You are on page 1of 14

Construction

Law Report
JULY 20 07 KEEPING YO U INF O RMED

TIME IS MONEY
The Condominium Developer’s Guide to Delay Claims

“Time is money” is an appropriate motto in


the field of high-rise condominium projects.
Yet, delays are an expected, although
unfortunate, reality of such projects.

Introduction
The developer is at the project’s centre, orchestrating the
progress of the project and dealing with all others involved
in the process including:

■ unit purchasers;

■ contractors;

■ lenders;

■ consultants, which may include architects,


engineers and cost consultants;.

■ the municipality; and

■ Tarion.

A developer is vulnerable to damage from delays because


the project revenue is fixed early in the process by the sale
price of the condominium units. Return on invested equity
is always diminished by delays. Further, some project costs
may be variable and sensitive to delays, such as financing
costs, especially where there is a variable interest rate,
and possibly construction costs, depending on whether
BY IRVING MARKS AND BARBARA GREEN the contracts are “stipulated price” or “cost plus”. When

Robins Appleby & Taub LLP Suite 2600, 120 Adelaide Street West, Toronto, ON M5H 1T1 (416) 868-1080
CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

project costs are sensitive to delays, the developer’s ultimate  municipality delays
return on investment is also sensitive to delay.  lender delays

In recent years, there has been little litigation driven by ■ Assessing damages in delay claims:
condominium unit purchasers on the basis of delay because  notice requirements
of a strong market and rising prices. Although delay may
 when is a party entitled to damages on
cause these purchasers inconvenience, the delay often does
the basis of delay?
not generate financial losses significant to justify a lawsuit.
Even if a purchaser ultimately backs out of the deal, the  the categories of delay:
developer can often sell the unit to a new purchaser for ■ excusable
more money.
■ non-excusable
While there has been an unprecedented run of rising prices, ■ compensable
market conditions could easily change. If prices fall, even
■ non-compensable
marginally, a delay could cause the developer to suffer
significant losses. In the worst case scenario, all of the  damages arising from delay
purchasers could terminate, leaving the developer to resell ■ foreseeability
all of the units at lower prices. In those circumstances,
■ additional construction costs
the developer would want to hold the responsible parties
accountable for the delay. This paper briefly addresses ■ loss of profits
the remedies available to the developer, and the risks the ■ contract limitations
developer faces as the target of delay lawsuits.
 supporting documents
Delay claims are frequently complicated, requiring an  expert evidence
analysis of complex factual and legal arguments. The
 mitigation of damages
number of parties and different legal relationships between
them often leads to multi-party litigation with numerous ■ Review of some typical terms in construction con-
crossclaims, counterclaims and third party claims. tracts:

 exclusion clauses/disclaimers
The topic of delay claims is so broad that entire textbooks
have been written on the subject. Given the scope of this  penalty claims vs. liquidated damages clauses
topic, the purpose of this paper is to introduce some key  “time is of the essence” clauses
concepts and issues which arise in delay claims from the
 arbitration clauses
perspective of the developer, as well as to provide some
practical tips to protect the developer, even before the  implied terms
project encounters a delay. ■ Defences to delay claims, including:

 “force majeure” clauses


The paper addresses the following topics:
■ Where delays can occur in a project:  concurrent delay

 developer delays  exclusion clauses

 general contactor delays ■ A checklist for success

 subcontractor delays

 consultant delays

Robins Appleby & Taub LLP 2 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

Where Delays Arise in a Condominium Project ■ excessive changes in requirements or design;


and Who May be Liable ■ defective or insufficient plans;
Delays can occur at any time and at more than one stage
■ the failure to obtain necessary work permits; and
of development and construction of a condominium project.
A delay at one step often leads to delays at other steps ■ the failure to provide or approve drawings in a
because the steps are so inter-dependent. Typical stages of reasonable time.
such a project include: Where some part of the construction must be carried out
by or on behalf of the developer before the contractor can
■ The developer purchases land suitable for the
perform its work under the contract, any delay in the work
project.
amounts to a breach of contract for which the developer
■ A concept or design for the project is developed. may be liable. However, if a contractor is delayed because
■ The developer obtains the necessary zoning other contractors have defaulted and the developer is
and development approvals from the municipal not responsible for the delay, the developer will not be
authorities. responsible for paying damages to the contractor arising
from the delay unless the contract states that the developer
■ Tarion registration.
must prevent such delays.3
■ Unit pre-sales.
When the developer causes delay, it commonly grants an
■ The developer obtains project financing.
extension of time to the contractor to complete its work.
■ The project is constructed. If the contractor accepts the extension from the developer
■ Unit purchasers take interim occupancy. without claiming damages for the delay, this may amount to
a “waiver” (or an acceptance) of the developer’s breach and
■ The condominium is registered.
may prevent the contractor from later claiming damages
■ Final closing. from the developer for delay.4

a) Delays Caused by the Developer


The relationship between a condominium unit purchaser b) Delays Caused by a Contractor
A contractor who is responsible for delay in the completion
and the developer, both with respect to delays and more
of work will be in breach of its contractual obligations and
generally, is governed by the terms of the Agreement of
may be liable to the developer for damages. A sufficient
Purchase and Sale. For new condominium units, the Ontario
delay may also enable the developer to terminate the
New Home Warranty Program Act also sets out a regime
contract altogether.5 In addition to the contractor’s duty
of permissible delays and limitations on the purchaser’s
to perform the work pursuant to the terms of the contract,
potential claims on the basis of delay.1
the contractor may have additional obligations under the
A contractor is entitled to assume that the work will be contract, such as compliance with statutory rules and
completed in the time provided for in the contract, and to regulations and by-laws. If the contractor fails to fulfil these
arrange other projects accordingly. Even if the contract obligations, this constitutes a breach of contract.6 Other
does not provide a specific completion date, the developer examples of delay caused by the contractor include:
must not do, or fail to do, anything to delay the contactor
■ contractor management and performance
in carrying out the work. A developer who causes delay by,
problems;
for example, directing work to be performed in a sequence
different than originally planned, imposing testing beyond ■ contractor management and performance
what is necessary, or interferes in some similar fashion, problems;
could be liable for interference.2 Other examples of delay ■ failure to properly staff the job;
caused by the developer include:

Robins Appleby & Taub LLP 3 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

■ failure to order materials and equipment in a For instance, in Axelrod v. City of Toronto, the Court ordered
timely fashion; and a municipality to issue demolition permits to a developer
■ the unavailability of labour, material or after its refusal to do so without proper grounds.11
equipment.
Legal proceedings against a municipality will likely cause
A contractor who incurs additional costs because of its further delays given that the judicial process is frequently
own delay is not entitled to recover such costs from the slow.
developer.7
f) Delays by the Lender
If a contractor knows in advance that it will not be able to The rights between a developer and its lender, typically
complete its work in a timely fashion, it may apply to the a large financial institution, are governed by the lending
developer for an extension of time. If the developer grants commitment agreement between them. A developer may
the extension and the work is completed within the extended have limited contracting freedom with a lender as the
time period, the contractor will not be considered to have lending agreements are frequently geared towards protecting
breached the contract. If the delay was solely the fault of the latter’s interests. Delays by a lender in making proper
the contractor, the developer is not required to grant an advances could result in a failure to pay contractors and
extension.8 the registration of construction liens. However, depending
on the terms of the agreement, a developer may have a
Standard form construction contracts have timelines
claim for breach of contract and damages for loss of profits
that specifically address the issue of delay. For instance,
in circumstances where the lender failed to abide by the
General Condition 6.5 of the stipulated price contract in
terms of their agreement which results in project delays.
CCDC 2-1994 contains a specific delay section, attached
For instance, in National Trust Co. v. Saks, the developer
as Appendix “A”.9
was successful in its claim against the lender for breach of
contract when the latter wrongfully disregarded the terms of
c) Delays Caused by Subcontractors
the loan agreement by demanding that the developer make
Delay caused by the subcontractors or the contractor’s
cash equity injections to pay cost overruns.12
suppliers is the contractor’s responsibility as far as the
developer is concerned.10

d) Delays Caused by Consultants Assessing Damages in Delay Claims


If work performed by a consultant is not timely or is The following section explores the topic of the computation
deficient, which leads to delay, the developer may have a of damages in delay claims and how notice provisions in
claim in contract or professional negligence against the the contract and the duty of the innocent party to mitigate
consultant. Examples of this are: design deficiencies, delay its losses impact the claim. In addition, the significance of
in approval of change work orders, and delays in payment proper documents and expert evidence on delay claims is
certification. briefly reviewed.

e) Delays by the Municipality a) Notice Requirements: A Possible Precondition


Practically speaking, it may be difficult and expensive to to a Damages Claim
successfully sue a municipality for causing development Construction contracts frequently require that a specific
delays. However, Courts have held municipalities liable for form of timely notice be given to the defaulting party as
delays in unique circumstances. An application can be made a precondition to preserving the innocent party’s right to
to Court under section 8 of the Building Code Act, 1992 to claim compensation for delay. It is essential that the notice
require issuance of a building permit or demolition permit. requirements of a contract be strictly adhered to in order

Robins Appleby & Taub LLP 4 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

to preserve the right to claim damages. Particulars must recover damages for breach of contract, and the breaching
be given in a timely fashion so that the defaulting party is party is excused from any further performance under the
notified that a claim will be advanced against it for costs contract. The developer may terminate the contract and
related to delays but has the opportunity to take protective retain other forces to complete the contractor’s work.15
measures.13
However, if the innocent party does not accept the repudiation,
the breaching party is not excused from further performance,
b) When is a Party Entitled to Damages on the
Basis of Delay? and the innocent party can still claim damages for the
breach of contract.16 Whether in any given circumstances
A delay can be categorized as “excusable” or “non-
the breach is sufficiently fundamental so as to amount to a
excusable”. To decide which category a delay falls into,
repudiation is in each case a question to be determined in
the construction contract is reviewed first to determine
light of the particular terms of that contract.17
whether it permits the delay and whether it provides for
entitlement to compensation or an extension of time in the
circumstances. c) Damages Arising From Delay
In order to recover damages, the innocent party must be
An “excusable” delay is a delay for which the claimant able to establish that there has been a breach of duty or
is entitled to an extension in the contract time, or contract, that it suffered a loss, and that the loss is a result
compensation for the delay, or both. If there is entitlement of the breach of contract or negligence. The purpose of
to compensation, as well as an extension in the contract awarding damages is to put the injured party, as far as
time, the delay is a “compensable excusable delay.” If the money can accomplish this, into the same position as if the
claimant is only entitled to an extension of the contract time, innocent party’s rights had not been violated.
the delay is a “non-compensable excusable delay”. Delays
Typical heads of damage for a delay claim made by a
not caused by a party, such as acts of G-d, severe weather,
developer include:
and natural disasters such as floods or fires, are generally
considered “non-compensable excusable delays”. When such ■ additional construction costs
delays occur, the developer typically is required to give the
■ overhead and carrying costs, such as interest and
contractor an extension of time to perform the contract,
property tax during the period of delay
but this does not permit the developer to make any claim
for additional costs arising out of the delay, or to terminate ■ liquidated damages (depending on the terms of
the contract on that basis. A “non-excusable delay” is one the contract)
for which the party is entitled to neither an extension in the ■ diminution of value of the project
contract time nor any monetary compensation.14
■ loss of profits
The usual remedy sought by a party to a building contract
is damages for breach of the contract. A claim for breach i) Foreseeability
Even if a delay amounts to a breach of contract, not all
of contract may only be made against the party with whom
damages are necessarily recoverable. Damages are only
the contract was made. If the breach is of such a nature
recoverable if they arise naturally from the breach or, in
that there is a “repudiation” of the contract (ie: the breach
some circumstances, if they could reasonably have been
goes to the root of the contract or there is a substantial
within the contemplation of the parties when they entered
failure of performance or the breaching party has indicated
into the contract. All other damages will be considered too
its intention to no longer be bound by the contract), the
remote. For instance, if a developer requires a building to be
innocent (ie: non-breaching) party may elect to accept the
completed by a certain date, and its purpose is to generate
repudiation and treat the contract as terminated by the
income, a contractor who fails to complete its work in time
breach. In these circumstances, the innocent party may

Robins Appleby & Taub LLP 5 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

will be liable to the developer for damages for loss of profits ordered damages to be paid pursuant to the method selected
only if the contractor actually knew that the building was by the parties and set out in the contract.23
required for such purpose, or if that purpose was reasonably
within the parties’ contemplation.18 d) Supporting Documents
Supporting documents are critical in proving that there
ii) Additional Construction Costs was a delay, that it was caused by the Defendant, that the
Since the purpose of a damages award is to grant full Plaintiff suffered compensable damages as a result of the
compensation, but not a windfall, if the developer is the delay, and that a particular measure of damages is proper
innocent party, the cost of completing or correcting the work in the circumstances.
over and above the contract price is the proper measure
The following are suggestions of steps and documents
of damages in many cases, especially when the contractor
that should be maintained throughout the course of the
failed to perform the work. It is usually more expensive
project:
to call in another contractor during the course of work to
complete it, and such additional costs must be paid by the ■ The developer should have a well-established
defaulting contractor if the developer reasonably incurred project schedule and maintain accurate and
such costs. In other cases, the proper measure of damages timely records of all delays, as they occur, and
is based on the loss in the value of the land.19 how the delay impacted upon the project. This
will assist the developer to corroborate any
iii) Loss of Profits consequential losses resulting from the delay.
Where a contractor can prove that it suffered a loss as a
■ Immediately put the responsible parties on
result of the developer’s breach, the measure of damages is
notice of the need to comply with a specific
the net loss occasioned by the breach.20 Where a contractor
deadline and that they will be held responsible
can establish that it has lost profit as a result of the owner’s
for any delay.
breach of contract, it will be entitled to recover lost profit as
damages.21 A contractor is also entitled to claim damages ■ Keep clear and accurate records of all contracts
for idle equipment and for office overheads as a result of related to the project.
the delay. Further, if the scope of the contractor’s work ■ Maintain detailed accounting records since the
is significantly changed by the owner during construction, losses will be financial.
the contractor will be entitled to the increased costs as
■ All staff involved in the construction project
damages.22
should keep detailed records of daily events
Loss of profit claims are complex and usually involve an during the course of construction.
analysis of actual profits as against budgeted or projected ■ Photos and video footage showing the status of
profits. The question is how much profit would have been a construction project on any given day are often
realized “but for” the delay. The analysis usually includes helpful in proving delay claims, as well as logs
a discount for the risk that the projections might not have and journals which recorded details of events
been achieved even if there were no delays. that transpired on site.

■ Keep all correspondence, as well as written notes


iv) Contract Limitations
of discussions.
Many contract clauses provide that if there is a delay,
recoverable damage will be computed in accordance with a ■ Any problems related to delays in the
particular formula or only using specified heads of recovery. construction schedule should be addressed during
In Goodfellow’s Trucking Ltd. v. New Brunswick, the Court

Robins Appleby & Taub LLP 6 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

meetings. Minutes of those meetings should be Tips and Traps of Common Construction
circulated to attendees for approval.24 Contract Clauses: Strategies for Examining
Contractual Terms
e) Expert Evidence The terms of the contract have clear implications on delay
In order to establish a claim for delay of any significant size, claims. For instance, what does the contract say about
expert evidence will be necessary. It is strongly recommended delivery dates? Are the dates firm? Does the contract make
that the expert be retained in the early stages of litigation “time of the essence”? Set out below is a brief analysis
so that the expert can assist in the preparation of pleadings, and practical tips regarding some common construction
assist with the discovery process, assist counsel to prepare contract terms, including: exclusion clauses, penalty and
the case for trial, and appear as a witness at trial. liquidated damages clauses, “time is of the essence”
provisions, arbitration clauses, as well as the effect of
At trial, experts are permitted to give evidence of the proper
implied contractual terms.
method to be adopted in assessing a delay claim as a matter
of industry practice, and testify as to any exceptions to
that method which should be made in the case. The expert a) Exclusion Clauses/Disclaimers
Construction contracts frequently contain clauses which
may also express an opinion about the type of effect that is
attempt to limit or exclude a party’s liability if certain events
generally caused by the delay of one branch of a construction
occur. Often, a developer includes such a provision stating
project upon other branches of the project. The expert can
that in no, or only limited, circumstances will it be liable to
also provide factual evidence about construction techniques
the contractor. If a developer seeks to exclude its liability for
and practice.25 Expert accounting evidence will also be
delay in respect of its own breaches of contract, it may do
required to establish a loss of profit claim.
so but it is mandatory that the disclaimer expressly provides
that it includes the developer’s own breach of contract.
f) Mitigation of Damages
Language such as “the developer shall in no circumstances
In the case of a breach of contract, the innocent party
be responsible to the contractor for damages resulting from
is required to mitigate (minimize) its damages by taking
the delay of the contractor’s work operations” has been
reasonable steps to protect itself from further loss. In other
found to be insufficient because it fails to include in express
words, the innocent party must behave in a reasonable
language the situation where the developer has breached its
manner with a view to ensuring that its damages resulting
contractual obligations.28
from the breach are as minimal as possible, which includes
seeking the most economical and efficient way of making up By contrast, in Perini Pacific Ltd. v. Greater Vancouver
for a delay. It may also include the least expensive method Sewerage & Drainage District (No. 2), the Supreme Court
of returning the innocent party to the same position. For of Canada held that the addition of the more specific phrase:
instance, the developer must attempt to replace a contract “whether or not such delay may have resulted from anything
as quickly as possible where a contractor has failed to done or not done by [the developer] under the contract” was
complete. The onus is on the party asserting that the an effective exclusion clause as this was exactly the kind of
innocent party has not mitigated its damages to prove that loss which precluded the claim according to the language
it did not do so.26 The innocent party’s failure to mitigate of the contract.29
could significantly reduce the damages ultimately awarded
to it by the court.27 Because exclusion clauses and disclaimers are strictly
construed, it is necessary that clear and unambiguous
language be used. If there is ambiguity, an exclusion
clause will be read strictly against the party for whose
benefit it was inserted. Therefore, the best tool to attack an
exclusion clause is to have it strictly construed against the

Robins Appleby & Taub LLP 7 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

interest of the party who put it forward, on the grounds of clause. Further, the developer will likely have to prove that
ambiguity.30 it suffered actual damages in the amount of the claimed
liquidated damages.35
There is no rule that necessarily invalidates an exclusion
clause in the event of a fundamental breach or other type Liquidated damages provisions for delay in completion are
of breach of contract.31 In deciding whether to enforce inapplicable if the contractor never started the work under
an exclusion clause in the face of a fundamental breach the contract, as they apply only once work has begun.36
of contract, the court will decide whether doing so would
be “unconscionable” or so unreasonable that the parties c) “Time is of the Essence” Provisions
could not have intended this result. “Unconscionability” Where a construction contract makes time “of the essence”,
usually arises in situations where there is a vast disparity the breach of an obligation calling for performance at a
of contractual bargaining power between two parties to specified time may amount to a breach of an essential
the contract so that the imposition of the disclaimer was element of the contract which can be treated by the innocent
essentially forced upon a party (usually the contractor) with party as discharging the agreement and relieving against
no real commercial choice but to accept the term. Where performance by the innocent party.37 In contracts where
there is equality of bargaining power, the courts will usually time is of the essence, even a 10-minute delay has been
give effect to the bargain.32 held to be a breach of this term.38 Therefore, when a time is
of the essence clause exists in a contract, strict compliance
b) Penalty Clauses vs. Liquidated Damages with time limits is imperative. Therefore, when a time is of
Clauses the essence clause exists in a contract, strict compliance
Construction contracts sometimes contain clauses which with time limits is imperative.
provide for the payment of a stipulated sum of money per day
for any delays in completing the work beyond the completion d) Arbitration Clauses
date in the contract. Such clauses may be characterized as Construction contracts often contain arbitration clauses,
either a liquidated damages clause or a penalty clause. such as the one set out in General Condition 8.2 of the CCDC
Stipulated Price Contract, attached as Appendix “A”. It is
Penalty clauses are void and unenforceable because a party strongly recommended that all contracts in a given project
cannot legally provide in a contract for the payment of a be consistent with respect to arbitration provisions. Either
penalty.33 For example, a late payment clause of $1,500.00 all project contracts should contain an arbitration clause, or
per day in a contract worth $59,000.00 to install new none should have this clause. This consistency may prevent
foundations and pillars and to replace 13 existing buildings procedural problems and a multiplicity of proceedings given
on new structures was held to bear no relation to reality, that section 7(1) of the Arbitration Act, 1991 provides that
nor was it a genuine attempt to make a pre-estimate of the a court proceeding must be stayed in favour of arbitration
damages likely to occur. It was therefore held to be a penalty when there is an agreement to arbitrate.
clause and void.34
Further, any arbitration clause contained in the construction
Parties to a contract are, however, permitted to provide contracts should specifically exclude arbitration where a
for a pre-estimate of damages which are likely to arise developer has been sued and wishes to commence third
in certain circumstances and to agree on the payment of party proceedings. Otherwise, the main action could proceed
liquidated damages in such circumstances. In order for a in court while the third party claim proceeds by arbitration,
liquidated damages clause to be considered valid, it must resulting in a multiplicity of proceedings and potentially
provide for payments which bear a relation to reality and inconsistent results.
must be a genuine attempt to make a pre-estimate of the
damages which are likely to occur. The amount should not However, these concerns are not usually an issue when
be excessive. Otherwise, the Court will view this as a penalty a developer has entered into a General Contract with a

Robins Appleby & Taub LLP 8 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

general contractor. In this situation, the developer has no of such a clause. If the event occurred without the clause
direct relationship with the subcontractors so any delay in the contract, the contract would be frustrated and the
claims would be governed solely by the contract between parties no longer bound to perform their future contractual
the developer and the general contractor (and the developer obligations.
would not need to bring claims against the subcontractors
In order to rely on a force majeure clause as a defence
for delay).
to a delay claim, the circumstance which occurred should
The prevalence of arbitration in construction cases (and not have been foreseen and could not have been prevented.
other commercial cases) has lead to a dearth of recent Strict compliance with the notice provisions set out in
reported court cases on these issues. While this may benefit the contract has been held to be a condition precedent to
the immediate parties (lower costs, speed and privacy), it invoking a force majeure clause.40
deprives subsequent parties and their lawyers the benefit
of guidance from decided case law. b) Concurrent Delay
Concurrent delay occurs when two or more causes of delay
e) Implied Terms operate at the same time. If different parties are responsible
Since it is almost impossible to foresee all situations that for different concurrent delays, the court will generally
may arise during the course of construction to provide for assign a percentage of fault to each responsible party. A
all of them in the contract, the court will sometimes have court will do the best it can to apportion responsibility on
to imply a term to address a situation when the parties did an estimated basis, on the basis of expert evidence. If the
not deal with it expressly. court cannot decide how to apportion the fault, an equal
percentage of the blame will be assigned to each party.41
In the absence of an express provision in a contract, it is an
implied term of a construction contract that the developer Concurrent delay is frequently used as a defence to a delay
will do everything reasonable to allow the contractor to claim. If a party can successfully assert a concurrent delay
complete its work, such as making timely payments and so that the court apportions the concurrent delay, the party
refraining from interfering with the contractor’s work which might be able to reduce such a claim by the percentage of
may result in delay in its completion.39 concurrent delay for which the claimant is responsible. For
instance, in Alberta Engineering Co. v. Blow, the contractor
brought an action for the balance of the contract owing. The
owner counterclaimed for delay on the basis that the project
Defences to Delay Claims
was delivered several months after the agreed completion
Depending on the circumstances, there may be some
date and the owner lost rental income as a result. The
available grounds to reduce or eliminate a delay claim. Set
contractor asserted that the owner was responsible for some
out below is a brief analysis of some common defences:
concurrent delay. The court attributed over a quarter of the
“force majeure” clauses, concurrent delay as a defence,
concurrent delay to the owner, thereby reducing the owner’s
and disclaimer clauses.
claim for rent.42

a) “Force Majeure” Clauses Further, if a party can prove that an excusable but non-
Frustration of a contract occurs when its performance compensable delay ran concurrently with the compensable
becomes impossible due to a supervening event caused by delay, the party can try to entirely defeat the delay claim
neither party, and not within their contemplation. Many on the grounds that the non-compensable delay overrides
condominium construction contracts contain a force the compensable delay such that only an extension of time
majeure clause to address these situations. Section 6.5.2 of is permitted.43
the CCDC-2 1994, set out in Appendix “A”, is an example

Robins Appleby & Taub LLP 9 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

Proving a concurrent delay may reduce or defeat the delay APPENDIX “A”
claim even when the defending party is not asserting a delay
GC 6.5 DELAYS
claim itself.44 6.5.1 If the Contractor is delayed in the performance of
the Work by an action or omission of the Owner,
c) Exclusion Clauses Consultant, or anyone employed or engaged by them
Exclusion clauses, also known as disclaimers, are a possible directly or indirectly, contrary to the provisions of
defence to a delay claim, as set out above. the Contract Documents, then the Contract Time
shall be extended for such reasonable time as the
Consultant may recommend in consultation with
Conclusion and Checklist for Success the Contractor. The Contractor shall be reimbursed
Preparation in advance is the key to a successful delay claim by the Owner for reasonable costs incurred by the
and will assist in the defence of any such claim. Below is Contractor as the result of such delay.
a short checklist to assist the developer to prepare itself.
6.5.2 If the Contractor is delayed in the performance of
These steps are summarized in greater detail above, and
the Work by a stop work order issued by a court
should be considered and, where applicable, undertaken
or other public authority and providing that such
from the outset of the project and on an on-going basis
order was not issued as the result of an act or
throughout the project:
fault of the Contractor or any person employed or
■ take care in the review and co-ordination of all engaged by the Contractor directly or indirectly,
project contracts; then the Contract Time shall be extended for such
reasonable time as the Consultant may recommend
■ establish and maintain a project schedule;
in consultation with the Contractor. The Contractor
■ maintain records of construction progress; shall be reimbursed by the Owner for reasonable
■ maintain proper accounting records; costs incurred by the Contractor as the result of
such delay.
■ comply with all contractual notice provisions;

■ act reasonably to mitigate losses; and 6.5.3 If the Contractor is delayed in the performance
of the Work by labour disputes, strikes, lock-outs
■ be prepared to devote the time, attention and
(including lock-outs decreed or recommended for its
money necessary to win. Litigation is expensive
members by a recognized contractors’ association,
and it may end up becoming the developer’s next
of which the Contractor is a member or to which the
project! „
Contractor is otherwise bound), fire, unusual delay
by common carriers or unavoidable casualties, or
without limit to any of the foregoing, by a cause
beyond the Contractor’s control, then the Contract
Time shall be extended for such reasonable time
as the Consultant may recommend in consultation
with the Contractor. The extension of time shall not
be less than the time lost as the result of the event
causing the delay, unless the Contractor agrees
to a shorter extension. The Contractor shall not
be entitled to payment for costs incurred by such

Robins Appleby & Taub LLP 10 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

delays unless such delays result from actions by of the matter in dispute and the relevant provisions
the Owner. of the Contract Documents. The responding party
shall send a notice in writing of reply to the dispute
6.5.4 No extension shall be made for delay unless notice in within 10 Working Days after receipt of the notice
writing of claim is given to the Consultant not later of dispute setting out particulars of this response
than 10 Working Days after the commencement and any relevant provisions of the Contract
of delay, providing however, that in the case of a Documents.
continuing cause of delay only one notice of claim
shall be necessary. 8.2.3 The parties shall make all reasonable efforts to
resolve their dispute by amicable negotiations and
6.5.5 If no schedule is made under paragraph 2.2.9 of agree to provide, without prejudice, frank, candid
GC 2.2 - ROLE OF THE CONSULTANT [ie: the and timely disclosure of relevant facts, information,
Consultant will furnish Supplemental Instructions and documents to facilitate these negotiations.
to the Contractor with reasonable promptness or
in accordance with a schedule agreed to by the 8.2.4 After a period of 10 Working Days following
Consultant and the Contractor], no claim for delay receipt of a responding party’s notice in writing
shall be allowed because of failure of the Consultant of reply under paragraph 8.2.2, the parties shall
to furnish instructions until 10 Working Days after request the Project Mediator to assist the parties
demand for such instructions has been made and to reach agreement on any unresolved dispute.
not then, unless the claim is reasonable.”] The mediated negotiations shall be conducted in
accordance with the latest edition of the Rules for
GC 8.2 NEGOTIATION, MEDIATION, AND Mediation of CCDC 2 Construction Disputes.
ARBITRATION
8.2.5 If the dispute has not been resolved within 10
8.2.1 In accordance with the latest edition of the Rules
Working Days after the Project Mediator was
for Mediation of CCDC 2 Construction Disputes,
requested under paragraph 8.2.4 or within such
the parties shall appoint a Project Mediator
further period agreed by the parties, the Project
.1 within 30 days after the Contract was Mediator shall terminate the mediated negotiations
awarded, or by giving notice in writing to both parties.

.2 if the parties neglected to make an appoint- 8.2.6 By giving a notice in writing to the other party,
ment within the 30 day period, within 15 not later than 10 Working Days after the date
days after either party by notice in writing of termination of the mediated negotiations under
requests that the Project Mediator be ap- paragraph 8.2.5, either party may refer the dispute
pointed. to be finally resolved by arbitration under the latest
8.2.2 A party shall be conclusively deemed to have edition of the Rules for Arbitration of CCDC 2
accepted a finding of the Consultant under GC Construction Disputes. The arbitration shall be
2.2 - ROLE OF THE CONSULTANT and to have conducted in the jurisdiction of the Place of the
expressly waived and released the other party from Work.
any claims in respect of the particular matter dealt
8.2.7 On expiration of the 10 Working Days, the
with in that finding unless, within 15 Working Days
arbitration agreement under paragraph 8.2.6 is not
after receipt of that finding, the party sends a
binding on the parties and, if a notice is not given
notice in writing of dispute to the other party and
under paragraph 8.2.6 within the required time,
to the Consultant, which contains the particulars
the parties may refer the unresolved dispute to the

Robins Appleby & Taub LLP 11 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

courts or to any other form of dispute resolution, Endnotes


including arbitration, which they have agreed to 1. Ontario New Home Warranty Program Act, R.S.O.
use. 1990, c. O.31

2. Immanuel Goldsmith and Thomas G. Heintzman,


8.2.8 If neither party requires by notice in writing given
Goldsmith on Canadian Building Contracts, 4th
within 10 Working Days of the date of notice
(Toronto: Thomson Carswell, 1988) at 5-9
requesting arbitration in paragraph 8.2.6 that
a dispute be arbitrated immediately, all disputes 3. Ibid.
referred to arbitration as provided in paragraph 4. Esposito, Anna M. and Maria Tassou, “Overview of
8.2.6 shall be Construction Delay Claims and Delay Damages” in
Construction Delay Claim: Following the Critical Path,
.1 held in abeyance until
Ontario Bar Association, Continuing Legal Education
(1) Substantial Performance of the Work, [CLE Program] (2006: Toronto, Ontario) at 3.
(2) the Contract has been terminated, or 5. Anderson Industrial Doors Ltd. v. Genstar Construction
(3) the Contractor has abandoned the Work, Ltd. [1985] CarswellBC 768 (B.C.S.C.)

whichever is earlier, and Supra, note 2 at 5-16

.2 consolidated into a single arbitration under 6. Supra, note 2 at 5-18


the rules governing the arbitration under 7. Josyln & Olsen Contractors Ltd. v. Bouey [1976]
paragraph 8.2.6. CarswellAlta 21 (A.C.A.)

8. Supra, note 4 at 4

9. “CCDC” stands for “Canadian Construction Documents


Committee”, which is a joint committee comprised of
owners and representatives of various institutes. The
italicized terms are defined terms in the contract.

10. Supra, note 2 at 5-17

11. [1984] CarswellOnt 519 (Div. Ct.); (1984) 13 D.L.R.


(4th) 634 (H.C.J.); varied at [1985] O.J. No. 2664
(H.C.J.)

12. [1998] CarswellOnt 2554 (O.C.A.)

13. Supra, note 4 at 9

W.J. Kenny, Cook Duke Cox (Edmonton-Calgary), Delay


Claims at 37(source unknown)

For further reading on the issue of the importance


of timely notice on such claims, please see: Esposito,
Anna M. and Maria Tassou, “Overview of Construction
Delay Claims and Delay Damages” in Construction
Delay Claim: Following the Critical Path, Ontario
Bar Association, Continuing Legal Education [CLE
Program] (2006: Toronto, Ontario) at 9 to 12.

Robins Appleby & Taub LLP 12 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

14. Supra, note 4 at 2 and 3 For a lengthier discussion on this topic, please see this
article at pages 3 and 4 (ecarswell).
15. Torbray (Town Council) v. Metro Enrg. & Const. Ltd.
(1980) 30 Nfld. & P.E.I.E. 298 (Nfld. T.D.) 29. [1967] CarswellBC 187 (S.C.C.)

16. Supra, note 2 at 6-3 and 6-4 30. W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),
Delay Claims at 32 (source unknown)
17. Ibid, at 6-5
31. A fundamental breach can be defined as a breach going
18. Smith v. Tennant (1890), 20 O.R. 180
to the root of the contract, or one based on performance
Can. Foundry Co. v. Edmonton Portland Cement Co. that is totally different from that which the contract
(1918) CarswellAlta 157 contemplated.
(P.C.). 32. Syncrude Canada Ltd. v. Hunter Engineering Co.
19. Supra, note 2 at 6-9 and 6-10 [1989] CarswellBC 37 (S.C.C.)

20. Pendivic Contracting Co. v. International Nickel Co. W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),
[1975] CarswellOnt 299 (S.C.C.) Delay Claims at 32 (source unknown).

21. Lowe v. Robb Engineering Co. [1905] CarswellNS 11 Some other cases that have considered the effect
(N.S.S.C.) of exclusion clauses in the context of construction
delay claims are: Alden Contracting Ltd. v. Newman
22. Shore & Horowitz Construction Co. & Franki of
Bros. Ltd. [1997] CarswellOnt 3734 (Gen. Div.) and
Canada Ltd. [1964] CarswellOnt 70 (S.C.C.)
Summitville Consolidated Mining Co. v. Klohn Leonoff
23. [2003] CarswellNB 587 (N.B.Q.B.); aff’d at [2005] [1989] CarswellBC 697 (B.C.S.C.). For further reading
CarswellNB 411 (N.B.C.A.) on the topic of exclusion clauses, please see: Mueller,
24. Supra, note 4 at 12 and 13 Warren H.O. “Contractual Exclusion and Limitation
of Delay Claims” 47 C.L.R. (3d) 5 (2005).
25. Cogar Estate v. Central Mountain Air Services Ltd.
[1992] CarswellBC 305 (B.C.C.A.) 33. Covert v. Janzen (No. 2) [1908] CarswellSask 128
(S.C.A.)
26. W.J. Kenny, Cook Duke Cox (Edmonton-Calgary),
Delay Claims at 41 (source unknown) Macdonald v. Northwest Biscuit Co. [1924]
CarswellAlta 84 (A.C.A.)
27. Some cases which address the duty to mitigate and the
effect of mitigation on a claim for damages are: Rice 34. H.A.R. Construction Ltd. v. DeMerchant Construction
v. Sockett [1913] CarswellOnt 425 (O.C.A.); Sault [1989] CarswellNB 68 (N.B.Q.B.)
Ste. Marie (City) v. Proctor & Redfern Ltd. [1986] 35. Calgary v. Janse-Mitchell Const. Co. [1919]
CarswellOnt 785 (H.C.J.); and Westland Investment CarswellAlta 156 (S.C.C.)
Corp. v. Carswell Collins Ltd. [1996] CarswellAlta 29
36. Lembke v. Chin Wing [1912] CarswellBC 208
(Alta Q.B.).
(B.C.S.C.)
28. Westcounty Construction Ltd. v. Nova Scotia [1985]
37. 1473587 Ontario Inc. v. Jackson [2005] CarswellOnt
CarswellNS 124 (N.S.T.D.)
712 (S.C.J.); aff’d at [2005] CarswellOnt 3282
D.J. Lowe (1980) Ltd. v. Nova Scotia (Attorney (C.A.)
General) [1993] CarswellNS 152
38. Union Eagle Ltd. v. Golden Achievement Ltd., [1997]
Mueller, Warren H.O. “Contractual Exclusion and A.C. 514 (Hong Kong P.C.), referred to with approval in
Limitation of Delay Claims” 47 C.L.R. (3d) 5 (2005) 1473587 Ontario Inc. v. Jackson [2005] CarswellOnt
at 4 and 22 (note: page references are to ecarswell). 712 (S.C.J.) and in Harris v. McNeeley (1998) 21

Robins Appleby & Taub LLP 13 (416) 868-1080


CONSTRUCTION LAW REPORT “Time is Money” The Condominium Developer’s Guide to Delay Claims JULY 2007

R.P.R. (3d) 291; aff’d at (2000) 47, O.R. (3d) 161


(O.C.A.)

39. W.J. Crowe Ltd. v. Pigott Construction Ltd. [1963]


CarswellOnt 64 (S.C.C.)

Smith v. Johnson Brothers Co. [1953] CarswellOnt


100 (H.C.J.) Irving Marks is the senior partner of
thelitigation group. Irving has extensive
W.A. Stephenson Construction (Western) Ltd. v. Metro
experience in all aspects of business litigation
Canada Ltd. [1987] CarswellBC 675 (B.C.S.C.)
in the superior and appellate courts.
Supra, note 4 at 4 and 5.
Barbara Green is a senior associate in the
40. Some cases which have considered the effect of a force
litigation group, focusing on commercial
majeure clause are: Perini Pacific Ltd. v. Greater
litigation with an emphasis on real property
Vancouver Sewerage & Drainage District [1966]
disputes, commercial leasing, condominium
CarswellBC 182 (B.C.C.A.), aff’d at [1967] S.C.R. 189
litigation, banking litigation and corporate
(S.C.C.) and World Land Ltd. v. Daon Development
disputes.
Corp. [1982] CarswellAlta 131.

Supra, note 2 at 1-66.

Supra, note 4 at 5 - 7.

41. Korban Inc. v. Pigott Construction Ltd. [1993]


CarswellOnt 825 (Gen. Div.)

Supra, note 4 at 15

For further reading on the subject of concurrent delay,


please see: Grenier, Glenn. “Evaluating Concurrent
Delay - Unscrambling the Egg.” 53 C.L.R. (3d) 46
(2006).

42. [1914] CarswellAlta 165 (Alta T.D.)

Grenier, Glenn. “Evaluating Concurrent Delay -


Unscrambling the Egg.” 53 C.L.R. (3d) 46 (2006) at
8. provides expertise in all areas of business law
including commercial real estate, municipal
43. Grenier, Glenn. “Evaluating Concurrent Delay -
and property tax assessment, banking and
Unscrambling the Egg.” 53 C.L.R. (3d) 46 (2006) at
insolvency law, tax law and estate planning,
8.
commercial litigation and corporate law.
44. Ibid, at 11

Robins Appleby & Taub LLP 14 (416) 868-1080

You might also like