PROJECT

Weekly Progress Report


GOOGLE VISTA HUB
Weekly Progress Report # 002 Date: Feb 19, 2018
Mechanical Contractor:
KALAYAAN ENGINEERING CO., INC. MECHANICAL WORKS
A. ACCOMPLISHMENT (THIS WEEK) : PHASE-1
OVERALL PROJECTED (3 Weeks Look Ahead)
ACCOMPLISHMENTS (PHASE-1)
Previous This Week To Date Next 1st Wk Next 2nd Wk Next 3rd Wk
TARGET 3.46% 4.95% 8.41% 14.22% 17.22% 15.90%
ACTUAL 0.00% 7.56% 7.56%
VARIANCE -3.46% -2.61% -0.85%
ADVANCE/DELAY (NO. OF DAYS)

B. ACCOMPLISHMENT (THIS WEEK) : PHASE-2


OVERALL PROJECTED (3 Weeks Look Ahead)
ACCOMPLISHMENTS (PHASE-2)
Previous This Week To Date Next 1st Wk Next 2nd Wk Next 3rd Wk
TARGET 1.02% 1.10% 2.12% 0.60% 0.23% 3.37%
ACTUAL 0.00% 0.00% 6.60%
VARIANCE -1.02% 4.48%
ADVANCE/DELAY (NO. OF DAYS)

C. ACCOMPLISHMENT (THIS WEEK) : PHASE-3


OVERALL PROJECTED (3 Weeks Look Ahead)
ACCOMPLISHMENTS-PHASE-3
Previous This Week To Date Next 1st Wk Next 2nd Wk Next 3rd Wk
TARGET 0.69% 0.30% 0.99% 0.88% 1.52% 0.98%
ACTUAL 0.00% 0.00% 4.94%
VARIANCE -0.69% 3.95%
ADVANCE/DELAY (NO. OF DAYS)

B. BRIEF SUMMARY OF ACCOMPLISHMENTS (THIS WEEK)


WORKS DESCRIPTION STATUS

Installation of A/C Duct Works (FAD)


Installation of Ventilating Ductworks
Distmantling of Existing Duct
Dismantling of Existing FCUs
Dismantling of Existing Refrigerant Piping
Installation and relocation of FCU cassette Type
Continue Layout and Fabrication of Ducts (Off-Site)
C. ACCOMPLISHMENT (NEXT WEEK PROJECTION)
WORKS DESCRIPTION STATUS

Continue Installation of A/C Duct Works (FAD)


Continue Installation of Ventilating Ductworks
Continue Dismantling of Existing FCUs
Continue Dismantling of Existing Refrigerant Piping
Continue Installation and relocation of FCU cassette Type
Continue Layout and Fabrication of Ducts (Off-Site)

D. OWNER SUPPLIED MATERIALS (OSM)

1.0 Water Cooled Chillers 4.0 FCU's 7.0 B.I. Pipes


2.0 Pumps 5.0 Cooling Towers
3.0 AHU's and PAU 6.0 Fans and Blowers
E. MANPOWER AT SITE (THIS PERIOD)
1. Project Manager 1 11. Warehouseman 1
2. Project In Charge 1 12. Tinsmith 9
3. Site Engineer 0 13. Duct Installer 23
4. Project Engineer 1 14. Electrician 5
5. AutoCAD Operator 1 15. Insulator 4
6. Site Admin/Time Keeper 1 16. Gas Welder 4
7. Supervisor 1 17. Pipe Fitter 2
8. Safety Officer 2 18. Helper's 20
9. Foreman 2 19. A/C Tech 2
10. Time Keeper 1 20. Fabricator (Off-Site) 10
TOTAL MANPOWER THIS WEEK: 91
F. TOOLS and EQUIPMENTS QTY. QTY.
1.0 Measure Tape 10 6.0 Speed Cutter 2
2.0 Chalks Stone (Marker) 10 7.0 Hacksaw Frame with Blade 10
3.0 Hilti Drill 10 8.0 Pipe Vise 2
4.0 Electric Drill 10 9.0 Pliers 10
5.0 Welding Machine 2 10.0 Scaffolding Set 70