 390.8 25.12 45.57
1 Welder 26 208 48.85 390.8
1 Carpenter 23.35 186.8 39 312
1 Gas Welding Machine 73.4 80.75 3.06 3.36
48 M.H., Daily Totals 676.2 1174.35 28.18 48.93

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-14
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman (ou 25.35 202.8 42.35 338.8 22.83 38.63
5 Carpenters 23.35 934 39 1560
4 Building Laborers 18.55 593.6 31 992
4 Rodmen (reinf.) 25.85 827.2 47.1 1507.2
2 Cement Finishers 23.05 368.8 36.7 587.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 80 Ton, & Tools 962.4 1058.65
3 Power Tools 24.6 27.05
2 Gas Finishing Mach. 74.4 81.85 7.37 8.11
144 M.H., Daily Totals 4349.4 6729.55 30.2 46.74

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-15
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman (ou 25.35 202.8 42.35 338.8 22.18 37.09
2 Carpenters 23.35 373.6 39 624
3 Building Laborers 18.55 445.2 31 744
2 Cement Finishers 23.05 368.8 36.7 587.2
1 Rodman (reinf.) 25.85 206.8 47.1 376.8
2 Power Tools 16.4 18.05
1 Gas Finishing Mach. 37.2 40.9 0.74 0.82
72 M.H., Daily Totals 1650.8 2729.75 22.92 37.91

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-16
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 22.01 37.04
3 Building Laborers 18.55 445.2 31 744
2 Cement Finishers 23.05 368.8 36.7 587.2
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
2 Rodmen (reinf.) 25.85 413.6 47.1 753.6
1 Concrete Pump (small) 542.6 596.85 7.54 8.29
72 M.H., Daily Totals 2127.4 3263.65 29.55 45.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.5 40.51
8 Skilled Workers 24.1 1542.4 39.85 2550.4
80 M.H., Daily Totals 1960 3240.8 24.5 40.51

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17A
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.51 40.5
8 Skilled Workers 24.1 1542.4 39.85 2550.4
0.125 Equip. Oper. (crane) 24.95 24.95 39.8 39.8
0.125 Crane, 80 Ton, & Tools 120.3 132.35
0.125 Hand Held Power Tools 1.02 1.15
0.125 Walk Behind Power Tools 4.65 5.1 1.56 1.71
81 M.H., Daily Totals 2110.92 3419.2 26.07 42.21

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17B
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.51 40.49
8 Skilled Workers 24.1 1542.4 39.85 2550.4
0.25 Equip. Oper. (crane) 24.95 49.9 39.8 79.6
0.25 Crane, 80 Ton, & Tools 240.6 264.65
0.25 Hand Held Power Tools 2.05 2.25
0.25 Walk Behind Power Tools 9.3 10.25 3.07 3.38
82 M.H., Daily Totals 2261.85 3597.55 27.58 43.87

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17C
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.52 40.48
8 Skilled Workers 24.1 1542.4 39.85 2550.4
0.375 Equip. Oper. (crane) 24.95 74.85 39.8 119.4
0.375 Crane, 80 Ton, & Tools 360.9 397
0.375 Hand Held Power Tools 3.08 3.4
0.375 Walk Behind Power Tools 13.95 15.35 4.55 5.01
83 M.H., Daily Totals 2412.78 3775.95 29.07 45.49

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17D
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.52 40.48
8 Skilled Workers 24.1 1542.4 39.85 2550.4
0.5 Equip. Oper. (crane) 24.95 99.8 39.8 159.2
0.5 Crane, 80 Ton, & Tools 481.2 529.3
0.5 Hand Held Power Tools 4.1 4.5
0.5 Walk Behind Power Tools 18.6 20.45 6 6.6
84 M.H., Daily Totals 2563.7 3954.25 30.52 47.08

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-17E
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.5 40.51
8 Skilled Workers 24.1 1542.4 39.85 2550.4
1 Hyd. Jack with Rods 57.4 63.15 0.72 0.79
80 M.H., Daily Totals 2017.4 3303.95 25.22 41.3

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-18
Hr. Daily Hr. Daily Bare Costs Incl. O&P
0.125 Labor Foreman (out) 20.55 20.55 34.3 34.3 18.77 31.37
1 Building Laborer 18.55 148.4 31 248
1 Concrete Cart, 10 C.F 47.4 52.15 5.27 5.79
9 M.H., Daily Totals 216.35 334.45 24.04 37.16

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-19
Hr. Daily Hr. Daily Bare Costs Incl. O&P
0.125 Labor Foreman (out) 20.55 20.55 34.3 34.3 18.77 31.37
1 Building Laborer 18.55 148.4 31 248
1 Concrete Cart, 18 C.F 96 105.6 10.67 11.73
9 M.H., Daily Totals 264.95 387.9 29.44 43.1

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-20
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.06 33.06
5 Building Laborers 18.55 742 31 1240
1 Cement Finisher 23.05 184.4 36.7 293.6
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
2 Gas Engine Vibrators 64.8 71.3
1 Concrete Pump (small) 542.6 596.85 9.49 10.44
64 M.H., Daily Totals 1891 2783.75 29.55 43.5

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-21
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 20.06 33.06
5 Building Laborers 18.55 742 31 1240
1 Cement Finisher 23.05 184.4 36.7 293.6
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
2 Gas Engine Vibrators 64.8 71.3
1 Concrete Conveyer 130 143 3.04 3.35
64 M.H., Daily Totals 1478.4 2329.9 23.1 36.41

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-22
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Rodman Foreman 27.85 222.8 50.75 406 26.08 47.27
4 Rodmen (reinf.) 25.85 827.2 47.1 1507.2
0.125 Equip. Oper. (crane) 24.95 24.95 39.8 39.8
0.125 Equip. Oper. Oiler 20.25 20.25 32.3 32.3
0.125 Hyd. Crane, 25 Ton 63.53 69.9 1.51 1.66
42 M.H., Daily Totals 1158.73 2055.2 27.59 48.93

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-23
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.2 39.75
6 Skilled Workers 24.1 1156.8 39.85 1912.8
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 90 Ton 994.4 1093.85 12.43 13.67
80 M.H., Daily Totals 2930.4 4273.85 36.63 53.42

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-24
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker Forem 26.1 417.6 43.15 690.4 24.2 39.75
6 Skilled Workers 24.1 1156.8 39.85 1912.8
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Truck Crane, 150 Ton 1441 1585.1 18.01 19.81
80 M.H., Daily Totals 3377 4765.1 42.21 59.56

Bare Costs Incl. Subs O&P Cost per Manhour


Crew C-25
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Rodmen (reinf.) 25.85 413.6 47.1 753.6 20.55 37.3
2 Rodmen Helpers 15.25 244 27.5 440
32 M.H., Daily Totals 657.6 1193.6 20.55 37.3
Bare Costs Incl. Subs O&P Cost per Manhour
Crew D-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer 24.05 192.4 39.6 316.8 21.45 35.33
1 Bricklayer Helper 18.85 150.8 31.05 248.4
16 M.H., Daily Totals 343.2 565.2 21.45 35.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Bricklayers 24.05 577.2 39.6 950.4 22.1 36.44
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
0.5 Carpenter 23.35 93.4 39 156
44 M.H., Daily Totals 972.2 1603.2 22.1 36.44

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Bricklayers 24.05 577.2 39.6 950.4 22.04 36.31
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
0.25 Carpenter 23.35 46.7 39 78
42 M.H., Daily Totals 925.5 1525.2 22.04 36.31

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer 24.05 192.4 39.6 316.8 21.21 34.64
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Grout Pump 102.8 113.1
1 Hoses & Hopper 24.2 26.6
1 Accessories 10.4 11.45 4.29 4.72
32 M.H., Daily Totals 816.2 1259.55 25.5 39.36

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer 24.05 192.4 39.6 316.8 24.05 39.6
1 Power Tool 36.8 40.5 4.6 5.06
8 M.H., Daily Totals 229.2 357.3 28.65 44.66

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Bricklayers 24.05 577.2 39.6 950.4 21.53 35.47
3 Bricklayer Helpers 18.85 452.4 31.05 745.2
0.25 Carpenter 23.35 46.7 39 78
50 M.H., Daily Totals 1076.3 1773.6 21.53 35.47

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Tile Layer 23.5 188 37.05 296.4 21.1 33.28
1 Tile Layer Helper 18.7 149.6 29.5 236
16 M.H., Daily Totals 337.6 532.4 21.1 33.28

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-8
Crew D-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Bricklayers 24.05 577.2 39.6 950.4 21.97 36.18
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
40 M.H., Daily Totals 878.8 1447.2 21.97 36.18

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Bricklayers 24.05 577.2 39.6 950.4 21.45 35.33
3 Bricklayer Helpers 18.85 452.4 31.05 745.2
48 M.H., Daily Totals 1029.6 1695.6 21.45 35.33

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer Foreman 26.05 208.4 42.9 343.2 22.55 36.88
1 Bricklayer 24.05 192.4 39.6 316.8
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Truck Crane, 12.5 Ton 441.2 485.3 11.03 12.13
40 M.H., Daily Totals 1343.2 1960.5 33.58 49.01

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer Foreman 26.05 208.4 42.9 343.2 22.98 37.85
1 Bricklayer 24.05 192.4 39.6 316.8
1 Bricklayer Helper 18.85 150.8 31.05 248.4
24 M.H., Daily Totals 551.6 908.4 22.98 37.85

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer Foreman 26.05 208.4 42.9 343.2 21.95 36.15
1 Bricklayer 24.05 192.4 39.6 316.8
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
32 M.H., Daily Totals 702.4 1156.8 21.95 36.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew D-13
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Bricklayer Foreman 26.05 208.4 42.9 343.2 22.68 37.23
1 Bricklayer 24.05 192.4 39.6 316.8
2 Bricklayer Helpers 18.85 301.6 31.05 496.8
1 Carpenter 23.35 186.8 39 312
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Truck Crane, 12.5 Ton 441.2 485.3 9.19 10.11
48 M.H., Daily Totals 1530 2272.5 31.87 47.34
Bare Costs Incl. Subs O&P Cost per Manhour
Crew E-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Welder Foreman 28 224 52.6 420.8 25.7 46.1
1 Welder 26 208 48.85 390.8
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Gas Welding Machine 73.4 80.75 3.06 3.36
24 M.H., Daily Totals 690.2 1187.15 28.76 49.46

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 25.31 45.73
4 Struc. Steel Workers 26 832 48.85 1563.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 90 Ton 994.4 1093.85 17.76 19.53
56 M.H., Daily Totals 2412 3654.65 43.07 65.26

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 26.67 50.1
1 Struc. Steel Worker 26 208 48.85 390.8
1 Welder 26 208 48.85 390.8
1 Gas Welding Machine 73.4 80.75
1 Torch, Gas & Air 66 72.6 5.81 6.39
24 M.H., Daily Totals 779.4 1355.75 32.48 56.49

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 26.5 49.79
3 Struc. Steel Workers 26 624 48.85 1172.4
1 Gas Welding Machine 73.4 80.75 2.29 2.52
32 M.H., Daily Totals 921.4 1673.95 28.79 52.31

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Struc. Steel Foremen 28 448 52.6 841.6 25.72 47.04
5 Struc. Steel Workers 26 1040 48.85 1954
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Welder 26 208 48.85 390.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Crane, 90 Ton 994.4 1093.85
1 Gas Welding Machine 73.4 80.75
1 Torch, Gas & Air 66 72.6 14.17 15.59
80 M.H., Daily Totals 3191.4 5010.4 39.89 62.63

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Struc. Steel Foremen 28 672 52.6 1262.4 25.77 47.2
9 Struc. Steel Workers 26 1872 48.85 3517.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Welder 26 208 48.85 390.8
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Crane, 90 Ton 994.4 1093.85
1 Gas Welding Machine 73.4 80.75
1 Torch, Gas & Air 66 72.6
90.2 99.2
Compact Wrenches 59.6 65.55 10.03 11.03
128 M.H., Daily Totals 4582 7453.95 35.8 58.23

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 25.72 47.04
4 Struc. Steel Workers 26 832 48.85 1563.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Welder Foreman 28 224 52.6 420.8
2 Welders 26 416 48.85 781.6
1 Crane, 90 Ton 994.4 1093.85
2 Gas Welding Machines 146.8 161.5 14.27 15.69
80 M.H., Daily Totals 3198.8 5018.55 39.99 62.73

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 25.56 46.53
4 Struc. Steel Workers 26 832 48.85 1563.2
1 Welder Foreman 28 224 52.6 420.8
4 Welders 26 832 48.85 1563.2
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Crane, 90 Ton 994.4 1093.85
4 Gas Welding Machines 293.6 322.95 12.38 13.62
104 M.H., Daily Totals 3946.4 6256.4 37.94 60.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Struc. Steel Foremen 28 448 52.6 841.6 25.77 47.2
5 Struc. Steel Workers 26 1040 48.85 1954
1 Welder Foreman 28 224 52.6 420.8
5 Welders 26 1040 48.85 1954
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Crane, 90 Ton 994.4 1093.85
5 Gas Welding Machines 367 403.7
1 Torch, Gas & Air 66 72.6 11.15 12.27
128 M.H., Daily Totals 4725.8 7612.15 36.92 59.47

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-10
Crew E-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Welder Foreman 28 224 52.6 420.8 27 50.72
1 Welder 26 208 48.85 390.8
4 Gas Welding Machines 293.6 322.95
1 Truck, 3 Ton 155.8 171.4 28.09 30.9
16 M.H., Daily Totals 881.4 1305.95 55.09 81.62

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Painters, Struc. Steel 22.55 360.8 45.05 720.8 21.69 39.49
1 Building Laborer 18.55 148.4 31 248
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Air Compressor 250 C.F.M. 102.8 113.1
1 Sand Blaster 24.2 26.6
1 Sand Blasting Accessories 10.4 11.45 4.29 4.72
32 M.H., Daily Totals 831.4 1414.75 25.98 44.21

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Welder Foreman 28 224 52.6 420.8 25.55 44.72
1 Equip. Oper. (light) 23.1 184.8 36.85 294.8
1 Gas Welding Machines 73.4 80.75 4.59 5.05
16 M.H., Daily Totals 482.2 796.35 30.14 49.77

Bare Costs Incl. Subs O&P Cost per Manhour


Crew E-16
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Welder Foreman 28 224 52.6 420.8 27 50.72
1 Welder 26 208 48.85 390.8
1 Gas Welding Machines 73.4 80.75 4.59 5.05
16 M.H., Daily Totals 505.4 892.35 31.59 55.77
Bare Costs Incl. Subs O&P Cost per Manhour
Crew F-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter 23.35 186.8 39 312 23.35 39
1 Power Tools 26 8.2 9 1.03 1.13
8 M.H., Daily Totals 195 321 24.38 40.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 23.35 39
2 Power Tools 16.4 18.05 1.03 1.13
16 M.H., Daily Totals 390 642.05 24.38 40.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
4 Carpenters 23.35 747.2 39 1248 23.67 39.16
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Hyd. Crane, 12 Ton 375.4 412.95
2 Power Tools 16.4 18.05 9.8 10.77
40 M.H., Daily Totals 1338.6 1997.4 33.47 49.93

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
4 Carpenters 23.35 747.2 39 1248 23.1 38.02
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Equip. Oper. Oiler 20.25 162 32.3 258.4
1 Hyd. Crane, 55 Ton 710 781
2 Power Tools 16.4 18.05 15.13 16.65
48 M.H., Daily Totals 1835.2 2623.85 38.23 54.67

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman 25.35 202.8 42.35 338.8 23.85 39.84
3 Carpenters 23.35 560.4 39 936
2 Power Tools 16.4 18.05 0.51 0.56
32 M.H., Daily Totals 779.6 1292.85 24.36 40.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 21.75 35.96
2 Building Laborers 18.55 296.8 31 496
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
1 Hyd. Crane, 12 Ton 375.4 412.95
2 Power Tools 16.4 18.05 9.8 10.77
40 M.H., Daily Totals 1261.8 1869.4 31.55 46.73

Bare Costs Incl. Subs O&P Cost per Manhour


Crew F-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 20.95 35
2 Building Laborers 18.55 296.8 31 496
2 Power Tools 16.4 18.05 0.51 0.56
32 M.H., Daily Totals 686.8 1138.05 21.46 35.56
Bare Costs Incl. Subs O&P Cost per Manhour
Crew G-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Roofer Foreman 23.25 186 41.95 335.6 19.82 35.76
4 Roofers, Composition 21.25 680 38.35 1227.2
2 Roofer Helpers 15.25 244 27.5 440
1 Application Equipment 148.4 163.25 2.65 2.92
56 M.H., Daily Totals 1258.4 2166.05 22.47 38.68

Bare Costs Incl. Subs O&P Cost per Manhour


Crew G-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Plasterer 22.8 182.4 37.25 298 20.13 33.13
1 Plasterer Helper 19.05 152.4 31.15 249.2
1 Building Laborer 18.55 148.4 31 248
1 Grouting Equipment 242.8 267.1 10.12 11.13
24 M.H., Daily Totals 726 1062.3 30.25 44.26

Bare Costs Incl. Subs O&P Cost per Manhour


Crew G-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Sheet Metal Workers 26.65 426.4 42.7 683.2 22.6 36.85
2 Building Laborers 18.55 296.8 31 496
3 Power Tools 24.6 27.05 0.77 0.85
32 M.H., Daily Totals 747.8 1206.25 23.37 37.7

Bare Costs Incl. Subs O&P Cost per Manhour


Crew G-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (outsid 20.55 164.4 34.3 274.4 19.22 32.1
2 Building Laborers 18.55 296.8 31 496
1 Light Truck, 1.5 Ton 153.4 168.75
1 Air Compr., 160 C.F.M. 90.2 99.2 10.15 11.17
24 M.H., Daily Totals 704.8 1038.35 29.37 43.27

Bare Costs Incl. Subs O&P Cost per Manhour


Crew G-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Roofer Foreman 23.25 186 41.95 335.6 19.25 34.73
2 Roofers, Composition 21.25 340 38.35 613.6
2 Roofer Helpers 15.25 244 27.5 440
1 Application Equipment 148.4 163.25 3.71 4.08
40 M.H., Daily Totals 918.4 1552.45 22.96 38.81
Bare Costs Incl. Subs O&P Cost per Manhour
Crew H-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Glaziers 23.5 376 38 608 24.75 43.42
2 Struc. Steel Workers 26 416 48.85 781.6
32 M.H., Daily Totals 792 1389.6 24.75 43.42

Bare Costs Incl. Subs O&P Cost per Manhour


Crew H-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Glaziers 23.5 376 38 608 21.85 35.67
1 Building Laborer 18.55 148.4 31 248
24 M.H., Daily Totals 524.4 856 21.85 35.67

Bare Costs Incl. Subs O&P Cost per Manhour


Crew H-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Glaziers 23.5 188 38 304 20.8 34.08
1 Helper 18.1 144.8 30.15 241.2
16 M.H., Daily Totals 332.8 545.2 20.8 34.08
Bare Costs Incl. Subs O&P Cost per Manhour
Crew J-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Plasterers 22.8 547.2 37.25 894 21.3 34.81
2 Plasterer Helpers 19.05 304.8 31.15 498.4
1 Mixing Machine, 6 C.F. 38.6 42.45 0.97 1.06
40 M.H., Daily Totals 890.6 1434.85 22.27 35.87

Bare Costs Incl. Subs O&P Cost per Manhour


Crew J-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Plasterers 22.8 547.2 37.25 894 21.62 35.21
2 Plasterer Helpers 19.05 304.8 31.15 498.4
1 Lather 23.2 185.6 37.2 297.6
1 Mixing Machine, 6 C.F. 38.6 42.45 0.8 0.88
48 M.H., Daily Totals 1076.2 1732.45 22.42 36.09

Bare Costs Incl. Subs O&P Cost per Manhour


Crew J-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Terrazzo Worker 23.7 189.6 37.35 298.8 21.53 33.92
1 Terrazzo Helper 19.35 154.8 30.5 244
1 Terrazzo Grinder,Electric 37.2 40.9
1 Terrazzo Mixer 58.6 64.45 5.99 6.59
16 M.H., Daily Totals 440.2 648.15 27.52 40.51

Bare Costs Incl. Subs O&P Cost per Manhour


Crew J-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Tile Layer 23.5 188 37.05 296.4 21.1 33.28
1 Tile Layer Helper 18.7 149.6 29.5 236
16 M.H., Daily Totals 337.6 532.4 21.1 33.28
Bare Costs Incl. Subs O&P Cost per Manhour
Crew K-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter 23.25 186.8 39 312 21.25 35.1
1 Truck Driver (light) 19.15 153.2 31.2 249.6
1 Truck w/ Power Equip. 155.8 171.4 9.74 10.71
16 M.H., Daily Totals 495.8 733 30.99 45.81

Bare Costs Incl. Subs O&P Cost per Manhour


Crew K-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 24.38 44.22
1 Struc. Steel Worker 26 208 48.85 390.8
1 Truck Driver (light) 19.15 153.2 31.2 249.6
Truck w/ Power Equip. 155.8 171.4 6.49 7.14
24 M.H., Daily Totals 741 1232.6 30.87 51.36
Bare Costs Incl. Subs O&P Cost per Manhour
Crew L-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician 26.7 213.6 41.4 331.2 27.05 42.15
1 Plumber 27.4 219.2 42.9 343.2
16 M.H., Daily Totals 432.8 674.4 27.05 42.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter 23.35 186.8 39 312 20.73 34.58
1 Carpenter Helper 18.1 144.8 30.15 241.2
16 M.H., Daily Totals 331.6 553.2 20.73 34.58

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter 23.35 186.8 39 312 25.01 40.53
0.5 Electrician 26.7 106.8 41.4 165.6
0.5 Sheet Metal Worker 26.65 106.6 42.7 170.8
16 M.H., Daily Totals 400.2 648.4 25.01 40.53

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Skilled Worker 24.1 385.6 39.85 637.6 22.1 36.62
1 Helper 18.1 144.8 30.15 241.2
24 M.H., Daily Totals 530.4 878.8 22.1 36.62

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 26.14 48.09
5 Struc. Steel Workers 26 1040 48.85 1954
1 Equip. Oper. (crane) 24.95 199.6 39.8 318.4
508.2 559 9.08 9.98
M.H., Daily Totals 1971.8 3252.2 35.22 58.07

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Plumber 27.4 219.2 42.9 343.2 27.17 42.4
0.5 Electrician 26.7 106.8 41.4 165.6
12 M.H., Daily Totals 326 508.8 27.17 42.4

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 22.46 37.06
1 Building Laborer 18.55 148.4 31 248
0.5 Electrician 26.7 106.8 41.4 165.6
28 M.H., Daily Totals 628.8 1037.6 22.46 37.06

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Carpenters 23.35 373.6 39 624 24.16 39.78
0.5 Plumber 27.4 109.6 42.9 171.6
20 M.H., Daily Totals 483.2 795.6 24.16 39.78

Bare Costs Incl. Subs O&P Cost per Manhour


Crew L-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Labor Foreman (inside 19.05 152.4 31.8 254.4 21.22 36.3
2 Building Laborers 18.55 296.8 31 496
1 Struc. Steel Worker 26 208 48.85 390.8
0.5 Electrician 26.7 106.8 41.4 165.6
36 M.H., Daily Totals 764 1306.8 21.22 36.3
Bare Costs Incl. Subs O&P Cost per Manhour
Crew M-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
3 Elevator Constructors 27.25 654 42.5 1020 25.89 40.38
1 Elevator Apprentice 21.8 174.4 34 272
5 Hand Tools 80 88 2.5 2.75
32 M.H., Daily Totals 908.4 1380 28.39 43.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew M-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Millwrights 24.35 389.6 38.8 620.8 24.35 38.8
2 Power Tools 16.4 18.05 1.03 1.13
16 M.H., Daily Totals 406 638.85 25.38 39.93
Bare Costs Incl. Subs O&P Cost per Manhour
Crew Q-1
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Plumber 27.4 219.2 42.9 343.2 24.65 38.58
1 Plumber Apprentice 21.9 175.2 34.25 274
16 M.H., Daily Totals 394.4 617.2 24.65 38.58

Bare Costs Incl. Subs O&P Cost per Manhour


Crew Q-2
Hr. Daily Hr. Daily Bare Costs Incl. O&P
2 Plumbers 27.4 438.4 42.9 686.4 25.57 40.02
1 Plumber Apprentice 21.9 175.2 34.25 274
24 M.H., Daily Totals 613.6 960.4 25.57 40.02

Bare Costs Incl. Subs O&P Cost per Manhour


Crew Q-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Plumber Foreman (ins 27.9 223.2 43.65 349.2 26.15 40.93
2 Plumbers 27.4 438.4 42.9 686.4
1 Plumber Apprentice 21.9 175.2 34.25 274
32 M.H., Daily Totals 836.8 1309.6 26.15 40.93

Bare Costs Incl. Subs O&P Cost per Manhour


Crew Q-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Plumber Foreman (ins 27.9 223.2 43.65 349.2 26.15 40.93
1 Plumber 27.4 219.2 42.9 343.2
1 Welder (plumber) 27.4 219.2 42.9 343.2
1 Plumber Apprentice 21.9 175.2 34.25 274
1 Electric Welding Mach. 45.8 50.4 1.43 1.57
32 M.H., Daily Totals 882.6 1360 27.58 42.5
Bare Costs Incl. Subs O&P Cost per Manhour
Crew R-3
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 26.55 41.4
1 Electrician 26.7 213.6 41.4 331.2
0.5 Equip. Oper. (crane) 24.95 99.8 39.8 159.2
0.5 S.P. Crane, 5 Ton 112.6 123.85 5.63 6.19
20 M.H., Daily Totals 643.6 951.85 32.18 47.59

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-4
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Struc. Steel Foreman 28 224 52.6 420.8 26.54 48.11
3 Struc. Steel Workers 26 624 48.85 1172.4
1 Electrician 26.7 213.6 41.4 331.2
1 Gas Welding Machine 73.4 80.75 1.84 2.02
40 M.H., Daily Totals 1135 2005.15 28.38 50.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-5
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 23.62 37.38
4 Electrician Lineman 26.7 854.4 41.4 1324.8
2 Electrician Operators 26.7 427.2 41.4 662.4
4 Electrician Groundme 18.1 579.2 30.15 964.8
1 Crew Truck 169.6 186.55
1 Tool Van 308 338.8
1 Pick-up Truck 113.4 124.75
0.2 Crane, 55 Ton 142 156.2
0.2 Crane, 12 Ton 75.08 82.6
0.2 Auger, Truck Mtd. 313.8 345.2
1 Tractor w/ Winch 265.4 291.95 15.76 17.34
88 M.H., Daily Totals 3465.68 4815.65 39.38 54.72

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-6
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 23.62 37.38
4 Electrician Linemen 26.7 854.4 41.4 1324.8
2 Electrician Operators 26.7 427.2 41.4 662.4
4 Electrician Groundme 18.1 579.2 30.15 964.8
1 Crew Truck 169.6 186.55
1 Tool Van 308 338.8
1 Pick-up Truck 113.4 124.75
0.2 Crane, 55 Ton 142 156.2
0.2 Crane, 12 Ton 75.08 82.6
0.2 Auger, Truck Mtd. 313.8 345.2
1 Tractor w/ Winch 265.4 291.95
3 Cable Trailers 392.4 431.65
0.5 Tensioning Rig 127.9 140.7
0.5 Cable Pulling Rig 764 840.4 30.36 33.39
88 M.H., Daily Totals 4749.98 6228.4 53.98 70.77

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-7
Crew R-7
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 19.62 32.16
5 Electrician Groundme 18.1 724 30.15 1206
1 Crew Truck 169.6 186.55 3.53 3.89
48 M.H., Daily Totals 1111.2 1730.15 23.15 36.05

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-8
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 23.92 37.78
3 Electrician Linemen 26.7 640.8 41.4 993.6
2 Electrician Groundme 18.1 289.6 30.15 482.4
1 Pick-up Truck 113.4 124.75
1 Crew Truck 169.6 186.55 5.9 6.49
48 M.H., Daily Totals 1431 2124.9 29.82 44.27

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-9
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 22.46 35.88
1 Electrician Linemen 26.7 213.6 41.4 331.2
2 Electrician Operators 26.7 427.2 41.4 662.4
4 Electrician Groundme 18.1 579.2 30.15 964.8
1 Pick-up Truck 113.4 124.75
1 Crew Truck 169.6 186.55 4.42 4.86
64 M.H., Daily Totals 1720.6 2607.3 26.88 40.74

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-10
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 25.35 39.66
4 Electrician Linemen 26.7 854.4 41.4 1324.8
1 Electrician Groundma 18.1 144.8 30.15 241.2
1 Crew Truck 169.6 186.55
3 Tram Cars 462.6 508.85 13.17 14.49
48 M.H., Daily Totals 1849 2599 38.52 54.15

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-11
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Electrician Foreman 27.2 217.6 42.2 337.6 24.38 38.42
4 Electricians 26.7 854.4 41.4 1324.8
1 Helper 18.1 144.8 30.15 241.2
1 Common Laborer 18.55 148.4 31 248
1 Crew Truck 169.6 186.55
1 Crane, 12 Ton 375.4 412.95 9.73 10.71
56 M.H., Daily Totals 1910.2 2751.1 34.11 49.13

Bare Costs Incl. Subs O&P Cost per Manhour


Crew R-12
Hr. Daily Hr. Daily Bare Costs Incl. O&P
1 Carpenter Foreman 23.85 190.8 39.85 318.8 21.96 37.01
4 Carpenters 23.35 747.2 39 1248
4 Common Laborers 18.55 593.6 31 992
1 Equip. Oper. (med.) 24.1 192.8 38.45 307.6
1 Steel Worker 26 208 48.85 390.8
1 Dozer, 200 H.P. 832 915.2
1 Pick-up Truck 113.4 124.75 10.74 11.82
88 M.H., Daily Totals 2877.8 4297.15 32.7 48.83

You might also like