Professional Documents
Culture Documents
C-560
TOROMOCHO PROJECT
DISTRIBUTION A B C D 0 1 2 3 4 5 6 7 8 9
Client 7-3 7-11 9/22
Procurement
Field
Internal Review 6-24
INDEX
PAGE
1 SCOPE................................................................................................................... 3
3 GENERAL.............................................................................................................. 4
2 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
1 SCOPE
In particular, it applies to the Potable and Domestic Water system regulation, supply
& distribution, and inside building facilities; and for the Sewage System interior
facilities, collector branches, sewage treatment plant, and final disposition of the
water treatment effluent.
For general site data, see Appendix A - Standard Technical and Site Dates - SI Units.
3 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
Written permits from the Local Provincial & Municipalities in the Toromocho
Project are required prior to any work associated with the Potable (PW),
Domestic (DW) and Sewer (SS) water systems.
Any additional installation that is not connected to the system mentioned above
shall require its own written permit.
3 GENERAL
For the Construction Camp, filtered fresh water will be chlorinated as required for
general use for the water closets, urinals, lavatories and showers.
Temporary construction facilities will use domestic water during construction then
connected to the potable water system thereafter as required by Operations.
Potable water will be used for all permanent facilities in the Concentrator area.
Temporary construction facilities that are to be used for operation shall be
connected to the potable water system.
The Operation Plant, Construction Camp and Truck Shop will be provided each
with an STP. Remote bathroom facilities such as the Primary Crushing and Paste
Thickening Plant areas shall be provided with a septic tank where applicable.
4 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
4 CALCULATION BASIS
4.1 Population
The population to be considered for the domestic, potable water and sewage
systems is defined in the Technical Bases 400-BT-C-002 with Contract CC-016;
and for the Non Process Buildings, the Technical Bases 400-BT-C-003 and
Contract CC-017.
For other facilities such as the Administration Buildings, design is defined in the
Construction Contract CC-025; Truck Shop Building per Technical Bases 140-
BT-C-001 and Contract CC-018.
4.2 Endowment
The values of the service endowments are based from previous project of similar
facilities and are used to size the storage tanks for each facility.
For the design of piping network, the probable maximum instantaneous flow shall
be used based on installed fixture units.
5 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
For the Toromocho Project, a recovery coefficient equal to 1.0 will be used, that
is to say, all the potable water will pass through the sewage system network.
Fresh water is filtered, chlorinated as required and stored in a tank for non-
potable water usage. Water is drawn from this tank and treated in a packaged
water treatment plant to potable water quality, stored in a tank and distributed to
the pipe network.
Each area facility will have its own fresh or potable water storage tank.
Depending on the available terrain, water may be pumped or gravity flow from a
higher elevation to distribution lines.
The stored domestic or potable water shall be 1½ times the average daily
consumption to account for interrupted services from the supply feeding the
storage tank.
Bottled drinking water will be delivered to the Primary Crusher and the Paste
Thickening Plant.
Concentrator area will have a separate fresh and potable storage tanks. These
tanks will also supply the Hydromet plant.
The quality of the water for human consumption shall meet the requirement
stipulated in the State and/or Local Peruvian Standards whichever is most
stringent.
Storage and supply rate shall be based on the number of personnel in each area.
The Potable water quantity shall be defined by the average flow stated in Section
4.3 of this document.
Access to the water storage area will be restricted to prevent any risk to
contamination through vandalism or other such intent. Fencing with locks is
required for all of the potable water supply tanks.
Domestic water and potable water systems shall have separate storage tanks.
6 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
Operation facilities are defined as those in the Truck Shop (incl. Admin Bldg) and
the Concentrator areas
For the calculation of the tank volume, the following shall be considered:
For water usage, consider the number of personnel on rotation in each area and
the endowment listed in Table 1 above.
The water volume will be calculated on a basis of one construction daily shift.
For storage volume, use the population indicated in the Technical Bases of the
Construction Camp, Document Nº 400-BT-C-002, based on each person using
100 liters per person in 1.5 hours in the morning. This volume will be used as the
Total Probable Maximum Flow to the Construction Campsite.
Tank Characteristic
The storage tanks shall be steel carbon, designed and built according to API 650,
with Epóxy-Amine internal coating approved for potable water service. External
painting shall be per Document No. 000-GC-S-012, Painting and Protective
Coating, System P2.
For Tank dimensions, include the volume below the pipe nozzle discharge invert
elevation and the volume above the overflow pipe.
The tank shall have a vent and drain with valve connections and level
indicator/transmitter.
The materials of construction for piping shall be approved for potable water
service and shall be according to Peruvian Norma OS.050. High density
polyethylene (HDPE) approved for potable service may be used.
The network shall be provided with isolation valves to isolate parts of the system
for maintenance where necessary.
7 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
The network shall be provided with valves for draining or purging to facilitate
cleaning prior to commissioning for service.
Network Design
For distribution external to the buildings, the design flows will be determined
according to the criteria stated in Section 5.5.
a) Water piping between the tank and the delivery point to the network
Hydraulic Design
Piping
First preference is for piping to be routed above ground on sleepers and covered
with dirt to prevent exposure to the elements or direct sunlight as long as it does
not interfere with normal access or traffic. Another option is direct burial and
coated-and-wrapped for carbon steel.
Strategically located valves in the distribution nets will be used for isolation, in the
event maintenance is needed in some portions of the network. Isolation valves
shall not be more than 2000 m apart along the length of the pipeline. Drain
connections shall be located at low points and adjacent to isolation valves.
8 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
The design flows for the sanitary devices installed in each building shall be with
the Local Peruvian Regulations. This information is provided in Architecture
drawings and corresponding specifications: Technical Basis 400-BT-P-002 for
the construction and operation camp; Technical Basis 400-BT-C-003 for the non
process buildings, and 140-BT-C-001 for the buildings corresponding to the
Trucks Shop.
The Coefficient of Simultaneity will be proposed in the facilities for the project and
the operation characteristics for shifts (work rotation) for the Project Toromocho.
Other Flows
For emergency eyewash (15 L/min) and combination eyewash and shower (76
L/min), consider one set each (91 L/min) for the Truck Shop Concentrator and
the Hydromet areas. This flow rate must be added to the maximum probable
flow, Qmp.
Fire water flow rate is specified in Fire Protection Design Criteria, 000-GD-P-106.
The minimum residual pressure (adjusted for elevation) at the farthest user shall
not be lower than 15 m c.w. (145 kPag).
The testing of the facilities shall be in accordance with the local Peruvian Norms
and Regulations.
9 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
The sewage system shall be gravity flow with sufficient elevation between the
highest fixture units and the sewage treatment plant (STP) to accommodate the
design flow at the required slope.
There will be one independent STP for each of the facility area listed below:
Each STP maybe composed of multiple units that can be installed in stages from
during construction to operation periods.
The collection system shall be designed in accordance with the local Peruvian
Norm.
The piping materials shall be approved by the local Peruvian Authority for use in
the sewage systems and may be PVC, HDPE or other acceptable material.
The network shall have drop boxes for inspection and/or cleaning and
maintenance.
The sewage water average flow for the collection network will be calculated in
accordance with Section 4.0.
To determine the maximum hourly flow (Qhm), multiply the average daily flow
(Qad) by the Harmon Coefficient.
10 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
For P<100 people use the data on Boston Civil Engineering Society (BSCE),
Annex A
For P from 100 to 1000 people, a value shall be interpolated between BCES
Annex A for 100 people and the maximum flow (Qhm =M * Qad) corresponding
to 1,000 people.
The cumulative population and location of each building shall be taken into
account when routing the collector network.
Minimum Slope
The minimum design slopes are given in the local Peruvian Norm.
The pipes shall be routed with downward slope. The minimum slope in the first
100 m from the highest point shall be 2% and 1% on succeeding 100-m run if
there are no contributors from other collectors.
For other segments, size and slope will be determined for a self-draining sewer
line shown in Table 1.
Q x n =A x R2/3
S0.5
The calculation will be based on full pipe depth of flow = pipe ID or H=D and
velocity = 0.6 m/s for both the Operations and Construction areas.
11 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
The criteria stipulated in Annex A of the Boston Civil Engineering Society (BCES)
standard will be used.
Note 1. This is the estimated flow on the collection header serving the number of
people shown
For the Toromocho population shown, use the flow (L/s) for the corresponding
number of people shown in the BCES Annex A and verify the depth of flow,
considering that this flow will occur at least once a day
For population served between 201 and 1000 people, verify self-draining
capability assuming 60% of the interpolated flow for the number of people served
is flowing. See above for Harmon coefficient application.
For population served over 1000 people, verify self-draining capability assuming
that 60% of the maximum hourly flow (Qmh = Qad * M) as calculated above is
flowing.
The collector pipes shall be installed in trenches and covered with compacted
materials in accordance with the Technical Specification 000-GC-V-001,
considering vehicular traffic over the buried piping.
Sewage inspection drop boxes shall be provided at change of direction and
collectors junction. All the building discharge connections shall have inspection
drop box at the street connection. Other drop boxes shall be provided at no
more than 90 m apart. For 200 mm NPS pipes, drop boxes shall be located at
no more than 120 m apart.
12 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
The sewage water will be treated in a packaged sewage treatment plant STP.
The STP design flow of treatment shall be in accordance with population served
and the consumption endowment, according to the criteria indicated in the
Section 4 of this specification.
The quality of the sewage water effluent shall correspond with the characteristics
of the hygienic services provided for Truck Shop, Concentrator and the
Construction Camp facilities for the Toromocho Project.
Pollutant Concentrations
Unit Weak Medium Strong
Total Suspended Solid (ST) mg/L 350 720 1,200
Biological Oxygen Demand
mg/L 110 220 400
(DBO5)
Grease mg/L 50 100 150
Fecal Coliforms Nº/100 mL 104 105 106
The quality of the treated effluent will be according to the Local Peruvian Norm
and shall meet or exceed the requirement shown in Table 3 below. The
Q:\Shared\R0534200\01_Eng_Doc\05_Pip\01_Design_Criteria\02_Int_App\000-GD-P-206 Fresh, Potable and Sewage Water
System\560-000-GD-P-206_0.doc
13 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
undiluted treated water may be collected in pond or other means of storage for a
variety of usage at the discretion of the Engineer or owner
Maximum
Pollutants Unit Permissible
Limits
Total Suspended Solid (ST) mg/L80 80
Biological Oxygen Demand (DBO5) mg/L35 35
Grease mg/L20 20
Fecal Coliforms Nº/100 mL103 103
The treated mud may be transported by trucks for final disposition by the
Engineer or Minera Peru Copper. For transporting purposes, mud with 97%
humidity is preferable.
Waste
The amount of sludge produced will be determined when the STP vendor is
selected.
Treatment Units
All sewage system inside the buildings shall be designed and tested in
accordance with the Peruvian Norm for Regulation of Potable and Sewage
Facilities.
Sewage water flow from each facility shall be based on the Hydraulic Equivalent
Units (HEU) corresponding to each fixture units served and the occurrence of
high demand (coefficient of simultaneity) during shift changes.
14 of 15
Project R0532300
Design Criteria 000-GD-P-206
Potable and Sewage Water Systems
Rev. 0
Minimum pipe size from each internal facility to the external network shall be 100
mm NPS.
Materials
The interior collector shall be PVC pipe, sanitary union bell spigot with rubber
ring. The ventilations and main sewer lines that are exposed to sunlight shall be
covered with metallic shield.
Installations
Install only standard fixtures with built-in hydraulic seals. Floor drains shall also
be provided with hydraulic seal
The interior horizontal piping shall have minimum of 3% towards the exit without
a low point in between to avoid any deposit that may cause bad odor. All change
of directions and connections to main sewer lines shall be provided with sealed
cleanouts.
The sewage drop boxes that are inside the facilities and within a distance of 5 m
shall have double sewage drop boxes with sealed cover to avoid exit of gases.
Facilities that are isolated from the main collection areas shall be provided with
septic tank and leach fields.
15 of 15