You are on page 1of 17

GOVERNMENT OF ANDHRA PRADESH

PANCHAYATRAJ ENGINEERING DEPARTMENT

RECASTED ESTIMATE

Name of the Work : Construction of culvert at Pedakadimi

Estimate Amount Rs.1.00 lakhs

Grant : ZPGF

DISTRICT : WEST GODAVARI

CIRCLE : ELURU

DIVISION : ELURU

SUB-DIVISION : ELURU

MANDAL : PEDAVEGI
mi
SPECIFICATION REPORT

Name of the Work : Construction of culvert at Pedakadimi

Estimate Amount Rs.1.00 lakhs

The work"Construction of culvert at Pedakadimi",Est.Cost.Rs.1.00 lakhs was sanctioned under


ZPGF 2007-2008 vide Progs.Rc.No C1/4529/2007 Dt.19.9.2007 of the CEO,ZP,Eluru

The estimate for the work was technically sanctioned vide SDR No.394/2007-08 Dt.13.11.2007
of the Dy.E.E,PRI,Eluru with the following provisions:-

1.Curtain walls with CC(1:3:6) on four sides


2.RCC NP2 class hume pipes of 300mm dia along with collars
3.CC(1:2:4) for Ramp

But after inspection of the work spot and as per the local enquiry,it is found that a skew slab
culvert of 2.00m span and 17.00m length is necessary to divert the water flow from right side of the road to left side.
Further,it is necessary to provide 600mm dia NP3 class RCC pipes to guide run-off water from the street on right
side into the slab culvert,so that there will not be any problem for formation of approaches on all the three sides to
fecilitate traffic without any hindrance.

But due to paucity of funds,only the following provisions could be accomodated in the present
estimate:-
1.Earth work excavation for abutments
2.M10 grade PCC of 0.15m thick as bed concrete
3.Abutments upto a height of 0.58m using PCC M15 grade nominal mix.

The Hon'ble MLA,Denduluru has proposed the balance work under CDP grant for an amount of
Rs.3.00 lakhs(Copy of the letter enclosed).The following balance provisions will be made in that estimate of
obtaining administrative sanction:-

1.Abutments for the balance height of 0.97m


2.Bed blocks of 0.45m width and 0.23m thickness using M20 grade nominal mix
3.Deck slab of 0.275m thickness using RCC M20 grade nominal mix
4.Cost,supply and laying of 600mm dia RCC NP3 class plain ended pipes---5.00 Rmt
5.Formation of approaches with barrowed earth on three sides---
6.Formation of GSB layer of 0.15m thickness on three sides---

Further the following lump sum provisions are also made in the present estimate:-

1)Provision for VAT @ 4.00%


2)QC charges @ 0.5%
3)Provision for insurance@ 0.5%

The estimate is prepared as per the current SSR,i.e.2010-2011 rates and as per
the A.P Revised Standard data work will be carried out as per APDSS.
Asst.Executive Engineer Dy.Executive Engineer
PRI,Eluru PRI,Eluru
RT

mount Rs.1.00 lakhs

t.Rs.1.00 lakhs was sanctioned under

e SDR No.394/2007-08 Dt.13.11.2007

enquiry,it is found that a skew slab


ow from right side of the road to left side.
e run-off water from the street on right
of approaches on all the three sides to

could be accomodated in the present

de nominal mix.

work under CDP grant for an amount of


s will be made in that estimate of

M20 grade nominal mix

lain ended pipes---5.00 Rmt

sent estimate:-

0-2011 rates and as per


SUPPLIMENTARY DATA SHEET

Name of the Work : Construction of culvert at Pedakadimi


Estimate Amount Rs.1.00 lakhs
Index-code S. No Description Unit Quantity Rate Rs.
1 2 3 4 5

RBR-FNDN-1 1 Excavation for Structures


Earthwork in excavation for structures as per drawing
and technical specifications Clause 305.1 including
setting out, construction of shoring and bracing,
removal of stumps and other deleterious material and
disposal upto a lead of 50 m, dressing of sides and
bottom and backfilling in trenches with excavated
suitable material as per Technical Specification 305
MORD / 304 MORTH

Note : Classifications of Earth Work Specification


are as per 302.2.1(a) of MORD and 301.2.1 of
MORT&H
(B) Mechanical Means
i Upto 3 m depth
Unit = cum
Taking output = 240 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 8.32 196.00
b) Machinery
Hydraulic Excavator 1 cum bucket capacity hour 6.00 1808.5
Seinorage charges for earth@Rs22/- per Cum
c&d) Overheads & Contractors Profit
Add MA@25% on labour charges
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent
of labour cost. Assessment for dewatering shall be made as per site conditions.
2 Filling in foundation trenches as per drawing and
RBR-FNDN-2 technical specification Clause 305.3.9 MORD & 304
MORTH
I Sand filling
Unit = cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.31 196.00
b) Material
Sand cum 1.05 814.21
Sienorage charges for sand cum 1.05 40.00
Add MA@25% on labour charges
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
3 Providing concrete for plain/reinforced concrete in
open foundations using 40 mm nominal size
Graded hard stone aggregate, mechanically mixed,
placed in foundation and compacted by vibration
RBR-FNDN-4 including curing for 14 days complete as per
drawings and technical specifications Clause 802,
803, 1202 & 1203 MORD and 1500, 1700 & 2100
MORTH.

I P.C.C grade M 10
(i) Nominal mix 1:3:6
Unit = cum
(a) Material
Cement t 0.22 5100.00
Coarse sand cum 0.45 964.21
40 mm aggregate cum 0.9 1124.74
Sienorage charges for sand cum 0.45 40.00
Sienorage charges for HBG metal cum 0.9 50.00
Water kl 1.2
(b) Labour
Mate day -
Mason (1st Class) day 0.1 258.00
Mazdoor (Unskilled) day 1.39 196.00
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted hour 0.40 345.00
with water measuring device and preferably also with
load cell.
Water tanker 6 kl capacity hour 0.13 345.00
(d) Formwork @ 4% on cost of material, labour and 4.00%
machinery (a+b+c)
Add MA@25% on labour charges
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

4 Plain/reinforced cement concrete in substructure


complete as per drawings and technical
RBR-SBST-5 specification Clauses 802, 804, 805, 806, 807, 1202
and 1204 MORD and 1500, 1700 & 2200 MORTH
Note : Water for concrete : A provision for cost of
water may be added at 1.2 kl / 1 cum (including curing
purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can
also be used instead of graded metal, keeping the site
conditions in view
For height upto 5 m
Unit = cum
I P.C.C grade M 15
i Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement t 0.275 5100.00
Coarse sand cum 0.480 964.21
40 mm aggregate cum 0.580 1124.74
20 mm aggregate cum 0.320 1679.74
Sienorage charges for sand cum 0.48 40.00
Sienorage charges for HBG metal cum 0.90 50.00
(b) Labour
Mate day -
Mason (1st Class) day 0.100 258.00
Mazdoor (Unskilled) day 1.390 196.00
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity hour 0.400 345.00

(d) Formwork @ 10% on cost of material, labour 10.00%


and machinery (a+b+c)
Add MA@25% on labour charges
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

Asst.Executive Engineer Deputy Executive Engineer,


PRI,Eluru PRI Sub-Division, Eluru
te Amount Rs.1.00 lakhs
Amount
Remarks
Rs.
6 7

1630.72

10851.00
5280.00

407.68
18169.40
75.71
quired, up to 10 per cent
onditions.

60.76

854.92
42.00
15.19
972.87

1122.00
433.89
1012.26
18.00
45.00

25.80
272.44

138.00

44.85
124.49

74.56

3311.29
1402.50
462.82
652.35
537.52
19.20
45.00

25.80
272.44

138.00

355.56

74.56

3985.75

Executive Engineer,
-Division, Eluru
LEAD STATEMENT

Name of the Work : Construction of culvert at Pedakadimi

Sl. Description of Material Unit Name of the Lead in Conveyanc Initial Cost
No. Quarry KM e charges

1 2 3 4 5 6 7
1 Coarse Sand for Mortor 1.00 Cum Rajahmundry 110.00 744.21 220.00
2 Coarse Sand for filling 1.00 Cum Rajahmundry 110.00 744.21 70.00
3 HBG 10mm nominal size---SS5 1.00 Cum I.Pangidi 80.00 554.74 560.00
4 HBG 20mm nominal size---SS5 1.00 Cum I.Pangidi 80.00 554.74 844.00
5 HBG 40mm nominal size---SS5 1.00 Cum I.Pangidi 80.00 554.74 500.00
6 Gravel 1.00 Cum Janampeta 7.00 65.44 50.50
7 Steel 1.00 MT 40000.00
8 Cement 1.00 MT 5100.00
9 600mm dia RCC plain ended NP3 1.00 Rmt Kalaparru 10.00 74.90 1915.00
class pipes

1.Certified that the above leads are correct to the best of my knowledge
2.Certified that the work spot lies within 12 Km from the Corporation limits

Asst.Executive Engineer
PRI,Eluru
Estimate Amount Rs.1.00 lakhs

Blasting Machine Total


charges crushing Amount
charges

8 9 12
0.00 0.00 964.21
0.00 0.00 814.21
70.00 140.00 1324.74
70.00 211.00 1679.74
70.00 0.00 1124.74
0.00 0.00 115.94
0.00 0.00 40000.00
0.00 0.00 5100.00
0.00 0.00 1989.90

Deputy Executive Engineer,


PRI Sub-Division, Eluru
SUB-ESTIMATE

Name of the Work : Construction of culvert at Pedakadimi

Estimate Amount Rs.1.00 lakhs

S.No Description of item Nos Measurements Quantity Rate Per Amount


Length Bredth Depth

1 Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1
including setting out, construction of shoring and bracing, removal of stumps and other
deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and
backfilling in trenches with excavated suitable material as per Technical Specification 305 MORD
/ 304 MORTH

Abutment R/s 1X1 18.00 1.20 0.75 16.20Cum


Abutment L/s 1X1 17.40 1.20 0.75 15.66Cum
31.86Cum 75.71 1.00Cum 2412

2 Providing concrete for plain/reinforced concrete in open foundations using 40 mm nominal size
Graded hard stone aggregate, mechanically mixed, placed in foundation and compacted by
vibration including curing for 14 days complete as per drawings and technical specifications
Clause 802, 803, 1202 & 1203 MORD and 1500, 1700 & 2100 MORTH.M10 Grade for bed
concrete

Abutment R/s 1X1 18.00 1.20 0.15 3.24Cum


Abutment L/s 1X1 17.40 1.20 0.15 3.13Cum
6.37Cum 3311.29 1.00Cum 21093

3 Plain/reinforced cement concrete in substructure complete as per drawings and technical


specification Clauses 802, 804, 805, 806, 807, 1202 and 1204 MORD and 1500, 1700 & 2200
MORTH M15 grade nominal mix(1 : 2.5 : 5) for abutments

Abutment R/s 1X1 17.80 (1.0+0.89)/2 0.58 9.24Cum


Abutment L/s 1X1 17.20 (1.0+0.89)/2 0.58 8.93Cum
18.17Cum 3985.75 1.00Cum 72421

4 Provision for VAT@4% --------------LS-------------------- 2686


S.No Description of item Nos Measurements Quantity Rate Per Amount
Length Bredth Depth
5 Provision for 0.5% Q.C.Charges --------------LS-------------------- 480

6 Provision for insurance --------------LS-------------------- 480

7 Provision for unforeseen items ----------------------------- LS -------------------------------------------------------- 428

TOTAL 100000