You are on page 1of 58

14

Chapter - 12

Foundation

Sl. No. Quantity Description Rate per

I. In Ordinary Soil [Including dewatering]

B. MECHANICAL MEANS
(i) Depth upto 3 m [ including dewatering]:
Unit = = Cum
Taking Output = = 240 cum
a) Labour :
0.32 Nos Mate 292.00 /
8.00 Nos Mazdoor 282.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity 1302.00 /

Tot
Total
Add for dewatering on cost of
5% labour & machinary
10161.44

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 10669.51
Total
C) Contractor's profit 10% on 12803.41
Rate for 240 cum
Rate for 1 cum = 14083.75 /
15

Sl. No. Quantity Description Rate per

Earth Work for foundation in ordinary


= 58.68 /
soil mechanically for depth upto 3 m

II. In Ordinary rock not requiring blasting [excluding dewatering]


B. MECHANICAL MEANS
(i) Depth upto 3 m [excluding dewatering]:
Unit = = Cum
Taking Output = = 180 cum
a) Labour :
0.24 Nos Mate 292.00 /
6.00 Nos Mazdoor 282.00 /
Tot
b) Machinary
Hydraulic excavator 1 cum bucket
6.00 Hour capacity
1302.00 /
Tot
Total
0.0% Add for dewatering on cost of labour 9574.08
T

(ii) For minor bridges in road packages and culverts


b) Overheads 20% on 9574.08
Total
C) Contractor's profit 10% on 11488.90
Rate for 180 cum
Rate for 1 cum = 12637.79 /
Earth work for foundation upto 3 m
mechanically in oridinary rock not = 70.21 /
requiring blasting
16

Sl. No. Quantity Description Rate per

12.4. Plain concrete 1:3:6 nominal mix in foundation with crushed s


aggregates 40 mm nominal size mechanically mixed, placed in found
and compacted by vibrator including curing for 14 days.

MORT & H Specifitation No: 2100


Unit = Cum
Taking Output = 15 cum
a) Labour :
0.64 Nos Mate 292.00 /
1.00 Nos Mason class I 451.00 /
15.00 Nos Mazdoor 282.00 /
Tot
b) Material:
13.50 Cum 40 mm ISS metal 1009.30 /
6.75 Cum Sand for mortar 293.06 /
Cement (3.45-10% of 3.45 as per
3.11 Tonne cl 601.3.3
6642.48 /

18.00 KL Cost of water 150.00 /


Tot
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
2.00 Hour Water tanker 310.00 /
Tot
Total [a+

(ii) For minor bridges in road packages and culverts


17

Sl. No. Quantity Description Rate per

C) Overheads 20% on 48079.71


Total [a+
C) Contractor's profit 10% on 57695.65
Rate for 15 cum

Rate for 1 cum = 63465.22 /

PCC 1:3:6 for foundation 4231.01 /

12.8 Plain cement concrete M 20 in foundation with crushed stone aggreg


B. 40 mm nominal size mechanically mixed, placed in foundation
compacted by vibrator including curing for 14 days.
MORT & H Specifitation No: 1500, 1700 & 2100
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 282.00 /
Tot
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.16 Tonne Cement 6642.48 /
Tot
Total
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Tot
Total [a+
18

Sl. No. Quantity Description Rate per

d) Form work
On cost of materials, labhour and
4.00% machinary
61755.94 /
Tot
Total [a+b+

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 64226.18
Total [a+b+c+
f) Contractor's profit 10% on 77071.42
Rate for 15 cum
Rate for 1 cum = 84778.56 /

PCC M 20 for foundation = 5651.90 /


19

Rate per Amount

Nos 93.44
Nos 2256.00
Total [a] 2349.44

Hour 7812.00

Total [b] 7812.00


Total [a+b] 10161.44

= 508.07

Total 10669.51

es and culverts
2133.90
Total [a+b] 12803.41
1280.34
= 14083.75
240
20

Rate per Amount

cum

excluding dewatering]

Nos 70.08
Nos 1692.00
Total [a] 1762.08

Hour 7812.00
Total [b] 7812.00
Total [a+b] 9574.08
= 0.00
Total 9574.08

es and culverts
1914.82
Total [a+b] 11488.90
1148.89
= 12637.79
180

cum
21

Rate per Amount

tion with crushed stone


ixed, placed in foundation
days.

Nos 186.88
Nos 451.00
Nos 4230.00
Total [a] 4867.88

Cum 13625.55
Cum 1978.16

Tonne 20658.12

KL 2700.00
Total [b] 38961.83

Hour 1398.00
Hour 2232.00
Hour 620.00
Total [c] 4250.00
Total [a+b+c] 48079.71

es and culverts
22

Rate per Amount

9615.94
Total [a+b+c] 57695.65
5769.57
= 63465.22

15

cum

crushed stone aggregates


laced in foundation and
s.

Nos 251.12
Nos 676.50
Nos 5640.00
Total [a] 6567.62

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34275.21
Total [b] 51558.32
Total [a+b] 58125.94

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 61755.94
23

Rate per Amount

0 2470.24
Total [d] 2470.24
Total [a+b+c+d] 64226.18

es and culverts
12845.24
Total [a+b+c+d+e] 77071.42
7707.14
= 84778.56
15

cum
74

CHAPTER - 13
Sl. No. Quantity Description Rate per

13.5. b. PCC M 20 for substructure using Concrete mixer:


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 282.00 /
Total [a
b) Material:
5.40 Cum 40 mm ISS metal 1009.30 /
5.40 Cum 20 mm ISS metal 1341.30 /
2.70 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
5.16 Tonne Cement 6642.48 /
Total [b
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [b
PCC M 20 - upto 5m height:
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c
d) Form work
On cost of materials, labour and
10% machinary
61755.94 /
Total [d
Total [a+b+c+d

(ii) For minor bridges in road packages and culverts


75

Sl. No. Quantity Description Rate per


e) Overheads 20% on 67931.53
Total [a+b+c+d+e
f) Contractor's profit 10% on 81517.84
Rate for 15 cum
Rate for 1 cum = 89669.62 /
PCC M 20 for substructure with concrete = 5977.97 /
mixer upto 5 m height

-*/-/*-/*-/*-/*-

13.5.f. RCC M 25 using concrete mixer


MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 282.00 /
Total [a
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.05 Tonne Cement 6642.48 /
Total [b
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total [c

RCC M 25 - upto 5m height using concrete mixe


a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Total [a+b+c
76

Sl. No. Quantity Description Rate per


d) Form work
On cost of materials, labour and
10% machinary
68450.75 /
Total [d
Total [a+b+c+d

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 75295.83
Total [a+b+c+d+e
f) Contractor's profit 10% on 90355.00
Rate for 15 cum
Rate for 1 cum = 99390.50 /
RCC M 25 for substructure using concrete mixer
for height upto 5 m
= 6626.03 /

Supplying, fitting and placing HYSD bar reinforcement in


13.6. complete as per drawing and techincal specificaion
MORT & H Specification No: 1600 & 2200
Unit = MT
Taking Output = 1 MT
Labour for cutting, bending, shifting to site, tying
a) position

0.34 Nos Mate 292.00 /


2.00 Nos Blacksmith 348.00 /
6.50 Nos Mazdoor 282.00 /
Total [a

b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
6.00 Kg Binding wires 45.60 /
Total [b
Total [a+b
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 49958.22
Total [a+b+c+d+e
77

Sl. No. Quantity Description Rate per


f) Contractor's profit 10% on 59949.86
Rate for 1 MT
Rate for 1 cum = 65944.85 /

HYSD reinforcement for substructure = 65944.85 /


-*/-*/-

Supplying, fitting and placing Mild steel reinforcement in


13.7. complete as per drawing and techincal specificaion
MORT & H Specification No: 1600 & 2200
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tying
0.28 Nos position
Mate 292.00 /
1.50 Nos Blacksmith 348.00 /
5.50 Nos Mazdoor 282.00 /
Total [a
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
6.00 Kg Binding wires 45.60 /
Total [b
Total [a+b
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 49484.70
Total [a+b+c+d+e
f) Contractor's profit 10% on 59381.64
Rate for 1 MT
Rate for 1 cum = 65319.80 /

Mild steel reinforcement for substructure = 65319.80 /


-*/-*/-
78

Sl. No. Quantity Description Rate per


13.8. Providing weep holes in brick masonry /plain / reinforc
abutment, wing walls / return wall with 100 mm dia AC pip
through the full width of the structure with slope of aV:
drawing face, complete as per drawing and techinical specifi

MORT & H Specification No: 2706 & 2200


Unit = Nos.
Taking Output = 30 Nos.
Labour for cutting, bending, shifting to site, tying
a) position
0.03 Nos Mate 292.00 /
0.50 Nos Mason 451.00 /
0.25 Nos Mazdoor 282.00 /
Total [a
b) Material:
AC pipe 100 mm dia [including
31.50 RM wastage at 5%] 50.00 /
30.00 Nos. MS clamp 15.00 /
10.00 Nos. Collar for AC pipes [ Average] 25.00 /
0.05 Cum Cement mortar 1:3 3960.86 /
Total [b
Total [a+b

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 2777.80
Total [a+b+c+d+e
f) Contractor's profit 10% on 3333.36
Rate for 30 Nos.
Rate for 1 cum = 3666.70 /
Weep holes = 122.22 /
-*/-*/-
### Back filling behind abutment, wing walls / return wall complete as per
techinical specifications.
79

Sl. No. Quantity Description Rate per

MORT & H Specification No: 710.1.4 of IRC :78 & 2200


Unit = Cum
Taking Output = 10 Cum
a) Labour
0.28 Nos Mate 292.00 /
7.00 Nos Mazdoor 282.00 /
Total [a
b) Material:
12.00 Cum Granular material 246.95 /
Total [b
C) Machinary

2.50 Hour Plate compactor /power rammer 155.00 /

0.05 Hour Water tanker 310.00 /


Total [c
Total [a+b+c

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 5422.16
Total [a+b+c+d
e) Contractor's profit 10% on 6506.59
Rate for 10 Cum
Rate for 1 cum = 7157.25 /
Back filling behind abutment, wing walls / return
wall
= 715.73 /
-*/-*/-
13.10. Providing and laying of filter media with granular mater
crushed aggregates satisfying the requirements laid dow
2504.2.2 of MORT & H specifications to a thickness of not l
mm with smaller size towards the wall and provided ov
surface behind abutment, wing walls and return walls to th
compacted to a firm condition complete as per drawing a
specifications.

MORT & H Specification No: 710.1.4 of IRC :78 & 2200


80

Sl. No. Quantity Description Rate per


Unit = Cum
Taking Output = 10 Cum
a) Labour
0.32 Nos Mate 292.00 /
7.00 Nos Mazdoor 255.00 /
1.00 Nos Mazdoor 282.00 /
Total [a

b) Material:
Sand for filling 296.11
Gravel 246.95
Sand for mortar 293.06
836.12 /
Granular material = 278.71
Filter media conforming to
12.00 Cum clause 2504.2.2. of MORT &H 278.71 /
specification
Total [b
C) Machinary
0.06 Hour Water tanker 310.00 /
Total [c
Total [a+b+c

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 5523.56
Total [a+b+c+d
e) Contractor's profit 10% on 6628.27
Rate for 10 Cum
Rate for 1 cum = 7291.10 /
Filter media behind abutment, wing walls and
return wall
= 729.11 /
-*/-*/-
81

Rate per Amount

g Concrete mixer:

Nos 251.12
Nos 676.50
Nos 5640.00
Total [a] 6567.62

Cum 5450.22
Cum 7243.02
Cum 2611.71
Cum 1978.16
Tonne 34275.21
Total [b] 51558.32

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
5m height:
6567.62
51558.32
3630.00
Total [a+b+c] 61755.94

0 6175.59
Total [d] 6175.59
Total [a+b+c+d] 67931.53

es and culverts
82

Rate per Amount


13586.31
Total [a+b+c+d+e] 81517.84
8151.78
= 89669.62
15

cum

Nos 251.12
Nos 676.50
Nos 5640.00
Total [a] 6567.62

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40187.02
Total [b] 58253.13

Hour 1398.00
Hour 2232.00
Total [c] 3630.00

using concrete mixer:


6567.62
58253.13
3630.00
Total [a+b+c] 68450.75
83

Rate per Amount

0 6845.08
Total [d] 6845.08
Total [a+b+c+d] 75295.83

es and culverts
15059.17
Total [a+b+c+d+e] 90355.00
9035.50
= 99390.50
15

cum

ar reinforcement in substructure
pecificaion

, shifting to site, tying and placing in

Nos 99.28
Nos 696.00
Nos 1833.00
Total [a] 2628.28

MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49958.22
es and culverts
9991.64
Total [a+b+c+d+e] 59949.86
84

Rate per Amount


5994.99
= 65944.85
1

MT

el reinforcement in substructure
pecificaion

, shifting to site, tying and placing in


Nos 81.76
Nos 522.00
Nos 1551.00
Total [a] 2154.76

MT 47056.34
Kg 273.60
Total [b] 47329.94
Total [a+b] 49484.70
es and culverts
9896.94
Total [a+b+c+d+e] 59381.64
5938.16
= 65319.80
1

MT
85

Rate per Amount


nry /plain / reinforced concrete
100 mm dia AC pipe, extending
with slope of aV:20H towards
nd techinical specifications.

, shifting to site, tying and placing in

Nos 8.76
Nos 225.50
Nos 70.50
Total [a] 304.76

RM 1575.00
Nos. 450.00
Nos. 250.00
Cum 198.04
Total [b] 2473.04
Total [a+b] 2777.80

es and culverts
555.56
Total [a+b+c+d+e] 3333.36
333.34
= 3666.70
30
Nos.

wall complete as per drawing and


86

Rate per Amount

Nos 81.76
Nos 1974.00
Total [a] 2055.76

Cum 2963.40
Total [b] 2963.40

Hour 387.50

Hour 15.50
Total [c] 403.00
Total [a+b+c] 5422.16

es and culverts
1084.43
Total [a+b+c+d] 6506.59
650.66
= 7157.25
10

Cum

with granular materials / stone


quirements laid down in clause
a thickness of not less than 600
ll and provided over the entire
nd return walls to the full height
e as per drawing and techinical
87

Rate per Amount

Nos 93.44
Nos 1785.00
Nos 282.00
Total [a] 2160.44

Cum 3344.52

Total [b] 3344.52

Hour 18.60
Total [c] 18.60
Total [a+b+c] 5523.56

es and culverts
1104.71
Total [a+b+c+d] 6628.27
662.83
= 7291.10
10

Cum
107

Chapter - 12
Foundation
Sl. No. Quantity Description Rate per
-*/-*/-*/

Case I RCC Grade M-25 using concrete mixer


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 282.00 /
Total
b) Material:
5.99 Tonne Cement 6642.48 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-25 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
20% machinary
68052.20 /
Total [a+b+c
108

Sl. No. Quantity Description Rate per


(i) For major bridges and minor bridges
e) Overheads 25% on 81662.64
Total [a+b+c+d
f) Contractor's profit 10% on 102078.30
Rate for 15 Cum
Rate for 1 cum = 112286.13 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7485.74 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 81662.64
Total [a+b+c+d
f) Contractor's profit 10% on 97995.17
Rate for 15 Cum
Rate for 1 cum = 107794.69 /
RCC M-25 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7186.31 /

-*/-*/-*/

Case I RCC Grade M-35 using concrete mixer


MORT & H Specification No: 1500, 1600 & 1700
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.90 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 282.00 /
Total

b) Material:
6.33 Tonne Cement 6642.48 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
109

Sl. No. Quantity Description Rate per


Total
C) Machinary
6.00 Hour Concrete mixer 0.40 / 0.28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
I RCC M-35 FOR SOLID SLAB SUPERSTRUCTURE USING
a) Labour charges MIXER
b) Cost of materials
c) Hire charges for machinary
Cost of materials, labour and machinary =
a. UPTO 5 m HEIGHT
d) Form work
On cost of materials, labour and
18% machinary 70604.33 /
Total [a+b+c
(i) For major bridges and minor bridges
e) Overheads 25% on 83313.11
Total [a+b+c+d
f) Contractor's profit 10% on 104141.39
Rate for 15 Cum
Rate for 1 cum = 114555.53 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7637.04 /
(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 83313.11
Total [a+b+c+d
f) Contractor's profit 10% on 99975.73
Rate for 15 Cum
Rate for 1 cum = 109973.30 /
RCC M-35 for Solid slab superstructure using
concrete mixer for height upto 5 m
= 7331.55 /

-*/-*/-*/
Supplying, fitting and placing HYSD bar reinforcement in
14.2 complete as per drawing and techincal specificaion
110

Sl. No. Quantity Description Rate per


MORT & H Specification No: 1600
Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 292.00 /
3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 282.00 /
Total
b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /

8.00 Kg Binding wires 45.60 /


Total
Total [a
(i) For major bridges and minor bridges
c) Overheads 25% on 50849.62
Total [a+b
d) Contractor's profit 10% on 63562.03
Rate for 1 MT
Rate for 1 cum = 69918.23 /

HYSD reinforcement for superstructure = 69918.23 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 50849.62
Total [a+b+c+d
f) Contractor's profit 10% on 61019.54
Rate for 1 MT
Rate for 1 cum = 67121.49 /

HYSD reinforcement for superstructure = 67121.49 /


-*/-*/-

-*/-*/-
111

Sl. No. Quantity Description Rate per


Providing and laying Cement Concrete wearing coat M-30 gr
14.4. concrete mixer and excluding reinforcement:
MORT & H Specification No: 1500, 1700 & 2200
Unit = Cum
Taking Output = 1 Cum
a) Labour :
0.90 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 282.00 /
Total
b) Material:
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
6.10 Tonne Cement 6642.48 /
Total
C) Machinary
6.00 Hour Concrete mixer040/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total

CC M 30
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of M - 30 grade concrete for 15 cum
Cost of M - 30 grade concrete for 1cum =
1.00 Cum M-30 grade concrete 4605.10 /
Mazdoor for cleaning deck slab
0.15 Nos concrete surface
282.00 /

To
(i) For major bridges and minor bridges
e) Overheads 25% on 4647.40
To
112

Sl. No. Quantity Description Rate per


f) Contractor's profit 10% on 5809.25
Rate for 1 Cum
Rate for 1 CUM = 6390.18 /

Wearing coat in CC M 30 = 6390.18 /


(ii) For minor bridges in road packages and culverts
e) Overheads 20% on 4647.40
To
f) Contractor's profit 10% on 5576.88
Rate for 1 Cum
Rate for 1 cum = 6134.57 /

Wearing coat in CC M 30 = 6134.57 /

*/-*/-*/-*/

14.9 Drainage spouts complete as per drawing and specifications

MORT & H Specification No: 2705


Unit = 1 No.
Taking Output = 1 No.
a) Labour :
For fabrication
0.02 Nos Mate 292.00 /
0.02 Nos Black smith 348.00 /
0.02 Nos Mazdoor 282.00 /
For fixing in position
0.01 Nos Mate 292.00 /
0.01 Nos Mason class I 451.00 /
0.20 Nos Mazdoor 282.00 /
Total
b) Material:
Corrosion resistant structural
4.00 Kg steel 43.00 /

6.00 m GI pipe 100 mm dia 210.00 /


113

Sl. No. Quantity Description Rate per


6.00 Nos. GI bolt 10 mm dia 1.30 /
2.00 Nos. GaIvanised MS flat clamp 7.50 /
Total
Cost of materials and labour

For electrodes, cutting gas,


5% sealent, anticorrosive bituminous 1537.07 /
paint, mild steel grating etc.

(i) For major bridges and minor bridges


e) Overheads 25% on 1613.92
To
f) Contractor's profit 10% on 2017.40
Rate for 6M
Rate for 1 M/NO = 2219.14 /
Drainage spout = 369.86 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 1613.92
To
f) Contractor's profit 10% on 1936.70
Rate for 6M
Rate for 1 M/NO = 2130.37 /

Drainage spout = 355.06 /


*/-*/-*/-*/

14.10. Plain cement concrete M 15 grade levelling course bel


approach slab complete as per drawing and techni
specification

MORT & H Specification No: 1500, 1700 & 2200


Unit = Cum
Taking Output = 15 cum
a) Labour :
114

Sl. No. Quantity Description Rate per


0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
20.00 Nos Mazdoor 282.00 /
Total
b) Material:
8.10 Cum 40 mm ISS metal 1009.30 /
4.05 Cum 20 mm ISS metal 1341.30 /
1.35 Cum 10 mm ISS metal 967.30 /
6.75 Cum Sand for mortar 293.06 /
4.13 Tonne Cement 6642.48 /
Total
C) Machinary
6.00 Hour Concrete mixer 40/28 cum 233.00 /
6.00 Hour Generator 33 KVA 372.00 /
Total
Total [a+b
(i) For major bridges and minor bridges
d) Overheads 25% on 54522.70
Total [a+b+c
e) Contractor's profit 10% on 68153.38
Rate for 15 cum
Rate for 1 cum = 74968.72 /

PCC M 15 below approach slab = 4997.91 /

(ii) For minor bridges in road packages and culverts


d) Overheads 20% on 54522.70
Total [a+b+c
e) Contractor's profit 10% on 65427.24
Rate for 15 cum
Rate for 1 cum = 71969.96 /

PCC M 15 below approach slab = 4798.00 /


*-*-*-*-*-*-
115

Sl. No. Quantity Description Rate per


14.11 RCC railing of M 30 grade approach slab including reinforce
work complete as per approved drawings and technical spec

MORT & H Specification No: 1500, 1600 & 1700 & 2704
Unit = Cum
Taking Output = 15 cum
a) Labour :
0.86 Nos Mate 292.00 /
1.50 Nos Mason class I 451.00 /
21.00 Nos Mazdoor 282.00 /
Total
b) Material:
6.10 Tonne Cement 6642.48 /
6.75 Cum Sand for mortar 293.06 /
8.10 Cum 20 mm ISS metal 1341.30 /
5.40 Cum 10 mm ISS metal 967.30 /
Total
C) Machinary
Concrete mixer
6.00 Hour 0.40 / 0.28 cum
233.00 /

6.00 Hour Generator 33 KVA 372.00 /


Total
RCC M-30 USING CONCRETE MIXER
a) Labour charges
b) Cost of materials
c) Hire charges for machinary
Cost of RCC M 30 for 15 cum =
Cost of RCC M 30 for 15 cum = 69064.88 /
= 4604.33 /
Cost of HYSD bar reinforcements:

Unit = MT
Taking Output = 1 MT
a) Labour for cutting, bending, shifting to site, tyin
0.44 Nos position
Mate 292.00 /
116

Sl. No. Quantity Description Rate per


3.00 Nos Blacksmith 348.00 /
8.00 Nos Mazdoor 282.00 /
Total

b) Material:
HYSD bars including 5 % for
1.05 MT overlaps and wastages
44815.56 /
8.00 Kg Binding wires 45.60 /
Total
Total [a
Rate for 1 MT
RCC M-30 For approach slab USING CONCRETE MIXE
reinforcements
Unit = Cum
Taking Output = 1 Cum
RCC M 30 mix excluding steel
1.000 Cum reinforcement
4604.33 /

For fromwork for casting in


2% casting yard
4604.33 /

HYSD bars including 5 % for


0.050 MT overlaps and wastages
50849.62 /

(i) For major bridges and minor bridges


e) Overheads 25% on 7238.90
To
f) Contractor's profit 10% on 9048.63
Rate for 1 Cum
Rate for 1 cum = 9953.49 /
RCC M 30 for approach slab using concrete
mixer including reinforcements
= 9953.49 /

(ii) For minor bridges in road packages and culverts


e) Overheads 20% on 7238.90
To
f) Contractor's profit 10% on 8686.68
117

Sl. No. Quantity Description Rate per


Rate for 1 Cum
Rate for 1 cum = 9555.35 /

RCC M 30 for approach slab using concrete


mixer including reinforcements
= 9555.35 /

*/-*/-*/-*/

*/-*/-*/-*/
[ii] Providing and fixing 20 mm thick compressible fibre board
joint complete as per drawing and technical specifications

MORT & H Specification No: 2605


Unit = Rm
Taking Output = 12 Rm
a) Labour for cutting bending, carrying and fixing, etc.
0.01 Nos Mate 292.00 /
0.10 Nos Mazdoor 255.00 /
0.10 Nos Mazdoor [Skilled] 282.00 /
Total

b) Material:

20 mm thick compressible fibre


3.00 Sqm board 12 m long x 25 cm deep
726.00 /

Total

(i) For major bridges and minor bridges


e) Overheads 25% on 2234.62
To
f) Contractor's profit 10% on 2793.28
Rate for 12 Rm
Rate for 1 Rm = 3072.61 /
20 mm thick fibre board = 256.05 /
(ii) For minor bridges in road packages and culverts
118

Sl. No. Quantity Description Rate per


e) Overheads 20% on 2234.62
To
f) Contractor's profit 10% on 2681.54
Rate for 12 Rm
Rate for 1 Rm = 2949.69 /

20 mm thick fibre board = 245.81 /


*/-*/-*/-*/
119

Rate per Amount

te mixer

Nos 251.12
Nos 676.50
Nos 5640.00
Total [a] 6567.62

Tonne 39788.47
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 57854.58

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
6567.62
57854.58
3630.00
[a+b+c] 68052.20

0 13610.44
Total [a+b+c+d] 81662.64
120

Rate per Amount


bridges
20415.66
Total [a+b+c+d+e] 102078.30
10207.83
= 112286.13
15

Cum

s and culverts
16332.53
Total [a+b+c+d+e] 97995.17
9799.52
= 107794.69
15

Cum

te mixer

Nos 262.80
Nos 676.50
Nos 5922.00
Total [a] 6861.30

Tonne 42046.92
Cum 1978.16
Cum 10864.53
Cum 5223.42
121

Rate per Amount


Total [b] 60113.03

Hour 1398.00
Hour 2232.00
Total [c] 3630.00
RUCTURE USING CONCRETE
6861.30
60113.03
3630.00
[a+b+c] 70604.33

0 12708.78
Total [a+b+c+d] 83313.11
bridges
20828.28
Total [a+b+c+d+e] 104141.39
10414.14
= 114555.53
15

Cum

s and culverts
16662.62
Total [a+b+c+d+e] 99975.73
9997.57
= 109973.30
15

Cum

reinforcement in superstructure
ecificaion
122

Rate per Amount

shifting to site, tying and placing in


Nos 128.48
Nos 1044.00
Nos 2256.00
Total [a] 3428.48

MT 47056.34

Kg 364.80
Total [b] 47421.14
Total [a+b] 50849.62
bridges
12712.41
Total [a+b+c] 63562.03
6356.20
= 69918.23
1

MT

s and culverts
10169.92
Total [a+b+c+d+e] 61019.54
6101.95
= 67121.49
1

MT
123

Rate per Amount


aring coat M-30 grade using
nt:

Nos 262.80
Nos 676.50
Nos 5922.00
Total [a] 6861.30

Cum 10864.53
Cum 5223.42
Cum 1978.16
Tonne 40519.15
Total [b] 58585.26

Hour 1398.00
Hour 2232.00
Total [b] 3630.00

6861.30
58585.26
3630.00
ete for 15 cum 69076.56
4605.10
Cum 4605.10

Nos 42.30

Total 4647.40
bridges
1161.85
Total 5809.25
124

Rate per Amount


580.93
= 6390.18
1

Cum

s and culverts
929.48
Total 5576.88
557.69
= 6134.57
1

Cum

and specifications

Nos 5.84
Nos 6.96
Nos 5.64

Nos 2.92
Nos 4.51
Nos 56.40
Total [a] 82.27

Kg 172.00

m 1260.00
125

Rate per Amount


Nos. 7.80
Nos. 15.00
Total [b] 1454.80
[a+b] 1537.07

0 76.85

Total 1613.92
bridges
403.48
Total 2017.40
201.74
= 2219.14
6
m

s and culverts
322.78
Total 1936.70
193.67
= 2130.37
6

velling course below


wing and technical
126

Rate per Amount


Nos 251.12
Nos 676.50
Nos 5640.00
Total [a] 6567.62

Cum 8175.33
Cum 5432.27
Cum 1305.86
Cum 1978.16
Tonne 27433.46
Total [b] 44325.08

Hour 1398.00
Hour 2232.00
Total [b] 3630.00
Total [a+b+c] 54522.70
bridges
13630.68
Total [a+b+c+d] 68153.38
6815.34
= 74968.72
15

cum

s and culverts
10904.54
Total [a+b+c+d] 65427.24
6542.72
= 71969.96
15

cum
127

Rate per Amount


including reinforcementand form
and technical specifications.

00 & 1700 & 2704

Nos 251.12
Nos 676.50
Nos 5922.00
Total [a] 6849.62

Tonne 40519.15
Cum 1978.16
Cum 10864.53
Cum 5223.42
Total [b] 58585.26

Hour 1398.00

Hour 2232.00
Total [c] 3630.00
CRETE MIXER
6849.62
58585.26
3630.00
[a+b+c] 69064.88
15
Cum
nforcements:

shifting to site, tying and placing in


Nos 128.48
128

Rate per Amount


Nos 1044.00
Nos 2256.00
Total [a] 3428.48

MT 47056.34
Kg 364.80
Total [b] 47421.14
Total [a+b] 50849.62
= 50849.62
CONCRETE MIXER including
nts

Cum 4604.33

0 92.09

MT 2542.48

Total 7238.90
bridges
1809.73
Total 9048.63
904.86
= 9953.49
1

Cum

s and culverts
1447.78
Total 8686.68
868.67
129

Rate per Amount


= 9555.35
1

Cum

essible fibre board in expansion


al specifications

arrying and fixing, etc. :


Nos 2.92
Nos 25.50
Nos 28.20
Total [a] 56.62

Sqm 2178.00

Total [b] 2178.00


[a+b] 2234.62
bridges
558.66
Total 2793.28
279.33
= 3072.61
12
Rm
s and culverts
130

Rate per Amount


446.92
Total 2681.54
268.15
= 2949.69
12

Rm
174

COMMON DATA - 2015-2016 (Bitumen & Emulsion rate as on 01.09.2015)

Circle: MADURAI Division: Madurai

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
1 Earthwork for foundation in ordinary soil: 304
A. By mechanical means
i) Depth up to 3 m excluding Err:509 / Cum Err:509 / Cum
dewatering
ii) Depth up to 3 m including Err:509 / Cum Err:509 / Cum
dewatering
iii) Depth 3 m to 6 m including Err:509 / Cum Err:509 / Cum
dewatering
Depth 3 m to 6 m including Err:509 / Cum Err:509 / Cum
dewatering
iv) Depth above 6 m including Err:509 / Cum Err:509 / Cum
dewatering
B. By Mechanical means
i) Depth upto 3 m including Err:509 / Cum 58.68 / Cum
dewatering
ii) Depth 3 to 6 m including Err:509 / Cum Err:509 / Cum
dewatering
iii) Depth above 6 m including Err:509 / Cum Err:509 / Cum
dewatering
2 Earthwork for foundation in ordinary rock 304
not requiring blasting
A. Manual means
i) Depth upto 3 m excluding Err:509 / Cum Err:509 / Cum
dewatering
B. Mechanical means:

i) Depth upto 3 m excluding Err:509 / Cum 70.21 / Cum


dewatering and not requiring
blasting

ii) Depth upto 3 m excluding Err:509 / Cum Err:509 / Cum


dewatering and requiring blasting

3 Sand filling-304 Err:509 / Cum Err:509 / Cum

375461281.xlsxabstract
175

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
4 PCC 1:3:6 for foundation-2100 Err:509 / Cum 4231.01 / Cum
using 40mm metal

5 Cement mortar 1:3 without Err:509 / Cum


contractor profit and overheads
6 Brickwork in CM 1:3 for Err:509 / Cum Err:509 / Cum
foundation-1300
7 Stone masonry in CM 1:3 for Err:509 / Cum Err:509 / Cum
foundation-1405.4

8 Random rubble masonry in C. M Err:509 / Cum Err:509 / Cum


1:3(coursed/uncoursed)-1405.3

9 PCC M 15 for foundation using Err:509 / Cum Err:509 / Cum


concrete mixer-1500,1700&2100

10 PCC M 20 for foundation using Err:509 / Cum 5651.90 / Cum


concrete mixer
11 PCC M 25 for foundation

a. Using concrete mixer 6397.58 / Cum 6141.68 / Cum


b. Using batching plant 5960.04 / Cum 5721.64 / Cum
12 PCC M 30 for foundation
a. Using concrete mixer 6438.89 / Cum 6181.33 / Cum
b. Using batching plant 5996.88 / Cum 5757.01 / Cum
13 RCC M 20 for foundation
a. Using concrete mixer 5993.71 / Cum 5753.96 / Cum
b. Using batching plant 5551.15 / Cum 5329.11 / Cum
14 RCC M 25 for foundation

a. Using concrete mixer 6509.95 / Cum 6249.55 / Cum

b. Using batching plant 6068.46 / Cum 5825.72 / Cum

15 RCC M 30 for foundation


a. Using concrete mixer 6525.78 / Cum 6264.74 / Cum
b. Using batching plant 6086.92 / Cum 5843.45 / Cum
16 RCC M 35 for foundation

375461281.xlsxabstract
176

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
a. Using concrete mixer 6638.50 / Cum 6372.96 / Cum
b. Using batching plant 6201.76 / Cum 5953.69 / Cum
17 Cast in situ 750 mm dia pipein RCC M 35 grade
a. Using concrete mixer 6622.61 / Cum 6357.70 / Cum

Using batching plant 6602.15 / Cum 6338.07 / Cum


18 Cast in situ 1000 mm dia pipein RCC M 35 grade

a. Using concrete mixer 10919.15 / Cum 10482.38 / Cum


Using batching plant 10899.81 / Cum 10463.81 / Cum
19 Cast in situ 1200 mm dia pipein RCC M 35 grade
a. Using concrete mixer 13942.93 / Cum 13385.22 / Cum

b. Using batching plant 13915.09 / Cum 13358.49 / Cum


20 Pile load test
21 Initial load test 300.00 / MT
22 Latreral load test 5000.00 / MT
23 Pile cap in RCC M 20
a. Using concrete mixer 5964.71 / Cum 5726.12 / Cum
b. Using batching plant 5542.18 / Cum 5320.49 / Cum
24 Pile cap in RCC M 25
a. Using concrete mixer 6515.64 / Cum 6255.02 / Cum
b. Using batching plant 6093.10 / Cum 5849.38 / Cum
25 Pile cap in RCC M 30
a. Using concrete mixer 6585.30 / Cum 6321.89 / Cum
b. Using batching plant 6162.76 / Cum 5916.25 / Cum
26 Pile cap in RCC M 35
a. Using concrete mixer 6730.95 / Cum 6461.71 / Cum
b. Using batching plant 6308.41 / Cum 6056.07 / Cum
27 Levelling course below pile cap 4997.91 / Cum 4798.00 / Cum
using concrete mixer
28 HYSD reinforcement for piles 68522.77 / MT 65781.86 / MT

375461281.xlsxabstract
177

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
29 MS reinforcement for piles 68848.32 / MT 66094.38 / MT
30 Brickwork in CM 1:3 1300&2200 Err:509 / Cum Err:509 / Cum

31 Pointing Brickwork in CM 1:3- Err:509 / Sqm Err:509 / Sqm


1300&2200
32 Plastering in CM 1:3-1300&2200 Err:509 / Sqm Err:509 / Sqm

33 RR masonry in CM 1:3 Err:509 / Cum Err:509 / Cum


(coursed/uncoursed) 1400&2200

34 CR masonry in CM 1:3( first sort ) Err:509 / Cum Err:509 / Cum


1400&2200
35 PCC M 15 for substructure
1500,1700&2200
a. Height upto 5m Err:509 / Cum Err:509 / Cum
b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
36 PCC M 20 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum 5977.97 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
37 PCC M 25 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum Err:509 / Cum

b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum

38 PCC M 25 for substructure using batching plant

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
39 PCC M 30 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum

40 PCC M 30 for substructure using batching plant

375461281.xlsxabstract
178

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
a. Height upto 5m Err:509 / Cum Err:509 / Cum
b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
41 RCC M 20 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
42 RCC M 20 for substructure using batching plant

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
43 RCC M 25 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum 6626.03 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
44 RCC M 25 for substructure using batching plant

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
45 RCC M 30 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
46 RCC M 30 for substructure using batching plant
a. Height upto 5m Err:509 / Cum Err:509 / Cum
b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
47 RCC M 35 for substructure using concrete mixer

a. Height upto 5m Err:509 / Cum Err:509 / Cum


b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum
48 RCC M 35 for substructure using batching plant

a. Height upto 5m Err:509 / Cum Err:509 / Cum

b. Height 5m to 10 m Err:509 / Cum Err:509 / Cum

375461281.xlsxabstract
179

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
49 HYSD bar reinforcement for sub Err:509 / MT 65944.85 / MT
structure 1600&2200
50 MS bar reinforcement for sub Err:509 / MT 65319.80 / MT
structure 1600&2200
51 Weep holes with 100mm dia AC Err:509 / Nos. 122.22 / Nos.
pipe 2706&2200
52 Back filling behind abutment, wing Err:509 / Cum 715.73 / Cum
and return walls (Granular
materials-710.1.4 of
IRC78&MORT&H 2200)

53 Filter media behind abutment, Err:509 / Cum 729.11 / Cum


wing and return walls(Granular
materials satisfying requirements
laid down in 2504.2.2 of
MORT&H-710.1.4 of
IRC78&MORT&H 2200)

54 RC C M 20 Solid Slab Superstructure using concrete


mixer 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
55 RC C M 20 T beam & slab Superstructure using
concrete mixer 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
56 RC C M 20 Solid Slab Superstructure using batching
plant 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
57 RC C M 20 T beam & slab Superstructure using
batching plant 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum

b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum

58 RC C M 25 solid slab Superstructure using concrete


mixer 1500,1600&1700
a. For height upto 5 m 7485.74 / Cum 7186.31 / Cum

375461281.xlsxabstract
180

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum

59 RC C M 25 T beam & slab Superstructure using


concrete mixer1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
60 RC C M 25 solid slab Superstructure using batching
plant1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
61 RC C M 25 T beam & slab Superstructure using
batching plant 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
62 RC C M 30 solid slab Superstructure using concrete
mixer1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
63 RC C M30 T beam & slab Superstructure using
concrete mixer1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
64 RC C M 30 solid slab Superstructure using
batchingplant1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum

b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum

65 RC C M 30 T beam & slab Superstructure using


batching plant 1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
66 RC C M 35 solid slab Superstructure using concrete
mixer1500,1600&1700
a. For height upto 5 m 7637.04 / Cum 7331.55 / Cum

375461281.xlsxabstract
181

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum

67 RC C M35 T beam & slab Superstructure using


concrete mixer1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
68 RC C M 35 solid slab Superstructure using
batchingplant1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
69 RCC M 35 T-Beam and slab Superstructure using
batching plant1500,1600&1700
a. For height upto 5 m Err:509 / Cum Err:509 / Cum
b. For height 5 - 10 m Err:509 / Cum Err:509 / Cum
70 HYSD bar reinforcement for 69918.23 / MT 67121.49 / MT
superstructure1600
CONFIRMING TO IS 1786
71 MS bar reinforcement for Err:509 / MT Err:509 / MT
superstructure1600
72 CC Wearing coat in M 30 6390.18 / cum 6134.57 / cum
Concrete using concrete mixer-
2702 (excluding reinforcement)
73 Wearing coat in Mastic Asphalt Err:509 / Sqm Err:509 / Sqm
12mm thick-515&2702 (60/70
grade bitumen)
74 RCC M 30 Railing cast in casting Err:509 / Rm
yard 1500,1600,1700&2703

75 RCC M 30 Railing cast in Err:509 / Rm Err:509 / Rm


situ1500,1600,1700&2703
76 Drainage spout 2705 369.86 / Each 355.06 / Each
77 PCC M 15 Levelling course 4997.91 / Cum 4798.00 / Cum
below approach slab-2700
using concrete mixer
78 RCC M 30 approach slab using 9953.49 / Cum 9555.35 / Cum
concrete mixer including
reinforcement1500,1600,1700&27
04
79 Copper plate expansion joint Err:509 / Rm Err:509 / Rm
12mm thick(2605)

375461281.xlsxabstract
182

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
80 20 mm thick fibre board 256.05 / Rm 245.81 / Rm
expansion joint-2605
81 20 mm thick premoulded joint 308.89 / Rm 296.53 / Rm
filler-2605
82 Joint sealing compound 1 cm 22.97 / Rm 22.05 / Rm
depth-2605
83 Boulder without wire crates-2503 1269.94 / cum 1219.14 / cum

84 PCC M 15 for CC blocks for 5097.87 / cum 4893.96 / cum


apron (0.5x0.5x0.5m)-2503
85 Pitching side slopes with 1269.94 / cum 1219.14 / cum
stone/boulders over filter media-
2504
86 Pitching side slopes with CC 5097.87 / cum 4893.96 / cum
blocks over filter media-2504-
(0.3x0.3x0.3m)
87 Filter materials below side slope 927.51 / cum 890.41 / cum
pitching -2504
88 Rubble stone laid in CM 1:3 over 6009.00 / cum 5768.64 / cum
cc bedding-2505
89 Flooring with CC blocks M 15 8921.01 / cum 8711.02 / cum
over cc bedding-2505
90 Dry rubble stone Flooring-2506 1687.18 / cum 1619.70 / cum

91 Flexible apron 1 m thick Dry 1321.97 / cum 1269.09 / cum


rubble stone Flooring -2507.2
92 Dismantling CC wearing course- 110.00 / sqm 105.60 / sqm
2809
93 Dismantling AC wearing course- 83.15 / sqm 79.82 / sqm
2809
94 Gravel packing to rough stone dry 791.91 / cum 760.23 / cum
packing
95 Rough stone dry packing for 1540.55 / cum 1478.93 / cum
revetment
96 Slurry seal for 5 mm thickness- 72.45 / Sqm
516
97 Slurry seal for 3 mm thickness- 50.29 / Sqm
516
98 Slurry seal for 1.5 mm thickness- 30.71 / Sqm
516

375461281.xlsxabstract
183

Minor bridges in
Major and Minor
S. No. Description of item
Bridges
road packages and
culverts
99 Fog spray-518 40.39 / Sqm

100 Crack prevention course SAM for 12.36 / Sqm


less than 6 mm crack-522
101 Crack prevention course SAM for 14.74 / Sqm
6 mm to 9 mmcrack-522
102 Crack prevention course SAM for 102.58 / Sqm
more than 9 mm crack-522
103 Cement Kerb M 20 using 291.12 / Rm
concrete mixer-408
104 20 mm thick PC using mini hot 158.14 / Sqm
mix plant -511-60/70 grade
bitumen
105 5th KM stone including painting, 3180.39 / each
lettering and fixing-804

106 KM stone including painting, 1898.74 / each


lettering and fixing-804

107 HM stone including painting, 534.52 / each


lettering and fixing-804

108 Boundary pillar including lettering 425.11 / each


and fixing but excluding painting-
806-IRC 25-1967

109 Pipe culverts:


a. Foundation in CC 1:3:6-408 3856.39 / cum

b. Supply of NP4 1000 mm RCC 2750.00 / Rm


pipes confirming to IS 458&
cluase 1010 MORT&H

c. Fixing of NP4 1000 mm single 170.24 / Rm


row RCC pipes specification 2900

d. Fixing of NP4 1000 mm two row 340.48 / Rm