RR1 And RR2 Rates

CONCRETE G25 (for 2.5mᶟ)

RR2(base level to 1st floor slab level)


JCB 3 HRS 3*3500 10500
OPERATOR 3 HRS 2000/8*3 750
SKILL 16 HRS 2000/8*15 4000
UNSKILL 48 HRS 1500/8*40 9000
CURING 28 HRS 1500/8*28 5250
G25 READYMIX 2.5m3 price 14586*2.5 36465
Overhead 25% 16491.25
Total price for 2.5mᶟ 82456.25
So, 1mᶟ Total cost 32,982.50

RR1(base level to 1st floor slab level)


SKILL 15 HRS 2000/8*15 3750
UNSKILL 40 HRS 1500/8*40 7500
CURING 28 HRS 1500/8*28 5250
G25 READYMIX 2.5m3 price 16773*2.5 41932.5
Overhead 25% 14608.125
Total price for 2.5mᶟ 73040.625
So, 1mᶟ Total cost 29,216.25

RR1 ( 1st floor to roof level )


add 5% 30677.0625

RR2 ( 1st floor to roof level )


add 5% 34631.625

RR1 (roof leve to water tank level )


add 7% 31,261.39

RR2 (roof leve to water tank level )


add 7% 35,291.28

EXCAVATION
for 8 mᶟ (not exceeding 1m)
Excavator 8hrs 1700/8 1700
Operator 8hrs 2000/8 2000
Unskill 8hrs 1500/8 1500
Backfilling
Unskill 32hrs 1500/8 6000
Skill 16hrs 2000/8 4000
wacker 16hrs 1000/8 2000
Total 17200
For 1mᶟ 2,150.00

1m to 2m
add 200% 4300

2m to 5m( including shoring)


Excavator 8hrs 1700/8 1700
JCB 2hrs 2500/8 625
Operator 8hrs 2000/8 2000
Unskill 8hrs 1500/8 1500
Backfilling
Unskill 32hrs 1500/8 6000
Skill 16hrs 2000/8 4000
wacker 16hrs 1000/8 2000
Total 17825
For 1mᶟ 2228.13
Overhead 25% 2785.16
Shoring 4363
Total 7,148.16

Removing top soil (150 mm depth) 49.5m³


Labour component
Labour 16 hrs 1800/8 3000
JCB operator 16 hrs 2000/8 4000
JCB 16 hrs 2500/hr 5000
Transprtiong 8hrs 3000/8 3000
total 15000
Overhead 25% 18750
For 1m³ 378.79

Filling ( 20m³ )
Labour 40hrs 1500/8 7500
Skill labour 24 hrs 2000/8 6000
Transporting soil 5hrs 3000/8 1875
wacker 10hrs 5000/8 6250
total 21625
Overhead 25% 27031.25
For 1m³ 1,351.56

Aggrigate Filling (2.83m³)


Labour 40hrs 1500/8 7500
Aggrigate 1m³ 1m³ 4000 4000
Total 11500
Overhead 25% 14375
For 1m³ 5,079.51

Formwork
Formwork For Column (1.5 m²) Base to Slab bottomlevel)
Labour 8Hrs 1500/8 1500
Skill Labours 4 Hrs 2000/8 1000
Powersaw 2Hrs 1000/8 250
Plywood 1.5 m² 4800/2.88 2571.43
2x2 trust 9.6m 133/m 1276.8
2x4 trust 4.8m 224/m 1075.2
Acrowjack 4nos 15/day 60
Nails 0.35 Kg 220/kg 77.00
Mould oil .25 Ltr 402.5/Ltr 100.63
10% wastage 5010.49
Overhead 25% 16,151.93
Total 12,921.54
For 1m² 10,767.95
3time usage 3,589.32

Formwork For Column (1.5 m²)1st floor levelto roof level)


Add 5% 3,768.78
Formwork For Column (1.5 m²)roof level to water tank beam level
Add 7% 3,840.57

Form work for Beams (5 m²)


Labour 36Hrs 1500/8 6750
Skill Labours 12 Hrs 2000/8 3000
Powersaw 5Hrs 1000/8 625
Plywood 5 m² 4800/2.88 8571.43
2x2 trust 29.85m 133/m 3970.05
2x4 trust 14.925m 224/m 3343.2
Acrowjack 9nos 15/day 2835
Nails .5 Kg 220/kg 110.00
Mould oil 1.6 Ltr 402.5/Ltr 644.00
10% wastage 16059.08
Total 29094.68
Overhead 25% 36,368.35
For 1m² 7,273.67
3time usage 2,424.56

Form work for Slabs (26.25 m²)


Labour 64Hrs 1500/8 12000
Skill Labours 32 Hrs 2000/8 8000
Powersaw 10Hrs 1000/8 1250
Plywood 26.25 m² 4800/2.88 45000.00
2x2 trust 26m 133/m 3458
GI pipe 26m 20/day 2520
Nails 3 Kg 220/kg 660.00
Mould oil 8.75 Ltr 402.5/Ltr 3521.88
10% wastage 73240.19
Acrowjack 50nos 15/day 21000
Total 170650.06
Overhead 25% 213,312.58
For 1m² 8,126.19
3time usage 2,708.73

Form work for column footing (8.64m²)


Labour 32Hrs 1500/8 6000
Skill Labour 16Hrs 2000/8 4000
Powersaw 4Hrs 1000/8 500
Plywood 8.64 m² 4800/2.88 14400
2x2 trust 11.2 m 133/m 1489.6
Nails .700/kg 220/kg 154
Mould oil 1.5Ltr 402.5/Ltr 603.75
10% wastage 2714.735
Total 29862.085
Overhead 25% 7465.52125
For 1m² 4320.324797
3time usage 1440.11

Reinforcement (1.95T)
Labour 600hrs 1500/8 112500
Skill Labousr 400Hrs 2000/8 100000
Bar Bender 24Hrs 1500/8 4500
Bar Cutter 40Hrs 1500/8 7500
Grinder 8Hrs 700/8 700
Binding Wire 100Kg 140/kg 14000
1T Tor steel 1T 120000/T 120,000.00
Total 359200
Overhead 25% 449000
For 1T 230,256.41
Brick (3m³ 225 thick)
Labour 56Hrs 1500/8 10500
Skill Labousr 32Hrs 2000/8 8000
Cement 6nos 975/bag 5850
Sand 1cube 14500/1cube 14500
Bricks 1600nos 16/brick 25600
Scafolding 3%/Labour 555
Tools 3%/Labour 555
Transport 3Hrs 2000/8 750
Total 66310
Wastage 10% 4595
Overhead 25% 17726.25
For 1m³ 29,543.75

112.5 thick (10m²)


Labour 36Hrs 1500/8 6750
Skill Labousr 20Hrs 2000/8 5000
Cement 2nos 975/bag 1950
Sand 0.5cube 14500/1cube 7250
Bricks 600nos 16/brick 9600
Transport 1Hrs 2000/8 250
Total 30800
Wastage 10% 1880
Overhead 25% 8170
For 1m³ 4,085.00

Plastering (10m² 16mm thick 1:3)


Labour 24Hrs 1500/8 4500
Skill Labousr 20Hrs 2000/8 5000
Cement 2.5nos 975/bag 2437.5
Sand 0.25cube 14500/1cube 3625
Scafolding 3%/Labour 285
Transport 2Hrs 2000/8 500
Tools 3%/Labour 285
Total 16347.5
Overhead 25% 20434.375
For 1m³ 2,043.44

Plastering (10m² 16mm thick 1:1:5)


Labour 20Hrs 1500/8 3750
Skill Labousr 16Hrs 2000/8 4000
Cement 1.25nos 975/bag 1218.75
Sand 0.25cube 14500/1cube 3625
Lime 0.75bags 300/20 11.25
Scafolding 3%/Labour 232.5
Transport 2Hrs 2000/8 500
Tools 3%/Labour 232.5
Total 13337.5
Overhead 25% 16671.875
For 1m³ 1,667.19

Rubble (13.2m³ 1:5)


Labour 320Hrs 1500/8 60000
Skill Labousr 192Hrs 2000/8 48000
Cement 28nos 975/bag 27300
Sand 4.5cube 14500/1cube 65250
Transport 16Hrs 2000/8 4000
Tools 3%/Labour 3240
Total 207790
Overhead 25% 259737.5
For 1m³ 19,677.08

Roof Frame (9.3m²)

sheet 9.3/m² 2513/m² 23370.9


2x2 15.3/m 359/m 5492.7
4x22 22/m 1049/m 23078
Foil 9.3/m² 576/m 5356.8
Net 9.3/m² 273/m 2538.9
Total 59837.3
Overhead 15% (according to site
conditions 8975.595
for 1m² 7,399.24
Shoring (11.5m ²,20days)
Labour component
Labour (for handling GI pipe) 24 hrs 1500/8 4500
Riggers ( for clamping and fixing board) 16 hrs 2000/8 4000
Material Component
GI pipe 3.4 nos 3.4*3000 10200
18mm thick plywood board 04 nos 4*2960 11840
Acrow jack 32 nos 32*15*20 9600
Total 40140
Overhead 25% 50175
For 1m² 4363.043
`